1 SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The test questions that appear in this sample examination are retired from the CRE pool and have appeared in past CRE examinations. Since they are now available to the public, they will NOT appear in future CRE examinations. This sample examination WILL NOT be allowed into the exam room. Appendix A contains the answers to the sample test questions. ASQ will not provide scoring and analysis for this sample examination. Remember: These test questions will not appear on future examinations so your performance on this sample examination may not reflect how you perform on the formal examination. A self-appraisal of how well you know the content for the specific areas of the body of knowledge (BOK) can be completed by using the worksheet in Appendix B. On page 2 of the instructions, it states There are 150 questions on this 4-hour examination. Please note that this sample exam only contains 75 questions. If you have any questions regarding this sample examination, please [email protected] 2011 ASQ ASQ grants permission for individuals to use this sample examination as a means to prepare for the formal examination. This examination may be printed, reproduced and used for non-commercial, personal or educational purposes only, provided that (i) the examination is not modified, and (ii) ASQ s copyright notice is included. The user assumes all risks of copyright infringement.
2 THIS PAGE WAS LEFT BLANK INTENTIONALLY
3 NAME CERTIFIED RELIABILITY ENGINEER Please print your name above. Read all the instructions before beginning the examination. If you are unsure about any part of the instructions, consult your proctor. In order for ASQ to be able to properly scan the Scantron answer sheet you must completely fill in the circle. Each circle must be filled in dark enough for the scanner to properly pick up the answer you chose. If not this could result in the exam not being scored correctly, or potentially delay your results. General Instructions All answers must be recorded on the Scantron Answer Sheet; no exam will be graded with the answers marked in the exam booklet. 1. Using a soft lead pencil (#2 or softer) only, blacken the circle of the correct answer. Do not use ink. If you change your answer, be sure to erase the previous answer completely. 2. Each question has ONE correct answer only. 3. This is a timed test, so do not linger over difficult questions. Instead, skip the questions that you are unsure of and return to them if you have time when you reach the end of the test. 4. Do not fold, staple, or tear the answer sheets. 5. Although this is an open-book examination and personally generated materials/notes from training or refresher courses are allowed, the following conditions apply: Each examinee must make his/her reference materials available to the proctor for review. Absolutely no collections of questions and answers or weekly refresher course quizzes are permitted. Reference sources that contain such copy are not allowed unless the questions and answers are removed or obscured. Examples of such sources include but are not limited to refresher and preparatory primers. Calculator Policy: With the introduction of palmtop computers and the increasing sophistication of scientific calculators, ASQ has become aware of the need to limit the types of calculators that are permitted for use during the examinations. Any silent, hand-held, battery-operated calculator WITHOUT an alphabetic keyboard will be permitted. However all programmable memory must be cleared from the calculator before you enter the exam room. The examination is written so that a simple calculator will be sufficient to perform all calculations. No laptop or palmtop computers are allowed. No Cell Phones are allowed in exam room Reference materials and calculators may not be shared. 6. When you have finished, check your answer sheet to be sure it is properly identified with your name and member number. Return your examination booklet, answer sheet, and scratch paper to your proctor. You must sign the roster sheet to signify the return of your test booklet. 7. It is strictly forbidden to copy or remove examination materials. You will be disqualified from the examination and not certified by ASQ if you breach this trust. 8. TEST Results you can check your test results 7 10 days after the exam date by logging into website and navigating to the Certification webpage. Otherwise, your exam results will be mailed in approximately two weeks. Please Be Patient we do not answer telephone requests for results.
4 Special Instructions 1. Please note that your answer sheet has been personalized with your name, member number, section number, and test type. 2. Do NOT make any changes to these parts of the answer sheet. Doing so will only delay your exam results. Instead notify the Proctor of any changes. 3. If you don t have a personalized answer sheet, see your Proctor for further instructions. 4. There are 150 questions on this four-hour examination. STOP DO NOT CONTINUE UNTIL INSTRUCTED
5 CERTIFIED RELIABILITY ENGINEER Test Directions: Each of the questions or incomplete statements below is followed by four suggested answers or completions. Select the one that is best in each case and then fill in the corresponding space on the answer sheet. 1. Which of the following methods will most improve the reliability of a product? (A) Reducing confidence levels (B) Reducing variation (C) Increasing sample size (D) Increasing test time 5. Which of the following assumptions is true about degradation? (A) It is inherent and irreversible. (B) It is inherent and reversible. (C) It is unacceptable and irreversible. (D) It is unacceptable and reversible. 2. Which of the following methods can be used to quantitatively identify items that are risk-critical? (A) Design review (B) Fault-tree analysis (C) Concurrent engineering (D) Human reliability analysis 6. A parts-count reliability prediction is calculated by summing only the (A) parts failure rates (B) number of parts in the system (C) variances of the part failure rates (D) parts failure rates with application stress 3. At the design stage of a product, the first safety focus should be on which of the following? (A) Regulatory requirements (B) Production tools (C) Controls and equipment (D) End-user applications 4. Which of the following statements is true about response surface methods? (A) They can eliminate day-to-day variations in a manufacturing environment. (B) They are more efficient than two-level factorial design techniques. (C) They do not require technical considerations to implement the method. (D) They determine how an output is affected by a set of variables over a specified region. 7. A part has a constant hazard rate. If preventive maintenance is used, the part s failure probability will be affected in which of the following ways? (A) It will increase. (B) It will decrease to a fixed value greater than zero. (C) It will decrease to zero. (D) It will remain the same. 8. The use of experimental design techniques early in the process development stage generally results in (A) increased personnel and product costs (B) increased product development time (C) decreased variability around target requirements (D) decreased start-up process yields 3
