How To Plan For Post Disaster Recovery
|
|
|
- Abraham Gregory
- 5 years ago
- Views:
Transcription
1 Pre-Disaster Planning for Post-Disaster Recovery NAS Disaster Roundtable October 17, 2007 Laurie A. Johnson, AICP Dr. Robert Olshansky, AICP
2 Agenda California s Experience APA PAS Report and Model Recovery Ordinance Florida s Initiative Observations Acknowledgments Ken Topping, California State Polytechnic University, San Luis Obispo Sandy Meyer, Project Manager, Florida Division of Community Planning
3 California s Pre-Disaster Recovery Planning Experience 1976, LA Mayor appointed task force to explore how city might respond to a credible earthquake prediction Early 1980s, LA established Emergency Operations Organization (EOO) pursuant to task force recommendation 1980s, NSF-funded Pre-Earthquake Planning for Post- Earthquake Rebuilding (PEPPER) Multidisciplinary team predicted earthquake intensities, structural damage and damage costs for 4 LA scenario earthquakes Recommended a planning process that included: Periodic evaluations of seismic risk and possible response Development of policies and procedures for post-earthquake land use planning and rebuilding Model ordinance to establish a rebuilding and recovery organization
4 California s Pre-Disaster Recovery Planning Experience LA Recovery and Reconstruction ordinance (adopted Sept. 1989) Formalizes a Recovery and Reconstruction division in the city s Emergency Operations Ordinance with planning chief as head LA Recovery and Reconstruction Plan draft 1988; revised post-1989 earthquake; revised draft, fall 1993 Post-Northridge, planning-led management structure not followed; recovery led by combination of Mayor and Council committees Prescriptive task nature was helpful in organizing various departments responsibilities Other Products: California OES recovery and reconstruction planning guidelines (1991 and 1993) Series of earthquake scenarios for major California faults FEMA post-disaster rebuilding exercises (earthquakes and floods)
5 APA/FEMA Planning for Post-Disaster Recovery and Reconstruction, 1998 (PAS 483/484) Geared towards practicing planners, emphasizing links between comprehensive planning, mitigation, and emergency operations planning Series of case studies: tornado, flood, hurricane, wildfire and earthquake Model ordinance, to be adopted pre-event: Establish a recovery organization to prepare recovery plan and define post-disaster authorities Calls for adoption of the plan and ordinance by governing body Defines a variety regulatory powers and procedures, such as: Damage assessment Development moratoria Expedited permit processing Handling non-conforming uses Demolition of damaged historic buildings
6 State of Florida Post Disaster Redevelopment Plan Initiative Florida Department of Community Affairs is beginning a 3-year post-disaster redevelopment planning initiative Funding from NOAA, through Florida Coastal Management Program Product: a guidebook that can be used by each local government to prepare a Post-Disaster Redevelopment Plan (PDRP) All of Florida's 203 coastal counties and municipalities are required to adopt these plans. Inland communities are encouraged to prepare them Program will be overseen by a focus group representing federal, state, regional, and local organizations, and the academic community
7 State of Florida Post Disaster Redevelopment Plan Initiative (cont.) Communities already have plans for mitigation and response. PDRPs are to identify policies, strategies, and responsibilities to ensure that long-term recovery implements the community's previously-identified growth management and hazard mitigation goals. The statute recommends the plans include long-term policies for: Redevelopment Infrastructure Densities Nonconforming uses Future land use patterns
8 Phase Phase Phase Literature review, survey of existing post-disaster plans in Florida, development of draft guidelines. 2. Test the draft guidelines in a pilot community. 3. Analyze pilot test, prepare Post-Disaster Redevelopment Plan guidebook (latest addition to the best practices series published by the Florida Department of Community Affairs). Recommend legislative changes to clarify the minimum requirements of a Post-Disaster Redevelopment Plan.
9 Florida s Initiative: Intended Results Model Post-Disaster Redevelopment Plan Addressing all elements of Redevelopment Consensus of Local Govt, Planners, EM Responders, Business Organizations & other Stakeholders Regional Integration, if possible Planning Template Capture the process (roadmap to the plan) Creating planning partnerships of stakeholders Marketing the plan
10 Observations Both mitigation and recovery must be priorities both before and after disasters. Mitigation emphasizes substance. It is difficult to sell before a disaster, and much easier to understand after one. Recovery emphasizes process. It is much easier to conceptualize before a disaster than in the chaos following one. Both are far easier to develop before a disaster than in the post-disaster pressure cooker.
