1 Best practice guidance for tendering to win business in UK civil nuclear supply chains Prepared by Evan Wright, Consultant, EOSCP INTRODUCTION Part 1 General Tendering Advice 1.1 Pre proposal/tender activities Market and Customer Intelligence Receiving the ITT 1.2 Preparing the proposal/tender Structure and scheduling the tender Ensuring compliance with the tender s online, structures and size Graphics and photographs Winning themes Establish the technical baseline offer Making your disadvantages positives Pricing strategy Review and company sign off 1.3 Executive summary & covering letter Executive summary Covering letters 1.4 Publication of the Tender Plan ahead 1.5 Tender submission 1.6 post submission actions Presentations and questions 1.7 Customer feedback Part 2 Specific advice for tendering to Tier 2 contractors 2.1 Introduction 2.2 Tier 2 tender environments 2.3 Tender timescales 2.4 Tender process Part 3 Top tips for successful tendering

2 Introduction The UK nuclear industry, including operation, decommissioning and future new build activities, offers major high-value opportunities for engineering and design businesses. To be successful in this very competitive sector, winning companies need to write first-class tenders. This document gives best practice guidance for tendering for nuclear supply chain work and is based on experience gained over many years of bid writing and evaluation by nuclear industry specialists. Advice given is 'high-level' and is not a precise step-by-step guide for writing a tender. Who is the guidance for? SMEs tendering for sub-contracts to either Tier 1 site licence companies (e.g. Sellafield Ltd) or Tier 2 management contractors within the nuclear industry (e.g. Doosan Babcock, Amec, Jacobs etc). Suitable for both new entrants and experienced contractors. Suitable for non-nuclear work in other high-integrity sectors such as oil & gas and pharmaceutical. Some definitions... A Tier 1 company is a nuclear site licence company such as Sellafield Ltd and Magnox North and South. A Tier 2 company is any company that tenders directly to a Tier 1 company. In the context of this document Tier 2 companies are regarded as large management companies such as Amec, Doosan Babcock and Jacobs. A Tier 3 company subcontracts to a Tier 2. Guidance is given in two parts: Part 1 covers general tendering advice and Part 2 covers specific advice for tendering into nuclear Tier 2 organisations. Whilst of fundamental importance to successful tendering, the document does not cover pricing and risk in detail. It is recommended that before reading this document, the reader first reads the EOSCP document 'UK nuclear market opportunities', available via This document explains the fundamentals of the commercial structure of the industry and outlines business development strategies for SMEs in the sector. We update this guidance (Jan 2011) with kind permission of TWI. It was originally produced in 2009 as part of the Northwest Supply Chain project (NWSC), funded by the North West Development Agency (NWDA). We have endevoured to be as accurate and up to date as possible. Please check with the WCDA s Energy Opportunities Supply Chain Project (EOSCP) if you have any questions. Learn more at Acknowledgements We are grateful to Mark Watters (Nuclear Director, Cumbria of Doosan Babcock), Tony Lawrence (Relationship Manager, Amec), Zoe Whittle (Supply Chain Ombudsman of Sellafield Ltd) and Sam Dancy (Market Development Manager of the Nuclear Decommissioning Authority) for their valuable contributions to this document.

3 Part 1 - General tendering advice This document is primarily aimed at companies tendering into Tier 2 organizations for significant subcontracts within large projects, for which the Tier 2's are themselves tendering. Typically Tier 2's will be tendering for project contracts in the order of 1m to 250m. However, the principles outlined in the guidance can be applied to the preparation of any tender. 1.1 Pre proposal/tender activities It's assumed that your company has decided its strategy to tender for contracts in the nuclear sector and that you fully understand why you want to do it and the commitments required to win business Market and customer intelligence Tender submission timescales are generally tight, therefore in advance of the Request for Quotation (RFQ) or Invitation to Tender (ITT), it is important to find out what opportunities are coming to market, when and what their scope will be, and how it fits into the customer's business. Also, find out as much relevant information as you can about the customer and your competition. You can do this by attending trade events and arranging one to one meetings with buyers. You will gain an understanding of the customer's general requirements and those specific to the opportunity you are considering. For a specific contract opportunity find out... Is the customer confident about award timescales? How strong is the competition? Where do you fit in the competition? Be honest! Where does the customer think you fit in with the competition? What is the scope of work? Think about how you will provide it in a better way than the competition. Will you need to team with another organisation? If so, understand why and build your partnership early before someone else beats you to it, and then demand their full commitment 1. 1 Guidance on best practice in partnering can be found in PAS 11000:2006. This is a strategic framework to improve collaborative relationships in organisations of all sizes. Go to for more information.

4 1.1.2 Receiving the ITT The ITT may be preceded by a request for prequalification. If so, treat this like a tender but also as an opportunity to communicate with the customer about the subsequent contract. If you have gathered your intelligence and communicated with the customer, the receipt of the ITT should not be a surprise. If it is a surprise then you may be in a weak position compared with better prepared competitors. Always acknowledge receipt of the ITT. To bid or not to bid? This seems obvious but you need to ask yourself some hard questions. Bid preparation is time and resource-intensive. Honestly compare your capability and competitive position with the opportunity, customer and competition. Estimate what it will cost you to win the bid and decide if this is good business. Decide 'Bid - No Bid'. Only bid if you have a realistic chance of winning if the opportunity is real and will make you an acceptable return. If you decide NOT to bid Tell the customer and explain why Don't burn your bridges! For example, if you have capability gaps, tell the customer what they are and say how you will rectify this for future tenders Ask for a meeting and seek advice about what you need to change in your organisation or strategy to win business in future. If you decide TO bid Assign proposal responsibilities, such as who will lead and write each tender section, e.g. technical offer, safety approach, pricing, commercial terms and delivery schedule Consider who will type, print, bind and despatch the tender Understand the customer's evaluation criteria and weighting. Then put most effort into those aspects of your tender where you will get most reward. Remember though, the whole of your tender responses must excel!

