ITD Project Management and System Development Procedure ITD PROJECT MANAGEMENT AND SYSTEM DEVELOPMENT PROCEDURE

Size: px
Start display at page:

Download "ITD Project Management and System Development Procedure ITD PROJECT MANAGEMENT AND SYSTEM DEVELOPMENT PROCEDURE"

Transcription

1 PURPOSE ITD PROJECT MANAGEMENT AND SYSTEM DEVELOPMENT PROCEDURE ITD s core business is to implement IT solutions. The purpose of this procedure is to facilitate the identification, management and monitoring of IT projects through their life cycles. Most projects do not require an explicit design phase as it is University policy to implement existing commercial solutions rather than developing bespoke in-house solutions. PROCEDURE RMS is used as a central repository for all projects. The process for implementing IT solutions consists of six stages: 1. Project Proposal (Code 6 + Checklist & auto ) 2. Project Proposal Circulation (Code 16 & auto to Mgt Team) 3. Project Approval (Code 46 auto ) 4. Project Analysis and Planning (Code 47 & RMS Notes) 5. Project Implementation (Code 48 & RMS Notes + auto requesting project plans to be forwarded to Section Head / Manager) 6. Verification and Validation (Code 86 - Auto ) 7. Project Completion (Code 99) Additional Code: Project On Hold (Code 49) (see Exception Conditions) Progression of an ITD project is the responsibility of the assigned project leader. New project proposals are reviewed weekly at the management meeting. Project plans are reviewed at section meetings. A review of all projects takes place fortnightly between the Director and section Head. Project reports are stored on SharePoint: &FolderCTID=0x C541FC65BE642BA1D0AE59D05C63A&View={7D92FEC8-5B41-4C F8B776DE22F} Inputs: Requests are generated by: 1. The University to implement strategic objectives/new initiatives. 2. ITD staff, following consultation with customers to: a. Deploy IT infrastructure/services b. Develop and Deploy new services c. Enhance current processes d. Trend analysis, Preventative or Corrective Action e. Follow-on from Change Control Requests. Page 1 of 6 Rev: 22

2 Project Proposal Stage All project requests are logged in RMS. The Call Type is PRO, and the Application is PRO. This generates a checklist of proposal questions, which is saved with the call. The status code changes to 6. This generates an auto- to the Section Head / Manager. Upon receipt of the , the Section Head / Manager will change the status to 16, which will generate an to the Management Team outlining details of the project proposal. The management team evaluates project proposals weekly at the ITD management meeting. Based on the business need and availability of resources, projects are either accepted or rejected. Projects are classified as: Size Duration SLA 1. Small 3 months SML 2. Medium 6 months MED 3. Large 1 year LGE The size of the project is recorded using the SLA field in RMS. Project Approval Stage (Stop / Go #1) If accepted, a project leader is assigned to the project. The Section Head / Manager updates the status after the operational meeting. The project leader then becomes the call owner in RMS. The status code changes to 46. This generates an to the requestor, and a copy is sent to the project leader, stating that the project proposal has been approved and can now move to the planning phase. If the proposal is rejected, the person who proposed the project is informed and the reason for rejection is given. A record of this communication is kept in the Notes field of the call. The status code changes to 90. In the event that a project is being handed over to another Division, relevant notes will be recorded and the project will be closed at code 90. Project Analysis and Planning Stage Once work begins on the planning stage, the status code is changed to 47. It is recommended that any additional documentation relating to projects be stored as document links to the project call in RMS. It is the responsibility of the project leader to determine the project requirements. These requirements should be arrived at after reviewing any available customer inputs. The customer requirements and inputs may have to be interpreted from trend data, customer surveys, customer meetings or interviews on specific projects as required. The project leader determines how to achieve this at the start of the project. The projects requirements should include as a minimum: Page 2 of 6 Rev: 22

