CHAPTER 16: PROJECT SCHEDULING



Similar documents
GUIDELINES FOR PREPARING POSTERS USING POWERPOINT PRESENTATION SOFTWARE

Software Project Planning. CITS1220 Software Engineering

Microsoft Excel Basics

Briefing document: How to create a Gantt chart using a spreadsheet

Intermediate PowerPoint

Introduction to Project Management

Microsoft Project 2013

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Creating a Poster in PowerPoint A. Set Up Your Poster

Microsoft Office PowerPoint Creating a new presentation from a design template. Creating a new presentation from a design template

Project Management. References: Text, Chapter 16 (and 1 thru 3) Most introductory management books. Get organized!

Microsoft Excel 2013: Charts June 2014

Create a Poster Using Publisher

Using Microsoft Project 2000

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

Formulas, Functions and Charts

Excel Tutorial. Bio 150B Excel Tutorial 1

A simple three dimensional Column bar chart can be produced from the following example spreadsheet. Note that cell A1 is left blank.

Sample Table. Columns. Column 1 Column 2 Column 3 Row 1 Cell 1 Cell 2 Cell 3 Row 2 Cell 4 Cell 5 Cell 6 Row 3 Cell 7 Cell 8 Cell 9.

Examples of Data Representation using Tables, Graphs and Charts

Lab 1 Introduction to Microsoft Project

Publisher 2010 Cheat Sheet

University of Sunderland. Microsoft Project. Basic Guide

Excel -- Creating Charts

Creating an Excel XY (Scatter) Plot

Figure 1. An embedded chart on a worksheet.

Excel 2007 A Beginners Guide

How to make a line graph using Excel 2007

Excel Math Project for 8th Grade Identifying Patterns

Using MS Project in Translation Projects Management

Introduction to Microsoft Project 2010

Microsoft Project 2010

Excel 2003 A Beginners Guide

In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class.

CURRICULUM FOUNDATIONS

Graphing in excel on the Mac

DIRECTIONS FOR SETTING UP LABELS FOR MARCO S INSERT STOCK IN WORD PERFECT, MS WORD AND ACCESS

Microsoft Excel 2010 Charts and Graphs

DOING MORE WITH WORD: MICROSOFT OFFICE 2010

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

Microsoft Word 2010 Prepared by Computing Services at the Eastman School of Music July 2010

Fact Sheet No. 3 Topic: Creating Deliverables Applicable to: Microsoft Project Server 2007/Microsoft Office Project 2007 (Professional)

In this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move

ELECTRO-MECHANICAL PROJECT MANAGEMENT

DIGITAL DESIGN APPLICATIONS Word Exam REVIEW

As in the example above, a Budget created on the computer typically has:

Microsoft Excel 2013 Tutorial

Microsoft Excel 2010 Part 3: Advanced Excel

Microsoft Publisher 2010 What s New!

Creating a PowerPoint Poster using Windows

CREATING FORMAL REPORT. using MICROSOFT WORD. and EXCEL

Word basics. Before you begin. What you'll learn. Requirements. Estimated time to complete:

ME 4054W: SENIOR DESIGN PROJECTS

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider :: :: info@bluepecan.co.

Computer Literacy Syllabus Class time: Mondays 5:00 7:00 p.m. Class location: 955 W. Main Street, Mt. Vernon, KY 40456

KB COPY CENTRE. RM 2300 JCMB The King s Buildings West Mains Road Edinburgh EH9 3JZ. Telephone:

Applied Project Management ( APM )

Introduction to Microsoft Excel 2007/2010

INTRODUCTION TO DESKTOP PUBLISHING

Planning and Managing Projects with Microsoft Project Professional 2013

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

What's new in Project 2010

Astronomy 101: On-Line Reading Quizzes

Instructions to Create Your Rollup Poster in PowerPoint

Developing a Gantt and PERT Chart

Creating a Poster Presentation using PowerPoint

Excel 2003 Tutorial I

Section Five Learning Module D:

Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

Excel 2007 Basic knowledge

2. Building Cross-Tabs in Your Reports Create a Cross-Tab Create a Specified Group Order Filter Cross-Tab by Group Keep Groups Together

Creating a New Project

Intro to Excel spreadsheets

Updates to Graphing with Excel

Preparing a Simple Project Plan with MS Project

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Computer Training Centre University College Cork

Data Visualization. Prepared by Francisco Olivera, Ph.D., Srikanth Koka Department of Civil Engineering Texas A&M University February 2004

CONTINUOUS IMPROVEMENT EXERCISE L. Leslie Gardner, Ph.D., Assistant Professor School of Business University of Indianapolis

Step 2: Headings and Subheadings

MICROSOFT WORD TUTORIAL

SECTION 5: Finalizing Your Workbook

Appendix A How to create a data-sharing lab

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

Introductory Project Management Module. Mansfield Adult Continuing Education 1 Inc

