SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT



Similar documents
Specifications for Residential Property Owners Connection to New Public Sewer

Septic System Design Manual

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

FY08 SEWER POINT REPAIRS BID TABULATION

EFFECTIVE FEBRUARY note: drainage permit required to call for a dampproof inspection

Town House Center Highway North Huntingdon, PA 15642

Understanding and Living With Your Septic System

Beacon Hill Sewer District Standard Specifications

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

ONSITE WASTEWATER TREATMENT SYSTEM Property Transfer Certification Instructions and Inspection Report

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

Onsite Wastewater Concepts, Materials, Regulations & The Application Process Part I

LS 2540 SEWER LATERALS AND INSPECTION TEES

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SHORELINE SANITATION

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

DO-IT-YOURSELF SEPTIC SYSTEM INSPECTION FIELD GUIDE (Mound System)

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

Septic System Owner s Manual

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

SEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

SANITARY SEWER SPECIFICATIONS

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE TRANSACTION INSPECTIONS

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

Designing Septic Systems

SECTION STORM DRAINAGE TABLE OF CONTENTS

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

SECTION STORM DRAINAGE SYSTEM

Procedures for Correcting a Sludge / Grease Clogged Elevated Sandmound Sewage Disposal System.

WASTEWATER TREATMENT AND DISPOSAL BY ON-SITE WASTEWATER TREATMENT SYSTEMS

City of Shelbyville Site Inspection Checklist

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Homeowners and Home Buyers Guide to Wells and Private Sewage Systems

ON-LOT SEWA G E S Y S T E M S

ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Section SEWER PIPE INSTALLATION AND TESTING

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS

CERTIFYING DRAINLAYER

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

THURSTON COUNTY SEPTIC TANK PUMPERS' MANUAL

Soakage Trenches. A better way to manage stormwater. Thinking Globally and Acting Locally

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

Emerging Technologies in Wastewater Collection Systems

Jay R. Smith Mfg. Co.

Sewage Compliance Form Instructions

SECTION EARTH MOVING

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

CHAPTER 32 PLUMBING CODE

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION GRAVITY SANITARY SEWERS

Section 2100-Trenching and Tunneling

HOW A SEPTIC SYSTEM FUNCTIONS

Learning Objectives. History of Vacuum Testing for Precast. Vacuum Testing. Terminology and purpose

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE STANDARDS. James L. Tomarken, MD, MPH, MBA, MSW Commissioner of Health Services

Properly maintaining your septic system will help reduce the. It s Your Septic System. Homeowner s Guide. Here s How to Take Care of It

Wastewater Capital Projects Management Standard Construction Specification

Stormwater/Wetland Pond Construction Inspection Checklist

Septic Systems and Their Maintenance

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

SECTION BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

SECTION 9: Pumping Systems

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Mobile Home Pre-Inspection Checklist

Homeowner s Guide to Maintaining a Sewage Treatment System

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

[L] If the top of the tank is level with or above ground level, finding it should not be a problem.

Transcription:

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County, Maryland. These requirements are based on Maryland Environmental regulations COMAR 26.04.02 and state and local policy. Sand mound system construction requirements are established in the Maryland Department of the Environment Design and Construction Manual for Sand Mound Systems. 1. Application for Installation Permit Prior to commencing work, the St. Mary s County licensed septic system contractor must submit application to Environmental Health and receive approval. The approved application will serve as the permit to install the septic system. Drawing of proposed installation or approved site plan must accompany application. A one-hundred dollar inspection fee must accompany the installation application. 2. Inspections Applicant must give Environmental Health 24 hours notice when septic system is ready for inspection. All work must be completed and left uncovered prior to inspection. A bucket of water must be provided to check gravity-system distribution boxes. Pressurized systems require operational check of effluent pump and high water alarm. This inspection must be scheduled with the area Sanitarian. Inspector will notify applicant of inspection results. 3. Sewer Pipe, Building to Distribution Box a. Sewer line from building to septic tank must be 4-inch diameter minimum schedule 40 PVC or cast iron with neoprene gasket or leaded joints, minimum grade is ¼ inch per foot.

