Project Charter. VoIP Plan Task Force Document Version 3 Prepared by Sandra Germenis, ITS Last Edited October 19, VoIP Plan Task Force
|
|
|
- Ethan Gilbert
- 10 years ago
- Views:
Transcription
1 Prepared by Sandra Germenis, ITS Last Edited October 19, Project Charter Summary A task force of representatives from McCombs School of Business, The College of Natural Sciences, the College of Liberal Arts, the College of Communication, the Cockrell School of Engineering and Information Technology Services has been assembled to review the current needs for telephony on campus and determine the best approach to provide this service moving forward. Business Need and Background Voice over IP (VoIP) was identified through the SITAC process and prioritized by the IT Architecture and Infrastructure Committee (AIC) to be investigated as a future direction for campus telephone services. It is believed that VoIP, and changes to the way services are provided, can decrease the cost of providing telephone service while also providing increased flexibility and new features. While the current infrastructure has served campus well for over 25 years, it is time to re-examine the previous strategies. Driving the urgency for this investigation are the needs of four new buildings being constructed, whose investments could be used as a foundation for a newly vetted telephone service for campus. Some of those construction plans may even accelerate the need to transition the entire campus to VoIP delivery ahead of expected obsolescence. Additional considerations for this investigation include the current aging infrastructure and lifecycle upgrade investments being expended as a due course of business and the parallel ITS rate reviews for telephone rates and cross-subsidies. Project Description The approach for this project will be customer focused and data driven. Departments will present desired telephone service profiles in the new buildings. Based on those presentations, the working group will choose a set of features, options, services, and also funding and reliability needs. Technologies will then be architected and priced for presentation back to the relevant governance groups for input and review. Project Goals Determine an industry standards-based Voice over Internet Protocol (VoIP) architecture for telephone service on campus, to be initially deployed in four new buildings VoIP architecture will simplify provisioning and change management, address institutional needs for directory information and number identification, and plan for growth and evolving technology 1
2 VoIP architecture will be designed to provide telephone service via a central organization and distributed departmental providers at reasonable cost VoIP architecture will reduce telephone costs and seek to maximize economies of scale for campus procurements VoIP architecture will be used as an input to telephone rate setting process on campus. Initial implementation and lifecycle costs will be projected (both for campus and typical department) Reliability needs will be documented Schedule and Milestones Milestone/Deliverable Target Date Project kickoff meeting, scope and charter discussion September 13, Presentations department vision for VoIP September 27, Feature and options discussion based on presentations October 11, Finalize menu of feature and options, draft ready for Committee review Draft of Technical requirements to implement approved features & options October 25, December 13, Cost gathering and review begins January 7, 2011 February 7, 2011 Preliminary draft report with recommendations due for March 1, 2011 Committee review and approval Draft revisions complete to submit to IT governance for approval March 31, 2011 Scope The scope of this project is to define the telecom services needed by departments, the feature sets for varying levels of service and reliability levels for various services, and the desired funding models. In Scope A report detailing telephone services to support research and business functions (faculty, staff, and student workers not students) in the four new buildings, to be extended to campus Selection of telephone features and service levels (e.g. basic, business, advanced) Infrastructure requirements and impacts to other systems to deliver services beginning in fiscal years Rate recommendations for the new architecture for the next 1, 3, and 5 years Implementation time lines Levels reliability needed for services and emergency response (911) call location information Phone numbers and identity issues Pricing and funding model recommendations for the new architecture Project Charter 2
3 Out of Scope Pilot projects are out of scope Unified Communication features are out of scope for this phase of the project and should be addressed at a later date Project Management and Governance Role Name(s)/Title(s) Responsibilities Sponsor(s) Brad Englert, CIO Ensures governance groups, senior management, and other campus leaders are aware of the project s progress and that they are being properly engaged. Project Manager Project Facilitator Technical Lead Working Group Sandra Germenis; ITS Telecom Services Manager Merri Su Ruhmann, ITS Senior Technical Communicator Jay Riekenberg; ITS Telecom Engineer David Burns, Director McCombs School of Business; Patrick Boyd, IT Manager, College of Liberal Arts; Bob Gloyd, Director Cockrell School of Engineering; William Green, Director ITS Networking and Telecommunications Working Group Chair; Bryan Harold, Director College of Natural Sciences; James Lewis, IT Manager College of Liberal Arts; Toren Smith, Software Ensures all project s timeline stays on track and plan is kept updated, ensures all key parties are engaged and communicated with. Meeting facilitator, issues tracking, and project communications as needed. Subject matter expert to identify technology needed to support new features, reliability levels, scalability, and any integration requirements with the current environment. Project Charter 3
