NENA Communications Center/PSAP Disaster and Contingency Plans Model Recommendation

Similar documents
NENA Call Answering Standard/Model Recommendation

NENA Human Resources Subcommittee Resource List (OID)

NENA Emergency Call Processing Protocol Standard

NENA/APCO. Operations Information Document (OID)

NENA IP Capable PSAP Features And Capabilities Standard

WIRELESS PHASE I & II FEATURES & FUNCTIONS Operational Information Document (OID)

AMBULATORY SURGICAL CENTERS

HOSPITALS STATUTE RULE CRITERIA. Current until changed by State Legislature or AHCA

Emergency Management Planning Criteria for Ambulatory Surgical Centers (State Criteria Form)

EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS

Emergency Management Planning Criteria for Assisted Living Facilities (State Criteria Form)

Table of Contents ESF

Hospital Emergency Operations Plan

Verizon, 911 Service and the June 29, 2012, Derecho

AMBULATORY SURGICAL CENTERS (Based upon AHCA Form # JUL 94)

Emergency Management Planning Criteria for Hospital Facilities (State Criteria Form)

PUBLIC SAFETY FIRE. Functional Coordinator: Fire Chiefs

Overview of Business Continuity Planning Sally Meglathery Payoff

Franklin County Emergency Management Department (FCEMD) All County Emergency Response Team (CERT) Agencies. Table of Contents

University of Prince Edward Island. Emergency Management Plan

It also provides guidance for rapid alerting and warning to key officials and the general public of a potential or occurring emergency or disaster.

EMERGENCY MANAGEMENT PLANNING CRITERIA FOR HOSPITALS

CITY OF RICHMOND CONTINUITY OF OPERATIONS (COOP) DEPARTMENT PLAN TEMPLATE

NENA Integrating Applications on Intelligent Workstations Technical Information Document

Emergency Operations Plan ANNEX K - UTILITIES RESTORATION ESF #3, #12 I. MNWALK REQUIREMENTS. Item #: 1, 4, 46, 53, 54

*****IMPORTANT SUBMITTAL INFORMATION*****

CEMP Criteria for Residential Treatment Facilities

EMERGENCY MANAGEMENT PLANNING CRITERIA FOR ADULT DAY CARE FACILITIES

NG9-1-1 System and PSAP Operational Features and Capabilities Requirements

<Client Name> IT Disaster Recovery Plan Template. By Paul Kirvan, CISA, CISSP, FBCI, CBCP

Chapter 5.58 SECURITY ALARM SYSTEMS

Alabama Radiological Emergency Preparedness Plan

The Emergency Operations Plan provides guidance for managing emergency communications resources.

ANNEX B COMMUNICATIONS

All-Hazard Continuity of Operations Plan. [Department/College Name] [Date]

LOCAL RADIO STATION MODEL VULNERABILITY ASSESSMENT CHECKLIST. Developed by the Toolkit Working Group for the Media Security and Reliability Council

NURSING HOME STATUE RULE CRITERIA

BUSINESS CONTINUITY PLANNING

Emergency Management of Long-term Care Facilities

CROSS-REFERENCE FOR COMPREHENSIVE EMERGENCY MANAGEMENT PLAN RESIDENTIAL TREATMENT CENTERS FOR CHILDREN AND ADOLESCENTS

Table of Contents ESF

Green Mountain College EMERGENCY RESPONSE AND RECOVERY PLAN

EMERGENCY MANAGEMENT ORGANIZATION

AUSTRACLEAR REGULATIONS Guidance Note 10

Supplement No Telephone - PA P.U.C. No. 5 Palmerton Telephone Section 10 Company Original Sheet 1 UNIVERSAL EMERGENCY SERVICE NUMBER - 911

CISM Certified Information Security Manager

Emergency Management Planning Criteria For Residential Treatment Facilities

TOOELE COUNTY EMPLOYEES EMERGENCY SAFETY HANDBOOK 2012 REVISION

Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0

IT Disaster Recovery Plan Template

ASX CLEAR (FUTURES) OPERATING RULES Guidance Note 10

BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged)

