FIDIC AND. DISPUTE ADJUDICATION BOARDS (DAB(s))



Similar documents
Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision

The FIDIC Suite of Contracts

Dispute Board Manual

FIDIC Conditions of Contract and the Dispute Adjudication Procedure. December 4-5, 2003 Simpsons in the Strand, London.

SCHEDULE 5 DISPUTE RESOLUTION

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

The ICC Uniform Rules for Demand Guarantees ("URDG") in Practice: A Decade of Experience

Managing Payment Risks on International Construction Projects

Taking Action. Dispute resolution, legal action and claims for negligence

60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management

CEDR Rules for the Facilitation of Settlement in International Arbitration

Contractor s Claims Under The FIDIC Contracts For Major Works

EXPERT RULES PROPOSAL OF EXPERTS AND NEUTRALS APPOINTMENT OF EXPERTS AND NEUTRALS ADMINISTRATION OF EXPERT PROCEEDINGS

IBA International Construction Projects Committee. ADR in Construction. Ireland. Authors: Jarleth Heneghan and Cassandra Byrne.

Jurisdiction. Egypt.

Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction

osb.ic.gc.ca All about Bankruptcy Mediation

Sample MEDIATION IN DOMESTIC RELATIONS

Industrial Disputes Prevention & Settlement

ALTERNATIVE DISPUTE RESOLUTION IN ADMINISTRATIVE MATTERS

FIDIC/MDB Approach in respect of Dispute Adjudication Boards

MEDIATION RULES OF THE COURT OF ARBITRATION AT THE POLISH CHAMBER OF COMMERCE

THE CITY OF EDMONTON PROJECT AGREEMENT VALLEY LINE LRT STAGE 1. Schedule 20. Dispute Resolution Procedure

SCHEDULE 13 DISPUTE RESOLUTION PROCEDURE. In this Schedule, in addition to the definitions set out in Section 1.1 of the Agreement:

Representing Yourself In Employment Arbitration: An Employee s Guide

CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS

CHAPTER NINE DISPUTES SETTLEMENT ARTICLE 187 Scope of the Chapter The provisions of this Chapter shall apply to the settlement of disputes concerning

Regulation and Adjudication in Construction Contracts

UNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL) UNCITRAL Conciliation Rules

South Africa Arbitration Guide IBA Arbitration Committee

Complaint Policy and Procedure

Conflict avoidance and dispute resolution in construction

A new Danish Arbitration Act came into force on 1 July It is largely based on the UNCITRAL model law.

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill

Do We Need Process Of Dispute Settlement In Managing Today? Professor Chris Rowley

(1) risks should be allocated to the party that is in the position to control them and

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

LEGAL COSTS IN SOUTH AUSTRALIA'S WORKERS' COMPENSATION SCHEME

Customer. Arbitration

Dispute Resolution. White Paper. This document on Dispute Resolution outlines the four main approaches to resolving contractual disputes.

THE GENERAL INSURANCE OMBUDSERVICE

ARBITRATION IN GHANA THE ALTERNATIVE DISPUTE RESOLUTION ACT 2010 By Kwadwo Sarkodie

J.V. Industrial Companies, Ltd. Dispute Resolution Process. Introduction

ALTERNATIVE DISPUTE RESOLUTION METHODS. e-business Issue.

Describe the Different Methods of Alternative Dispute Resolution Available to do with Civil Courts.

MODEL DIRECTIONS FOR CLINICAL NEGLIGENCE CASES (2012) - before Master Roberts and Master Cook

Amongst the most significant International Conventions ratified by Lebanon are the 1958 New York Convention and 1965 Washington Convention.

BBB Rules of Non-Binding Arbitration for Extended Service Plans/Extended Service Coverage Naming BBB as Administrator

Guide to Filing Ethics Complaints and Arbitration Requests

ORI Gu idel in es f o r Inst it u t ion s an d Wh ist l eblow e rs: (November 20, 1995)

Best Practice Guide Effective dispute resolution

A Contract for Just Digging a Hole

TAKING A SMALL CLAIMS ACTION IN THE COUNTY COURT USING AN EXPERT

Parent Rights & Responsibilities in Nevada Early Intervention

The Government of Republic of India and the Government of The Republic of Cyprus (hereinafter referred to as the Contracting Parties );

Your Guide to Will Dispute Mediation

What is Online Dispute Resolution? Why use Online Dispute Resolution? What are the different types of Online Dispute Resolution?

