Level 2 Energy Audit. NRSBU Bell Island Wastewater Treatment Plant. Engineering Advisor Nelson Regional Sewerage Business Unit (NRSBU)
|
|
- Job Clyde Lewis
- 8 years ago
- Views:
Transcription
1 Level 2 Energy Audit NRSBU Bell Island Wastewater Treatment Plant Performed for: Johan Thiart Engineering Advisor Nelson Regional Sewerage Business Unit (NRSBU) June 212
2 CONTENTS EXECUTIVE SUMMARY INTRODUCTION BACKGROUND PURPOSE OF ENERGY AUDIT ENERGY REVIEW PERIOD HISTORIC ENERGY USE HISTORIC ELECTRICITY USE ELECTRICITY USE CONSUMPTION PROFILES ELECTRICITY SPLIT TARIFF REVIEW ELECTRICITY PROCESS DESCRIPTION PRELIMINARY TREATMENT PRIMARY TREATMENT SECONDARY TREATMENT SOLIDS TREATMENT AUXILIARY PROCESSES AND EQUIPMENT ENERGY MANAGEMENT OPPORTUNITIES ELECTRICITY SUPPLY MAIN PROCESSES HEATING, VENTILATION AND AIR CONDITIONING (HVAC) LIGHTING MISCELLANEOUS EQUIPMENT APPENDIX A SITE MAP WITH MAIN PROCESS LOCATIONS APPENDIX B TYPICAL ELECTRICITY BILL APPENDIX C ELECTRICITY METERS APPENDIX D POWER FACTOR READINGS APPENDIX E QUOTES APPENDIX F TECHNICAL RESOURCES NRSBU BISTP Level 2 Energy Audit
3 EXECUTIVE SUMMARY An energy audit at the Nelson Regional Sewerage Business Unit (NRSBU) Bell Island Sewerage Treatment Plant (BISTP) was conducted by Enercon for the following reasons: To find methods to improve energy efficiency; o An energy audit had never been performed on the site since its inception in 1982 To develop an energy balance of the entire plant; To analyse the optimal performance of the overall waste water treatment process on site. Overall, the plant is operating very energy efficiently, with many energy conserving features and practices already in place. Site staff have a proactive and knowledgeable approach towards energy management, which is encouraging when considering long term efficiency. The Bell Island Sewerage Treatment Plant is administered by NRSBU, and is operated by a contractor, CPG. Reduce Energy Consumption The Bell Island Sewerage Treatment Plant has an annual energy spend of approximately $535, based on the year ending March 212. The site was found to be highly energy efficient in regards to the operation of existing processes, and would fit in the top 1% of Energy audits we have done for operating efficiency. Examples of this efficiency are: Variable speed drives are installed as and where appropriate; Site equipment is regularly maintained and reviewed, including the cost and payback period of more efficient approaches; Power factor is universally high, ensuring no supplied power is wasted through poor distribution; Operational issues are quickly dealt with, resulting in little equipment left operating to compensate for the issues; Process equipment is easily controlled and monitored from the SCADA system in the main office; Staff are knowledgeable about what each water treatment process is trying to achieve and what needs to be operating as a result; Air conditioning use is kept to a minimum; Lighting is sparingly used and relates closely to occupancy (e.g. there were almost no lights on overnight when staff had left the island). NRSBU BISTP Level 2 Energy Audit 1
4 Electricity is not currently generated on site. A number of Energy Management Opportunities (EMOs) have been identified that, when implemented, will decrease the electricity consumed (and therefore the cost). Table.2 summarises the energy consumption and the savings that can be made. Note that average energy prices from February 211 to January 212 have been used. Table.2: Summary of Annual Energy Usage for Bell Island Sewerage Treatment Plant Electricity (kwh e ) Electricity Generated (kwh e ) Electricity Imported (kwh e ) Total Cost ($) Cost Savings ($) Cost Savings (%) Current 3,824,1 3,824,1 $534,9 - - If T1 met 3,682,1 3,682,1 $512,4 $22,5 4.2% If T1 & T2 met 3,68,3 3,68,3 $512,2 $22,7 4.2% Table.3 provides benchmark figures for the energy consumption of the plant. The total electricity consumption can be expressed with index values of.71kwh e /m³ of wastewater and 9.8 /m³ of wastewater, or 9,161 kwh e /tonne ($1,281/tonne) of