NSPS Subpart OOOO: Applicability and Compliance Basics



Similar documents
PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

THE BASICS Q: What is VOC? Q: What are flashing losses/voc emissions from hydrocarbon storage tanks? - 1 -

Control Device Requirements Charts For Oil and Gas Handling and Production Facilities

FINAL UPDATES TO REQUIREMENTS FOR STORAGE TANKS USED IN OIL AND NATURAL GAS PRODUCTION AND TRANSMISSION

Calculating Volatile Organic Compounds (VOC) Flash Emissions from Crude Oil and Condensate Tanks at Oil and Gas Production Sites

Comparison of Emission Calculation Methodologies for the Oil and Gas Industry. Presented by: Leanne Sills

COLORADO REGULATION 7

Class II General Permit G35-C Registration to (Construct, Modify, etc.)

Air Quality Regulation of the Oil and Gas Production Sector in Colorado and Beyond. Garry Kaufman Holland & Hart LLP

Colorado Oil and Gas Emissions Rules

REGULATORY ANALYSIS. February 11, Colorado Department of Public Health and Environment

Highlights of Colorado s New Oil and Gas Hydrocarbon Emission Reduction Rules - Adopted February 2014

Rule Overview Regulation No.3, 6 and 7

State of New Jersey. General Permit. For. Boilers and Heaters [Individually Less Than 10 MMBTU/HR]

Oil and Natural Gas Sector: Standards of Performance for Crude Oil and Natural Gas Production, Transmission, and Distribution.

Garry Kaufman Colorado Air Pollution Control Division May 14, 2014

RULE DRY CLEANERS USING SOLVENT OTHER THAN PERCHLOROETHYLENE

Subpart XX Standards of Performance. Terminals. Environmental Protection Agency

RULE ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS

Company Name: City, State, Zip Code: Annual Report Summary

NOTIFICATION OF PERFORMANCE TESTING FOR GASOLINE DISPENSING FACILITIES (GDFs) NESHAP 40 CFR, Part 63, Subpart CCCCCC (Sections

AESTHETIC AND NOISE CONTROL REGULATIONS

ENVIRONMENTAL STANDARDS FOR PETROLEUM OIL REFINERIES EMISSIONS. Standards for emissions from furnaces, boilers and Power Plant

(Adopted July 7, 1989)(Amended December 7, 1990) (Amended May 13, 1994) FUGITIVE EMISSIONS OF VOLATILE ORGANIC COMPOUNDS

INDEX GENERAL

Regulatory Impact Analysis

Oil and Gas Air Quality Regulations and Permitting

Developing Colorado s s Oil and Gas Emissions Controls Overview of the Process and Requirements

Thermal Mass Flow Meters

How To Make A High Co 2 Gas Blend

Emissions from Natural Gas Production in the Barnett Shale Area and Opportunities for Cost Effective Improvements

Natural Gas Dehydrator Optimization

Description of Thermal Oxidizers

COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT Stationary Sources Program / Air Pollution Control Division. PS Memo 14-03

Nitrogen Blanketing for Methanol Storage and Transportation

Michigan Dry Cleaning Environmental Compliance Workbook

Characterization of Greenhouse Gas Emissions Involved in Oil and Gas Exploration and Production Operations

RULE FURTHER CONTROL OF VOC EMISSIONS FROM HIGH- EMITTING SPRAY BOOTH FACILITIES

THE DETECTION OF GREENHOUSE GASES

Air Permitting in Colorado. Martha Hyder Wind River Environmental Group LLC September 2013

Texas Commission on Environmental Quality Page 1 Chapter Control of Air Pollution from Nitrogen Compounds

Summary of Environment and Social Impacts for Activates Associated with Petroleum Refining and the Storage of Petroleum Products

STATE OF MISSOURI, DEPARTMENT OF NATURAL RESOURCES MISSOURI AIR CONSERVATION COMMISSION PERMIT TO CONSTRUCT

INDUSTRIAL BOILER MACT FACTSHEET

SULFUR RECOVERY UNIT. Thermal Oxidizer

Factory owners must ensure the boiler is:

Lessons Learned from Natural Gas STAR Partners. Installing Vapor Recovery Units on Storage Tanks. Executive Summary. Technology Background

State of the Art (SOTA) Manual for Boilers and Process Heaters

Site Identification No.: AAO Application No.:

Tips from the Help Desk

Process Heater Burners, Flare Systems, Thermal Oxidizers and Catalyst Systems. Combustion Technology