NENA Recommended Standards For Local Service Provider Interconnection Information Sharing

ASX SETTLEMENT OPERATING RULES Guidance Note 10

Workforce Solutions Business Continuity Plan May 2014

Template Policy on Healthcare Facility Patient Evacuation and Shelter-in Place

BUSINESS CONTINUITY MANAGEMENT PLAN

Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans

Comprehensive Emergency Management Plan (CEMP) Annex V CONTINUITY OF OPERATIONS PLAN (COOP)

CRISIS PREPAREDNESS:

Offsite Disaster Recovery Plan

IT Service Management

SOLUTION BRIEF. Motorola FSA4000. How to Achieve Near 100% Fire Station Alerting Reliability

ANNEX 9. PUBLIC INFORMATION AND WARNING

Emergency Management Planning Criteria for Nursing Home Facilities (Criteria)

PRIVATE SWITCH (PS) E DATABASE STANDARD

EMERGENCY RESTORATION PLAN SKYLINE TELEPHONE MEMBERSHIP CORPORATION. Revised: December 30, 2011 TABLE OF CONTENTS. I. Purpose 2

Sample Model Security Management Plan

Business Continuity Plan (BCP)

Draft 8/1/05 SYSTEM First Rev. 8/9/05 2 nd Rev. 8/30/05 EMERGENCY OPERATIONS PLAN

Massachusetts Institute of Technology. Functional Area Recovery Management Team Plan Development Template

SECTION 15 INFORMATION TECHNOLOGY

RUSK COUNTY ELECTION CONTINGENCY PLAN

Emergency Response & Recovery Basic Plan

Request for Proposals. For a. Fire Station Alerting System

Abnormal Operating Conditions Emergency Plans and Public Awareness Plans for Natural Gas Systems

Emergency Operations California State University Los Angeles

UNION COLLEGE SCHENECTADY, NY EMERGENCY MANAGEMENT PROCEDURES

West Chester University of Pennsylvania Official University Mass Communication Methods

Emergency Restoration Plan (ERP) Components

The Jefferson County Board of Supervisors does ordain as follows:

SAMPLE IT CONTINGENCY PLAN FORMAT

ICS ORIENTATION Saskatchewan

Fire Station IP Alerting System

Fairfax County Government. Emergency Planning Guidance for Medical and Patient Care Facilities

Page Administrative Summary...3 Introduction Comprehensive Approach Conclusion

The University of Iowa. Enterprise Information Technology Disaster Plan. Version 3.1

NAIT Guidelines. Implementation Date: February 15, 2011 Replaces: July 1, Table of Contents. Section Description Page

EMERGENCY PREPAREDNESS PLAN

LAMAR STATE COLLEGE - ORANGE INFORMATION RESOURCES SECURITY MANUAL. for INFORMATION RESOURCES

B E F O R E T H E E M E R G E N C Y

Transcription:

NENA Communications Center/PSAP Disaster and Contingency Plans Model Recommendation NENA Communications Center/PSAP Disaster and Document 53-001 Prepared by: National Emergency Number Association (NENA) SOP Committee, Contingency Planning Sub- Committee, Disaster Recovery Working Group Published by NENA Printed in USA

NENA Operational Standard/Model Recommendation NOTICE This Operational Standard/Model Recommendation is published by the National Emergency Number Association (NENA) as an information source for the voluntary use of communication centers and is provided as an example only. It is not intended to be a complete operational directive. NENA reserves the right to revise this for any reason including, but not limited to, conformity with criteria or standards promulgated by various regulatory agencies, utilization of advances in the state of operational techniques or services described herein. It is possible that certain federal, state or local regulations may restrict or require modification of the recommendations contained in this document. Therefore, this document should not be the only source of information used. NENA members are advised to contact their legal counsel to ensure compatibility with local requirements. By using this document, the user agrees that NENA will have no liability for any consequential, incidental, special, or punitive damages arising from use of the document. NENA s Operations Committee has developed this document. Recommendations for change to this document may be submitted to: National Emergency Number Association 4350 North Fairfax Drive Suite 750 Arlington, VA 22203-1695 800-332-3911 703-812-4600 Page 2 of 15