11 Observations Guidance for both mitigation and recovery planning needs clarification and enhanced coordination Mitigation guidance with DMA 2000 (before) and Stafford Act (after); both do not adequately address catastrophic events Recovery planning mainly emphasized after, as part of NRP ESF 14; now being rolled into new national response framework Recently funded APA-FEMA Planners Advisory Service project "Integrating Hazard Mitigation into Local Planning"
12 Observations Increased emphasis on catastrophic/regional (response & recovery) planning Hurricane Pam exercise revealed many issues preevent and raised awareness FEMA Catastrophic Scenario initiatives in several regions across the U.S. Other scenario-based initiatives underway (e.g. New Madrid, Southern California) Other regional preparedness also underway within various sectors (e.g. Bay Area NGOs)
Association of State Flood Managers Annual Conference Wednesday, June 4, 2014
Association of State Flood Managers Annual Conference Wednesday, June 4, 2014 Hillsborough County, In the Trenches Local Mitigation Eugene Henry, CFM, AICP Hazard Mitigation Manager Floodplain Administrator
Summer Disaster Institute. PLAN 740 Disaster Recovery: Concepts, Policies and Approaches. Overview
Summer Disaster Institute PLAN 740 Disaster Recovery: Concepts, Policies and Approaches Karl Kim, Andrew Rumbach, Dolores Foley Ken Tingman, Gavin Smith, Carolyn Harshman University of Hawaii Wednesday,
New Hampshire Recovery Plan
ANNEXES LEAD AGENCY: RECOVERY SUPPORT FUNCTION (RSF) 1 COMMUNITY PLANNING AND CAPACITY BUILDING N.H. Homeland Security and Emergency Management (HSEM) SUPPORT AGENCIES: N.H. Attorney General s Office (AG)
American Planning Association
American Planning Association Planning for Post-Disaster Recovery Session 1 Moderator: Tim Gelston, FEMA Region 8 Speakers: Kenneth C. Topping, FAICP, Topping Associates International J. Barry Hokanson,
The Florida Post Disaster Redevelopment Planning Initiative An Implementation Guide for Local Governments. Video Transcript
The Florida Post Disaster Redevelopment Planning Initiative An Implementation Guide for Local Governments Video Transcript Slide 1 This presentation was developed to assist local communities in the long
Pre Disaster Planning for Post Disaster Recovery: Case Studies
Pre Disaster Planning for Post Disaster Recovery: Case Studies Final Report: Prepared for: Federal Emergency Management Agency Prepared by: Community Planning Workshop Community Service Center 1209 University
CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION
CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION 37.01 Authority 37.07 Temporary Regulations 37.02 Purposes 37.08 Demolition of Damaged Buildings 37.03 Definitions 37.09 Temporary and Permanent Housing
CASE STUDY. Jefferson County EMA Alabama Recovery Plan
Jefferson County EMA Alabama Recovery Plan NOTE: Jefferson County EMA contracted with ERI International / All Hands Consulting to fully develop the county's recovery plan and program. The original concept
Resources FEMA CURRICULUM. FEMA Mitigation Curriculum MITIGATION TRAINING. Resident Courses
MITIGATION TRAINING is provided mainly through the courses and programs of the Emergency Management Institute (EMI) located in Emmitsburg, Maryland. The EMI serves as the focal point for the development
How To Help A City Recover From A Disaster
MODEL PRE-EVENT RECOVERY ORDINANCE One action a community can take to move toward better management of disaster mitigation, preparedness, response, and recovery is the adoption of an ordinance before or
Beaufort County 2011-2012 Disaster Recovery Plan
Beaufort County 2011-2012 Disaster Recovery Plan Beaufort County, South Carolina Beaufort County Council Beaufort County Recovery Task Force Weston Newton, Chairman, Beaufort County Council Gary Kubic,
