How a Traditional Project Manager Transforms to Scrum: PMBOK vs. Scrum
|
|
|
- Charlene Warner
- 10 years ago
- Views:
Transcription
1 1 How a Traditional Project Manager Transforms to Scrum: PMBOK vs. Scrum Jeff Sutherland, Ph.D., Nafis Ahmad, PMP Abstract Transitioning from a traditional project manager to Scrum is challenging. The PMI Project Manager manages the project by ensuring that intermediate deliverables are delivered at various stages of the project. Agile development emphasizes the need for producing tangible results as soon as possible and as often as possible. The resulting role of an Agile project manager is fundamentally different from a PMI Project Manager. We have provided a mapping between the PMI responsibilities to Scrum and show a project manager how to more easily make the transition to an agile practice Keywords: PMI; PMBOK, Project Manager; Scrum; Agile I. INTRODUCTION T HE Project Management Institute (PMI) has defined the Project Management Body of Knowledge (PMBOK) [1] which has codified the role of a project manager in a project. PMBOK defines the knowledge areas, phases and activities of a project that are conducted during the life of a project. The PMBOK approach towards project management is plan-oriented and activity centric, and thereby, results in a number of processes that has various inputs and outputs. The PMI Project Manager (Traditional Project Manager) manages the project by ensuring that these intermediate project deliverables are planned and delivered at various stages of the project. The Agile Manifesto [11] acknowledges the need for several of these deliverables but does not put as much emphasis on their creation and control. The Agile development process is geared towards people and interactions, and emphasizes the need for producing tangible results as soon as possible and as often as possible during the life of a project. The resulting role of an Agile Project Manager is thereby fundamentally different than that of a Traditional Project Manager. This paper attempts to highlight the major differences between the Traditional Project Manager and an Agile Project Manager. We will use the simplest and most common Agile methodology Scrum, to present the differences. Additionally, we will provide a mapping of the PMI Knowledge Areas to Agile/Scrum practices that will also help to highlight the major differences in the two approaches. Finally, the paper will provide a mapping between a PMI Project Manager role and a Scrum Master, which would help the reader who is transitioning from a traditional project management role to a more agile environment. II. TRADITIONAL PROJECT MANAGEMENT (TPM) A traditional project typically has the following characteristics: Phased: TPM is divided into distinct phases of homogeneous activities like requirements, design, implementation, verification and maintenance phases. A technical transfer or handoff, transitions the project from one phase to another. Sequential: The phases of the project are typically sequential where one phase starts when the previous phases are completed and perfected. Non-iterative: The phases of project are typically not repeated unless through a formal process of change control which may trigger a sequential execution of phases again. Plan-driven: TPM is driven by a detailed project plan which describes the various activities during the phases and predicts the chronology of the activities, tasks, phases of the project and the effort that would be required to execute them. The progress in a traditional project is seen to be flowing downwards like a waterfall through the various phases of the project, thereby such projects are said to be using the waterfall approach. Traditional approaches to project management are largely based upon the PMI defined practices and processes of project management. Even though PMI does not specify a methodology such as waterfall, most project managers who follow the PMI processes end up using the waterfall approach. III. PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK) For several years the gold standard of project management has been the PMBOK in which the Project Management Institute (PMI) has described the practices, processes, phases and knowledge areas that are commonly encountered in projects. The PMBOK defines 5 Process Groups (Initiating, Planning, Executing, Monitoring and Controlling, and Closing), and 9 knowledge areas (Integration, Scope, Time, Cost, Quality, Human Resource, Communication, Risk and Procurement Management).
2 2 IV. PMI PROJECT MANAGER The PMBOK describes the Project Manager as major stakeholder within a project who is assigned to achieve project objectives. The PMI project manager is responsible for: [6] - Developing the project management plan and all related component plans, - Keeping the project on track in terms of schedule and budget - Identifying, monitoring, and responding to risk, and - Providing accurate and timely reporting of project metrics The PMBOK defines the project manager as the lead person responsible for communicating with all stakeholders, particularly the project sponsor, project team, and other key stakeholders. The project manager occupies the center of the interactions between stakeholders and the project itself. [6] V. MAPPING PMI CONCEPTS TO AGILE/SCRUM The PMBOK does not explicitly prescribe a development methodology, however the Waterfall methodology is most commonly associated with it. An Agile and iterative methodology like Scrum can also be mapped to the PMBOK definition of a project when a few definitions are made clear. A phase defined in the PMBOK is equivalent to a Scrum Release and the sub-phases are then mapped to individual iterations or sprints. The adjustment that the traditional project need to make is to consider each sub-phase or sprint as a complete cycle of design, development and test, such that the deliverable is working code and not an intermediate artifact as common in Waterfall methodology. In this way the product is defined, developed and enhanced as part of a progressive elaboration. The Scrum project manager (ScrumMaster) is responsible for developing the team and instilling the Scrum values and practices, whereas the team is responsible for all the deliverables including the planning of the project. The following sections will present the formal PMI concepts Process Groups and Knowledge Areas, in terms of their Scrum equivalents, to provide the user a comparison and transition point. VI. MAPPING PMBOK PROCESS GROUPS Initiation: Scrum has Initiation processes that are responsible for the definition of the product roadmap, releases and sprints, and project authorization. Project Initiation phases vary from company to company, for example, Citrix Systems uses a formal enterprise Scrum model, which requires a detailed checklist that is used to initiate and authorize Scrum projects at Citrix. In contrast, a startup would have a lot less formalism for its initiation process. The first sprint may be used to provide a general structure and plan of the project, but would still deliver at least one feature of the product. Planning: Scrum defines a Release Planning Meeting which establishes a plan and goal that the Scrum teams and the rest of the organization can understand and communicate. [2] The Sprint Planning Meeting is used to define and plan the goals and tasks of a phase or sub-phase of the project. Additionally, a Daily Scrum (meeting) is conducted to plan the day for individual team members. The main difference is that the whole team is involved in the planning processes at all levels in Scrum, and is thereby committed to the delivery as the team owns the plan. Executing: The Scrum team is responsible for carrying out the sprint and release tasks that result in a deliverable defined by the sprint/product backlog. The ScrumMaster plays the role of a facilitator to ensure all the roadblocks are removed so that the team can execute. Project execution is done throughout the Scrum project, with the intent of providing a piece of working software as the end of each sprint. ScrumMasters do not manage or execute the project, instead they manage the (Scrum) principles, and in turn the Scrum principles manage the teams. Monitoring and Control: Regular reviews conducted by the team as part of sprint/release retrospectives as well as the daily scrums that help