6 9. A qualification test is planned to establish whether a unit meets required minimum mean time between failures (MTBF). Which of the following tools can be used to estimate the chance that the unit will pass the test even if its true MTBF is below the required level? (A) Operating characteristic curve (B) Block diagram (C) Fault tree (D) Transition state matrix 10. The reliability block diagram of a system is shown in the following figure with component reliability noted in each block. Questions refer to the following information. A reliability engineer needs to use an accelerated test plan to select a new material. The failure modes are known to be temperature-related. 11. Which of the following stress-related characteristics should be considered by the reliability engineer during the material selection stage? (A) Activation energy (B) Flexural energy (C) Tensile strength (D) Compression strength Which of the following test techniques would allow the reliability engineer to evaluate the material quickly? What is the reliability of the system? (A) (B) (C) (D) (A) Ambient temperature test (B) Step-stress test (C) Full system test (D) Durability test 13. Which of the following approaches should be used for a field validation test of the new material? (A) Implement the material change and monitor field performance. (B) Field test a sample of only the new material in the system. (C) Field test samples of both old and new material in the system. (D) Run lab tests on two systems. 4
7 14. Which of the following statements best describes the set of all values of a random variable? 18. To be most cost-effective, a corrective action should be implemented between which of the following events? (A) It is finite. (B) It is an interval. (C) It can be discrete or continuous. (D) It can be tracked by using control charts or scatter plots. After (A) Initial build (B) Final qualification test (C) Initial production (D) Field release Before Final qualification test Initial production Field release Field upgrades 15. Which of the following is the best description of randomization? (A) A technique used to increase the precision of an experiment (B) A means of assuring representative sampling (C) The repetition of an observation or measurement (D) The relationship between two or more variables 16. The hazard rate function for a device is given by and if t 10 hours if t > 10 hours What is the reliability of this device at 12 hours? (A) (B) (C) (D) In the model y = 12.1x x 2 + ε, the x 1 follows a Weibull distribution with a shape parameter of 3.5 and a characteristic life of 20; x 2 follows a lognormal distribution with a mean of 16 and a standard deviation (σ) of 2.5; and ε is a random variable with a mean of 0 and a σ of 1. In this situation, which of the following methods would be best to evaluate the distribution of y? (A) Regression analysis (B) Monte Carlo simulation (C) Analysis of variance (D) Numerical integral 20. In design of experiments, the concept of loss function is related to (A) Monte Carlo simulation (B) Taguchi methods (C) evolutionary methods (D) regression analysis 17. Fault isolation is best facilitated by using (A) trouble reports, corrective action reports, and inspection data (B) interchangeability, redundancy, and corrective maintenance (C) preventive maintenance, built-in test equipment, and design simplification (D) periodic condition inspections and correction of detected deterioration 21. A certain electronic component has a constant failure rate of /hour. A system requires the use of 64 units of this component, and all of the components must function for the system to work. What is the system failure rate? (A) /hour (B) /hour (C) hours (D) hours 5
8 22. When the order of items is not important, which of the following is the method to use to determine the number of sets and subsets of items? (A) Combination (B) Permutation (C) Factorization (D) Simulation 23. A system has four components in series with mean time between failures (MTBF) of 5,000, 6,000, 4,500 and 2,000 hours, respectively. What is the 200-hour system reliability? 26. Which of the following best offsets the implementation costs of a product safety program? 27. (A) Increased production quality (B) Increased manufacturing safeguards (C) Reduced regulatory requirements (D) Reduced liability exposure Percent failed (A) (B) (C) (D) One hundred units are subjected to a reliability test with duration 500 clock hours. During the test, 2 failures occur, at T 1 = 110 hours and at T 2 = 300 hours. The failed units are not replaced. On the basis of this sample, the one-sided 95% lower confidence limit of reliability of these units for a mission of 600 hours is (A) (B) (C) (D) Time or Cycles Which of the following can be inferred from the Weibull analysis plot above? (A) There is an initial period of time where no failures occur. (B) The analysis includes censored data. (C) More than one failure mechanism is included in the data. (D) The hazard rate remains constant. 25. A fair coin is tossed 10 times. What are the expected mean and variance of the number of heads? Mean Variance (A) (B) (C) (D) Which of the following must be known in order to establish a reliability specification? (A) The usage environment (B) The level of the system s quality (C) The company s reliability policy (D) The reliability model being used 6
9 29. Which of the following probability distributions best satisfies the inequality P(x < 0) > 0? (A) Two-parameter Weibull (B) One-parameter exponential (C) Normal (D) Lognormal 30. Which of the following is considered the most valuable source of information on actual failure modes and mechanisms? (A) Field data (B) Qualification tests (C) FMEAs (D) User profiles 34. A repair facility consists of two independent stations in a series. Repair times in hours follow normal distributions as shown below. Station Mean Standard Deviation What is the probability of completing a repair in 35 hours or less? (A) 0.65 (B) 0.71 (C) 0.92 (D) A component has strength with mean value of 9,000 N and standard deviation of 900 N. It has to withstand a load with mean value of 5,500 N and standard deviation of 800 N. Both strength and load are normally distributed. What is the probability of failure for the component? (A) (B) (C) (D) Early in the concept phase of a new product development program, which of the following methods is most effective for incorporating desired product attributes into the design? (A) Quality function deployment (QFD) (B) Failure mode and effect analysis (FMEA) (C) Fault-tree analysis (FTA) (D) Failure reporting and corrective action systems (FRACAS) 33. Which of the following is the most appropriate measure of reliability? (A) Manufacturing cost per unit (B) Service cost per unit (C) External customer satisfaction (D) Internal customer satisfaction 35. In a cross-functional team environment, the reliability function can influence product reliability primarily by (A) integrating the reliability requirements into product design (B) developing reliability tests (C) performing thorough failure analysis (D) monitoring the failure rates of various products 36. A Pareto analysis of field failure data indicates approximately equal magnitudes of the main failure modes. In this situation, the best next course of action is to look at (A) the failure mode that is least expensive to investigate (B) the failure mode that provides the highest return on investment if eliminated (C) the failure mode that is closest to no fault found (D) every possible contributor for each main failure mode 37. Which of the following types of data is best to estimate the life of a product? (A) Time-to-failure (B) Time-to-repair (C) Failure modes (D) Failure criticality 7