5 1.2 Preparing the proposal/tender Structure and scheduling the tender Using storyboarding to structure a tender Storyboarding is a proven technique used to structure tenders and to ensure compliance with the ITT. Storyboarding is a group activity facilitated for the bid team by the bid manager. Storyboarding is done in a room where there is wall space to post the pages so all involved can refer to them as the storyboard and tender develop. The bid team brainstorm, debate, agree and record on flip chart pages the key points that need to be communicated in each section of the tender. Using storyboard ensures that the tender's messages are consistent across all the sections of the bid. Ensure that senior managers buy into the storyboard, particularly those that will be asked to sign the final tender. Regularly check the bid team understands the storyboard. You should produce a simple tender programme showing what, who and when. Work back from the submission date and include partner contributions, then communicate key dates to all people that are involved in writing or approving the tender. Producing a tender is a project in itself with duration, cost, deliverables and, not least, people to manage. The leader (sometimes called bid manager) is in reality a project manager. To help you to manage the tender preparation, consider producing a project plan similar to the one below.

6 Sample project plan Preparation & submission of tender Who? : Analyse bid, define offering & engage partners JPJ Analyse bid as lead organisation Identify and engage partners Define bid offering and partnership roles Assign bid writing roles & responsibilities 2: Write bid, cost & price the tender EMW Write technical offer Write safety approach Write quality approach Estimate cost Set price Define commercial terms Write executive summary and winning themes Bid review and final modification 3. Assemble and submit bid NME Type up bid Print and bind bid copies Get bid signed off Despatch to client Depending upon the scale and complexity of the opportunity be prepared for long hours of smart working (otherwise don't bid, because you won't win)

7 1.2.2 Ensuring compliance with the tender's outline, structure and size Prepare a compliance matrix to list all the things the customer wants to see responses to, for example CVs Price schedule Management structure Key staff Track record Your understanding of the scope Your technical approach to deliver the scope Innovations Safety record Insurances Risks Exclusions Tick them off the list after you have included in your tender the detail required by the customer. If the ITT includes returnable schedules, ensure these are completed, signed by the appropriate person and included with the tender. Structure your tender responses as instructed in the ITT, or if there is no instruction by the customer, it is sensible to structure it in the same order and using the same headings as those used by the customer in their ITT. Evaluation criteria are often published in ITT's by customers. Make it easy for the assessors to find information in your tender which demonstrates your capability linked to these criteria. The tender should have an executive summary which summarises its content and its winning themes (see section 1.3). Each section of your tender response should have an introduction, body of information and conclusion and include one or two relevant winning themes. If the ITT specifies a page or word limit per section and or page, stick within it Graphics and photographs Where possible use relevant tables, graphs, pie charts etc and photographs to relay information. The golden rule, to maintain the interest of the reader (who awards the contract) is to aim for 1/3 white space 1/3 graphics and 1/3 text on each page.

8 Graphics and photographs can be powerful in communicating information. For example, if you have five years of safety awards, scan and reduce these and put them all on one page in the safety section of the tender. Similarly, include in appropriate sections relevant accreditations and professional body memberships such as Investors in People awards and ISO 9001:2000. Draw pie charts to show, for example, the proportion of staff you have in each discipline or trade and use captions like 'we can fully resource this contract with the right people.' See the example below. Similar charts could be used to communicate information about the type of equipment you have or the breakdown of your business turnover by sector. In all cases only communicate relevant information to help enable the customer to select you Winning themes The most important question to answer in the tender is WHY select US? Winning themes support this. What is a winning theme? A supported claim. An advantage compared to a competitor. A compelling argument. A conclusive reason why the customer should select you. Six winning themes are a sensible number. Include one or two technical capability themes, one or two management capability themes and one or two safety themes. Also consider track record and commercial themes. Example winning themes 'We are the only UK contractors that have done this type of work before'. 'Our safety record in this industry has been recognised by five gold awards'. 'Our manufacturing facilities and procedures demonstrate performance in excess of the ITT requirements'. 'Our programme duration reflects low risk linked to our experience to apply alternative methods if problems arise'. 'Our local labour force can rapidly mobilise'.