4 Committee Campus IT Governance Oversight Engineer College of Natural Sciences; Charles Soto, Director College of Communication; Patti Spencer, Director College of Natural Sciences Janice Daman, John Eckerdt, Joe TenBarge, Patti Spencer, Janet Dukerich Operational IT Committee, IT Architecture and Infrastructure Committee Review and approve findings from the work group. Project Facilities and Resources The project will determine the facilities and technologies needed for deployment. Proof of concept trials may be required. Assumptions Solutions will be based on VoIP technology There will be both central and distributed voice services provided to departments New construction projects will primarily utilize VoIP with some high reliability delivery option for life safety services Current construction project funds as well as the ITS zero-based capital voice budget will be used to fund the initial deployment of new systems in support of the upcoming large construction projects Rate reviews of ITS phone charges will happen in time to inform this process There will not be ubiquitous indoor cellular coverage or universally provided Communication Device Allowances for cell phones for all faculty, staff, and student workers Impact Analysis The departments represented by the project team will be most immediately affected as they have large building projects in construction and are scheduled to be substantially complete beginning with the Belo Center for which equipment must be purchased by 2011, approximately 7 months. All campus units and departments will be affected by this project as the service is extended across campus. ITS currently provides telephone services centrally, including a VoIP offering. Any changes in the way that telephone services are provisioned either centrally or distributed will affect the entire campus including rate impacts. The current telephone rate structure is subsidizing other ITS services and is in need review (see Risks). Project Charter 4
5 Constraints Levels of reliability identified as part of this project will constrain the offerings and costs Risks Department networks may constrain the VoIP offerings Construction project budgets and ITS capital budgets may also constrain service solutions Construction project timelines constrain the solutions Traditional telephone service expectations may constrain options Unified Communication features and other technologies available may create some increase in scope If cross-subsidies and historic rate structures are not reviewed and updated additional funding may be required Supporting ITS telephone customer base: o o 1) If more affordable/responsive services are not offered, the customers may move to alternative services so quickly that the remaining base would not be economically viable 2) If the base moves to quickly to a newer ITS offering, the existing system might not be economically viable. Revision History Version Date Description V 1 Sept. 13, Initial draft completed V 2 Sept. 24, Committee draft V 3 Oct. 15, Exec committee reviewed Signatures Formal written signoff. Name Role Signature Date William Green Work Group Chair Brad Englert Sponsor Committee Janice Daman, John Eckerdt, Joe TenBarge, Patti Spencer, Janet Dukerich Project Charter 5
VoIP Deployment Committee Charter
Version 1.6 Prepared by William Green, ITS Last Edited October 30, 2012 Charter Summary A task force and executive committee of representatives from the College of Natural Sciences, Cockrell School of
DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The project will document campus requirements for IAM functionality and select and procure one or more technology
Project Charter. Identity & Access Management Strategy. Executive Summary. Business Need and Background. Document Version 1.
August 30, 2012 Executive Summary The Identity and Access (IAM) Strategy project will provide a roadmap for implementing a comprehensive and full- featured set of IAM services to encourage collaboration,
Project Charter. Office 365 2015 Migrations Document Version 2.0 Prepared by Sabina Winters, ITS Last Edited February 19, 2015
Prepared by Sabina Winters, ITS Last Edited February 19, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary In December of 2014, the IT Governance Architecture
Project Charter. UT Web Infrastructure Project Document Version 9.0 Prepared by John Lovelace & David Moss Last Edited March 13, 2012
Prepared by John Lovelace & David Moss Last Edited March 13, 2012 Project Charter UT Web Infrastructure Project Executive Summary The goal of this project is to select and implement a solution that will
IT Architecture and Infrastructure Committee
IT Architecture and Infrastructure Committee 9:00 10:30 a.m., September 11, 2015, FAC 228D I. Committee Member Introductions II. IT Governance Overview (Brad Englert) III. Building Access Control System
DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE. This project is part of the Identity and Access Management Roadmap.
