Pakse Urban Environmental Improvement Project (RRP LAO 43316)
|
|
|
- Everett Carson
- 9 years ago
- Views:
Transcription
1 FINANCIAL ANALYSIS 1. Financial viability was assessed for solid waste management (SWM) improvements, which is the project s only revenue-earning subcomponent. 1 A financial sustainability analysis was undertaken for Pakse Urban Development Administration Authority (P-UDAA) as recipient of this investment in urban environment improvements, and as the responsible authority for operation and maintenance (O&M). A financial management assessment (FMA) was also completed for the Department of Housing and Urban Planning (DHUP) in the Ministry of Public Works and Transport (MPWT) and the P-UDAA. An FMA for Champasack DPWT (C-DPWT) was not completed, as it is a provincial department of the executing agency 2. A. Financial Viability of Solid Waste Management Improvements 2. The financial viability assessment was conducted in kip (KN), with prices expressed in constant early 2012 kip; the subcomponent investment cost included physical but not price contingency and excluded financial cost during implementation. The base case demand forecast for the SWM subcomponent was used to estimate the revenue stream. Capital and O&M costs for the subcomponent were taken from the base case engineering estimates. Capital cost included equipment replacement costs. The analysis assumes that P-UDAA will continue to apply the current SWM fee tariff, with adjustment for expected inflation, until project completion, at which time a tariff increase could be introduced to ensure recovery of the SWM subproject operating cost and a share of capital cost for future operations. 3. The P-UDAA s SWM fee tariff recognizes service needs of four different market segments: households (I), institutions (II), skip-based collection (III), and disposal at landfill site (IV). The fee tariff, adopted in 2006, was designed for full cost recovery of the service; for the households segment, the tariff incorporates cross-subsidization of low-affordability households by higher-affordability households. The current tariff provides for an average fee revenue for the complete collection and disposal service provided to the I, II and III market segments averaging about KN18,000 per month per household or institution. For the financial analysis, a fee tariff increase has been assumed that will provide for an average monthly fee revenue from segments I, II and III of KN26,000 per household or institution starting in The fee for disposal only service (section IV) has been kept unchanged for the financial analysis. Table 1 compares the new average monthly fee revenue with the average capital and O&M cost of the SWM subproject. The SWM fee tariff will be reviewed during the feasibility study preparation for the possible landfill expansion and adjustment has been made as a condition for expansion. 3 Table 1: Solid Waste Management Subproject Cost and Proposed Average User Fee (kip) Item Per Per User per Month a Kilogram Operation and Maintenance Cost ,311 Capital Cost ,941 Total Cost b ,252 Proposed average I, II and II segments user fee c 26,000 a Based on an assumed average 4.2 kilogram daily household or institutional waste generation and a 26-day month. 1 ADB Framework for the Economic and Financial Appraisal of Urban Development Sector Projects. Manila. 2 This is a summary of the Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the report and recommendation of the President [RRP]). 3 Details of the current fee tariff is in Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the RRP)
2 b Estimated cost in c c The balance of the total cost will be covered by the tipping free for disposal only service 4. Based on the above fee assumption, the financial internal rate of return (FIRR) was found to be 3.5%. This exceeds the weighted average cost of capital (WACC) of 0.4%, indicating financial viability of the SWM improvements (Table 2). Table 2: Weighted Average Cost of Capital Item ADB ADB Government Total (Loan) (Grant) Funds b Amount (KN million) 194,000 26,000 31, ,446 Weight 77% 10% 13% 100% Nominal Cost a 1.5% 0.0% 8.0% Tax Rate 35% 35% 35% Tax Adjusted Nominal Rate 1.0% 0.0% 5.2% Inflation Rate 0.5% 0.0% 5.0% Real Cost 0.5% 0.0% 0.2% Weighted Component of WACC 0.4% 0.0% 0.0% 0.4% ADB = Asian Development Bank, KN = kip, WACC = weighted average cost of capital. a Based on the Asian Development Fund loan nominal rate of 1.5% per annum for ADB, and the government nominal cost of funds of 8% per annum by Ministry of Finance statistics. b Includes community funds of KN4,300 million. 5. In a sensitivity test, the FIRR was recalculated under four scenarios, with revenue at +10% and 10%, and the investment cost at +10 and 10% of the respective base case value. In all cases, the FIRR remains above the WACC (Tables 3 and 4). Table 3: Sensitivity Analysis Scenario FIRR (%) Base case % increase in capital investment cost % reduction in capital investment cost % increase in revenues % reduction in revenues 0.6 FIRR = financial internal rate of return Table 4: Financial Internal Rate of Return (KN million), in 2012 prices Year Project Incremental Incremental Net Cost O&M Cost Revenues a Inflows , ,249 (12,377) , ,730 (867) ,433 1,329 2,230 (5,531) ,042 1,322 2, ,044 1,614 2,912 (15,745) ,917 4,454 2, ,164 4,930 2, ,425 5,413 2, ,698 5,877 3, ,989 6,356 3,367