biochemical oxygen demand (BOD) removal. Table.3: Summary of Benchmark Energy Consumption Figures Annual Wastewater Flow Annual BOD (m³) tonne (kwh e /m³ Wastewater) Consumption Benchmark (kwh e /tonne BOD) Cost Benchmark ( /m³ Wastewater) ($/tonne BOD) Current 5,456, , ,281 If T1 met 5,456, , ,228 If T1 &T2 met 5,456, , ,227 Table.4 compares the energy consumption of the Bell Island Sewerage Treatment Plant to two other wastewater treatment plants in New Zealand (North Shore and Christchurch). Table.4: Summary of Benchmark Energy Consumption Figures BISTP North Shore Christchurch (kwh e /m³) ( /m³) (kwh e /m³) ( /m³) (kwh e /m³) ( /m³) Current As can be seen in Table.4, the Bell Island Sewerage Treatment Plant is more energy intensive than the North Shore and Christchurch wastewater treatment plants. North Shore and Christchurch wastewater treatment plants both use anaerobic digesters, while the Bell Island Sewerage Treatment Plant uses aerobic digesters. The Bell Island Sewerage Treatment Plant has the potential to be a net exporter of energy (as is the case at the Christchurch wastewater treatment plant), were it to convert from aerobic to anaerobic digesters. This measure is discussed further in EMO 2.1 of this report, which states 4,4, kwh/year could potentially be generated / NRSBU BISTP Level 2 Energy Audit 2
5 saved using anaerobic digesters, compared to the 3,824,1 kwh/year used over the 12 month historical period analysed. Significant energy saving opportunities with short paybacks can be found by: Having CPG pay for energy accounts as part of their performance contract Replacing the flow meter for gravity fed outflow Removing the time-of-use metering at the dewatering plant Possible longer term investments include: Anaerobic Digesters Gravity Belt Thickener (GBT) use instead of Dissolved Air Floatation unit (DAF) use This audit needs to be seen as the first step to reducing and managing energy costs. The next phase is to implement the recommendations from this report. Thereafter, ongoing energy management will be needed to ensure energy savings are realised into the future. Energy management will also ensure operating and maintenance issues are identified early and assist in improving the energy awareness of employees. Energy audits should be conducted at sites every 3 5 years to achieve good energy management. Continual energy management will ensure operating and maintenance issues are identified early, new technologies are utilised as they become available and cost efficient, and assist in improving the energy awareness of staff. A summary of the Energy Management Opportunities (EMOs) recommended is shown in Tables.5,.6 and.7. Note that the capital costs are budget figures only. A full description of each of these EMOs is given in Section 5. EMO Designation: The decimal number labels each EMO in a sequence. The first number is coded: 1 Electricity Supply 2 Main Processes 3 Lighting 4 HVAC 5 Office Equipment Note that some EMOs are further separated into the following: a b c Paybacks less than 1 year Paybacks between 1 and 5 years Paybacks over 5 years NRSBU BISTP Level 2 Energy Audit 3
6 Table.5: T1 EMOs (payback less than one year) EMO Action Capital Cost Annual savings Simple Payback Include energy account payments in the performance contract for CPG Remove the non-half-hourly metering at the dewatering plant Negotiable $~21, N/A $5 $2,7.2 years 2.2 Replace the flow meter for gravity fed outfall $6, $19,5.3 years 2.4 Optimise O 2 levels in Aeration Basin Management Needs further investigation Needs further investigation Place the Aeration Basin Distribution-Board Room fan on a thermostat Use one freezer instead of two in the room next to the tea room $15 $25.6 years $ $8 Immediate Total T1 (Note: exc. EMO 1.1) $6,7+ $22,5+.3 years Table.6: T2 EMOs (payback between one and five years) EMO Action Capital Cost Annual savings Simple Payback 4.1 Switch outside lighting off during the day $29 $ years 4.2 Occupancy sense freezer room lights $15 $7 2.2 years Total T2 $44 $ years Total T1 + T2 $7,1+ $22,7+.3 years Table.7: T3 EMOs (payback over five years) EMO Action Capital Cost Annual savings Simple Payback 1.3 Investigate metering requirements for the ponds Needs Further Investigation $1,75 - $3,5 Needs Further Investigation 2.1 Use anaerobic digesters instead of aerobic digesters $7,2, $4, 18 years 2.3 Investigate using the Gravity Belt Thickener instead of the Dissolved Air Floatation unit for secondary sludge thickening Needs Further Investigation $~$7, Needs Further Investigation Note: All costs in this report exclude GST. NRSBU BISTP Level 2 Energy Audit 4