3 1. Functional and performance requirements 2. Applicable statutory and regulatory requirements 3. Applicable information derived from previous similar designs 4. Any other requirements essential for design and development The project leader produces a project plan, which must indicate: 1. Resources required a. In particular human resource required the project team 2. Project Milestones consisting of: a. When milestone activity is scheduled to begin b. How long it should take to complete c. When a review is planned Project plans and milestones are discussed at section team meetings. (Stop / Go #2) Small projects proceed to implementation once the project leader has prepared the project plan and populated the Notes field in RMS appropriately. Medium and Large projects are reviewed fortnightly with the Director and Section Head. Project reports are stored on SharePoint. Project Implementation Stage At this stage of the procedure, the status code in RMS changes to 48. Support structures (for example, Project Board, Steering Committee) are put in place as appropriate and recorded in the notes field of the project call in RMS. (Stop / Go #3) Project milestones are recorded in the notes field in RMS. Although achieving a milestone may be the responsibility of other team members, the overall responsibility for the project management and progression of milestones rests with the project leader. The project leader monitors the project plan and provides status reports at individual section meetings. Project delays, cancellations or accelerations are recorded in the RMS notes field. Verification and Validation Stage Once work has been complete on the project, and before the final closure, the project leader sets the status code to 86. This code generates an automatic to the Section Head / Manager. The Section Head / Manager verifies that the results of the project meet the requirements and validates the final product/service meets the customer needs. Closure Stage The Section Head / Manager closes the call at 99, when: Page 3 of 6 Rev: 22

4 1. The project outputs have been verified. 2. The customers have formally accepted all outcomes (validated). 3. Documentation and reference material is in place. 4. Operational procedures are in place. 5. The training and handover to operational staff has been completed. 6. The stakeholders are notified of the project outcome. 7. Any further actions and recommendations are documented and disseminated. 8. The project has been reviewed. a. Small projects are reviewed with the head of section of the project leader. b. Medium projects are reviewed by ITD Management team c. Large projects may be externally audited All project documentation is held in RMS. A periodic overview of all projects is conducted by the Management Team. EXCEPTION CONDITIONS Non-ITD Projects UL-managed projects that require ITD resources will be logged in RMS at Code 6 project proposal. Once the project has been approved at the weekly operational meeting, it does not go through the complete ITD project life-cycle, but progress / updates are recorded in the Notes field in RMS. On-Hold Projects Projects are put on-hold by changing priorities and/or resourcing. The Section Head / Manager changes the status code to 49 (Project On-Hold) and updates the notes field with the reason for stoppage. Code 49 will stop the clock against the SLA in RMS. When work resumes on the project, the status code is changed back to the pre on-hold status. RECORDS Records are maintained in RMS for a minimum of 3 years. Project reports are stored on SharePoint. All other project records are stored in a projects network folder and are maintained for a minimum of 3 Years. It is the responsibility of the project leader to manage changes to the projects network folder. This may be facilitated by imposing access restrictions to the projects network folder or specific files within the projects network folder. Page 4 of 6 Rev: 22

5 PROCESS VERIFICATION Evaluation of process effectiveness is carried out using Internal / External Quality Audits and the Corrective Action process where the procedure itself is found to be the source of the problem under investigation. Particular attention is paid to any feedback on the results of the project from the user community via RMS or direct contact through management. Project review meetings are conducted monthly. Review records, along with relevant minutes, are stored on SharePoint. Revision No. Date Approved by: Details of Change 1 Feb 05 Mgt Team Initial Release 2 18 Apr 05 Martin Leonard Updated procedure as a result of internal audit 3 25 Apr 05 Martin Leonard Added info re templates, corrected database references Apr 05 Martin Leonard More detailed record keeping. Removed references to development Better clarification on closure May 05 Martin Leonard Clarified ISO requirements, added references to the Database June 05 Martin Leonard Simplified procedure for small projects. Added detail for rejected/cancelled projects Clarified the data to be recorded in the database June 05 Martin Leonard Improved wording for clarity following suggestions from ITD staff June 05 Kim O Mahony Updated title and headings for consistency 9 12 Sept 06 Kim O Mahony Procedure revised to use RMS for project management instead of Martin s customised database May 07 Kim O Mahony Page 2 (Project Analysis and Planning Stage) updated to include the ITD Management link on the portal for additional project documentation May 07 Kim O Mahony / George Hayes Updated procedure to change tense of the grammar. Also identified the three Stop / Go phases of the project life cycle Jul 08 Kim O Mahony Updated to include reference to project overview by Mgt team. Also some typographical changes following recent audit Oct 08 Kim O Mahony / George Hayes Updated Procedure section on page 1 to outline macro-level project reviews and details of the monthly project meeting. Included the section Exception Conditions to refer to UL-managed projects and also On-Hold projects. These Page 5 of 6 Rev: 22