3 Year Project Incremental Incremental Net Cost O&M Cost Revenues a Inflows ,958 3,306 6, ,068 3,734 7,403 1, ,001 7,913 3, ,290 4,282 8,435 1, ,581 8,994 4, ,754 4,894 9, ,224 9,717 4, ,572 10,149 4, ,939 10,599 4, ,327 14,893 8,566 FIRR 3.5% WACC 0.4% 13,300 ( ) = negative, FIRR = financial internal rate of return, KN = kip, NPV = net present value, O&M = operation and maintenance, WACC = weighted average cost of capital. Source: Project preparatory technical assistance consultant s estimates B. Financial Sustainability of Pakse Urban Development Administration Authority 1. Current Performance and Constraints 6. The P-UDAA s current operating performance and financial status assessment is based on a review of P-UDAA financial reports for fiscal years P-UDAA financial reporting follows the mandatory Government of the Lao People s Democratic Republic (Lao PDR) reporting system based on the cash-based International Public Sector Accounting Standards (IPSAS). Under the system, the primary financial statement is the statement of cash receipts and payments. 7. Operation and maintenance cost recovery in solid waste and septage management. P-UDAA earns user charge revenues sufficient to recover O&M cost, with a small surplus. SWM revenue and cost are predominant. The solid waste user charge tariff is designed to recover cost while spreading the cost burden on the basis of differential willingness to pay and affordability. 8. Operation and maintenance cost, fee revenue, and external support in collective urban services. Services provided to the community collectively comprise drainage, stormwater management, public lighting and maintenance of traffic signs and signals, upkeep of public green spaces, and riverbank erosion management. To defray the cost of collective services, P-UDAA is implementing various approved fees, including a contribution to wastewater management and public lighting, sign adverts and billboards, building permit fees, and rental for use of public space. Imbalance has been substantial and persistent between revenues collected and the O&M cost of collective urban services. 9. Some high operating costs receiving external support. Public lighting, on a monthly average, costs close to the same as the total SWM user charge revenue. Previously, the surcharge collected on metered electricity consumption has met resistance from retail electricity users and has been unpopular with the electricity authority. Collective wastewater management service (i.e., drainage) has met with the same response from metered users of revenue water and the provincial nam papa (water utility). Provincial and central support is currently provided in the form of accounts receivable of the two state-owned utilities; this support modality should be converted to a public service obligation. The subsidy provided may be justified given Pakse s critical administrative and economic role in Champasack Province.
4 Once the subsidy for these two basic services is taken into account, the imbalance between the collective services revenue and operating cost becomes less significant Appropriateness of urban obligation fee. The urban obligation fee related to property value (including land value) is an approved P-UDAA fee, which has not been implemented by any UDAA in the country, although it appears to have large revenue generating potential. There is a strong subregional cultural preference for investing in land and property, not for recurrent income but as a means of accumulating savings. The Lao PDR has an existing tax of a graded flat amount per square meter on land distinguished into three categories the highest charge is on land with access to public amenities and the lowest is on agricultural land. In this context, a levy (or fee) based on regularly assessed property value (i) introduces an added regulatory risk to property investment, (ii) can create cash flow issues for the property owner, and (iii) appears an unjust penalty for an activity accepted as worthy. With a strategy of employing land concession to raise public revenue, the government s interest is aligned with a property-owner resistance to a property-value based benefits levy. Hence, developing a fiscal mechanism for funding the new collective service operating cost may be a better alternative. 2. Operation and Maintenance Approach 11. Project solid waste management fee tariff. Based on discussions with P-UDAA and the private sector, and with future adjustments as noted above, the current SWM tariff structure will be implemented under the project by the concession and P-UDAA. 5 It has been proposed that P- UDAA will hold a 20% share of the waste processing concession but will retain waste collection and disposal, and disposal of waste brought to the landfill (tipping fee). The details will be reviewed during implementation, as amendments are proposed to the existing concession contract. 12. Exploration of new revenue sources. P-UDAA senior management plans to explore new revenue sources to help supplement the O&M expenses of nonrevenue earning subcomponents. Pakse is the administrative and commercial capital of Champasack and its commercial positioning affects the economy of Champasack and the neighboring provinces of Saravanh, Sekong, and Attapeu. It also receives thousands of tourists from Cambodia, Thailand, and Viet Nam. 6 Hence, the beneficiaries of an effective and efficient urban infrastructure in Pakse include (i) residents of the four provinces, (ii) domestic travelers to the four provinces, and (iii) international travelers arriving at international borders in Champasack. On the principle that the beneficiaries should bear the cost of Pakse s urban amenities, it will be justified to fund that cost from (i) local government revenue, (ii) revenue apportioned between the central and local levels of government, and (iii) tourism establishments in Champasack. 