10 38. Which of the following techniques is used to discover design flaws and implement fixes to affect all future manufactured units? (A) Reliability growth modeling (B) Reliability physics (C) Markov modeling (D) Monte Carlo simulation 39. Which of the following is the most appropriate way to improve product reliability during the design phase? (A) Perform a worst-case analysis. (B) Track manufacturing defects. (C) Conduct supplier auditing. (D) Increase the staff on the product development team. 40. The term failure mode is defined as the (A) consequence of the mechanism through which a failure occurs (B) physical, chemical, electrical, or thermal process that results in failure (C) event or inoperable state in which an item or part of an item does not perform as specified (D) failure caused by the failure of an associated item 41. Which of the following activities is most effective in increasing reliability during a product s lifecycle? (A) Improving gage repeatability and reproducibility (B) Developing an aggressive testing strategy (C) Developing robust designs (D) Developing capable processes 42. The following ANOVA table was completed from a full factorial experiment. The object of the experiment was to determine whether the impact of factors A, B, or their interaction (AXB) was significant at the 0.95 confidence level. Source df SS A B AXB Error Total In this situation, which of the following is true? (A) Only source A is significant. (B) Only source B is significant. (C) Only the interaction (AXB) is significant. (D) All sources (A, B, and AXB) are significant. 43. In statistics, an estimation error that is persistent or systematic is called (A) bias (B) sensitivity (C) random (D) shift 44. Which of the following is designed to ensure that a structure has sufficient strength to operate in its service environment and under the loads specified? (A) Stress-strength analysis (B) Analysis of variance (C) Destructive physical analysis (D) Environmental stress characterization 8
11 45. The influence of a failure mode and effects analysis (FMEA) on reliability is maximized at which of the following stages of development? (A) Design (B) Prototype (C) Test (D) Operation 46. The two-sample t-test used in hypothesis testing assumes that the two (A) populations have the same mean (B) populations are normally distributed (C) samples are the same size (D) samples are not randomly selected 50. A system consists of five units, as shown below. X The reliability of the X unit is The other four units are identical. If the system reliability goal is , what is the minimum reliability that each of the Y units must have? (A) (B) (C) (D) Y Y Y Y 47. Before sending a corrective action notice to a supplier, a manufacturer should review which of the following? (A) The supplier s financial condition (B) Its own manufacturing schedules (C) Documented evidence of failures related to that supplier (D) All procedures, processes, and training records related to that supplier 48. Which of the following information helps determine the value of a product s reliability to the customer? (A) The failure rate and price of the product (B) A Weibull analysis of product failure data (C) An SPC analysis of product performance (D) The effectiveness of corrective action on product failure 51. If final product and preproduction test data differ, which of the following types of data would be best for evaluating product reliability? (A) Field use (B) Accelerated test (C) Monte Carlo modeling (D) Force-field analysis 52. Which of the following is the most effective technique for prioritizing critical factors for problem-solving? (A) Venn diagram (B) Scatter diagram (C) Pareto diagram (D) Cause and effect diagram 49. The most cost-effective product development phase in which to eliminate a hazard is (A) design (B) manufacturing (C) burn-in (D) field-failure analysis 9
12 53. In reliability, the most common use of the Pareto principle is in determining (A) whether the output of a process is stable (B) whether problems in a system are sporadic or chronic (C) what the defects are in a product or process (D) what defects are responsible for the majority of the problems 54. Which of the following statements is true about the bathtub curve? (A) The early phase represents wearout failures. (B) The early phase shows increasing failure rate. (C) The middle phase shows a decreasing failure rate. (D) The middle phase represents random failures. 55. Which of the following practices represents the principle of preventive maintenance? (A) Inspect periodically and repair or replace parts as necessary. (B) When parts fail, replace with good ones. (C) When parts fail, repair the failed parts. (D) Replace all parts on a regularly scheduled basis. 57. A company is in a multi-product, competitive market. Which of the following is the most appropriate strategy to help capture the maximum market share? (A) Reducing cycle time while introducing new, reliable products (B) Increasing the reliability of current products (C) Improving the capacity of manufacturing processes (D) Performing aggressive field-testing 58. Accelerated life testing is most beneficial when performed on (A) dead-on-arrival products (B) products released to manufacturing (C) products under development (D) products returned from the field 59. A system has an availability of 95% when the MTBF is 500 hours and the mean time to repair is (A) 22 hours (B) 26 hours (C) 133 hours (D) 167 hours 56. Which of the following statements is true about reliability prediction? (A) It is accurate in the determination of system failure causes. (B) It contributes directly to system reliability. (C) It forms decision criteria for selecting courses of action that affect reliability. (D) It demonstrates that a proposed design will meet its reliability requirement. 60. The x and y axes of the bathtub curve are x y (A) time reliability (B) reliability time (C) time hazard rate (D) hazard rate time 61. Which of the following is the most effective approach to minimize accidents caused by human error? (A) Provide easy access to equipment. (B) Provide clear user instructions to customers. (C) Put automatic preventive features into the products. (D) Put warning signs at the most visible locations. 10