in removing any obstacles that impede the team s progress. Additionally, burndown charts are used to monitor the progress of the team. Closing: The final sprint (Sprint N+1) can be used to perform administrative closure of the project, as well as perform any product hardening, fulfill audit/assessments requirements, or develop product transitioning documentation like user/installation/configuration manuals, etc. Sprint and Release retrospectives are conducted to ensure learning and feedback to improve the process and the priorities of the product backlog. VII. MAPPING PMBOK KNOWLEDGE AREAS The PMBOK defines nine knowledge areas which define the roles, responsibilities and deliverables for project stakeholders, including the project manager and the team. This section describes the mapping between each of the knowledge areas and the Agile/Scrum practice or process that corresponds to that knowledge area. a) Integration Management In both the Agile and Traditional paradigms, Integration Management brings the various processes together to create a concerted effort to deliver customer needs. The main difference is in the role of a project manager in each approach. The ScrumMaster has a lighter touch than the traditional project manager the former plays the role of a facilitator who helps the team perform optimally in a self-sufficient manner, whereas the latter depends upon plans that direct all phases and aspect of the project in as much detail as possible. The Scrum approach is more like a controlled chaos whereas TPM is more scripted in nature. This requires a natural mind shift on part of the project manager where they need to give up control in an Agile/Scrum project and empower the team to make and live their own decisions. The resulting project environment may appear to be chaotic, where the team decides the next steps on the project while applying the empirical data from the project to adjust and adapt. However, this is inline with the modern theories of optimal execution. Theoretical biologist, Stuart Kauffman has developed mathematical [2]
3 3 models that show that rate of evolution is maximized in evolving systems near the edge of chaos. [9] Develop Project Charter: In both approaches, development of a project charter is essential to secure funding and buy-in from senior management. In both cases, feedback and approval may be necessary to start the project but the Scrum approach emphasizes the involvement of the project team even at this early stage. Most Agile projects call this step envisioning and the resulting deliverable is a vision statement or a product description box [3] developed by the Scrum team and not just the Project Manager/ScrumMaster. Develop Project Management Plan: A detailed, integrated project plan is a main deliverable of TPM and a traditional project manager spends a lot of time and effort in creating a detailed project plan up front. Scrum also utilizes planning on release and sprint levels, but the overall approach for planning Scrum projects is more of a just-in-time (JIT) planning approach where the next few sprints are planned in more detail within the context of an overall release plan. The more important questions for a ScrumMaster are the length of the iterations, the size and scope of a release (how many sprints in a particular release) and setting up the framework of the project where it can iterate through various phases of the project. Another important difference is that the traditional project manager is solely responsible for the project plan, whereas in the Agile/Scrum paradigm, the project teams are active collaborators and the collective owners of the plan. In other words, project planning is a team deliverable and not just the project manager s burden to carry. Direct and Manage Project Execution: Scrum thrives on selforganizing teams where individual team members take more responsibility of their actions. The ScrumMaster does not manage the project but leads by facilitating the team to achieve their objectives. Scrum fosters a process of continuous improvement using Sprint and Release Retrospectives, to provide learning from the previous sprint or release and adapt to the changes and lessons learned. The ScrumMaster is responsible for facilitating the retrospectives. Integrated Change Control: There is no formal Change Control process in Scrum. However, change control is implicitly built into the Scrum process, with the team replacing the Change Control Board (CCB), and the product owner as the final decision making authority on the team. The change control process thus becomes management and up keep of the prioritized product backlog. Certain amount of change is expected in every project and practices and patterns have emerged that handle interrupts and changes in a Scrum project. For example, the Interrupt Pattern (Illegitimus Non Interruptus) defines three rules that advocate using buffers for unexpected items based on historical data. [10] Project Closeout: The final sprint of the final release of an Agile/Scrum project serves as the final product handout to the customer, which is also accompanied by the administrative closure of the project. A project retrospective is conducted to document and discuss any lessons learned and suggestions for improvement of the products and processes. b) Scope Management Scope is a part of the iron triangle of traditional project management (Time, Cost, Scope & Quality it really is a tetrahedron). TPM tries to define all the vertices of the triangle and makes efforts to keep them from changing. The Agile approach solves this seemingly intractable problem by keeping Time and Cost fixed (time-boxed iterations with a set Agile team), the only item that is negotiable is the scope. Scope control is the explicit responsibility of the product owner, who (re)prioritizes the product backlog to manage the scope, and produces features that are actually needed instead of following a plan-based approach which may result in features that are never used. Scope Planning and Definition: A Scope Management Plan is not needed in Scrum. Agile projects use a Product Roadmap to guide the overall release and sprint plan for the whole project. The actual specification of the features that need to be built in a particular sprint is elaborated during or just before the sprint by the product owner. Scope is defined and controlled through the product backlog. Create a WBS: Creation of a detailed Work Breakdown Structure (WBS) is not needed in Scrum - a typical project schedule is divided into releases and sprints and generally does not document the tasks that are performed in each sprint. Only the features or user stories that are to be implemented are identified. The feature set may be further elaborated into tasks for individual team members to be implemented in that particular sprint. Some teams also create an overall Feature Breakdown Structure (FBS) which severs as a roadmap for Agile releases [3]. Systematic, a Danish IT firm that has successfully combined CMMI and Agile, replaced 3 levels of WBS by a backlog, achieving 80% reduction in project management costs. [11] Scope Verification: Acceptance testing is part of a sprint. Thereby verification of scope is a continuous activity that is performed throughout the project and controlled by the product backlog. Scope Control: Scope control is performed by active product backlog management and time-boxing. The time-boxed structure of the sprint prevents customers from changing the features/scope and makes them wait until the next iteration to make any changes. Exceptions and interruptions are expected and can be handled using the rules defined in the Interrupt Pattern. [10] c) Time Management The Scrum approach towards time management is a more topdown approach, whereas TPM favors a more bottom-up approach. TPM is based upon Activities - their definition, estimation, and scheduling, captured in a Project Plan (Schedule), whereas, the Scrum approach is more value-based, but there is still a need for estimation of effort which is done on a high-level (releases) and a lower-level (sprints). A Release Plan encompasses multiple sprints using abstract measurements, like story points, to estimate the product (release) backlog. Sprint Plans are developed at sprint planning meetings, and are a list of activities and tasks that are part of the next sprint.
