PMP Test C05_ A Work Breakdown Structure numbering system allows project team to:
|
|
- Prosper Jefferson
- 7 years ago
- Views:
Transcription
1 PMP Test C05_ A Work Breakdown Structure numbering system allows project team to: A. Systematically estimate costs of work breakdown structure elements. B. Provides project justification. C. Identify the level at which individual elements are found. D. Uses it in project management software. 02. The Work Breakdown Structure can best be thought of as an effective aid for communications. A. Team. B. Project manager. C. Customer. D. Stakeholder. 03. Which of the following is the key attribute of scope verification? A. More complete project scope management plan. B. Customer acceptance of project deliverables. C. Improved schedule estimates. D. An improved project management information system. 04. During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages? A. WBS dictionary. B. Activity list. C. Preliminary project scope statement. D. Project scope management plan. 05. During what part of the project management process is the project scope statement created? A. Initiating. B. Planning. C. Executing. D. Monitoring and controlling. 06. The program was planned years ago before there was a massive introduction of new technology. While planning the next project to start in this program, the project manager has expanded scope definition because as a project becomes more complex, the level of uncertainty in the scope. A. remains the same B. decreases C. decreases then increases D. increases 07. A project management plan should be realistic in order to be used to manage the project. Which of the following is the best method to achieve a realistic project management plan? Página: 1
2 A. Sponsor creates the project management plan based on input from the project manager. B. Functional manager creates the project management plan based on input from the project manager. C. Project manager creates the project management plan based on input from senior management. D. Project manager creates the project management plan based on input from the team. 08. A new project manager is being mentored by a more experienced certified project management professional (PMP). The new project manager is finding it difficult to find enough time to manage the project because the product and project scope are being progressively elaborated. The PMP mentions that the basic tools for project management, such as a work breakdown structure, can be used during project executing to assist the project. For which of the following can a work breakdown structure be used? A. Communicating with the customer. B. Showing calendar dates for each work package. C. Showing the functional managers for each team member. D. Showing the business need for the project. 09. During a project team meeting, a team member suggests an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work and only the work required. This is an example of: A. Change management process. B. Scope management. C. Quality analysis. D. Scope decomposition. 10. When should scope verification be done? A. At the end of the project. B. At the beginning of the project. C. At the end of each phase of the project. D. During the planning processes. 11. The project is mostly complete. The project has a schedule variance of 300 and a cost variance of All but one of the quality control inspections has been completed and all have met the quality requirements. All Items in the issue log have been resolved. Many of the resources have been released. The sponsor is about to call a meeting to obtain product verification when the customer notifies the project manager that they want to make a major change to the scope. The project manager should: A. Meets with the project team to determine if this change can be made. B. Asks the customer for a description of the change. C. Explains that the change cannot be made at this point in the process. D. Informs management. 12. You have just joined the project management office after five years of working on projects management. One of the things you want to introduce to your company is the need to do WBSs. Some of the project managers are angry that you are asking them to do "extra work." Which of the following would be the BEST thing you could tell the project managers to convince them to use WBSs? Página: 2
3 A. Tell them it will prevent work from slipping through the cracks. B. Tell them that it is mandatory. C. Tell them it is required if the project involves contracts. D. Tell them it is the only way to identify risks. 13. A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to him, he asks you what software he should use to create the WBS and what should he do with it when he is finished creating it. You might respond that it is not the picture that is the most valuable result of creating a WBS. It really is: A. A bar chart. B. Team content agreement. C. Activities list. D. A list of risks. 14. To manage a project effectively, work should be broken down into small pieces. Which of the following does not describe how maximum far to decompose the work? A. Until it has a meaningful conclusion. B. Until it cannot be logically subdivided further. C. Until it can be done by one person. D. Until it can be realistically estimated. 15. A project manager may use it to make sure the team clearly knows what work is included in each of their work packages: A. The project scope statement. B. The product scope. C. A WBS dictionary. D. A schedule. 16. A project manager has just been assigned to a new project and has been given the project charter. The first thing the project manager must do is: A. Create a project scope statement. B. To get all the stakeholders requirements. C. Analyze overall project risk. D. Begin work on a quality management plan. 17. The construction phase of a new software product is near completion. The next phase is testing and implementation. The project is two weeks ahead of schedule. What should the project manager be most concerned with before moving on to the final phase? A. Verify Scope. B. Perform quality control. C. Performance reports. D. Cost control. 18. You are managing a six-month project and have held bi-weekly meetings with your project stakeholders. After five and a half months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. This situation will delay the project completion by one month. The most important process that could have prevented this situation is: Página: 3
