Advanced Technology Portable End-to-End Test System (PETS) Final Project Report
|
|
|
- Avis Elliott
- 9 years ago
- Views:
Transcription
1 Advanced Technology Portable End-to-End Test System (PETS) Final Project Report Developed by SCE Transmission & Distribution, Advanced Technology Organization Address Southern California Edison Advanced Technology Chestnut St. Westminster, Ca 92683
2 Disclaimer Acknowledgments Prepared for: Southern California Edison, Advanced Technology, Public Utilities Commission of the State of California Prepared by: Aleida Gonzalez Principle Investigators (s): Christopher Clarke, Aleida Gonzalez Change Log Version Date Description of Change Project Report No First revision PS Final version PS i
3 Table of Contents PS , PETS, Final Report 1 Executive Summary Project Summary Project Objective Problem Statement Scope Schedule Milestones and Deliverables Test Set-Up/Procedure Software/Hardware Test Methodology Test Case development Test Set-Up Project Results Technical Results, Findings, and Recommendations Technical Lessons Learned Value Proposition Technology/Knowledge Transfer Plan Metrics Appendix ii
4 List of Figures Figure 1 Test set-up... 4 Figure 2 Start Timer... 5 Figure 3 Runtime Controls... 6 Figure 4 Two Terminal Oneline Diagram... 6 Figure 5 Example of Script... 7 Figure 6 Three Terminal Oneline Diagram... 8 Figure 7 GTAO Setup Configuration... 9 Figure 8 GTFPI Setup Configuraiton... 9 List of Tables Table 1 Project Schedule... 3 Table 2 Milestones and Deliverables... 4 Table 3 Source Model Data... 5 Table 4 Script Input Parameters... 7 Preface iii
5 1 Executive Summary The intention of this demonstration project is to develop a Portable-End-to-End Test System (PETS) tool to conduct end-to-end testing of relay protection equipment using a portable Real Time Digital Simulator (RTDS) at each substation connected to the line under test. The test is designed to provide realistic fault simulations in order to prove that the entire relay protection schemes are properly configured including physical wirings. Aside from being able to conduct existing End-to-End test procedures which focus on the relay, the tool would be able to test the system as well. More specifically the tool would be able to test all communications pertaining to the line being tested and run a large number of disturbances using an automated script to identify a pass or fail based on predetermined SCE test criteria. Test reporting procedures would be similar to what is performed in the RTDS lab today to ensure that all performed tests are properly evaluated. This project does not support any existing regulatory proceedings. However, relay testing falls under NERC/WECC bulk power reliability criteria. Therefore, this project, as a proof of concept has the potential to increase the reliability of our protective schemes via rigorous testing and thus demonstrate SCE s proactive approach towards reliability. The first step was to overcome the difficulty of being able to sync the simulation of the system under test using the portable RTDS units located at different substations. Close collaboration with the software developer resulted in an addition of a case start timer to the simulation software, which allowed the start time be synchronized. After a few delays in ordering the necessary equipment, test cases, scripts and draft test plans were created to test a two and three point line end-to-end relay test utilizing the prototype PETS tool. Preparations were made to conduct a preliminary test under a control environment in order to test the prototype prior to field testing. In the process of developing the methodology to perform the test in the field, and through feedback from the end-users it was discovered that there were a limited number of test scenarios where the tool would be a great improvement over existing test procedures. As a result the project team concluded that there was no substantial value in further pursuing the development of the PETS tool. Although the tool would be an improved method of testing system performance when conducting end-to-end relay tests, the implementation of a companywide Portable End-to- End Test system (utilizing a Real Time Digital Simulator system) would not be cost effective when compared to traditional test methods. The major aspects that would drive the cost of implementing the PETS projects are: Development of specialized training would be required for field crews to be able to use the tool Availability of the tool; it would be extremely costly to purchase several PETS test sets to accommodate the different regions within SCE s territory when compared to purchasing existing tool in use Dedicated engineering staff to support issues related to maintenance and training After careful deliberation of the benefits associated with proceeding with the PETS project, the team concluded that the tool did not provide value to the rate payers, except for demonstration purposes. Notwithstanding the innovation of the tool, it is not currently a viable option. Furthermore, the early close-out of this project does not impact how protection schemes are tested today as it was intended to be a proof of concept demonstration project. Page 1