Acknowledgments: This document has been developed by the National Emergency Number Association (NENA) Disaster Recovery Working Group, Contingency Planning Sub-Committee, Standard Operating Procedures Committee. The following individuals are recognized for their contributions in development of this document. Members: Rick Jones Operations Issues Director Norm Forshee Operations Committee Liaison (2004-2005) Bill Weaver Operations Liaison (2003-2004) Steve O Conor, ENP SOP Committee Chair John Haynes Contingency Planning Sub-Committee Chair Wendi Lively Human Resources Sub-Committee Chair Ed Marecki Human Resources Sub-Committee Chair Linda Draughn-Woloski, ENP, Disaster Recovery WG Chair Roy Hamlin, Disaster Recovery WG Ben Robinett, Disaster Recovery WG Susan Makky, Disaster Recovery WG Paul Adams Mark Adler Marc Berryman Clay Carter Ruthie Doles Tom Donohoe Chuck Freeman Sandi Hutchcroft Dick Nelson Susan Pettingill Benjamin Robinett Fran Self Julie Thruman Company/Agency NENA St Clair County, IL ETSB Combix Corporation Brevard County, FL Chester County, PA Spartanburg, SC Dover, DE 9-1-1 Consulting Miami, FL St. Charles County, MO St. Charles County, MO Huntington County, IN Palm Beach County, FL Greater Harris County, TX Huntington County, IN Pinellas County, FL Minneapolis, MN Pinellas County, FL Dubuque, IA Marion County, FL Orange County, FL St. Charles County, MO Palm Bay, FL Rochelle, IL Page 3 of 15

TABLE OF CONTENTS NENA Communications Center/PSAP Disaster and 1. EXECUTIVE OVERVIEW...5 2. INTRODUCTION...6 2.1 PURPOSE AND SCOPE...6 2.2 REASON TO IMPLEMENT...6 2.3 BENEFITS...6 2.4 TECHNICAL IMPACTS SUMMARY...6 2.5 DOCUMENT TERMINOLOGY...6 2.6 REASON FOR REISSUE...7 2.7 COST FACTORS...7 2.8 COST RECOVERY CONSIDERATIONS...7 2.9 ACRONYMS/ABBREVIATIONS...7 3. DISASTER AND CONTINGENCY PLANS...7 3.1 STAFFING...7 3.2 IT SECURITY...8 3.3 REDUNDANT SYSTEMS...8 3.4 RATIONALE FOR EVACUATION...9 3.5 EVACUATION PROCEDURES...10 3.5 RETURN TO NORMAL OPERATIONS...11 4. REFERENCES...12 5. EXHIBITS...13 Page 4 of 15

1. Executive Overview This document is provided as a Model Recommendation for the creation of the Disaster and Contingency Planning section of a Standard Operating Procedure (SOP) for use by Communications Centers and/or PSAPs as guidance in the formulation of an agency SOP. Each agency is unique in it resources and operations. This document is a Model Recommendation and should be changed to meet the requirements of differing modes of operations. The unique nature of Communications Centers/PSAPs requires that daily operations continue regardless of circumstance. It is therefore imperative that PSAPs have plans and procedures for circumstances that have the potential to adversely affect the ability of the staff to perform their duties. This document includes guidelines and procedures on: Staffing IT Security Redundant Systems Situations requiring evacuation Evacuation Procedures Return to Normal Operations Page 5 of 15