April 5, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The (CARE) project will improve the resiliency of the UTLogin, Shibboleth, and Active Directory
CASI Project Charter. Centralized Authentication System Implementation. Executive Summary. Business Need and Background
Prepared by Kara Nicholas, ITS Executive Summary The (CASI) project involves the development and release of a new UT EID- based authentication, to replace the aging Central Web Authentication (CWA). CASI
Information Technology Services ServiceNow: Change Management Phase I Project Charter
ServiceNow: Change Management Phase I Project Charter VERSION: 1.3 REVISION DATE: 9/28/2011 Approval of the Project Charter indicates an understanding of the purpose and content described in this deliverable.
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
Unified Communications and Desktop Integration
S T R A T E G I C W H I T E P A P E R Unified Communications and Desktop Integration Unified communications (UC) is recognized as one of the top strategic new technology areas in IT operations. The Alcatel-Lucent
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
Task Force Charter. Mobile Strategy Document Version 3.0 Chief Information Officer, ITS Last Edited December 17, 2012.
Chief Information Officer, ITS Last Edited December 17, 2012 Task Force Charter Mobile Strategy Executive Summary The mobile strategy will provide the policies, best practices, mobile website and application
Standards for Developing and Implementing Administrative Systems at UC Davis
Page 1 of 7 Standards for Developing and Implementing Administrative Systems at UC Davis Introduction The purpose of this document is to describe Standards for Developing and Implementing Administrative
DELAWARE CENTER FOR EDUCATIONAL TECHNOLOGY
DELAWARE CENTER FOR EDUCATIONAL TECHNOLOGY ACTION PLAN FY2003 NOVEMBER 2001 STATE OF DELAWARE Introduction Delaware Center for Educational Technology Action Plan The Delaware Center for Educational Technology
[BSU Mobile] [Version Number 1.2] Project Charter. Bridgewater State University Information Technology. BSU Mobile. Project ID: 209358
Project Charter Bridgewater State University Information Technology BSU Mobile Project ID: 209358 VERSION: [1.2] REVISION DATE: [10 May 2013] i Contents Section 1. Project Overview... 1 1.1 Problem Statement...
Project Charter. Secure Message System Upgrade
Prepared by Cooper Henson, ITS Last Edited March 24, 2014 Project Charter Secure Message System Executive Summary The Secure Message System provides authorized employees in The University of Texas System
GTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
IT Governance Overview
IT Governance Overview Contents Executive Summary... 3 What is IT Governance?... 4 Strategic Vision and IT Guiding Principles... 4 Campus-Wide IT Strategic Vision... 4 IT Guiding Principles... 4 The Scope
Data Center Consolidation: Lessons From The Field. John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy
Data Center Consolidation: Lessons From The Field John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy Agenda Factors to consider Technology strategy Building a project team How to use vendors wisely
Project Charter Updated
Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document
Enterprise Directory Project Pre-Feasibility Study Information and Educational Technology
UC DAVIS: OFFICE OF THE VICE PROVOST INFORMATION & EDUCATIONAL TECHNOLOGY Enterprise Directory Project Pre-Feasibility Study Information and Educational Technology Background Unprecedented growth and an
Governance of Evaluation, Proof of Concept and Pilot Projects
Governance of Evaluation, Proof of Concept and Pilot Projects (OCIO) Government of Newfoundland & Labrador Prepared By: (PMO) Table of Contents 1.... 2 2. Definition of an Evaluation... 2 2.1 Example...