6 2 Project Summary The intention of this demonstration project is to develop a Portable-End-to-End Test System (PETS) tool to conduct end-to-end testing of relay protection equipment using a portable Real Time Digital Simulator (RTDS) at each substation connecting the line under test. The RTDS is a computer that is capable of simulating electric power system transients in real time. It has hardware in the loop (HIL) capability and can simulate system conditions and implement the closed-loop response of the device under test. The PETS tool test is designed to provide realistic fault simulations in order to prove that the entire relay protection schemes are properly configured including physical wirings. 2.1 Project Objective PETS will provide more thorough testing in fewer hours than required by traditional tests during commissioning and routing of transmission lines. Test technicians would be provided with more accurate and extensive test results which means higher assurance that critical transmission and distribution lines and components are operationally adequate and exceed NERC/WECC bulk power reliability criteria. 2.2 Problem Statement The existing end-to-end protective relaying scheme provides for a limited testing of relay schemes. The PETS tool would provide an opportunity for more comprehensive testing of protective relay schemes at high voltage transmission lines. The PETS tool would: Be able to test system performance (currently there does not seem to be a method to test the entire protection scheme at the same time, for example provide the same currents and voltages to all the relays at the same time). Provide greater flexibility to test crews when performing 3 terminal end to end relay tests. Existing test set-up is limiting given that test personnel only have access to very few predetermined fault scenarios. Typically the scenarios are created using past DFR recorded events, or created using comtrade files from previous tests. The PETS tool would provide flexibility in creating different fault scenarios where fault type, inception angle, location and resistance could easily be changed. Have the ability to test relays in adjacent positions at the same time by injecting the same faults. The adjacent relays would then experience a reverse fault and their behavior could be observed. 2.3 Scope This demonstration project will explore the feasibility of developing and implementing an end-toend relaying scheme test tool using portable RTDS, amplifiers and satellite clocks. The tool set would address 1) relay protection equipment, 2) communications, and 3) provide a pass/fail grade based on the results of automated testing using numerous simulated disturbances. When compared to existing tools, which provide a limited number of scenarios (disturbances) and focus on testing protection elements, the PETS project will additionally provide testing of system protection. It will also develop a process and methodology to perform such testing in the field. Tests will be documented using a reporting procedure used in the RTDS lab today, ensuring all test data is properly evaluated. Initially the scope aimed to achieve three main tasks: Page 2
7 PS , PETS, Final Report Develop and validate RTDS power system model for end-to-end testing. Demonstrate in-lab test of 2 and 3 terminal lines using RTDS hardware-in-the-loop. Test plan document developed in-lab to be used during end-to-end field testing Demonstrate field test of a 3 terminal line using the RTDS in the field. Final report with results of end-to-end field testing and test procedure based on NERC requirements. During the process of developing the methodology to demonstrate the in-lab test and development of documentation to perform end-to-end field testing, and through feedback from the end-users it was discovered that there is a limited number of test scenarios where the tool would be a great improvement over how the tests are conducted today. Although the PETS system would be an improved method of testing system performance when conducting end-to-end relay tests, the implementation of a companywide Portable End-to-End Test system (utilizing a Real Time Digital Simulator system) would not be cost effective when compared to traditional methods of conducting these tests. Also while in the process of preparing for the first demonstration, it became apparent that using the PETS tools would require specialized training that would not be readily available to field crews. After reviewing the feasibility of company wide deployment of the PETS tools it was deemed prudent to discontinue the project in its early stages. The completed tasks include development of test cases, scripts and draft test plans to test a two and three point line end-to-end relay test. Other factors that affected the development of this project were delays in ordering and delivery of equipment as well as group-reorganization. 2.4 Schedule A high level schedule overview is presented in the following table: Task Name Authority to proceed Spec & Procure Portable RTDS Create RTDS end-to end test tool Create test cases and Scripts Create and test reporting tool Test tool in field Train SCE stakeholders Create final report End project Table 1 Project Schedule Duration 0 days 4 Months 9 Months 3 Months 3 Months 2 Months 2 Months 3 Months 0 days Page 3