4 A. Risk monitoring and control. B. Schedule control. C. Scope planning. D. Control scope. 19. All of the following are part of the scope baseline except the: A. Project scope management plan. B. Project scope statement. C. Work breakdown structure. D. WBS dictionary. 20. One of the stakeholders on the project contacts the project manager to discuss some additional scope they would like to add to the project. The project manager asks for details in writing and then works through the scope control process. What should the project manager do next when the evaluation of the requested scope change is completed? A. Ask the stakeholder if there are any more changes expected. B. Complete integrated change control. C. Make sure the impact of the change is understood by the stakeholder. D. Find out the root cause of why the scope was not discovered during project planning. 21. Sources of expert judgment may come from any of the following except: A. Other units within the performing organization. B. No industry executives. C. Consultants and technical professional associations. D. Industry group publications. 22. The scope management plan should include: A. Project deliverables, justifications and objectives. B. A description of how formal scope verification will be obtained and how scope changes will be handled. C. A description of how project scope will be managed, the project s product and all supporting details. D. A description of how scope changes will be integrated along with corrective actions and lessons learned. 23. All the following statements are true about outputs of scope planning except: A. Supporting details are sometimes called critical success factors. B. The project justification provides a basis for evaluating future trade offs. C. The scope statement should include the project product. D. Project objectives must include at least cost, schedule and scope estimates. 24. The scope statement should include all of the following except: A. The business need that the project was undertaken to address. B. A summary of the product description and project deliverables. C. Clear responsibility assignments. D. Project objectives or criteria that must be met for the project to be considered successful. Página: 4
5 25. Which of the following tools and techniques are commonly used in the create WBS process? A. WBS templates and decomposition. B. Identification of alternatives and decomposition. C. Product and benefit/cost analysis. D. Expert judgment and inspection. Página: 5
6 PMP Test C05_01 Solution QUESTION GROUP ANSWER 01 Scope C 02 Scope D 03 Scope B 04 Scope A 05 Scope B 06 Scope D 07 Scope D 08 Scope A 09 Scope B 10 Scope C 11 Scope B 12 Scope A 13 Scope B 14 Scope C 15 Scope C 16 Scope B 17 Scope A 18 Scope C 19 Scope A 20 Scope B 21 Scope B 22 Scope B 23 Scope A 24 Scope C 25 Scope A Página: 6
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
More informationWhat is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
More informationPROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
More informationMinnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
More informationpm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationIT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
More informationProject Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
More informationPROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationInput, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
More informationBest Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
More informationSCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationProject Time Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within
More informationProject Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More informationProject Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
More informationoutput: communications management plan
Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More informationInterpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Lewis Gray, Ph.D., PMP Abelia Fairfax, Virginia USA www.abelia.com Copyright 2002 by Abelia Corporation. All rights reserved
More informationHow to Craft a World-Class Work Breakdown Structure
How to Craft a World-Class Work Breakdown Structure Laura Miller, PMP laura.miller2@hp.com 1 Copyright Copyright 2012 2012 Hewlett-Packard Development Development Company, Company, L.P. The L.P. information
More informationProject Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
More informationProject Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
More informationProject Management Professional (PMP)
Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.
More informationChapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationTime Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
More informationIT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: ghazy@ccis.ksu.edu.sa Mobile: 0502862400
More informationProject Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: adonald@gwu.edu Objectives Basic understanding
More information10 Critical Steps to Create a Project Plan
10 Critical Steps to Create a Project Plan Elizabeth Larson, PMP, CBAP and Richard Larson, PMP, CBAP Principals, Watermark Learning, Inc. Industry Article Watermark Learning 7300 Metro Blvd, Suite 207
More informationTIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
More informationLean Six Sigma Black Belt Certification Recommendation. Name (as it will appear on the certificate) Address. City State, Zip
Lean Six Sigma Black Belt Certification Recommendation Name (as it will appear on the certificate) IQF Member Number Address City State, Zip Country We the undersigned, on behalf of the Sponsoring Organization,
More informationUSFWC Project Management Workshop May 31 st, 2014
USFWC Project Management May 31 st, 2014 Project Management Basics Project Management Basics Project Definition Why do projects fail? Pain Curve Triple Constraint Principle Progressive Elaboration vs.
More informationAt the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used?
