Metrics-Based Process Mapping (MBPM) ASQ Lean Six Sigma Conference March 2, 2009 Company LOGO Learning Objectives The difference between a value stream map and a metrics-based process map. Key time and quality metrics for office, service, and knowledge work processes. The step-by-step approach for creating current and future state MBPMs. How to use the results obtained through this methodology to monitor processes and drive ongoing improvement. 2 1
Traditional Mapping Method: Process Flow Chart Where s the quality? Where s the time? 3 What is a Metrics-Based Process Map? A visual process analysis tool, which integrates: Functional orientation of traditional swim lane process maps Key Lean time and quality metrics Tool which highlights the disconnects / wastes / delays in a process Keeps the improvement focus properly directed Serves as standard work for workforce training and process monitoring 4 2
Metrics-Based Process Mapping (MBPM) When Do We MBPM? Value Stream Driven VSM is the strategic tool that identifies when we need to perform a more detailed analysis of a process MBPM is a tactical tool used to flesh out the details at each step to see the waste behind the waste Enables a team to drill down from a few targeted blocks on the VSM Often the first activity in an office-based Kaizen Event 6 3
Functions Step 1 Step 2 Parallel Steps Identify Critical Path & Create the Timeline 4
MBPM Post-it Conventions Step # Activity (Verb / Noun) Function that performs the task # Staff (if relevant) Barriers to flow (if relevant) % Complete & Accurate PT (process time) LT (Lead time) Task-Level Metrics: Time Process time (PT) The time it takes to actually perform the work, if one is able to work on it uninterrupted Includes task-specific doing, talking, and thinking aka touch time, work time, cycle time Lead time (LT) The elapsed time from the time work is made available until it s completed and passed on to the next person or department in the chain aka throughput time, turnaround time, elapsed time 10 5
Key Lean Metric: Quality %Complete and Accurate (%C&A) % time downstream customer can perform task without having to CAC the incoming work: Correct information or material that was supplied Add information that should have been supplied Clarify information that should or could have been clear This output metric is measured by the immediate downstream customer and all subsequent downstream customers. 11 Creating the Current State MBPM Phase I 1. Label the map in upper right corner. Process name, date, facilitator and/or team members 2. List the functions involved in left column. 3. Document all activities/steps. Verb/noun; concise language; include function as well. 4. Number the activities. One number per column; concurrent activities are labeled A, B, C, etc. 5. Add activity-specific metrics (PT, LT, %C&A), barriers to flow, and number of staff involved (if relevant). Include units of measure (mins, hrs, days, etc.) 12 6
Step 2: Create swim lanes for each functional area 13 Step 3: Document each activity and handoff(s) Step 4: Number the activities Step 4: Add key metrics (PT, LT, %C&A) and barriers to flow 7
%C&A Details Typically obtained via interview Who determines? Immediate downstream customer All subsequent downstream customers who use a party s output in any way Where placed? On the post-it for the person producing the output 0% at a particular step is not rare 15 Creating the Current State MBPM Phase II 6. Define the critical path. Longest LT unless dead-end step; use colored marker 7. Create the timeline. 8. Calculate the summary metrics CP PT Sum, CP LT Sum, AR, RFPY, Total PT, Labor Required 9. Identify the value-adding and necessary nonvalue-adding activities Use small colored post-it labeled with VA and N. 10. Circle the step-specific metrics that indicate the greatest opportunity for improvement. Use red marker. Longest LTs, Low %C&As, High PTs, Low step-specific ARs 16 8
Step 6: Define the Timeline Critical Path With parallel activities: Chose the longest LT unless a dead-end activity Step 7: Create the Timeline 9
Step 8: Calculate Summary Metrics - Time Critical Path PT Sum (CP PT) Critical Path LT Sum (CP LT) Activity Ratio (AR) The percentage of time work is being done to the patient/item/data passing through the process AR = (CP PT Sum CP LT Sum) 100 Expressed as a percentage 100 AR = % of time product is idle 19 Step 8 (continued): Calculate Summary Metrics - Quality Rolled First Pass Yield (RFPY) = Product of all %C&A s The percentage of items (material, information, or people) that pass through the entire process with no rework required Process check: The RFPY will always be lower than the lowest &C&A. 20 10