Working with Tables: How to use tables in OpenOffice.org Writer

Designing a Poster using MS-PowerPoint

SHAREPOINT 2010 FOUNDATION FOR END USERS

Excel 2003 PivotTables Summarizing, Analyzing, and Presenting Your Data

Microsoft Excel Training - Course Topic Selections

Microsoft Project 2013 Guide to Task and Resource Planning

Creating a Newsletter with Microsoft Word

Introduction to Visio 2003 By Kristin Davis Information Technology Lab School of Information The University of Texas at Austin Summer 2005

Scientific Graphing in Excel 2010

CONSTRUCTING SINGLE-SUBJECT REVERSAL DESIGN GRAPHS USING MICROSOFT WORD : A COMPREHENSIVE TUTORIAL

Access Tutorial 1 Creating a Database

Basic Excel Handbook

Creating Bar Charts and Pie Charts Excel 2010 Tutorial (small revisions 1/20/14)

Transcription:

CHAPTER 16: PROJECT SCHEDULING Chapter outline Responsibility Allocation Matrix (RAM chart) Gantt chart Whenever you're working on a large project, it s crucial to share the workload, coordinate your activities, and establish and stick to a schedule. Successful teams use meeting minutes, the course syllabus, and two other important tools to help them stay on top of things: the Responsibility Allocation Matrix, commonly called a RAM chart, and the Gantt chart. The RAM chart details who s in charge of what and when it s due; the Gantt chart is a schedule of tasks using a timeline. You may wonder why you need a RAM and Gantt chart in addition to a syllabus. The answer is, they offer something more: A RAM chart gives you a detailed view of tasks (not all of which are specified on the syllabus) and shows who is responsible for performing the task and by what date. A Gantt chart displays at a glance what work needs to be completed, when it should start and finish, and which tasks need to be worked on simultaneously. A Gantt chart is the overall plan for the project, whereas the RAM is the weekly to do list to help you follow through on that plan. Activities on the Gantt chart generally take a week or two (with the exception of milestones, which are single events). The RAM includes the specific tasks embedded in those activities. If you were to try to include that level of fine detail in a Gantt chart, you would spend more time managing the chart than doing the work. A RAM chart is a quicker, more effective means to plan and manage the details on a week-to-week basis and to help the team stay on target with the Gantt chart schedule. 16.1 RESPONSIBILITY ALLOCATION MATRIX (RAM CHART) The RAM chart is a good project-planning tool because it shows the primary and secondary tasks of each individual on the team. It is also a good record- 149

keeping tool because it helps instructors, supervisors, and others know who did (or was supposed to do) what. The most useful RAM charts divide complex tasks and major deliverables into subtasks. For instance, testing a mockup might be divided into getting materials for the mockup, building it, writing the user interview guide, testing the mockup, and writing up the results. Some RAM charts include a column for noting who completed a task or when it was completed. This helps the team keep a record of whether people are actually doing their work and doing it on time. A RAM chart takes the form of a grid, with tasks listed on one axis and team members and due dates on the other. If a square is marked with an X, a 1, or an equivalent mark, this means the person assigned to that task has primary responsibility for seeing it is done. A corresponding mark, such as an O or a 2, shows who else is working on that task. A blank square means the corresponding team member is not involved in that task. A well-written RAM chart divides large tasks among team members, rather than giving all members primary responsibility for all or most tasks. Here s a RAM chart that fails: Because the tasks are not subdivided sufficiently, it allocates responsibility to everyone for almost all tasks. And even if everyone is involved in a task, it s best to make one person responsible (i.e., the leader for that job). Example 16.1: RAM Chart with ineffective task division RAM chart (5/19 to 5/28) Task Due date Sinem Sharifah Jeff Sean Person who completed task Mockups 5/19 X X X X Write Client Meeting Summary # 2 Design Review Proposal Draft Write Progress Report # 3 Write Meeting Agenda for Team Meeting # 3 5/19 0 X 5/24 X X X X 5/26 X X X X 5/28 0 X 0 0 5/28 X The following revised RAM chart succeeds because it sufficiently divides tasks and indicates what each team member needs to do and by what date: 150

Example 16.2: Revised RAM chart with effective task division RAM chart (5/12 to 5/28) Task Due date Sinem Sharifah Jeff Sean Person who completed task Prepare alternatives matrix 5/12 X 0 0 0 Schedule appointment with shop professional Prepare mockup planning sheets 5/12 X 0 5/14 X 0 Order materials for mockups 5/15 X 0 Build mockups 5/19 0 X Write client meeting summary # 2 5/19 X 0 Do lab testing of mockups 5/20 X 0 Analyze test results 5/22 X 0 Synthesize information for design review 5/22 0 X Make design review slides 5/23 0 X Make design review questionnaires 5/23 X 0 Write first proposal draft 5/26 X 0 Write progress report # 3 5/26 0 X 0 0 Write meeting agenda for team meeting # 3 5/28 X Key: X=primary responsibility 0=secondary responsibility Creating the RAM chart should be a team activity so that it draws on everyone s knowledge and makes members feel invested in performing the tasks. After your team has figured out the necessary tasks, has assigned them based on members skills and interests, and has chosen realistic due dates, have one member type up the chart, post it to the team s online workspace, and place it in the project notebook. Because it is difficult to know weeks in advance what tasks will be required and who will do them, you should prepare a new RAM chart every one to two weeks, detailing who will do what in the coming weeks. In EDC, you are required to submit a RAM chart with your written deliverables, and to include all charts in your project notebook as a way of documenting teamwork. 151