4 4 Activity Definition: In Scrum the definition of activities and tasks that are needed to develop the feature set for the iteration is done by the project team and is facilitated by the Scrum Master. Note that a TPM project plan would have tasks or activities with work packages attached to them as the lowest level in the WBS. In Scrum the work packages equate to features which may in turn have activities associated with them. Activity Estimation and Sequencing: In Scrum task estimation and task sequencing is done by the team during sprint planning meetings. Schedule development and control: In Scrum a schedule is developed at the Release level and then the sprint schedule is refined during the sprint planning. Since the sprint length remains time-boxed, the only planning needed is the inclusion, estimation and elaboration of individual features targeted for the sprint. The control of the schedule is achieved by disallowing any scope change while the sprint is in progress. The sprint retrospective provides the opportunity to optimize the overall schedule. d) Cost Management As in TPM, the ScrumMaster also needs to work within the budgetary constraints and processes of their organizations. Scrum provides better budgetary control to the customer by providing better insight into the project through direct involvement with the team. The ScrumMaster facilitates the team and helps the customer to collaborate with the team to make realistic cost decisions. [4] Cost Estimation: The costs of a Scrum project are estimated top-down a release plan is first developed and costs are estimated by using abstract measurements like Story Points. The rolling wave nature of a Scrum project planning allows elaboration of the estimates of tasks associated with each sprint. As part of the continuous improvement, the feedback from sprint planning then helps refine the overall release estimates. The other important aspect of cost estimation in Scrum is that costs are always estimated by the team with customer as an integral part of the team. In Scrum, estimation is done at different points in the project, like the beginning, after two or three sprints, or/and at the end/start of a release. Cost Budgeting: The cost baseline of a project is created by adding up the costs of all the sprints. The estimates of the project or release are refined at the end of each sprint, as new features or functionality is uncovered and as the project velocity becomes apparent. An additional sprint can be planned as management buffer by savvy project managers to provide for any contingency. Cost Control: In Scrum the ScrumMaster is responsible for making sure that the customer is involved with the team and thereby knows the various scope changes as well as the team velocity. As more information about the estimated (both over and under) features, the scope changes are then handled through the prioritized project backlog. The Product Burndown Charts are used to show the progress of sprint and can be used as a cost controlling aide. In more regulated and formal environments, like the Government and Federal sectors, Earned Value Management (EVM) is a project requirement, and it can still be used by measuring progress at a higher granularity, as prescribed in AgileEVM AgileEVM (as traditional EVM) will still only measure the spend on the project at the time of measurement, but would not provide the actual business value delivered to the customer. [4] e) Quality Management Cross-functional nature of the Scrum teams makes Quality Assurance (QA) an integral part of Scrum, where QA personnel are involved in planning, design and implementation of a product. In turn the demands of Scrum are making QA rely more on QA automation tools to keep pace with the rapid pace of development and delivery of Scrum projects. Quality Planning: Quality Planning is part of the overall planning and is the responsibility of the whole crossfunctional Scrum team. Quality Assurance: In Scrum QA is performed by the team itself, however in more formal environments, a third party can be brought in for assessments and audits; generally an extra sprint (Sprint N+1) is used for such assessment to fulfill the regulatory or industry compliance obligations. Additionally, retrospectives and reviews throughout the project, provides continuous QA. Quality Control: Quality control is performed as part of the iteration by a combination of automated testing tools, QA team members and acceptance testing by product owners and business representatives. Burndown charts are also used as quality tools to monitor the trends of feature development. As part of quality control, some companies are beginning to add acceptance tests in the product backlog. f) Human Resource Management The Agile framework establishes cross-functional teams with mutual accountability, that are self-directing and selfcorrecting using regular team retrospection. Human Resource Planning: Scrum creates cross-functional teams that are dedicated to the project for the duration of the project. Acquiring a Project Team: Scrum recommends development of a cross-functional project team that is seven plus or minus two people (strive for an odd number of team members) for the entire duration of the project. [2] Develop the Project Team: Use the Agile and Scrum values (commitment, openness, focus, courage and respect) to develop and build the team. Manage the Project Team: An Agile project manager facilitates and coaches their team, while providing real-time feedback to the team. g) Communication Management Instead of formally documenting a Communications Management Plan, rely on the informality of Scrum teams that creates and emphasizes direct and face to face communication. Daily Scrum meetings are used for direct and frequent exchange of information. In Scrum, Stakeholders are engaged via the cross-functional team and thereby managing them is not necessary. Information distribution and progress reporting is also simplified because of this structure. Online [5].
5 5 communication tools, like instant messaging or Skype videos are used frequently to work with team members that are not collocated. h) Risk Management Scrum is a Risk Reduction System [8] that handles risk on both strategic and tactical level. On a strategic level, it handles product risks like time to market, rapid response to change, etc. On a tactical level it handles product development risks by using Impediments/Issues lists. Risk Management Planning is done informally instead of a documented plan, as risk management is intrinsically built into the Scrum process. The whole team is involved in identification and analysis of risk at various points in the sprints and the project, using the daily scrums, and Sprint and Project Retrospectives. i) Procurement Management Scrum teams play a more active role in evaluating and selecting the sellers, often engaging in a proof of concept, possibly as part of one of the early iterations. Several contract types are used with Scrum projects, with clauses that allow flexibility for the customers. Scrum allows for contracts with early termination clause, commonly referred as Money for Nothing, where a customer can terminate a contract at the end of any sprint by paying 20% of remaining contract value. Another clause, Change for Free, states that a customer shall make changes to Scope without incurring any additional cost if total scope of contracted work is not changed. [12] VIII. THE TRANSITION ORGANIZATIONAL GAME PLAN The transition from the Traditional to Agile Project Management approach can be achieved in at least three major ways: A. Apply Agile Techniques In this approach various techniques that are commonly used in Agile projects are applied in a traditional project context to gain some efficiencies. For example, develop cross-functional teams and insist on having a product owner from the business to be part of the team or at least be available to the team during the life of the project or phase. Another Agile technique would be to use the daily standup meetings (scrums) that would keep the focus on immediate deliverables and removal of impediments quickly. Various other development and coding techniques, usually defined in the XP methodology can also improve the efficiency of a Traditional Project. This type of an approach is useful for environments where there is resistance to (radical) change, such as the government, department of defense, etc. A project group at Google, which has a non-prescriptive project management culture, successfully introduced Scrum practices, piecemeal, over a period of six months; sprints were introduced in the fourth month. B. Use An Incremental Delivery Approach A traditional waterfall project can be divided into several mini-waterfalls, where the design, coding and testing phases are sequential within the iteration but the product is delivered in increments, and thereby there would be opportunity between the iterations to modify the features sets by changing the priority of features or modifying the feature itself before the start of next waterfall. C. Switch to a Pure Agile Approach This approach is the most beneficial as it provides the full benefits of an Agile approach and the efficiencies it offers. However, this is a radical mind shift and it needs a cultural and organizational change that may or may not be feasible for some organizations. Hybrid approaches, such as the ones described above, may lead into a total organizational shift towards later on as the organization sees the benefits of the Agile approach. IX. THE TRANSITION INDIVIDUAL GAME PLAN A. Understand the Differences 1. Value vs. Plan driven Approach The main difference between an Agile/Scrum and Traditional approach is that the former is a valuedriven paradigm, and the later is more driven by project plans, or a desire to plan out the entire project up front. This does not mean that Scrum projects do not do any planning. In fact, Scrum approaches define plans at both the release and iteration level but the emphasis is on providing the highest value features in each iteration or release as the project team iterates through the project. The Traditional Projects Management approach is based upon detailed planning which is typically done up front and which defines the detailed-level tasks that are to be performed throughout the life of the project. 2. Empirical vs. Prescriptive Approach: Scrum implements an empirical approach based in process control theory [8]. Using first-hand observations and backlog graphs, the ScrumMaster and the team adapts to the results of previous or current sprints by adjusting delivery targets to the team velocity or adjusting the team to improve the velocity itself. The TPM approach is prescriptive, in that it tries to predict the future, and develops a plan upfront based upon assumptions and no empirical data. 3. Self-Organizing vs. Directed Teams The ScrumMaster takes a step back and lets the teams organize themselves. They provide the environment and opportunity for the teams to thrive and deliver. Scrum teams are highly selfdisciplined; rather than imposing discipline,