9 1.2.5 Establish the technical baseline offer Decide what you are offering at the outset of the tender and don't chop and change during tender preparation. If you do change your offering, rigorously control technical change and ensure it is accounted for in your commercial offer. Be careful you don't over engineer and add cost. Establish whether the work is on or off-nuclear site. The time periods required for gaining access to a nuclear site are longer than you may be used to with other customers, and the amount of administration and documentation is more than for non-nuclear customers' sites Making your disadvantages positives There may be weak areas of your bid that you need to mitigate. If you have no nuclear experience, counteract this by stressing your experience in other industries with similar quality and technical standards, using wording such as 'We are the leading contractor of choice in the petrochemical industry for this type of work and have completed [xxx] projects. We will bring this experience to the nuclear industry where similar high standards are required and which will be met by us.' If your last contract was delivered late or fell short technically you should highlight how you have learnt from the experience, using wording such as 'Our programme and cost schedules are underpinned by the lessons we have learnt during project [xxx] and we have confidence that the changes we have made will enable us to deliver on time and within budget' Pricing strategy The NWSC project does not offer specific assistance with commercial aspects of tendering. However, competitive pricing, risk, exclusions and value for money may be the overriding factors in the customer's decision to place a contract with you. This will often be the case if all other aspects of your tender are equal to the competition.

10 1.2.8 Review and company sign off Review Depending upon the size of your company you will be likely to have different procedures for review and sign off, but be aware that the two things are different. Appoint someone or a team who has not been involved in your tender preparation to review it as if they are the customer. Make appropriate change but allow enough time in the tender programme for this activity and follow-on actions, which is sometimes called a 'Red Review'. Sign off A duly appointed person within your company will need to sign off the tender. While it is being written, keep this person informed of progress, developing cost estimates and the risks. Don't leave sign off until the last minute, otherwise if the signatory queries any aspect of the tender, you could be working all night to incorporate their changes and, inevitably, mistakes will be made. 1.3 Executive summary & covering letter Executive summary An executive summary is intended to help the reader understand the context and structure of the whole tender. It is aimed at the buyer's senior executives who don't have time to read the whole tender. What should and shouldn't be in the executive summary? It should contain all the winning themes. It should be a true summary of the tender. It should be concise. It should follow the same structure as the tender. It should guide the reader to the relevant main sections in the tender. It should not contain any information that is not explicit in the main body of the tender Covering letter

11 This is a business letter of no more than one page to thank the customer for the opportunity to tender. It should provide assurances from the senior signatory, that the customer's requirements will be met in an efficient and effective manner. 1.4 Publication of the Tender Plan ahead Tenders for large contracts with complex scope and site works elements can be large documents. Customers, particularly Tier 1's, often require multiple paper copies, plus an original signed copy and electronic copies. Be clear about what they have requested and have ready the required stationery, such as binders, quality paper, discs and equipment. Don't run out of ink at midnight and expect to punch holes in 200 sheets in five minutes with a one sheet punch! For a large tender, have enough people on hand to do the collation and binding. Include a simple index page. Have a box or boxes to hand, and package and label the tender in accordance with the instructions to tenderers. 1.5 Tender submission The main concern is to submit the proposal on time. Be sure that you know what this date and time is. If practicable take the tender by hand to the person named in the ITT as the recipient. If this cannot be done, use a reliable guaranteed delivery method. 1.6 Post submission actions Presentations and questions The customer may require you to present your tender or answer written questions. Take as much care with this as with the primary tender. After short listing of bidders, customers will often base their choice on what is explained in the presentation or offered as answers to questions. Customers will sometimes use this opportunity not just to clarify your tender but to add scope and or reduce your price and their risk. If this is the case, then to make decisions, you will need good market intelligence and the same level of expert commercial advice which was applied to the content of the tender.

12 1.7 Customer feedback Whether or not your tender is successful, seek feedback from the customer at a meeting. Send someone who understands your business and the tender but try to avoid sending anyone who prepared the tender. Note the positive and negative comments and use the information to improve future tenders. This can be an excellent opportunity to build customer confidence in your organisation. Part 2 - Specific advice for tendering to Tier 2 contractors 2.1 Introduction Large Tier 2 organisations are those who tender for nuclear site prime contracts such as AMEC, Doosan Babcock, Nuvia, Costain, Jacobs and Redhall Group. Their requirements from the Tier 3 supply chain flow down from Tier 1 requirements and for Tier 3 SME's that are unfamiliar with nuclear work these can be daunting. For this reason it is sensible to establish relationships early with Tier 2 organisations and seek to be included on their approved supplier lists as early as possible before actual tenders are required from you. 2.2 Tier 2 tender environments Large UK nuclear contracts let to Tier 2 organisations typically include 30% work for subcontracts. The Tier 2 company will be under time pressure from the primary Tier 1 customer, but will need to fully understand the scope of work, produce a Work Breakdown Structure (WBS) and coordinate and write sub contract specifications and enquiries before inviting Tier 3 sub contractors to tender. Sub contract tenders will be needed by the Tier 2 well in advance of the primary customer's return date so that the Tier 2 can evaluate and co ordinate responses and build these into his overall tender. For these reasons the time available to the sub contractor to produce a sub contract tender can be very short.

