ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT



Similar documents
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

High Strain Dynamic Load Testing of Drilled Shafts

METHOD OF STATEMENT FOR STATIC LOADING TEST

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

SECTION 1 GENERAL REQUIREMENTS

Step 11 Static Load Testing

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

Section SEWER PIPE INSTALLATION AND TESTING

C. Section TESTING LABORATORY SERVICE.

PERFORMANCE TEST REPORT. Rendered to: FORMTECH ENTERPRISES, INC. SERIES/MODEL: Truline PRODUCT TYPE: PVC Seawall

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

RECENT EXPERIENCES WITH BI-DIRECTIONAL STATIC LOAD TESTING

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Wastewater Capital Projects Management Standard Construction Specification

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION 10 WATER WELL SUPPLY SCOPE OF WORK

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

SECTION NONREINFORCED CONCRETE SEWER PIPE

SECTION GUARDRAILS

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

GLOSSARY OF TERMINOLOGY

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SETTLEMENT INSTRUMENTATION & MONITORING

Code of Standard Practice for Timber Frame Structures

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

The Installation and Load Testing of Drilled Shafts

Method Statement for Static Load Testing (Compression) for Micropiles

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 700 STRUCTURES SECTION 701 DRIVEN PILING MATERIALS Materials Materials shall be in accordance with the following:

Embedded Parts Introduction - Anchors

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

Standard Test Methods for Deep Foundations Under Static Axial Tensile Load 1

CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

PILE TESTING SPECIFICATION

Field Application Note

BLADDER SURGE CONTROL SYSTEM

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

SECTION STORM DRAINAGE SYSTEM

Designed and Engineered to Perform

GMC 2013: Piping Misalignment and Vibration Related Fatigue Failures

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

DIVISION 4300 STORM DRAINAGE

The International Workshop on Micropiles, 2007

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM):

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

SECTION STORM DRAIN SYSTEM

SECTION 3 SANITARY SEWER DESIGN

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION ABANDONMENT OF SEWER MAINS

SECTION SHEETING, SHORING AND BRACING

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

Safe & Sound Bridge Terminology

Technical Notes 3B - Brick Masonry Section Properties May 1993

Pump Skid Fabrication for Magnetic Coupling. Rick Soltis Chief Mechanic City of Bedford

MANUFACTURED HOUSING USED AS DWELLINGS

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Oil and Gas Exploration and Production Oil and gas exploration and production... 22a-472-1

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Annular Space Grouting of Slipline Products

Lighthouse Engineering, L.L.C.

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

ATLAS RESISTANCE Pier Foundation Systems

CHAPTER 6 - SANITARY SEWER

SERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC)

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

SECTION SITE PREPARATION

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

New Safe Confinement

Index Page. Pumping Systems Intensifiers Gas Boosters High Pressure Generators

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

Transcription:

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load Test and reporting the results. The Contractor shall supply all material and labor as hereinafter specified and including prior to, during and after the load test. The test shaft shall be constructed at the location shown on the site plan and in accordance with the requirements of these special provisions and also as outlined elsewhere in project plans and/or contract documents. The Contractor shall employ the services of Loadtest, Inc. 2631-D NW 41 st Street Gainsville, FL 32606 Phone (800) 368-1138 (352) 378-3717 Fax: (352) 378-3934 to instrument and conduct the load test(s) on the drilled shaft(s) used for the load test. The Contractor shall provide auxiliary equipment and services as detailed herein. If a test shaft is constructed at a production shaft location (intended to carry structural service loads) it shall be left in a condition suitable for use as a production shaft in the finished structure. Materials: The Contractor shall furnish all materials required to install the O-Cell, conduct the load test, and remove the load test apparatus as required. The Contractor shall furnish one (1) or more O-Cells as required for each load test. The O-Cell(s) to be provided shall have a bi-directional capacity as called for in the project plans and/or contract documents and shall be equipped with all necessary hydraulic lines, fittings, pressure source, pressure gage and telltale devices. Construction Method: 1. Submittals: The Contractor shall submit a testing plan with working drawings which outline the test setup, including details of all system elements, instrumentation, materials, data collection system and procedures. This testing submittal shall be developed in coordination with and submitted concurrently with the Drilled Shaft working drawing submittal as required in related specifications elsewhere in the contract documents. All submittals shall comply with the working drawing submittal requirements as outlined in Article 1.05.02 of the Form 816. 2. Equipment: The Contractor shall supply equipment and labor required to install the O-Cell, conduct the load test, and remove the load test apparatus as required. Required equipment includes but is not limited to:

(a) Fresh, clean, potable water from an approved source to be used as hydraulic fluid to pressurize the O-Cell. (b) Materials sufficient to construct a stable reference beam system for monitoring movements of the shaft during testing. The system shall be supported at a minimum distance of 3 shaft diameters from the center of the test shaft to minimize disturbance of the reference system. A good quality, self-leveling surveyor s level shall be provided to monitor the reference system. (c) Materials sufficient to construct a protected work area (including provisions such as a tent or shed for protection from inclement weather for the load test equipment and personnel) of size and type required by Loadtest, Inc. In the case of cold weather, the protected work area shall be maintained at a temperature above 40 F in order to insure proper operation of the load testing equipment. (d) Stable electric power source, as required for lights, welding, instruments, etc. (e) Materials for carrier frame, steel bearing plates and/or other devices needed to attach O-cell to rebar cage, as required. (f) Welding equipment, certified welding personnel and labor, as required, to assemble the test equipment under the supervision of Loadtest, Inc., attach instrumentation to the O-Cell(s), and prepare the work area. (g) Equipment and labor to construct the steel reinforcing cage and/or placement frame including any steel bearing plates required for the test shaft. (h) Equipment and operators for handling the O-Cell, instrumentation and placement frame or steel reinforcing cage during the installation of the O-Cell and during the conduct of the test, including but not limited to a crane or other lifting device, manual labor, and hand tools as required by Loadtest, Inc. (i) Equipment and labor sufficient to erect the protected work area and reference beam system, to be constructed to the requirements of Loadtest, Inc. (j) Air compressor (minimum 185cfm, 100psi) for pump operation during the load test. 3. Installation and Removal of Load Testing Apparatus: For the drilled shaft(s) selected for testing in the contract or by the Engineer, the Contractor shall construct the drilled shaft using the approved shaft installation techniques until the drilled shaft excavation has been completed. The O-Cell, hydraulic supply lines and other instruments will be assembled and made ready for installation under the direction of Loadtest, Inc., in a suitable area, adjacent to the test shaft, to be provided by the Contractor. When a steel reinforcing cage is required for the shaft, the O-Cell assembly shall be welded to the bottom of the cage in conjunction with the construction of the cage. The plane of the bottom plate(s) of the O-