6 6 ScrumMaster provides the requisite leadership and coaching to the team to balance the agility and structure. 4. Stakeholder Management vs. Stakeholder Involvement Business Stakeholders are not managed by project managers; instead Scrum dictates that the product owner should be a part of the Scrum team. Such an arrangement ensures that the business is part of all the decisions and obviates the use of elaborate progress and status reporting. 5. Project Manager vs. ScrumMaster Scrum Projects replaces the role of a project manager with a ScrumMaster and splits the former s responsibilities into the ScrumMaster, the Product Owner and the Scrum team in general. The ScrumMaster is responsible for the velocity of the Scrum sprints, whereas the Product Owner is responsible for the vision and revenue of the product. The ScrumMaster manages Scrum principles, while the principles mange the Scrum teams. 6. Top-down vs. Bottom-Up Planning Scrum favors a top-down approach where an overall roadmap is developed, which is progressively elaborated into releases and sprints. The traditional approach emphasizes on detailing individual tasks into Work Breakdown Structure (WBS) to construct the complete project plan at the beginning of the project. B.. Understand the Similarities 1. Project Phases and Sub-Phases The phases and sub-phases described in the PMBOK are similar to the releases and sprints used for the Scrum projects as long as (a) a sub-phase is defined as a complete cycle of delivery (b) a subphase is always of a fixed length (4 weeks or less in case of the Scrum sprint) (c) requirements, design, development, etc are considered activities and not phases. 2. Software Engineering Practices Software Engineering practices such as the ones described by XP can be used in either paradigm to improve efficiency of the teams. Three main XP practices continuous integration, automated testing and pair programming/code reviews, are cited as requisite practices for Scrum and are also used by several CMM 5 organizations. C. Learn New Skills 1. Servant-Leadership Learn the art of Servant-leadership to achieve results for your organization by giving priority attention to the needs of the colleagues and the teams that you are serving. Main function of the Scrum leader is to remove impediments for the team so that the team can be empowered to make decisions, execute freely and deliver value. 2. Foster Collaboration Improve the interaction of individuals by using concepts of self-organization, self-discipline, respect for individuals, conflict resolution and technical competency. 3. Balance Flexibility and Stability Too much structure stifles creativity; too little structure breeds inefficiency.[3] The traditional project manager needs to de-emphasize the focus on control and provide more flexibility for the team to function, while making sure that the project still follows the basic Scrum principles and processes. Paradoxically, a well-executed Scrum requires more (self) discipline than traditional project management, in order to achieve and maintain the right balance of flexibility and stability. 4. Scrum Values Embody the Scrum values of commitment, openness, focus, courage and respect to develop and build the team. 5. Embrace Changes, Risks and Uncertainty Scrum works on the agile concept that opportunity, uncertainty and risk reside in the proposed product not in the approach to project management. [3] Changes, risks and uncertainty are inherent part of new product development, and their complete avoidance is neither possible nor necessary. Using Agile/Scrum methodology provides a way to handle changes to the project at any stage. D. Unlearn Old Skills 1. Planning Everything Up-front Unlearn to plan for everything upfront. Requirements are almost never completely known and are always prone to changes as the software is being developed. Thereby, complete and detailed project planning should be replaced by just-in-time planning for only the parts that are of highest values and are best understood at the time of planning. 2. Big Design Up Front (BDUF) In a Scrum project, a design need not be completed before implementation can start. Instead of BDUF, the iterative nature of the Scrum process favors the need for Emergent Designs and Architectures, where a just enough design is done in each iteration to support the features that are being delivered, resulting in leaner and maintainable code. The Emergent design techniques depend upon frequent code refactoring. [13] 3. Formal Change Management
7 7 A prerequisite of Scrum projects is that the teams are empowered to make decisions through the involvement of the product owner. Formal processes for change management are not needed, and are in fact anathema to a successful Scrum project. 4. Task Mastership Discovery, evaluation, triage and prioritization of tasks are responsibilities of a Scrum team. Scrum Masters need to learn to let go and trust the team to make the right decisions. Studies show that this is the most difficult skill to unlearn while transitioning to Scrum. [14] 5. Triple Constraints The PMI Iron triangle of Time, Cost, Scope and Quality (it is really a tetrahedron) is not managed in the traditional manner in a Scrum project. Time and costs are fixed (time-boxed) for all the sprints. Scope is defined at the beginning of a sprint and is then locked down. And Quality is addressed during each sprint by Acceptance testing. E. Rinse and Repeat Chances are that a traditional project manager transitioning to Scrum will not get everything right the first time, or the first few times. The Scrum paradigm allows the flexibility to improve the performance of the project based upon the empirical data from the previous sprints and releases. Using the data and first-hand observations, make the adjustments in the next iteration or project and optimize value creation for your customers. X. CONCLUSION The transition from Traditional to Agile Project Management is difficult due to the inherent philosophic differences between the two approaches. There are several concepts that are similar and can be mapped from one to the other, but there are others, like emphasis on upfront planning, which are fundamentally different, and thereby difficult to reconcile between the two. The practitioners who are making the transition from the traditional approaches to Agile would do well to understand and appreciate the philosophic differences between the two approaches and adhere to the underlying basic principles that form the core of the Agile manifesto and movement.. REFERENCES 1. Project Management Body of Knowledge (PMBOK), Fourth Edition 2. Ken Schwaber, Jeff Sutherland, ( ), Scrum Guide 3. Jim Highsmith (2004), Agile Project Management, Creating Innovative Products 4. Michele Sliger and Stacia Broderick (2008), The Software Project Manager s Bridge to Agility 5. Tamara Sulaiman, Brent Barton, Thomas Blackburn (2006), AgileEVM Earned Value Management in Scrum Projects 6. PMBOK, Fourth Edition, Section 2.3 Stakeholders 7. PMBOK, Fourth Edition, Appendix G Interpersonal Skills 8. Ken Schwaber, Mike Beedle, 2002, Agile Software Development with Scrum 9. Stuart Kauffman, 1993, Origins of Order: Self- Organization and Selection in Evolution 10. Illegitimus Non Interruptus, -patterns/team-pattern-language/illigitimus-noninterruptus 11. Jeff Sutherland, Carsten Jakobsen, Kent Johnson, Scrum and CMMI Level 5: The Magic Potion for Code Warriors 12. Money for Nothing, Change For Free, Agile Contracts, Scott Bain, 2008, Emergent Design: The Evolutionary Nature of Professional Software Development 14. Dina Friis, Jens OStergaard, Jeff Sutherland, Virtual Reality Meets Scrum: How a Senior Team Moved from Management to Leadership 15. The Agile manifesto, Dr. Jeff Sutherland is one of the inventors of the Scrum software development process. Together with Ken Schwaber, he created Scrum as a formal process at OOPSLA'95. They have extended and enhanced Scrum at many software companies and IT organizations. Jeff is a Distinguished Graduate of the United States Military Academy, a Top Gun of his USAF RF-4C Aircraft Commander class and flew 100 missions over North Vietnam. Jeff has advanced degrees from Stanford University and Ph.D from University of Colorado School of Medicine. He is currently a Chief executive officer of Scrum, Inc in Boston, Massachusetts and Senior Advisor to OpenView Venture Partners Mr. Nafis Ahmad is a Software Development Manager, managing multiple teams involved in software engineering projects for the Federal Aviation Authority (FAA). He is a skilled technologist and project manager, having held positions of CTO, CIO and Technology Director of several Boston area companies. Mr. Ahmad has a Masters in Computer Science from Texas &M University, and a Bachelor s in Computer Engineering. He is a PMI certified project Manager (PMP) and a Certified Scrum Master (CSM)..