13. Some ideas will be explored further during implementation with P-UDAA, which will require extensive consultation with government agencies, local business establishments, the chamber of commerce, tourists, residents, and other stakeholders. These include (i) a possible Pakse environmental levy (PEL) to fund the recurrent cost of urban infrastructure and services O&M 7 (alternative revenue sources will also be explored, e.g., surcharge on the sales of the hospitality trade); (ii) an urban services charge on commercial businesses and tourism establishments such as hotels, restaurants, and guesthouses; and tour companies; and (iii) 4 P-UDAA s operating performance for fiscal years in Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the RRP). 5 Table 1 in Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the RRP). 6 Pakse Tourism Development (accessible from the list of linked documents in Appendix 2 of the RRP). 7 Local government revenue and the revenue apportioned between the central and local government as defined in the Budget Law (2006) is intended to be used to fund the capital cost of urban infrastructure and services.
5 establishment of a recycling program in Pakse, whereby an accreditation system may be established awarding commercial business with a Green Pakse Certificate. 14. A financial statement analysis of P-UDAA was conducted to examine its financial sustainability under its responsibility to operate and maintain the project s urban improvements, assuming a PEL is implemented. Such an analysis helps to illustrate the type of impact such a levy (or an alternative source of income) could have on the financial sustainability of P-UDAA. However, it must be noted that the introduction of any new fee or levy will require that P-UDAA gains the target group s concurrence and willingness to pay. The fee or levy will need to have a successful appeal to the principle of fair beneficiary cost-sharing. It also needs clarity in communication of its rationale and purpose; transparency in information disclosure on the use of funds raised; and a fee collection method that safeguards the revenue, is efficient, and does not aggravate the visitors. The institutional development output will include an assignment to assist P-UDAA in developing a detailed design and implementation plan for an alternative revenuegenerating source. 8 C. Financial Management Assessment 15. A financial management assessment was undertaken of the DHUP and P-UDAA in their respective roles of prospective executing agency on behalf of the MPWT, and potential implementing agency and home of the project management and implementation unit (PMIU). Findings show that the DHUP, as the MPWT department responsible for urban development and water supply and sanitation, has experience managing externally financed projects in urban development and in water supply and sanitation. 9 The findings show that P-UDAA has skilled top management and senior financial and accounting management staff who have been with the organization since its creation and who have some experience of implementing an ADBfinanced project through their involvement with the Secondary Towns Development Project The DHUP has consistently applied the project accounting system developed under ADB-supported technical assistance in For the proposed project, the accounting system will be dedicated to the recording, reporting, and financial control of project financial transactions. If found necessary after review, adjustments will be made to this accounting system to ensure a more effective system tailored to the requirements of the project. 17. The project implementation arrangements are similar to those described in the fund flow arrangements, with annual audits conducted by the State Organization of Audit. The project will include support for (i) assignment of senior accounting and financial management staff to oversee DHUP s responsibilities in the project coordination unit, and P-UDAA s responsibilities in the PMIU; (ii) introductory training on project accounting, disbursements, and procurement for project coordination unit and PMIU staff; (iii) on-the-job training by existing project implementation staff from an ongoing ADB-supported urban development project located in the DHUP; and (iv) project management implementation consultant services support. Hence, it is considered that the DHUP and P-UDAA would be capable bodies for their designated executing and implementing agency roles in implementing the project. 8 Details in the Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the RRP). 9 ADB projects in the Development Coordination (accessible from the list of linked documents in Appendix 2 of the RRP). 10 ADB Completion Report: Secondary Towns Urban Development Project in the Lao PDR. Manila. Details in the Complete Financial Analysis (accessible from the list of linked documents in Appendix 2 of the RRP). 11 ADB Capacity Building in Project Accounting in the Lao PDR, Viet Nam, and Cambodia. Manila (TA 5689-REG).
FINANCIAL ANALYSIS. A. Introduction and Methodology
Coastal Towns Environmental Infrastructure Project (RRP BAN 44212) FINANCIAL ANALYSIS A. Introduction and Methodology 1. The Coastal Towns Environmental Infrastructure project finances basic urban service
OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.