7 1 INTRODUCTION 1.1 Background Occupying 53ha of Bell Island on the Waimea Inlet, the Bell Island Sewerage Treatment Plant (BISTP) serves the communities of Nelson South, Richmond and Mapua. The plant was commissioned in 1983, with an original design population of 33, people, and the plant consisted of a fully mixed aeration basin, three facultative oxidation ponds (in parallel), two maturation ponds (in series) and a tidal discharge. As of 27, the plant had a design population of 133, people. Bell Island Sewerage Treatment Plant processes approximately 5.5 million cubic meters of wastewater per year. The plant provides primary and secondary treatment. Two-thirds of this flow originates from residential sources; the remaining one-third comes from commercial and industrial producers. However, the industrial users produce two-thirds of the biochemical oxygen demand (BOD). Peak flows and loads are highly variable due to the combined effects of storm water filtration and the seasonal nature of industrial food processing activities. Treated effluent is discharged into the inlet on the outgoing tide. Stabilised sludge (bio-solids) is beneficially applied to forests on Rabbit Island. The treatment plant consists of an aeration basin, clarifier, Dissolved Air Flotation unit (DAF) and an Autothermal Thermophilic Aerobic Digestion (ATAD) plant that treats captured solids to produce bio-solids. A system of pumps and pipework transfers bio-solids to Rabbit Island. The oxidation pond system at Bell Island Sewerage Treatment Plant consists of three facultative ponds in parallel and two maturation ponds in series. Effluent from the last maturation pond is discharged into the Waimea Inlet via an outfall pipeline and diffusers. To manage increasing flows and tightening environmental requirements, a number of process upgrades have been made since the plant s construction. Following a review in 1992 the following were installed: Desludging of the oxidation ponds was undertaken from due to the overloading (and subsequent malodour generation) of these ponds caused by stratification and organic load build up in excess of treatment capacity. Mechanical aeration mixing (completed 1996) Clarifier and Autothermal Thermophilic Aerobic Digestion (completed 1996). This phase of the project was implemented to reduce the loadings entering the oxidation ponds, thus reducing odour nuisance from the plant. From 23-25, a retrofit of the plant took place that included installation of the Dissolved Air Flotation unit. More recently, a Gravity Belt Thickener (GBT) has been installed on site. This was used for 2 months, before it was decided the system was not required at that stage. As of 27, the following developments were being considered in future planning. Anaerobic digestion is explored in this report. NRSBU BISTP Level 2 Energy Audit 5
8 27/8 Inlet load reduction (primary clarifier) 28/9 Outfall capacity upgrade 21/11 Expand bio-solids treatment facilities 213/15 Anaerobic Digestion and Co-generation 215/16 Nitrogen / phosphorous Removal 215/16 Pond De-sludging A 15 year review of all site equipment is typical, although exceptions could be made for systems that are proven to be more energy efficient or more productive. A full process description can be found in Section 4. Bell Island Sewerage Treatment Plant has the following operating hours: Operation Days/week Hours/day Comments Process Control Room BMS remotely accessible Offices Mon Fri employees 1.2 Purpose of Energy Audit The Nelson