SUPPLEMENTARY ECONOMIC ANALYSIS
|
|
|
- Megan Green
- 10 years ago
- Views:
Transcription
1 Koror Airai Sanitation Project (RRP PAL: 42439) A. Context of the Analysis SUPPLEMENTARY ECONOMIC ANALYSIS 1. For technical and environmental reasons, creating a single sewage collection and treatment system integrating Koror and Airai is not feasible. The project, therefore, consists of two physically separate projects, though their costs and benefits are considered together. 2. In Koror, the existing system was first built in the 1970s. It consists of a central collection network feeding to a sewage treatment plant in Malakal. Though only about 60 percent of households are now connected to the system (about 1,890 of a total of approximately 3,149 households in Koror), the system is overloaded and performs poorly, as shown in Table SA1 below. Non-domestic connections (commercial establishments and the government, a total of 1,120 connections) account for about 40 percent of the total effluent treated. Table SA1: Capacity vs Load, Koror Sanitation System System Component Capacity Load Shortfall (%) SECT 1 - Central (Koror) Trunk Sewer (L/s) None SECT 2 - Central (Koror) Trunk Sewer (L/s) % Sewage Pump Station SPS 1 (L/s) ( ) 172 ( ) SPS 1 Force Main (L/s) % Malakal Trunk Sewer (L/s) % Sewage Pump Station SPS 2 (L/s) ( ) 200 ( ) SPS 2 Force Main (L/s) % Sewage Treatment Plant (kg BOD/day) 1,600 1, % 3. The system is poorly maintained, and leaks and overflows are a daily occurrence, threatening the livability of the urban area, inland and coastal areas, the coastal marine environment, agriculture (taro patches), and public health. As Palau depends on tourism for 50% of its national income (and most tourists spend the bulk of their time and money in Koror), the dilapidated system also poses a serious threat to future income prospects, as tourism is acutely sensitive to health issues. 1 The implicit threat of an outbreak of a waterborne disease epidemic will increase through time unless and until the system is rehabilitated, and if such an event were to occur, tourist arrivals can be expected to fall substantially and for an extended period. Under the proposed project, the number of domestic and non-domestic connections will be increased, leaking pipes will be replaced, the sewage treatment plant will be overhauled with expanded capacity, system maintenance will be strengthened, and overflows will be sharply reduced. 4. In Airai, some 325 households and a small number of businesses and public facilities (government offices and a school) make up the community of Kesebelau. The community was established on government land, with housing built and leased to the public. There is no sewage system in the area at present, and all residents are using septic tanks. Because of poor soil conditions for septic leaching, the septic tanks require frequent pumping (twice a week) in order to avoid overflows which, when emitted, largely flow on the surface, ponding in residential and agricultural areas. Surveys have shown that Kesebelau households do not carry out pumping with anything close to the required frequency, and surface flows have become continuous, threatening the habitability of the area. A simple sewage collection and package treatment 1 International Monetary Fund (IMF) Republic of Palau: 2012 Article IV Consultation, Staff Report, IMF Country Report No. 12/54.
2 2 system is proposed, allowing the community to discontinue use of septic tanks, and thus eliminate the present requirement of frequent pumping. 5. In summary, the project will address looming threats to the public health and habitability of the urban areas of Palau, and will help to safeguard a land and coastal marine environment on which a continued vibrant tourism sector and a large part of national income depend. B. Least-Cost Analysis 6. In Koror, three potential solutions have been identified to address the deficiencies of the present system: (i) the proposed project, which is a rehabilitated centralized collection system connected to an overhauled and expanded sewage treatment plant in Malakal; (ii) a new collection system routed around the coastal areas and connected to an overhauled and expanded sewage treatment plant in Malakal; and (iii) a decentralized collection and treatment system, resulting in eight new small collection and treatment plant systems distributed around Koror. 7. As all of the alternatives are subject to equivalent energy, maintenance, and personnel costs, the least-cost decision rests on a comparison of the respective economic capital costs, as summarized in Tables SA2 SA4 below. 2 The proposed project in Koror is least cost ($24.4 million compared to $33.0 million and $35.5 million for approaches 2 and 3, respectively) because it minimizes the need for procurement and installation of new facilities. Table SA2: Approach 1 (Proposed Project): Centralized Collection System Description Amount ($) Gravity Interceptor Sewer 3,065,875 Major Pump Station Upgrade 1,002,500 Minor Pump Station Rehabilitation 832,500 Major Force Main Upgrade 1,890,000 Sewage Treatment Plant 9,500,000 Overflow Management Facility 497,000 Public Toilet Facilities 97,500 Telemetry/Remote Monitoring 190,125 Consulting services (survey, design, tendering, supervision) 2,711,000 Consulting services (management support) 1,468,750 Physical Contingency 3,189,000 Total 24,447,000 2 Converted from financial costs by removing taxes.
3 3 Table SA3: Approach 2: Coastal Carrier System Description Amount ($) Mangrove clearing and earth fill to accommodate new coastal gravity sewers etc 3,979,105 New coastal gravity sewers including: connecting existing system to new sewers 4,973,881 Decommission existing pump stations and rehabilitate sites 621,735 New pump stations to support coastal carrier system 2,437,202 New force mains to support coastal carrier system 559,562 SPS1 upgrade including overflow facility 298,433 SPS2 upgrade 74,608 SPS1 force main adjustment 346,928 SPS2 new force main 134,295 New SPSA8 248,694 New SPS8 force main 447,649 SPSA1 force main adjustment 130,564 New telemetry system 193,981 New Malakal STP 9,947,762 New and rehabilitated public toilets 149,216 Consulting services (survey, design, tendering, supervision) 3,558,825 Physical Contingency 4,908,723 Total 33,011,163 Table SA4: Approach 3: Decentralized Collection & Treatment System Description Amount ($) New satellite STPs 15,916,419 New STP Access 621,735 New pump station lift to north side to protect Necco Bay 696,343 New force main lift to north side to protect Necco Bay 417,806 Adjust existing gravity sewers to connect to new STPs 994,776 Mangrove clearing and earth fill to accommodate new STPs 795,821 New STP ocean outfalls 5,968,657 SPS1 upgrade including overflow facility 298,433 SPS2 upgrade 74,608 SPS1 force main adjustment 134,295 SPS2 new force main 134,295 New telemetry system 193,981 New and rehabilitated public toilets 149,216 Consulting services (survey, design, tendering, supervision) 3,827,476 Physical Contingency 5,279,277 Total 35,503, In Airai, the least-cost analysis compares (i) continued use of septic tanks in Kesebelau, combined with pumping and cleaning operations of a frequency sufficient to eliminate the present surface flows of sewage with (ii) the proposed project a centralized sewage collection and treatment system serving the same area. Alternative (i) is available at no initial investment cost but high operational cost, while alternative (ii) comes with a significant initial investment cost but comparatively low operational costs. The initial investment cost of the proposed project is summarized in Table SA5 below.
