Practical Applications for Clinical Demand and Operations Planning

Similar documents
Equipping your Forecasting Toolkit to Account for Ongoing Changes

Minimize overspend by gaining visibility of total demand

Best Practice Approaches to Improving Clinical Supply Chain Management. Matthew Do Client Development Lead Almac Pharmaceutical Services

SAP APO SNP (Supply Network Planning) Sample training content and overview

Analysis One Code Desc. Transaction Amount. Fiscal Period

Understanding When to Employ IVR and IWR independently or in Combination

Drug Pooling in Clinical Trial Supply Chain

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AGILE RANDOMIZATION AND TRIAL SUPPLY MANAGEMENT SOLUTIONS: A RECIPE FOR SPEED, SIMPLICITY AND SERVICE

Streamlining clinical trial supply management

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

The Thinking Approach LEAN CONCEPTS , IL Holdings, LLC All rights reserved 1

msd medical stores department Operations and Sales Planning (O&SP) Process Document

Delivering a Comprehensive Serialization Traceability Program Peggy Staver - Pfizer

ASCO. R&D Supply Chain and Clinical Trials Supply Management A Life Sciences Solution. Award for the "Best Business Transformation project 2010

How to Utilize an IVRS for Efficient Management of Clinical Supplies

GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4

SAP Business One Integration with Radley icaras EDI. Mascidon, LLC March, 2011 Dr. Don Maes

3.7 Logistics Execution

Optimizing the Clinical Trial Supply Chain

The Training Material on Supply Chain Collaboration & Logistics Solutions has been produced under Project Sustainable Human Resource Development in

End to end Clinical Trial Supply Management with SAP

Materials Management - Inventory Management

Logistics. Drug Pooling in the Clinical Trial Supply Chain

How the Global Supply Chain Organization is Managing the Transition at Eli Lilly & Company. Ronald Bohl

Addressing Risk in Partner / Contractor Selection and Onboarding. Michael Davidson VP Quality Systems and Compliance March 2014

Clinical Supply Chain Management Driving Operational Performance

ELA Standards of Competence on the Supervisory/Operational Management Level

Supply chain maturity study Comparator report HSCNI

MASTER PRODUCTION SCHEDULE

Managing the Extended Clinical Supply Chain in an Outsourced World

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Volume EASTMAN KODAK COMPANY. Worldwide Purchasing. Supplier Manual

Consolidating Multiple Product Development Systems at TreeHouse Foods into SAP Product Lifecycle Management

Developing a Strategy to Optimize Clinical Trial Supplies

Supply Chain development - a cornerstone for business success

GXS Active. Orders. Optimizing the Procure-to-Pay Process. Order Planning and Execution. Order Lifecycle Management.

S&OP Case Study Creating Value at O Neal Manufacturing Services. Anthony Zampello, CPIM, CIRM, CSCP Adjunct Faculty Bentley University

Solution-Driven Integrated Learning Paths. Make the Most of Your Educational Experience. Live Learning Center

CEI Document Management in S/4 Initial Call

Standard of measurement by which efficiency, performance, progress, or quality of a plan, process, or product can be assessed 1.

Daryl Fullerton. Oil & Gas Industry Principal

Manufacturing Flow Management

Supplier Conference Call

Going Lean the ERP Way

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

Managing Open Source Code Best Practices

SAP SCM SUMMIT Best Practices for Supply Chain Optimization in SAP for Vendor Managed Services

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Review of IDR Inventory Control Processes and Implementation of Procedures to Minimize Future Discrepancies. Submitted by Karen Young

BEST PRACTICES IN DEMAND AND INVENTORY PLANNING

GXS Active. Orders. Optimising the Procure-to-Pay Process. Order Planning and Execution. Order Lifecycle Management.

Operational Analytics for APO, powered by SAP HANA. Eric Simonson Solution Management SAP Labs

A BEST Case: Forecast Improvement Project. A Tale of Two BUs

Integrated Fulfillment: Modern Warehouse Management

City & County of San Francisco Permit & Project Tracking System

OVERVIEW OF THE SUPPLY CHAIN ROADMAP

Product Documentation SAP Business ByDesign Supply Chain Setup Management

How To Be Successful In A Business

Oracle EBS Service Contracts Extensions for Oracle Endeca

EMR Capacity Market Implementation Coordination Workshop

How to build a great compliance program for your U.S. imports

GTA Board of Directors September 4, 2014

Process Validation Workshops. Overview Session

COORDINATION IN THE SUPPLY CHAIN: VENDOR MANAGED INVENTORY IS THE WAY TO GO

Executive Branch IT Reorganization Project Plan

Appendix O MANUFACTURING YOUTH APPRENTICESHIP PRODUCTION OPERATIONS MANAGEMENT PATHWAY PRODUCTION OPERATIONS MANAGEMENT (UNIT 8)