Council of State Community Development Agencies 1825 K Street NW Suite 515 Washington, DC 20006. Tel: (202) 293-5820 Fax: (202) 293-2820
Council of State Community Development Agencies 1825 K Street NW Suite 515 Washington, DC 20006 Tel: (202) 293-5820 Fax: (202) 293-2820 http://www.coscda.org TABLE OF CONTENTS MODULE 1: OVERVIEW... 1 TARGET
CHAPTER 7. EMERGENCY SERVICES
CHAPTER 7. EMERGENCY SERVICES Although better forecasts and warning processes have helped save lives by providing more lead time to evacuate, the tremendous growth of development and human population in
PLANNING FOR POST-DISASTER RECOVERY BRIEFING PAPERS
12 PLANNING FOR POST-DISASTER RECOVERY BRIEFING PAPERS VISIONING Visioning is a community activity intended to produce a common vision, accompanied by goals, for the future. Ideally, it is broadly based
Emergency Management in Turkey Adil Özdemir
Adil Özdemir Turkey has been exposed to natural disasters throughout history. The main sources of these natural disasters have been earthquakes, floods, erosion and avalanches. Disaster response policies
p a s r e p o r t 5 7 6 PLANNING FOR POST-DISASTER RECOVERY: NEXT GENERATION James C. Schwab, aicp, Editor
p a s r e p o r t 5 7 6 PLANNING FOR POST-DISASTER RECOVERY: NEXT GENERATION James C. Schwab, aicp, Editor POWER TOOLS ABOUT THE AUTHORS APA RESEARCH MISSION APA conducts applied, policy-relevant research
Broward County Emergency Management BROWARD COUNTYWIDE RECOVERY PROCESS (CRP)
Broward County Emergency Management BROWARD COUNTYWIDE RECOVERY PROCESS (CRP) August 5, 2011 Table of Contents Chapter 1 Introduction... 5 Overview... 5 Broward Countywide Recovery Process Phases... 6
Disaster Recovery 101 the basics.
Disaster Recovery 101 the basics. Scott MacLeod, MA Emergency Management Agency Hazard Mitigation & Disaster Recovery Division Manager December 19, 2012 1 Today s discussion Define disaster recovery Provide
Lesson 5. After a Disaster: Recovery and Hazard Mitigation Programs. Disaster Assistance
Introduction The previous four lessons focused on pre-disaster mitigation: developing a program, and writing and implementing a hazard mitigation plan. The Disaster Mitigation Act of 2000 (DMA 2000) encourages
Planning for Post-Disaster Recovery in New Orleans after Hurricane Katrina
Planning for Post-Disaster Recovery in New Orleans after Hurricane Katrina Tamiyo KONDO Disaster Reduction and Human Renovation Institution Abstract This paper examines the recovery planning process and
SELECT RESOURCES FOR DISASTER RECOVERY & CRISIS MANAGEMENT
SELECT RESOURCES FOR DISASTER RECOVERY & CRISIS MANAGEMENT Alesch, D. J., Arendt, L. A., & Holly, J. N. (2009). Managing for Long-Term Community Recovery in the Aftermath of Disaster. Fairfax, VA: Public
Triangle Alliance Conference DISASTERS & HISTORIC PRESERVATION. October 23, 2009
Triangle Alliance Conference DISASTERS & HISTORIC PRESERVATION October 23, 2009 Topic Outline FEMA s Mission Programs: Individual Assistance, Public Assistance, Mitigation, National Preparedness Environmental
Hurricane Sandy: The Challenges and Opportunities to Link Disaster Management and Climate Change Adaptation*
Hurricane Sandy: The Challenges and Opportunities to Link Disaster Management and Climate Change Adaptation* Gavin Smith, Ph.D. Associate Research Professor Department of City and Regional Planning University
APPENDIX XVIII: EMERGENCY SUPPORT FUNCTION 18 BUSINESS, INDUSTRY, AND ECONOMIC STABILIZATION
APPENDIX XVIII: EMERGENCY SUPPORT FUNCTION 18 BUSINESS, INDUSTRY, AND ECONOMIC STABILIZATION PRIMARY AGENCY: SUPPORTING AGENCY: Florida Department of Economic Opportunity Florida Division of Emergency
Basic system of measures for flood damage mitigation in Japan. Preparedness for major floods