Page 1 of 4 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. FINANCIAL MANAGEMENT, COST ESTIMATES, FINANCIAL
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS 122 HANDBOOK FOR THE ECONOMIC ANALYSIS OF WATER SUPPLY PROJECTS CONTENTS 5.1 Introduction...123 5.2 Financial Revenues...124 5.3 Project Costs...126 5.3.1 Investments...127
FINANCIAL AND ECONOMIC ANALYSES
Tonga-Fiji Submarine Cable Project (RRP TON 44172) FINANCIAL AND ECONOMIC ANALYSES A. Introduction 1. The Tonga Fiji Submarine Cable Project will support the Government of Tonga to establish an 827 kilometer
PROGRAM IMPLEMENTATION SCHEDULE
Water Sector Improvement Program (RRP PAL 44031) A. Program Description PROGRAM IMPLEMENTATION SCHEDULE 1. The Program will support reform of the water and sanitation sector, focusing on improving policy
6 STEP 6 - PREPARING THE ACTION PLAN 2
CONTENTS 6 STEP 6 - PREPARING THE ACTION PLAN 2 6.1 USER GUIDE TO THIS STEP 2 6.2 KEY MESSAGES OF THIS STEP 4 6.3 PREPARING THE ACTION PLAN 5 6.4 PRE-FEASIBILITY STUDY 8 6.5 PREPARING AN INVESTMENT PLAN
NSSMP Technical & Financial Toolkit. Joint ADB-WB Philippine Workshop on Wastewater Management 29 January 2014
NSSMP Technical & Financial Toolkit Joint ADB-WB Philippine Workshop on Wastewater Management 29 January 2014 1 Outline I. Technical and Financial Toolkit II. Parameters used in the Financial Toolkit III.
A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
The Kingdom of Thailand: Capacity Building for the Neighbouring Countries Economic Development Cooperation Agency
Technical Assistance Report Project Number: 40137 December 2006 The Kingdom of Thailand: Capacity Building for the Neighbouring Countries Economic Development Cooperation Agency The views expressed herein
Revenue and Financing Policy
Revenue and Financing Policy The Revenue and Financing Policy explains how the Council funds each activity it is involved in and why. Council provides a number of distinct activities and services to its
A Quick Guide to Municipal Financial Statements MUNICIPAL AFFAIRS
A Quick Guide to Municipal Financial Statements MUNICIPAL AFFAIRS June 2010 Alberta Municipal Affairs (2010) A Quick Guide to Municipal Financial Statements Edmonton: Alberta Municipal Affairs For more
ATTACHED TECHNICAL ASSISTANCE: DARKHAN URBAN UTILITY INSTITUTIONAL IMPROVEMENT ACTION PLAN
Darkhan Wastewater Management Project (RRP MON 37697) ATTACHED TECHNICAL ASSISTANCE: DARKHAN URBAN UTILITY INSTITUTIONAL IMPROVEMENT ACTION PLAN A. Introduction 1. The capacity development technical assistance
REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18
REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18 COUNTY EXECUTIVE MEMBER, FINANCE, PLANNING AND COUNTY DEVELOPMENT LAIKIPIA COUNTY February 2014 i EXECUTIVE
SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES 1. 1. Sector Performance, Problems, and Opportunities
Country Partnership Strategy: Kyrgyz Republic, 2013 2017 SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES 1 Sector Road Map 1. Sector Performance, Problems, and
Proposed Loan and Administration of Grant Urban Environment and Climate Change Adaptation Project (Viet Nam)
SUMMARY PROCEDURE FOR OFFICIAL USE ONLY R132-15 6 November 2015 Proposed Loan and Administration of Grant Urban Environment and Climate Change Adaptation Project (Viet Nam) 1. The Report and Recommendation
FINANCIAL MANAGEMENT AND PERFORMANCE ASSESSMENT
Power Transmission Rehabilitation Project (RRP ARM 46416-002) A. Introduction FINANCIAL MANAGEMENT AND PERFORMANCE ASSESSMENT 1. An assessment on the financial management capacity and financial performance
Draft Revenue and Financing Policy
Draft Revenue and Financing Policy Introduction The Local Government Act 2002 (LGA) requires every local authority to adopt a Revenue and Financing Policy and incorporate it into the LTP. The Revenue and
Town of Mattawa Asset Management Plan. December 2013
Town of Mattawa Asset Management Plan December 2013 2 P a g e Town of Mattawa Asset Management Plan Executive Summary This Asset Management Plan is intended to describe the infrastructure owned, operated,
9.1 Draft Revenue and financing policy
1. Policy purpose and overview The purpose of the Revenue and financing policy is to provide predictability and certainty about sources and levels of funding available to the council. It explains the rationale
SECTOR ASSESSMENT (SUMMARY): PUBLIC MANAGEMENT INVESTMENT CLIMATE
A. INTRODUCTION Increasing Competitiveness for Inclusive Growth Program, Subprogram 2 (RRP PHI P43396) SECTOR ASSESSMENT (SUMMARY): PUBLIC MANAGEMENT INVESTMENT CLIMATE 1. This updated assessment provides
Outline feasibility study for ORET application in the health care sector
Outline feasibility study for ORET application in the health care sector In this section we outline the information needed for a proper assessment of your application for financing under the ORET program.