13 The Tier 2, ought to produce sub contract tender packages for you which will enable compliance with Tier 1 needs. In return you will be expected to produce a tender which is compliant and right first time. Tips for a successful relationship with your Tier 2 company The Tier 2 will be under severe pressure to deliver the primary tender to the Tier 1 customer, so react quickly to their ITT. They are your customer and they will not look kindly upon incomplete or late submissions from you. Seek regular meetings during your tender period. Be as flexible as you can be without compromising your own business. Be aware that their scope, technical solution and commercial strategies may change during the tender period. Help them to manage the effect of this on you. 2.3 Tender timescales Typically a Tier 1 contract tender period is 8 weeks. The Tier 2 contractor will need to spend about 2 weeks setting strategy and preparing sub contract packages, about 4 weeks to produce the tender and 2 weeks to review and gain internal approvals. It is a high pressure environment for all. As a Tier 3 sub contractor you may only have three weeks to prepare and submit your sub contract tender. Careful planning and project management, as described in section 3, is vital. 2.4 Tender process The more that you can prepare in advance the less pressure you will be under! In advance of the Tier 2 ITT you will need to... Decide if you will sign an exclusivity agreement and non disclosure agreement. Have to hand QA accreditations. Have to hand health and safety statistics and performance. Have to hand insurances and, if required, a broker to quote for any top ups. Have proof of relevant commercial track record, such as working for demanding customers in nuclear, oil & gas and other high-integrity industries. Have to hand CV's, training and SQEP (Suitably Qualified & Experienced Personnel) records of staff. Have references from similar customers for similar work. Have a good understanding of your cost base and price structure.

14 ...and the Tier 2 company will require from you... A competitive quote. Concise answers to all questions in electronic format which can be edited, copied and pasted into the primary tender document using native format. Well written company capability sheets using graphics and photos. A detailed schedule and cost break down in accordance with the WBS. Any assumptions and exclusions listed clearly. All certificates and accreditations in electronic format. Risks clearly identified and quantified, if possible. Answers to all questions - these are likely to be cut and pasted into the primary tender. Accountability. You and your Tier 2 customer will need to be able to trust each other. You should meet them during the tender period to Play back the scope of your work to fully understanding what is required Suggest ideas and innovations Honestly appraise your capability Build relationships Understand their drivers, constraints and internal processes. From the Tier 2 company, expect Fair and reasonable terms and conditions Clear instructions Real opportunities and not price checks. This might not always be the case, but industry bodies, led by NDA, are working to establish common principles for supply chain interaction. For further information, go to When you have won the sub contract, serve them well and seek long term relationships.

15 Part 3 - Top tips for successful tendering Comply with all reasonable requests from the client. Provide information and answers to questions in full and in formats required. Submit a compliant bid. If necessary, be clear about any technical and commercial assumptions and/or exclusions. Don't 'hide' them and put them in one place. In the post-bid, negotiation phase, avoid introducing changes not covered in your bid as the bid could rapidly become non-compliant. Don't assume that the client's past experience of you is a substitute for answering questions - often the client can only use the information presented. Always provide examples and evidence to support answers. Accept that there may be frustrations in working in the environment your client works in. Seek ways in your bid to illustrate your knowledge and understanding of the client's working environment. Look at information provided by your client e.g. web sites, procurement plans. Providing unrequested information can be frustrating for the client and may be seen as 'padding'. Accept that some requirements flow down from the client's customer. Balance selling your company in the tender with detail of what is going to be delivered and how it will be done. If you have no nuclear experience, counteract this by stressing work you have done in similarly regulated, controlled and hazardous environments and industries. Draw parallels with the nuclear industry. When invited to present the tender by the client, use this as an opportunity to explain a written answer in more detail. Stick to what is required (as this is what is of real interest) and don't 'pad' the presentation out with information not requested. Answer any Requests for Clarification in full - don't restate what you have already written in your tender. Requests for clarification are made for a reason; the original answer wasn't adequate.

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information

Delivering progress towards meeting HMG targets on the SME growth agenda

Delivering progress towards meeting HMG targets on the SME growth agenda Delivering progress towards meeting HMG targets on the SME growth agenda Action Plan Version 1.1 dated 16 th August 2013 Author: Robert Astall, Head of Commercial Profession and Capability Background The

More information

How to do Business with the London. Borough of Sutton

How to do Business with the London. Borough of Sutton How to do Business with the London Borough of Sutton February 2013 1 About this guide This guide has been developed to assist businesses wishing to sell their goods and services to the Borough. Contents

More information

Top Tips for Successful Tendering

Top Tips for Successful Tendering June 2012 Successful Tendering Guide Top Tips for Successful Tendering Contents Is your business ready? 1 Be prepared 2 Bid or No Bid 4 Prepare a bid plan 5 Focus on what the Buyer wants 6 Pricing 7 Prepare

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

The SME Engagement Handbook

The SME Engagement Handbook The SME Engagement Handbook The purpose of this document is to help microbusinesses and small to medium enterprises ( SMEs ) interact more effectively when bidding to supply goods or services to larger

More information

How to Do Business with the Scottish Ambulance Service

How to Do Business with the Scottish Ambulance Service How to Do Business with the Scottish Ambulance Service March 2015 How to do business with the Scottish Ambulance Service A Guide for Suppliers Overview This guide is to provide practical help for suppliers,

More information

Invitation to Quote (ITQ) for STREET WORKS IT SOLUTION

Invitation to Quote (ITQ) for STREET WORKS IT SOLUTION Easthampstead House, Town Square, Bracknell, Berkshire RG12 1AQ Tel: (01344) 352000 Invitation to Quote (ITQ) for STREET WORKS IT SOLUTION xxx COMPLETED BY ORGANISATION [Supplier to complete] NAME DATE

More information

Contracts, agreements and tendering

Contracts, agreements and tendering Contracts, agreements and tendering 1) Introduction This guidance note provides an overview of the types of contracts and other agreements you might need to use in setting up and running a local energy