Regional Sewerage Business Unit decided to have an energy audit performed at the Bell Island Sewerage Treatment Plant for the following reasons: To find methods to improve energy efficiency To develop an energy balance of the entire plant To analyse the optimal performance of the overall waste water treatment process on site. 1.3 Energy Review Period The energy review was performed with two day-time site visits. An evening inspection was performed as well. Energy figures throughout the report are based on energy data from February 211 to January 212 (unless otherwise specified). NRSBU BISTP Level 2 Energy Audit 6
9 2 HISTORIC ENERGY USE 2.1 Historic Electricity Use Table 2.1 shows a summary of the net electricity consumption and cost for the year ending March 212 for the entire Bell Island Wastewater Treatment Plant. The Net Energy Cost represents the total marginal charge for each kwh whereas the total electricity cost includes fixed costs such as line charges. Please note: Historical cost figures are based on Meridian charges prior to the switch to Trustpower in February 212. Energy savings calculations use projected Trustpower TOU rates from June 212 to May 213. Table 2.1: Electricity Consumption (April 211 March 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 3,824,1 $482,3 $534,9 Table 2.2a shows a summary of the electricity consumption for meter 48125NTFE5 (Aeration Basin, Dissolved Air Floatation Unit, Return Activated Sludge, Waste Activated Sludge) for the year ending March 212. This meter accounts for 63% of the entire plant energy use. Table 2.2a: Electricity Consumption for Meter 48125NTFE5 (Feb 211 Jan 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 2,419,8 $295,4 $334,3 Table 2.2b shows a summary of the electricity consumption for meter 597NT746 (Digesters, Secondary Clarifier, Workshop, Sludge Tanks / Pumps). This meter accounts for 32% of the entire plant energy use. Table 2.2b: Electricity Consumption for Meter 597NT746 (Feb 211 Jan 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 1,238,9 $154,8 $166,8 Table 2.2c shows a summary of the electricity consumption for meter 32543NT962 (Inlet, Screens, Outfall, Wash-water etc.). This meter accounts for 3% of the entire plant energy use. Note: Net energy cost is higher than total electricity cost for this meter as large fixed cost refunds occurred during the year analysed. Table 2.2c: Electricity Consumption for meter 32543NT962 (Feb 211 Jan 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 12,8 $22, $21,2 Table 2.2d shows a summary of the electricity consumption for meter (Pond Aerators, Farmers Water). This meter was not analysed in detail as it covers a large area with comparatively small energy use (1% of total BISTP use). NRSBU BISTP Level 2 Energy Audit 7
10 Table 2.2d: Electricity Consumption for meter (Feb 211 Jan 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 42,6 $9,2 $9,6 The Bell Island Wastewater Treatment Plant also has a small meter (592NT-B86) for the Dewatering Plant and Electrician s Workshop, but as Table 2.2e shows, this only consumes around 1,8 kwh/year. The meter costs Bell Island Wastewater Treatment Plant $2,9, of which only $4 is for energy that only keeps this filter on standby. It is recommended this meter be removed. Table 2.2e: Electricity Consumption for meter (592NT-B86) (Feb 211 Jan 212) Electricity Consumption (kwh e ) Net Energy Cost TOTAL Electricity Cost 1,8 $4 $2,9 2.2 Electricity Use Consumption Profiles Figure 2.1 compares the monthly electricity consumption for the main site to the amount of wastewater treated for January 211 March 212. The amount of electricity consumption has a very weak relationship to the throughput of wastewater with much of the equipment operating at a set load throughout the year. As expected, the electricity consumption profile is relatively flat throughout the year. However, the discharge rate varies by as much as 4% (e.g. between February and June 211) due to changes in weather conditions, while the corresponding electricity use variation is only around 3%. Note that the inflows become high with heavy rains due to storm water entering the waste water catchment area. The energy use per m 3 of water also varies greatly. The energy use per unit of discharged treated water was particularly high for February April , Electricity use and water discharge 1.8 Energy use / m3 of water 7, 1.6 Monthly m3 / Monthly kwh 6, 5, 4, 3, 2, kwh/ m ,.2. Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Average Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Average Discharge (m3) Electricity Use (kwh) Discharge Inflow Figure Electricity Consumption and Wastewater Flow Figure 2.2 reinforces the findings of Figure 2.1. The electricity consumption and generation have relatively flat profiles and do not vary significantly with wastewater flow. Only 26% of the variation in electricity consumption can be NRSBU BISTP Level 2 Energy Audit 8
11 attributed to changes in treated water discharge (as indicated by an R² value of 26%). Only 9% of the variation in electricity consumption is related to changes in wastewater inflow. Discharge (m3) vs. Energy use (kwh) Inflow (m3) vs. Energy use (kwh) 4, 35, y =.672x R² = , 35, y =.4x R² =.861 3, 3, 25, 25, kwh 2, 2, 15, 15, 1, 1, 5, 5, 1, 2, 3, 4, 5, 6, 7, 8, 1, 2, 3, 4, 5, 6, 7, kwh 8, 9, Water discharge (m3) Water discharge (m3) Figure Electricity Consumption vs. Wastewater Flow Biochemical oxygen demand (BOD) has only been logged at Bell Island Wastewater Treatment Plant since September 211. BOD is the amount of dissolved oxygen needed by aerobic biological organisms in a body of water to break down organic material present in a given water sample at certain temperature over a specific time period. BOD is sometimes used as a gauge of the effectiveness of wastewater treatment plants. For Bell Island Sewerage Treatment Plant, 2/3 of BOD (though 1/3 of flow) is from industry. Figure 2.3 compares electricity use against BOD. Monthly Energy Use vs. Monthly Inlet BOD Daily Energy Use vs. Daily Inlet BOD 3, 16, Energy Use (kwh/month) 25, 2, 15, 1, y =.1156x R² =.7 Energy Use (kwh/day) 14, 12, 1, 8, 6, 4, y = -.342x R² =.369 5, 2, 1, 2, 3, 4, 5, 6, Inlet BOD (kg/month) 2, 4, 6, 8, 1, 12, 14, 16, Inlet BOD (kg/day) Figure Electricity Consumption vs. Biochemical Oxygen Demand (BOD) The data above highlights unexpected relationships between BOD and energy use for Bell Island Wastewater Treatment Plant. It is expected that the higher the BOD is, the higher the energy use is. However, only 4% of the daily variation in electricity consumption can be attributed to changes in BOD (as indicated by an R² value of 4%). The daily recordings are sporadic (i.e. are not recorded every day of the week). This would help to establish the relationship between BOD and energy use more accurately. The establishment of a benchmark for which to compare wastewater treatment productivity to energy use requires further investigation. NRSBU BISTP Level 2 Energy Audit 9
12 Figure 2.4 shows the hourly load and load duration curve for each time-of-use meter for the historical energy use period (February 211 January 212). The load for the Aeration Basin etc. meter is inconsistent but one-off peak loads are rare. The kva load duration pattern sees two sharp increases in kva with no corresponding changes to kw readings. This is likely to be due to one or two large items of equipment. The load for the Autothermal Thermophilic Aerobic Digesters (ATAD) etc. follows a seasonal pattern and a smooth load duration curve with the exception of the highest few loads. The Inlet, Outfall etc. meter had a poor power factor before June 211 and peak load reductions have resulted since its improvement. The peaks well above normal operation are likely to be the result of wet weather. Aeration Basin etc.: Load Aeration Basin etc.: Load Duration kva/kw kva/kw Feb 11 Mar 11 Apr 11 May 11 Jun 11 Jul 11 Aug 11 Sep 11 Percentile kw kva Oct 11 Nov 11 Dec 11 Jan Percentile kw kva ATAD Plant etc.: Load ATAD Plant etc.: Load Duration kva/kw kva/kw Feb 11 Mar 11 Apr 11 May 11 Jun 11 Jul 11 Aug 11 Sep 11 Percentile kw kva Oct 11 Nov 11 Dec 11 Jan Percentile kw kva Inlet, Outfall etc.: Load Inlet, Outfall etc.: Load Duration kva/kw kva/kw Feb 11 Mar 11 Apr 11 May 11 Jun 11 Jul 11 Aug 11 Sep 11 Percentile kw kva Oct 11 Nov 11 Dec 11 Jan Percentile kw kva Figure Load Duration Curve NRSBU BISTP Level 2 Energy Audit 1
