Important Factors for Success of Public Construction Projects



Similar documents
CRITICAL SUCCESS FACTORS FOR KNOWLEDGE MANAGEMENT STUDIES IN CONSTRUCTION

A Success Measurement Model for Construction Projects

PROBLEMS IN RUNNING HEALTHCARE PROJECTS

Critical Success Factors Influencing Performance of Construction Projects

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Assessment of Critical Success Factors for Construction Projects in Pakistan

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Project Management Practices: The Criteria for Success or Failure

ICT Project Management

Improve Net Present Value using cash flow weight

QUALITY ASSURANCE GUIDE FOR GREEN BUILDING RATING TOOLS

CONTRACT MANAGEMENT FRAMEWORK

A Study On Factors Influencing Construction Contract Claim Management

Project Diagnostics Assessing the Condition of Projects and identifying Poor Health

[Arunmozhi, 5(1): January- March, 2015] ISSN: Impact Factor: (SIJF)

Promote knowledge management in your organisation

Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry

Good governance outcomes for CCGs: A survey tool to support development and improvement of governance

9 TH INTERNATIONAL ASECU CONFERENCE ON SYSTEMIC ECONOMIC CRISIS: CURRENT ISSUES AND PERSPECTIVES

Quality Management Subcontractor QM Guide-Section Two

Manager, Procurement and Contracts

ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession.

Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2

Best practice. Corporate Governance. Financial Reporting Council. July Audit Tenders. Notes on best practice

Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

RMBC s Governance Framework for Significant Partnerships

Masters Comprehensive Exam and Rubric (Rev. July 17, 2014)

Voluntary Certification Scheme for Traditional Health Practitioner

Agile-Fall Process Flow Model A Right Candidate for Implementation in Software Development and Testing Processes for Software Organizations

IMPROVING THE CRM SYSTEM IN HEALTHCARE ORGANIZATION

EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

INTRODUCTION. The Merlin Principles. The Elements of each Principle

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information

Introduction. Project Management in New Zealand

Appendix 1: Performance Management Guidance

QUALITY MANAGEMENT SYSTEMS REQUIREMENTS FOR SERVICE QUALITY BY PUBLIC SERVICE ORGANIZATIONS

REQUIREMENTS MANAGEMENT: HOW IT BENEFITS YOUR BUSINESS

The Effectiveness of Ethics Program among Malaysian Companies

Risk Management in Construction Projects

Information Technology Engineers Examination

Contract Management. Brief 22. Public Procurement. September 2011

CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT

Influence of Tactical Factors on ERP Projects Success

Procurement Policy Review Feedback Summary

DRAFT Revised Guide to the National CDEM Plan 2015 July 2015

Guidance for Australian Government Agencies and Funding Recipients

UNECE PPP Healthcare Standard

Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)

Contents. Before you begin. How to work through this learner guide Assessment. Introduction: Developing and managing performance management processes

PERFORMANCE APPRAISAL SYSTEM TO PERFORMANCE MANAGEMENT SYSTEM IN BOKARO STEEL PLANT (SAIL): AN EVALUATION

TEAM/PROGRAMME: Health/Programme Implementation Number of Position: 2 GRADE: C-2 CHILD SAFEGUARDING: Type of Contract: Fixed Term

InProc Quality Management System

What are the critical factors that measure the success of capital projects?

Programme Specification. Course record information. Admissions requirements. Aims of the course

PLANNING & FORENSIC DELAY ANALYSIS

Procurement guidance Managing and monitoring suppliers performance

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

Transport for London. Projects and Planning Panel

Interface Management on Megaprojects: A Case Study

University of Cambridge: Programme Specifications MASTER OF STUDIES IN INTERDISCIPLINARY DESIGN FOR THE BUILT ENVIRONMENT

The programming, design

Will Shs 1.5 trillion be well managed? Findings from the performance audit of road works

AN ANALYTICAL STUDY OF PERFORMANCE APPRAISAL SYSTEM OF THE SELECTED INFORMATION TECHNOLOGY ENABLED SERVICES (ITES) COMPANIES