More information

BSB41513 Certificate IV in Project Management Practice

BSB41513 Certificate IV in Project Management Practice RPL Assessment Tool Kit AUSTRALIAN SALESMASTERS TRAINING CO RPL Assessment Tool Kit BSB41513 Certificate IV in Project Management Practice Page 1 of 126 BSB415137 Certificate IV in Project Management Practice

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

TENDER SPECIFICATION DOCUMENT WEST MIDLANDS INTERNATIONAL TRADE LLP MARKETING FILMS ON EXPORTING AND GOVERNMENT SUPPORT 14/15 15/16

TENDER SPECIFICATION DOCUMENT WEST MIDLANDS INTERNATIONAL TRADE LLP MARKETING FILMS ON EXPORTING AND GOVERNMENT SUPPORT 14/15 15/16 TENDER SPECIFICATION DOCUMENT WEST MIDLANDS INTERNATIONAL TRADE LLP MARKETING FILMS ON EXPORTING AND GOVERNMENT SUPPORT 14/15 15/16 Tender for the Supply of Film Production Date: March 2015 West Midlands

More information

Tendering to Public Sector Organisations

Tendering to Public Sector Organisations Tendering to Public Sector Organisations Introduction Authorities have to meet contract regulations and must ensure they provide equal opportunity and achieve the best value for money. Other factors include

More information

Writing a business plan

Writing a business plan Writing a business plan Many potential start-up businesses are daunted by the prospect of writing a business plan. But it is not a difficult process - and a good business plan focuses the mind as well

More information

Demonstrate and apply knowledge of project management in

Demonstrate and apply knowledge of project management in Demonstrate and apply knowledge of project management in mechanical engineering 22918 version 2 Page 1 of 5 Level 6 Credits 15 Purpose This unit standard is intended primarily for use in diploma courses

More information

Volunteer Managers National Occupational Standards

Volunteer Managers National Occupational Standards Volunteer Managers National Occupational Standards Contents 00 Forward 00 Section 1 Introduction 00 Who are these standards for? 00 Why should you use them? 00 How can you use them? 00 What s in a Standard?

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

SUPPLY CHAIN CODE OF PRACTICE. Streamlining processes and increasing value for the oil and gas industry

SUPPLY CHAIN CODE OF PRACTICE. Streamlining processes and increasing value for the oil and gas industry SUPPLY CHAIN CODE OF PRACTICE Streamlining processes and increasing value for the oil and gas industry About The Supply Chain Code of Practice The Supply Chain Code of Practice (SCCoP) outlines a set

More information

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...

More information

A COMPARISON OF PRINCE2 AGAINST PMBOK

A COMPARISON OF PRINCE2 AGAINST PMBOK Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

The Small Business Friendly Concordat. A statement of principles for Basingstoke and Deane Borough Council

The Small Business Friendly Concordat. A statement of principles for Basingstoke and Deane Borough Council The Small Business Friendly Concordat A statement of principles for Basingstoke and Deane Borough Council Declaration of Support for the Small Business Friendly Concordat Basingstoke and Deane Borough

More information

Health Informatics Service Accreditation Manual. Assessment Process. May 2013, Version 1

Health Informatics Service Accreditation Manual. Assessment Process. May 2013, Version 1 Health Informatics Service Accreditation Manual Assessment Process May 2013, Version 1 Contents 1. Contacts... 2 2. Introduction... 3 3. Assessment principles... 6 4. Assessment outcome... 7 5. Planning

More information

Aggregation. Is bigger always better?

Aggregation. Is bigger always better? Aggregation Is bigger always better? Contents Purpose of this guidance 1 What is aggregation? 2 When should aggregation be considered? 4 Why use aggregation? 6 Some practical considerations 8 Further reading

More information

ISO 14001 Environmental Management It s your responsibility. Your implementation guide

ISO 14001 Environmental Management It s your responsibility. Your implementation guide ISO 14001 Environmental Management It s your responsibility Your implementation guide ISO 14001 - Environmental Management Background ISO 14001 is the internationally recognized standard for successful

More information

To join Achilles UVDB, visit www.achilles.com/uvdb, call +44 (0)1235 861118 or email [email protected]

To join Achilles UVDB, visit www.achilles.com/uvdb, call +44 (0)1235 861118 or email enquiries@achilles.com UVDB Achilles UVDB FAQ s About Achilles UVDB What is the Achilles UVDB Supplier Information Management Service? Achilles UVDB is the community for the UK utilities industry. It enables the utilities sector

More information

National Occupational Standards. Compliance

National Occupational Standards. Compliance National Occupational Standards Compliance NOTES ABOUT NATIONAL OCCUPATIONAL STANDARDS What are National Occupational Standards, and why should you use them? National Occupational Standards (NOS) are statements

More information

Supply Chain Guide Working together in partnership

Supply Chain Guide Working together in partnership CASE STUDIES Plan Smart, Deliver Lean Supply Chain Guide Working together in partnership Background to the ISA The Infrastructure Strategic Alliance (ISA) provides a site wide consistent approach to the

More information

HOW MUCH MONEY HAVE YOU WASTED ON G-CLOUD?