8 2.5 Milestones and Deliverables PS , PETS, Final Report Table 2 shows a list of milestones and deliverables. Due to early close-out of project, a status of cancelled is shown in status column. Milestone/Deliverable Specs & Procure Portable RTDS Develop PETS tool Create RTDS end-to-end test tool (Dec. 2014) Create test cases & scripts (Dec. 2014) Create and test reporting tool Test tool in the field Training SCE Stakeholders Create final report Final Report Out to Stakeholders Table 2 Milestones and Deliverables 3 Test Set-Up/Procedure Status Completed Completed Cancelled Completed Cancelled Cancelled Cancelled Completed Completed PETS will employ portable Real-Time Digital Simulators (RTDS s) in substations at each end of the transmission line being tested (see figure 1). Figure 1 Test set-up 3.1 Software/Hardware Different software interfaces were utilized in the development this project. RTDS modeling and validation was performed using RSCAD version Load flow data was viewed and extracted using PSLF 18, and short circuit data was viewed and extracted using CAPE All scripting was done in Notepad++ and Microsoft Excel. ProtTest software was used to interact between relays and Doble test sets and GE Enervista was used to communicate with protective relays. The hardware components of the PETS tool consist of Portable RTDS units, Doble test sets (voltage and current amplifiers), GPS clock and antenna for synchronization. Page 4
9 3.2 Test Methodology PS , PETS, Final Report There are two main stages to the development of the PETS tool. The first stage comprised of creating test cases, scripts and draft test plans in order to complete dry run in a control lab environment. In the second stage the tool would involve prototype lab testing and field tests. A multi-terminal (3-point) test would be conducted with a field crew at each location to test the full capabilities of the tool. 90 percent of the first stage was completed, the second stage was not achieved. 3.3 Test Case development The initial test case development took place in the Advanced Technologies Power System Lab. A less complex 2 terminal end-to-end case was created in RTDS to test the start timer in order to perform synchronization tests. Figure 2 Start Timer The RTDS simulates a model of the system under test and surrounding nearby area in real time. Every substation modeled contains a bus label and infinite source model. The label defines the bus name, voltage base, and type. The label information used show in table 3. After the model is built it can be manipulated through RSCAD Runtime. RSCAD Runtime provides two critical functions, 1) it allows the user to interact with and manipulate the simulation and 2) it enables the simulation results to be monitored and recorded. Error! Reference source not found.3 below shows the controls for the fault conditions. The slider, pushbutton, dial, and switch components are all model inputs that assign the value they are given in the Runtime to the associated variable in the draft model. Figure 4 shows a one line diagram of the two terminal test case with internal and external fault locations. Page 5
10 Bus Name Short Name Source P Source Q Load P Load Q Pardee PAR (117.5) Sylmar SY 1,134.0 (479.0) - - Gould GO (74.0) Eagle Rock ER Santa Clara SC (2.4) Vincent VIN Goodrich GR (140.0) (29.0) - - Mesa ME Center CE Walnut WL Litehipe LI 54.2 (3.2) - - Redondo RE Rio Hondo RH (137.0) Laguna Bell LB Del Amo DELA 97.2 (19.8) - - Table 3 Source Model Data PS , PETS, Final Report Figure 3 Runtime Controls Page 6
11 Figure 4 Two Terminal Oneline Diagram Scripts were utilized in order to control the operation of the simulation and to collect and analyze the results. Figure 5 shows a snapshot of one of the scripts used to control and set-up the fault conditions and table 4 shows case scenarios that are used as inputs to the script. Page 7
12 Figure 5 Example of Script Test No. Description Location (FLTDIAL) Fault Time (FLTTIME) Fault POW (FLTPOW) FLTA FLTB FLTC FLTAB FLTBC FLTCA 1 Right Bus - BG Right Bus - AB % Beyond Right Bus - CG % Beyond Right Bus - ABC Left Bus - AG Left Bus - CA % Beyond Left Bus - AG % Beyond Left Bus - BCG % From Left Bus - AB % From Left Bus - CG % From Left Bus - BCG % From Left Bus - ABCG % From Left Bus - BG % From Left Bus - CA % From Left Bus - BC % From Left Bus - AG % From Left Bus - ACG % From Left Bus - ABCG Table 4 Script Input Parameters After successfully running the 2 terminal end-to-end simulation, a 3 terminal end-to-end test case was created, a one line diagram in shown in figure 6. Ultimately the 3 terminal test did make it to the actual field test. Page 8