1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7
Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project evaluation 5 3.0 Project feasibility 7 3.1 Defining the objectives
Guidelines for Preparing Performance Evaluation Reports for Public Sector Operations
Guidelines for Preparing Performance Evaluation Reports for Public Sector Operations January 2006 Operations Evaluation Department Asian Development Bank ABBREVIATIONS ADB Asian Development Bank EIRR economic
2014 Business Plan & Budget
2014 Business Plan & Budget Finance Department Mission Statement To support our internal and external stakeholders in bringing together people, partnerships and possibilities to be financially strong and
Fiscal Impact Analysis of the Annexation Proposed by the Town of Beaumont. Leduc County FINAL REPORT
Fiscal Impact Analysis of the Annexation Proposed by the Town of Beaumont Leduc County FINAL REPORT Suite 2220 Sun Life Place 10123 99 Street Edmonton, Alberta T5J 3H1 T 780.425.6741 F 780.426.3737 www.think-applications.com
Financing of Smart Cities. Kumar V Pratap Economic Adviser Ministry of Urban Development Government of India
Financing of Smart Cities Kumar V Pratap Economic Adviser Ministry of Urban Development Government of India Responsibilities and finances of ULBs 2 Responsibilities Water and sewerage provision; Waste
LOAN AGREEMENT (Special Operations)
LOAN NUMBER 3044-VIE (SF) LOAN AGREEMENT (Special Operations) (Secondary Cities Development Project in Quang Nam Province (Tam Ky), Ha Tinh Province (Ha Tinh) and Dak Lak Province (Buon Ma Thuot)) between
ASEAN GREEN HOTEL STANDARD
FINAL ASEAN GREEN HOTEL STANDARD Presented to the Thirty-Fifth Meeting of the ASEAN National Tourism Organization (35 th ASEAN NTOs) 8-9 January 2012 Manado, Indonesia INDEX PAGE 1. Foreword... 1 2. Introduction...
Alternative infrastructure funding and financing
Alternative infrastructure funding and financing Research Paper (commissioned by the Queensland Government) 21 March 2016 Department Of Infrastructure, Local Government and Planning This page intentionally
GOVERNANCE RISK ASSESSMENT AND MANAGEMENT PLAN
Integrated Urban Development Project (RRP NEP 42161) A. Introduction GOVERNANCE RISK ASSESSMENT AND MANAGEMENT PLAN 1. Integrating governance risk assessments more systematically into the Asian Development
PROJECT PREPARATORY TECHNICAL ASSISTANCE
A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and
Role of PPPs in Indian Smart City Mission. Kumar V Pratap Economic Adviser Ministry of Urban Development Government of India
Role of PPPs in Indian Smart City Mission Kumar V Pratap Economic Adviser Ministry of Urban Development Government of India Indian Smart City Mission 31% of Indian population lives in urban areas and contributes
Table of Contents. WATER AND WASTEWATER MODEL AND SITUATIONAL ANALYSIS 6 Model Development 6 10-Year Water/WW - Challenges, Risks and Opportunities 7
Table of Contents LONG-RANGE FINANCIAL PLAN INTRODUCTION 1 Water and Wastewater Financial Plan 2 What is a Long Range Financial Plan 3 Importance of a Long Range Financial Plan 4 General Approach to Preparing
Socialist Republic of Viet Nam: Greater Mekong Subregion Corridor Towns Development Project
Project Administration Manual Project Number: 43319-043 Loan and/or Grant Number(s): {LXXXX; GXXXX} November 2012 Socialist Republic of Viet Nam: Greater Mekong Subregion Corridor Towns Development Project
TARIFF AND GOVERNANCE ASSESSMENT
Power System Expansion and Efficiency Improvement Investment Program (RRP BAN 42378) A. Tariff Assessment 1. Introduction TARIFF AND GOVERNANCE ASSESSMENT 1. Electricity tariffs in Bangladesh are unbundled