4 4 Table SA5: Airai Proposed Project, Initial Costs Description Amount ($) Gravity Sewer Network 1,372,000 Package Sewage Treatment Plant 1,372,000 Minor Pump Station and Pressure Main 373,000 Physical Contingency (15%) 468,000 Total 3,585, In addition, the estimated economic operation and maintenance (O&M) costs of the project include consumption of 75,000 kwh of electricity per annum, valued at about $38,000/year, and routine system maintenance of approximately $11,000/year, or a total of about $49,000 per year at startup. Over the project s operating period, the cost of electricity is assumed to increase in real terms per annum at the rate of 1.9%, consistent with rising diesel fuel prices. Under these assumptions, the net present value (NPV) of total costs of the project over its operating life, discounted at 12%, is approximately $4.0 million. 10. The approximately 325 households in Kesebelau that would be served by the project are expected to increase at an average rate of 3.3% per annum, reaching 645 households by There is also a small number of non-domestic (commercial and government facilities) in the area that would be served by the project (2 currently, increasing to 5 by 2036). 3 The frequency of pumping each septic tank, either of a household or a commercial establishment, required to prevent surface flows of effluent is estimated at twice per week, or 104 times per year. 4 The economic cost of pumping a septic tank of a household is conservatively estimated at $24 (accounting for fuel and maintenance), and that of a commercial or government establishment at $30. 5 These estimates are summarized in Table SA6 below. Table SA6: Airai Alternative: Septic Tank Maintenance Costs (Frequent Pumping) Item Value Number of household connections Housing growth rate 3.3% Number of non-domestic connections Expected added non-domestic connections 3 Cost of pumping household septic tank ($/pumping) 24 Frequency of pumping (per household connection per year) 104 Cost of pumping non-domestic septic tank ($/pumping) 30 Frequency of pumping (per non-domestic connection per year) There is a number of large hotels in the area also, but they have their own sewage treatment and disposal facilities and so are not expected to be connected to the project. 4 Based on average expected volume input. 5 The cost of purchasing tank trucks (6 working full-time are estimated to be needed to handle the expected volume of pumping) has not been included in the analysis, as it is likely that such trucks are available for hire from the private sector. Any need to purchase trucks would add substantially to the first-year costs of the septic tank pumping scenario.
5 5 11. Under these assumptions, the pumping required for septic tanks in Kesebelau will cost an estimated $791,000 in the first year, rising (because of increasing households) to about $1.6 million per year by the end of the period. The NPV of total costs of pumping operations over the life of the project (to 2036), discounted at 12%, is approximately $7.7 million. It is therefore concluded that the proposed project is the least-cost alternative in Airai in terms of life cycle costs. C. Methodology 12. A with project scenario is compared directly to a without project scenario in order to make explicit the benefits of the project and its incremental costs over the project lifetime. Costs and benefits under both scenarios are discounted at the standard economic opportunity cost of capital (EOCC) of 12%. 13. The local currency in Palau is the United States dollar. There are no levies or duties on imported materials. Local labor is taxed at 6% on all income up to $8,000 per year, and at 12% on income exceeding $8,000/year. Taxes are excluded from the economic costs. 14. As Palauans have free rights to migrate and work and claim social benefits in the United States, there is virtually no unemployment in Palau and local wage rates are an accurate measure of the opportunity cost of labor. Under these circumstances, it is estimated that the shadow wage rate and exchange rate factors necessary to equilibrate the border and domestic price levels of traded and non-traded goods in Palau are not materially different from 1.0. D. Project Economic Costs 15. Project economic costs include the initial costs associated with (i) civil and mechanical works and equipment associated with the development or rehabilitation of sewage collection and treatment facilities; (ii) surveys and other technical investigations contributing to detailed design; (iii) consulting services for carrying out design work, tendering, implementation supervision, and management support activities; and (iv) a physical contingency allowance. Economic costs associated with the operational phase of the with-project scenario include (i) incremental routine repairs and maintenance; (ii) asset replacements scheduled according to the frequency with which they are expected to wear out; and (iii) incremental energy costs. Operational phase costs include personnel costs. The residual value of sewerage assets at the end of their economic life is zero. E. Project Economic Benefits 16. In both subproject areas (Koror and Airai), the objective of the project is to reduce the significant public health and associated environmental risks of poor sanitation by substantially reducing sewage overflows (in Airai, these are caused by improper maintenance of septic tanks), improving responsiveness of operators to emergencies, and ensuring that effluent ultimately discharged to the environment is properly treated. As mentioned above, in the case of Koror (and Palau generally), a key consideration in protecting the environment from pollution from wastewater and foul air is to protect incomes the economy depends crucially on tourism. Deterioration of Palau s pristine marine and coastal environments potentially leading to an outbreak of water borne disease such as cholera or typhoid would cause grievous damage to the tourism industry in Palau and destruction of livelihoods requiring multiple years to recover, in addition to having a potentially devastating impact on the local population.
