1 MINUTES Meeting: GLA Group Collaborative Procurement Board (Informal Meeting) Date: Time: Place: am Room 8.9, City Hall, The Queen's Walk, London, SE1 2AA Summary minutes of the meetings of the GLA Group Collaborative Procurement Board will be published on the GLA s website at (except in those cases where information in the papers may be exempt from disclosure under the Freedom of Information Act). Meetings of this internal officerlevel Board will not be held in public and are only open to those invited to attend by the Chair of the Board. Present: Members: Sir Edward Lister, Mayor s Chief of Staff (Chair); Mark Atkinson, Deputy Head of Procurement, LFEPA; Annabel Cowell, Head of Strategic Finance and Resource Management, MOPAC; Gerry Murphy, Executive Director of Finance and Corporate Services, LLDC Andrew Quincey, Director, Comemrical, TfL; and Selina Seesunkur, Interim Operations Manager, OPDC; Officers: Martin Clarke, Executive Director of Resources, GLA; Andrew Mayes, Lead Commercial Manager, TfL; Matthew Beals, Financial Analyst, GLA; and Rebecca Arnold, Clerk. Guests: Alan Rourke, Category Director - Corporate & Professional Services, Metropolitan Police Service; and Ben Shepherd, Director, PwC City Hall, The Queen s Walk, London SE1 2AA Enquiries: minicom:
2 1 Apologies for absence and Chair's announcements (Item 1) 1.1 Apologies for absence were received on behalf of: the Mayor s Office for Policing and Crime (MOPAC) representative on the Board, Stephen Greenhalgh (Deputy Mayor for Policing and Crime), for whom Annabel Cowell (Head of Strategic Finance and Resource Management, MOPAC) attended as a substitute; the Old Oak and Park Royal Development Corporation (OPDC) representative on the Board, Darrell Redmond (Interim Director of Operations, OPDC) for whom Selina Seesunkur (Interim Operations Manager, OPDC) attended as a substitute; and the London Fire and Emergency Planning Authority (LFEPA) representative on the Board, Sue Budden (Director of Finance and Contractual Services, LFEPA), for whom Mark Atkinson (Deputy Head of Procurement, LFEPA) attended as a substitute. 1.2 Apologies for absence were also received from Michael Hawdon (Partner, PwC Observer). Ben Shepherd (Director, Pwc) attended in his place. 1.3 Alan Rourke (Category Director - Corporate & Professional Services, Metropolitan Police Service) also attended the meeting as an invited guest. 2 Declarations of Interest (Item 2) 2.1 There were no declarations of interest. 3 Minutes (Item 3) 3.1 The Board received the minutes of the informal meeting held on 22 October DECISION: That the minutes of the informal meeting held on 22 October 2015 be agreed as a correct record. 4 Actions Arising from Previous Meeting (Item 4) 4.1 The Board received a report which set out the completed and outstanding actions arising from previous meetings of the Board. 4.2 In addition, the following updates were provided in relation to actions arising from the 22 October 2015 meeting of the Board: Action arising from Minute 5: It was noted that OPDC had now returned to the TfL Legal Team the documents required formally to establish the Board. Therefore, signed documents were awaited just from MOPAC. The MOPAC Board Member raised some queries regarding the charges arising from the methodology set out under Schedule 4 of the GLA Collaborative 2
3 Procurement Board working arrangement document. Following discussion the Executive Director of Resources, GLA agreed to review those charges to ensure that they reflected the correct annual charge for each functional body, having had regard to the categories of procurement managed by the GLA Collaborative Procurement Team on behalf of each of the functional bodies, and to write to MOPAC following the meeting regarding possible revisions. It was noted that, subject to this taking place, MOPAC would then be in a position to sign the formal paperwork; Action Arising from Minute 6: It was noted that MOPAC would report back to the Board in due course regarding the outcome of consideration of potential future usage by the MPS of the new Customer Research and Insight Services Framework, once the tender had been issued and it was possible to benchmark the potential benefits of using the new contract; Action Arising from Minute 7: The Lead Commercial Manager confirmed, in the context of the Pan-GLA Records Storage, Retrieval, Disposal and Digitisation Services Procurement Strategy, that TfL had produced a strategy for increasing the volume of documents stored digitally within