Network Analysis and Project Management an Overview
|
|
|
- Sydney Owen
- 9 years ago
- Views:
Transcription
1 Journal of the Applied Mathematics, Statistics and Informatics (JAMSI), 1 (2005), No. 1 Network Analysis and Project Management an Overview FERDINAND GLIVIAK AND PETER SAKÁL Abstract The network analysis results have used for application tasks solution in project management. This paper gives an overview of basic network analysis problems and also some other ones in project management field. The article briefly describes the situation in finished software products for project management as well. Mathematics Subject Classification 2000: 90B50, 90B10 Additional Key Words and Phrases: network analysis, project management INTRODUCTION This paper is divided into 8 following parts: a project and its graphs, time analysis, resource analysis, cost analysis, traditional project management approaches, non traditional project management approaches, current software tools and experiences with applications in Slovak republic. 1. A PROJECT AND ITS GRAPHS A project it is some complex or real task such as a house building, reconstruction of production hall, a product introduction, etc. The project consists of many partial activities. Some of them can be done by series and some of them by parallel. One activity is a set of labor hasing the same technical conditions to neighborhood. It is a practice to specify them in particular field. These activities are used in a project as one unit but they can be divided into the parts in the engineering practice. We will study conjunctive deterministic projects only, i. e. such project P that: a) to every activity of P is given a positive real number as its duration, b) given activity i of P can start only at that time if all immediate predecessors are done. Table 1 describes the example of the project; see [J1, p. 77]. 101
2 F. Gliviak, P. Sakál Table 1: The house building Order Task Amount of time Prec. tasks 1. setting out the building estate delivering the building materials dining the foundations 2 1,2 4. building the foundations building the walls building the roof covering the roof plumbing outside the house plasterworking outside 2 7,8 10. putting the windows in 1 7,8 11. putting the ceilings laing out the garden 4 9, plumbing inside the house putting insulation on the walls 3 10, painting the walls moving in 5 15 Other type of projects (e. g. conjunctive stochastic) are mentioned in the literature but they have not such applications and therefore we will not talking about them. We can allocate two different graphs into this project: (1) network graph N(P) of a project P, (2) activity graph A (P) of a project P. In network graph N (P) we present every activity I of P by an oriented edge evaluated by its duration time d i. More precise description of network graph construction is given in [SŠ1] and [GV]. We only notice that this graph N(P) contains this activity edges and also fictive edges that are useful for performance coordination between activities. Figure 1 give the network graph N (P) of the project P presented in Table
3 Network Analysis and Project Management an Overview 13/5 14/3 15/3 16/5 11/3 f/0 f/0 s f/0 f/0 1/3 2/2 3/2 4/2 5/7 6/3 8/3 10/1 7/1 f/0 9/2 12/4 f/0 z Fig. 1. Network graph N(P) In activity graph A(P) we represent every activity i of P by a vertex evaluated by its time d i. We join two activities i, j, by oriented edge [i, j], if the activity i is immediate predecessor of activity j. Moreover there are some fictive activities joining the start s the project P and the finish vertex z of P. Figure 2 give the activity graph A(P) of the project P from Table 1. Fig. 2. Activity graph A (P) Network graph N (P) arise in 1957 as first graph but now activity graph A (P) is the most used. Both these graphs must be cyclic and this fact is controlled automatically in current software system. Time analysis, resource analysis and cost analysis are similar for both types of graphs. Therefore we have been talking only about activity graphs. 103