13 62. When parts are selected for a product in development, which of the following key elements should be considered first? (A) Cost (B) Serviceability (C) Availability (D) Application 63. A certain component has its strength distributed normally with an average of 20,000 pounds per square inch (psi) and a standard deviation of 1,200 psi. The stress on the component is also normally distributed with an average of 17,500 psi and a standard deviation of 800 psi. On the basis of this information, what is the component s reliability? (A) (B) (C) (D) Correlation analysis is a technique used to measure the degree of (A) statistical relationship between two random variables (B) causal relationship between two random variables (C) goodness of fit to normal distribution (D) goodness of fit to exponential distribution 66. A fault tree analysis (FTA) differs from a failure mode and effects analysis (FMEA) in that an FTA (A) starts by considering individual or combined lowerlevel failures first (B) starts by considering system failure effects or top events first (C) does not take into account human factors such as incorrect operation (D) is typically used in conjunction with a cause and effect diagram 67. Which of the following statements is true about maintainability? (A) It should be initiated during the logistics review. (B) It should be initiated during the design stage. (C) It is primarily a field service issue. (D) It is primarily a contractual requirement. 68. Which of the following calculations is used to determine the overall tolerance for a serial combination of components? (A) The average of the tolerances (B) The maximum of the tolerances (C) The sum of the tolerances (D) The square root of the sum of the squares of the tolerances 65. When the plot of the cumulative MTBF and the cumulative operating hours on log-log paper follows a straight line, the plot is known as (A) a Weibull plot (B) a normal plot (C) a Duane plot (D) an exponential plot 69. The primary objective of reliability-centered maintenance (RCM) is to (A) obtain maintainability data (B) preserve system function (C) track maintenance training (D) characterize the downtime distribution 11
14 70. A system is comprised of units X and Y in parallel with hazard rates as shown below. Hazard rate Hazard rate 0 m 2m 3m time 0 m 2m 3m time Unit X Unit Y 72. As a result of improper machining, a gear-tooth in a vehicle s transmission breaks causing the transmission to lock up and the vehicle to crash, injuring the driver. The failure mode in this case should be identified by the reliability engineer as the (A) injured driver (B) jammed transmission (C) improper machining (D) vehicle crash 73. An electromigration model for stress testing (MTTF = AJ n e Ea KT ) is based on the (A) stresses of voltage and vibration raised to powers (B) Arrhenius temperature dependence and a constant (C) current density to a power and the Arrhenius temperature dependence (D) environmental stress screening and HALT testing If m is the scheduled replacement interval, then replacement of unit (A) X will increase failure probability of system (B) X will decrease failure probability of system (C) Y will increase failure probability of system (D) Y will decrease failure probability of system 74. Which of the following is a model used for monitoring reliability growth? (A) Duane (B) Arrhenius (C) Normal (D) Lognormal 71. Typically, which of the following distributions is used to model equipment maintenance times? (A) Lognormal (B) Gamma (C) Inverse beta (D) Exponential 75. When reliability goals are being developed, reliability predictions are initially used to (A) set goals for all portions of the life cycle of a system (B) estimate potential performance of hardware and software with respect to reliability requirements (C) measure customer needs and provide a means of defining quantitative reliability goals (D) establish a competitive position with respect to reliability STOP. IF YOU FINISH BEFORE TIME IS CALLED, YOU MAY GO BACK AND CHECK YOUR WORK ON THIS TEST. 12
15 APPENDIX A: Answer Sheet For each sample test question, the correct answer is provided below along with the area of the body of knowledge (BOK) that the item is classified to. This sample examination is not intended to represent all areas of the BOK but to provide a sampling from each major topic area. All ASQ examinations are based on the BOK for that particular exam. To view the BOK for CRE, please go to Question BOK Correct Answer 1 II.B.2 B 2 III.A.5 B 3 I.C.3 D 4 II.B.2 D 5 III.B.2 A 6 IV.B.1 A 7 VI.B.1 D 8 III.A.7 C 9 IV.B.2 A 10 IV.A.2 B 11 V.B.1 A 12 V.B.1 B 13 V.C.1 C 14 II.A.1 C 15 II.B.2 B 16 II.B.1 A 17 VI.B.4 C 18 VII.B.2 A 19 IV.A.3 B 20 III.A.7 B 21 IV.B.2 A 22 II.A.2 A 23 IV.A.2 A 24 II.B.2 B 25 II.A.3 B 26 I.C.3 D 27 VII.B.1 C 28 III.B.4 A 29 II.A.3 C 30 IV.A.1 A 31 III.A.2 B 32 I.A.7 A 33 I.A.2 C 34 VI.B.2 C 35 I.A.3 A 36 VII.B.2 B 37 VII.A.2 A 38 IV.A.3 A Question BOK Correct Answer 39 I.A.1 A 40 III.A.3 A 41 I.B.4 C 42 III.A.7 D 43 II.A.1 A 44 III.A.2 A 45 III.A.3 A 46 II.B.3 B 47 VII.A.2 C 48 I.A.1 A 49 I.C.3 A 50 III.A.12 C 51 V.A.2 A 52 VII.B.1 C 53 VII.B.1 D 54 II.A.3 D 55 VI.B.1 A 56 IV.B.2 C 57 I.B.2 A 58 V.B.1 C 59 VI.A.3 B 60 II.A.3 C 61 III.A.10 C 62 III.B.1 D 63 III.A.2 B 64 II.A.1 A 65 V.B.3 C 66 III.A.5 B 67 VI.A.1 B 68 III.A.6 D 69 VI.A.2 B 70 VI.B.1 A 71 VI.B.2 A 72 III.A.3 B 73 V.B.1 C 74 V.B.3 A 75 IV.B.2 B 13
16 APPENDIX B: Analyzing Body of Knowledge (BOK) Content The following worksheet can be used to help you analyze the results of your answers on this sample examination. It can be used to determine which areas of the body of knowledge (BOK) you may want to study. After learning which sample test questions you had correct, total the number you had correct and enter that number into the 2 nd column of the worksheet. The 3 rd column provides the total number of test questions that are in this sample examination for that major area of the BOK. The last column provides the total number of test questions that appear in a formal ASQ examination for that area of the BOK. BOK Topic Area I. Reliability Management II. Probability and Statistics for Reliability III. Reliability in Design and Development IV. Reliability Modeling and Predictions V. Reliability Testing VI. Maintainability and Availability VII. Data Collection and Use Total You Had Correct on Sample Exam Total in the Sample Exam Total in Formal ASQ Exam GRAND TOTAL
THIS PAGE WAS LEFT BLANK INTENTIONALLY
SAMPLE EXAMINATION The purpose of the following sample examination is to present an example of what is provided on exam day by ASQ, complete with the same instructions that are given on exam day. The test
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to present an example of what is provided on exam day by ASQ, complete with the same instructions that are given on exam day. The test
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to provide an example of what is provided on exam day by ASQ, complete with the same instructions that are provided on exam day. The
Certified Reliability Engineer
Certified Reliability Engineer Quality excellence to enhance your career and boost your organization s bottom line asq.org/certification Certification from ASQ is considered a mark of quality excellence
CHAPTER 1 THE CERTIFIED QUALITY ENGINEER EXAM. 1.0 The Exam. 2.0 Suggestions for Study. 3.0 CQE Examination Content. Where shall I begin your majesty?