2. Introduction 2.1 Purpose and Scope The purpose of the NENA Model Recommendation for Disaster and Contingency Plans is to provide general guidelines for circumstances that may adversely impact the Communications Center/PSAP personnel to receive, process, dispatch and monitor emergency calls for assistance. As each agency has unique resources and circumstances, this document should be changed to meet the individual needs of the Communications Center/PSAP as required to plan for disaster operations. 2.2 Reason to Implement The NENA Model Recommendation for Disaster and Contingency Plans has been developed to provide standardized guidelines for use during disaster situations that may impact the Communication Center s/psap s ability to maintain normal operations. 2.3 Benefits Implementation of this Model Recommendation as a Standard Operating Procedure will: Prepare Communications Centers/PSAPs for disaster situations. Provide guidelines for the orderly evacuation of the Communications Center. Provide guidelines for the return to normal operations. Increase the probability of maintaining functionality during a disaster situation. 2.4 Technical Impacts Summary In the event of an evacuation of the Communications Center/PSAP, alternate means of call receipt, entry, dispatch and monitoring must be available. The technical impact will vary greatly dependent upon the size and complexity of the center. At a minimum the phone service provider, radio and Computer-Aided-Dispatch vendor should be consulted to review options for alternate call taking and dispatching services. 2.5 Document Terminology The terms "shall ", "must " and "required" are used throughout this document to indicate required parameters and to differentiate from those parameters that are recommendations. Recommendations are identified by the words "desirable" or "preferably". Page 6 of 15

2.6 Reason for Reissue NENA Communications Center/PSAP Disaster and NENA reserves the right to modify this document. Whenever it is reissued, the reason(s) will be provided in this paragraph. 2.7 Cost Factors It is recommended that a back-up facility be adequate to meet the basic needs of the system. It need not be a fully redundant, mirror of the primary Communications Center. The cost of this recommendation will vary greatly depending on the size and complexity of the system. Cost will include reoccurring and nonrecurring expenses, which will likewise be dependent upon the system. Wherever feasible, a back-up facility should be dual use. An example of dual use is a back-up facility that is also used for telecommunicator training. 2.8 Cost Recovery Considerations Cost Recovery will vary greatly depending on the jurisdiction of the Communication Center/PSAP. Administrators are urged to review their cost recovery legislation and apply for all available funding. 2.9 Acronyms/Abbreviations The acronyms/abbreviations used in this document have been approved. The master glossary is located at http://www.nena.org/9-1-1techstandards/nena_recommended_standards.htm 3. Disaster and Contingency Plans 3.1 Staffing The supervisor is responsible for assuring that minimum staffing levels are met for each duty assignment. Minimum staffing means the predefined minimum number of staff required per shift. If minimum staffing levels are not being met the supervisor shall make every effort to complete staffing with overtime personnel who are fit for duty. If off duty personnel are not available and minimum staffing has not been met then the supervisor shall require that on duty personnel remain on duty until minimum staffing can be met or they reach maximum hours worked. Maximum hours worked is the predefined maximum allowable hours a telecommunicator is permitted to work between 8 hours of rest. If qualified telecommunicators are not available then off duty supervisory personnel shall fill positions to meet minimum staffing requirements. Page 7 of 15

3.1.1 During times of inclement weather telecommunicators should plan accordingly. This includes planning to arrive at work on time and preparing to stay for an extended time if required. 3.1.2 Safe transportation should be considered if travel conditions warrant. 3.1.3 Sleeping accommodations should be available for all staff staying at the Communications Center during disaster operations. 3.1.4 Food and comfort facilities should be available for all staff during disaster operations. Commentary: The safety of Communications Center staff will dictate both travel and the requirement to remain at the center. Staff who are not comfortable driving in certain weather conditions should make prior arraignments to arrive at work on time and, if necessary, remain at the Center for extended periods. 3.2 IT Security Today s Public Safety Answering Points (PSAPs) face more threats than ever before. From hackers to intruders to inadvertent user error PSAPs must carefully protect their information technology components. The availability of a PSAP can be directly impacted by any of the aforementioned threats and as such an in-depth approach to IT Security is required. IT Security can be defined as the protection of information systems against unauthorized access to or unauthorized modification of information whether in storage, processing or transit, and against the denial of service to authorized users, including those measures necessary to detect, document and counter such threats [Source: Department of Defense Information Assurance Policy and Technology Computer Based Training CD, Version 1.0, October 2003] Any Contingency or Disaster Recovery Plan should include appropriate IT security measures. Please refer to an upcoming Technical Information Document from the NENA Security Working Group that addresses IT Security as it relates to the PSAP in greater detail. 3.3 Redundant Systems Component failure is inevitable. Any issue which hinders the ability to receive, process, dispatch and monitor emergency calls must be quickly handled with minimal disruption. Redundant systems are needed to continue operation when a failure causes the loss of a needed resource. These systems include but are not limited to: 3.3.1 Electrical power 3.2.1.1 The Communications Center will have at least one back-up generator with the capacity to operate all essential electrical components of the system. Page 8 of 15