6 14 6 July 09 Management Team were recommendations made during the NSAI audit in Sept. Updated procedure following recommendations from internal audit on 28 may. 1) Made reference to projects being handed over to other Divisions; 2) Included auto at code 48 for copy of project plan to be sent to Section Head / Mgt for approval at next project board meeting (pg 3) May 10 Kim O Mahony Projects now reviewed at the monthly quality meeting instead of the management operational weekly meeting. Noted this on Page Nov 10 Kim O Mahony Clarified under Project Approval Stage that the project proposal has been approved to move to the planning stage (p2) Jan 11 Kim O Mahony Implemented new phase in the procedure (Code 16 Project Proposal Circulation) which allows the Mgt Team to view project proposals prior to discussion at the weekly meeting. (See minutes of weekly meeting 24 Jan 11) 18 5 Apr 11 Kim O Mahony Updated procedure to outline current practice for approving project proposals and project plans May 11 Kim O Mahony Removed reference to project folders on Clio and SharePoint. All project documentation to be stored as linked files to the project call. Also included SharePoint link to project reports Jan 12 Kim O Mahony Updated procedure to outline current practice for project reviews Oct 12 Kim O Mahony Replaced Quality Officer with Section Head / Manager Jul 13 George Hayes Two procedural changes: 1. All project documentation is stored in RMS 2. Project review meetings are conducted monthly Page 6 of 6 Rev: 22

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

A checklist for project managers

A checklist for project managers A checklist for project managers The checklist presented below aims to help you decide what project documents are needed, approximately when you need to create them, and what other resources are available.

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012)

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) Project Name : data.bris DBSG/5/2 JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) WORKPACKAGES Month: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Oct 11 Nov Dec

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

CDC UNIFIED PROCESS PRACTICES GUIDE

CDC UNIFIED PROCESS PRACTICES GUIDE Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Quality Management System Process/ Management Review

Quality Management System Process/ Management Review Directorate in charge: Process concerned: Process owner: Executive Directorate Quality Management System Process/ Management Review Quality Section Manager Véronique Magnier Purpose and Scope of the :

More information

DCO No. Released By: Effective Date Document No. Rev.

DCO No. Released By: Effective Date Document No. Rev. 1.0 Purpose The Engineering Change Order is a tool utilized by the Safety that records and tracks the design and review process for engineering jobs. 2.0 Scope All new designs and modifications to existing

More information

Change Management Procedures Re: The Peoplesoft Application at Mona

Change Management Procedures Re: The Peoplesoft Application at Mona Change Management Procedures Re: The Peoplesoft Application at Mona (The original Peoplesoft document was modified to relate more closely to UWI Mona) See also.. MITS Project Management Methodology & MITS

More information

OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL. PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6.

OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL. PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6. OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6.6 STATUS FINAL Approvals The undersigned have approved the release of Version 6.6

More information

Project Management for Everyone

Project Management for Everyone Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group System, Analytics & Insights Group Phone: (202) 994-6867 Email: adonald@gwu.edu Objectives Basic

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY

CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY CHILDREN AND YOUNG PEOPLE'S PARTNERSHIP BOARD CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY 1 Introduction 1.1 The purposes of this strategy are to set out: i) the arrangements

More information

Independent Test and Evaluation

Independent Test and Evaluation Independent Test and Evaluation ProPath Office of Information and Technology Table of Contents Independent Test and Evaluation Process Maps... 1 Process: Independent Test and Evaluation... 3 Independent

More information

EMS Example Example EMS Audit Procedure

EMS Example Example EMS Audit Procedure EMS Example Example EMS Audit Procedure EMS Audit Procedures must be developed and documented with goals which: Ensure that the procedures incorporated into the EMS are being followed; Determine if the