QReview 1 CHAPTER 1 THE CERTIFIED QUALITY ENGINEER EXAM 1.0 The Exam 2.0 Suggestions for Study 3.0 CQE Examination Content Where shall I begin your majesty? The White Rabbit Begin at the beginning, and
CERTIFIED QUALITY ENGINEER (CQE) BODY OF KNOWLEDGE
CERTIFIED QUALITY ENGINEER (CQE) BODY OF KNOWLEDGE The topics in this Body of Knowledge include subtext explanations and the cognitive level at which the questions will be written. This information will
SAMPLE EXAMINATION. If you have any questions regarding this sample examination, please email [email protected]
SAMPLE EXAMINATION The purpose of the following sample examination is to present an example of what is provided on exam day by ASQ, complete with the same instructions that are given on exam day. This
CERTIFIED QUALITY ENGINEER (CQE) BODY OF KNOWLEDGE
CERTIFIED QUALITY ENGINEER (CQE) BODY OF KNOWLEDGE The topics in this Body of Knowledge include subtext explanations and the cognitive level at which the questions will be written. This information will
Certified Quality Process Analyst
Certified Quality Process Analyst Quality excellence to enhance your career and boost your organization s bottom line asq.org/certification The Global Voice of Quality TM Certification from ASQ is considered
Certified Quality Engineer
Certified Quality Engineer Quality excellence to enhance your career and boost your organization s bottom line asqmena.org/certification.php www.asqmena.org Certification from ASQ is considered a mark
"Reliability and MTBF Overview"
"Reliability and MTBF Overview" Prepared by Scott Speaks Vicor Reliability Engineering Introduction Reliability is defined as the probability that a device will perform its required function under stated
Learning Objectives Lean Six Sigma Black Belt Course
Learning Objectives Lean Six Sigma Black Belt Course The overarching learning objective of this course is to develop a comprehensive set of skills that will allow you to function effectively as a Six Sigma
Alessandro Birolini. ineerin. Theory and Practice. Fifth edition. With 140 Figures, 60 Tables, 120 Examples, and 50 Problems.
Alessandro Birolini Re ia i it En ineerin Theory and Practice Fifth edition With 140 Figures, 60 Tables, 120 Examples, and 50 Problems ~ Springer Contents 1 Basic Concepts, Quality and Reliability Assurance
Fairfield Public Schools
Mathematics Fairfield Public Schools AP Statistics AP Statistics BOE Approved 04/08/2014 1 AP STATISTICS Critical Areas of Focus AP Statistics is a rigorous course that offers advanced students an opportunity
Unit 1: Introduction to Quality Management
Unit 1: Introduction to Quality Management Definition & Dimensions of Quality Quality Control vs Quality Assurance Small-Q vs Big-Q & Evolution of Quality Movement Total Quality Management (TQM) & its
Gamma Distribution Fitting
Chapter 552 Gamma Distribution Fitting Introduction This module fits the gamma probability distributions to a complete or censored set of individual or grouped data values. It outputs various statistics
Comparison of EngineRoom (6.0) with Minitab (16) and Quality Companion (3)
Comparison of EngineRoom (6.0) with Minitab (16) and Quality Companion (3) What is EngineRoom? A Microsoft Excel add in A suite of powerful, simple to use Lean and Six Sigma data analysis tools Built for
THE SIX SIGMA YELLOW BELT SOLUTIONS TEXT
THE SIX SIGMA YELLOW BELT SOLUTIONS TEXT 2014 by Bill Wortman - All rights reserved SECTION II SIX SIGMA FUNDAMENTALS - SAMPLE QUESTIONS 2.1. The DPMO for a process is 860. What is the approximate six
BODY OF KNOWLEDGE CERTIFIED SIX SIGMA YELLOW BELT
BODY OF KNOWLEDGE CERTIFIED SIX SIGMA YELLOW BELT The topics in this Body of Knowledge include additional detail in the form of subtext explanations and the cognitive level at which test questions will
TRAINING TITLE: CAPA System Expert Certification (CERT-003)
TRAINING TITLE: CAPA System Expert Certification (CERT-003) OVERVIEW: Medical devices, biopharmaceutical, and traditional drug manufacturing companies devote an important part of their resources dealing
Business Statistics. Successful completion of Introductory and/or Intermediate Algebra courses is recommended before taking Business Statistics.
Business Course Text Bowerman, Bruce L., Richard T. O'Connell, J. B. Orris, and Dawn C. Porter. Essentials of Business, 2nd edition, McGraw-Hill/Irwin, 2008, ISBN: 978-0-07-331988-9. Required Computing
Normality Testing in Excel
Normality Testing in Excel By Mark Harmon Copyright 2011 Mark Harmon No part of this publication may be reproduced or distributed without the express permission of the author. [email protected]
An Introduction to Reliability testing
An Introduction to Reliability testing Dr Jane Marshall Product Excellence using 6 Sigma Module PEUSS 2011/2012 Reliability testing Page 1 Objectives of this session Reliability testing Accelerated life
Course Overview Lean Six Sigma Green Belt
Course Overview Lean Six Sigma Green Belt Summary and Objectives This Six Sigma Green Belt course is comprised of 11 separate sessions. Each session is a collection of related lessons and includes an interactive
Course Text. Required Computing Software. Course Description. Course Objectives. StraighterLine. Business Statistics
Course Text Business Statistics Lind, Douglas A., Marchal, William A. and Samuel A. Wathen. Basic Statistics for Business and Economics, 7th edition, McGraw-Hill/Irwin, 2010, ISBN: 9780077384470 [This
Lean Six Sigma Black Belt-EngineRoom
Lean Six Sigma Black Belt-EngineRoom Course Content and Outline Total Estimated Hours: 140.65 *Course includes choice of software: EngineRoom (included for free), Minitab (must purchase separately) or
Product Excellence using 6 Sigma (PEUSS)
Section 7 WARWICK MANUFACTURING GROUP Product Excellence using 6 Sigma (PEUSS) Introduction to Reliability AN INTRODUCTION TO RELIABILITY ENGINEERING Contents 1 Introduction 1 2 Measuring reliability 4
Data Analysis Tools. Tools for Summarizing Data
Data Analysis Tools This section of the notes is meant to introduce you to many of the tools that are provided by Excel under the Tools/Data Analysis menu item. If your computer does not have that tool
DEDICATED TO EMBEDDED SOLUTIONS
DEDICATED TO EMBEDDED SOLUTIONS RELIABILITY IN SUBSEA ELECTRONICS TECHNIQUES TO OBTAIN HIGH RELIABILITY STIG-HELGE LARSEN KARSTEN KLEPPE DATA RESPONS 2012-10-16 AGENDA Introduction Analysis and Design
Ensuring Reliability in Lean New Product Development. John J. Paschkewitz, P.E., CRE
Ensuring Reliability in Lean New Product Development John J. Paschkewitz, P.E., CRE Overview Introduction and Definitions Part 1: Lean Product Development Lean vs. Traditional Product Development Key Elements
Reliability Block Diagram RBD
Information Technology Solutions Reliability Block Diagram RBD Assess the level of failure tolerance achieved RELIABIL ITY OPTIMIZATION System reliability analysis for sophisticated and large scale systems.