Asphalt Roofing A Guide to Air Quality Regulations

Rule EMISSIONS OF OXIDES OF NITROGEN FROM LARGE WATER HEATERS AND SMALL BOILERS

Leak free means a system where no gasoline is leaked while the system is

Source Sampling Manual Volume II

SNAP CODE: SOURCE ACTIVITY TITLE: Flaring in Gas and Oil Extraction NOSE CODE:

Air Quality PERMIT TO CONSTRUCT

Presentation Outline. Background

1 March Al Dussinger Embrace Home Loans 25 Enterprise Center Middletown, RI Dear Mr. Dussinger,

West Virginia Department of Environmental Protection Division of Air Quality. Fact Sheet

How To Make Calcium Carbide

COMMONWEALTH OF MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION 310 CMR 7.00 AIR POLLUTION CONTROL REGULATIONS

BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS. November 06, 2014 By: François Thibodeau, Eng.

METHANE EMISSIONS MITIGATION OPTIONS IN THE GLOBAL OIL AND NATURAL GAS INDUSTRIES

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600

Welding Codes and How They're Used (DOD) (ANSI). (AWS), (ASME) (API). not American Welding Society AWS D1.1 AWS D1.2 AWS D1.3 AWS D1.4 AWS D1.

Implementation Question and Answer Document. for

Fundamentals of Vapor Recovery

Gas Standards and Safety. Guidance Note GAS INSTALLATIONS SUPPLIED FROM BIOGAS FACILITIES - ACCEPTANCE REQUIREMENTS GAS ACT 2000

Optimization of Natural Gas Processing Plants Including Business Aspects

COMPRESSED GASES. 1.2 The contents of each cylinder and container must be clearly identified (by tag or stamp) on the cylinder.

Emissions from Natural Gas Production in the Barnett Shale Area and Opportunities for Cost-Effective Improvements

Industries. March Prepared for Environmental Defense Fund 257 Park Avenue South New York, NY 10010

Using Advanced Process Controls to Drive Regulatory Emissions Compliance

Subpart I Delaware. 40 CFR Ch. I ( Edition) (10) Amendments to Section V (Surveillance)

GUIDELINE FOR THE INSTALLATION AND OPERATION OF CONTINUOUS EMISSION MONITORING SYSTEMS (CEMS) AND THEIR USE FOR REPORTING UNDER THE PROVISIONS OF

5.2 Transportation And Marketing Of Petroleum Liquids General

Hazardous Waste Accumulation, Storage, & Labeling

Torino Nord. Cogeneration Plant. The gas turbine. The steam generator. The Torino Nord cogeneration plant produces electricity and heat for district

Natural Gas Safety. What You Need to Know

Ethanol Vehicle and Infrastructure Codes and Standards Citations

ANNEX 17 DRAFT AMENDMENTS TO SOLAS REGULATIONS II-2/4 AND II-2/16. Part B Prevention of fire and explosion

Fixing the Leaks: What Would it Cost to Clean Up Natural Gas Leaks?


Transcription:

NSPS Subpart OOOO: Applicability and Compliance Basics Kentucky Oil & Gas Association 2013 Western Kentucky Meeting September 12, 2013 Roy Rakiewicz All4 Inc. Rob Flynn Environmental Standards, Inc. www.all4inc.com Kimberton, PA 610.933.5246 Kennesaw, GA 678.460.0324

Introduction Environmental Standards, Inc. All4 Inc. 2 Your environmental compliance is clearly our business.

Presentation Overview General Applicability Affected Facilities Rule Structure Storage Vessel Affected Facilities Standards for storage vessel affected facilities Recordkeeping for storage vessel affected facilities Reporting for storage vessel affected facilities Compliance for storage vessel affected facilities Gas Well Affected Facilities Standards for gas well affected facilities Recordkeeping for gas well affected facilities Reporting for gas well affected facilities Notification for gas well affected facilities Compliance for gas well affected facilities 3 Your environmental compliance is clearly our business.

General Applicability Commence construction, modification or reconstruction after August 23, 2011 Construction Modification Reconstruction Presentation will address: Storage vessels Gas wells 4 Your environmental compliance is clearly our business.

Subpart OOOO Affected Facilities Gas wells Centrifugal compressors Reciprocating compressors Pneumatic controllers Storage vessels Leak standards at onshore processing plants Sweetening units at onshore natural gas processing plants 5 Your environmental compliance is clearly our business.

Subpart OOOO Structure Determining applicability Effective date Construction, reconstruction, or modification Deadlines Standards Compliance Demonstration Monitoring Testing Notification, recordkeeping, and reporting 6 Your environmental compliance is clearly our business.