SharePoint 2013 Project Charter
Prepared by David Moss Last Edited June 27, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE SharePoint 2013 Project Charter Executive Summary The SharePoint 2013 project
Unit Specific Questions Administrative
Unit Specific Questions Administrative Name of individual completing this report: Charles D. Warner E-mail address of individual completing this report: [email protected] Goals and Mission 1. How are
Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com
WHITE PAPER Network Consulting Services Lead Enterprise Transformation Sponsored by: HP Leslie Rosenberg February 2011 Curtis Price Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
STRATEGIC IT ACCOUNTABILITY BOARD (SITAB) AGENDA WEDNESDAY, JUNE 15, 2011 2:30 3:30 p.m. STARK LIBRARY
STRATEGIC IT ACCOUNTABILITY BOARD (SITAB) AGENDA WEDNESDAY, JUNE 15, 2011 2:30 3:30 p.m. STARK LIBRARY Attendees: William Powers Alex Albright, Jay Boisseau, Pat Clubb, Brad Englert, Rod Hart, Kevin Hegarty,
20-20 Voice and Data Switching System. Building a Better Communications Network
20-20 Voice and Data Switching System Building a Better Communications Network Teltronics. Understanding VoIP In today s competitive business environment, we all face challenges but the decision of integrating
How To Make A Multi-Line Phone A Multi Line Phone A Money Maker
Fixed Mobile Convergence Brough Turner Senior Vice President, Chief Technology Officer http://blogs.nmscommunications.com/communications NMS at a Glance Founded in 1983, publicly traded since 1994 Technology
ivoice Networks Pte Ltd
ivoice Networks Pte Ltd 1 North Bridge Road, #19-04/05 High Street Centre, Singapore 179094 Phone: +65 31080707 - Fax: +65 68264115 www.ivoice.sg Company Highlights Name of Company: Registration No: SBO
Company A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
Cloud Based Email and Collaboration Project Charter
Cloud Based Email and Collaboration Project Charter Business Case Analysis Phase Version 0.9.5 May 23, 2012 Prepared by: Carol Gravatt Project Directors: Bob Micielli, DNR Dave Kirk, OCIO Document Revision
The University of Alabama at Birmingham. Information Technology. Strategic Plan 2011 2013
The University of Alabama at Birmingham Information Technology Strategic Plan 2011 2013 Table of Contents Message from the Vice President... 3 About UAB... 4 About UAB Information Technology Meeting needs
That the Board of Regents approve ASU upgrading its current Avaya Definity PBX System.
Page 1 of 5 EXECUTIVE SUMMARY ACTION ITEM: ASU Avaya Definity PBX System Upgrade ISSUE: ASU s current Avaya Definity PBX system can not support the current release of the operating system. To allow us
How To Write A System Replacement Plan
BUSINESS SERVICES COMMITTEE (BSC) Meeting Agenda May 11, 2012 2:00 pm to 3:30 pm FAC 228D I. Identity Management Strategy (C.W. Belcher) II. imodules (John McCall) III. Administrative System Master Plan
LDAP Authentication Configuration Appendix
1 Overview LDAP Authentication Configuration Appendix Blackboard s authentication technology is considered a focal point in the company s ability to provide true enterprise software. Natively, the Blackboard
UNIVERSITY OF WISCONSIN SYSTEM INFORMATION TECHNOLOGY SUMMARY FISCAL YEAR 2015
UNIVERSITY OF WISCONSIN SYSTEM INFORMATION TECHNOLOGY SUMMARY FISCAL YEAR 2015 This page intentionally left blank. UW System IT Summary FY 2015 Page 2 CONTENTS INTRODUCTION... 5 GENERAL IT SERVICES...
Managed Hosted IP Telephony Services shared services for Government One Network. One Planet. Infinite Possibilities.
Managed Hosted IP Telephony Services shared services for Government One Network. One Planet. Infinite Possibilities. www.globalcrossing.com Managed Hosted IP Telephony Services Government organisations
Drupal Foundation Project Charter
Prepared by Christina Konstantinidou, ITS Last Edited February 10, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Drupal Foundation Project Charter Executive Summary
Project Plan. Executive Summary. Minnesota Geospatial Commons Test Implementation. Project Name: Minnesota Geospatial Commons Test Implementation
Project Plan Project Name: Minnesota Geospatial Commons Test Implementation Date: 06/07/2010 Version: 1.3 Prepared By: Mark Kotz A Executive Summary Business Need/Opportunity The Minnesota geospatial community
VoIP / SIP Planning and Disclosure
VoIP / SIP Planning and Disclosure Voice over internet protocol (VoIP) and session initiation protocol (SIP) technologies are the telecommunication industry s leading commodity due to its cost savings
Under moderate supervision, tests and troubleshoots hardware and/or software problems, makes repairs. May supervise or provide leadership to staff.