Basic system of measures for flood damage mitigation in Japan Preparedness for major floods Past major floods and state-level efforts Role of the 2 MLIT's disaster prevention efforts Disaster prevention
Emergency Support Function #14 Long Term Community Recovery and Mitigation
Emergency Support Function #14 Long Term Community Recovery and Mitigation Primary Agency FEMA Board of Visitors Radford University Cabinet Secondary/Support Agencies Radford University Office of Emergency
CONTINUITY OF OPERATIONS PLANNING
University of North Carolina Wilmington CONTINUITY OF OPERATIONS PLANNING November 9, 2010 Lumina Theater, Fisher Student Center Development of Continuity Planning University of North Carolina Wilmington
Chatham County Disaster Recovery Plan Recovery Planning Update. Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015
Chatham County Disaster Recovery Plan Recovery Planning Update Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015 Welcome Introduction to Recovery Planning Recovery Planning Process
Flood Hazard Mitigation
District of Columbia Homeland Security and Emergency Management Agency Flood Hazard Mitigation DC Homeland Security and Emergency Management Agency 2720 Martin Luther King Jr., Avenue, SE Washington, DC
Oregon Pre-Disaster Mitigation Program Plan Update Training Manual
FEMA Oregon Pre-Disaster Mitigation Program Plan Update Training Manual Prepared by: Oregon Partnership for Disaster Resilience OPDR FEMA OPDR FEMA OPDR 2010, University of Oregon s Community Service Center
Disaster Recovery Financial Assistance
Disaster Recovery Financial Assistance Recovering from a disaster is a partnership effort among local, state and federal government agencies in conjunction with private and non-profit organizations. Rebuilding
Chapter IX: Strategic Planning for Disaster Recovery
Chapter IX: Strategic Planning for Disaster Recovery 82 Disaster recovery planning and preparedness is no longer strictly for communities that regularly experience flooding, forest fires or hurricanes.
September 2012 U.S. Department of Homeland Security Coastal Hazards Center of Excellence The University of North Carolina at Chapel Hill
State Disaster Recovery Planning Guide September 2012 U.S. Department of Homeland Security Coastal Hazards Center of Excellence The University of North Carolina at Chapel Hill State Disaster Recovery Planning
Floodplain 8-Step Process in accordance with Executive Order 11988: Floodplain Management. New Jersey Department of Environmental Protection
Floodplain 8-Step Process in accordance with Executive Order 11988: Floodplain Management New Jersey Department of Environmental Protection U.S. Department of Housing and Urban Development Community Development
Emergency Management Certification and Training (EMC & T) Refresher Terry Hastings, DHSES Senior Policy Advisor
Emergency Management Certification and Training (EMC & T) Refresher Terry Hastings, DHSES Senior Policy Advisor 2015 NYSEMA Conference 2 Please sign in to ensure that you receive credit for the refresher
BASIC PLAN: Appendix 7 Disaster Recovery
Recovery activities involve the restoration of services to the public and returning the affected area(s) to pre-emergency conditions. A disaster may strike quickly, leaving the need for recovery operations
Interim Housing Tabletop Exercise August 6, 2013
Interim Housing Tabletop Exercise August 6, 2013 1 Opening, Introductions, & Overview 2 Welcome and Opening Remarks Sign In RCPGP Regional Match and Time Collection Forms Lunch Tabletop Exercise Materials
CITY OF KENT, WASHINGTON COMPREHENSIVE EMERGENCY MANAGEMENT PLAN APPENDIX 3 REFERENCES
CITY OF KENT, WASHINGTON COMPREHENSIVE EMERGENCY MANAGEMENT PLAN APPENDIX 3 REFERENCES The City of Kent Comprehensive Emergency Management Plan was developed and is maintained pursuant to, but not limited