Policies & Procedures
Budget and Business Plan 2015 Policies & Procedures POLICIES & PROCEDURES Policies & Procedures Presentation of Halton Region s Financial Information General Guidelines Halton Region prepares and presents
CAPITAL PLANNING GUIDELINES
CAPITAL PLANNING GUIDELINES 1. INTRODUCTION... 2 2. EXTENSION OF EXISTING INFRASTRUCTURE PROJECTS... 2 3. NEW CAPITAL PROJECTS... 2 4. MINIMUM INFORMATION REQUIRED... 3 5. PREPARATORY WORK... 3 5.1 NEEDS
Risk Management. Risk Identification
Management This part provides guidance on the treatment of risks on a PPP project, and; Identifies the major risks common to many PPP projects across all sectors; Allocates the identified risks between
ESTIMATION OF PROJECT COSTS AND BENEFITS
SESSION 2.1 ESTIMATION OF PROJECT COSTS AND BENEFITS Introductory Course on Economic Analysis of Investment Projects Economics and Research Department (ERD) 2 Project Statements Comparison of costs and
HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 SECTION INTRODUCTION
HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 HORNSBY SHIRE COUNCIL LONG TERM FINANCIAL PLAN 2014/15-2023/24 SECTION INTRODUCTION P1 P2 CONTENTS Executive Summary Financial Results Future
OUTPUT: RURAL ROAD ASSET MANAGEMENT
Rural Roads Improvement Project II (RRP CAM 42334) OUTPUT: RURAL ROAD ASSET MANAGEMENT A. Introduction 1. The Project. The Royal Government of Cambodia (the Government) has requested for a loan from Asian
SECTOR ASSESMENT (SUMMARY): EDUCATION 1
Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESMENT (SUMMARY): EDUCATION 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Country context. In Viet Nam, education is
Examples of Good Practice
Examples of Good Practice Cost Estimates and Financing Plans February 2015 Financial Management Unit Operations Services and Financial Management Department 1 TABLE OF CONTENTS 1 Introduction... 3 2 Investment
SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities
Country Partnership Strategy: Bangladesh, 2011 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Power generation gap. Bangladesh endures long
REPORT ON FINANCIAL PLAN, COST OF SERVICE AND RATES WATER AND SEWER OPERATING FUND
REPORT ON FINANCIAL PLAN, COST OF SERVICE AND RATES WATER AND SEWER OPERATING FUND Harford County, Maryland APRIL 2016 Black & Veatch Holding Company 2011. All rights reserved. Harford County Report on
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
SECTOR ASSESSMENT (SUMMARY): MICRO, SMALL AND MEDIUM-SIZED ENTERPRISE DEVELOPMENT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities
Small Business and Entrepreneurship Development Project (RRP UZB 42007-014) SECTOR ASSESSMENT (SUMMARY): MICRO, SMALL AND MEDIUM-SIZED ENTERPRISE DEVELOPMENT 1 Sector Road Map 1. Sector Performance, Problems,
Papua New Guinea: Supporting Public Financial Management, Phase 2
Technical Assistance Report Project Number: 44379 012 Capacity Development Technical Assistance (CDTA) November 2012 Papua New Guinea: Supporting Public Financial Management, Phase 2 The views expressed
Country Operations Business Plan. Project Number: 26194 August 2013. Samoa 2014 2016
Country Operations Business Plan Project Number: 26194 August 2013 Samoa 2014 2016 CURRENCY EQUIVALENTS (as of 11 August 2013) Currency Unit tala (ST) ST$1.00 = $0.4256 $1.00 = ST2.3496 ADB ADF GDP IMF
The Municipal Infrastructure Grant Programme
The Municipal Infrastructure Grant Programme An Introductory Guide Prepared by Department of Provincial and Local Government March 2004 TABLE OF CONTENTS 1. Introduction... 1 1.2 About this document...