6 6 17. A common approach to quantifying the benefits of improved sanitation, as with an incremental water supply, is to estimate the beneficiaries willingness to pay for the improved service. This provides a direct measure of the beneficiaries perception of the economic benefit of the improvement to them. In Palau, however, the cost and effectiveness of sanitation (and of government services in general) is a highly charged political issue, and it is unlikely that a concerted effort to obtain willingness to pay data by survey in the present climate will reap meaningful results. The approach to economic analysis adopted for present purposes measures (i) in Koror, the direct economic impact of operation and maintenance (O&M) savings, avoided costs due to sewage overflows in terms of health care, environmental clean up by the government, households, and the commercial sector, and detrimental impact on tourism; and (ii) in Airai, the avoided costs of properly operating and maintaining septic tank systems in the residential area of Kesebelau. In both subprojects, there is a small but significant benefit of local employment associated with project implementation. 18. The economic benefits including in the analysis of each subproject and the method of quantification of each are summarized below. F. Koror Subproject 19. The economic analysis of the Koror subproject rests on five quantified benefits: (i) reductions in asset replacement costs due to improved asset management resulting from the project; (ii) avoided health costs and production losses that arise due to gastrointestinal infections resulting from exposure to sewage overflows; (iii) avoided costs to government, households, and the commercial sector to clean-up land, coastal, agricultural, and inhabited areas after overflows occur; (iv) increased local employment during implementation; and (v) avoided loss of national income that occurs because of overflows that may cause an outbreak of a life-threatening contagious disease such as cholera or typhoid, in turn leading to a sharp and sustained downturn in tourist arrivals in Palau. 20. Improvements in asset management. The entity responsible for operating and maintaining the Koror sewage system lacks appropriate control mechanisms for pumps and other equipment, which therefore wear out and need to be replaced well before their design life expires. Under current conditions assumed to continue without the project, sewage pumps in pump stations typically need to be replaced every 5 years compared to a design life of 15 years, and electrical control boards need to be replaced every 10 years compared to a design life of 20 years. By introducing inexpensive but effective control mechanisms and by applying a coherent asset management plan under the project, these assets will last and remain operable for their full design lives. 21. There are 45 minor pump stations in Koror, each with 2 pumps valued at $15,000 each, and 2 major pump stations, each with 4 pumps valued at $75,000 each. Replacing all pumps incurs a cost of $1.95 million. There is one electrical control panel in each pump station. Control panels are valued at $30,000 and $150,000 in minor and major pump stations, respectively. Replacing all control panels incurs a cost of $1.65 million. 22. With the project, pump, and control panel replacements occur relatively far in the future (15 years for pumps and 20 years for control panels, after the start of operations). Expenditures for replacing these assets with the project have a net present value (discounted at 12%) of $375,000. In comparison, without the project, asset replacements continue from the present every 5 years for pumps and every 10 years for control panels, and have a net present value of
7 7 $3.0 million. The difference ($2.62 million) between the net present asset replacement costs of the with-project and without-project scenarios is included as a benefit of the project. 23. Health benefits (avoided costs of treatment and lost production). The Ministry of Health has released monthly data on the incidence of gastroenteritis (GI, inflammation of the stomach and intestines due to ingestion of harmful bacteria) that shows a strong correlation between sewage overflows and recorded cases of the disease. In the period from 1 April 2011 to 31 March 2012, the ministry recorded 862 cases in Koror, of which 429 or 50 percent occurred in the three months from November 2011 through January That period of 3 months was also when the Aimeliik power station was out of service due to a fire, and the Koror sewage pump stations could not function. Sewage overflows during that period were continuous, and account for the very high incidence of GI cases during that time. During normal times, sewage flows are also common. A significant overflow is estimated to occur on average twice per week in Koror and reported GI incidence (less than actual incidence, since many if not most cases, go unreported) averages cases per month. On this basis, it is assumed that the average number of cases in Koror of GI and other serious waterborne diseases requiring medical care is 10 per significant sewage overflow. The economic cost of medical care per case, accounting for the opportunity cost of doctors and nurses time and hospital occupancy ($40 per case) and medicines required for treatment ($10), is estimated at $50. In addition, it is assumed that a diagnosed case of GI or other serious water borne disease requires the patient to lose 5 working days. Production lost during such sick days is valued at $3/hour or $24/day or $120/case. In combination with treatment costs, the economic cost of GI is thus valued at $170 per case, or $1,700 per overflow. 24. As mentioned, the current frequency of serious overflows in Koror is estimated at two per week or 104 per year. It is further assumed that, without the project, the sewer system will continue to deteriorate, pumps will fail more frequently, blockages will become more frequent, and pipes will become more leaky, all leading to a gradually increasing frequency of overflows. Due to these causes, the frequency of overflows is assumed to increase at the rate of 5% per annum. 25. Under these conditions, avoided costs (with the project) for medical treatment and lost production due to infection from overflows is calculated at about $177,000 per annum in the first year of operations, rising gradually to $469,000 per annum by the end of the project period, resulting in a net present value of $1.5 million as a project benefit. 26. Avoided costs due to clean-up of overflows. The service provider responsible for operating and maintaining the Koror sewage system is required to make frequent emergency responses for clean-up of overflows, at considerable cost per incidence. In cases where overflows are not actually cleaned up by the service provider, costs are still borne by those directly affected (e.g., households facing ponding sewage in close proximity their living area will suffer direct clean-up costs or a loss of living standard and use of property and assets; commercial establishments such as tourist resorts or restaurants will undertake strenuous activity to cleanup effluent in their vicinity in order to avoid losing customer patronage, etc.). The actual cost of clean-ups of historical overflows has not been recorded. To estimate the economic cost conservatively, it is assumed that cleaning up an overflow and appropriately disposing of the effluent costs a multiple (100%) of the existing cost of collecting and treating effluent in the sewage system in Koror. Further, given the current estimated frequency of 6 ADB Technical Assistance to the Republic of Palau for Sanitation Sector Development preliminary environmental estimate. Manila.