More information

Exit Interview Assessment

Exit Interview Assessment Exit Interview Assessment David Meyer, PhD and Craig Scott, PhD Exit Interviews: Opportunity or Albatross? Meyer Scott Exit Interview Assessment Slide 1 I/UCRC June 2007 Background Exit Interviews do not

More information

Having a Project Support Office

Having a Project Support Office www.ronrosenhead.co.uk Having a Project Support Office The case for a (or programme) support office Produced by Ron Rosenhead Telephone: 020 8446 7766 www.ronrosenhead.co.uk www.agency.co.uk The case for

More information

Change Management Framework

Change Management Framework Change Management Framework Document Approval Name Prepared by: EMSA DD-MM-YYYY Checked by: SSN DCG Quality control by: EMSA Approved by: SSN group 23-05-2013 Date Change Control History Version Date Description

More information

Castellon, 27 28 of January 2011. Copyright Grupo Europeo de Consultoría LocalEurope. Reservados todos los derechos.

Castellon, 27 28 of January 2011. Copyright Grupo Europeo de Consultoría LocalEurope. Reservados todos los derechos. Management of REINPO RETAIL Project Castellon, 27 28 of January 2011. Objective: managing the control of all the steps needed for the projectimplementation: schedule, budget, results, partnership, etc.

More information

Project Management for Everyone

Project Management for Everyone Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: adonald@gwu.edu Objectives Basic understanding

More information

Performance Management and Service Improvement Framework

Performance Management and Service Improvement Framework Performance Management and Service Improvement Framework Author Marcus Evans, Operational Director - Performance and Customer Insight Date: September 2014 Contents Page 1. Introduction 3 2. Strategic ning

More information

Finance Process Documents Accounts Receivable

Finance Process Documents Accounts Receivable REVISION HISTORY Rev. No. Date Description of Change Process Owner 1.00 Aug-2007 Original Final Version Approved Liam Ryan, AR Staff 2.00 Jan-2015 Revised structure of documents in line with new template

More information

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit Page 1 Walton Centre Monitoring & Audit Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt Page 2 Table of Contents Section Contents 1 Introduction 2 Responsibilities Within This

More information

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise

More information

Advisory User Group Meeting. October 18, 2011

Advisory User Group Meeting. October 18, 2011 Advisory User Group Meeting October 18, 2011 1 Agenda 11:30 Welcome Christine Lavoie 11:35 Session Objectives Christine Lavoie 11:40 USC s Research Administration System Christine Lavoie 11:50 Project

More information

Case Management powered by Microsoft Dynamics CRM

Case Management powered by Microsoft Dynamics CRM - From case capture to resolution powered by Microsoft Dynamics CRM CasePoint is a Solution that combines the best of the Microsoft Dynamics CRM with purpose-built functionality to deliver complete case

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

Service Catalog Management: A CA Service Management Process Map

Service Catalog Management: A CA Service Management Process Map TECHNOLOGY BRIEF: SERVICE CATALOG MANAGEMENT Catalog : A CA Process Map JULY 2009 Enrico Boverino SR PRINCIPAL CONSULTANT, TECHNICAL SALES ITIL SERVICE MANAGER ITAC CERTIFIED Table of Contents Executive

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

Project Q Contact Management Service. UK Link Committee Meeting 10 November 2011

Project Q Contact Management Service. UK Link Committee Meeting 10 November 2011 Project Q Contact Management Service UK Link Committee Meeting 10 November 2011 Agenda 1. Project Q Update 1.1 Project Timeline Indicative Milestones 1.2 Service Name 1.3 Contact Management Service Landing

More information

THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD?

THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD? THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD? Nigel Anderson, Head of Global Service Delivery Group Corporate Facilities Management, EMEA 1. SETTING THE SCENE Customer service expectations in

More information

BlueCielo Meridian Today

BlueCielo Meridian Today BlueCielo Meridian Today Positioning of our current product portfolio BlueCielo Meridian Customer Day June 26, 2014 Gilze Rijen The Netherlands Edwin van Dijk, Business Solution Specialist BlueCielo ECM

More information

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Enterprise Risk Management Process and Procedures Scope In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Risk identification

More information

4/1/2009. Short-termterm

4/1/2009. Short-termterm Hi, my name is Susan ITIL in the Workplace The Practical Application of a Best Practice Framework Susan Ryan April 3, 2009 IT industry worker for over 25 years ITIL v2 Manager Certified itsmf Minnesota

More information

IT Governance. Infocom India Presentation. Pathfinder Technology Solutions. December 6, 2006

IT Governance. Infocom India Presentation. Pathfinder Technology Solutions. December 6, 2006 IT Governance Infocom India Presentation December 6, 2006 Pathfinder Technology Solutions Agenda Why have IT Governance? What is IT Governance? Various elements of IT Governance Frameworks for IT Governance

More information

SapphireIMS Service Desk Feature Specification

SapphireIMS Service Desk Feature Specification SapphireIMS Service Desk Feature Specification All rights reserved. COPYRIGHT NOTICE AND DISCLAIMER No parts of this document may be reproduced in any form without the express written permission of Tecknodreams

More information

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe

More information

Why do Project Fail? 42% 37% 27% 26% 24% 24% 0% 10% 20% 30% 40% 50% IBM Software Group Rational software. Source: AberdeenGroup, August 2006

Why do Project Fail? 42% 37% 27% 26% 24% 24% 0% 10% 20% 30% 40% 50% IBM Software Group Rational software. Source: AberdeenGroup, August 2006 Why do Project Fail? Unclear or continually changing product definitions Product does not meet customer or market requirements 37% 42% Unrealistic schedule expectations Projects not adequately staffed

More information

URBACT III Programme Manual

URBACT III Programme Manual URBACT III Programme Manual Fact Sheet 2E Network Management Table of contents Fact Sheet 2E 0. Introduction... 1 1. Roles and responsibilities of Lead and Project Partners... 2 2. The legal framework...

More information

The Danwood Group Professional Services Offering DANWOOD

The Danwood Group Professional Services Offering DANWOOD The Danwood Group Professional Services Offering DANWOOD Our Professional Services Our Professional Services department can provide you with a variety of services from Audit and Assessment to Technical

More information

Identity and Access Management Memorial s Strategic Roadmap

Identity and Access Management Memorial s Strategic Roadmap Identity and Access Management Memorial s Strategic Roadmap Executive Summary January 29, 2015 Identity and Access Management Identity and Access Management (IAM) is an integrated system of policies, business

More information

SESSION 109 Monday, November 2, 10:15am - 11:15am Track: Strategic View

SESSION 109 Monday, November 2, 10:15am - 11:15am Track: Strategic View SESSION 109 Monday, November 2, 10:15am - 11:15am Track: Strategic View It's All About the Services: Implementing a Service Portfolio Nelli Serifovski Senior Process Manager, NNIT A/S nser@nnit.com Session

More information

ITD BACKUP MANAGEMENT PROCEDURE

ITD BACKUP MANAGEMENT PROCEDURE ITD BACKUP MANAGEMENT PROCEDURE PURPOSE The purpose of this document is to ensure that effective and efficient processes are in place to identify and safeguard data required to run and support applications

More information

Yale University Change Management Process Guide

Yale University Change Management Process Guide Yale University Management Process Guide Yale University Management Process 1 of 29 Table of Contents Introduction... 3 Purpose... 3 Scope... 3 Management Overview... 3 Management Key Concepts... 4 Management

More information

IT Project: System Implementation Project Template Description

IT Project: System Implementation Project Template Description 2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation

More information

Managing Open Source Code Best Practices

Managing Open Source Code Best Practices Managing Open Source Code Best Practices September 24, 2008 Agenda Welcome and Introduction Eran Strod Open Source Best Practices Hal Hearst Questions & Answers Next Steps About Black Duck Software Accelerate

More information

An Introduction to Internal Audits

An Introduction to Internal Audits An BRC Global Standards. Trust in Quality Internal Audits (Section 3.4 excluding 3.4.4) An internal audit is any audit completed by or on behalf of the company, rather than conducted by a second or third

More information

South Dakota Board of Regents. Web Time Entry. Student. Training Manual & User s Guide