At the end of this chapter Project Charter Describe what a project charter is and why it is critical to project success. Explain what a project scope statement is and why it is important. List the various
More informationApplication of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationKnowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationDescription of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
More informationComputing Services Network Project Methodology
Computing Services Network Project Prepared By: Todd Brindley, CSN Project Version # 1.0 Updated on 09/15/2008 Version 1.0 Page 1 MANAGEMENT PLANNING Project : Version Control Version Date Author Change
More informationModule 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
More informationEvaluability Assessment Template
Evaluability Assessment Template Evaluability Assessment Template An Evaluability Assessment examines the extent to which a project or a programme can be evaluated in a reliable and credible fashion. An
More informationCSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
More informationThe PMP Application Process
The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the
More informationA COMPARISON OF PRINCE2 AGAINST PMBOK
Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the
More informationIntroduction to Project Management
L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You
More informationThe Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
More informationQuick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
More informationManual on Training Preparation
Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training
More informationPMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
More informationSoftware Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
More informationThe Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
More informationInitiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
More informationIS&T Project Management: Project Management 101. June, 2006
IS&T Project Management: Project Management 101 June, 2006 Session Objectives Review basics management Discuss obstacles to effective management Share practices that work for you Empower you to try some
More informationPROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
More informationPROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationPartnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
More informationAppendix 3: Project Management Substation Guidelines (General Process Flow Template)
365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It
More informationThe PMP Exam Application Reference Guide
The PMP Exam Application Reference Guide Version 3.0 (4 th Ed. PMBOK Guide) September 2011 112 Townpark Dr. NW Suite 150 Kennesaw, GA 30144-3743 Toll-Free 888.568.2527 Local 770.424.3535 Fax 770.424-3565
More information200Canada Bridges Page 1 07/11/2009. Project Management: Trainee Guide Module 1 INTRODUCTION
200Canada Bridges Page 1 07/11/2009 Project Management: Trainee Guide Module 1 INTRODUCTION Bridges Social Development Project Management Training Program www.canadabridges.com http://training.canadabridges.com/
More informationpm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationCreating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting
More informationIntroduction to project management and concepts
37E01500 Project Management and Consulting Practice Introduction to project management and concepts Matti Rossi, Professor Dept. of Information and Service Economy Lecture 1, Mon 26.10.2015 Learning objectives
More informationProject Delivery Process Overview
New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation
More informationProfesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C13_01
PMP Test C13_01 1. Near the end of your last project, additional requirements were demanded by a group of stakeholders when they learned they would be affected by your project. This became a problem because
More informationIntroduction to Project Management
Introduction to Project Management Grant that we may not so much seek to be understood as to understand. ~St. Francis of Assisi Daniel B. Edds, MBA. PMP FCS GROUP WFOA Annual Conference, September 2008
More informationOrganization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
More informationComparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500
Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: office@sts.ch Phone:
More informationProject Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information
More informationA Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition
Brochure More information from http://www.researchandmarkets.com/reports/2326795/ A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition Description: A compendium of ready made
More informationINTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
More informationInternal Audit Checklist
Internal Audit Checklist 4.2 Policy Verify required elements Verify management commitment Verify available to the public Verify implementation by tracing links back to policy statement Check review/revisions
More informationProject Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
More informationPMP Project Management Professional Study Guide, Third Edition
PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
More informationGeneral Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
More informationWORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
More informationPMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
More informationSummary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
More informationSTARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP
STARTING A PROJECT Sergey V. Nesterov MD, PhD, PMP QUESTIONS to ask at the start 1. What is the situation? 2. What do you need to do? 3. Why do you need to do it? 4. What will you do? 5. How will you do
More information1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles
1. What is PRINCE2? Projects In a Controlled Environment Structured project management method Generic based on proven principles Isolates the management from the specialist 2 1.1. What is a Project? Change
More informationState of California. Contents. California Project Management Office Project Management Framework. Project Management. Framework.
Contents State of California Project Management Framework Page i Contents Overview 1 Introduction 3 8 15 Overview of the CA-PMF Document Structure and Convention Guide Discussion of Lifecycles Templates
More informationProject Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
More informationExpert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
More informationOverview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion
More informationPROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
More informationOPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
More informationThe Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
More informationUnit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
More information5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]
231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for
More informationProject Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997
Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then
More informationImportance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationA Model to Develop and Use Risk Contingency Reserve
A Model to Develop and Use Risk Contingency Reserve NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant/Agile Coach - RefineM Agenda 1. Your Expectations from this Presentation 2. Introduction Myself
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
More informationInternal Quality Assurance Arrangements
National Commission for Academic Accreditation & Assessment Handbook for Quality Assurance and Accreditation in Saudi Arabia PART 2 Internal Quality Assurance Arrangements Version 2.0 Internal Quality
More informationA Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition
A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise
More informationIT Baseline Management Policy. Table of Contents
Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...
More informationSix sigma project management
Six sigma project management Bizagi Suite Six sigma project management 1 Table of Contents Six Sigma Project Management... 3 Process Elements... 9 Project Charter... 9 Define... 11 Measure...12 Analyze...12
More information