8 8 significant overflows (104 per year), it is estimated that approximately 20% of the full volume of effluent in Koror is accounted for by overflows and that the remaining 80% is treated successfully within the system. Under these assumptions, the estimated cost of a clean-up per overflow (shared as an economic cost by all households, commercial establishments, or government entities affected) is approximately $14,900. As discussed above, without the project it is assumed that as the system continues to deteriorate, the frequency of overflows increases through the planning period at the rate of 5% per annum. 27. With the project, overflows will be sharply reduced, but not 100% eliminated. It is estimated that in the first year of operations, an overflow will occur once in two months (i.e., 6 per year), falling to 2 per year by the end of the first ten years of operations. The total volume of effluent involved in overflows will fall to 2% of the total volume during the first 10 years, falling further to 1% thereafter. The with-project overflows will also be less severe than those without the project, and will incur an economic cost of about $3,000/overflow. The without-project overflow clean-up costs have an estimated NPV of $13.1 million, offset by the NPV of withproject clean-up costs of $0.1 million; the difference ($13.0 million) is included as a project net benefit. 28. Local employment benefit. During the 3-year construction period of the Koror subproject, local labour will be employed, generating local earnings estimated at about $2.3 million. 29. Prevention of damage to livelihoods derived from tourism. Koror and the adjacent areas contain beautiful tropical seascapes and diving opportunities that have helped to make Palau a major international attraction and tourism to contribute about half of the country s gross domestic product (GDP), as mentioned above. However, the tourism sector in Palau as elsewhere is highly vulnerable to health threats, similar in this respect to terrorism threats. Frequent overflows cause foul smells in places where tourists congregate and often lead to closure of near-shore waters for tourist use; a critical threat in the dense urban environment of Koror is that of a major outbreak of serious water-borne disease such as cholera or typhoid that could arise from human exposure to raw sewage. Past experience with epidemics (e.g., severe acute respiratory syndrome and bird flu) in other parts of the world suggest that tourism in the affected areas is severely dampened and takes a number of years to recover. In a small economy such as Palau s, such an impact would be (and, as was seen to a degree in the wake of the 9/11 terrorism when tourist traffic worldwide was diminished, was) devastating to local livelihoods. 30. The sewage system in Koror is already overloaded, leaky, and subject to frequent overflows, presenting a considerable risk to the public health. It is a widely held view among health and tourism sector stakeholders that there is already a significant and rising risk of an outbreak of a seriously contagious water-borne disease, such as cholera or typhoid. 7 Such an outbreak would drive away tourist visitors to Palau and jeopardize the longer-term prospects of the tourism sector. In this sense, the proposed project can be viewed as an insurance policy, addressing the risks faced by an economic sector vital to Palau s national income. 31. According to the International Monetary Fund (IMF) 2012 Article IV Consultation in Palau, a one percentage point change in the growth rate of tourist arrivals is estimated to 7 Social surveys conducted in Koror under this PPTA indicate serious concerns in this regard by public officials (Palau Visitors Authority) and resort/hotel owners. Resort/hotel owners are also increasingly concerned by the health risk to guests of sewage overflows.
9 9 change real GDP growth in Palau by 0.2 percentage points on average, based on an analysis of the historical relationship between GDP and tourist arrivals. A model has been developed for the economic analysis to measure this effect with respect to impacts on tourist arrivals from hypothesized probabilities (measures of risk) of a cholera/typhoid outbreak occurring as a result of human exposure to contamination from the dilapidated sewage system. The model s parameters and assumptions are summarized below. 32. Based on the above-referenced IMF report, the projected medium- to long-term growth rate in Palau s real GDP is 2% per annum. In current dollars, the 2011 GDP was approximately $221 million and at the indicated growth rate will be about $230 million in constant dollars in To begin the analysis, it is assumed that, without the project, the probability (i.e., level of risk) of an outbreak of cholera/typhoid is one incident every twenty years, i.e., 5% per annum, and that, due to continued deterioration of the sewage system, the probability itself increases by 5% in each year through the planning period. 8 It is further assumed (conservatively) that if and when such an incident occurs, the growth rate of tourist arrivals in Palau will decline by 30%, and the decline will be sustained for 2 years. Applying the IMF s ratio of change in tourist arrivals growth to change in real GDP growth of 0.2, these assumptions imply an immediate change in the real GDP growth rate, if and when an incident occurs, from 2% to -4% [= (1+2%+(-30%*0.2))-1]. 33. To determine the expected value of the risk to tourism posed in each year by the dilapidated sewage system, the above change in real growth, which applies only if the incident occurs, is multiplied by the applicable probability of an incident occurring in a particular year (e.g., 5% in 2013) and a factor which incorporates the expected 2-year impact of the tourism decline. When an incident occurs, the second year of decline in national income is discounted by 12% to place the impact in present value terms at the start of the year in which the impact occurs. 34. Under these assumptions, the value of the risk to national income from tourism posed by the dilapidated sewage system without the project is estimated at $1.4 million (0.5% of Palau GDP) in 2013, rising to $2.4 million (0.9%) in real terms 9 by 2025, and $5.5 million (1.5%) by G. Airai Subproject 35. The economic benefit of the project in Airai is the avoided costs, with the project, of preventing surface flows of sewage without the project, which entails frequent pumping of sludge from all septic tanks by tank truck and cartage and proper disposal of it at the sewage treatment plant (without the project, the relevant plant is in Malakal). The essential economic benefit of the project is thus the higher efficiency and lower life-cycle cost of a centralized collection and treatment system used in place of continuing with a septic tank-based system. (Improved sewage treatment per se is not part of the postulated economic benefit, since it is assumed that pumping sewage and carting it to a treatment plant will result in the same quality of treatment as treating it in a new plant in Airai; the difference that matters is in the costs of collection and treatment.) 8 For example, if the probability which starts at 5% in 2013 is increasing at 5%/year without the project, the probability will double (i.e., reach 10%) after about 14 years (by around 2027). 9 Expressed in 2011 dollars.
10 The costs associated with frequent pumping of septic tanks in Airai are discussed above in the least-cost analysis section of this report. With the project, these costs are avoided and constitute the project benefits. H. Economic Internal Rate of Return (EIRR) and Economic Net Present Value (ENPV) 37. Under the parameters and assumptions discussed above, the EIRR of the two subprojects is 18.4%, with an NPV (discounted at 12%) of $14.3 million. The EIRR is considered to be acceptable as it exceeds the economic opportunity cost of capital adopted for this analysis of 12 percent. The EIRR/ENPV calculation table is shown overleaf in Table SA7.