HOW MUCH MONEY HAVE YOU WASTED ON G-CLOUD? Winning on G-Cloud & The Digital Marketplace 6 TIPS FROM SUCCESSFUL SUPPLIERS HOW MUCH MONEY HAVE YOU WASTED ON G-CLOUD? As of 2 February, there were a total of 1,852 suppliers registered on the G-Cloud

More information

Joint Bidding Guide. 9. Opportunity Assessment. prepared for Leaders of Potential Consortia and Bid Managers

Joint Bidding Guide. 9. Opportunity Assessment. prepared for Leaders of Potential Consortia and Bid Managers Joint Bidding Guide 9. Opportunity Assessment prepared for Leaders of Potential Consortia and Bid Managers Figure 1.1 The Joint Bidding Cycle Key Chapter for Both Sides 1. Introduction Chapter for Supply

More information

IMPROVING DELIVERY PROCUREMENT AND SUPPLY CHAIN MANAGEMENT

IMPROVING DELIVERY PROCUREMENT AND SUPPLY CHAIN MANAGEMENT PROCUREMENT AND SUPPLY CHAIN MANAGEMENT We support customers to select and motivate their suppliers setting the standards for both behaviour and performance Confederation of British Industry Doing more

More information

Project Management. From small self contained projects through to major change projects. Brought to you by Project Agency www.projectagency.co.

Project Management. From small self contained projects through to major change projects. Brought to you by Project Agency www.projectagency.co. Solutions * Ideas * Tips Project Management From small self contained projects through to major change projects Solutions * Ideas * Tips Brought to you by Project Agency www.projectagency.co.uk Why Write

More information

Chartered Engineer. Go back to www.iop.org to choose an alternative status. Write your professional review report

Chartered Engineer. Go back to www.iop.org to choose an alternative status. Write your professional review report Chartered Engineer Start your journey Chartered Engineers are characterised by their ability to develop appropriate solutions to engineering problems, using new or existing technologies, through innovation,

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required

More information

Airmic review of the supply chain insurance market Review of recent developments in the supply chain insurance market

Airmic review of the supply chain insurance market Review of recent developments in the supply chain insurance market REPORT Airmic review of the supply chain insurance market Review of recent developments in the supply chain insurance market 1. Executive summary Increasingly complex supply chains, together with greater

More information

A PASSION FOR QUALITY A QUEST FOR PERFECTION

A PASSION FOR QUALITY A QUEST FOR PERFECTION A PASSION FOR QUALITY A QUEST FOR PERFECTION Bespoke maintainable software, carefully designed, and artistically implemented WE SOFTWARE DEVELOPMENT www.geeks.ltd.uk all of these clients wanted... PERFORMANCE

More information

Spectrum Community Forum Grants. Application Pack

Spectrum Community Forum Grants. Application Pack Spectrum Community Forum Grants Application Pack Community Forum Grants (765120) Grant Application Form 1. What is the Community Forum Grant and what will it support? Community Forum Grants may be used

More information

Building a career in specification sales A guide to specification sales

Building a career in specification sales A guide to specification sales Building a career in specification sales A guide to specification sales What is specification selling? Who is the specifier? What stages does the specification decision process go through? What are the

More information

Doing business with the European Commission Tips for potential contractors

Doing business with the European Commission Tips for potential contractors Doing business with the European Commission Tips for potential contractors EUROPEAN COMMISSION Text A business opportunity for you C O N T E N T S Doing business with the European Commission Tips for potential

More information

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB41507 Certificate IV in Project Management First published 2010 ISBN 978-1-74205-510-7 Department of Training

More information

Info sheet : Considering labour standards in the procurement process

Info sheet : Considering labour standards in the procurement process Info sheet : Considering labour standards in the procurement process In line with the EU procurement rules and the Government s value for money principle, contracting authorities can take steps to consider

More information

TENDER SPECIFICATION DOCUMENT. Mobile Phone Contract. Tender for Mobile Phone Contract for EMB-Group

TENDER SPECIFICATION DOCUMENT. Mobile Phone Contract. Tender for Mobile Phone Contract for EMB-Group TENDER SPECIFICATION DOCUMENT Tender for for EMB-Group Date: September 2015 The EMB Group incorporates: East Midland Business Ltd EMB Excellence Ltd EMB Certification Ltd EMB-Group Ltd Registered Office:

More information

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Procedures for Tenders and Contracts October 2014 Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Huon Valley Council Procedures for Tenders and Contracts October 2014

More information

Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement

Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable

More information

ACCREDITATION. APM Corporate CASE STUDY

ACCREDITATION. APM Corporate CASE STUDY Introduction Sellafield Ltd is responsible for safely delivering decommissioning, reprocessing, nuclear waste management and fuel manufacturing activities on behalf of the Nuclear Decommissioning Authority.

More information

BS 11000 Collaborative Business Relationships It s your choice. Your implementation guide

BS 11000 Collaborative Business Relationships It s your choice. Your implementation guide BS 11000 Collaborative Business Relationships It s your choice Your implementation guide BS 11000 - Collaborative Business Relationships Background BS 11000 is a recognized standard for ensuring mutually

More information

How to write a great CV

How to write a great CV How to write a great CV No matter what the selection process is for the role you are applying for, the first step is making sure you have a great CV! Your CV will be used to assess your suitability for

More information

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and

More information

Involve-Project Manager

Involve-Project Manager Involve-Project Manager This article will describe: What is Project Management Why is Project Management so important to community and voluntary organisations The Key Phases of Project Management: o Initiation

More information

Tender feedback in Catering & Cleaning

Tender feedback in Catering & Cleaning Briefing 12-44 September 2012 Tender feedback in Catering & Cleaning This briefing provides the information that those tendering for public sector contracts should request in the event that a particular