How a Traditional Project Manager Transforms to Scrum Jeff Sutherland & Nafis Ahmad
How a Traditional Project Manager Transforms to Scrum Jeff Sutherland & Nafis Ahmad August 11 th, Agile 2011, Salt Lake City Brief Bios Dr. Jeff Sutherland ([email protected]) Co-inventor of Scrum Chairman
SCRUM BODY OF KNOWLEDGE (SBOK Guide)
A Guide to the SCRUM BODY OF KNOWLEDGE (SBOK Guide) 2013 Edition A Comprehensive Guide to Deliver Projects using Scrum TABLE OF CONTENTS TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1 Overview of Scrum...
PMP vs. Scrum Master
PMP vs. Scrum Master Compatible or Incompatible? Presented by: Karen Little, PMP, CSM, CBAP, ITIL, MCP, MBA Copyright 2007 by Karen Little 1 Agenda Introductions Background on Agile and SCRUM Methodologies
Atern The latest version of the DSDM approach which makes DSDM appropriate to all types of project.
THE AGILE PROJECT LEADER S DICTIONARY This dictionary attempts to de-mystify the jargon around the world of Agile projects. Part 1 translates common Agile terms into more traditional words. Part 2 translates
Course Title: Planning and Managing Agile Projects
Course Title: Planning and Managing Agile Projects Course ID: BA15 Credits: 21 PDUs Course Duration: 3 days (Live in person class only) Course Level: Basic/Intermediate Course Description: This 3-day course
Agile Project Management Mapping the PMBOK Guide to Agile Practices. Michele Sliger [email protected] Twitter: @michelesliger
Agile Project Management Mapping the PMBOK Guide to Agile Practices Michele Sliger [email protected] Twitter: @michelesliger Michele Sliger Sliger Consulting, Inc. www.sligerconsulting.com Over
Agility in Project Management
Agility in Project Management A recipe for turbulent times By Anil Kumar Natogi, PMP Infosys Technologies Limited Contents Why agility is required? Recipe for success Concept of agile project management
Agile Project Management
Agile Project Management with Bill Doescher, PMP, MBA, CSM Pi Principal i lconsultant tand Product tdevelopment tdirector Bill Doescher, PMP, CSM Bill Doescher is a Principal Consultant and Product Development
Course Title: Managing the Agile Product Development Life Cycle
Course Title: Managing the Agile Product Development Life Cycle Course ID: BA25 Credits: 28 PDUs Course Duration: 4 days (with optional Executive session) Course Level: Intermediate/Advanced Course Description:
Changing Roles and Responsibilities from Traditional project management to Agile project management
Changing Roles and Responsibilities from Traditional project management to Agile project management Vishvadeep Tripathi School of computer science and IT Devi Ahilya University Indore, India [email protected]
PMBOK? You Can Have Both! June 10, 2009. Presented by: www.esi-intl.com
Agile or the PMBOK? You Can Have Both! June 10, 2009 Presented by: David M. Sides, Vice President, ESI Consulting Services www.esi-intl.com Agenda June 10, 2009 Pic? Agile Framework Agile Truths & Myths
CSSE 372 Software Project Management: More Agile Project Management
CSSE 372 Software Project Management: More Agile Project Management Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected] Learning Outcomes: Plan Create a plan for
D25-2. Agile and Scrum Introduction
D25-2 Agile and Scrum Introduction How to Use this Download This download is an overview of a discussion Intertech has with clients on Agile/Scrum This download has an overview of Agile, an overview of
Agile Project Management: Adapting project behaviors to the software development environment
Agile Project Management: Adapting project behaviors to the software development environment with Bill Doescher, PMP, CSM PrincipalConsultant and Product Development Director Business Management Consultants
Agile in Financial Services A Framework in Focus
Agile in Financial Services A Framework in Focus John B. Hudson, B.Sc, PMP, CSM PMI NJ Chapter February 19, 2013 19 Feb 2013 1 Objectives 1. Agile Development an Overview 2. The Agile Enterprise Infrastructure
Agile Development Overview
Presented by Jennifer Bleen, PMP Project Services Practice of Cardinal Solutions Group, Inc. Contact: Agile Manifesto We are uncovering better ways of developing software by doing it and helping others
LEAN AGILE POCKET GUIDE
SATORI CONSULTING LEAN AGILE POCKET GUIDE Software Product Development Methodology Reference Guide PURPOSE This pocket guide serves as a reference to a family of lean agile software development methodologies
Certified ScrumMaster (CSM) Content Outline and Learning Objectives January 2012
Certified ScrumMaster (CSM) Content Outline and Learning Objectives January 2012 The following pages present the CSM taxonomy as validated through the 2011 Scrum Alliance Validation Study. Each percentage
Introduction to Agile Scrum
Introduction to Agile Scrum by Julia M. Lobur Penn State Harrisburg CMPSC 487W Fall 2015 Introduction to Scrum Learning Goals Relationship of Scrum to other Agile methods Scrum Framework Scrum Roles Scrum
CS435: Introduction to Software Engineering! " Software Engineering: A Practitioner s Approach, 7/e " by Roger S. Pressman
CS435: Introduction to Software Engineering! " " " " " " " "Dr. M. Zhu! Chapter 3! Agile Development! Slide Set to accompany Software Engineering: A Practitioner s Approach, 7/e " by Roger S. Pressman
International Association of Scientific Innovation and Research (IASIR) (An Association Unifying the Sciences, Engineering, and Applied Research)
International Association of Scientific Innovation and Research (IASIR) (An Association Unifying the Sciences, Engineering, and Applied Research) International Journal of Engineering, Business and Enterprise
Agile Practitioner: PMI-ACP and ScrumMaster Aligned
Agile Practitioner: PMI-ACP and ScrumMaster Aligned The PMI Agile Certified Practitioner (PMI-ACP) ScrumMaster credential validates your ability to understand agile principles, agile concepts, and establishes
How To Plan An Agile Project
GAO Scheduling Best Practices Applied to an Agile Setting by Juana Collymore and Brian Bothwell April 15, 2015 Outline Why is scheduling important? GAO Schedule Assessment Guide Overview Status of the
Certified ScrumMaster (CSM) Content Outline and Learning Objectives January 2012