South Dakota Board of Regents. Web Time Entry. Student. Training Manual & User s Guide South Dakota Board of Regents Web Time Entry Student Training Manual & User s Guide Web Time Entry Self Service Web Time Entry is a web-based time entry system designed to improve accuracy and eliminate

More information

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September

More information

SCOPE MANAGEMENT PLAN <PROJECT NAME>

SCOPE MANAGEMENT PLAN <PROJECT NAME> SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

Rail Network Configuration Management

Rail Network Configuration Management Division / Business Unit: Function: Document Type: Enterprise Services Engineering Procedure Rail Network Configuration Management Applicability ARTC Network Wide SMS Publication Requirement Internal /

More information

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE TABLE OF CONTENTS STEP 1 IDENTIFY THE CHANGE... 5 1.1 TYPE OF CHANGE... 5 1.2 REASON FOR THE CHANGE... 5 1.3 SCOPE THE CHANGE... 6 1.4 WHERE ARE YOU NOW?...

More information

Progress Report Template -

Progress Report Template - Progress Report Template - Project Name Project Website Report compiled by Kultur, University of Southampton (lead institution) http://kultur.eprints.org Victoria Sheppard Reporting period Oct 07 Apr 08

More information

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017 From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days

More information

PROJECT AUDIT METHODOLOGY

PROJECT AUDIT METHODOLOGY PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit

More information

February 10 12, 2006 Amanda Mewborn Hardy & Adrienne Jarvis Dickerson

February 10 12, 2006 Amanda Mewborn Hardy & Adrienne Jarvis Dickerson Leading Revenue Cycle Process Improvement February 10 12, 2006 Amanda Mewborn Hardy & Adrienne Jarvis Dickerson Speaker Introduction Adrienne Dickerson Adrienne graduated from the Georgia Institute of

More information

EMR Capacity Market Implementation Coordination Workshop

EMR Capacity Market Implementation Coordination Workshop EMR Capacity Market Implementation Coordination Workshop Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight

More information

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:

More information

Education Data Portal ( EDP ) Data Dashboard Solutions

Education Data Portal ( EDP ) Data Dashboard Solutions NYSED DATA DASHBOARD SOLUTIONS RFP Attachment 6.8 Statement of Work Template THIS IS STATEMENT OF WORK dated [Date] (the SOW ) to the Contract dated [Date] (the Agreement ) between NEW YORK STATE EDUCATION

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

PHASE 9: OPERATIONS AND MAINTENANCE PHASE

PHASE 9: OPERATIONS AND MAINTENANCE PHASE PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.

More information

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Ashley Institute of Training Schedule of VET Tuition Fees 2015 Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-

More information

Quality Management System Manual

Quality Management System Manual Quality Management System Manual This manual has been reviewed and approved for use by: Jack Zazulak President, Aurora Machine Limited March 07, 2011 Date - Copyright Notice - This document is the exclusive

More information

Contents of the ISO 9001:2008 Quality System Checklist

Contents of the ISO 9001:2008 Quality System Checklist Contents of the ISO 9001:2008 Quality System Checklist Page Hyperlinks (click underlines) This SAMPLE document includes 4 clauses of the standard. You receive the Windows.doc file (with hyperlinks). You

More information

Gilead Clinical Operations Risk Management Program

Gilead Clinical Operations Risk Management Program Gilead Clinical Operations Risk Management Program Brian J Nugent, Associate Director 1 Agenda Risk Management Risk Management Background, Benefits, Framework Risk Management Training and Culture Change

More information

Requirements Analysis/Gathering. System Requirements Specification. Software/System Design. Design Specification. Coding. Source Code.