their organisation. He agreed to share that paper with members of the Board; Action Arising from Minute 10: In relation to the office equipment and supplies category, the Lead Commercial Manager explained that some initial benchmarking had taken place in relation to the benefits of the MPS utilising the LCSG framework versus waiting to analyse the potential benefits of utilising the new CCS framework - which was due to start in A further update would be provided in due course; In relation to the utilities category, the LLDC Board Member confirmed that she would contact the Lead Commercial Manager with some suggestions for potential improvements in online access and billing; The Lead Commercial Manager confirmed that possible changes to the Collaborative Team to ensure the Team focused its resources on those categories with the greatest potential for collaboration were still under consideration; The Lead Commercial Manager indicated that he would be contacting PwC to use the data analysis service to analyse the data provided by the MPS in relation to their usage of their current recruitment contract. The Category Director - Corporate & Professional Services, MPS explained that, under current arrangements, the MPS had an implanted team from the current contract provider which managed the recruitment contract on a day-to-day basis and noted that the value of this - versus any additional expense to employ a resource to undertake that function - also needed to be taken into account in terms of the cost-benefit analysis of moving to an alternative contract. The MOPAC Board Member noted that reference to this work being undertaken to analyse the possible benefits of moving to a different provider needed to be included in the paper going to the MOPAC Board in January 2016; 3
4 In relation the print category, it was noted that the potential barriers to the MPS moving across to the GLA/TfL contract with CDS were being discussed and a further update would be provided in due course. Again, the MPS s current print provider provided a fully managed service with a dedicated team managed the contract on a day-to-day basis and the MPS therefore did not currently employ staff to undertake that function. 4.3 DECISION: That the completed and outstanding actions arising from previous meetings of the Board, as set out in the report, and the additional updates provided, as set out above, be noted. 5 Transcription and General Note Taking Services - Procurement Strategy (Item 5) 5.1 The Board received the proposed Transcription & General Note Taking Services Procurement Strategy for consideration. 5.2 The Strategy set out the rationale for the retender of the TfL Transcription Services Contract and the GLA Transcription Services Contract. Going forward, it was envisaged that one agreement would be put in place covering all the Functional Bodies. 5.3 It was noted that paragraph 3.2 of the covering report should refer to a total spend over the four year framework of 1.25m not 125m. 5.4 The Executive Director of Resources, GLA requested that further discussions be had with the GLA regarding ensuring that the contract would deliver the GLA s requirements in full, noting that, unlike the Functional Bodies, the GLA used transcripts for formal meetings and published the transcripts and in addition currently received a Rolls Royce service which it was looking to replicate. 5.5 It was noted that OPDC and LLDC had indicated that they did not currently use or have a need for a transcription service and LFEPA usage was fairly small. However, the Collaborative Procurement Team would analyse, via the Management Information contract, whether all relevant usage had been captured. Some head room would be allowed in case MPS usage grew. The Lead Commercial Manager confirmed that the MPS s specific requirements in relation to data security had been taken on board. 5.6 DECISION: That the proposed Transcription and General Note Taking Services Procurement Strategy, as attached as Appendix A to the report, and implementation of the procurement programme as set out within the strategy be approved, subject to the comments recorded above. 4