Information Technology University of Kansas Job Title Definitions Job Family Definition: Provides functional and/or technical support of software and hardware in the conceptualization, creation, development,
Microsoft Active Directory Project
Microsoft Active Directory Project Simcoe County District School Board Project Kick-off Meeting Rami Wehbe (Solution Architect) January 18, 2012 Agenda Introductions Project objectives and drivers Approach
State of Minnesota IT Governance Framework
State of Minnesota IT Governance Framework June 2012 Table of Contents Table of Contents... 2 Introduction... 4 IT Governance Overview... 4 Process for Developing the New Framework... 4 Management of the
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
University of Wisconsin Platteville IT Governance Model Final Report Executive Summary
University of Wisconsin Platteville IT Governance Model Final Report Executive Summary February 2013 Project Objectives & Approach Objectives: Build on the efforts of the Technology Oversight Planning
Ten Steps to a Successful Business Phone System Implementation. By Clare Kaufman
Ten Steps to a Successful Business Phone System Implementation By Clare Kaufman Contents Introduction...2 Planning a Business Phone Solution...2 1. Define business requirement...3. 2. Line Up Technical
Wireless & Mobile. Working Group
Wireless & Mobile Working Group Table of Contents 1 Executive Summary... 3 2 Mission & Motivation... 3 3 Scope... 3 4 Goals & Non-Goals... 4 5 Deliverables... 5 6 Milestones... 6 7 Example Use Cases Summaries...
ELECTRONIC FILE STORAGE. Laurie Hafner Dahms Mark Wilson. David Bronder
ELECTRONIC FILE STORAGE Project Information Project Team Leads: Project Manager: Laurie Hafner Dahms Mark Wilson David Bronder TeamDynamix Project Number: 241112 Project Overview Centralize standard electronic
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
2007 Magnus.net All rights reserved. Next Generation Enterprise Network Architecture
2007 Magnus.net All rights reserved. Next Generation Enterprise Network Architecture Global Enterprise Business undergone major transformations Global enterprise is no longer Fortune 500 company Commoditization
Project Processes. Media Snapshot. Project Management Process Groups
Project Processes PROJECT LIFECYCLE A project normally requires a number of processes. A process is a series of actions directed toward a particular result Project management can be viewed as a number
Microsoft Office 365 Request For Proposal
Microsoft Office 365 Request For Proposal A survey of the formal RFP process currently underway at The Scripps Research Institute to migrate from on premise Exchange 2007 to Office 365 Current Exchange
Mobile Software Testing Facing the Future Challenges
WWW.QUALTECHCONFERENCES.COM Europe s Premier Software Testing Event World Forum Convention Centre, The Hague, Netherlands The Future of Software Testing Mobile Software Testing Facing the Future Challenges
Federal Cloud Computing Initiative Overview
Federal Cloud Computing Initiative Overview Program Status To support the Federal Cloud Computing Direction and Deployment Approach, the ITI Line of Business PMO has been refocused as the Cloud Computing
STATE OF HAWAII CHIEF INFORMATION OFFICER AND THE OFFICE OF INFORMATION MANAGEMENT AND TECHNOLOGY UPDATE ON THE INFORMATION TECHNOLOGY STRATEGIC PLAN
STATE OF HAWAII CHIEF INFORMATION OFFICER AND OFFICE OF INFORMATION MANAGEMENT AND TECHNOLOGY REPORT ON UPDATE ON THE INFORMATION TECHNOLOGY STRATEGIC PLAN DECEMBER 2011 SUBMITTED TO THE TWENTY-SIXTH STATE
Cancer Treatment Centers of America Enhances Patient Care and System Efficiency with Rock-Solid Architecture
Cancer Treatment Centers of America Enhances Patient Care and System Efficiency with Rock-Solid Architecture Cisco Solution Helps Improve Communication, Increase Patient Outreach, and Fuel Growth for Unique
State-of-the-Art Headquarters Includes Centralized Physical Security
Customer Case Study State-of-the-Art Headquarters Includes Centralized Physical Security EXECUTIVE SUMMARY Alexander Forbes Financial Services Johannesburg, South Africa Approximately 4,000 Employees BUSINESS
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the