13 2.3 Electricity Split Figure 2.5 shows the electric energy split for the entire process area. Energy splits provide the basis for audit calculations and are used to identify areas with high energy consumption and methods to reduce this. The electricity splits shown below have been estimated from data recorded during the site visits and from the motor list data provided. The processes which consume the most electricity are aeration (58%) and the Autothermal Thermophilic Aerobic Digestion plant (ATAD) (26%). Note: ATAD includes pumps and motors associated with each train of digesters. Pumps / motors at either end of the trains are included within sludge tanks / pumps. The review period used for the total electricity consumption and cost is the year ending January 212. Clarifiers.9% Ponds & Farmers Water 1.8% RAS/WAS DAF 2.% 2.7% Sludge tanks/ pumps 6.3% Preliminary Outfall.8%.6% Washwater.4% Other.7% ATAD 26.5% Aeration 57.7% Figure Electric Energy Split Figure 2.6 shows the annual cost split for the entire process area. DAF 2.7% RAS/WAS 1.9% Clarifiers 1.1% Ponds & Farmers Water 1.8% Sludge tanks/ pumps 6.3% Preliminary 1.% Outfall.7% Washwater.5% Other 1.2% ATAD 25.3% Aeration 56.8% Figure Electricity Cost Split NRSBU BISTP Level 2 Energy Audit 11
14 3 TARIFF REVIEW 3.1 Electricity Meridian Energy supplied electricity to Bell Island Wastewater Treatment Plant through multiple 11kV feeders via Network Tasman during the 12 months of energy data analysed (February 211 January 212). Copies of typical electricity bills for each tariff are shown in Appendix B. Bells Island Wastewater Treatment Plant has 3 time-of-use meters. These are: 48125NTFE5 (Aeration Basin, Dissolved Air Floatation, Return Activated Sludge, Waste Activated Sludge) 32543NT962 (Inlet, Screens, Outfall, Wash Water) 597NT746 (Autothermal Thermophilic Aerobic Digestion plant, (ATAD), Secondary Clarifier, Workshop, Sludge Tanks and Pumps) There is also a small fraction of energy use on non-half-hourly (NHH) metering. 5923NT-B86 (Dewatering Plant and Electrician s Workshop) (Pond Aerators, Farmers Water) Energy Charges For the time-of-use meters, electricity is purchased at a Fixed Price Variable Volume (FPVV) which divides the year into 144 time slots for time of day (4 hour slots), day of week (business days and non-business days) and month of year. Each time slot has a fixed hedge rate based on a number of variables related to the time of year. The average hedged rate for these meters for the year ending January 212 was 9.6 /kwh. (Note: Under the new electricity tariff in effect February 212, the average hedged rate will decrease to 8.7 /kwh for the year ending January 213 and 9.2 /kwh for the year ending January 214). The energy tariff for meters has the following components: Variable Charges: ATAD Plant etc. Aeration basin etc. Inlet, Outfall etc. Hedged Energy Charge 4-17 /kwh 4-17 /kwh 4-17 /kwh Nelson City Council Electricity Authority Charge Fixed Charges:.24 /kwh.24 /kwh.24 /kwh Data Reconciliation / Reading Fee $32 /month $32 /month $32 /month CT Monthly Fee (sewerage plant only) $15 /month TOTAL ENERGY COST $125,9 /year $24,1 /year $1,6 /year For ICP number 5923NT-B86 electricity is purchased on an anytime tariff. Variable Charges: Anytime Rate /kwh TOTAL ENERGY COST $78 /year NRSBU BISTP Level 2 Energy Audit 12
