NTV s AGV575 Train Homologation Process Technical Training Manager Production Dept., NTV, Italy
Contents Company presentation The Actors of Homologation AGV001 «PEGASE» Prototype tests AGV575 Pre-series trains tests Homologation Process Timeline From Technical approval to Commercial Service 2
Nuovo Trasporto Viaggiatori First private High Speed railway operator in the European Union. Overall employment generated: 2,000 jobs. Service offered: 50 trains/day, 12 million trainskm/year. Demand on Italo by 2014: 8 million passengers. Market share by 2014: 25%. In service from April 2012: 9 trains pairs operated; 150.000 passengers carried (40% load factors). 3
Company mission and approach NTV targets: Guarantee the operation of commercial services with an high quality standard. Keep the costs under control, in particular all those related to the operation. Organization and processes have to be LIGHT, SAFE and TOTALLY INTEGRATED 4
NTV fleet 25 AGV (Automotrice Grand Vitesse) Alstom HS trainsets ~ 25 mln euro per trainset TECHNICAL FEATURES Type: Articulated trainset Composition: 11 vehicles 12 bogies Length: 201 m Traction: Distributed Power: 3 kv dc + 25 kv ac Maximum speed o 250 km/h (3 kv dc) o 300 km/h (25 kv ac) 5
The Actors of Homologation The first private HS railway operator in Europe meets the first train homologated by the Constructor. Testing laboratory Process Responsible Train Responsible (during tests) Technical Dossier Predisposition Train Responsible Technical Dossier Assessment Homologation Monitoring Processes RU Operational service (during tests) Slot Availability Authorization to run 6 6
AGV001 PEGASE prototype tests Pegase arrives in Italy 7 January 2010 Starting tests on Pegase 9 February2010 Test end 21 December 2010 Test runs performed on 45.000 km for understanding dynamic behavior of the train and anticipating homologation tests for signalling. 7
AGV575 Pre-series trains tests PS01 Test Start Marc 10 th, 2011 Test end December 5 th, 2011 L02 Test Start April 10 th, 2011 Test End December 9 th, 2011 Tests performed: Traction/Braking: performance evaluation, speed step up, braking test, and braking distance measuring to comply with safety requirements, homologation of the system as a type system. Signalling System: set up and verification of the correct interface between on board and ground devices Pantograph: dynamic behavior at high speed, current collection quality, both off 3kV and 25kV. Tunnel aerodynamics interactions Test performed: Running dynamics up to 330 km/h on the 25kV HS line Milano Bologna (commercial speed + 10% as specified by international regulation) Running dynamics up to 275 km/h on the 3kV DD line Roma Firenze (commercial speed + 10% as specified by international regulation) External aerodynamics on fixed installation along the line (such as platform, etc.) Electro Magnetic Compatibility (EMC) Outside Noise level measurement 8
AGV575 Pre-series trains tests L03 Tests performed: Test Start November 17 th, 2011 Test end December 18 th, 2011 Signalling system homologation and put into service: 10000 km under supervision running on all kind of line in order to demonstrate to safety authority the robustness and reliability of the type system under homologation Reliability growth endurance test L03 L05 Test performed: Test Start November 10 th, 2011 Test End December 11 th, 2011 Test were performed on the still to be opened (at that time) French Rhin-Rhone 25kV High Speed Line, together with French TGV and German ICE trainstes. Over speed test at 330km/h to have a complete benchmark on dynamic behavior of that train running on different infrastructures Completing of the external aerodynamics on fixed installation along the line that were left from test in Italy. Reliability growth endurance test 9
Homologation Process Timeline 2008 2009 2010 2011 2012 Homologation request Documentation Pegase testing train Testing authorisation 15 Dec 09 Testing runs 07 Jan 10 21 Dec 10 PS01 L02 L03 L05 Testing authorisation 3Mar 11 Testing runs 10 Mar 11 18 Dec 11 Homologation For pre-commercial ser. For commercial service 10
Homologation Process Timeline 2008 2009 2010 2011 2012 Homologation request Documentation Pegase testing train Testing authorisation 15 Dec 09 Testing runs 07 Jan 10 21 Dec 10 PS01 L02 L03 L05 Testing authorisation 3Mar 11 Testing runs 10 Mar 11 18 Dec 11 Homologation For pre-commercial ser. For commercial service 11
Process Milestone Documentation for test Requested by Released by Date (PS1) Technical approval for test Ammissione tecnica per prove RINA March 3 rd, 2011 Vehicle registration for test RINA March 3 rd, 2011 Authorisation to run for test Circolabilità per prove RINA March 9th, 2011 Documentation Requested by Released by Date Technical approval Autorizzazione di messa in servizio Vehicle registration Immatricolazione Authorisation to run Circolabilità March 6 th, 2012 March 21 st, 2012 March 23 rd, 2012 12
Homologation Process Lessons learned Logistic support for maintenance and for operations Clear definition of the actors involved in the process with related responsibility perimeter; Harmonisation of national / European standard not fully achieved; Strong technical support by Rolling Stock Manufacturer (Alstom); Training of personnel during homologation period is a key for gaining experience on the rolling stock; Strong presence of Railway Undertaking during homologation test is fundamental for anticipating possible issues during operations. 13