Certified ScrumMaster (CSM) Content Outline and Learning Objectives January 2012 The following pages present the CSM taxonomy as validated through the 2011 Scrum Alliance Validation Study. Total questions
Agile Software Development with Scrum. Jeff Sutherland Gabrielle Benefield
Agile Software Development with Scrum Jeff Sutherland Gabrielle Benefield Agenda Introduction Overview of Methodologies Exercise; empirical learning Agile Manifesto Agile Values History of Scrum Exercise:
RISK MANAGMENT ON AN AGILE PROJECT
BIO PRESENTATION W3 6/28/ 11:30 AM RISK MANAGMENT ON AN AGILE PROJECT Michele Sliger Rally Software Development Better Software Conference June 26 29, Las Vegas, NV USA Michele Sliger Michele Sliger has
Agile vs. Waterfall. Why not both. Arnold Okkenburg PMP
Agile vs. Waterfall Why not both Arnold Okkenburg PMP Project Management Agile Project Management Traditional Project Management Key Questions for Project Managers 1. Impact on Existing Project Methodologies:
Mastering the Iteration: An Agile White Paper
Rally Software Development Corporation Whitepaper Mastering the Iteration: An Agile White Paper Dean Leffingwell Abstract: The heartbeat of Agile development is the iteration the ability of the team to
Issues in Internet Design and Development
Issues in Internet Design and Development Course of Instructions on Issues in Internet Design and Development Week-2 Agile Methods Saad Bin Saleem PhD Candidate (Software Engineering) Users.mct.open.ac.uk/sbs85
Scrum and CMMI Level 5: The Magic Potion for Code Warriors
Scrum and CMMI Level 5: The Magic Potion for Code Warriors Jeff Sutherland, Ph.D. Patientkeeper Inc. [email protected] Carsten Ruseng Jakobsen Systematic Software Engineering [email protected]
A Viable Systems Engineering Approach. Presented by: Dick Carlson ([email protected])
A Viable Systems Engineering Approach Presented by: Dick Carlson ([email protected]) Philip Matuzic ([email protected]) i i Introduction This presentation ti addresses systems engineering
Agile Engineering Introduction of a new Management Concept
Journal of Applied Leadership and Management 4, 39-47 39 Agile Engineering Introduction of a new Management Concept Philipp Hecker ([email protected]) Artur Kolb ([email protected])
Strategy. Agility. Delivery.
Strategy. Agility. Delivery. AGILE COURSES SCRUM MASTER CERTIFICATION THE PRODUCT OWNER & USER STORIES AGILE & KANBAN ACHIEVING AGILITY AGILE FOR EXECUTIVES Implementing Agile Project Management is a challenge
An Agile Project Management Model
Agile Project Management Jim Highsmith Chapter 5 An Agile Project Management Model We improve effectiveness and reliability through situationally specific strategies, processes, and practices. One of the
The Agile Manifesto is based on 12 principles:
The Agile Manifesto is based on 12 principles: Customer satisfaction by rapid delivery of a useful product solution Welcome changing requirements, even late in development Working products are delivered
Agile and Secure: Can We Be Both?
Agile and Secure: Can We Be Both? OWASP AppSec Seattle Oct 2006 Keith Landrus Director of Technology Denim Group Ltd. [email protected] (210) 572-4400 Copyright 2006 - The OWASP Foundation Permission
Development. Lecture 3
Software Process in Modern Software Development Lecture 3 Software Engineering i Practice Software engineering practice is a broad array of principles, concepts, methods, and tools that must be considered
The Scrum Guide. The Definitive Guide to Scrum: The Rules of the Game. July 2013. Developed and sustained by Ken Schwaber and Jeff Sutherland
The Scrum Guide The Definitive Guide to Scrum: The Rules of the Game July 2013 Developed and sustained by Ken Schwaber and Jeff Sutherland Table of Contents Purpose of the Scrum Guide... 3 Definition of
Introduction to Agile and Scrum
Introduction to Agile and Scrum Matthew Renze @matthewrenze COMS 309 - Software Development Practices Purpose Intro to Agile and Scrum Prepare you for the industry Questions and answers Overview Intro
SCRUM BODY OF KNOWLEDGE (SBOK Guide)
A Guide to the SCRUM BODY OF KNOWLEDGE (SBOK Guide) 2013 Edition A Comprehensive Guide to Deliver Projects using Scrum 2013 SCRUMstudy, a brand of VMEdu, Inc. All rights reserved. Library of Congress Cataloging-in-Publication
Project Management and Scrum A Side by Side Comparison by Anne Loeser, October 2006
Project Management and Scrum A Side by Side Comparison by Anne Loeser, October 2006 For decades, software development projects have followed the classic waterfall method in which software development initiatives
Agile Project Management
Agile Project Management Overview Fabrizio Morando Application Development Manager martedì 20 novembre 2012 What is Agile? Agile is used to denote the ability of Agile Methods to respond to changing requirement
Capstone Agile Model (CAM)
Capstone Agile Model (CAM) Capstone Agile Model (CAM) Approach Everything we do within the Capstone Agile Model promotes a disciplined project leadership process that encourages frequent inspection and
Comparing Scrum And CMMI
Comparing Scrum And CMMI How Can They Work Together Neil Potter The Process Group [email protected] 1 Agenda Definition of Scrum Agile Principles Definition of CMMI Similarities and Differences CMMI
How Agile methods resolve chaos and unpredictability in software projects
WHITE PAPER How Agile methods resolve chaos and unpredictability in software projects Author: Jack Milunsky Scrum Master and COO Brighstpark3 January 2009 INTRODUCTION This paper attempts to show why an
Certified ScrumMaster Workshop
Certified ScrumMaster Workshop Learn, understand, and execute on the three overarching principles behind Scrum: iterative development, self-management, and visibility. Even projects that have solid, well-defined
Extreme programming (XP) is an engineering methodology consisting of practices that ensure top-quality, focused code. XP begins with four values:
Scrum with XP By Kane Mar, Ken Schwaber. Introduction Scrum and extreme programming (XP) are both Agile methodologies. We've heard controversy regarding the value of each, with people familiar with each
Agile Scrum and PMBOK Compatible or Contrary?