Attachment 16.5 SA Power Networks: Supply Chain Strategy

SAP Sales and Operations Planning Compare & Contrast with SAP APO. Phil Gwynne SAP UKI 2013

Product Development and Commercialization Lifecycle

Clinical Supply Chain: Audio Transcript Slide 1: Welcome to the Clinical Supply Chain Course. The upcoming lessons will help you become familiar with

Inventory Management 101: Time to revisit the principles

Cargo Training International

DLA Balanced Scorecard. Janet Foote Senior Strategic Planner 16 December 2004

IT S ALL ABOUT THE CUSTOMER FORECASTING 101

MSD Supply Chain Programme Strategy Workshop

Improve the Agility of Demand-Driven Supply Networks

Rapid Consumption and Deployment of SAP Software as Virtual Appliances Using SAP Cloud Appliance Library

Anatomy of an Enterprise Software Delivery Project

Business Challenges. Customer retention and new customer acquisition (customer relationship management)

ENTERPRISE MANAGEMENT AND SUPPORT IN THE INDUSTRIAL MACHINERY AND COMPONENTS INDUSTRY

Steel supply chain transformation challenges Key learnings

MM - Managing Material Master Data

Real-time Visibility for SAP in Supply Chain & Logistics:

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Inventory Management & Warehouse Management Data Collection & Validation UNON, UNEP & UN-Habitat

Using IVRS in Clinical Trial Management

Ross Systems Inventory Control Module

Materials Management Terms in SAP

Transcription:

Practical Applications for Clinical Demand and Operations Planning Randy Schwemmin Genentech Clinical Demand and Supply Planning Biotech Supply Chain Academy 8 November 2011

Agenda Vision for Clinical Supplies Demand and Supply Planning Process Overview Lead Times and Horizons Drive CD&OP Demand Timeline Supply Timeline Conclusion

Vision for Clinical Supplies

Full visibility of our products in the Supply Chain demand data In order to reliably meet our commitments (compliance, quality, speed, agility, and costs) we need full transparency in the process, an integrated data flow and an automated process. supply execution Patient Enrollment Actuals Clinical Study Forecasting Supply Planning Manufacturing Execution Inventory Mgt and Distribution Label Information Kit IDs Regulatory Information Packaging Orders DP Demand Improved reliability right drug in the right place at the right time, every time. Reduced distribution costs and lower material wastage. Single set of data so everyone can do their job right the first time. 5

All demand and inventory for a product in a single system. demand Connecting Clinical Study demands with TDT demands for upstream production - linking all demand and inventory for a product in a single system. data supply API Active Pharmaceutical Ingredient DP Drug Product FG Finished Goods Raw Materials & Starting Materials Raw Materials & Starting Materials Raw Materials & Starting Materials Improved demand signals. Total network demand visibility improved capacity management. Improved Mfg capacity management. 6

Ensuring aligned demand and supply demand Execution of a Clinical Demand and Operations Planning process (CD&OP) through an integrated global business management process processes supply Transparency to supply costs and improved reliability in financial performance. Single source of data and alignment with Finance processes. Transparency to data and longer term capacity requirement visibility. 7

Clinical Supply Vision integrated an planning and execution process for clinical supplies to meet all clinical trial and development requirements while driving business value through efficient use of our resources. Full visibility of product in our supply chain. All demand and inventory for a product in a single system Ensuring aligned demand and supply 8

Demand and Supply Planning Process Overview

Our Clinical Supply Chain process links information and operations across the company to ensure no patient goes without DEMAND Our process takes in all demands for our clinical products as well as other study drugs (comparators): 1. GNE Sponsored Trials 2. Investigator Sponsored Trials 3. Partner Demand 4. R&D / Tox Demand 5. CMC Demand 6. Commercial Product Demand for Clinical Capacity SUPPLY And converts it into integrated production plans in SAP for all of our products (both internally produced as well as contract manufactured): 1. Commercial product intermediates 2. Drug Substance 3. Drug Product 4. Finished Goods 5. Other Study Drug procurement 5. Movement to our primary depots DISTRIBUTE & RESUPPLY Upon release our products are held at our warehouse, depot, and subdepot locations based on inventory policies used both to resupply sites as well as trigger replenishment production: 1. SAP 2. IVRS 3. Manual processes for non- IVR trials and partner shipments 10