Enterprise 2.0 Knowledge Management Development Trends

PERARES PROJECT EVALUATIONS

Town of Montreat Buncombe County, North Carolina

Conceptualizing Total Quality Management (TQM) for Improving Housing Areas for the Urban Poor

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles

Certificate IV in Property Services (Real Estate) CPP Unit Descriptions & Evidence Required to Demonstrate Competency

Contractor Performance Report Scoring Guide

Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries

EFFECTIVE ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PROCESS

INTRODUCTION...1 FREQUENTLY ASKED QUESTIONS ABOUT REFERENCE CHECKS...2

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

Developing CMMI in IT Projects with Considering other Development Models

TEC Capital Asset Management Standard January 2011

Procurement Capability Standards

Performance audit report. Ministry of Education: Monitoring and supporting school boards of trustees

Chapter 1 Introduction to Contract Management and Administration

OE PROJECT CHARTER TEMPLATE

UoD IT Job Description

Oak Park School District. Administrator Evaluation Program

Business Administration Certificate Program

PERCEPTION OF BUILDING CONSTRUCTION WORKERS TOWARDS SAFETY, HEALTH AND ENVIRONMENT

Yale University Knowledge Management Process Guide

AC : ENTERPRISE RESOURCE PLANNING: A STUDY OF USER SATISFACTION WITH REFERENCE TO THE CONSTRUCTION INDUSTRY

HKITPC Competency Definition

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Volume 3, Issue 4, April 2015 International Journal of Advance Research in Computer Science and Management Studies

DGS Customer Satisfaction Survey An action plan to improve customer service

NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT

U.S. DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION. Air Traffic Organization Policy

JOB DESCRIPTION SYSTEMS DEVELOPMENT OFFICER - Grade 6

ASSESSMENT PLAN Computer Science, MS Updated May 25, 2007

Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia

Performance Management and Staff Development System

How To Know The Effect Of Demographic Factors On The Preference For Wealth Management In Udaipur

JUNE Assurance for high risk projects

Transcription:

2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Important Factors for Success of Public Construction Projects S. Z. S. Tabish1, K. N. Jha 2 ¹Ph.D Candidate, IIT Delhi and Superintending Engineer, C.P.W.D., Government of India ² Assistant Professor, Department of Civil Engineering, IIT Delhi Abstract. Modern public construction projects involve multiple stakeholders, such as designers, contractors, subcontractors, construction managers, consultants, and specialists from different disciplines. In a multi-agency work environment, it is natural to have clash of objectives and interests among the different stakeholders. The objective of public project management is to ensure the success of a project which not only involves managing the schedule, cost, and quality, generally known as the iron triangle, but also satisfying a number of other performance criteria, such as avoiding disputes, and complying with safety norms. Identification of the success factors is considered the key to achieving success in these projects. Through an extensive literature review, 36 success factors were identified and a questionnaire-based survey was undertaken to elicit views of construction professionals on the criticality of these factors for the success of public construction projects. The responses from 105 professionals with an average of 22 years of experience in public construction projects in India were collected and analyzed using ANOVA and most important factors for success for various success criteria are presented. The success factors of generic nature are: owners need thoroughly understood and defined, a high degree of trust shared by project participants, timely and valuable decision from top management, availability of resources as planned throughout the project, top management s support, and regular monitoring and feedback by top management, whereas success factors of specific nature are: thorough understanding of scope on the part of project manager and contractor, comprehensive pretender site investigation, regular monitoring and feedback by owner, no bureaucratic interference, no social and political interference, clearly articulated scope of work, quality control and quality assurance activities, and adequate communication among all project participants. The results would be helpful to public construction project professionals in taking proactive measures for successful completion of public projects. Keywords: Success factors; India; Public projects. 1. Introduction Growing economy is an indicator of a country s development. Development of physical infrastructure is most critical issue for sustained future growth (Construction Industry Development Council, 2005). Global construction market is worth around US $3,200 billion per year (Sohail and Cavill, 2008). The Government of India has committed an outlay of INR 20,562 Billion (US $ 514 billion at an exchange rate of Rs 40 for $1) to infrastructural development in its Eleventh Five Year Plan (2007-2011). Large investments in infrastructure, have almost assured the growth prospects of the businesses. The performance of the Indian Construction Projects has not been very encouraging owing to time and cost overruns. As per the report of the Ministry of Statistics and Programme Implementation (Infrastructure and project monitoring division), Government of India, time and cost overruns have been a major problem affecting the public sector projects (http://www.mospi.gov.in). Studies conducted for improving the performance have revealed a number of factors called success factors. It is well acknowledged that there is a significant difference between public sector and private sector organization, in terms of funding, serving public and accountability constraints. Public projects demand a high level of transparency and accountability and are therefore accountable to external financial audit and 1 Corresponding author. Tel.: + (919968411168); fax: +(916122539882). E-mail address: (szstabish@yahoo.co.uk). 64