More information

Guide to to good handling of complaints for CCGs. CCGs. May 2013. April 2013 1

Guide to to good handling of complaints for CCGs. CCGs. May 2013. April 2013 1 Guide to to good handling of complaints for CCGs CCGs May 2013 April 2013 1 NHS England INFORMATION READER BOX Directorate Commissioning Development Publications Gateway Reference: 00087 Document Purpose

More information

King Fahd University of Petroleum and Minerals

King Fahd University of Petroleum and Minerals King Fahd University of Petroleum and Minerals Department of Construction Engineering and Management CEM 515 Project Quality Management Term Paper Procurement Quality Management In Construction Project

More information

Becoming Tender Ready

Becoming Tender Ready Becoming Tender Ready Difference Between Procurement & Tendering Procurement is the process of acquiring goods, works and services, covering both acquisition from third parties and from in-house providers.

More information

AER reference: 52454; D14/54321 ACCC_09/14_865

AER reference: 52454; D14/54321 ACCC_09/14_865 Commonwealth of Australia 2014 This work is copyright. In addition to any use permitted under the Copyright Act 1968, all material contained within this work is provided under a Creative Commons Attribution

More information

NEATH PORT TALBOT LOCAL HEALTH BOARD CORPORATE GOVERNANCE HANDBOOK

NEATH PORT TALBOT LOCAL HEALTH BOARD CORPORATE GOVERNANCE HANDBOOK NEATH PORT TALBOT LOCAL HEALTH BOARD CORPORATE GOVERNANCE HANDBOOK Purpose of this Handbook This handbook sets out, in broad terms, the Corporate Governance arrangements in place within Neath Port Talbot

More information

Procurement Reform Bill : Consultation response from the Scottish Fair Trade Forum

Procurement Reform Bill : Consultation response from the Scottish Fair Trade Forum The Scottish Fair Trade Forum 1 2 Thistle Court Thistle Street Edinburgh EH2 1DD Procurement Reform Bill : Consultation response from the Scottish Fair Trade Forum Overview The Forum welcomes this timely

More information

The University of Adelaide Business School

The University of Adelaide Business School The University of Adelaide Business School MBA Projects Introduction There are TWO types of project which may be undertaken by an individual student OR a team of up to 5 students. This outline presents

More information

1 Beyond Network CRM (Quotation)

1 Beyond Network CRM (Quotation) 1 Beyond Network CRM (Quotation) Invitation to Quote DESIGN, DEVELOPMENT AND IMPLEMENTATION OF A CRM SYSTEM FOR THE BEYOND NETWORK (A BUSINESS SUPPORT PROGRAMME) 2 Beyond Network CRM (Quotation) PART 1:

More information

Performance Management and Service Improvement Framework

Performance Management and Service Improvement Framework Performance Management and Service Improvement Framework Author Marcus Evans, Operational Director - Performance and Customer Insight Date: September 2014 Contents Page 1. Introduction 3 2. Strategic ning

More information

ADVICE NOTE EMPLOYING CONTRACTORS. How to go about employing competent contractors

ADVICE NOTE EMPLOYING CONTRACTORS. How to go about employing competent contractors ADVICE NOTE EMPLOYING CONTRACTORS How to go about employing competent contractors 2 CONTENTS Note: As the leading trade body for residential leasehold management, ARMA is also an important resource for

More information

Getting the most from Contracts Finder

Getting the most from Contracts Finder Getting the most from Contracts Finder A guide for businesses and the public May 2012 What s in this guide What s this guide for?...2 What s on Contracts Finder...2 Searching for notices the basics...2

More information

HS2 Supply Chain FAQs

HS2 Supply Chain FAQs HS2 Supply Chain FAQs As part of our ongoing market engagement activity, High Speed Two (HS2) Limited contacted four key umbrella, industry and trade associations. Our aim was to poll a sample of their

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

An Introduction to Key Performance Indicators produced and written for CCI by Dr. Will Swan and Emma Kyng

An Introduction to Key Performance Indicators produced and written for CCI by Dr. Will Swan and Emma Kyng An Introduction to Key Performance Indicators produced and written for CCI by Dr. Will Swan and Emma Kyng Centre for Construction Innovation - November 2004 CONTENTS Executive Summary... 3 1. Introduction...

More information

Circular 10/14: Initiatives to assist SMEs in Public Procurement

Circular 10/14: Initiatives to assist SMEs in Public Procurement Ref: DPE108/001/2014 16 April 2014 To Heads of Departments 1 Circular 10/14: Initiatives to assist SMEs in Public Procurement A Dhuine Uasail, 1. In the context of the reform of the Public Service and

More information

UNDERSTANDING EFFECTIVE LEAD GENERATION TICK #THINKGROWTH

UNDERSTANDING EFFECTIVE LEAD GENERATION TICK #THINKGROWTH UNDERSTANDING EFFECTIVE LEAD GENERATION TICK #THINKGROWTH CONTENTS 1 INTRODUCTION Page 3 2 COMPETITIVE PROPOSITION Page 4 3 USER PROFILING/AUDIENCE DNA Page 9 ENSURE YOUR BRAND HAS A CLEAR, COMPELLING