A Case Study in Software Enhancements as Six Sigma Process Improvements: Simulating Productivity Savings
A Case Study in Software Enhancements as Six Sigma Process Improvements: Simulating Productivity Savings Dan Houston, Ph.D. Automation and Control Solutions Honeywell, Inc. [email protected] Abstract
Design Verification The Case for Verification, Not Validation
Overview: The FDA requires medical device companies to verify that all the design outputs meet the design inputs. The FDA also requires that the final medical device must be validated to the user needs.
Certified Six Sigma Yellow Belt
Certified Six Sigma Yellow Belt Quality excellence to enhance your career and boost your organization s bottom line asq.org/cert The Global Voice of Quality TM Certification from ASQ is considered a mark
Maps between the 2016 CSQE BOK and the previous BOK
Maps between the 2016 CSQE BOK and the previous BOK The Certified Software Quality Engineer (CSQE) body of knowledge (BOK) has recently undergone an update so that the most current knowledge areas are
Lean Six Sigma Black Belt Body of Knowledge
General Lean Six Sigma Defined UN Describe Nature and purpose of Lean Six Sigma Integration of Lean and Six Sigma UN Compare and contrast focus and approaches (Process Velocity and Quality) Y=f(X) Input
Effective Root Cause Analysis For Corrective and Preventive Action
Effective Root Cause Analysis For Corrective and Preventive Action Manuel Marco Understanding Key Principles Requirement need or expectation that is stated, generally implied, or obligatory Generally implied
THE SIX SIGMA BLACK BELT PRIMER
INTRO-1 (1) THE SIX SIGMA BLACK BELT PRIMER by Quality Council of Indiana - All rights reserved Fourth Edition - September, 2014 Quality Council of Indiana 602 West Paris Avenue West Terre Haute, IN 47885
Mathematics. What to expect Resources Study Strategies Helpful Preparation Tips Problem Solving Strategies and Hints Test taking strategies
Mathematics Before reading this section, make sure you have read the appropriate description of the mathematics section test (computerized or paper) to understand what is expected of you in the mathematics
Copyright 2010-2012 PEOPLECERT Int. Ltd and IASSC
PEOPLECERT - Personnel Certification Body 3 Korai st., 105 64 Athens, Greece, Tel.: +30 210 372 9100, Fax: +30 210 372 9101, e-mail: [email protected], www.peoplecert.org Copyright 2010-2012 PEOPLECERT
Six Sigma Continuous Improvement
Chapter 4 Six Sigma Continuous Improvement The signifi cant problems we face cannot be solved at the same level of thinking we were at when we created them. Albert Einstein 4.1 SIX SIGMA CONTINUOUS IMPROVEMENT
An Introduction to. Metrics. used during. Software Development
An Introduction to Metrics used during Software Development Life Cycle www.softwaretestinggenius.com Page 1 of 10 Define the Metric Objectives You can t control what you can t measure. This is a quote
Course Syllabus STA301 Statistics for Economics and Business (6 ECTS credits)
Course Syllabus STA301 Statistics for Economics and Business (6 ECTS credits) Instructor: Luc Hens Telephone: +32 2 629 11 92 e-mail: [email protected] Web site: http://homepages.vub.ac.be/~lmahens/ Course
CHAPTER 14 STEP STRESS TESTING (SST) CONTENTS
Applied R&M Manual for Defence Systems Part C - R&M Related Techniques CHAPTER 14 STEP STRESS TESTING (SST) CONTENTS Page 1 Introduction 2 2 Application and use of SST 3 3 Constraints and Limitations of
THE CERTIFIED SIX SIGMA BLACK BELT HANDBOOK
THE CERTIFIED SIX SIGMA BLACK BELT HANDBOOK SECOND EDITION T. M. Kubiak Donald W. Benbow ASQ Quality Press Milwaukee, Wisconsin Table of Contents list of Figures and Tables Preface to the Second Edition
FEGYVERNEKI SÁNDOR, PROBABILITY THEORY AND MATHEmATICAL
FEGYVERNEKI SÁNDOR, PROBABILITY THEORY AND MATHEmATICAL STATIsTICs 4 IV. RANDOm VECTORs 1. JOINTLY DIsTRIBUTED RANDOm VARIABLEs If are two rom variables defined on the same sample space we define the joint
Reliability Analysis A Tool Set for. Aron Brall
Reliability Analysis A Tool Set for Improving Business Processes Aron Brall ManTech International 1 Introduction Outline Defining Business Process Reliability Quantifying Business Process Reliability Business
Introduction to Basic Reliability Statistics. James Wheeler, CMRP
James Wheeler, CMRP Objectives Introduction to Basic Reliability Statistics Arithmetic Mean Standard Deviation Correlation Coefficient Estimating MTBF Type I Censoring Type II Censoring Eponential Distribution
Why Is EngineRoom the Right Choice? 1. Cuts the Cost of Calculation
What is EngineRoom? - A Web based data analysis application with an intuitive, drag-and-drop graphical interface. - A suite of powerful, simple-to-use Lean and Six Sigma data analysis tools that you can
CALCULATIONS & STATISTICS
CALCULATIONS & STATISTICS CALCULATION OF SCORES Conversion of 1-5 scale to 0-100 scores When you look at your report, you will notice that the scores are reported on a 0-100 scale, even though respondents
ABSORBENCY OF PAPER TOWELS
ABSORBENCY OF PAPER TOWELS 15. Brief Version of the Case Study 15.1 Problem Formulation 15.2 Selection of Factors 15.3 Obtaining Random Samples of Paper Towels 15.4 How will the Absorbency be measured?