Requirements Analysis/Gathering. System Requirements Specification. Software/System Design. Design Specification. Coding. Source Code. Change Control and Configuration Management IVT 11 th Annual conference April 2010 DISCLAIMER Amgen is not responsible for the written or verbal bl content t of fthi this presentation tti Gisele Fahmi,

More information

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 Appendix 2 Action Plan Due Date Status Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 CS1027 ICT Improvement Programme 31 January 2016 Objectives: CORPORATE SERVICES: ICT

More information

ISO 9001:2008 STANDARD OPERATING PROCEDURES MANUAL

ISO 9001:2008 STANDARD OPERATING PROCEDURES MANUAL 8200 Brownleigh Drive Raleigh, NC 27617-7423 Phone: (919) 510-9696 Fax: (919) 510-9668 ISO 9001:2008 STANDARD OPERATING PROCEDURES MANUAL ALLIANCE OF PROFESSIONALS & CONSULTANTS, INC. - 1 - Table of Contents

More information

Quality Manual TABLE OF CONTENTS APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3

Quality Manual TABLE OF CONTENTS APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3 TABLE OF CONTENTS DESCRIPTION SECTION PAGE INTRODUCTION 1.0 1 APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3 CORPORATE POLICY 3.0 3 QUALITY MANAGEMENT SYSTEM 4.0 4 GENERAL

More information

Important Dates Calendar 2014-2015 FALL

Important Dates Calendar 2014-2015 FALL Important Dates Calendar 204-205 FALL Rev. 6-8-4 st 8 H st 0 2nd 0 st 5 2nd 5 3rd 5 LSC Advanced Registration Begins May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 Returning Students Advanced

More information

IT Service Management

IT Service Management RL Consulting People Process Technology Organization Integration IT Service Management Change Management Methods and Implementation Best Practices White Paper Prepared by: Rick Leopoldi June 19, 2002 Change

More information

Insurance and Banking Subcommittee

Insurance and Banking Subcommittee Insurance and Banking Subcommittee Citizens Depopulation Update September 16, 2015 Christine Ashburn VP Communications, Legislative and External Affairs 2 3 Depopulation Customer Communications 1. 40 days

More information

Retail Market IT Services Service Level Agreement

Retail Market IT Services Service Level Agreement Electric Reliability Council of Texas Retail Market IT Services Service Level Agreement Summary: Availability targets and related service information for the IT services provided by ERCOT that facilitate

More information

AP Automation at Fossil. How Fossil implemented Opentext Vendor Invoice Management Wim Schalken

AP Automation at Fossil. How Fossil implemented Opentext Vendor Invoice Management Wim Schalken AP Automation at Fossil How Fossil implemented Opentext Vendor Invoice Management Wim Schalken Agenda INTRODUCTION LANDSCAPE PROJECT PROCESS LESSONS LEARNED Click to edit super huge text copy The Fossil

More information

Legislative Brief: PAY OR PLAY PENALTIES LOOK BACK MEASUREMENT METHOD EXAMPLES. EmPowerHR

Legislative Brief: PAY OR PLAY PENALTIES LOOK BACK MEASUREMENT METHOD EXAMPLES. EmPowerHR EmPowerHR Legislative Brief: PAY OR PLAY PENALTIES LOOK BACK MEASUREMENT METHOD EXAMPLES The Affordable Care Act (ACA) imposes a penalty on applicable large employers (ALEs) that do not offer health insurance

More information

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor

More information

CDL Warrior Truck Driver Communication & Safety (TDCS) System. May 12, 2015

CDL Warrior Truck Driver Communication & Safety (TDCS) System. May 12, 2015 CDL Warrior Truck Driver Communication & Safety (TDCS) System May 12, 2015 Background Estimated that 4,000 to 9,000 trucks used over the life of a well. This volume, combined with the remote location,

More information

Finance Process Document - Expense Claims and Payment

Finance Process Document - Expense Claims and Payment REVISION HISTORY Rev.. Date Description Responsible 1.0 Aug 2007/2011 Original Final Version Approved Niall Doyle (MAPS Irl Ltd.)/Margaret Dillon 2.0 Jan 2015 Revised structure of documents in line with

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

"Your career as a project manager begins here!"

Your career as a project manager begins here! CHECK-LIST Audited project phases: Auditor: Project name: Prepared by: Date: Project completion Instructions for completion: When filling in the Checklist think about the actual contents of the audited

More information

VICTORIAN CARDIAC OUTCOMES REGISTRY. Data Management Policy

VICTORIAN CARDIAC OUTCOMES REGISTRY. Data Management Policy VICTORIAN CARDIAC OUTCOMES REGISTRY Data Management Policy Version 1.0 26 February 2014 Table of Contents 1. Document Version Control... 1 1. Preface... 2 2. Project Information... 2 2.1 Purpose of VCOR...