Step 8 (continued): Calculate Summary Metrics - Labor Requirements # FTES* = Total PT** (in hrs) x # occurrences/year Available work hrs/year/employee Freed Capacity = CS FTEs - FS FTEs * FTE = Full-time Equivalent (2 half time employees = 1 FTE) ** Total PT = Sum of all activities PTs, not just critical path Step 8 (continued): Document Results Metric Current State Projected Future State Projected % Improvement CP PT CP LT AR RFPY Total PT Labor requirements Freed capacity 22 11
Step 9: Label the value-adding (VA) and necessary non-value adding (N) activities 23 Step 10: Circle the data that indicates the greatest need for improvement 12
Typical Current State Findings Islands of value-adding activities All other time is waste. Rework First Step Adding Value Last Step Future State Design: How can we progress from one VA or N step to the next and eliminate all waste? 25 Future State Design Goals Reduce overall LT Improve RFPY Reduce overall PT Improve LT, PT, and %C&A at individual steps How? Eliminate NVA steps Minimize handoffs Eliminate rework Reduce batching Eliminate unnecessary IT Reduce WIP 26 13
Root Cause Analysis 4 Key Tools 5 Why s Why? Why? Why? Why? Why? Cause-and and-effect Diagram People Material / Info Method Lack of experience No stnd spread sheet Changing schedule Time availability Input rec d late No sense of import No standard work Email vs. FedEx Budgets Submitted Late Forecast in other system Manual vs. PC No milestones Weather delays System avail. $ vs. units Dispersed sales force Machine Measurement Environment Check Sheets Quantify Occurrences Reason Tally Material shortage Quality issue requiring rework Staffing/absenteeism Order entry error Changing customer requirements w/ no adjustment to expected delivery Equipment failure P a r e t o C ha r t Credit Applicat ion De lays 3500 100% 1 0 0 % 9 7 % 2 9 0 9 9 4 % 90% 3000 8 6 % 7 7 % 80% 2 4 9 3 2500 70% 2000 60% 50% 1500 4 1 % 40% 1000 30% 6 2 7 5 6 1 20% 500 2 4 2 1 8 0 10% 0 0% N o Si gna t ur e I ns uf f i c i e nt N o pr i or C u r r e n t N o C r e di t O t h e r B a nk I n f o a ddr e s s C u s t o me r H i s t or y Reason f or Delay Ease of Implementation Difficult Easy 9 5 7 2 PACE Prioritization Matrix 4 23 8 22 17 21 10 3 13 1 16 15 20 14 19 6 11 18 12 High Anticipated Benefit Low 14
Step 8 (continued): Document Results Metric Current State Projected Future State Projected % Improvement CP PT CP LT AR RFPY Total PT Labor requirements Freed capacity 29 Electronic Documentation? Archive the team s work Distribute the maps to remote locations Document the new standard work for the process Training/retraining staff Monitoring process performance Communicate the impact of Kaizen Events and other improvement activities 30 15
Excel-Based Option Custom toolbar with pull-down menus Seven sheets Current State Future State Summary Metrics Audit Findings Metrics Descriptions Sample MBPM Quick Start Guide Map Structure Functions Process Steps 0 Current State Metrics-Based Process Map 1 0 15 6-1 PT Units Process Details Mapping Team Seconds Hours Process Name Order Fulfillment Diane O'Shea Ryan Austin Minutes Days Specific Conditions Domestic orders through sales force Sean Michaels Mary Townsend LT Units Occurrences per Year 37,500 Sam Parks Seconds Hours Hours Worked per Day 8 Sally Dampier Facilitator Minutes Days Date Mapped 25-Jun-08 Michael Prichard Dave Morgan Step # 1 2 3 4 5 0 Function / Department Activity PT LT %C&A Activity PT LT %C&A Activity PT LT %C&A Activity PT LT %C&A Activity PT LT %C&A 1 Customer Fax PO to Sales Rep 0 0 45% 2 Sales Rep Review PO; clarify with customer as needed 20 2 90% Fax PO to warehouse 10 4 90% 5 Finance 6 Warehouse / Shipping Check inventory levels; notify Sales Rep re: status 5 4 95% Fax PO to Sales Rep 5 0.33 90% Critical Path PT Critical Path LT Rolled %C&A Total PT 0 20 10 5 5 0 2 4 4 0.33 45% 90% 90% 95% 90% 0 20 10 5 5 Key Metrics & Timeline Blue color-coded cells indicate the critical path 16
The Critical Path: Blue Color-Coding Critical Path Critical path metrics auto-populate timeline 33 Color-Coded Summary Metrics Sheet Auto-Calculates: Summary time and quality metrics for before and after maps Projected % improvement (color-coded for visual ease) Staffing requirements User-defined metrics 17
MBPM Tips 10 people max per team; use same people for both current and future state Documenting the current state takes 1/3 to double the time of the future state design phase Avoid gaps between current and future state mapping Typical teams need 5-10 blocks to truly understand what you re asking in terms of the metrics Can chunk metrics if needed Use a skilled, impartial facilitator 35 Learning Objectives The difference between a value stream map and a metrics-based process map. Key time and quality metrics for office, service, and knowledge work processes. The step-by-step approach for creating current and future state MBPMs. How to use the results obtained through this methodology to monitor processes and drive ongoing improvement. 36 18
MBPM Resources Additional Questions? Karen Martin, Principal 7770 Regents Road #635 San Diego, CA 92122 858.677.6799 ksm@ksmartin.com 38 19