5 6 Management Information Data Contract (Oral Update) (Item 6) 6.1 The Lead Commercial Manager, TfL proposed that a representative from PwC be invited to the Board s next meeting to give a presentation on the services available via the Management Information contract. 6.2 It was noted that the service provided through that contract included an automated savings tracker which was a powerful tool to track savings arising from the collaborative procurement arrangements, both in terms of process and arising directly from procurements. 6.3 DECISION: (1) That the oral update be noted; and (2) That it be agreed to invite a representative from PwC be invited to the Board s next meeting to give a presentation on the services available via the Management Information contract 7 Draft Implementation Plan (Item 7) 7.1 The Board received a paper which set out the draft implementation plan for in-scope categories. 7.2 The Lead Commercial Manager additionally provided the following updates In relation to the business travel/accommodation and conferencing category, it was noted that Capita - who were the Crown Commercial Services Provider - had submitted a full proposal. This was currently being reviewed and analysed, but initial evaluation highlighted possible savings in excess of 1m across the Group as a whole; The records storage and associated services category had been discussed at the Board s previous meeting. It was noted that deep storage contracts were being looked at separately as they did not fall within this category and that the MPS had some particular requirements in this regard, for example around the storage of criminal case exhibits; In relation to the consultancy categories, the Collaborative Procurement Team were looking to manage the pipeline more efficiently as there was a great deal of activity in this area; In relation to the event management category OPDC requested that they be involved in the current scoping work; In relation to the Legal Services category, it was noted that the MPS was due to award the contract in relation to the National Legal Services Framework in January/February 5
6 7.3 DECISION: The MPS agreed to share details of savings derived from that award with other Board members. That the report be noted and the procurement category updates provided, as set out above, be noted. 8 Work Programme for Future Board Meetings (Item 8) 8.1 The Board received a paper which set out the proposed date and business for the Board s next meeting. 8.2 As well as the additional item agreed at Item 6 (Management Information Data Contract - Oral Update), the Board also noted that the Insurance Category Strategy would potentially be submitted to the Board at its February 2016 meeting. 8.3 It was agreed that a Board meeting should also be scheduled for March and noted that the Financial Services Strategy would now be submitted to that meeting rather than the February meeting. The Print Strategy would also potentially be submitted to that meeting. 8.4 DECISION: That the date and proposed business for the next meeting of the Board, as set out in the report, be agreed, subject to the changes set out above. 9 Date of Next Meeting (Item 9) 9.1 It was noted that the Board s next meeting would take place at 2pm on Thursday 4 February 2016 in Committee Room 3, City Hall. 10 Close of Meeting 10.1 The meeting closed at 12.32pm. Contact Officer: Rebecca Arnold, Committee Services Manager; Telephone: ; [email protected]. 6
REQUEST FOR MAYORAL DECISION MD405. Title: Disaster Recovery Services
REQUEST FOR MAYORAL DECISION MD405 Title: Disaster Recovery Services Executive Summary: In May 2006, the GLA entered into an agreement with a recovery partner to offer immediate replacement IT equipment
GREATERLONDONAUTHORITY
GREATERLONDONAUTHORITY REQUEST FOR MAYORAL DECISION MD1 648 Title: Hockey additional grant funding Executive Summary: This decision seeks approval to commit a further 300,000 from the major sports events
Transport for London. Minutes of the Audit and Assurance Committee
Transport for London Minutes of the Audit and Assurance Committee Conference Rooms 1 and 2, Ground Floor, Palestra, 197 Blackfriars Road, London, SE1 8NJ 10.00am, Tuesday 8 December 2015 s Keith Williams
PART 50 BEHAVIOUR ORDERS
Contents of this Part PART 50 BEHAVIOUR ORDERS When this Part applies rule 50.1 Behaviour orders: general rules rule 50.2 Application for behaviour order and notice of terms of proposed order: special
Conference Room, Office of the Police & Crime Commissioner, Clemonds Hey, Oakmere Road, Winsford, CW7 2UA. Agenda Page
MANAGEMENT BOARD Friday 18 December 2015 9.00am Conference Room, Office of the Police & Crime Commissioner, Clemonds Hey, Oakmere Road, Winsford, CW7 2UA Agenda Page 1 NOTES OF MANAGEMENT BOARD ON 9 DECEMBER
Procurement of communications support for the launch of Healthy Schools London