The CD&OP Cycle Steps Step 1 Demand Review Clinical - Include all GNE & IST Trial, Partner, PR&D, Tox Provides feedback to customers on the stability and quality of their inputs and requests Step 2 Pre-Supply Meeting Working sessions where plant schedulers and global planner review the orders coming into the horizon Most issues are resolved here before taken to the next step Step 3 Supply Planning Endorses the monthly supply plan Monitors the health of the clinical supply processes Reviews root cause analysis of major supply misses (i.e. interruptions in patient dosings) Step 4 Executive CD&OP Review Owns clinical asset strategy Governs major clinical supply initiatives (like integration) Reviews annual production budgets, resource plans, and capacity targets Align supply and production plan with business plan 11

Lead Times and Horizons Drive CD&OP - Demand Timeline

Timeline of activities required to successfully enable trial supply (NOTE: assumes drug product is available) *Simplified GSET Timeline US FPI ExUS FPI Final protocol Kit IDs Final country list Ship to US Sites months CRO Assignment US Label/Pack Production July Aug Sept Oct 10 9 8 7 6 5 4 3 2 1 Nov Dec Jan Feb March April GOL assigned Trial assumptions Execution PDM submitted GSM assigned Protocol # Pre country list Protocol summary Comparator procurement decisions Artwork creation Draft label text Labels Approved Mfg tickets created Translated Label Text Depot Contract Finalized Comparator Procured FPI Site Activation Ship to ExUS Sites Ship to Depot (add an add. Month to ship to sites from Depot post QP Rls) ExUS Label/Pack Production ExUS Label/Pack Procured Items 13

Why is the data needed? Trial Assumptions (FPI, LPI, FSA, # of patients, dosing arms, kit configuration) Needed to define the planning SKUs that will be used for the trial, enter demand in the system and create initial supply plans Protocol Summary Needed by Inventory Order Operations to appropriately set up shipment contracts and licensing needs Protocol # - Needed to create planning SKUs and submit the execution PDM Pre Country List Needed to begin depot selection and contract agreements. Needed for label text creation Pre country list should be extensive but within reason taking into consideration: The added work and resources required by Regulatory Label Development to create labels for countries eventually not pursued The added work and contract costs for depot selection and set up for Mfg Collaborations and Inventory Order Operations Comparator Procurement Decisions Needed to create the appropriate planning SKUs and to engage Procurement, Mfg Collaborations & IOO to identify source of supply and distribution requirements CRO Assignment Needed to ensure the final country list can be identified prior to label approval. Needed to define procurement strategies. Needed to finalize the protocol. Final Protocol Needed as confirmation that no more trial changes are expected it represents our time fence point. Changes after this point put supply timelines and activities at risk Kit IDs Needed to be able to order labels for label/pack job Final Country List Needed to finalize the label and place the order with the vendor in time to support label/pack dates Final country list should be a subset of pre country list. New country additions reset the timeline to the start 14

Impact of different types of delays Type of Delay Study Design/Protocol Summary Decisions Protocol Number CRO Selection Impact Bulk inventory and allocation of API to DP cannot be accurately evaluated to support the trial (Planning) Evaluation of the appropriate distribution network and contract requirements cannot be set up (Mfg Collaborations & Distribution) May impact ability to meet FPI due to inability to schedule production, complete label requirements, procure material, etc (Planning, Mfg, Labels, Procurement) Prevents submission of execution PDM to kick off creation of artwork/label, tickets, etc (Planning) Impacts ability to set up the IVRS which can cause delays in release of material or shipments (Distribution) Causes delay in final country selection which impacts artwork/label creation, depot selection/contracts, etc (Labels, Distribution) Regulatory submissions may be delayed (Regulatory) Country List Delays decision on comparator strategy (Procurement) Evaluation of the appropriate distribution network and contract requirements cannot be set up (Mfg Collaborations & Distribution) Label artwork creation can be delayed or resources could be wasted on unneeded countries (Labels) Comparator Drug Decisions Prevents submission of execution PDM to kick off creation of artwork/label, tickets, etc (Planning) Delays depot selection dependant on labeling requirements for the comparator chosen (Mfg Collaborations & Distribution) Impacts purchasing selection options (Procurement) 15

Demand Review Excerpt: Near Term Changes to Trials Trials in upcoming 6 months that have had a change in FSA or FPI 4 month TF 6 month TF 16