4 F. Gliviak, P. Sakál 2. A TIME ANALYSIS Every project starts at beginning (vertex s) and at time 0.Time in counted as discrete time form o during whole project duration. In time analysis we use only time and topological relations between activities given by edges of graph A (P). We do not use resources. We suppose that there is enough resource of every needed type. For every activity i we compute the first possible beginning t i of i and the last possible beginning T i of i. The first possible beginning t i we compute by forward way (from start s to goal z) this way: t s = 0 t i = max {t k + duration activity k/ for all edges [k,i] of A (P)} Specially, we receive at least possible end of the project t z for fictive activity z (the goal of P). We put these time t z equal to the last possible end of the project T z. i. e. t z = T z. We compute the last possible beginning T i of activity i to the the step backward (from the goal z to the start s ) in this way: T z = t z T i = min{t j duration activity i / for all edges [i, j] of A (P)} Figure 3 shows numbers t i and T i for every activity i of the project given in Table 1. 14/14 17,17 22,22 25,25 28, /0 7/ /17 17/20 18/21 0/0 3/ s 0, /29 33,33 2 7/18 12 z 18/ Fig. 3. The whole reserves and critical path The difference m i = T i t i between the latest possible and the first possible beginning of activity i is called the total reserve of activity i. In the current software system there are used these ones and also further reserves of activity i. 104
5 Network Analysis and Project Management an Overview Critical path of Project P is the longest path staring at vertex s and finishing at vertex Z. The length of a path is the duration sum of activities lying on the path. Critical path of project P see at Figure 3. It is the path (s, 1, 3, 4, 5, 11, 13, 14, 15, 16, z). We mention that one project P can contain more than one critical path. Moreover, the sum of the whole reserve of any critical path of project P is 0. Current software system for network analysis and project management illustrates the results of time analysis by Gantt diagram. It is a diagram with two axis x, y where on x is time and on axis y are different activities. For details see [U1], [T2]. Now we will talking about a resource analysis. 3. RESOURCE ANALYSIS Generally, we need several resources for any project realization. Some of them depend on themselves. In the literature and also in the current practice it is supposed that resources are not mutually dependent. Then we often consider any resource separately what we will suppose in the future. After time analysis we must count the demand of every resource in every discrete time. This is done for either left hand side plan (i. e. all activities start in first possible time) or right hand side plan (i. e. all activities start in latest possible time). The left hand side plan is used more then right one. The result of this counting is step curve different form abscissa. In resource analysis there are two professional problems [GV1], [SŠ1]: a) to arrange the demand of every resource, b) to assign constraint resource to activities. In the first problem there are used three criteria of arranging of a resource [ZR1], [T2]: 1) The dispersion of the resource demand, 2) Maximal absolute deviation from average demand, 3) Maximal demand to a resource. Let t = 1, 2,, N is a discrete time in project P. Let Z (t) is a demand of resource Z in 1 time t. Let Z = N i t = 1 Z( t) is an average claim of resource Z per time unit. Then the N ( Z ) demand dispersion of resource Z is s = Z( t) 2 1 Z N t =
6 Criteria number one requires to minimize dispersion max Criteria number two requires to minimize the relation Z( t) Criteria number three to minimize the relation ( Z( t) ) max t 1, N. t 1, N 2 s Z. ( Z ) There are different approaches this optimization task but none of them give an optimal solution of these tasks. They give approximation solutions only. For example this approximation algorithm of A. R. Burges for one resource is published in [K1]. The algorithm for one project for several independent resources providing one activity needs only one resource is published in [K1]. Levy, Thompson and Wiest study problem of several project and several independent resources, see [B2, p. 32]. Now we will study the second main problem. Let us suppose that arranging of every resource is done and we have less amount of some resource that is needed. Then the project realization is late. Algorithms allotting of delimit resource would allot the delimit resource at smallest possible delay of finishing project time. Probably the best know algorithm for resource allotting is algorithm of J. E. Kelly solving this task for one project and one resource, [K1]. There is a generalization of this algorithm for one project, several independent resources and assumption that one activity needs only one resource. The problems of allotting resources for more projects would be discussed in part six (non tradition approaches to project management). Now we will study one specific resource money. F. Gliviak, P. Sakál. 4. COST ANALYSIS A project costs there is money necessary for its realization. Cost analysis solves optimal synchronization between project costs and time of project realization. First of all we will talk about project cost, project duration and finally about basic facts of project shortening. We will specify the activity costs and the project costs this way: a) Direct activity costs usually contain the sum of the costs of materials equipments, salary of particular employees, etc. The direct costs of a project c d are a sum of direct costs of all their activities. b) Overhead costs on a project are usually given as overhead expenses per time unit c o and their amount is given by multiplying of c o by project duration. 106