Form 6A ALTERNATIVE DISPUTE RESOLUTION (ADR) FORM

MEMORANDUM OF UNDERSTANDING. Between THE UNION DES ASSOCIATIONS EUROPEENNES DE FOOTBALL (HEREAFTER UEFA) And

Bylaws of the Lawyer-Client Fee Dispute Resolution Committee of the Cleveland Metropolitan Bar Association. Enacted November 18, 2015

This innovative Scheme has been developed to resolve small claims disputes within the maritime industry.

Guide to International Arbitration

Workers Compensation Insurance

CLAIMS HANDLING GUIDELINES. for CTP Insurers

Rules of Arbitration

ARBITRATION RULES OF THE COURT OF ARBITRATION AT THE POLISH CHAMBER OF COMMERCE

The goal is to improve the welfare of the peoples of the member countries.

THE CANADIAN LIFE AND HEALTH INSURANCE OMBUDSERVICE

DISPUTE RESOLUTION IN KANSAS PROVIDED BY THE: DISPUTE RESOLUTION ADVISORY COUNCIL AND THE

Arbitration and Mediation in International Business

REGULATIONS FOR THE POSTGRADUATE DIPLOMA IN INTERNATIONAL ARBITRATION AND DISPUTE SETTLEMENT (PDipArb)

ISTANBUL ARBITRATION CENTRE ARBITRATION RULES

ARBITRATION RECENT TRANSACTIONS

DESIRING to intensify economic cooperation between both States;

THE GENERAL INSURANCE BROKERS CODE OF PRACTICE

SAMPLE EXAMINATION PAPER LEGAL STUDIES. Question 1 Explain the meaning and the nature of law (10 marks)

Protocol for the Instruction of Experts to give Evidence in Civil Claims

Alternate Dispute Resolution and Asbestos

Resolving IP and Technology Disputes Through WIPO ADR. Getting back to business

IMPROVING THE RESOLUTION OF TAX TREATY DISPUTES

Expedited Dispute Resolution Bond (P3 Form)

LAW ON ARBITRATION. Official Gazette no. 88/2001) P a r t O n e GENERAL PROVISIONS Scope of application Article 1

Any questions concerning the certificate requirements may be directed to the ADR Program Director, Professor Lisa Klerman:

Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 ARRANGEMENT OF SECTIONS. 6. Right to refer payment disputes to adjudication.

Grievance Management. What s in this section? Process is important. Scale the mechanism to project needs. Put it in writing and publicize it

OFFICIAL COURT NOTICE OF SETTLEMENT

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Forensic Services. kpmg.hu

Practices and Procedures for Appeals under Section 11.1 of the School Act

Transcription:

FIDIC AND DISPUTE ADJUDICATION BOARDS (DAB(s)) Christopher R. Seppälä Partner, White and Case LLP, Paris Legal Advisor, FIDIC Contracts Committee Vice-President Emeritus, ICC International Court of Arbitration March 18, 2015 1 99911766v2

FIDIC and Dispute Adjudication Boards (DAB(s)), Outline Outline I. Historical Background II. The Development of Dispute Boards for Major Projects III. Dispute Boards in Practice IV. Conclusion 2

FIDIC and Dispute Adjudication Boards (DAB(s)), I. Historical Background I. Historical Background A. Pre-Arbitral Settlement of Disputes by the Engineer When FIDIC published its first international standard form of construction contract for civil engineering works the Red Book in 1957, it was based on the Conditions of Contract of the English Institution of Civil Engineers the ICE Conditions. Accordingly, the FIDIC Red Book incorporated the traditional English system for the pre-arbitral resolution of disputes by the Engineer. 3