vigilance agencies. Tabish and Jha (2011) developed a frame work based on transparency, professional standards, fairness, contract monitoring and regulation, and procedure for corruption-free performance in public projects. The literature on the success factors for public construction project reveals that very few studies have been taken up and that too they are not focused on individual performance criterion. For example, Jacobson and Choi (2008) and Toor and Ogunlana (2009) identified success factors for overall performance such as: specific plan/vision, open communication and trust, political support, expert advice and review, high degree of commitment, clear role and responsibility, willingness to compromise/collaborate, respect, risk awareness and community outreach and shared vision between the client, architect and contractor, project planning and control, project personnel and involvement of client. Hence more awareness of success factors of public projects with specific reference to different performance criteria needs to be created among the construction professionals. In addition to success factors, the term success itself has undergone a sea change in the complex project environment with so many stakeholders involved. The objective of public project management is to ensure the success of the project, and this involves not only managing the schedule, cost, and quality, generally known as the iron triangle, but also satisfying a number of criteria for performance measurement, such as no-disputes and complying with safety norms. The earlier research on the project success factors includes perception of respondents and data gathered from either private sector or both private and public sector uniformly. Since public sector projects are different from private sector ones, the success factors shall also be different. Existence of differences in the perceptions about the relative importance of success factors between private and the public sectors has been reported (Yang et al. 2009; Divakar and Subramanian 2009). Hence, uniformity of respondents (employees of public sector) is also very important. So, only public sector construction projects and perception of their engineers are used in this study. Thus the objective of the study is to determine the important factors for success of public construction projects addressing the limitations of the past studies as pointed out. 2. Research Method Through literature review 36 success factors were identified. Then, a questionnaire-based survey was conducted to draw the views of experienced public sector professionals on these success factors. A list of all on-going major and medium public work monitored by Government of India was developed. One hundred and five responses were received against all 813 major and medium projects. The responses were analyzed using analysis of variance (ANOVA) which compares mean values of sample and population distributions and thus useful for hypotheses testing. The following hypotheses were examined to explore the relationship between success factors for various criteria for highly successful projects. H o : There is no significant difference in identified success factors for successful and not successful projects H 1 : There is a significant difference in identified success factors for successful and not successful projects The significance level was set to 0.05. The respondents were asked to rate the performance on various criteria on a nine-point scale, in which 1 represented very low performance and 9 represented very high performance. Projects rated more than 6 on scale were considered high performing ones. The projects which were high and very high performing were rated as successful projects whereas other projects with a value/rating less than or equal to 6 on scale were rated as not successful. In addition, the respondents were also asked to rate the success factors for the project in which they were involved on a nine-point scale in which 1 represented strong disagreement and 9 represented strong agreement for the success factors. The top five significant success factors for various criteria identified using ANOVA are presented and discussed briefly in the following section. 3. Data Analysis 65