7 Network Analysis and Project Management an Overview c) Project extension deficits they are determined concerning c e (T T p ), where c e are project extension deficits per unit, T p is a planning time of project duration an T is a real time of project duration. d) Total costs c(t) for project realization per time T are given by: c (T) = c d +c o T +c e (T T p ) Duration of an activity usually is not a constant but it consists of upper duration t u, lower duration t e and further discrete values between them. Upper duration t u of an activity is a activity duration with minimal resource requirements. We do not permit the extension of this duration behind the value t u because of technological or other reasons. Lowe duration t e of an activity is a value that it is not possible reduce by further increasing of direct costs for the activity of using the same technology. If activity duration is the greatest t j = t u than its direct costs are the lowest and equal to c l. Vice versa, if its duration is t l than the direct costs are the greatest and equal to c u. The relation between activity duration (axis x) and direct costs of their activity (axis y) is in the figure four. It is termed cost curve pre one activity. The cost curve of whole project had the similar shape, [U1], [SŠ1]. Fig. 4. Expense curve of an activity In the literature it is usually suppose that cost curve of the project is continuous, nonlinear and convex. During the project extension the nonlinear part AB of project is a approximating by line passing the point A, B. c i = -a i t i + b i, where u e ai = u t l e l t 107
8 F. Gliviak, P. Sakál Index a i is constant of costs gradient and it expreses increase of costs per unit of extension of project duration- Well known method of duration extension of the project is Weber s methods described in [U1]. Further methods of project abbreviation are described in [W1], [ZR1], and [B1]. All these methods give a heuristic solution of this main task: To determine the optimal duration of a project (ad hence duration of all activities) using this input data: upper and lower duration of every activity, upper and lower direct costs of every activity, planning time T p of duration of this project, project extension deficits towards planning time T p per time unit. Current algorithms of solution for this main task are not published and moreover, they are business secret of particular firm. 5. TRADITIONAL APPROACHES TO PROJECT MANAGEMENT Methods of network analysis are used in practice for project management. First of all we urge that a project is not only event but also its preparation, realization and documentation. Project management needs five different management activities [T2], [P1]: 1) defining of project goals, 2) planning of fulfilling project goals, 3) managing of project implementations, 4) monitoring of project activities process, 5) finishing of the project. Now we notice only some main application problems concerning the previous five points. Detailed description of these activities would be longer and it is not a goal of this paper. 1) The definition of project goals would contain measurable material and verifying acceptation criteria to make sure the final output is really acceptable. Every goal have to contain exact and clear defined contents, scale (including the deviations) dead line, person who is responsible for goal fulfillment, way and periodicity of evaluation, see [P1], [B2]. 2) Planning of goals fulfillment should have contain following properties, [T2]: a) identifying all activities necessary for project finishing, 108
9 Network Analysis and Project Management an Overview b) it should have contains flow chart to set these activities, c) defining necessary sources and time of their application, d) it had the budget for every activity, e) it contains back up for unpredictable events, f) the plan is credible for implementation and project managers, too. The credibility of plan (property f) is important during the whole realization of the project. Reserves (property e) need some methodology for considering of project risks. These risks are uncovered before starting of the project and during the morning of project process. Some methodic are published and some of them are firm property only, [K2]. The main properties of these methodic are described in [T2]. The term project risks relate with the term critical path described is the chapter network graphs, part 2. 