Chapter Seven. Multiple regression An introduction to multiple regression Performing a multiple regression on SPSS
Chapter Seven Multiple regression An introduction to multiple regression Performing a multiple regression on SPSS Section : An introduction to multiple regression WHAT IS MULTIPLE REGRESSION? Multiple
QUIZ MODULE 1: BASIC CONCEPTS IN QUALITY AND TQM
QUIZ MODULE 1: BASIC CONCEPTS IN QUALITY AND TQM These questions cover Sessions 1, 2, 5, 6, 7. The correct answer is shown in bold A fundamental attribute of TQM is Drawing control charts Having team meetings
096 Professional Readiness Examination (Mathematics)
096 Professional Readiness Examination (Mathematics) Effective after October 1, 2013 MI-SG-FLD096M-02 TABLE OF CONTENTS PART 1: General Information About the MTTC Program and Test Preparation OVERVIEW
American Society for Quality (ASQ) CERTIFIED SIX SIGMA GREEN BELT (CSSGB) BODY OF KNOWLEDGE 2014
American Society for Quality (ASQ) CERTIFIED SIX SIGMA GREEN BELT (CSSGB) BODY OF KNOWLEDGE 2014 Included in this body of knowledge (BOK) are explanations (subtext) and cognitive levels for each topic
Engineering Problem Solving and Excel. EGN 1006 Introduction to Engineering
Engineering Problem Solving and Excel EGN 1006 Introduction to Engineering Mathematical Solution Procedures Commonly Used in Engineering Analysis Data Analysis Techniques (Statistics) Curve Fitting techniques
Preliminary Evaluation of Data Retention Characteristics for Ferroelectric Random Access Memories (FRAMs).
1 Preliminary Evaluation of Data Retention Characteristics for Ferroelectric Random Access Memories (FRAMs). 1.0 Introduction 1.1 FRAM Technology Background Ashok K. Sharma/NASA [email protected]
Validation and Calibration. Definitions and Terminology
Validation and Calibration Definitions and Terminology ACCEPTANCE CRITERIA: The specifications and acceptance/rejection criteria, such as acceptable quality level and unacceptable quality level, with an
Help Desk Strategic Plan. Goals
Help Desk Strategic Plan The motivation for an Help Desk is to deliver computer services for faculty/staff while providing real-world training for students interested in becoming computer technicians.
Chapter 1 Approach to Quality Assurance
Chapter 1 Approach to Quality Assurance Semiconductor Quality and Reliability Handbook Chapter 1 Approach to Quality Assurance 1.1 Approach toward Quality Assurance... 1-2 1.1.1 Basic Policy... 1-2 1.1.2
Lean Six Sigma Analyze Phase Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY
TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY Before we begin: Turn on the sound on your computer. There is audio to accompany this presentation. Audio will accompany most of the online
MATH BOOK OF PROBLEMS SERIES. New from Pearson Custom Publishing!
MATH BOOK OF PROBLEMS SERIES New from Pearson Custom Publishing! The Math Book of Problems Series is a database of math problems for the following courses: Pre-algebra Algebra Pre-calculus Calculus Statistics
I. Enterprise-wide Planning and Deployment (25 questions)
ASQ Certified Master Black Belt (MBB) Body of Knowledge Multiple-Choice Section 100 Questions 2 ½ hours The topics in this Body of Knowledge (BOK) include descriptive details (subtext) that will be used
COMMONWEALTH OF MASSACHUSETTS HUMAN RESOURCES DIVISION EDUCATION AND EXPERIENCE RATING SHEET INSTRUCTIONS
COMMONWEALTH OF MASSACHUSETTS HUMAN RESOURCES DIVISION EDUCATION AND EXPERIENCE RATING SHEET INSTRUCTIONS FIRE CHIEF DEPUTY FIRE CHIEF DISTRICT FIRE CHIEF SUMMARY OF EXAMINATION PROCESS: Promotional Examination
Applied Reliability Page 1 APPLIED RELIABILITY. Techniques for Reliability Analysis
Applied Reliability Page 1 APPLIED RELIABILITY Techniques for Reliability Analysis with Applied Reliability Tools (ART) (an EXCEL Add-In) and JMP Software AM216 Class 4 Notes Santa Clara University Copyright
THE RELIABILITY ENGINEER SOLUTIONS TEXT
THE RELIABILITY ENGINEER SOLUTIONS TEXT 2009 by QCI - All rights reserved 2.1. Which of the following is required to establish a reliability specification? a. The usage environment b. The system quality
Part 2: Analysis of Relationship Between Two Variables
Part 2: Analysis of Relationship Between Two Variables Linear Regression Linear correlation Significance Tests Multiple regression Linear Regression Y = a X + b Dependent Variable Independent Variable
Current Standard: Mathematical Concepts and Applications Shape, Space, and Measurement- Primary
Shape, Space, and Measurement- Primary A student shall apply concepts of shape, space, and measurement to solve problems involving two- and three-dimensional shapes by demonstrating an understanding of:
Bowerman, O'Connell, Aitken Schermer, & Adcock, Business Statistics in Practice, Canadian edition
Bowerman, O'Connell, Aitken Schermer, & Adcock, Business Statistics in Practice, Canadian edition Online Learning Centre Technology Step-by-Step - Excel Microsoft Excel is a spreadsheet software application
CAPA Essentials Root Cause Analysis Tools and Techniques
CAPA Essentials Root Cause Analysis Tools and Techniques Presented by Edna R. Falkenberg 21/10/2014 Slide 1 in numbers: Growing from strength to strength 1 One-stop technical solution provider 150 years
Design Verification. Introduction
Design verification is an essential step in the development of any product. Also referred to as qualification testing, design verification ensures that the product as designed is the same as the product