FIDIC and Dispute Adjudication Boards (DAB(s)), I. Historical Background I. Historical Background A. Pre-Arbitral Settlement of Disputes by the Engineer [continued] Under FIDIC construction contracts from 1957 until 1987, all disputes had initially to be referred to the Engineer for a decision before they could be referred to arbitration. Employer Engineer hired, paid by and in Contract with Employer Engineer Engineer s dual role: Disputes Contractor (1) Employer s agent in some cases; and (2) In others, duty to act impartially between the Employer and the Contractor including when deciding disputes between them. 4

FIDIC and Dispute Adjudication Boards (DAB(s)), I. Historical Background I. Historical Background A. Pre-Arbitral Settlement of Disputes by the Engineer [continued] However, while this practice is widespread in common law countries, it is generally unknown in civil law countries. B. Why the Pre-arbitral Settlement of Disputes by the Engineer Declined As hired and paid by the Employer, the Engineer was subject to commercial pressures that made it difficult to act impartially. Contractor s claims might call into question the Engineer s conduct as designer and/or administrator of the works, creating a conflict of interest. As a result, the Engineer has lost credibility as a settlor of disputes and has been replaced by a Dispute Board ( DB ). 5

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects A. What is a Dispute Board ( DB )? Normally set up at the outset of a contract. Remains in place for its duration. Consists of 1 or 3 persons, usually engineers, ideally experienced in the work of the contract. They must be independent of, but must all be approved by, the parties. They must be provided with the contract documents and other project documents and become familiar with the project. Originally developed in the United States for use in settling on-site disputes in large civil engineering projects, e.g. tunnels, dams, etc. 6

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects B. How Does a DB Work? Promotes resolution of differences or disputes through: Regular visits to the site (every 3-4 months) and meetings with the parties, Identification and discussion of issues before they become disputes, Providing informal opinions on issues if both parties so request, Organizes full hearings, if necessary, to hear the parties, and Makes written recommendations or binding decisions on disputes referred to it by the parties, which may later be submitted in arbitration. Normally paid a monthly retainer and a daily fee for site visits, etc. 7

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects C. The Development of the Dispute Review Board ( DRB ) i.e., a DB that makes recommendations rather than decisions binding on the parties The U.S. Experience: 1975 First Domestic DRB in U.S. (Eisenhower Tunnel). Development of DRBs Internationally: 1981 1 st international DRB (El Cajón Dam, Honduras). 1995 World Bank makes DRBs mandatory for all World Bank-financed projects over US$ 50m (later reduced to projects over US$ 10m). 1996 Asian Development Bank and EBRD adopt DRB approach. 8

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects D. The Development of the Dispute Adjudication Board ( DAB ) i.e., a DB that makes binding decisions rather than recommendations 1987-93 Successful use of a particular type of DAB for the Anglo-French Channel Tunnel project. 1995 FIDIC introduces a DAB into a standard form (the Orange Book ). 1996 FIDIC proposes DAB as an acceptable alternative to the Engineer as dispute-settlor in the Red Book. 1999 FIDIC adopts DAB approach as mandatory in its forms for major works. 2005 World Bank and other multi-lateral development banks adopt DAB approach in their standard form (harmonized edition of FIDIC Red Book ). 9

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects E. Use of DABs in FIDIC Contracts The introduction of the DAB into FIDIC contracts was a logical development from the procedure for the pre-arbitral settlement of disputes by the Engineer. The FIDIC contracts provide for both a permanent DAB (Red and Gold Books) and an ad hoc DAB (Silver and Yellow Books): Permanent DAB: Maintains familiarity with project, visits site periodically throughout project, decides disputes that arise by (provisional) binding decisions. Ad hoc DAB: Constituted for and decides an individual dispute by a (provisional) binding decision and is then disbanded. 10

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects F. Use of DABs in FIDIC Contracts The DAB procedure is similar to that when disputes were decided by the Engineer. Settlement of Disputes by DAB Attempt at Amicable Settlement 84 days 28 days 56 days Referral of Referral of Dispute to DAB Referral of Final Date for DAB s Decision Referral of Referral of Final Date for Arbitration Issuance of Notice of May Dissatisfaction if Begin Dissatisfied with DAB s Decision 11