3) A problem of project implementations managing and a problem of monitoring project activities process are detail propositions frame of project management. We will not describe them here but readers can receive some basic knowledge in [G1], [C1] and [SJ1]. 4) The best reason for project finishing is fulfillment of all project goals defined at the project beginning. Necessity of all resources can change during the project realization but only by change process. Project success depends on many factors, e. g. clear and stable project goals, cognizant customer, experienced management, early project actualization, etc. (see e. g. [C1], [IB1]). 6. NON TRADITIONAL APPROACHES TO PROJECT MANAGEMENT A critical path of a project determines time necessary for project finishing. Every activity of a project can loose therefore there are insert some activity reserves into the project. They are based on pessimistic forecast of every activity duration. E. Godratt proposed to change this standard technique this way [G1]. Time change: We will not estimate duration of every activity by pessimistic forecast but the most probable estimation. We will not assign the reserves to every activity but only: to the end of a critical path (it is called project buffer), to the end of every project branch concerning to a critical path (it is called joining buffer). 109
10 F. Gliviak, P. Sakál When the activity duration will be greater than their estimation, we will draw the rime from the nearest buffer. The time is not enough for multiproject management. Resources are usually narrow and are used in several projects at the same time. Then, very strong relations between projects as consequences off resources exist, there. Resource change: E. Goldratt suggested carrying out everything that relate to one project resource, at once. More precisely, either bond of succession in activity graph or bond of using the same resource can give the dependence between two activities of one project. Then we have chains of sequentially depending activities. The longest chain from these chains is called critical chain. The critical chain is different term then the critical path. In critical chain, we work with time reserve by project buffer or joining buffer analogically as it was in the previous part when was concerning the time. 7. ACTUAL SOFTWARE POSSIBILITIES In this part we give only necessary orientation facts and we will not promote any software system. 1. Software system MS Project, version 2000 of firm Microsoft has been using by all universities for a little tariff. This system is very useful for teaching of project management and for first professional experiments with a project. 2. Society for Project Management in Slovakia (SPPR) organizes a conference or seminar concerning new applications of project management, every year. Both authors of this paper take part in these conferences. There is possible to see the trends in application and also in using some software systems, see [I1]. 3. Some software specialists are forecasting that there exist approximate 60 different software products for this area, now. We will not specify them only mention the names of that they are made good in our field. They are e. g. Superproject, Prochain, Primavera, Planisware. Promotional materials of all these systems give all their responsibilities and also their actual price in Slovak republic. 8. APPLICATION EXPERIENCES IN SLOVAC REPUBLIC Results of network analysis have transformed to software systems for project management gradually. This process was an international one and now we mention several facts concerning realization in Slovakia. 110
11 Network Analysis and Project Management an Overview 1. In Slovakia, there are two firms Slovakodata Bratislava and Aiten Trnava that have been dealing with project management more than 10 years. The both firms are approximately same large. Slovakodata Bratislava is solving about 15 parallel projects, see [K4]. Project management is one of the main activities of both firms, see [I4], [I5]. 2. Besides them, there exist a lot of industrial applications of project. Many of them are presented on the conferences society SPPR. Authors and contents of these projects can be found in [I1]. The seat of Slovak Society for Project Management is in Trnava at Faculty of Materials Science and Technology. 