Annex 4D.2. Economic and Financial Analyses - a Worked Example
Annex 4D.2 Economic and Financial Analyses - a Worked Example CONTENTS 1 WORKED EXAMPLE/ CASE STUDY 1 1.1 LAYOUT OF THE CASE STUDY 1 1.2 TRABZON AND RIZE MUNICIPALITY FINANCE 2 1.3 INVESTMENT PROGRAMME
REVENUE AND FINANCING POLICY
REVENUE AND FINANCING POLICY 1. Introduction The Revenue and Financing Policy (Policy) contains Council's policies with respect to the funding of operating expenditure and capital expenditure from various
TOWN OF RICHMOND HILL WATER AND WASTEWATER ONTARIO REGULATION 453/07 FINANCIAL PLAN
TOWN OF RICHMOND HILL WATER AND WASTEWATER ONTARIO REGULATION 453/07 FINANCIAL PLAN Financial Plan #022-301 JUNE 3, 2010 CONTENTS Page 1. INTRODUCTION 1.1 Study Purpose 1-1 1.2 Background 1-1 1.2.1 Financial
Pre-Feasibility Study Bhopal Solid Waste Management. May 2015 Executive Summary
Pre-Feasibility Study Bhopal Solid Waste Management May 2015 Executive Summary Cities Development Initiative for Asia P a g e 2 A. Rationale i. The Project 1. Bhopal is the capital and second largest city
Policy measures for the prevention and minimization of hazardous wastes
WASTE AND WASTE MANAGEMENT PROGRESS AND ACHEIVEMENTS Policy measures for the prevention and minimization of hazardous wastes 1. At the international level, Mongolia joined The Basel Convention on the Control
BRITISH COLUMBIA TRANSIT
Audited Financial Statements of BRITISH COLUMBIA TRANSIT Years ended March 31, 2005 and 2004 AUDITOR S REPORT BC TRANSIT 41 REPORT OF MANAGEMENT Years ended March 31, 2005 and 2004 The financial statements
PAI 5.08 Revised in June 2011 Page 2 of 8
Project Administration Instructions PAI 5.08 Page 1 of 8 PROJECT PERFORMANCE MONITORING A. Introduction 1. This project administration instruction (PAI) describes how the performance of ADB financed and
GOOD GOVERNANCE FRAMEWORK
Provincial Roads Improvement (RRP CAM 43309) GOOD GOVERNANCE FRAMEWORK In all instances, the Loan Agreement shall be the overriding legal document. Asian Development Bank () Procurement Guidelines (2010,
LONG-TERM FINANCIAL PLAN POLICY. Budgets FINANCE DEPARTMENT. City of Cape Town
ANNEXURE 14 LONG-TERM FINANCIAL PLAN POLICY Budgets FINANCE DEPARTMENT City of Cape Town 1 TABLE OF CONTENTS 1. DEFINITIONS AND ABBREVIATIONS... 3 2. INTRODUCTION... 4 3. PROBLEM STATEMENT... 4 4. PURPOSE...
Municipal Accounting ULB Level Reform
ULB Level Reform 1. The Reform In terms of the recommendations of the National Municipal Accounts Manual (NMAM) released by the Ministry of Urban Development MoUD, Government of India decided to introduce
SUPPLEMENTARY GREEN BOOK GUIDANCE
SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance
PPP Basics and Principles of a PPP Framework
Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership
Revenue and Financing Policy
Revenue and Financing Policy Background Section 102(4)(a) of the Local Government Act 2002 states that a local authority must adopt a revenue and financing policy. The revenue and financing policy must
THE PROJECTED ECONOMIC AND FISCAL IMPACTS OF A TENNESSEE HISTORIC REHABILITATION INVESTMENT INCENTIVE
THE PROJECTED ECONOMIC AND FISCAL IMPACTS OF A TENNESSEE HISTORIC REHABILITATION INVESTMENT INCENTIVE February 2014 Prepared by: Economic Impact Group, LLC. Copyright 2014 Economic Impact Group, LLC. EXECUTIVE
Project Finance Structuring: Case Study - Nam Theun 2
Project Finance Structuring: Case Study - Nam Theun 2 Session on Finance Sidharth Sinha Indian Institute of Management, Ahmedabad Project History 1970s - Mekong secretariat identified the hydropower potential
GMS Economic Cooperation Program
GMS Economic Cooperation Program In 1992, six countries bordering the Mekong River Cambodia, People s Republic of China (specifically, Yunnan province and later, Guangxi Zhuang Autonomous Region), Lao
Regulations for Determination of Pipeline Tariff for Natural Gas Pipelines
Draft Regulations for Determination of Pipeline Tariff for Natural Gas Pipelines Petroleum & Natural Gas Regulatory Board, New Delhi November 29, 2007 Reader may please note that this document is the property
Revenue and Financing Policy
Revenue and Financing Policy Objective Provide the funding mechanisms to ensure the equitable distribution of costs to those who benefit, and provide for the financial sustainability of the activities
Pricing Policy Statement - Excluded Retail Services. Introduction. Description of Excluded Services. Excluded Retail Services Offered in 2014/15