Storage Vessels Storage vessel is a tank containing: Crude oil, Condensate, Intermediate hydrocarbon liquids, or Produced water Storage vessels are not: Skid mounted or permanently attached to something that is mobile and on site for < 180 consecutive days Process vessels Pressure vessels 7 Your environmental compliance is clearly our business.

Storage Vessels Affected Facility Single storage vessel Oil and natural gas production segment Natural gas processing segment Natural gas transmission and storage segment Potential to emit (PTE) of volatile organic compound (VOC) emissions >than 6 tpy PTE determined using a generally accepted model or calculation methodology Based on the maximum daily throughput Can rely on enforceable limitations to < 6 TPY VOC PTE based on VOC emissions after any vapor recovery unit (VRU) 8 Your environmental compliance is clearly our business.

Storage Vessels What is a generally accepted model or calculation methodology Not specified by the rule, but examples provided by U.S. EPA in response to comment document include: API s E&P TANK software Vasquez Beggs Equation (VBE) Gas oil ratio (GOR) calculations Process simulation software: HYSIM, HYSYS, WINSIM, and PROSIM TANKS 4.0 Calculations from AP 42 For working and breathing losses only 9 Your environmental compliance is clearly our business.

Storage Vessels State specific tank emission protocols: California Air Resource Board (CARB) Draft Determination of Methane, Carbon Dioxide, and Volatile Organic Compounds from Crude Oil and Natural Gas Separation and Storage Tank Systems http://www.arb.ca.gov/cc/oilgas/flash_test_procedure_apr24.pdf Wyoming: http://deq.state.wy.us/aqd/oil%20and%20gas/march%202010% 20FINAL%20O&G%20GUIDANCE.pdf Texas http://www.tceq.texas.gov/assets/public/permitting/air/guidanc e/newsourcereview/guidance_flashemission.pdf http://www.tceq.texas.gov/assets/public/permitting/air/newsou rcereview/oilgas/produced water.pdf 10 Your environmental compliance is clearly our business.

Example Wyoming Protocol Method Emissions Calculated Comments 1 Direct measurement Working Breathing Flash Sampling and lab analysis required. Results are relatively accurate. 2 Process Simulator Flash only PROMAX, HYSIM, HYSIS, etc. Software is expensive but results are accurate when based on site specific sampling and lab analysis. 3 AP E&P Tanks Software V 2.0 Working Breathing Flash Requires site specific sampling. Not as accurate as more expensive process simulators and no longer supported by the software producer (American Petroleum Institute). 4 Laboratory measurement of the Gas Oil Ratio (GOR) from a pressurized liquid sample 5 EPA Tanks 4.0.9d Flash only Working Breathing only This is a direct laboratory analysis of the flash vapors emitted from a pressurized oil/condensate sample. Program distributed by the EPA through their website at: http://www.epa.gov/ttn/chief/efpac/efsoftware.html From Chapter 6, Section 2, page 22 of Wyoming Permitting Guidance for Oil and Gas Production Facilities: http://deq.state.wy.us/aqd/oil%20and%20gas/march%202010%20final%20o&g%20guidance.pdf 11 Your environmental compliance is clearly our business.

Storage Vessels Group 1 storage vessels Storage vessel for which construction, modification, or reconstruction commenced after August 23, 2011 and on or before April 12, 2013 Determine VOC PTE by October 15, 2013 Comply(install capture and controls) by April 15, 2015 Group 2 storage vessels Storage vessel for which construction modification, or reconstruction commenced after April 12, 2013 Determine VOC PTE by the later of April 15, 2014 or 30 days after start up Comply(install capture and controls) by the later of April 15, 2014 or 60 days after start up 12 Your environmental compliance is clearly our business.

Standards for Storage Vessel Affected Facilities Group 1 storage vessels Submit notification identifying location of each Group 1 vessel with initial annual report Reduce VOC emissions by 95% by April 15, 2015 or Maintain uncontrolled VOC to < 4 TPY after demonstrating that uncontrolled VOC emissions have been < 4 TPY for 12 consecutive months Uncontrolled VOC emissions determined on a monthly basis thereafter using average throughput for the month 13 Your environmental compliance is clearly our business.

Standards for Storage Vessel Affected Facilities Group 2 storage vessels Reduce VOC emissions by 95% by April 15, 2014 or within 60 days after startup or Maintain uncontrolled VOC to < 4 TPY after demonstrating that uncontrolled VOC emissions have been < 4 TPY for 12 consecutive months Uncontrolled VOC emissions determined on a monthly basis thereafter using average throughput for the month 14 Your environmental compliance is clearly our business.