11 11 Table SA7: Calculation of the EIRR and ENPV (Koror and Airai Sanitation Projects) All values USD '000 Year Capital Costs Incremental O&M Costs Overflow Clean up Costs Asset Replacement Costs Total Costs Avoided Asset Replacement Costs Incremental Local Labour Earnings Costs Avoided Health Care Costs Costs Impact Total Benefits Net Benefits , ,636-1, ,002-8, , ,199-1, ,935-10, , , ,389-4,733 Costs Avoided Septic Tank Pumping Avoided Overflow Clean up Avoided Detrimental Tourism ,550 1,404 3,975 3, ,628 1,504 4,189 3, , ,709 1,611 6,365 6, ,794 1,725 4,654 4, ,884 1,847 4,907 4, ,978 1,978 5,175 4, , ,077 2,119 5,459 5, ,600-1, ,181 2,269 9,359 9, , ,290 2,431 6,076 5, , ,405 2,603 6,422 6, , ,525 2,788 6,778 6, , ,651 2,986 7,155 6, ,950-1, ,784 3,198 9,504 9, , ,923 3,425 7,978 7, , ,069 3,668 8,426 8, ,950 2, , ,222 3,928 8,901 6, , ,383 4,207 9,405 9, ,600-1, ,553 4,506 13,539 13, , ,730 4,826 10,506 10, , ,917 5,169 11,106 10, ,650 2, , ,113 5,536 11,743 9,623 NPVs 25,334 1, ,397 2,995 2,478 7,694 1,494 13,100 13,915 41,677 14,280 EIRR 18.4% Benefits
12 The project provides considerable benefits to Palau and the people of Koror and Airai, by reducing the threat of damage to public health and to livelihoods, and by reducing the costs of maintaining an environment free of pollution from effluent. The project represents a considerable improvement to the allocation of public and private resources in comparison to continuing to cope with the effects of a weak and deteriorating sewage system. I. Sensitivity Analysis 39. Sensitivity analysis was carried out for adverse variations (by 20%) in the following parameters: (i) increase in capital and asset replacement cost; (ii) increase in incremental O&M cost; (iii) increase in rate of real increase in electricity price; (iv) decrease in incremental local employment; (v) decrease in avoided asset replacement, health care, septic tank pumping, and overflow clean-up costs; and (vi) decreases in avoided tourism impact. The sensitivity analysis results are summarised in Table SA8. Table SA8: Sensitivity Analysis Test Variation (+/- %) ENPV EIRR Sensitivity Indicator (SI) Basecase Parameter Switching Value (SV) Switching Value (+/-%) Test Case Base (reference case) 14, % Increases in Costs Capital and Asset Replacement Costs 20% 9, % ,717 39, % Incremental O&M Costs 20% 13, % ,680 15, % Electricity Price Escalation Rate 20% 14, % % 8.3% 336.3% Decreases in Benefits Avoided Costs -20% 9, % ,284 11, % Incremental Local Labour Earnings -20% 13, % , % Detrimental Tourism Impact -20% 11, % , % Costs Increased and Benefits Decreased 20% % A "Switching Value (+/-%)" of -100% indicates that reducing the parameter to zero does not reduce the economic internal rate of return below the 12% threshold. 40. The project EIRR remains above 12% when each of the adverse variations is applied, and for all of them applied simultaneously. The most sensitive parameter is found to be capital and asset replacement costs, with a sensitivity indicator (SI) of 1.80, indicating that, say, a 10% variation in such costs will result in a 18% change in the NPV of the project. Calculations of the switching value (the value of a parameter at which the project EIRR reaches the threshold of economic viability, 12%) show that capital and asset replacement costs can rise by approximately 56% before the EIRR falls below 12%, all other parameters equal. The next most sensitive parameter is the combined avoided costs included as benefits apart from tourism (avoided health, cleanup, asset replacement, and septic pumping costs), with SI=1.77, but such benefits could fall approximately 57% before EIRR falls below 12%. The avoided tourism impact parameter has an SI of about 1.0, but if this benefit were to fall to zero, the project EIRR would fall close to, but remain above, 12%. Variations in the other parameters are not significantly sensitive in terms of the economic outcome of the project.
Detailed Economic Analysis. November 2012. PNG: Maritime and Waterways Safety Project
Detailed Economic Analysis November 2012 PNG: Maritime and Waterways Safety Project CURRENCY EQUIVALENTS (as of 5 November 2012) Currency unit kina (K) K1.00 = $0.49 $1.00 = K2.06 ABBREVIATIONS EIRR economic
FINANCIAL ANALYSIS. A. Introduction and Methodology
Coastal Towns Environmental Infrastructure Project (RRP BAN 44212) FINANCIAL ANALYSIS A. Introduction and Methodology 1. The Coastal Towns Environmental Infrastructure project finances basic urban service
1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance
Ex-ante Evaluation 1. Name of the Project Country: India Project: Goa Water Supply and Sewerage Project (Loan Agreement: 09/14/2007; Loan Amount: 22,806 million yen; Borrower: The President of India )
Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water
United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows
FINANCIAL AND ECONOMIC ANALYSES
Tonga-Fiji Submarine Cable Project (RRP TON 44172) FINANCIAL AND ECONOMIC ANALYSES A. Introduction 1. The Tonga Fiji Submarine Cable Project will support the Government of Tonga to establish an 827 kilometer
SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES 1. 1. Sector Performance, Problems, and Opportunities
Country Partnership Strategy: Kyrgyz Republic, 2013 2017 SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES 1 Sector Road Map 1. Sector Performance, Problems, and
United States Environmental Protection Agency Office of Water 4204. Benefits of Protecting Your Community From Sanitary Sewer Overflows
United States Environmental Protection Agency June 2000832-F-00-005 Office of Water 4204 Benefits of Protecting Your Community From Sanitary Sewer Overflows Sanitary Sewer Overflow Control Enhances Community
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS 122 HANDBOOK FOR THE ECONOMIC ANALYSIS OF WATER SUPPLY PROJECTS CONTENTS 5.1 Introduction...123 5.2 Financial Revenues...124 5.3 Project Costs...126 5.3.1 Investments...127
Viet Nam Da Nang Waste water management
Case Study Country: City: Key Sectors: Viet Nam Da Nang Waste water management Local Partner Organization Geography and Population Da Nang People s Committee Department of Natural Resources and Environment
Environmental Science 101 Waste. Fall 2012. Lecture Outline: Terms You Should Know: Learning Objectives: Reading Assignment: Chlorinated.