3.1. Most significant factors for schedule performance criterion From Fig 1, it is observed that most important success factors for schedule compliance are: availability of resources as planned throughout the project, timely and valuable decision from top management, a high degree of trust shared by project participants, owners need thoroughly understood and defined, and no bureaucratic interference. Timely decision from top management not only helps in making the resources available but also helps in building trust and thus avoiding delay (David, 2009). Obviously, the owner s input in the development of a clear project brief, reflecting project requirements accurately is important (Chan et al., 2001) and to a certain extent avoids bureaucratic interference during execution. Role of project participant and their timely decision is vital for schedule criteria (Divakar and Subramamian, 2009). Figure 1 Success factors for schedule criteria 3.2. Most significant factors for cost performance criterion The most important success factors for cost compliance are: comprehensive pretender site investigation, thorough understanding of scope on the part of project manager (PM) and contractor, a high degree of trust shared by project participants and no social and political interference. Anderson et al.(2006) also observed that well understood project improves the managerial ability to deliver results in cost which is possible if PM and contractor understand the scope clearly. Comprehensive site investigation helps in sound planning which in-turn helps in clarifying the scope and developing a thorough understanding. Trust among the project participants helps in understanding the cost implications and delivering the project within cost. Clarity also limits the social and political interference. Hence all the four success factors are important for cost compliance. The ranking is shown in Fig. 2. Figure 2 Success factors for cost criteria 3.3. Most significant factors for quality performance criterion From Fig 3, it is observed that most important success factors for quality compliance are: owners need thoroughly understood and defined, regular quality control and quality assurance activities, regular monitoring and feedback by top management, top management s support, and availability of resources as planned throughout the project. Quality improves under watching eyes. This could be top management or quality control people and their regular monitoring and support. Availability of resources and clear scope are linked to the quality work on site (Chua et al., 1999). Hence all the mentioned success factors are important for quality compliance. The ranking of top five success factors is shown in Fig. 3. Figure 3 Success factors for quality criteria 66

3.4. Most significant factors for safety performance criterion Top five success factors for safety compliance are shown in Fig. 4, and they are: regular monitoring and feedback by owner, clearly articulated scope of work, regular monitoring and feedback by top management, availability of resources as planned throughout the project and top management s support. Figure 4 Success factors for safety criteria To foster a safety culture at a construction site, top management support and commitment to safety programme is must. Commitment and support by top management and owner would significantly drive up the performance on safety. Haslam et al. (2005) observed that shortcomings with resources/equipment are responsible for 56 per cent of the accidents. Availability of resources must be ensured throughout project lifecycle. Construction projects requiring the presence of more than forty different specialists at the construction site are not unusual (Ortega, 2000). Lack of clarity may lead to failure. Billy et al. (2006) reported that effective two way flow of information is essential for safety. Major changes during construction should also be avoided as it disturbs the planning and becomes potential source for accident. Clear scope helps in sound planning resulting in minimum changes during construction. 3.5. Most significant factors for no-dispute performance criterion Top five most important success factors for no-dispute performance are: owners need thoroughly understood and defined, regular monitoring and feedback by top management, adequate communication among all project participants, availability of resources as planned throughout the project, and timely and valuable decision from top management. This is shown in Fig. 5. In fact, conflicting parties should look for a mutually satisfactory solution, and this can be achieved by joint problem solving in order to seek alternatives for problematic issues. Public sector projects require management of all stakeholders, but this can also be used as an opportunity and a source of resources and support for dispute resolution (David, 2009). Valuable timely decision by top management and availability of resources can help in taking timely measures to avoid dispute. If any conflict during construction is not resolved and timely decisions are not given, dispute becomes complicated and difficult to resolve. Both contractor and project manager must have thorough understanding of the scope, to avoid dispute and conflict, which is possible if scope is clearly defined by owner. Top management and owner can also help in resolving the conflict. Figure 5 Success factors for no-dispute criteria It is evident from above that the success factors identified in this study are mostly in line with previous studies on public projects. 4. Concluding Remarks Based on the responses to a questionnaire survey conducted among Indian construction professionals engaged in public projects, a set of most significant success factors have been identified for different project 67