cell(s) shall be set at right angles to the long axis of the cage. The Contractor shall use the utmost care in handling the test assembly so as not to damage the instrumentation during installation. The contractor shall limit the deflection of the cage to two (2) feet between pick points while lifting the cage from the horizontal position to vertical. The maximum spacing between pick points shall be 25 feet. The contractor shall provide support bracing, strong backs, etc. to maintain the deflection within the specified tolerance. The O-cell assembly must remain perpendicular to the long axis of the reinforcing cage throughout the lifting and installation process. When the test shaft excavation has been completed, inspected and accepted by the Engineer, the O-cell assembly and the reinforcing steel may be installed. A common method is to install the O-cell assembly using a pump line or tremie pipe extending through the O-cell assembly to the base of the shaft. Depending on the configuration of the test assembly, it may be necessary to deliver a seating layer of concrete prior to installing the O-cell. In this case, the O-cell assembly would be installed while the concrete or grout at the base is still fluid, under the direction of the Loadtest, Inc. The O- Cell should end up at least partially submerged and firmly seated into the base grout or concrete After seating the O-Cell, the remainder of the drilled shaft will be concreted in a manner similar to that specified for production shafts. However, if approved by the Engineer, the Contractor may use high early strength cement (Type III) in the mix to reduce the time between concreting and testing. At least four (4) concrete test cylinders, in addition to those specified elsewhere, shall be made from the concrete used in the test shaft, to be tested at the direction of Loadtest, Inc. At least one of these test cylinders shall be tested prior to the load test and at least two cylinders shall be tested on the day of the load test. Load testing shall not begin until cylinder break testing has confirmed that the drilled shaft concrete has obtained the compressive strength as call for in the plans or contract documents. Testing to confirm the concrete strength shall be in conformance with Article 6.01.03 of the Form 816. During the load test, no casings may be vibrated into place in the foundation area near the load test. Drilling may not continue within a 100-foot radius of the test shaft. If test apparatus shows any interference due to construction activities outside of this perimeter, such activities shall cease immediately. After the completion of the load test, the Contractor shall remove any equipment, material, waste, etc. which are not to be a part of the finished structure. If the load test shaft is constructed at a production location and intended to carry service loads, the Contractor shall grout the interior of the O-Cell and annular space around the outside of the O-Cell using grouting techniques approved by Loadtest, Inc. 4. Testing and Reporting: The load testing and reporting shall be performed by Loadtest, Inc. The report shall be signed by a Professional Engineer registered in the State of Connecticut. The load testing shall be performed in general compliance with ASTM D 1143 Standard Test Method for Piles Under Static Axial Load using the Quick Load Test Method for Individual Piles. Initially the loads shall be applied in increments equaling 5 to 8% of the anticipated ultimate capacity of the test shaft. The magnitude of the load increments may be increased or decreased depending on the project requirements but should not be changed during the test.

Direct movement indicator measurements should be made of the following: O-cell expansion either directly or with telltales (minimum. of 3 indicators required), upward top-of-shaft displacement (minimum of 2 indicators required) and shaft compression above O-cell (minimum. of 2 indicators required). Loads shall be applied at the prescribed intervals until the ultimate capacity of the shaft is reached in either end bearing or side shear, until the maximum capacity or maximum stroke of the O-cell is reached, or unless otherwise directed by the Engineer. Multiple load cycles to the maximum stroke of the O-Cell will be required for test performed on non-production drilled shafts. At each load increment, or decrement, movement indicators shall be read at 1, 2, 4 and 8-minute intervals while the load is held constant. During unloading cycles the load decrement shall be such that at least 4 data points are acquired for the load versus movement curve. Additional cycles of loading and unloading using similar procedures may be required by the Engineer following the completion of the initial test cycle. Digital dial gages, LVDTs, or LVWDTs used to measure O-cell expansion and top-of-shaft displacement should have a minimum travel of 4 inches and be capable of being read to the nearest 0.001 inch division. When O-cell expansion is measured directly, or when testing requires the maximum stroke of the O-Cell to be reached, LVWDTs capable of measuring the full stroke of the O-Cell will be used. Digital dial gages, LVDTs, or LVWDTs used to measure shaft compression should have a minimum travel of 1 inch and be capable of being read to the nearest 0.001 inch division. Unless otherwise specified by the Engineer, the Contractor will supply six (6) copies of a report of each load test, as prepared by Loadtest, Inc. An initial data report containing the load-movement curves and data tables will be provided to the Engineer within 4 working days of the completion of load testing, to allow evaluation of the test results. A final report on the load testing shall be submitted to the Engineer within 7 working days after completion of the load testing. As a minimum, the report shall include the following: (a) As-installed location of the test shaft. (b) Logs of test borings conducted at the test shaft location. (c) Installation records of test shaft showing locations of all instrumentation. (d) Summary of the load test procedure and data collected during load testing. (e) Analysis of unit side adhesion in the test socket and unit end-bearing pressure. (f) Plots of axial load versus displacement at the base of the shaft, and axial load versus displacement and/or strain along the test socket.