3.2.1.2 All console equipment and radio equipment shall have Uninterrupted Power Supply. 3.2.1.3 Back-up power supply will have the ability to run indefinitely so long as fuel is available. 3.3.2 Telephone service 3.3.2.1 The Communications Center shall have a procedure to reroute emergency phone calls in the event of a failure of the primary phone system. This may be accomplished by several means: Advance Intelligent Network which directs calls to back-up numbers. These numbers may terminate at the console or at a secondary site. Transfer calls to an alternate PSAP. The alternate PSAP can be another jurisdiction or a back-up facility. 3.3.2.2 The Communications Center shall have access to the Emergency Alert System (EAS) to notify citizens in the event that 9-1-1 cannot be dialed. The notification shall have procedures for reporting emergencies. 3.3.3 Public Safety Radio Network 3.3.3.1 The Communications Center shall have a means of alerting and communicating with emergency responders in the event of a failure of the Public Safety Radio Network. 3.3.3.2 The back-up radio system should be readily available and routinely tested to ensure operational functionality. 3.2.4 Computer-Aided-Dispatch The Communications Center shall have a procedure to maintain operations in the event that the Computer-Aided-Dispatch system fails. Commentary: The method of redundancy will vary between Communications Centers. It is desirable to have at least two layers of redundancy for each major component of the system. All redundant systems should be tested for operability no less than monthly. 3.4 Rationale for Evacuation Relocation of personnel may be required for many specific reasons. The two main factors requiring evacuation of the PSAP are: Uninhabitable environment Infrastructure failure Page 9 of 15

3.4.1 Uninhabitable Environment Situations which make the Communications Center unsafe for personnel to continue daily operations. These conditions may include but are not limited to: Bomb Threats/Found Fire/Smoke Condition Gas leak Hazardous Materials Structural damage 3.4.2 Infrastructure Failure Situations during which technical components of the system fail - within or leading to the Communications Center. These conditions may include but are not limited to: Commentary: Phone service outage Radio component damage The reason for the need to evacuate is unimportant except for the urgency of removing personnel from a hazardous situation. It is desirable, if primary infrastructure is intact, that it be used during evacuation. 3.5 Evacuation Procedures The Director or Designee shall have the authority to activate all or any part of the Disaster and Contingency Plan. 3.5.1 On Duty Supervisor Notify off duty staff to respond to alternate site Direct non committed personnel to evacuate to alternate site Notify telephone company and when appropriate activate contingency routing of emergency phone calls. Ensure that routing includes both 9-1-1 trunks and other emergency lines. Notify radio contractor Ensure alternate PSAP is staffed/notified of evacuation Notify other PSAPs of evacuation and termination of direct lines Page 10 of 15

Alternate Route Law Enforcement Terminals Notify Nuclear facilities of evacuation NENA Communications Center/PSAP Disaster and Ensure all emergency responders are notified of evacuation Ensure the evacuation of all staff Confirm routing of emergency calls and ability to communicate with emergency responders 3.5.2 On Duty Telecommunicators Maintain operations until directed to evacuate Notify emergency responders of relocation Evacuate and report to assigned duty station as directed by supervisor 3.5.3 Off Duty Telecommunicators Commentary: Report to assigned duty station as directed by supervisor Evacuation procedures and duties must be adapted to the individual circumstances of the implementing agency. PSAPs should establish procures which provide for a quick transfer of operations from one location to another. Intermediate evacuation steps such as a mobile communications vehicle with phone and radio communications to maintain operations until the back up site is staffed will enhance the system and maintain service. 3.5 Return to Normal Operations Prior to a return to normal operations; the Communications Center should be thoroughly assessed to ensure that it is safe for personnel to return. If the event was an infrastructure incident then all technical contractors should assess their equipment for operational functionality. When the Communications Center has been assessed and all components found to be in normal working order the authorization to return to normal operations will be given 3.5.1 On Duty Supervisor Notify designated staff to return to Communications Center Ensure staffing of a back-up site until Communications Center is prepared to resume normal operations Notify telephone company and when appropriate activate normal routing of 9-1-1 trunks and other emergency phone lines Notify radio contractor Page 11 of 15