Agile Scrum and PMBOK Compatible or Contrary? Paul Despres PMI Emerald Coast Panama City Branch June 26, 2014 Meeting Overview Agenda Topics: Review Agile/Scrum Methods Review PMBOK Structure Demonstrate
Certified Scrum Master Workshop
Learn, understand, and execute on the three overarching principles behind Scrum: iterative development, selfmanagement, and visibility. Even projects that have solid, well-defined project plans encounter
Agile Project Management and the Real World. Emily Lynema DLF Fall 2010 November 1, 2010
Agile Project Management and the Real World Emily Lynema DLF Fall 2010 November 1, 2010 Outline Why care about project management? Traditional vs. Agile What is Agile? What is Scrum? Agile case study:
Managing a Project Using an Agile Approach and the PMBOK Guide
Managing a Project Using an Agile Approach and the PMBOK Guide Kathy Schwalbe, Ph.D. [email protected] Augsburg College Minneapolis, Minnesota September 25, 2012 Abstract This paper includes excerpts
Software processes that are:
Agile Processes Software processes that are: Incremental (small software releases with rapid cycles) Cooperative (customer and developer working together with close communication) Straightforward (method
Bridging the Gap: Traditional to Agile Project Management. I. S. Parente 1. Susan Parente, PMP, PMI ACP, CISSP, PMI RMP, ITIL, MSEM;
Bridging the Gap: Traditional to Agile Project Management ABSTRACT I. S. Parente 1 1 Susan Parente, PMP, PMI ACP, CISSP, PMI RMP, ITIL, MSEM; S3 Technologies, LLC, Principal Consultant; parente@s3 tec.com
Mature Agile with a twist of CMMI
Mature Agile with a twist of CMMI Carsten Ruseng Jakobsen Systematic Software Engineering [email protected] Kent Aaron Johnson AgileDigm, Incorporated [email protected] Abstract Systematic is
Integrating PRINCE2 and Scrum for successful new product development
1 Goal Professional Services Pty Ltd 2 Renewtek Pty Ltd Integrating PRINCE2 and Scrum for successful new product development Rankins G J 1 and Kearns M 2 This paper was presented at the Australian Institute
Scrum and CMMI Level 5: The Magic Potion for Code Warriors
Scrum and CMMI Level 5: The Magic Potion for Code Warriors Jeff Sutherland, Ph.D. Patientkeeper Inc. [email protected] Carsten Ruseng Jakobsen Systematic Software Engineering [email protected]
Agile So)ware Development
Software Engineering Agile So)ware Development 1 Rapid software development Rapid development and delivery is now often the most important requirement for software systems Businesses operate in a fast
Transitioning from Waterfall to Agile Course AG01; 3 Days, Instructor-led
Transitioning from Waterfall to Agile Course AG01; 3 Days, Instructor-led Course Description Identify the challenges you will face when implementing an Agile approach to software development and then plan
Agile Project Management and Agile Practices Training; with a Scrum Project that you will do.
1 PMI Agile Certified Practitioner (PMI-ACP) workshop course details. We are unique and specialists in Agile! Your workshop trainer by passion and is a senior Agile Coach who coached many teams and Kanban
Topics covered. Agile methods Plan-driven and agile development Extreme programming Agile project management Scaling agile methods
Topics covered Chapter 3 Agile Software Development Agile methods Plan-driven and agile Extreme programming Agile project management Scaling agile methods 1 2 Need for rapid software Rapid software Changing
Agile Software Development
Agile Software Development Use case for Agile Software Development Methodology in an Oil and Gas Exploration environment. White Paper Introduction No matter what business you are in, there are critical
Scrum Is Not Just for Software
Scrum Is Not Just for Software A real-life application of Scrum outside IT. Robbie Mac Iver 2/9/2009. Agile methods like Scrum can be applied to any project effort to deliver improved results in ever evolving
CSPO Learning Objectives Preamble. Scrum Basics
CSPO Learning Objectives Preamble This document contains topics for the Certified Scrum Product Owner (CSPO) training course. The purpose of this document is to describe the minimum set of concepts and
Rolling Wave Planning: Manage Projects Without Going Under
Rolling Wave Planning: Manage Projects Without Going Under Rolling Wave Planning: Manage Projects Without Going Under W. Charles Slaven MBA PMP CSSBB CPA (inactive) Director, Lean Deployment and Continuous
Agile Projects 7. Agile Project Management 21
Contents Contents 1 2 3 Agile Projects 7 Introduction 8 About the Book 9 The Problems 10 The Agile Manifesto 12 Agile Approach 14 The Benefits 16 Project Components 18 Summary 20 Agile Project Management
METRICS DRIVEN CONTINUAL SERVICE IMPROVEMENT USING AGILE CONCEPTS
METRICS DRIVEN CONTINUAL SERVICE IMPROVEMENT USING AGILE CONCEPTS John Osteen B Cognizant Business Consulting Process Quality Consulting Cognizant Technology Solutions, Chennai, India [email protected]
Frank Cervone Vice Chancellor for Information Services and Chief Information Officer Purdue University Calumet January 17, 2012 CARLI Anatomy of a
Frank Cervone Vice Chancellor for Information Services and Chief Information Officer Purdue University Calumet January 17, 2012 CARLI Anatomy of a Digital Project webinar series An overview and background
Applying Lean on Agile Scrum Development Methodology
ISSN:2320-0790 Applying Lean on Agile Scrum Development Methodology SurendRaj Dharmapal, Dr. K. Thirunadana Sikamani Department of Computer Science, St. Peter University St. Peter s College of Engineering
Improving Project Governance Using Agile and Metrics. Kevin Aguanno PMP, IPMA-B, MAPM, Cert.APM
Improving Project Governance Using Agile and Metrics Kevin Aguanno PMP, IPMA-B, MAPM, Cert.APM Your Presenter: Kevin Aguanno 20+ years of PM experience 20+ published books, audiobooks, DVDs, and CD-ROMs
Adapting Agile Software Development to Regulated Industry. Paul Buckley Section 706 Section Event June 16, 2015
Adapting Agile Software Development to Regulated Industry Paul Buckley Section 706 Section Event June 16, 2015 Agenda FDA s expectations for Software Development What is Agile development? Aligning Agile
The 2015 State of Scrum Report. How the world is successfully applying the most popular Agile approach to projects
The 2015 State of Scrum Report How the world is successfully applying the most popular Agile approach to projects RELEASED: JULY 2015 EXECUTIVE SUMMARY In February 2015, Scrum Alliance surveyed almost
Transitioning from Waterfall: The Benefits of Becoming Agile. ASPE Web Seminar Friday, February 27 th, 2015
Transitioning from Waterfall: The Benefits of Becoming Agile ASPE Web Seminar Friday, February 27 th, 2015 Objectives Give a high-level look at the challenges in software development Give a basic look
Agile & PMI Project Management Mapping MAVERIC S POINT OF VIEW. 10-10-2012 Vol. 7
10-10-2012 Vol. 7 MAVERIC S POINT OF VIEW Agile & Abstract: The purpose of this whitepaper is to explore the points of parity and differences between two of the most widely used methodologies. PMI Management
"Bezpieczny Projekt"
Konferencja "Bezpieczny Projekt" Wrocław 22 czerwca 2010 www.omec.pl Software Development with Agile SCRUM Chandrashekhar Kachole 22 nd of June 2010 1 Let s keep the cell phones in Silent mode 2 Agenda
Practical Agile Requirements Engineering
Defense, Space & Security Lean-Agile Software Practical Agile Requirements Engineering Presented to the 13 th Annual Systems Engineering Conference 10/25/2010 10/28/2010 Hyatt Regency Mission Bay, San
Introduction to Agile Software Development
Introduction to Agile Software Development Word Association Write down the first word or phrase that pops in your head when you hear: Extreme Programming (XP) Team (or Personal) Software Process (TSP/PSP)
Agile QA s Revolutionary Impact on Project Management
Agile QA s Revolutionary Impact on Project Management Introduction & Agenda Rachele Maurer Agile Coach, Platinum Edge Inc. PMP, CSM, PMI-ACP Agenda A quick overview of agile Current QA practices QA using
No one has to change. Survival is optional. - W. Edwards Deming - Continue your Beyond Budgeting Journey with help from Agile, Lean and Scrum
No one has to change. Survival is optional. - W. Edwards Deming - Continue your Beyond Budgeting Journey with help from Agile, Lean and Helge Eikeland, Statoil, October 2010 Today s challenge is complexity
History of Agile Methods
Agile Development Methods: Philosophy and Practice CPSC 315 Programming Studio Fall 2010 History of Agile Methods Particularly in 1990s, some developers reacted against traditional heavyweight software
Comparative Study of Agile Methods and Their Comparison with Heavyweight Methods in Indian Organizations
International Journal of Recent Research and Review, Vol. VI, June 2013 Comparative Study of Agile Methods and Their Comparison with Heavyweight Methods in Indian Organizations Uma Kumari 1, Abhay Upadhyaya
ACP Exam Prep Plus Desk Reference including the Project Management Agile Body of Knowledge TM (PMABOK TM )
ACP Exam Prep Plus Desk Reference including the Project Management Agile Body of Knowledge TM (PMABOK TM ) Contents Homework Assignment for 2 PDUs... 1 Chapter Close-Out... 2 Terminology Matching Exercise...