13 Figure 6 Three Terminal Oneline Diagram Test Set-Up The test set-up for the PETS prototype tool included the following equipment: 3 Portable RTDS units 3 Doble test sets (voltage and current amplifiers) 3 GPS Clocks 3 Antennas Protection relays At each end of the line would be equipped with a portable RTDS unit, doble test set, GPS clock and antenna. Voltage and current signals from the portable RTDS are sent via a GTAO interface card to the Doble test set which are subsequently transferred to the protection relays. The output scaling for the GTAO cards is adjusted so that the primary voltage and current measurements read by the relay matches that of the RTDS RunTime. Selected relay signals are mapped to outputs on the relay and then physically connected to the Portable RTDS front panel interface. In RSCAD, the GTFPI component outputs all the digital signals as a 16-bit word. The individual signals are extracted using word-to-bit conversion components. GTAO and GTFPI setup configuration are presented in figure 7 and 8 respectively. Page 9
14 Figure 7 GTAO Setup Configuration Figure 8 GTFPI Setup Configuraiton Page 10
15 4 Project Results No results were recorded. 4.1 Technical Results, Findings, and Recommendations PS , PETS, Final Report Project may be revisited at a later time if it deemed that it would provide greater reliability at lower costs. 4.2 Technical Lessons Learned The test setup yielded lessons learned that pointed the team to determining that this technology was not a viable option at this time. For example, the test set up required significant power to drive 5 Doble test sets, as well as an outdoor area to set up a GPS antenna. Additionally the test setup needed to mirror field conditions (i.e., no external monitors, all test equipment needed to be transportable, etc.), so that we would be able to perform the test in a remote location without any unexpected events. Furthermore, the setup required a mobile RTDS unit and Doble test set per terminal, meaning that 3 of each (RTDS unit and Doble test set) would be needed for lines that contained 3 terminals. The team s analysis discovered however, that in our system very few 220 lines in fact have more than 2 terminals, and that the existing test systems were adequate options for testing 2 terminal lines. 4.3 Value Proposition The objective of the PETS project was to meet EPIC s primary principle criteria of providing greater reliability to the customers. However, it was determined that the benefits associated with this demonstration project did not outweigh the costs and ultimately it would not provide added value. 4.4 Technology/Knowledge Transfer Plan A technology transfer plan was not developed. 5 Metrics The project was successful in proving that the tools exist to conduct advanced end-to-end relay testing, albeit not cost effective. Page 11
16 6 Appendix List of Acronyms AT EPIC GPS GTAO GTFPI PETS RTDS SCE Advanced Technology (the organization) Electric Program Investment Charge Global Positioning System Gigabit Transceiver Analogue Card Gigabit Transceiver Front Panel Interface Portable-End-to-End Test System Real Time Digital Simulator Southern California Edison Page 12
Everything you need for protection scheme testing
Power System Simulator for Testing Protection Relays and Schemes Everything you need for protection scheme testing The is the only instrument with the high power, flexibility and software to perform full
San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions August 10, 2015. Electric Grid Operations
San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions August 10, 2015 Electric Grid Operations Director Electric Grid Operations: Responsible for overall transmission
San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 4, 2015. Electric Grid Operations
San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 4, 2015 Electric Grid Operations Director Electric Grid Operations: Responsible for overall transmission
APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES
APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES J. Ariza G. Ibarra Megger, USA CFE, Mexico Abstract This paper reviews
Testing Intelligent Device Communications in a Distributed System
Testing Intelligent Device Communications in a Distributed System David Goughnour (Triangle MicroWorks), Joe Stevens (Triangle MicroWorks) [email protected] United States Smart Grid systems
Electric utilities may vary in their application of end-to-end testing
An Application Case of End-to-End Relay Testing of Communication-Based Protection Schemes Using GPS-Synchronized Secondary Injection Feature by J. Ariza, Megger USA G. Ibarra, CFE, Mexico Electric utilities
Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template
Application Note Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template Author Jens Baumeister [email protected] Date
Allen Goldstein NIST Synchrometrology Lab Gaithersburg, MD [email protected]
Time Synchronization in Electrical Power Transmission and Distribution Systems Allen Goldstein NIST Synchrometrology Lab Gaithersburg, MD [email protected] Abstract Synchronization of measurements
Midwest Reliability Organization Procedure For NERC PRC-012
Midwest Reliability Organization Procedure For NERC PRC-012 A. Introduction The following procedure developed by the MRO Protective Relay Subcommittee (PRS) and Transmission Assessment Subcommittee (TAS)
Best Practices for Creating Your Smart Grid Network Model. By John Dirkman, P.E.