More information

Lead Provider Framework Draft Scope. NHS England / 13/12/13 Gateway Ref: 00897

Lead Provider Framework Draft Scope. NHS England / 13/12/13 Gateway Ref: 00897 Lead Provider Framework Draft Scope NHS England / 13/12/13 Gateway Ref: 00897 1 Introduction The commissioning support lead provider framework is being developed in response to requests from CCGs for a

More information

Department of Energy and Climate Change (DECC) Information Management Assessment Programme Action Plan

Department of Energy and Climate Change (DECC) Information Management Assessment Programme Action Plan Department of Energy and Climate Change (DECC) Information Management Assessment Programme Action Plan # Recommendation Actions Priority High/ Low/ Medium R1 DECC must ensure that where key services are

More information

People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan

People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan This Project Management Plan details the key elements critical to the successful implementation of

More information

Introductory Certificate. The APM Project Fundamentals Qualification

Introductory Certificate. The APM Project Fundamentals Qualification The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment

More information

Leveraging Technology For ICD-10 Program Management Using MS SharePoint 2010. Poster Presentation by Maithili Vadula

Leveraging Technology For ICD-10 Program Management Using MS SharePoint 2010. Poster Presentation by Maithili Vadula Leveraging Technology For ICD-10 Program Management Using MS SharePoint 2010 Poster Presentation by Maithili Vadula ICD-10 Project using SharePoint: Project Background: New structure for coding diagnosis

More information

Project Execution Guidelines for SESAR 2020 Exploratory Research

Project Execution Guidelines for SESAR 2020 Exploratory Research Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project

More information

Project Lifecycle Management (PLM)

Project Lifecycle Management (PLM) Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS

More information

CMEMS user requirements and user uptake strategy

CMEMS user requirements and user uptake strategy CMEMS Service Evolution & User Uptake Workshop CMEMS user requirements and user uptake strategy Dominique Obaton Mercator Océan CMEMS Service Evolution & User Uptake Workshop The Copernicus Marine service

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Continuous Improvement, make it visible!

Continuous Improvement, make it visible! Continuous Improvement, make it visible! Ben Linders Operational Development & Quality Ericsson R&D, The Netherlands ben.linders@ericsson.com, +31 161 24 9885 International Conference on Software Process

More information

MONTHLY PROJECT PROGRESS REPORT

MONTHLY PROJECT PROGRESS REPORT MONTHLY PROJECT PROGRESS REPORT Project name: Project description: UCL School of Pharmacy Merger - IT & Data Programme A Programme to ensure all IT & Data elements of the UCL SoP Merger are co-ordinated

More information

Detailed guidance for employers

Detailed guidance for employers April 2015 3 Detailed guidance for employers Appendix A: Pay reference periods This document accompanies: Detailed guidance no. 3 Assessing the workforce Pay reference period calendars where the definition

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Monthly Status Report

Monthly Status Report Deliverable to: Montana Department of Public Health and Human Services Independent Verification and Validation (IV&V) Services for the Montana Medicaid Management Information System (MMIS) Monthly Status

More information

INTEGRATED MANAGEMENT SYSTEM MANUAL IMS. Based on ISO 9001:2008 and ISO 14001:2004 Standards

INTEGRATED MANAGEMENT SYSTEM MANUAL IMS. Based on ISO 9001:2008 and ISO 14001:2004 Standards INTEGRATED MANAGEMENT SYSTEM MANUAL IMS Based on ISO 9001:2008 and ISO 14001:2004 Standards Approved by Robert Melani Issue Date 30 December 2009 Issued To Management Representative Controlled Y N Copy

More information

Establishing the HKJC IT PMO. ISACA Forum. Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club. 8 April 2008

Establishing the HKJC IT PMO. ISACA Forum. Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club. 8 April 2008 Establishing the HKJC IT PMO ISACA Forum Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club 8 April 2008 1 Introduction to HKJC IT 2 Mission Committed to One Club, One Team, One Vision,

More information