Standards for Storage Vessel Affected Facilities Conditions regarding uncontrolled 4 TPY VOC compliance option if conditions at well change: If well undergoes fracturing or re fracturing: Reduce VOC emissions by 95% as soon as liquids from the well are routed to the storage vessel If VOC emissions increase to > 4 TPY without fracturing or re fracturing Reduce VOC emissions by 95% within 30 days of the determination 15 Your environmental compliance is clearly our business.

Standards for Storage Vessel Affected Facilities Storage vessels removed from service Submit notification in annual report identifying all affected vessels that are removed from service during the period If returning to service and associated with fracturing Comply with control requirement options immediately Submit notification in annual report If returning to service and not associated with fracturing Determine VOC emissions within 30 days If uncontrolled VOC emissions >4 TPY must comply with control requirements within 60 days of return to service Submit notification in annual report 16 Your environmental compliance is clearly our business.

Standards for Storage Vessel Affected Facilities Storage vessel control requirements Control device option Storage vessel cover and all openings must form continuous impermeable barrier over the entire surface area of the liquid Liquids, gases, and fumes must vent through a closed vent system to a control device or process Floating roof option Meet requirements of 40 CFR Part 60 Subpart Kb Vapor recovery units (VRU) must meet closed vent system requirements and have an operational uptime of 95% 17 Your environmental compliance is clearly our business.

Controls for Storage Vessel Affected Facilities Covers Cover and all openings on the cover shall form a continuous barrier over the entire surface area of the liquid in the storage vessel Each cover opening shall be secured in a closed, sealed position (gasket lid or cap) whenever material is in the unit Each storage vessel thief hatch shall be weighted and properly seated Closed vent system (CVS) Design the CVS to route all gases, vapors, and fumes emitted from the material in the storage vessel to a control device Design/operate a CVS with no detectable emissions, as determined using olfactory, visual and auditory inspections Meet control system bypass requirements as applicable 18 Your environmental compliance is clearly our business.

Controls for Storage Vessel Affected Facilities Control device Enclosed combustion device (e.g., thermal vapor incinerator, catalytic vapor incinerator, boiler, or process heater) Designed to reduce the mass content of VOC emissions by 95.0 percent or greater Ensure that each enclosed combustion device is maintained in a leak free condition Install and operate a continuous burning pilot flame Operate the enclosed combustion device with no visible emissions Operation of control devices at all times when gases, vapors, and fumes are vented from the storage vessel affected facility through the closed vent system 19 Your environmental compliance is clearly our business.

Monitoring for Storage Vessel Affected Facilities Closed Vents and Covers Conduct monthly olfactory, visual and auditory inspections for defects that could result in air emissions Control devices Monthly visible emissions test (Method 22) >14 days between tests All inspection, repair and maintenance activities for each unit must be recorded in a maintenance and repair log and must be available for inspection Continuous parametric monitoring system Combustion zone temperature for thermal oxidizers 20 Your environmental compliance is clearly our business.

Testing for Storage Vessel Affected Facilities Control device Testing exemptions Certain flares and boilers Performance test conducted by the manufacturer Testing requirements EPA Methods to determine sample port location and gas volumetric flowrate Collection of integrated bag samples or grab samples EPA Method 25A at inlet and outlet of control device Calculation of control device efficiency on a mass basis Test schedule Initial compliance test 180 days after start up Testing every 60 months thereafter 21 Your environmental compliance is clearly our business.

Recordkeeping for Storage Vessel Affected Facilities VOC PTE determination for each storage vessel with calculation methodology and/or calculation model used Deviations from requirements Mobile vessel consecutive days on site If removed and returned or replaced within 30 days, entire period will count as consecutive days Closed vent system inspections and results Control devices: Minimum and maximum operating parameter values Continuous parameter monitoring data Results of all compliance calculations Results of all inspections 22 Your environmental compliance is clearly our business.

Reporting for Storage Vessel Affected Facilities Initial annual report due January 15, 2014 Subsequent reports due 90 days following end of reporting period General information Storage vessel information Identification and location of each storage vessel affected facility constructed, modified, or reconstructed during the period Documentation of VOC emission rates Records of deviations that occurred during the reporting period Identification of each Group 1 storage vessel with location coordinates Compliance statement regarding initial compliance requirements Storage vessel affected facilities removed from service Storage vessel affected facilites returned to service 23 Your environmental compliance is clearly our business.