performance criteria. Depending on the nature of projects, for example public or private projects, the performance criteria vary. The study has revealed that some factors such as: owners need thoroughly understood and defined, a high degree of trust shared by project participants, timely and valuable decision from top management, availability of resources as planned throughout the project, top management s support, and regular monitoring and feedback by top management, are of generic nature and would be required to be present to ensure success against two-three performance criteria while there are some specific factors such as: thorough understanding of scope on the part of project manager and contractor, comprehensive pretender site investigation, regular monitoring and feedback by owner, no bureaucratic interference, no social and political interference, clearly articulated scope of work, quality control and quality assurance activities, and adequate communication among all project participants, which are required to be present to ensure success against a certain criterion. A project manager does not aim to achieve all the performance criteria at any point of time and depending on the circumstances the relative importance of performance criteria may vary. Under such situation, the distinction of generic and specific factors would play a role and with this knowledge the project manager would be in a position to distinguish the factors which needs higher attention and thus can ensure higher gain. The identification of success factors in this paper is a part of ongoing research work to identify success factors for public projects for various performance criteria and develop a model which would ultimately result in fair and transparent procurement practices avoiding the frequently occurring irregularities. A series of in-depth case studies on various public projects should be undertaken in future in other countries as well in order to verify the applicability and reliability of the success factors identified in this study. 5. References [1] Andersen, E.S., Birchall, D., Jessen, S.A., and Money, A.H. Exploring project success. Baltic Journal of Management. 2006, 1(2): 127-147. [2] Billy, H., Cameron, I., and Duff, A.R. Exploring the integration of health and safety with pre-construction planning. Engineering, Construction and Architectural Management. 2006, 13(5): 438-450. [3] Construction Industry Development Council, News letter December, 2005. [4] Chan, A.P.C., Ho, D.C.K., and Tam, C.M. Design and build project success factors: Multivariate analysis, Journal of Construction Engineering and Management. 2001, 127(2): 93 100. [5] Chua, D.K.H., Kog, Y.C., and Loh, P.K. Critical success factors for different project objectives. Journal of Construction Engineering and Management. 1999, 125(3): 142 150. [6] David, W. Public-Sector Project Management. John Wiley and Sons, Inc. Hoboken, New Jersey, 2009. [7] Divakar, K. and Subramanian, K. Critical successfactors in the real-timemmonitoring of construction projects. Research Journal of Applied Sciences, Engineering and Technology. 2009, 1(2): 35-39. [8] Haslam, R.A., Hide, S.A., Gibb, A.G.F., Gyi, D.E., Pavitt, T., Atkinson, S., and Duff, A.R. Contributing factors in construction accidents, Applied Ergonomics. 2005, 36: 401-415. [9] Jacobson, C., and Choi, S.O. Success factors: public works and public-private partnership. International Journal of Public Sector Management. 2008, 21(6): 637-657. [10] Ortega, I. Systematic prevention of construction failure. Quality Management and Technology. 2000, 9:1-13. [11] Sohail, M., and Cavill, S. Accountability to prevent corruption in construction projects. Journal of Construction Engineering and Management. 2008, 134(9): 729-738. [12] Tabish, S.Z.S. and Jha, K.N. Analysis of irregularities in public procurement in India, Construction Management and Economics. 2011, 29(3): 261-274. [13] Toor, S. and Ogunlana, S.O. Construction professionals perception of critical success factors for large-scale construction projects, Construction Innovation: Information, Process, Management,2009, 9(2):149-167. [14] Yang, J., Shen, G.Q., Ho, M., Drew, D.S., and Chan, A.P.C. Critical success factors for stakeholders management: Construction Practitioners Perspectives, Journal of Construction Engineering and Management. 2009, Doi:10.1061/(ASCE)CO.1943-7862.0000180. 68