TOWN OF STRATFORD PURCHASING DEPARTMENT STRATFORD, CONNECTICUT. Subject: Disaster Recovery Grant Management and Administration Services
TOWN OF STRATFORD PURCHASING DEPARTMENT STRATFORD, CONNECTICUT RFP No. 2012-092 Issued: November 7, 2012 Subject: Disaster Recovery Grant Management and Administration Services The Town of Stratford through
Proposed Ordinance 39 Disaster Recovery Ordinance
Proposed Ordinance 39 Disaster Recovery Ordinance Chapter. Disaster Recovery and Reconstruction Section 1. Section 2. Section 3. Section 4. Authority Purposes Definitions 1.1 Damage Assessment Survey 1.2
GAO DISASTER RECOVERY. Experiences from Past Disasters Offer Insights for Effective Collaboration after Catastrophic Events
GAO July 2009 United States Government Accountability Office Report to the Committee on Homeland Security and Governmental Affairs, U.S. Senate DISASTER RECOVERY Experiences from Past Disasters Offer Insights
PLANNING FOR POST-DISASTER RECOVERY BRIEFING PAPERS
04 PLANNING FOR POST-DISASTER RECOVERY BRIEFING PAPERS AFFORDABLE HOUSING Housing serves as more than just shelter. Research has shown that affordable and stable housing can be a platform for families
EMERGENCY SUPPORT FUNCTION (ESF) 14 LONG TERM RECOVERY AND MITIGATION
EMERGENCY SUPPORT FUNCTION (ESF) 14 LONG TERM RECOVERY AND MITIGATION Primary Agency: Chatham Emergency Management Agency Support Agencies: American Red Cross Chatham County Building Safety & Regulatory
Session 7. Holistic Disaster Recovery: Creating a More Sustainable Future
Session 7 Holistic Disaster Recovery: Creating a More Sustainable Future Shared Governance Time: 3 hours (Slide 7-1) Objectives: 7.1 Discuss exam 7.2 Discuss shared governance using the horizontal and
MEMORANDUM OF UNDERSTANDING BETWEEN THE DEPARTMENT OF HOMELAND SECURITY FEDERAL EMERGENCY MANAGEMENT AGENCY AND
MEMORANDUM OF UNDERSTANDING BETWEEN THE DEPARTMENT OF HOMELAND SECURITY FEDERAL EMERGENCY MANAGEMENT AGENCY AND THE NORTH AMERICAN MISSION BOARD SOUTHERN BAPTIST CONVENTION DISASTER RELIEF 1. PARTIES The
How To Plan For A Disaster Recovery
Chapter 2 THE DISASTER RECOVERY PROCESS Disaster recovery is viewed by some people as a fight against Mother Nature to restore order in a community. However, the disaster recovery process is not a set
TEMPLATES Disaster Recovery Framework & Recovery Support Function Guide April 2015
TEMPLATES Disaster Recovery Framework & Recovery Support Function Guide April 2015 Bay Area Urban Areas Security Initiative This page intentionally left blank TEMPLATES Disaster Recovery Framework & Recovery
Please see Section IX. for Additional Information:
The Florida Senate BILL ANALYSIS AND FISCAL IMPACT STATEMENT (This document is based on the provisions contained in the legislation as of the latest date listed below.) BILL: CS/SB 1094 Prepared By: The
MONTGOMERY COUNTY, KANSAS EMERGENCY OPERATIONS PLAN. ESF14-Long Term Community Recovery
MONTGOMERY COUNTY, KANSAS EMERGENCY OPERATIONS PLAN ESF14-Long Term Community Recovery Planning Team Support Agency Coffeyville Public Works Independence Public Works Montgomery County Public Works 1/15/2009
ESF 14. Long-Term Community Recovery
1. Purpose This annex provides an overview of the general process to be followed in recovering from the economic results of a natural disaster or other major emergency that may impact Coos County. It outlines
Disaster Preparedness and Safety Element
Disaster Preparedness and Safety Element Element Objectives The policies and actions of the Disaster Preparation and Safety Element are intended to achieve the following six objectives: 1. Establish and
Building Code Effectiveness Grading: In Brief. What? Why? When? And What Do I Do?