SAS Certificate Applied Statistics and SAS Programming
SAS Certificate Applied Statistics and SAS Programming SAS Certificate Applied Statistics and Advanced SAS Programming Brigham Young University Department of Statistics offers an Applied Statistics and
Simulation Exercises to Reinforce the Foundations of Statistical Thinking in Online Classes
Simulation Exercises to Reinforce the Foundations of Statistical Thinking in Online Classes Simcha Pollack, Ph.D. St. John s University Tobin College of Business Queens, NY, 11439 [email protected]
Curriculum Map Statistics and Probability Honors (348) Saugus High School Saugus Public Schools 2009-2010
Curriculum Map Statistics and Probability Honors (348) Saugus High School Saugus Public Schools 2009-2010 Week 1 Week 2 14.0 Students organize and describe distributions of data by using a number of different
INSTRUCTIONS TO CANDIDATES
Society of Actuaries Canadian Institute of Actuaries Exam MLC Models for Life Contingencies Friday, October 31, 2014 8:30 a.m. 12:45 p.m. MLC General Instructions 1. Write your candidate number here. Your
Statistics Review PSY379
Statistics Review PSY379 Basic concepts Measurement scales Populations vs. samples Continuous vs. discrete variable Independent vs. dependent variable Descriptive vs. inferential stats Common analyses
Governors State University College of Business and Public Administration. Course: STAT 361-03 Statistics for Management I (Online Course)
Governors State University College of Business and Public Administration Course: STAT 361-03 Statistics for Management I (Online Course) Instructor: Kevin M. Riordan, M.A. Session: Fall Semester 2011 Prerequisite:
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Body of Knowledge for Six Sigma Green Belt
Body of Knowledge for Six Sigma Green Belt What to Prepare For: The following is the Six Sigma Green Belt Certification Body of Knowledge that the exam will cover. We strongly encourage you to study and
Tutorial for proteome data analysis using the Perseus software platform
Tutorial for proteome data analysis using the Perseus software platform Laboratory of Mass Spectrometry, LNBio, CNPEM Tutorial version 1.0, January 2014. Note: This tutorial was written based on the information
MBA 611 STATISTICS AND QUANTITATIVE METHODS
MBA 611 STATISTICS AND QUANTITATIVE METHODS Part I. Review of Basic Statistics (Chapters 1-11) A. Introduction (Chapter 1) Uncertainty: Decisions are often based on incomplete information from uncertain
MATH 140 Lab 4: Probability and the Standard Normal Distribution
MATH 140 Lab 4: Probability and the Standard Normal Distribution Problem 1. Flipping a Coin Problem In this problem, we want to simualte the process of flipping a fair coin 1000 times. Note that the outcomes
Lean Six Sigma Black Belt Certification Recommendation. Name (as it will appear on the certificate) Address. City State, Zip
Lean Six Sigma Black Belt Certification Recommendation Name (as it will appear on the certificate) IQF Member Number Address City State, Zip Country We the undersigned, on behalf of the Sponsoring Organization,
PPG SUPPLIER DEVELOPMENT ASSESSMENT
Supplier: Address: Products: Assessment Date: Assessment Team: Certification: Supplier Contacts Position E-mail Phone General Comments: Assessment Results Summary Sections Non-conformity Action Point Quality
Measurement Systems Correlation MSC for Suppliers
Measurement Systems Correlation MSC for Suppliers Copyright 2003-2007 Raytheon Company. All rights reserved. R6σ is a Raytheon trademark registered in the United States and Europe. Raytheon Six Sigma is
Probability Distributions
CHAPTER 5 Probability Distributions CHAPTER OUTLINE 5.1 Probability Distribution of a Discrete Random Variable 5.2 Mean and Standard Deviation of a Probability Distribution 5.3 The Binomial Distribution
HYPOTHESIS TESTING: CONFIDENCE INTERVALS, T-TESTS, ANOVAS, AND REGRESSION
HYPOTHESIS TESTING: CONFIDENCE INTERVALS, T-TESTS, ANOVAS, AND REGRESSION HOD 2990 10 November 2010 Lecture Background This is a lightning speed summary of introductory statistical methods for senior undergraduate
Technical Note SolarEdge Reliability Methodology
Technical Note SolarEdge Reliability Methodology Summary SolarEdge Technologies develops and sells power electronics for the Photovoltaic market. The heart of the SolarEdge power harvesting system is a
One-Way Analysis of Variance (ANOVA) Example Problem
One-Way Analysis of Variance (ANOVA) Example Problem Introduction Analysis of Variance (ANOVA) is a hypothesis-testing technique used to test the equality of two or more population (or treatment) means
ZIMBABWE SCHOOL EXAMINATIONS COUNCIL. COMPUTER STUDIES 7014/01 PAPER 1 Multiple Choice SPECIMEN PAPER
ZIMBABWE SCHOOL EXAMINATIONS COUNCIL General Certificate of Education Ordinary Level COMPUTER STUDIES 7014/01 PAPER 1 Multiple Choice SPECIMEN PAPER Candidates answer on the question paper Additional materials:
QDA Q-Management A S I D A T A M Y T E S P E C S H E E T. From stand-alone applications to integrated solutions. Process optimization tool
QDA Q-Management Q-Management is the powerful base software package within ASI DATAMYTE s QDA suite that facilitates achievement and verification of quality goals such as process control, cost reduction,
Statistical Functions in Excel
Statistical Functions in Excel There are many statistical functions in Excel. Moreover, there are other functions that are not specified as statistical functions that are helpful in some statistical analyses.