Environmental Science 101 Waste Fall 2012 1 Lecture Outline: 17. SEWAGE DISPOSAL A. Sewage Handling B. Raw Sewage C. Wastewater Treatment Steps D. Individual Septic Systems E. Taking Stock Learning Objectives:
PROGRAM IMPLEMENTATION SCHEDULE
Water Sector Improvement Program (RRP PAL 44031) A. Program Description PROGRAM IMPLEMENTATION SCHEDULE 1. The Program will support reform of the water and sanitation sector, focusing on improving policy
Pakse Urban Environmental Improvement Project (RRP LAO 43316)
FINANCIAL ANALYSIS 1. Financial viability was assessed for solid waste management (SWM) improvements, which is the project s only revenue-earning subcomponent. 1 A financial sustainability analysis was
A Property Owner s Guide
The Operation and Maintenance of Domestic and Commercial Sewers A Property Owner s Guide KILDARE LOCAL AUTHORITIES WATER SERVICES DEPARTMENT TABLE OF CONTENTS Introduction 1. Why should I care? 2. What
DRAFT Public Outreach Document for What s an SSMP?
DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials
Based on the above, it is recommended that Lift Stations #1 and #3 be abandoned and their flows be diverted to the regional Lift Station #8.
Lakeside; Clairmont Heights; Portion of Clairmont currently serviced to Pump Station #2; Crossroads North and Crossroads South portion of flows that are diverted to Lakeside Trunk. It is understood that
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
Unauthorized Discharges and Sanitary Sewer Overflows
TCEQ REGULATORY GUIDANCE Field Operations Support Division RG-395 Revised April 2011 Unauthorized Discharges and Sanitary Sewer Overflows What does this document cover? The Texas Commission on Environmental
ON-SITE WASTEWATER TREATMENT SYSTEMS ACT
ON-SITE WASTEWATER TREATMENT SYSTEMS ACT Revised and reproduced by the Colorado Department of Public Health and Environment June, 2012 (PLEASE NOTE: This is an unofficial copy of this statute. The official
MACROECONOMIC AND FISCAL ASSESSMENT
Public Sector Financial Management Program (RRP SAM 46384) A. BACKGROUND MACROECONOMIC AND FISCAL ASSESSMENT 1. Samoa is composed of about 10 islands, 4 inhabited, and several uninhabited islets situated
Wastewater Who to ask: wastewater operator, health aides, public health nurse
Wastewater Wastewater Who to ask: wastewater operator, health aides, public health nurse 35. Have there ever been any outbreaks of sewage related diseases in the village? If yes, what diseases and when?
Understanding Septic Tank Systems
Understanding Septic Tank Systems Sewage and effluent can contain a variety of human disease-causing microorganisms and parasites. Disease can be spread to humans from this material by direct contact or
A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS
GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management
KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011
KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email [email protected]
FREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS VILLAGE OF CORRALES WASTEWATER UTILITY (SEWER) SYSTEM AND INDIVIDUAL PROPERTY OWNER SERVICE CONNECTIONS I. AVAILABILITY OF SEWER SERVICE; WHEN CONNECTION IS REQUIRED. Q. Where
Pay Later: The Cost of Inaction
FACTS NEVADA A M E R I C A N S E C U R I T Y P R O J E C T Pay Now, Pay Later: Nevada Two million people in Nevada depend on Lake Mead for daily water consumption. There is a 50% chance that it will be
Septic System Owner s Manual
Septic System Owner s Manual Sponsored by: copyright 2013 No part of this publication may be reproduced without our consent. www.callbrownies.com Brownie s Septic and Plumbing has provided quality service
Understanding and Living With Your Septic System
Chapter 9 Understanding and Living With Your Septic System Rural versus urban sewage treatment One of the big difference between rural and city life is how sewage is dealt with. Cities usually have community
Legislative Council Panel on Environmental Affairs. 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations
For discussion On 8 May 2001 Legislative Council Panel on Environmental Affairs 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations Purpose This paper seeks Members
2013-2015. Milwaukee Metropolitan Sewerage District STRATEGIC PLAN
Milwaukee Metropolitan Sewerage District STRATEGIC PLAN 2013-2015 The Strategic Plan identifies the District s strengths, weaknesses, opportunities, and threats, and provides direction and focus to help
SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.
SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage
Collection and disposal of wastewater
10 Collection and disposal of wastewater 10.1 Characteristics and hazards of wastewater from health-care establishments Wastewater from health-care establishments is of a similar quality to urban wastewater,
DID YOU KNOW... THE IMPACT OF ON-SITE SEWAGE SYSTEMS AND ILLICIT DISCHARGES ON THE ROUGE RIVER
DID YOU KNOW... THE IMPAT OF ON-SITE SEWAGE SYSTEMS AND ILLIIT DISHARGES ON THE ROUGE RIVER by Barry Johnson, P.E., M.S., amp Dresser & McKee and Dean Tuomari, Wayne ounty Department of Environment The
ECONOMIC ANALYSIS (Republic of the Marshall Islands: Public Sector Program)
Public Sector Program (RRP RMI 43321-1) A. Summary ECONOMIC ANALYSIS (Republic of the Marshall Islands: Public Sector Program) 1. The Republic of the Marshall Islands (RMI) gross domestic product (GDP)
PPG21. Pollution Prevention Guidelines. pollution incident response planning: PPG 21. 1. Introduction
PPG21 February 2004 Environmental Alliance working together Pollution Prevention Guidelines pollution incident response planning: PPG 21 These guidance notes have been drawn up to assist those developing
City of Bakersfield Public Works Department Sewer System Management Plan December 2014
City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals
WHY TREAT WASTEWATER?