Lead Times and Horizons Drive CD&OP - Supply Timeline

Some Time Fence Definitions Today Future Firm zone (SNP Horizon) Free zone PTF End of SNP horizon What is a Planning Time Fence? Defined period of time where the production schedule is considered locked (2 mo for SSF/CMO pack) Why establish a PTF? To provide stability to production schedule and supporting functions focused upon execution/readiness activities to meet the schedule What is an SNP horizon? Defined period of time where APO will not automatically plan production receipts (3 mo for SSF/CMO pack) Why establish a SNP horizon? To leverage APO planning functionality up until the point where order stability is required Why have time gap between PTF and SNP horizon? To allow for MPP to control orders in time bucket currently under review for feasibility through CD&OP 18

Packaging Lead Time sets the Time Fence on the Supply Side Product Planner: 1. Firm order for month crossing PTF includes quantity & lot allocation 2. Maintain accurate long-term plan 3. Specifies due date on MTO orders or initial supply to meet FPI goals Master Planner: 1. Sets priorities for jobs within given month crossing PTF 2. Ensuring plan matches site capabilities 3. Negotiates with GTC/Planner to level load capacity CD&OP: 1. Endorses time fence violations (CRASH requests) 2. Endorses low inventory risk (drop below target) 3. Process for outsourcing jobs as capacity relief 4. Process for network decision making Ties Together: 1) Roles & Resp 2) TF for Decision Making 3) SAP Order Mgmnt Now 2mo Timefence Exec CD&OP 1 focus Plnr/ GTC/ APO Control Slush Period/ MPP Control MPP Control & Crash Order Status Released Released Converted Firm Planned Plnd or Frm Plnd Plnd or Frm Plnd Plnd or Frm Plnd CD&OP Step Demand Review Pre Supply Plng Supply Planning Job Status Make/ Mfg Quality Release Jan Feb Mar Apr May Jun Jul 19

Set Safety Stock Levels to Cover Supply and Demand Variability Safety Stock must cover both demand and supply variability over the Supply Lead Time or Planning Time Fence Policy for Safety Stock 120 day minimum balance @ Primary Depot (fed inventory directly from packaging source) 60 day minimum balance @ Secondary depot (fed inventory from primary depot) Supply Variability Release variability (pack and/or vial lot) Schedule variability (readiness, competing priorities, optimization, etc.) Logistics delays/issues (QP release, depot receipt time, etc.) 4 months of forecasted shipments Demand Variability ~3 months Patient enrollment Dose assumptions (patient weight, other) Location of enrollment (country assumptions) Site activation rate assumption Changes to protocol (increased number of patients/sites) 20

Lead Times imply Inventory Targets, which set Supply Parameters Supply Planning 7.12 APO planning parameters are established per item with default values Re-Order Days Required = sets the safety stock minimum quantity based upon future demand Target Days Required = sets the order quantity to restock inventory based upon future demand Default APO parameters established for various item classifications (MTS, MTO, OSD, other?) For most common MTS item: Re-Order Days = 120 (60) and Target Days = 365 (180) Labels Pack Release Slope = Demand (ship rate from SAP) Stock Level Order Quantity (ceiling) = 365 days Reorder Level Reorder Point Pack Process Order Supply Lead Time Initial Pack order and release Reorder Interval (~8 months) Frozen Period (PTF) = ~2.5 mo Safety Stock (floor) = 120 days FPI Time 21

Production Plan Stability Measures Violations of the Planning Time Fence Packaging plan achieved target. Unadjusted miss reason codes fell into 4 categories 100% 80% 60% 40% 20% 0% Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 All Bulk 75% 83% 50% 92% 75% 50% All Fill 21% 48% 64% 68% 55% 44% All Pack 98% 81% 100% 85% 90% 100% Class A 95% 95% 95% 95% 95% 95% 10 9 8 7 6 5 4 3 2 1 0 Plan/Schedule Source Demand Make Metric reporting issue 14% True PPS miss 45% COMMENTS: 41% of all crashes to the May 2011 plan were approved in advance. Order management issues allowed some delayed lot disposition to appear as PPS Standard clinical business 41% RCA analysis is being performed at Pre-Supply Planning meetings. Verifying metric reporting issues Metric reporting issues require validation that only planned order data is being 22

Conclusions Clinical Demand and Operations Planning is a powerful communication method for balancing clinical needs with supply capability. The tools and steps used in CD&OP are simple and effective (IT investment not required), but doing it right is easier said than done! Understanding lead times in detail builds credibility with customers. Using those lead times as the time fences gives the process a starting point to ask for stable inputs, analyze process health, and improve capabilities. 23

Questions? 24