16.2 GANTT CHART Named for its inventor, management theorist Henry Gantt, the Gantt chart is the most widely used method of scheduling group work by due dates. Using both a table and bar graph format, the Gantt chart lists key project tasks on the vertical axis, and time frames (by weeks or months) on the horizontal axis. A bar across the columns indicates the time span for each task. These bars also indicate which tasks overlap, are interdependent, or take place simultaneously. Gantt charts are used for internal team planning, as in a progress report to a supervisor or client, and for external reporting, as in a project proposal. Like all project documentation, a Gantt chart undergoes modification as you complete portions of your project and better understand it. That s why you need to keep updating the chart throughout the project. Here is an explanation of a generic Gantt chart, produced with Microsoft Excel: At the top are the project title, section number, team name (or number), and last update of the chart. Along the left column are the main and subtasks. (In your chart you will give the tasks specific names. For example, you might name the first major task Preliminary research and the subtasks Interview client, Analyze Competitive/model products, and Observe users. ) Be sure to use action verbs to identify tasks, and include only those tasks related to the team s design process, not individual assignments (such as the individual essay). Darkly shaded bars indicate completed tasks; unshaded or lightly shaded bars indicate uncompleted tasks. Notice that the bars show which tasks can proceed simultaneously and which need to be completed before another task can begin. The stars indicate project milestones. These are events that need to happen at particular times in order to meet project goals. In EDC, it s useful to consider two types of milestones. The first includes deadlines imposed by the course syllabus, such as the due dates for assigned written reports and oral presentations. The second type includes milestones that your team has set in order to stay on target, such as the date when user testing must be completed in order to allow you enough time to choose a final design direction and construct a high-quality prototype. 152

Example 16.3: Generic Gantt chart Project ABC Team 2 Updated 1/31/06 WEEKS Tasks Task A 1 2 3 4 5 6 7 8 9 10 11 Subtask A1 Subtask A2 Subtask A3 Subtask A4 Task B Subtask B1 Subtask B2 Subtask B3 Task C Subtask C1 Subtask C2 Subtask C3 Subtask C4 Task D Subtask D1 Subtask D2 Subtask D3 Subtask D4 Task E Subtask E1 Subtask E2 Subtask E3 Task F Subtask F1 Subtask F2 Subtask F3 153

Below is an example of a Gantt chart for a winter quarter EDC project: Example 16.4: EDC winter quarter gantt chart One-handed crocheting project - Gantt Chart Team 2 Section 12 Updated 2/16/05 Weeks 2 3 4 5 6 7 8 9 10 Tasks Preliminary Research Research disability Research existing products Interview crochet experts Interview client Observe users Concept Generation Brainstorm/Cluster Ideas Generate alternatives Build Mockups Concept Testing Performance testing User testing Design Review Prepare review Analyze results Adjust project plans/tasks FINAL DELIVERABLES Prototype Build/Test New Mockups Build Prototype Poster Brainstorm Poster Designs Create Poster Write Oral Presentation Final Report Write Final Report KEY completed tasks uncompleted tasks progress report 16.2.1 Team guidelines for creating Gantt charts 1. Brainstorm all the tasks that need to be done for your project. 2. Group these tasks into categories, differentiating between main and subtasks. 3. List the tasks along your vertical axis. Begin at the top, listing tasks that must be done first. Use a hierarchical column to distinguish between main and subtasks. Omit the least important subtasks if your list gets too long. End the list with your final deliverables. 154

4. Divide your horizontal axis into columns, labeling each by week. 5. Use a horizontal bar to show the estimated beginning and end of each task. 6. Review your Gantt chart weekly to check your progress; revise the chart as you add tasks to your project plan. 7. Include updated Gantt charts in your progress reports and project notebook. 8. NOTE: Here s how to use Microsoft Excel to create easily updateable Gantt charts (Dufee & Chase, 2003): Under Page Setup in the File menu, do the following: Go to Page and select Landscape orientation. Also select Fit to one page. Go to Margins and select Center on page horizontally and vertically. Go to Sheet and make sure that Gridlines is un-selected. Under View, go to Toolbars and click Border and Drawing. Use the Border commands to make the bars. Use the Fill command on the Drawing toolbar to fill bars as you complete tasks. Use the Autoshapes command on the Drawing toolbar to make stars indicating project milestones. 16.3 REFERENCES Anderson, P. V. (1998). Technical communication: a reader-centered approach. 4th ed. San Diego, CA: Harcourt Brace. Dufee, W. & Chase, T. (2003). Brief tutorial on Gantt charts. Retrieved July 27, 2003, from http://www.me.umn.edu/courses/me4054/assignments/ gantt.html Markel, M. (1998). Technical communication: situations and strategies. 5th ed. New York, St. Martin s Press. Woolever, K.R. (1998). Writing for the technical professions. New York: Longman. 155

156