Pricing Policy Statement - Excluded Retail Services Introduction SA Water s Water and Sewerage Retail Services: 2013-14 to 2015-16 Revenue Determination (ESCOSA, 2013, Section 2.2) requires SA Water to
Drinking Water Quality Management System Financial Plan Number 047-101 O.Reg. 453/07
Drinking Water Quality Management System Financial Plan Number 047-101 O.Reg. 453/07 TABLE OF CONTENTS TABLE OF Contents... 2 1. INTRODUCTION... 4 1.1 MUNICIPAL DRINKING WATER LICENSING PROGRAM... 4 1.2
ASIAN DEVELOPMENT BANK Independent Evaluation Department
ASIAN DEVELOPMENT BANK Independent Evaluation Department SECTOR ASSISTANCE PROGRAM EVALUATION ON URBAN SERVICES AND WATER SUPPLY AND SANITATION SECTOR IN VIET NAM In this electronic file, the report is
Technical Assistance Report. Project Number: 42532 December 2008. Public Debt and Risk Management Forum
Technical Assistance Report Project Number: 42532 December 2008 Public Debt and Risk Management Forum ABBREVIATIONS ADB ADF Asian Development Bank Asian Development Fund DMC PDRM SDR developing member
PROGRAM EXPENDITURE AND FINANCING ASSESSMENT
Electricity Grid Strengthening Sumatra Program (RRP INO 49080) PROGRAM EXPENDITURE AND FINANCING ASSESSMENT 1. The program expenditure and financing assessment reviews the extent to which the Electricity
METHOD FOR PROJECT APPRAISAL: NET PRESENT VALUE OR NPV The sum of discounted cash flows.
OBJECTIVE: ECONOMIC ANALYSIS OF A PROJECT, consisting of the operation of a new incineration plant by the municipality. In particular we are interested in the computaton of a Solid Waste Tariff, consistent
DISTRICT OF NORTH VANCOUVER GUIDE TO FINANCIAL STATEMENTS
DISTRICT OF NORTH VANCOUVER GUIDE TO FINANCIAL STATEMENTS DISTRICT OF NORTH VANCOUVER Our goal at North Vancouver District is to make information sharing and reporting convenient, accessible and relevant
EXECUTIVE SUMMARY. Asset Management Relationships and Dependencies. Introduction
EXECUTIVE SUMMARY Introduction The Asset Management Plan demonstrates sound stewardship of the Region s existing assets to support services at desired levels and to ensure the support of the Region s infrastructure
City of Brantford Water and Wastewater Ontario Regulation 453/07 Financial Plans. Financial Plan #063-301
City of Brantford Water and Wastewater Ontario Regulation 453/07 Financial Plans Financial Plan #063-301 May 26, 2015 Contents Page EXECUTIVE SUMMARY (i) 1. Introduction... 1-1 1.1 Study Purpose... 1-1
MINISTRY OF SMALL BUSINESS AND REVENUE
The ministry's mission is to promote small business growth by working in partnership with British Columbians; to streamline and simplify the regulatory system to stimulate business growth and investment,
2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation
2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation Version 1 Table of Contents Executive Summary... 5 1.1 Background... 5 1.2 State of Local Infrastructure... 5 1.3 Desired Levels
SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE. 1. Sector Performance, Problems, and Opportunities
Climate Resilience Sector Project (RRP TON 46351) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE 1. Sector Performance, Problems, and Opportunities 1. Tonga is being affected by climate change,
MACROECONOMIC AND FISCAL ASSESSMENT
Public Sector Financial Management Program (RRP SAM 46384) A. BACKGROUND MACROECONOMIC AND FISCAL ASSESSMENT 1. Samoa is composed of about 10 islands, 4 inhabited, and several uninhabited islets situated
CE Entrepreneurship. Investment decision making
CE Entrepreneurship Investment decision making Cash Flow For projects where there is a need to spend money to develop a product or establish a service which results in cash coming into the business in
CODE FOR UNDERWRITING AGENTS: SYNDICATE EXPENSES. Explanatory Note. This code was issued in a regulatory bulletin 069/00 dated 12 September 2000
CODE FOR UNDERWRITING AGENTS: SYNDICATE EXPENSES This code was issued in a regulatory bulletin 069/00 dated 12 September 2000 Explanatory Note This code has been made under the Core Principles Byelaw in
Defence Land has the same meaning as in Section 22 of the Local Government Rating Act 2002 (LGRA).
Council Policy Policy Title: Revenue and Financing Policy Responsibility: Group Manager Corporate Services First Adopted: 2006 Review Date: June 2015 Review Frequency: Three Yearly, in conjunction with
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