CARIBBEAN ENVIRONMENTAL HEALTH INSTITUTE WHY TREAT WASTEWATER? ENVIRONMENTAL, HEALTH AND LEGAL CONSIDERATIONS The Importance of Effective Wastewater Treatment & Disposal Benefits to Hotels FORWARD In September
ATTACHED TECHNICAL ASSISTANCE: DARKHAN URBAN UTILITY INSTITUTIONAL IMPROVEMENT ACTION PLAN
Darkhan Wastewater Management Project (RRP MON 37697) ATTACHED TECHNICAL ASSISTANCE: DARKHAN URBAN UTILITY INSTITUTIONAL IMPROVEMENT ACTION PLAN A. Introduction 1. The capacity development technical assistance
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT
Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for
Mega Manila: Partnership in Action
Domestic WastewaterManagement in Mega Manila: Partnership in Action Leonor C. Cleofas Deputy Administrator Metropolitan Waterworks and Sewerage System Securing the Future Today The MWSS Privatization On
CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
Financing water supply and sanitation in the Greater Cairo area
MEDITERRANEAN COMPONENT of the EU Water Initiative (MED EUWI) Strategic Partnership on Water for Sustainable Development Lead Country: Greece MED EUWI Egypt Country Dialogue on Water Brief policy document
Package Treatment Plant Policy and Procedure
Package Treatment Plant Policy and Procedure PURPOSE There has been increased interest in the use of package treatment plants for new development proposals in the County. Current review procedures are
Chapter 14 Quiz. Multiple Choice Identify the choice that best completes the statement or answers the question.
Chapter 14 Quiz Multiple Choice Identify the choice that best completes the statement or answers the question. 1. Which of the following is NOT true regarding the Chesapeake Bay? a. it is one of many small
Technical Environmental Survey
Technical Environmental Survey The Technical Environmental Survey What is the Technical Environmental Survey? The Technical Environmental Survey includes the topics on community information (getting to
On-site Treatmentt for Domestic Wastewater in Thailand Suwanna. K. Boontanon Mahidol Univ. 2
WEPA International Workshop 2013 Cambodia On-site Treatment for Domestic Wastewater in Thailand Suwanna Kitpati Boontanon Assistant Professor, Faculty of Engineering Mahidol University February 18, 2013
On Site Sewage System Maintenance Inspections. March 2011. Building and Development Branch Ministry of Municipal Affairs and Housing
On Site Sewage System Maintenance Inspections March 2011 Building and Development Branch Ministry of Municipal Affairs and Housing Introduction The Building Code Act, 1992 and Building Code (Ontario Regulation
ESTIMATION OF PROJECT COSTS AND BENEFITS
SESSION 2.1 ESTIMATION OF PROJECT COSTS AND BENEFITS Introductory Course on Economic Analysis of Investment Projects Economics and Research Department (ERD) 2 Project Statements Comparison of costs and
A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project
Semi Annual Environmental Monitoring Report July 2013 L2557/2558 SRI: Greater Colombo Wastewater Management Project This environmental monitoring report is a document of the borrower. The views expressed
Development enquiry request
Development enquiry request Water supply and/or drainage capacity assessment for a proposed development NOTE: Please ensure all relevant sections of the application are completed and refer to the attached
Township of Terrace Bay Drinking Water System Financial Plan
Township of Terrace Bay Drinking Water System Financial Plan August 2014 Introduction Municipalities in Ontario recently adopted a full accrual accounting approach to tangible municipal assets in accordance
Country Operations Business Plan. Project Number: 26194 August 2013. Samoa 2014 2016
Country Operations Business Plan Project Number: 26194 August 2013 Samoa 2014 2016 CURRENCY EQUIVALENTS (as of 11 August 2013) Currency Unit tala (ST) ST$1.00 = $0.4256 $1.00 = ST2.3496 ADB ADF GDP IMF
ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project
ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION Lower Carmel River Floodplain Restoration and Enhancement Project I. Description of the Project and its Relationship to Other Projects in the Proposal The Lower
TITLE 6. Health and Sanitation CHAPTER 1. Health and Sanitation
TITLE 6 Chapter 1 Chapter 2 Pollution Abatement CHAPTER 1 6-1-1 Health Officer; Duties and Powers 6-1-2 Rules and Regulations 6-1-3 Health Nuisances 6-1-4 Compulsory Connection to Sewer and Water 6-1-5
Recovery of full cost and pricing of water in the Water Framework Directive
Abstract Recovery of full cost and pricing of water in the Water Framework Directive D. Assimacopoulos Professor, Department of Chemical Engineering, NTUA The Water Framework Directive (EC 2000/60) introduces
AFRICAN DEVELOPMENT BANK
AFRICAN DEVELOPMENT BANK URGENT WATER SUPPLY AND SANITATION REHABILITATION PROJECT COUNTRY: ZIMBABWE SUPPLEMENTARY GRANT Appraisal Team Regional Director Sector Director Division Manager Officer-In-Charge
PROFILE ON SHEEP AND GOAT FARM
PROFILE ON SHEEP AND GOAT FARM 21-2 TABLE OF CONTENTS PAGE I. SUMMARY 21-3 II. PRODUCT DESCRIPTION AND APPLICATION 21-3 III. MARKET STUDY AND PLANT CAPACITY 21-3 A. MARKET STUDY 21-3 B. PLANT CAPACITY
Construction Specification for Sewer Bypass Flow Pumping
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 4.01 April 2013 Pumping Table of Contents TS 4.01.01 SCOPE... 2 TS 4.01.02 REFERENCES... 2 TS 4.01.03
Operations Committee. District Engineer and Utilities Manager. Appendix A: Significance Assessment
Report To: From: Operations Committee District Engineer and Utilities Manager Date: Thursday, 3 July 2014 File reference: Document: 1227007 Appendix A: Significance Assessment Decision-making: Subject:
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington
PROJECT RISK EVALUATION METHODS - SENSITIVITY ANALYSIS
Annals of the University of Petroşani, Economics, 9(2), 2009, 33-38 33 PROJECT RISK EVALUATION METHODS - SENSITIVITY ANALYSIS MIRELA ILOIU, DIANA CSIMINGA * ABSTRACT: The viability of investment projects
Draft Water Services Strategic Plan
Draft Water Services Strategic Plan A Plan for the Future of Water Services Customer Water Wastewater Environment Growth Investment Safeguarding your water for your future Irish Water at a glance... Irish
SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE. 1. Sector Performance, Problems, and Opportunities
Climate Resilience Sector Project (RRP TON 46351) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE 1. Sector Performance, Problems, and Opportunities 1. Tonga is being affected by climate change,
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government
State of Qatar. Ministry of Environment. Intended Nationally Determined Contributions (INDCs) Report. November 19 th, 2015
State of Qatar Ministry of Environment Intended Nationally Determined Contributions (INDCs) Report November 19 th, 2015 State of Qatar is pleased to submit its Intended Nationally Determined Contributions
6. Principles of effective plumbing systems
6. Principles of effective plumbing systems This chapter summarizes the aims and objectives of a good local plumbing system that is, the drinking-water supply that serves a building and the system for
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND Wastewater Utility Overview In the late 1950 s, the Village of Old Forge began to realize the impacts of dumping sewage in the Moose River.