Compliance for Storage Vessel Affected Facilities Initial compliance Determine potential VOC emission rate Reduce VOC emissions as required Meet control requirements Submit required notification information Maintain required records Submit Group 1 notifications Continuous Compliance Reduce VOC emissions as specified Demonstrate continuous compliance with performance requirements Cover and closed vent system Control devices 24 Your environmental compliance is clearly our business.

Gas Wells Gas well affected facility Gas well or natural gas well means an onshore well drilled principally for production of natural gas Key distinctions Delineation wells Low pressure gas wells Wildcat wells 25 Your environmental compliance is clearly our business.

Standards for Gas Wells Completions with hydraulic fracturing begun before January 1, 2015 Capture/direct flowback to a completion combustion device (with reliable continuous ignition source) Exceptions include fire/explosion hazards, or where high heat may negatively impact tundra, permafrost or waterways General duty to safely maximize resource recovery and minimize releases to the atmosphere during flowback and subsequent recovery 26 Your environmental compliance is clearly our business.

Standards for Gas Wells Completions with hydraulic fracturing begun after January 1, 2015: Route the recovered liquids into one or more storage vessels or re inject the recovered liquids into the well or another well and; Route the recovered gas into a gas flow line or collection system, re inject the recovered gas into the well or another well, use the recovered gas as an onsite fuel source, or use the recovered gas for another useful purpose that a purchased fuel or raw material would serve, with no direct release to the atmosphere 27 Your environmental compliance is clearly our business.

Standards for Gas Wells Completions with hydraulic fracturing begun after January 1, 2015 (cont.): All salable quality gas must be routed to the gas flow line as soon as practicable Flow line means a pipeline used to transport oil and/or gas to a processing facility, a mainline pipeline, re injection, or routed to a process or other useful purpose In cases where flowback emissions cannot be directed to the flow line Capture/direct flowback to a completion combustion device (with reliable continuous ignition source) 28 Your environmental compliance is clearly our business.

Recordkeeping for Gas Wells All completions with hydraulic fracturing: Records of completions Records of deviations Daily log records for each completion: Post January 1, 2015 location, API well No., duration (hours) of flowback, duration of recovery to flow line, duration of combustion, duration of venting, and reasons for venting Pre January 1, 2015 same as above, except for recovery to flow line requirements Exemption records (e.g., fire, explosion, heat, etc.) Records of required digital photographs (for post January 1, 2015 completions) 29 Your environmental compliance is clearly our business.

Reporting for Gas Wells Annual reports Initial report due January 15, 2014 Subsequent reports due 90 days following end of the reporting period General information Company name and address Identification of each facility included Beginning and end date of the report period Certification of truth, accuracy, and completeness Gas well information Records of each well completion operation for each gas well affected facility conducted during the reporting period or a list of completions with hydraulic fracturing and associated records Records of deviations that occurred during the reporting period 30 Your environmental compliance is clearly our business.

Notifications for Gas Wells Commencement of well completion Electronic or written notification two (2) days prior to the commencement of each completion The anticipated commencement date Contact information of owner/operator API well number Latitude/longitude coordinates Planned flowback date State advance notice requirements are acceptable 31 Your environmental compliance is clearly our business.

Compliance for Gas Wells Initial compliance is demonstrated by: Submit required notifications/annual report Maintain completion logs Maintain records of digital photographs of completions (for post January 1, 2015 completions): Date and latitude/longitude imbedded or stored with the digital file Equipment for storing or re injecting recovered liquid Equipment for routing recovered gas to the gas flow line The completion combustion device (if applicable) connected to and operating at each gas well completion Continuous compliance is demonstrated by: Submitting required reports Maintaining required records 32 Your environmental compliance is clearly our business.

Key Points to Take Away Subpart OOOO is a complicated rule with many moving parts Broad applicability over entire oil and gas sector Determining if a tank is a storage vessel affected facility will likely require process/emissions sampling Time is of the essence Deadline for Group 1 tank VOC emissions determination is October 15, 2013 Annual report for initial compliance period is due January 15, 2014 33 Your environmental compliance is clearly our business.

Contacts Roy Rakiewicz Senior Consultant All4 Inc. 2393 Kimberton Road Kimberton, Pennsylvania 19442 rrakiewicz@all4inc.com www.all4inc.com (610) 933 5246 extension 127 (484) 269 6246 cell Robert W. Flynn, PG Senior Consulting Geoscientist Environmental Standards, Inc. 8331 East Walker Springs Lane Suite 402 Knoxville, Tennessee 37923 rflynn@envstd.com www.envstd.com (865) 376 7590 extension 806 (859) 619 1490 cell 34 Your environmental compliance is clearly our business.