REQUEST FOR DIRECTOR DECISION DD923 Title: Procurement of communications support for the launch of Healthy Schools London Executive Summary: The Healthy Schools London programme ( HSL Programme ) is one
House of Commons Corporate Governance Framework
House of Commons Corporate Governance Framework What is Corporate Governance? 1. Good corporate governance is fundamental to any effective organisation and is the hallmark of any well-managed corporate
May 2015. The Right Direction. The Mayor s Strategy for improving transport safety, security and reliability in London 2015-2017 Executive Summary
May 2015 The Right Direction The Mayor s Strategy for improving transport safety, security and reliability in London 2015-2017 Executive Summary Greater London Authority May 2015 Published by Greater London
SCRUTINY & OVERVIEW COMMITTEE 14 TH SEPTEMBER 2015
150914 SCRUTINY & OVERVIEW COMMITTEE 14 TH SEPTEMBER 2015 Present: Councillors: Leonard Crosbie (Chairman), David Coldwell (Vice- Chairman) Paul Clarke, Roger Clarke, Jonathan Dancer, Tony Hogben, Nigel
M O P 4. z ft o / One element of the Total Technology Programme Infrastructure (TFPI) is the replacement of the
Executive Summary: 9UE5flOR DMPC DECISION - DMPCD 201 4-1 05 DMPCD v4 I confirm I have considered whether or not I have any personal or prejudicial interest in this matter and Nov 2012 1 Signature Date
Transport for London. INVITATION TO TENDER FOR BRIDGE DESIGN CONSULTANCY SERVICES ITT REF: TfL/90711 PUBLICATION DATE: 13 FEBRUARY 2013
Transport for London INVITATION TO TENDER FOR BRIDGE DESIGN CONSULTANCY SERVICES ITT REF: TfL/90711 PUBLICATION DATE: 13 FEBRUARY 2013 Invitation to Tender TfL/90711 Bridge Design Consultancy Services
Investment & Performance Board (IPB)
Investment & Performance Board (IPB) Date of meeting: 19 January 2016 Title of paper: Developing a New Junior Electricity Supply Licence - Progress Report To be presented by: Cleared by: Classification:
Appendix 1C. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA PAYROLL CONTROL FRAMEWORK
Appendix 1C DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA PAYROLL CONTROL FRAMEWORK DISTRIBUTION LIST Audit Team Prakash Gohil, Audit Manager Karen Walker, Risk and Assurance
LONDON BOROUGH OF WALTHAM FOREST
LONDON BOROUGH OF WALTHAM FOREST Meeting / Date Cabinet /December 2015 Report Title Cabinet Portfolio Report Author/ Contact details Wards affected Public Access Appendices ICT Data Centre & Infrastructure
Invitation to Tender for 2015 Duty Provider Crime Contracts Information For Applicants
Invitation to Tender for 2015 Duty Provider Crime Contracts Information For Applicants The Legal Aid Agency (LAA) is inviting eligible Applicant Organisations to respond to the Invitations to Tender (ITT)
AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007
PAGE: 1 REPORT TO: SUBJECT: BY: AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 To provide the Audit and Performance Review
Members Councillors Mrs Bould, Hurst-Knight, Dr Jones (Chair), Kiernan, Mellings (Vice-Chair) and Roberts
5 Non-Exempt Minutes of the Meeting of Shropshire Wrekin Fire Rescue Authority Audit Performance Management Committee held in the Oak Room, Headquarters, Shrewsbury on Thursday, 29 January 2015 at 2.00
DIRECTORATE OF AUDIT, RISK AND ASSURANCE
Appendix 2 DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA DRAFT Review of Millennium Mills Grant Declaration 2014/15 DISTRIBUTION LIST Audit Team David Esling, Head of Audit
1.1 The Chair welcomed the Board members and officials to the meeting. 1.3 The Board accepted the Minute of 30 September as a true record.
Meeting of the Revenue Scotland Board MINUTE 09:00, 4 November 2015, Conference Room 3, VQ, Edinburgh Present: Dr Keith Nicholson [Chair] Lynn Bradley Jane Ryder OBE Ian Tait John Whiting OBE Attended:
DATA PROTECTION POLICY. Examples of personal data which TWM may require from clients include the following and for the reasons ascribed to each;
DATA PROTECTION POLICY Introduction TWM Solicitors maintain certain personal data about individuals for the purposes of satisfying operational and legal obligations. The Data Protection Act sets rules
REPORT TO: POLICY AND RESOURCES COMMITTEE ON 28TH MARCH 2007
ITEM:13 PAGE: 1 REPORT TO: POLICY AND RESOURCES COMMITTEE ON 28TH MARCH 2007 SUBJECT: BY: ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 This report provides details of progress over
Finance and Policy Committee. Date: 14 October 2014. Item 17: TfL Energy Purchasing 2017 to 2020. This paper will be considered in public.