Notify other PSAPs of return to normal operations and resumption of direct lines Reverse alternate routing of Law Enforcement Terminals Notify Nuclear facilities of return to normal operations Ensure all emergency responders are notified Ensure all personnel are accounted for Confirm routing of emergency calls and ability to communicate with emergency responders Release off duty Telecommunicators 3.5.2 On Duty Telecommunicators Maintain operations until directed return to Communications Center Notify emergency responders of relocation Report to assigned duty station as directed by supervisor 3.5.3 Off Duty Telecommunicators Commentary: Maintain operations until directed to cease as directed by supervisor Return to Normal Operations procedures and duties must be adapted to the individual circumstances of the implementing agency. PSAPs should establish procures which provide for a quick transfer of operations from one location to another. Intermediate relocation steps such as a mobile communications vehicle with phone and radio communications to maintain operations until the primary site is staffed and ready will enhance the system and maintain service. 4. References Not applicable Page 12 of 15

5. Exhibits A. Evacuation checklist (sample) B. Return to normal operations checklist (sample) Commentary: NENA Communications Center/PSAP Disaster and Checklists provide guidelines for tasks that must be completed. Each Communications Center/PSAP should develop checklist unique to their circumstances for evacuation and return to normal operations. Page 13 of 15

Exhibit A. Evacuation Checklist (sample) On Duty Supervisor Off Duty Staff notified (Page group) Priority Radio and MDT message Phone Company Special Circuits (XXX) XXX-XXXX notify only Radio Contractor (XXX) XXX-XXXX (Page Group) ARES/RACES (Page Group) Other County PSAPs Local Emergency Management (such as municipal, county and/or parish) State Emergency Management Law Enforcement Terminal (Alt. Route to XXXXXXX) Remote Site Operational Contingency route 9-1-1 and emergency lines Relocate unassigned personnel Account for personnel Director Commissioners/Staff Notified Supervisors Checklist reviewed Technician response Administrative staff response PIO response Remote sites notified/staffed/operational Radios/pagers tested CLEAN terminal forwarded Contingency call routing directed Staff Accounted for and assigned Technical Manager Technical staff responding Radio Techs responding Phone Techs responding Radios operational Phones Operational Pagers operational Contingency routing directed (Director) Page 14 of 15

Exhibit B. Return to Normal Operations Checklist (sample) NENA Communications Center/PSAP Disaster and On Duty Supervisor Assign staff to return to Communications Center Priority Radio canceled and MDT message Phone Company Special Circuits (XXX) XXX-XXXX notify only Radio Contractor (XXX) XXX-XXXX ARES/RACES Other County PSAPs Local Emergency Management (such as municipal, county and/or parish) State Emergency Management Law Enforcement Terminal (Reverse Alt. Route to XXXXXXX) Cancel contingency routing of 9-1-1 and emergency lines Release unassigned personnel Account for on duty personnel Director Ensure safety of Communications Center Technical Manager ensures system operational Commissioners/Staff Notified Supervisors Checklist reviewed Communications Center notified/staffed/operational Radios/pagers tested Reverse Law Enforcement Terminal Alternate Routing Cancel contingency call routing directed Staff Accounted for and assigned or released Remote site re-supplied and operational After-action report completed Technical Manager All systems operational Notify Director that Communications Center Operational Release technicians Page 15 of 15