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects F. Use of DABs in FIDIC Contracts [continued] FIDIC favoured a binding decision over a recommendation because: It was a continuation of the binding decisions made by the Engineer, It was felt that a binding decision procedure was more appropriate in international construction contracts as FIDIC contracts were (and perhaps still are) mainly used by public bodies, and public servants are often reluctant to take important decisions, and Public servants who agreed to a settlement based merely on a recommendation might be exposed to criticism, investigations or allegations of corruption. 12

FIDIC and Dispute Adjudication Boards (DAB(s)), II. The Development of DB for Major Projects II. The Development of Dispute Boards for Major Projects G. Dispute Avoidance Dispute avoidance and not merely deciding disputes is recognized as an increasingly important role for the DB. Thus, FIDIC s Design Build Operate form (the Gold Book ), 2008, provides as follows: If at any time the Parties so agree, they may jointly refer a matter to the DAB in writing with a request to provide assistance and/or informally discuss and attempt to resolve any disagreement that may have arisen between the Parties during the performance of the Contract. Such informal assistance may take place during any meeting, Site visit or otherwise. However, unless the Parties agree otherwise, both Parties must be present at such discussions. The Parties are not bound to act upon any advice given during such informal meetings, and the DAB shall not be bound in any future Dispute Resolution process and decision by any views given during the informal assistance process, whether provided orally or in writing. (Sub-Clause 20.5) 13

FIDIC and Dispute Adjudication Boards (DAB(s)), III. Dispute Boards in Practice III. Dispute Boards in Practice A. Enforcement Arbitral tribunals and courts have given effect to the parties agreement providing for a DAB: they have confirmed that disputes must be referred to a DAB before arbitration (e.g. English and Swiss courts); and they have enforced the decisions of DABs, whether binding or final and binding (e.g. Singapore and South African courts). 14

FIDIC and Dispute Adjudication Boards (DAB(s)), III. Dispute Boards in Practice III. Dispute Boards in Practice B. Statistics While there is no systematic reporting on the use of DBs, there is no doubt that they are being used increasingly on international projects. The Dispute Resolution Board Foundation ( DRBF ) has published statistics about the use of DBs in the U.S. and the world as a whole. According to the DRBF, DBs have been used in over 2,700 completed projects (overwhelmingly in the U.S. so far) having a total construction value of over US$ 225 billion. 15

FIDIC and Dispute Adjudication Boards (DAB(s)), III. Dispute Boards in Practice B. Statistics [continued] III. Dispute Boards in Practice DB Projects through 2014 (cumulative figures since 1982): 24 2394 9 3 3 41 12 100 40 12 57 Source: DRBF 16

FIDIC and Dispute Adjudication Boards (DAB(s)), III. Dispute Boards in Practice C. Cost of DABs III. Dispute Boards in Practice Given their greater rapidity and informality, they will be much less costly than arbitration. For a multi-hundred million dollar project, a three-member DAB can cost much less than 1% of project costs, whereas international arbitration may cost 10 to 15% or more of project costs. Ad hoc DABs are less costly than permanent DABs but, arguably, are not true DABs as they cannot perform a dispute prevention function. According to the DRBF, over 98% of disputes referred to DBs conclude the matter in issue, either directly or as a result of the parties using the DAB s decision or DRB s recommendation as a basis for settlement. 17

FIDIC and Dispute Adjudication Boards (DAB(s)), IV. Conclusion IV. Conclusion 1. FIDIC, like the World Bank, is a strong believer in DABs. 2. However, the use of DABs is still in its infancy internationally; they do not yet enjoy wide acceptance by Employers. Yet acceptance is vital as they cannot work unless they enjoy the confidence of the parties. 3. DABs are a great concept. Like an insurance policy, they protect against far more costly and much more lengthy arbitration. 4. Nevertheless, they are not a universal panacea. Whether and how they are used in any project, needs to be determined in light of the features of that project. 18

FIDIC and Dispute Adjudication Boards (DAB(s)) Thank You Chris Seppälä White & Case LLP 19 Place Vendôme 75001 Paris France Tel: + 33 1 55 04 15 15 cseppala@whitecase.com 19