5. Post-Test Grouting Procedures: Commentary: This section should be only be used when the test is to be performed on a production drilled shaft. It should be deleted if the load test is to be performed on a nonproduction drilled shaft. During the O-cell test, the shaft breaks on a horizontal plane separating the upper section above the O-cell (upper side shear) from the lower section below (combined end bearing and lower side shear). This creates an annular space, the size of which depends on the shaft/o-cell geometry and the expansion of the O-cell. When a production shaft has been tested, the Engineer may want to include the end bearing component from the lower section in order to obtain sufficient capacity of the production shaft. In such cases the contractor will be required to grout the O-Cell and the annular space around the O-Cell in order to allow load transfer to the lower side shear and end bearing. Grout used for filling Access Tubes shall conform to the requirements of Article M.03.01-12 of the Standard Specifications. The grout shall have strength properties equivalent to or better than those of the drilled shaft concrete. (a) Grouting of O-Cells i. The grout shall consist of Portland cement and water only, NO SAND. The grout shall be fluid and pumpable. An initial mix consisting of 6 to 7 gallons of water per 95-lb bag of cement is recommended. Adjust water to obtain desired consistency. ii. The mixing shall be thorough to ensure that there are no lumps of dry cement. Pass the grout through a window screen mesh before pumping. iii. Connect the grout pump outlet to one hydraulic line of the O-cell. Open the other line and establish a flow of water through the system. iv. Pump the grout through the O-cell hydraulic line while collecting the effluent from the bleed line. Monitor characteristics of effluent material and when it becomes equivalent to the grout being pumped, stop pumping. v. Take three samples of the grout for compression testing @ 28 days, if required. Recommended pre-mixed amount of grout for grouting of O-cell: O-cell Diameter (Inches) 13 21 26 34 Grout Volume (Cubic Feet) 4 7 9 13 (b) Grouting of Annular Space Around O-Cells i. Prepare a fluid grout mix consisting of Portland cement and water only, no sand. The mixing procedures should be as outlined for grouting the O-Cells. The quantity of grout

should be at least three (3) times the theoretical volume required to fill the annular space and grout pipes. ii. Pump water and establish a flow through the grout pipes (two per shaft). iii. Pump the fluid grout through one of the grout pipes until grout is observed flowing from the second grout pipe or until 1.5 times the theoretical volume has been pumped. iv. If no return of grout is observed from the second grout pipe, transfer the pump to the second pipe and pump grout through it until 1.5 times the theoretical volume has been pumped. v. If higher strength grout is deemed necessary, immediately proceed with pumping the higher strength grout (which may be a sand mix). The pumping procedures for this grout will be the same as described above for the initial cement-water grout. The entire grouting operation must be completed before the set time for the initial grout has elapsed. vi. Take three (3) samples of each type of grout for compression testing @ 28 days. Recommended pre-mix amount of grout for grouting of annular space: Shaft Diameter (Feet) 2 3 4 5 6 7 8 9 Grout Volume (Cubic Feet) 25 30 40 50 65 80 100 125 Method of Measurement: The Osterberg Cell Load Testing of Drilled Shaft shall be measured by the actual number of test(s) completed and accepted, and shall include and material, labor and equipment necessary for the O-Cell load testing of the drilled shaft(s). This item should include everything necessary to assemble, install and remove the load test apparatus, conduct and report results of the load test, and grouting of the O-Cell and annular space around the O-Cell. All costs associated with the normal production of the drilled shafts are measured and paid for elsewhere in the contract documents. Basis of Payment: The O-Cell load tests shall be paid for at the contract unit price each for accepted "Osterberg Cell Load Testing of Drilled Shaft". The price and payment shall be considered full compensation for furnishing all materials, providing all tools, equipment, labor and incidentals to perform the Statnamic load test, subsequent removal of test apparatus and appurtenances, and preparation of the load test report.