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

Planning Your Business Venture

Planning Your Business Venture Session Six Planning Your Business Venture Good plans shape good decisions. That s why good planning helps to make elusive dreams come true. Lester R. Bittel Overview: Learning to plan is an essential

More information

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October

More information

Commercial Skills and Competency Framework for. Practitioner Levels

Commercial Skills and Competency Framework for. Practitioner Levels Commercial Skills and Competency Framework for Developing and Practitioner Levels Sourcing Pre Market Document Title Author Commercial Skills and Competency Framework for Developing and Practitioner Levels

More information

Horizon NSL Pre-Application Intervention Strategy

Horizon NSL Pre-Application Intervention Strategy CIVIL NUCLEAR REACTOR PROGRAMMME NEW REACTOR LICENSING HORIZON NUCLEAR POWER COMPANY LIMITED S APPLICATION FOR A NUCLEAR SITE LICENCE TO INSTALL AND OPERATE TWO ADVANCED BOILING WATER REACTOR UNITS AT

More information

Curriculum Development Project Knowledge in Sales and Marketing Education and Training

Curriculum Development Project Knowledge in Sales and Marketing Education and Training Curriculum Development Project Knowledge in Sales and Marketing Education and Training End of Project Report Project summary and key achievements against original aims The original project bid aims of

More information

Guide for Applicants. Call for Proposal:

Guide for Applicants. Call for Proposal: Guide for Applicants Call for Proposal: COSME Work Programme 2014 TABLE OF CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 II.2.1.

More information

IT Project Management

IT Project Management IT Project Management IT Project Management provides a structured approach to making things happen and in doing so, enables initiatives (projects) to be delivered to time, quality and budget. www.business.wales.gov.uk/superfastbusinesswales

More information

Qualification Outline

Qualification Outline Qualification Outline Certificate IV in Project Management Practice BSB41513 Get it done. Get it done well Web: www.kneedeep.com.au/certification.html Phone: +61 8 7127 4885 Email: [email protected]

More information

How to get to grips with your competitors

How to get to grips with your competitors 10 Minute Guide How to get to grips with your competitors Membership Services Moor Hall, Cookham Maidenhead Berkshire, SL6 9QH, UK Telephone: 01628 427500 www.cim.co.uk/marketingresources The Chartered

More information

An Export Marketing Research Project. Guidance Notes

An Export Marketing Research Project. Guidance Notes An Export Marketing Research Project Guidance Notes 2 An Export Marketing Research Project Introduction UKTI encourages British business to use marketing research as an integral part of their export strategy.

More information

Allianz Professional Indemnity Insurance Construction Projects

Allianz Professional Indemnity Insurance Construction Projects Allianz Global Corporate & Specialty Pacific Allianz Professional Indemnity Insurance Construction Projects Proposal Form General Information The General Information set out below is provided for your

More information

Opening Doors. The Charter for SME Friendly Procurement

Opening Doors. The Charter for SME Friendly Procurement Opening Doors The Charter for SME Friendly Procurement Foreword 99% of all Welsh businesses are Small and Medium Enterprises (SMEs) and the Welsh Assembly Government recognises and appreciates the very

More information

Steel procurement in major projects: Guidance on the application of social issues. Purpose

Steel procurement in major projects: Guidance on the application of social issues. Purpose Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.

More information

White Paper. Supplier Lifecycle Management: Reduce risk, Improve Performance and drive Supplier Value

White Paper. Supplier Lifecycle Management: Reduce risk, Improve Performance and drive Supplier Value White Paper Supplier Lifecycle Management: Reduce risk, Improve Performance Supplier Lifecycle Management works from the premise that the supplier should be considered as central to procurement activities

More information

MEDIA MARKETING PACK 2015

MEDIA MARKETING PACK 2015 MEDIA MARKETING PACK 2015 INTRODUCTION Nuclear Connect has established itself as the UK s leading supply chain magazine and directory representing and targeting the nuclear industry. With an audience of

More information

Before starting it is worth considering what we mean by the term project - basically it can be defined as:

Before starting it is worth considering what we mean by the term project - basically it can be defined as: Delivering Successful Projects, Tom Moriarty, MDR Consulting This paper outlines the critical requirements of success in managing projects of all types from the definition of a business need to the delivery

More information

Guidance on Framework Agreements

Guidance on Framework Agreements 1. Introduction Guidance on Framework Agreements The purpose of this document is to provide guidance to public purchasers on the operation of framework agreements as provided for under current public procurement

More information

Management of Radioactive Waste & Materials Inventory Data

Management of Radioactive Waste & Materials Inventory Data Management of Radioactive Waste & Materials Inventory Data Critical Enabler Contents Executive Summary... 3 1. Introduction... 4 2. Inventory Data Users... 5 3. Current Situation... 7 3.1 Management of

More information

Enquiry 2014 15 Ref 034

Enquiry 2014 15 Ref 034 2014 12 03 Request for Quotation: Design, Printing and Supply of the Buffelsdraai Information Booklet and Brochure for the Environmental Planning and Climate Protection Department 1. Background Enquiry

More information

Procurement driving better value for money. Supplying New Zealand Government. A guide for suppliers on how to bid for government contracts

Procurement driving better value for money. Supplying New Zealand Government. A guide for suppliers on how to bid for government contracts Procurement driving better value for money Supplying New Zealand Government A guide for suppliers on how to bid for government contracts A guide for suppliers July 2010 Acknowledgement and thanks development

More information