Finance and Policy Committee Date: 14 October 2014 Item 17: TfL Energy Purchasing 2017 to 2020 This paper will be considered in public 1 Summary 1.1 This paper: (a) reviews the current purchasing strategy
Data Quality - A Review of the Audit Committee
AGENDA ITEM 6 TRANSPORT FOR LONDON AUDIT COMMITTEE SUBJECT: DATA QUALITY REVIEW 2007/08 DATE: 25 NOVEMBER 2008 1 PURPOSE AND DECISION REQUIRED 1.1 As part of its assessments of TfL, the Audit Commission
SOMERSET COUNTY COUNCIL KEY DECISION TAKEN BY THE COMMERCIAL AND BUSINESS SERVICES DIRECTOR
SOMERSET COUNTY COUNCIL KEY DECISION TAKEN BY THE COMMERCIAL AND BUSINESS SERVICES DIRECTOR Report title: Procurement of a preferred Software Licence Reseller and support services Officer(s): Richard Williams,
The Removal and Disposal of Vehicles Regulations 1986
SI 986/83 Page 986 No. 83 ROAD TRAFFIC The Removal and Disposal of Vehicles Regulations 986 Thomson Reuters (Legal) Limited. UK Statutory Instruments Crown Copyright. Reproduced by permission of the Controller
Team Leader Job Profile
Team Leader Job Profile About the HCPC The Health and Care Professions Council (HCPC) is the regulator of 16 different health professions, set up to protect the public. To do this, we keep a register of
HR/Payroll System - GLA Strategic Options
Appendix 1 HR/Payroll System - GLA Strategic Options Arnab Banerjee 9/2/2010 Review the partially drafted HR/Payroll systems requirement document and advise on the suitability of Tier 2 vendors to meet
CORPORATE HEALTH AND SAFETY COMMITTEE
CORPORATE HEALTH AND SAFETY COMMITTEE ABERDEEN, Friday, 20 February 2015. Minute of Meeting of the CORPORATE HEALTH AND SAFETY COMMITTEE. Present:- Councillor Graham Chairperson. City Council Representatives:-
2015-16 Your council tax explained
2015-16 Your council tax explained how your council tax has been calculated page 2 answers to common questions page 7 how your council tax is spent page 10 www.islington.gov.uk/counciltax 1 Your council
1.1 The Chair welcomed the Board members and officials to the meeting.
Meeting of the Revenue Scotland Board MINUTE 09:00, 30 September 2015, Conference Rooms 4&5, VQ, Edinburgh Present: Dr Keith Nicholson [Chair] Lynn Bradley Jane Ryder OBE Ian Tait John Whiting OBE Attended
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable
EAST AYRSHIRE COUNCIL GOVERNANCE AND SCRUTINY COMMITTEE
833 EAST AYRSHIRE COUNCIL GOVERNANCE AND SCRUTINY COMMITTEE MINUTES OF MEETING HELD ON FRIDAY 28 AUGUST 2009 AT 1000 HRS IN THE ROBERT BURNS SUITE, BURNS MONUMENT CENTRE, KAY PARK, KILMARNOCK PRESENT:
Ethical Sourcing Policy
Ethical Sourcing Policy Index 1.0 Policy Statement... 2 2.0 Organisational Scope and Compliance... 2 3.0 Policy Purpose... 3 4.0 The ETI Base Code... 3 5.0 Guiding Principles... 4 6.0 Identify suitable
INTERIM INTERNAL AUDIT REPORT
INTERIM INTERNAL AUDIT REPORT Graduate Schemes (IA 14 137) Tricia Riley, HR Director Audit Conclusion: Well Controlled and Audit Closed 31 July 2015 TfL RESTRICTED CONTENTS EXECUTIVE SUMMARY... 3 APPENDIX
JOB VACANCIES. Contract Management & Compliance Officer - Property Services Ref: 254
JOB VACANCIES Contract Management & Compliance Officer - Property Services Ref: 254 Salary Level 7: 25,440-28,746 South Essex Homes are currently looking for a Contract Management & Compliance Officer
Local Audit. Consultation. June 2014 Department for Communities and Local Government
Local Audit Consultation June 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown. You may re-use this information
Corporate ICT & Data Management. Data Protection Policy
90 Corporate ICT & Data Management Data Protection Policy Classification: Unclassified Date Created: January 2012 Date Reviewed January Version: 2.0 Author: Owner: Data Protection Policy V2 1 Version Control
Voluntary Severance Process (IA 12 107/F) Tricia Riley, Director of Human Resources. Audit Conclusion: Audit Closed
FINAL INTERNAL AUDIT REPORT Voluntary Severance Process (IA 12 107/F) Tricia Riley, Director of Human Resources Audit Conclusion: Audit Closed 5 August 2013 Issue categories Agreed actions Satisfactorily
Final Draft Guidance on Audit Committees
Guidance Corporate Governance April 2016 Final Draft Guidance on Audit Committees The FRC is responsible for promoting high quality corporate governance and reporting to foster investment. We set the UK
MINUTES OF A MEETING OF THE SAFEGUARDING, COMMUNITIES AND WELLBEING SCRUTINY COMMITTEE HELD AT THE GUIDHALL, WREXHAM ON WEDNESDAY, 21 OCTOBER 2015
MINUTES OF A MEETING OF THE SAFEGUARDING, COMMUNITIES AND WELLBEING SCRUTINY COMMITTEE HELD AT THE GUIDHALL, WREXHAM ON WEDNESDAY, 21 OCTOBER 2015 MEMBERS Councillor Carole O'Toole MBE, Chair Councillor
PRACTICE DIRECTION 27A FAMILY PROCEEDINGS: COURT BUNDLES (UNIVERSAL PRACTICE TO BE APPLIED IN THE HIGH COURT AND FAMILY COURT)
PRACTICE DIRECTION 27A FAMILY PROCEEDINGS: COURT BUNDLES (UNIVERSAL PRACTICE TO BE APPLIED IN THE HIGH COURT AND FAMILY COURT) This Practice Direction supplements FPR Part 27 1.1 The President of the Family
Statutory Declaration
Statutory Declaration Organisations must complete and submit this Statutory Declaration to the Australian Government Department of Education (the department), through the HELP IT System (HITS), when there
The post holder will be guided by general polices and regulations, but will need to establish the way in which these should be interpreted.