Best Practices for Creating Your Smart Grid Network Model By John Dirkman, P.E. Best Practices for Creating Your Smart Grid Network Model By John Dirkman, P.E. Executive summary A real-time model of their
DEVELOPING FUTURE SUBSTATION AUTOMATION STRATEGIES: SELECTING APPROPRIATE IEDs AND DEVELOPING NEW APPLICATIONS
DEVELOPING FUTURE SUBSTATION AUTOMATION STRATEGIES: SELECTING APPROPRIATE IEDs AND DEVELOPING NEW APPLICATIONS Mladen Kezunovic Tomo Popovic Texas A&M University Test Laboratories Intl, Inc. Department
Test & Data Management Software
Test & Data Management Software TDMS protective relays energy meters transducers power quality CT-VT-PT transformers ground grid circuit breakers batteries surge arresters The Integrated Testing Solution
Continuous integration for databases using
Continuous integration for databases using Red Wie Sie Gate die tools Microsoft SQL An overview Continuous integration for databases using Red Gate tools An overview Contents Why continuous integration?
Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014
1 Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables Bob Yinger Southern California Edison April 15, 2014 Southern California Edison SCE provides power to: Nearly
Testing for the Unexpected: An Automated Method of Injecting Faults for Engine Management Development
Testing for the Unexpected: An Automated Method of Injecting Faults for Engine Management Development By Shaun Fuller What will happen if a fault occurs in an automotive vehicle s electrical system? Similarly,
California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
SHORT TRAINING COURSES
Post Office Box SR 95, Spintex Road, Ghana Tel: +233 302 812680, Fax: +233 302 814709 E mail: [email protected] Website: www.automationghana.com SHORT TRAINING COURSES Equipping industries with
Mladen Kezunovic Texas A&M University
INTEGRATING DATA AND SHARING INFORMATION FROM VARIOUS IEDs TO IMPROVE MONITORING, CONDITION-BASED DIAGNOSTIC, MAINTENANCE, ASSET MANAGEMENT AND OPERATION TASKS Introduction Mladen Kezunovic Texas A&M University
IEC 61850: Communication Networks and Systems in Substations
IEC 61850: Communication Networks and Systems in Substations Sistemi e strumenti per l'automazione, A. Flammini, AA2011-2012 Background I: Power Grid Sistemi e strumenti per l'automazione A. Flammini,
Steve Lusk Alex Amirnovin Tim Collins
Steve Lusk Alex Amirnovin Tim Collins ViaSat Inc. Cyber-intrusion Auto-response and Policy Management System (CAPMS) Cybersecurity for Energy Delivery Systems Peer Review August 5-6, 2014 Summary: Cyber-intrusion
TDMS Test & Data Management Software
Test & Data Management Software TDMS protective relays energy meters transducers power quality CT-VT-PT transformers ground grid circuit breakers batteries surge arresters The Integrated Testing Solution
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
Clearing the Way for VoIP
Gen2 Ventures White Paper Clearing the Way for VoIP An Alternative to Expensive WAN Upgrades Executive Overview Enterprises have traditionally maintained separate networks for their voice and data traffic.