3. Universities in Slovakia have very good background in this field. Specialists for projects management finish every year at Slovak University of Technology Bratislava (Faculty of Materials Science and Technology, Faculty of Engineering), Economical University Bratislava. There are similar study branch at other universities, e.g. Komenius University, Faculty of Mathematics, Physics and Informatics, Bratislava there is study branch mathematics management. We are mentioning some examples of various business projects solving at The Department of Industrial Engineering and Management of Faculty of Materials Science and Technology of Slovak University of Technique in Slovak republic: Time analysis of fuel changing in power plant V-1 Jaslovské Bohunice by CPM methodology for EC 1021 (1983), Time analysis of new product loading in to the production of National Coin Kremnica (1991), Time analysis of general revision of automatic mechanical batten machine ASP 400 (1991), Layout of universal model of EMS construction by ISO in Chemosvit, a. s. Svit (1999), Application of project planning methods for construction of EMS in SE EBO Jaslovké Bohunice (2000), Project planning utilization for EMS loading in TOPOS, a. s. Továrniky (2004). You can find the other examples in actual information of SPPR, see [I1]. 111
12 F. Gliviak, P. Sakál ACKNOWLEDGMENTS The authors would like to thank to Dipl. Ing.Helena Vidová senior lecture of Department of Industrial Engineering and Management, Faculty of Materials Science and Technology Trnava, Slovak University of Technology for technical and lingual correction. REFERENCES [B1] Blecha V.: Síťová analýza ve stavebníctví. Dúm techniky ČSVTS, Praha, 1989, (in Czech). [B2] Bullová K.: Sieťová analýza a riadenie projektov. Diploma work for Mgr., supervisor F. Gliviak. Comenius University, FMFI, Bratislava, 2004, (in Slovak). [C1] Čambál M. Holková A. Horňák F.: Manažérstvo podniku. Slovak University of Technology, MtF, Trnava, 2000, (in Slovak). [G1] Goldratt E. M.: Kritický reťazec, Inter Quality, Praha, 1999, (in Czech, translation from English). [G2] Gros I.: Kvalitatívne metódy v manažérskom rozhodovaní. Grada, Praha, 2003, (in Czech). [GV1] Gliviak F. Vadkerti P.: Sieťová analýza a manžment projektov. Univerity of St. Cyrili and Methodi, FPV, Trnava, 2001, (in Slovak). [GY1] Gross J. Yellen J.: Graph Theory and its Applications. CRC Press, New York, [IB1] Ivaničová Z. Brezina I. - Pekár J.: Operačný výskum. Economical university, Bratislava, 2002, (in Slovak). [J1] Jungnickel D.: Graphs, Networks and Algoritms. Springer, Berlin, [K1] Klusoň V.: Kritická cesta a PERT v řídíci praxi. SNTL, Praha, 1968, (in Czech). [K2] Kubiš J: Existenčné riziká projektu a k nemu viazaných subjektov. In: Tvorba SW 2002 (celoštátna konferencia), Ostrava, Česká společnost pro systémovou integraci 2002, , (in Slovak). [K3] Kubiš J.: Cykly v projektoch. In: tvorba SW 2003(celoštátna konferencia), Ostrava, Česká společnost pro sysémovou integraci, 2003, 63 70, (in Slovak). [K4] Kubiš J.: Analýza výkonov SW firmy. In: Tvorba SW 2004, Ostrava, Česká společnost pro sysémovou integraci, 2004, , (in Slovak). [P1] Projektový manažment a jeho využitie v praxi. (Metódy a nástroje). Proc. of the seminar, Slovak University of Technology, MtF, Trnava, 2004, (in Slovak). [SŠ1] Sakál P. Štrpka A.: Operačná a systémová analýza. Slovenská technická univerzita, Strojnícka fakulta, Bratislava, 1982, (in Slovak). [SJ1] SakálP. Jerz V.: Operačná analýza v praxi manažéra. SP Synergia, Trnava, 2003, (in Slovak). [T1] Trávnik I. Vlach J: Sieťová analýza. ALFA, Bratislava, 1974, (in Slovak). [T2] Trávnik I.: Projektmanažment. Slovenská techniká univerzita, Stavebná fakulta, Bratislava, 2001, (in Slovak). [U1] Unčovský L. a kol.: Modely sieťovej analýzy. ALFA, Bratislava, 1991, (in Slovak). [ZR1] Zuchovicky S. J.- Radčikova J. A.: Matematické matódy síťové analýzy, SNTL, Praha, 1972, (in Czech, taranslation form Russian). [W1] Walter J.- Vejmola S.- Fiala P.: Aplikace metód síťové analýzy v řízení a plánovaní. SNTP, Praha, 1989, (in Czech). Internetové zdroje: [I1] [I2] [I3] [I4] [I5] 112
13 Network Analysis and Project Management an Overview 113
CHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Chapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
Priori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
NETWORK ANALYSIS OF A TOLLING PROJECT
NETWORK ANALYSIS OF A TOLLING PROJECT Kamila JANOVSKÁ a, Šárka VILAMOVÁ a, Iveta VOZŇÁKOVÁ a, Petr BESTA a, Josef KUTÁČ a, Jakub GAJDA b, Eva Švecová a a VSB-Technical University of Ostrava, Czech Republic,
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
Application Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK
PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK M Nazrul, ISLAM 1, Eugen, DRAGHICI 2 and M Sharif, UDDIN 3 1 Jahangirnagar University, Bangladesh, [email protected] 2 Lucian Blaga University
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
The management of the projects with MS Project
The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist
added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.
Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the
APPLICATION OF ANALYTIC HIERARCHY PROCESS METHOD IN THE EVALUATION OF MANAGERS OF INDUSTRIAL ENTERPRISES IN SLOVAKIA
Trendy v podnikání, 5(3) 28-35 The Author(s) 2015 ISSN 1805-0603 Publisher: UWB in Pilsen http://www.fek.zcu.cz/tvp/ APPLICATION OF ANALYTIC HIERARCHY PROCESS METHOD IN THE EVALUATION OF MANAGERS OF INDUSTRIAL
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans
RESEARCH PAPERS FACULTY OF MATERIALS SCIENCE AND TECHNOLOGY IN TRNAVA SLOVAK UNIVERSITY OF TECHNOLOGY IN BRATISLAVA
RESEARCH PAPERS FACULTY OF MATERIALS SCIENCE AND TECHNOLOGY IN TRNAVA SLOVAK UNIVERSITY OF TECHNOLOGY IN BRATISLAVA 2010 Number 29 3D MODEL GENERATION FROM THE ENGINEERING DRAWING Jozef VASKÝ, Michal ELIÁŠ,
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
RESEARCH PAPERS FACULTY OF MATERIALS SCIENCE AND TECHNOLOGY IN TRNAVA SLOVAK UNIVERSITY OF TECHNOLOGY IN BRATISLAVA
RESEARCH PAPERS FACULTY OF MATERIALS SCIENCE AND TECHNOLOGY IN TRNAVA SLOVAK UNIVERSITY OF TECHNOLOGY IN BRATISLAVA 2012 Special Number THE IMPORTANCE OF HUMAN RESOURCE PLANNING IN INDUSTRIAL ENTERPRISES
15. How would you show your understanding of the term system perspective? BTL 3
Year and Semester FIRST YEAR II SEMESTER (EVEN) Subject Code and Name BA7201 OPERATIONS MANAGEMENT Faculty Name 1) Mrs.L.SUJATHA ASST.PROF (S.G) 2) Mr. K.GURU ASST.PROF (OG) Q.No Unit I Part A BT Level
IMPROVING RESOURCE LEVELING IN AGILE SOFTWARE DEVELOPMENT PROJECTS THROUGH AGENT-BASED APPROACH
IMPROVING RESOURCE LEVELING IN AGILE SOFTWARE DEVELOPMENT PROJECTS THROUGH AGENT-BASED APPROACH Constanta Nicoleta BODEA PhD, University Professor, Economic Informatics Department University of Economics,
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
SUCCESSFUL IMPLEMENTATION OF BUSINESS INTELLIGENCE AS A TOOL FOR COMPANY MANAGEMENT Tomáš Mandičák, Peter Mesároš, Karol Hrubý. INTRODUCTION Nowadays, situation on the markets is not easy for companies.
USING THE WINQSB SOFTWARE IN CRITICAL PATH ANALYSIS
USING THE WINQSB SOFTWARE IN CRITICAL PATH ANALYSIS Abstract UŽITÍ PROGRAMU WINQSB V ANALÝZE KRITICKÉ CESTY Mgr. Kamil Peterek 2 College of logistics p.b.c., Perov e-mail: [email protected] In the
Resource Allocation and Scheduling
90 This section is about the general overview of scheduling and allocating resources. Assigning people and machines to accomplish work (work on tasks). Resource Allocation: Time-Constrained. Assigning
High-Mix Low-Volume Flow Shop Manufacturing System Scheduling
Proceedings of the 14th IAC Symposium on Information Control Problems in Manufacturing, May 23-25, 2012 High-Mix Low-Volume low Shop Manufacturing System Scheduling Juraj Svancara, Zdenka Kralova Institute
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
Outline. NP-completeness. When is a problem easy? When is a problem hard? Today. Euler Circuits
Outline NP-completeness Examples of Easy vs. Hard problems Euler circuit vs. Hamiltonian circuit Shortest Path vs. Longest Path 2-pairs sum vs. general Subset Sum Reducing one problem to another Clique
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
Introduction to Scheduling Theory
Introduction to Scheduling Theory Arnaud Legrand Laboratoire Informatique et Distribution IMAG CNRS, France [email protected] November 8, 2004 1/ 26 Outline 1 Task graphs from outer space 2 Scheduling
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
Optimization: Optimal Pricing with Elasticity
Optimization: Optimal Pricing with Elasticity Short Examples Series using Risk Simulator For more information please visit: www.realoptionsvaluation.com or contact us at: [email protected]
March 30, 2007 CHAPTER 4
March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review
MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING
MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
ADJUSTED INVENTORY MANAGEMENT SYSTEM OF LEVELS OF STRATEGIC GOODS DIFFERENTIATED BY USING THE ABC METHOD
The International Journal of TRANSPORT &LOGISTICS Medzinárodný časopis DOPRAVA A LOGISTIKA ISSN 1451-107X ADJUSTED INVENTORY MANAGEMENT SYSTEM OF LEVELS OF STRATEGIC GOODS DIFFERENTIATED BY USING THE ABC
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
BENEFITS AND ADVANTAGES OF BUSINESS INTELLIGENCE IN CORPORATE MANAGEMENT
International Journal of Latest Research In Engineering and Computing (IJLREC) Volume 3, Issue 1, Page No. 1-7 January-February 2015 www.ijlrec.com ISSN: 2347-6540 BENEFITS AND ADVANTAGES OF BUSINESS INTELLIGENCE
Critical Path Method (CPM)
Project Management Templates (CPM) http://spreadsheetml.com/projectmanagement/criticalpathanalysis.shtml Copyright (c) 2009-2010, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility
A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method
Send Orders for Reprints to [email protected] 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
A Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
SUPPLY CHAIN OPTIMIZATION MODELS IN THE AREA OF OPERATION
SUPPLY CHAIN OPTIMIZATION MODELS IN THE AREA OF OPERATION Tomáš DVOŘÁK, Martin VLKOVSKÝ Abstract: Main idea of this paper is to choose both suitable and applicable operations research methods for military
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Scheduling Shop Scheduling. Tim Nieberg
Scheduling Shop Scheduling Tim Nieberg Shop models: General Introduction Remark: Consider non preemptive problems with regular objectives Notation Shop Problems: m machines, n jobs 1,..., n operations
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics
Introduction to Project Management Chapter 2 The Project Management Life Cycle Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 2-1 What
Research on Task Planning Based on Activity Period in Manufacturing Grid
Research on Task Planning Based on Activity Period in Manufacturing Grid He Yu an, Yu Tao, Hu Da chao Abstract In manufacturing grid (MG), activities of the manufacturing task need to be planed after the
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
A SIMULATION APPROACH TO PRODUCTION LINE BOTTLENECK ANALYSIS
A SIMULATION APPROACH TO PRODUCTION LINE BOTTLENECK ANALYSIS Michal Leporis and Zdenka Králová Slovak University of Technology Faculty of Electrical Engineering and Information Technology Ilkovičova 3,
A study of cash flows in projects with fuzzy activity durations
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) A study of cash flows in projects with fuzzy activity
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Cost Model: Work, Span and Parallelism. 1 The RAM model for sequential computation:
CSE341T 08/31/2015 Lecture 3 Cost Model: Work, Span and Parallelism In this lecture, we will look at how one analyze a parallel program written using Cilk Plus. When we analyze the cost of an algorithm
ARTICLE IN PRESS. European Journal of Operational Research xxx (2004) xxx xxx. Discrete Optimization. Nan Kong, Andrew J.
A factor 1 European Journal of Operational Research xxx (00) xxx xxx Discrete Optimization approximation algorithm for two-stage stochastic matching problems Nan Kong, Andrew J. Schaefer * Department of
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
Arrangements And Duality
Arrangements And Duality 3.1 Introduction 3 Point configurations are tbe most basic structure we study in computational geometry. But what about configurations of more complicated shapes? For example,
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects Hamed Ziaidoostan 1, Hamidreza Ghaneh 2, Matin Amanin 3, Mohamadmahi Gholipoor 4 1,2,3,4-M A Student of Business
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
Chapter 11 Monte Carlo Simulation
Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important
Project management Project Management
Project management Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar A project is a temporary endeavour to produce a unique product, service, or result (PMI
Project Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall
3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery
SELECTED MODERN APPROACHES TO THE VALUATION OF FIXED ASSETS FOR INSURANCE PURPOSES
Anna Majtánová Lívia Sojková Ekonomická Univerzita v Bratislave SELECTED MODERN APPROACHES TO THE VALUATION OF FIXED ASSETS FOR INSURANCE PURPOSES Introduction Every business entity is forced to value
Project Management (CS 3730) Lecture 4 Name:
Ch. 6: Scheduling Project Work 1. Some people think that project management is nothing but scheduling, but scheduling is just one of the tools used to manage jobs and should not be considered the primary
A STUDY OF TASK SCHEDULING IN MULTIPROCESSOR ENVIROMENT Ranjit Rajak 1, C.P.Katti 2, Nidhi Rajak 3
A STUDY OF TASK SCHEDULING IN MULTIPROCESSOR ENVIROMENT Ranjit Rajak 1, C.P.Katti, Nidhi Rajak 1 Department of Computer Science & Applications, Dr.H.S.Gour Central University, Sagar, India, [email protected]
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two. By Eli Schragenheim and Daniel P. Walsh
vector strategies The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two By Eli Schragenheim and Daniel P. Walsh The floor looks similar to any other manufacturing floor.
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
Scheduling Algorithm for Delivery and Collection System
Scheduling Algorithm for Delivery and Collection System Kanwal Prakash Singh Data Scientist, DSL, Housing.com Abstract Extreme teams, large-scale agents teams operating in dynamic environments are quite
Project Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT. Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ VSB Technical University of Ostrava, Ostrava, Czech
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used