JOB DESCRIPTION Job Title: Membership and Events Manager Band: 7 Hours: 37.5 Location: Elms, Tatchbury Mount Accountable to: Head of Strategic Relationship Management 1. MAIN PURPOSE OF JOB The post holder
Change Makers Fund Guidance for applicants
Change Makers Fund Guidance for applicants Below is an outline summary of key information. Please see Section three for full eligibility criteria. Summary of key information What is the focus of the fund?
IN ATTENDANCE: Mr Toby Boyd (Secretary, IPSC), Ms Gundi Nabi (UoLIA).
The second meeting of the Inclusive Practice Sub-Committee (formerly the Special Needs Sub-Committee) of the University of London International Academy Thursday, 17 November 2011 MINUTES PRESENT: Dr Kathy
Aberdeen City Council IT Asset Management
Aberdeen City Council IT Asset Management Internal Audit Report 2014/2015 for Aberdeen City Council January 2015 Terms or reference agreed 4 weeks prior to fieldwork Target Dates per agreed Actual Dates
North Middlesex University Hospital NHS Trust. Annual Audit Letter 2005/06. Report to the Directors of the Board
North Middlesex University Hospital NHS Trust Annual Audit Letter 2005/06 Report to the Directors of the Board 1 Introduction The Purpose of this Letter 1.1 The purpose of this Annual Audit Letter (letter)
JOB DESCRIPTION. Job Reference number (coded):
Job Title: HR Business Support Manager Reporting To: Head of HR Business Services Department(s)/Location: Human Resources (HQ) Job Reference number (coded): 1. JOB PURPOSE To lead and develop the HR Business
Options for the Council s Debit & Credit Card (Merchant Acquirer) Contract Not a Key Decision
Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Strategy: Councillor Julie Smith Julia Minns Strategy & Resources Scrutiny Committee All
Public Audit (Wales) Act 2004
Public Audit (Wales) Act 2004 CHAPTER 23 CONTENTS PART 1 AUDITOR GENERAL FOR WALES New functions of the Auditor General for Wales 1 Transfer of functions of Assembly 2 Additional functions of Auditor General
Duty Solicitor Call Centre and CDS Direct Expansion
Duty Solicitor Call Centre and CDS Direct Expansion March 2007 Contents Section: Page Number: Introduction and Background 3 The Carter Review 5 The Current System 6 The Need For Change 7 The Proposal 8
A Working Protocol between ACPO, the Crown Prosecution Service (CPS), Her Majesty s Court & Tribunals Service (HMCTS), the Witness
A Working Protocol between ACPO, the Crown Prosecution Service (CPS), Her Majesty s Court & Tribunals Service (HMCTS), the Witness Service and the Senior Presiding Judge for England and Wales on Reading
Current Issues Note 27 Central London office market through the recession By Yeukai Muchenje and Nick Ennis
Current Issues Note 27 By Yeukai Muchenje and Nick Ennis copyright Greater London Authority November 2010 Published by Greater London Authority City Hall The Queen s Walk London SE1 2AA www.london.gov.uk
Supplier & Contract Management System (SCMS)
Meeting of the Executive Member for Corporate Services and Advisory Panel 30 October 2007 Report of the Assistant Director Audit and Risk Management Supplier & Contract Management System (SCMS) Summary