Agile Project Management. What it is and what it isn t
Agile Project Management What it is and what it isn t Moderator Janelle Abaoag Project Insight Marketing, Public Relations [email protected] www.projectinsight.net All participants will
Water-Scrum-Fall Agile Reality for Large Organisations. By Manav Mehan Principal Agile consultant [email protected]
Water-Scrum-Fall Agile Reality for Large Organisations By Manav Mehan Principal Agile consultant [email protected] Interests and Experience Leading Change and Transformation in Large, Complex organisations
Getting Agile with Scrum. Mike Cohn - background
Getting Agile with Scrum Mike Cohn Mountain Goat Software [email protected] 1 Mike Cohn - background 2 We re losing the relay race The relay race approach to product development may conflict
Agile Notetaker & Scrum Reference. Designed by Axosoft, the creators of OnTime the #1 selling scrum software.
Agile Notetaker & Scrum Reference Designed by Axosoft, the creators of OnTime the #1 selling scrum software. Scrum Diagram: Team Roles: roduct Owner: Is responsible for what goes into the product backlog
Agile Contracts. NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant - RefineM. Agenda
Agile Contracts NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant - RefineM Agenda 1. Your Expectations from this Presentation 2. Introduction Myself 3. Agile Contracts a. Overview of Agile and Contracts
AGILE & SCRUM. Revised 9/29/2015
AGILE & SCRUM Revised 9/29/2015 This Page Intentionally Left Blank Table of Contents Scrum Fundamentals Certified Course... 1 Scrum Developer Certified (SDC)... 2 Scrum Master Certified (SMC)... 3 Scrum
What is Scrum? Scrum Roles. A lean approach to software development. A simple framework. A time-tested process
What is Scrum? From http://www.scrumalliance.org/pages/what_is_scrum A lean approach to software development Scrum is an agile software development framework. Work is structured in cycles of work called
A Glossary of Scrum / Agile Terms
A Glossary of Scrum / Agile Terms Acceptance Criteria: Details that indicate the scope of a user story and help the team and product owner determine done-ness. Agile: the name coined for the wider set
What does it mean to be Agile. Marek Majchrzak, Andrzej Bednarz Wrocław, 11.10.2011
What does it mean to be Agile Marek Majchrzak, Andrzej Bednarz Wrocław, 11.10.2011 2 Traditional methods Assumptions: The customer knows what he wants The developers know how to build it Nothing will change
Agile Certification: PMI-ACP
Agile Certification: PMI-ACP Agenda What is PMI-ACP? Should I get certified? Contrast ACP to PMP Prerequisites Exam Content What to focus on? How to prepare? Resources Merits or demerits of certifications
CSE 435 Software Engineering. Sept 16, 2015
CSE 435 Software Engineering Sept 16, 2015 2.1 The Meaning of Process A process: a series of steps involving activities, constraints, and resources that produce an intended output of some kind A process
Agile Project. Management FOR DUMME&* by Mark C. Layton WILEY. John Wiley & Sons, Inc.
Agile Project Management FOR DUMME&* by Mark C. Layton WILEY John Wiley & Sons, Inc. Table of Contents»#» « Introduction / About This Book 1 Foolish Assumptions 1 Conventions Used in This Book 2 How This
Waterfall vs. Agile Project Management
Lisa Sieverts, PMP, PMI-ACP Phil Ailes, PMI-ACP Agenda What is a Project Overview Traditional Project Management Agile Project Management The Differences Product Life Cycle The Teams Requirements WBS/Product
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Introduction to Agile and Scrum
Introduction to Agile and Scrum Bob Schommer, CSP, PMP, MCTS Senior Project Manager Skyline Technologies, Inc. PMI Northeast Wisconsin Chapter May 3, 2011 About Skyline Technologies Microsoft Gold Certified
Lasting commercial success with Agile Evolution
Turning visions into business December 2011 Lasting commercial success with Agile Evolution Malte Foegen, David Croome, Timo Foegen Scrum techniques are spreading increasingly. In many cases, they lead
The Agile PMO. Contents. Kevin Thompson, Ph.D., PMP, CSP Agile Practice Lead cprime, Inc. 4100 E. Third Avenue, Suite 205 Foster City, CA 94404
The Agile PMO Kevin Thompson, Ph.D., PMP, CSP Agile Practice Lead cprime, Inc. 4100 E. Third Avenue, Suite 205 Foster City, CA 94404 [email protected] Abstract The development of Agile processes
Scrum for Managers, Zurich March 2010
Scrum for Managers Microsoft Corporation / TechTalk Zurich Switzerland March 2010 About Mitch Lacey Mitch Lacey 13+ years of program and project management experience Microsoft Program Manager 2001 2006
Making Sense of. Agile Project Management. Traditional. Project Management. 1/19/2011 2010 Breakthrough Solutions, Inc. 1
Making Sense of Agile Project Management Agile Project Management Traditional Project Management 1/19/2011 2010 Breakthrough Solutions, Inc. 1 My View of Project Management Today Subject Matter Knowledge