Continuous integration for databases using Redgate tools
Continuous integration for databases using Redgate tools Wie Sie die Microsoft SQL Server Data Tools mit den Tools von Redgate ergänzen und kombinieren können An overview 1 Continuous integration for
TURBOtech srl. SED-635 Digital Excitation System. Industrial Electronics Sector FEATURES
SED-635 Digital Excitation System SED-635 is a complete excitation system capable of adapting to control synchronous generators of any size. The integration of the TOUCH SCREEN operator interface and a
OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:
Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission
AVTS Advanced Visual Test Software, 3.3
, 3.3 AVTS Powerful, easy-to-use Microsoft Windows 2000/XP/Vista TM compatible Designed to manage all aspects of protective relay testing using the MPRT Relay Test Set Now loaded with more features and
Synchronization Essentials of VoIP WHITE PAPER
Synchronization Essentials of VoIP WHITE PAPER Synchronization Essentials of VoIP Introduction As we accelerate into the New World of VoIP we assume we can leave some of the trappings of wireline telecom
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Laboratory 4: Feedback and Compensation
Laboratory 4: Feedback and Compensation To be performed during Week 9 (Oct. 20-24) and Week 10 (Oct. 27-31) Due Week 11 (Nov. 3-7) 1 Pre-Lab This Pre-Lab should be completed before attending your regular
Computer Controlled Generating Stations Control and Regulation Simulator, with SCADA SCE
Technical Teaching Equipment Computer Controlled Generating Stations Control and Regulation Simulator, with SCADA SCE EDIBON SCADA System Teaching Technique used 4 5 2 Data Acquisition Board Cables and
Market Growth and New Regulations Demand Network Modernization
CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to
Enterprise Energy Management with JouleX and Cisco EnergyWise
Enterprise Energy Management with JouleX and Cisco EnergyWise Introduction Corporate sustainability and enterprise energy management are pressing initiatives for organizations dealing with rising energy
Implementation of Wi-Ap; An IEEE 802.11b/g Based Electrical Switch Module With Web Enabled Interface for Electrical Appliances Control
Research Journal of Applied Sciences, Engineering and Technology 3(12): 1335-1341, 2011 ISSN:2040-7467 Maxwell Scientific Organization, 2011 Submitted: February 20, 2011 Accepted: March 26, 2011 Published:
2.8. EM24 DIN Energy Analyser
2.8. EM24 DIN Energy Analyser 2.8.1. Multiplexer (transmission of counter values) with EM24 Function: Control and transfer of counter values Application: Registration of energy and operating hours etc.
Challenges and Opportunities for Aligning the Power System Cybersecurity and Reliability Objectives
Challenges and Opportunities for Aligning the Power System Cybersecurity and Reliability Objectives for Mexico, US and Canada Ameen H. Hamdon SUBNET Solutions Inc. [email protected] +1 403 270 8885 Cuernavaca,
Achieving PSTN Voice Quality in VoIP
Achieving PSTN Voice Quality in VoIP Voice over Internet Protocol (VoIP) is being widely deployed to offer users low-cost alternatives for long-distance and international telephone calls. However, for
APPENDIX 8 TO SCHEDULE 3.3
APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 8 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE
ECE 586b Course Project Report. Auto-Reclosing
ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1
Wireless power meter monitoring with power theft detection and intimation system using GSM and Zigbee networks
IOSR Journal of Electronics and Communication Engineering (IOSR-JECE) e-issn: 2278-2834,p- ISSN: 2278-8735.Volume 9, Issue 6, Ver. I (Nov - Dec. 2014), PP 04-08 Wireless power meter monitoring with power
DRTS 33. The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters
The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters Testing all relay technologies: electromechanical, solid state, numerical and IEC61850 Manual
Team Members: Adam Wroblaski Jared Kline Mark Reisinger Yu Chan. Advisor: Dr. Chen-Ching Liu Client: General Electric
Team Members: Adam Wroblaski Jared Kline Mark Reisinger Yu Chan Advisor: Dr. Chen-Ching Liu Client: General Electric April 25, 2007 Overview of Presentation Acknowledgements Definitions Introduction Project
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...
Config software for D2 systems USER S MANUAL
DT-CONFIG SOFTWARE Config software for D2 systems USER S MANUAL CONTENTS 1. Introductions ------------------------------------------------------------------- 3 2. System Requirement and Connection ----------------------------------------
Common Base BJT Amplifier Common Collector BJT Amplifier
Common Base BJT Amplifier Common Collector BJT Amplifier Common Collector (Emitter Follower) Configuration Common Base Configuration Small Signal Analysis Design Example Amplifier Input and Output Impedances
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER Responsible for performing entry level engineering analysis, design, plan, review and inspection for small to medium projects and/or designated segments of
Lab 3: Introduction to Data Acquisition Cards
Lab 3: Introduction to Data Acquisition Cards INTRODUCTION: In this lab, you will be building a VI to display the input measured on a channel. However, within your own VI you will use LabVIEW supplied
APPLICATION NOTE 183 RFC 2544: HOW IT HELPS QUALIFY A CARRIER ETHERNET NETWORK. www.exfo.com Telecom Test and Measurement. What is RFC 2544?