Building Code Effectiveness Grading: In Brief The Building Code Effectiveness Grading Schedule (BCEGS) assesses the building codes in effect in a particular community and how the community enforces its
Testimony of Mr. Robert J. Fenton, Jr. Assistant Administrator for Response, Office of Response and Recovery Federal Emergency Management Agency U.S. Department of Homeland Security Before House Committee
1. GENERAL ADVISORY BASE FLOOD ELEVATION (ABFE) QUESTIONS
INTRODUCTION As communities begin to recover from the devastating effects of Hurricane Sandy, it is important to recognize lessons learned and to employ mitigation actions that ensure structures are rebuilt
Federal Emergency Management Agency (FEMA) Preliminary Flood Insurance Rate Maps (FIRMs) and Preliminary Flood Insurance Study (FIS) for New York City
March 10, 2014 Submitted electronically via http://www.nyc.gov Mayor s Office of Long Term Planning and Sustainability c/o Flood Map Comments 253 Broadway, 10th Floor New York, NY 10007 Federal Emergency
Planning for Public Health & Health Care Recovery
Planning for Public Health & Health Care Recovery Governor s Hurricane Conference May 13, 2015 Innovation t Collaboration t Accountability t Responsiveness t Excellence AGENDA The Federal Perspective Byron
Texas Department of Public Safety Texas Division of Emergency Management. Local Emergency Management Planning Guide. TDEM-10 Revision 4
Texas Department of Public Safety Texas Division of Emergency Management Local Emergency Management Planning Guide TDEM-10 Revision 4 January 2008 FOR ADDITIONAL INFORMATION Requests for additional copies
Flooding Emergency Response Exercise
Flooding Emergency Response Exercise James Woodward, Senior Exercise Planner California Emergency Management Agency 3650 Schriever Ave. Mather, CA 95655 Cell: (916) 439-3546 Email: [email protected]
CSA Z1600 Emergency Management and Business Continuity Programs
CSA Z1600 Emergency Management and Business Continuity Programs Presented by: John Lindsay, Brandon University Department of Applied Disaster and Emergency Studies and Z1600 Technical Committee member
EMERGENCY MANAGEMENT PROGRAM GUIDE FOR COLORADO
EMERGENCY MANAGEMENT PROGRAM GUIDE FOR COLORADO January 2013 Colorado Office of Emergency Management Department of Public Safety Division of Homeland Security and Emergency Management Office of Emergency
Disaster Risk Reduction (DRR)
Disaster Risk Reduction (DRR) A. Introduction 1. In order to address the impacts of the May 12 Wenchuan Earthquake, the Government of China will implement an effective, comprehensive and sustainable recovery
DIVISION OF EMERGENCY MANAGEMENT
DIVISION OF EMERGENCY MANAGEMENT PROGRAM DESCRIPTION The Florida Division of Emergency Management (DEM) is responsible for maintaining a comprehensive statewide program of emergency management. In addition,
L101 Foundations of Emergency Management Wirtz, VA Oct 5-30
Emergency Management Institute Fiscal Year 2016 Schedule of Courses by Curriculum 1st and 2nd Semesters E - EMI Campus L - RESIDENT OFF-SITE V - VIDEO TELECONFERENCE COURSES K - Virtual (Adobe Connect)
Initiating the CCSF Lifelines Council. Interdependency Study
LAURIE JOHNSON CONSULTING Initiating the CCSF Lifelines Council Urban Planning Risk Management Disaster Recovery Interdependency Study Lifelines Council Meeting #7 November 17, 2011 (Source: JIIRC-UBC)
City of Disaster Recovery Plan
City of Disaster Recovery Plan 1. General Purpose Scope Coordination Relationship to other Plans Concept of Operations Plan Update 2. Recovery and Restoration Policy Residential, Commercial and Industrial
Integrating Hazard Mitigation Into Local Planning
Integrating Hazard Mitigation Into Local Planning Case Studies and Tools for Community Officials March 1, 2013 Table of Contents 1 Introduction... 1-1 Defining Integration... 1-1 Planning for Resilience...
ACADEMIC APPOINTMENTS 2008 to Assistant Professor, Department of Landscape Architecture and Urban Planning, present Texas A&M University
1 Current as of February, 2013 YU XIAO Assistant Professor, Department of Landscape Architecture and Urban Planning Faculty Fellow, Hazard Reduction and Recovery Center (HRRC) Texas A&M University, 3137