b. Sewer line from septic tank to distribution box or pump chamber must be 4-inch diameter minimum schedule 40 PVC; minimum grade is 2 inches per 100-feet. c. All schedule 40 PVC pipe in septic system and solid pipe in trench header ditches must be bedded in sand or pea gravel to a depth of 6. d. All sewer lines must be sleeved in schedule 40 PVC when crossing a driveway or right-of-way. 4. Septic Tank a. Reinforced concrete, top-seam, two-compartment tank. Design must be approved by Maryland Department of the Environment. b. Sewer pipe connections at inlet and outlet must be made through water-tight seals or with cement. c. Primary and secondary chamber outlets must be fitted with sanitary tees or factory installed baffles extending 18 inches below outlet invert. d. Two-foot diameter risers are required on both inlet and outlet ends of the septic tank. The risers are to be at least 6 inches above finished grade and have solid lids with inspection ports. e. Tank must be placed at least 10 from foundation, and must not be installed more than 3 deep from ground level to top of tank. 5. Pump Chamber a. Separate pump chamber in addition to the two-compartment septic tank is required for all systems utilizing sewage effluent lift pumps. b. Reinforced concrete, top-seam watertight chamber, minimum capacity of 1000- gallons. Design must be approved by Maryland Department of the Environment. c. Sewer pipe and force main connections at inlet and outlet must be made through water-tight seals or with cement. d. A reinforced concrete riser to ground surface is required for access.

6. Sewage Effluent Lift Pump a. Use effluent-grade pump only. Must be capable of delivering necessary flow (gallons per minute) at calculated design head (feet). b. Install pump on 6-inch riser. c. Pump must be equipped with pump-on/pump-off/high water alarm float switches. Volume between pump-on level and pump-off level must be a minimum of 125 gallons. d. Volume between high water alarm float and pump chamber inlet should be 500 gallons. High water alarm must be wired on separate electrical circuit, with control panel located above ground in waterproof enclosure or in a building. e. All electrical connections should be located outside pump chamber. f. Pump must have operational check by inspector before approval. This will involve observation of one complete pump cycle and inspection of distribution box with pump on. 7. Force Main a. Force main shall be minimum of 2-inch diameter schedule 40 PVC to within 10- feet of distribution box, at which point expansion coupling will be installed. Last 10-feet of force main shall be 4-inch diameter minimum schedule 40 PVC and needs to be visible during time of inspection. All couplings must be schedule 40 pressure quality. b. Siphon Breaker Hole of ¼ inch diameter may be drilled in force main inside pump chamber. Install quick disconnect union in force main before pump chamber outlet.

8. Distribution Box a. Boxes for gravity systems shall be concrete, 5-outlet minimum. b. Boxes for pressurized systems shall be concrete, 10-outlet minimum. c. Boxes with water-tight inlet and outlet seals are recommended; cemented connections may be approved. d. Speed levelers are to be used in on all box outlets on a gravity system. e. Do not install speed levelers on box outlets in pressurized systems; they will restrict flow and create back pressure. f. Boxes utilizing outlets opposite inlet is allowed. A brick is required to be cemented to box floor in all pressurized systems. 9. Sewer Pipe, Distribution Box to Drain Fields a. Sewer lines from distribution box to beginning of drain field should be minimum of 4-inch diameter ASTM F 810 solid PVC. Minimum grade is 2 inches per 100- feet. b. Pipes in drain fields should be a minimum of 4-inch diameter ASTM F 810 PVC with 3 rows of ¾ inch perforations installed at bottom of pipes. Required grade is 2 to 4 inches per 100-feet. 10. Drain fields a. Trenches must be located in sewage easement as shown on approved site plan. Keep trenches running parallel with contour (same elevation), do not run up or down hill. Stay 10-feet from property lines and buildings and 50-feet from drilled wells. b. Width: Trenches of depths between 2-feet and 3-feet must be 3-feet in width. Trenches 3 ½ -feet or deeper need to be 2-feet wide. c. Length: Trenches must be equal in length and parallel. Trenches cannot exceed 100-feet in length each and they must match total length as listed on perc slip.

d. Depth: As listed on perc slip. If suitable material is not encountered at specified depth, stop work and contact Environmental Health. However, keep in mind that not all septic systems are installed in what appear to be the most sandy soils. Do not dig deeper than the specified install depth to get into better material as that may bring the trench bottom too close to the ground water table. e. Gravel: Use washed gravel only; size required is from 3/4 inch to 2 inch. Trenches less than 7-feet in depth must have gravel to within 18 inches of ground surface; trenches 7-feet and deeper must have gravel to within 4-feet of ground surface. Place gravel 2 inches over top of pipe. f. Paper Fill Barrier: When trench is completed, place builder s paper or filter cloth on top of gravel along entire length of trench. This will prevent fill dirt from entering gravel during backfilling. Do not use felt paper. When installing trenches using a pressurized distribution, only use filter cloth or geotextile fabric. Use of builders paper is not allowed. g. There is no required distance between trees and trenches but it is recommended to cut down trees that pose the threat of root invasion of septic system. 11. What To Do in Case of Problems: STOP!!!! Call Environmental Health; if necessary a Sanitarian will visit the site. Changes to site plan layout may not be approvable. This includes but is not limited to, changing the location of the septic tank or installing 2-66 foot drain fields instead of the 3-44 foot drain fields that were approved on the site plan. Solve problems BEFORE you do any work. 01-07