CAPE COD. Regional Wastewater Management Plan Understanding the Cost Factors of Wastewater Treatment and Disposal
CAPE COD Regional Wastewater Management Plan Understanding the Cost Factors of Wastewater Treatment and Disposal MARCH 2013 Table of Contents INTRODUCTION...1 COST COMPARISON OF ON-SITE, CLUSTER, SATELLITE,
Environment Agency 2014 All rights reserved. This document may be reproduced with prior permission of the Environment Agency.
Flood and coastal erosion risk management Long-term investment scenarios (LTIS) 2014 We are the Environment Agency. We protect and improve the environment and make it a better place for people and wildlife.
Frequently Asked Questions About Septic System Maintenance Inspections
Frequently Asked Questions About Septic System Maintenance Inspections 1. What is a Septic System Maintenance Inspection Program? A septic system maintenance inspection program is a formal assessment of
INCIDENT RESPONSE MANAGEMENT PLAN DECEMBER 2015
INCIDENT RESPONSE MANAGEMENT PLAN DECEMBER 2015 DOCUMENT CONTROL Document Controller: Resilience Coordinator Date of last update: December 2015 Date of next update: December 2016 HPRM reference: HW2007-900/27/9.009
What to do if sewage floods your property
What to do if sewage floods your property This leaflet will answer some of your questions and concerns, as well as give you helpful information and advice. What we will do for you Sewer flooding is unpleasant
Water resources. The main problems of pollution that need to be addressed in the country are the following:
Translated from Spanish Water resources 1. The issue of water resources At the present time, sustainable standards for the development and use of water resources are not maintained in many parts of the
CERTIFIED SEPTIC EVALUATION PREPARED FOR MATT HASHEM 1673 MT. MAJOR HWY, ALTON, NH 03810
DATE: May 31, 2013 N.H. LICENSED DESIGNER OF SUBSURFACE DISPOSAL SYSTEMS 216 Hill Road Phone & Fax: 934-6206 Franklin, NH 03235 Cell: 393-3085 CERTIFIED SEPTIC EVALUATION PREPARED FOR MATT HASHEM 1673
The City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary
CITY OF LAKEWOOD COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary MAY 2006 storage conveyance treatment performance Prepared for: City of Lakewood, Ohio Prepared by: Metcalf & Eddy of Ohio,
USING GIS TO IMPROVE SEWER LINE MAINTENANCE TO PREVENT SANITARY SEWER OVERFLOWS
USING GIS TO IMPROVE SEWER LINE MAINTENANCE TO PREVENT SANITARY SEWER OVERFLOWS Brian Hewes, Department of Earth Sciences, University of South Alabama, Mobile, Al 36688. Email: [email protected].
Foul Drainage, systems and responsibility. Environmental Protection
Foul Drainage, systems and responsibility Environmental Protection The Building Act 1984 The Building Act 1984 can be used to deal with unsatisfactory provision for drainage and appliances which are harmful
Outline feasibility study for ORET application in the health care sector
Outline feasibility study for ORET application in the health care sector In this section we outline the information needed for a proper assessment of your application for financing under the ORET program.
Recurrent Expenditure Requirements of Capital Projects. Estimation for Budget Purposes. Abstract
Recurrent Expenditure Requirements of Capital Projects Estimation for Budget Purposes Ron Hood David Husband Fei Yu Abstract This paper examines the issue of estimating recurrent costs associated with
Emergency Preparedness Guidelines
DM-PH&SD-P7-TG6 رقم النموذج : I. Introduction This Guideline on supports the national platform for disaster risk reduction. It specifies requirements to enable both the public and private sector to develop
Sewage Back-Ups: Information for Residents
Sewage Back-Ups: Information for Residents Background: Severe rainstorms, floods, and even spring thaws can put a strain on sanitary sewers and septic systems. Large volumes of storm water and ground water
CONTENTS. Figures and Tables... ii. Preface... iii. Executive Summary... iv. 1: Introduction... 1. 2: Overview of Water Infrastructure...
CONTENTS Figures and Tables... ii Preface... iii Executive Summary... iv 1: Introduction... 1 2: Overview of Water Infrastructure... 4 3: The Overall Water and Wastewater Infrastructure Gap... 9 4: Regional
Water Rate Study & O.Reg.453/07 Water Financial Plan No.103-301A
March 2, 2012 dfa DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 33 Raymond Street St. Catharines Ontario Canada L2R 2T3 Telephone: (905) 938-0965 Fax: (905) 937-6568 March
ALL YOU NEED TO KNOW...
ALL YOU NEED TO KNOW... What do you know about your septic tank system? For the purposes of this booklet, a septic tank system refers to any kind of on-site sewage management system including traditional
Fiscal Impact Analysis of the Annexation Proposed by the Town of Beaumont. Leduc County FINAL REPORT
Fiscal Impact Analysis of the Annexation Proposed by the Town of Beaumont Leduc County FINAL REPORT Suite 2220 Sun Life Place 10123 99 Street Edmonton, Alberta T5J 3H1 T 780.425.6741 F 780.426.3737 www.think-applications.com
YOUR SEPTIC SYSTEM UNCOVERED
YOUR SEPTIC SYSTEM UNCOVERED By Raymond King District Director of Environmental Health It s underground where you can t see it. You don t really understand how it works. When it doesn t work your toilets
Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