RFC 2544: HOW IT HELPS QUALIFY A CARRIER ETHERNET NETWORK Bruno Giguère, Member of Technical Staff, Transport and Datacom Business Unit Service providers worldwide are actively turning up new services
Automation System TROVIS 6400 TROVIS 6493 Compact Controller
Automation System TROVIS 6400 TROVIS 6493 Compact Controller For panel mounting (front frame 48 x 96 mm/1.89 x 3.78 inch) Application Digital controller to automate industrial and process plants for general
NELSON VOLTAGE MONITOR INSTALLATION & PROGRAMMING MANUAL
NELSON VOLTAGE MONITOR INSTALLATION & PROGRAMMING MANUAL CONTENTS GENERAL INFORMATION...3 INSTALLATION...3 FIELD WIRING...4 PROGRAMMING...4 Circuit Monitor Options...5 Power Frequency...5 Alarm Silence
Scope of Restoration Plan
RWG Area Restoration Review Worksheet (10/28/09) EOP-006-02 Directory 8 EOP-005 NYSRG Rule G Text Restoration Plan Requirement R1.Each Reliability Coordinator shall have a Reliability Coordinator Area
Automatic ASAM MCD-3 supported test. PikeTec GmbH Dr. Jens Lüdemann
Automatic ASAM MCD-3 supported test PikeTec GmbH Dr. Jens Lüdemann Test challenges Clear test case description (Modeling) Continuity and consistency at all test platforms Automated Execution, Assessment,
LOCAL INTERCONNECT NETWORK (LIN)
54B-1 GROUP 54B LOCAL INTERCONNECT NETWORK (LIN) CONTENTS GENERAL INFORMATION........ 54B-2............ 54B-3 STRUCTURE................... 54B-2 54B-2 LIN refers to "Local Interconnect Network," which
EnerVista TM Viewpoint Monitoring v7.10
EnerVista TM Viewpoint Monitoring v7.10 Guideform Specifications July 7, 2014 Page 1 of 14 1 - Product Overview 1.1 Viewpoint Monitoring Scope EnerVista Viewpoint Monitoring is an easy to setup, powerful
Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach
Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, [email protected], Armando Altamirano, [email protected] Osama A. Mohammed, [email protected] Energy Systems
SenseLink TM. End-Point Controller. Addendum
SenseLink TM End-Point Controller Addendum MKS Instruments, Inc. Control & Information Technology Products Group 3350 Scott Blvd Bldg 4 Santa Clara, CA 95054 Main: 408.235.7620 Fax: 408.235.7625 SenseLink
LAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University
LAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to
APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution
APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic
An Automated Model Based Design Flow for the Design of Robust FlexRay Networks
SAE TECHNICAL PAPER SERIES 2008-01-1031 An Automated Model Based Design Flow for the Design of Robust FlexRay Networks Thorsten Gerke Synopsys GmbH David Bollati C&S Group/University of Applied Science
THEME Competence Matrix - Electrical Engineering/Electronics with Partial competences/ Learning outcomes
COMPETENCE AREAS STEPS OF COMPETENCE DEVELOPMENT 1. Preparing, planning, mounting and installing electrical for buildings and industrial applications He/She is able to prepare and carry out simple electrical
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
APPLICATION NOTE # Using Sage SMOS for VoIP Testing, IP Phone to IP Phone TABLE OF CONTENTS
Product: 930A L3 Communications Test Set 935AT Communications Test Set APPLICATION NOTE # Using Sage SMOS for VoIP Testing, IP Phone to IP Phone TABLE OF CONTENTS Introduction... 2 Configuring 935AT #1
EnerVista Viewpoint Monitoring
EnerVista Viewpoint Monitoring Easy to Use Monitoring and Data Recording EnerVista Viewpoint Monitoring is an easy to setup, powerful and simple to use data monitoring and recording software application
DSL Forum Technical Report TR-054
DSL Forum Technical Report TR-054 (Formerly WT-074v1) Updates and supercedes TR-038 DSL Service Flow-Through Fulfillment Management Overview Abstract: August 2002 This Working Text defines the first set
Data Center Commissioning: What you need to know
Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,
SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications. Contents
SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications Contents 1. Objective... 2 2. Background... 2 3. Responsibilities... 3 4. Controls... 4 5. Instructions... 5 5.1 Document Operations
SCADA System Overview
Introduction SCADA systems are critical to the control and monitoring of complex cyber-physical systems. Now with advanced computer and communications technologies, SCADA systems are connected to networks
The ISP Column A monthly column on all things Internet
The ISP Column A monthly column on all things Internet Just How Good are You? Measuring Network Performance February 2003 Geoff Huston If you are involved in the operation of an IP network, a question
Service Desk Best Practices
Service Desk Best Practices As an IT service provider, you understand that information can provide a powerful strategic advantage. In order to ensure the proper mechanisms are in place for information
Emulated Digital Control System Validation in Nuclear Power Plant Training Simulators
Digital Control System Validation in Nuclear Power Training s Gregory W. Silvaggio Westinghouse Electric Company LLC [email protected] Keywords: Validation, nuclear, digital control systems Abstract
Release Management: Effective practices for IT delivery
Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve
Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
The Danwood Group Professional Services Offering DANWOOD
The Danwood Group Professional Services Offering DANWOOD Our Professional Services Our Professional Services department can provide you with a variety of services from Audit and Assessment to Technical
FREJA Win Software for FREJA relay testing system
Software for FREJA relay testing system A Megger Group Company Software for FREJA relay testing system In FREJA Win, the all-round General instrument program serves as a convenient, easy to understand,
ARA Digital Train Radio System Functional Requirements For Australian Metropolitan Railway Operators. 19 September 2005
ARA Digital Train Radio System Functional Requirements For Australian Metropolitan Railway Operators 19 September 2005 1. General 1.1 General 1.1.1 Scope and Standard The Australian Metropolitan Railway
REAL-TIME POWER SYSTEM SIMULATOR TRAINING PROGRAM
USAID ENERGY POLICY PROGRAM POST-TRAINING EVALUATION REAL-TIME POWER SYSTEM SIMULATOR TRAINING PROGRAM OCTOBER 5-29, 2015 November 2015 This program is made possible by the support of the American people
Line Monitoring and Control in Subsea Networks
Line Monitoring and Control in Subsea Networks This paper discusses how submerged equipment is monitored and contrasts different methods of doing this. It also considers what features are required by the
Process Guide. Release Management. Service Improvement Program (SIP)
Process Guide Release Service Improvement Program (SIP) i Table of Contents Process Guide Release Document Information... 3 Approval... 4 Section 1: Process Vision... 6 Overview... 6 Process Mission and
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Synchro-Phasor Data Conditioning and Validation Project Phase 3, Task 1. Report on
Synchro-Phasor Data Conditioning and Validation Project Phase 3, Task 1 Report on Lessons Learned in the DV&C Project Prepared for the Office of Electricity Delivery and Energy Reliability, Transmission
Overview of the Telecommunications Network
1 Overview of the Telecommunications Network 15 Telecommunication Networks 2 Basic purpose of a telecommunications network: transmit user information in any form to another user of the network. Many forms
Cisco Application Networking for IBM WebSphere
Cisco Application Networking for IBM WebSphere Faster Downloads and Site Navigation, Less Bandwidth and Server Processing, and Greater Availability for Global Deployments What You Will Learn To address
Wide Area Monitoring Current Continental Europe TSOs Applications Overview
Wide Area Monitoring Current Continental Europe TSOs Applications Overview Version 5 System Protection & Dynamics Working Group 20th September 2015 1. Content 1. Content... 2 2. Introduction... 3 3. Main
SIRFN Capability Summary National Renewable Energy Laboratory, Golden, CO, USA
SIRFN Capability Summary National Renewable Energy Laboratory, Golden, CO, USA Introduction The National Renewable Energy Laboratory (NREL) is the U.S. Department of Energy s primary national laboratory