15 For ICP number electricity is purchased on a day/night tariff. Variable Charges: Day Rate (7 am 11 pm) 25.6 /kwh Night Rate (11 pm 7 am) /kwh TOTAL ENERGY COST $9,2 /year The energy prices used for savings calculations are listed below. Time-of-use rates (hedged energy charges), have been reduced compared to those for the analysed historical energy use period (Feb 211 Jan 212) due to Bell Island Sewerage Treatment Plant changing power suppliers from Meridian to Trustpower in February 212. ATAD Plant etc. and Aeration Basin etc. Inlet, Outfall etc. Non-Business Day Business Day Non-Business Day Business Day Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Average The anytime electricity rate for ICP number 5923NT-B86 is assumed to remain at /kwh throughout the year. The rates for ICP number are assumed to remain at 25.6 /kwh (day) and /kwh (night). Network Charges Bell Island Sewerage Treatment Plant has connections through the Network Tasman distribution network. Network Tasman bills Bell Island Sewerage Treatment Plant through the electricity retailer (Meridian Energy until February 212, Trustpower since). The following network charges are applicable to Bell Island Sewerage Treatment Plant. Variable Charges: ATAD Plant etc. Aeration basin etc. Inlet, Outfall etc. Winter RCPD Average Rate $.2272/kVA-day $.2272/kVA-day $.45/kVA-day Variable Distribution Charge /kwh /kwh /kwh Fixed Charges: Anytime Capacity Distribution $8,72 /year $24,18 /year $ /year TOTAL NETWORK COST $41, /year $94,2 /year $1,5 /year NRSBU BISTP Level 2 Energy Audit 13
16 The Winter Regional Coincident Peak Demand (Winter RCPD) Charge is based on the average of the 12 hourly peaks for each billed site co-incident with the highest peak demands experienced by Transpower. The amount charged stays constant on each meter for the year of energy use analysed (April 211 March 212). This equated to $.2272/kVA-day for the ATAD Plant etc. and Aeration Basin etc. and $.45 /kva-day for the Inlet / Outfall etc. The winter peak demand for billed sites is said by Network Tasman to regularly match the peak demand for Transpower due to weather, time of day etc. Therefore, sites that can move their peak demand to atypical times of the day should see a reduction in energy costs. As the load pattern for most of Bell Island Sewerage Treatment Plant is flat, a reduction in installed load should result in peak demand savings. The Anytime Capacity Distribution Charge equates to $.139 /kva-day. During the year April 211 March 212, the capacity considered to be required remained at the following for each of the sites: 172 kva ATAD Plant etc. 477 kva Aeration Basin etc. This capacity charge is billed based on the previous year of data, and is also independent of any site requirements for capacity (e.g. fuse sizes). Therefore, if the demand can be reduced, this charge can be reduced without capital expenditure on-site. For ICP number (Dewatering Plant), the capacity charge is $.52 /kva-day. The required capacity was determined to be 11 kva for the year from April 211 March 212. This charge equates to around 8% of the total annual cost of electricity for this meter. Given the very sparse energy use of this site, reducing this charge is the key to energy savings for this meter. Variable Charges: Capacity Charge $.52 /kva-day TOTAL NETWORK COST $2,465 /year The electricity bills for ICP number were not analysed. It is assumed for this meter there are no network charges and fixed costs are 96.5 /day. It is recommended the names of some meters be changed from those used on the Meridian electricity bills (if not done so already by Trustpower), as these are confusing. Names used by Meridian Energy (and proposed changes in brackets) are below: Sewerage Plant (Aeration Basin and DAF) Aeration Basin (Primary clarifier, inlet and outlet) New Sewerage ATAD Plant, Bell Island (Dewatering and Electrician s Workshop) No change is necessary for the main ATAD Plant meter. NRSBU BISTP Level 2 Energy Audit 14
17 4. PROCESS DESCRIPTION The Bell Island Sewage Treatment Plant (BISTP) processes 15, cubic metres of wastewater each day (on average). Sewage is transported through a network of underground pipes and pumps to BISTP. Pipe diameters increase in size as the water combines from pipe branches and approaches the treatment plant. Considerable infiltration of storm water occurs during heavy rains which can raise the hydraulic load of the plant by up to five times (13, m 3 for a dry day, 5, m 3 for a very wet day and 7, m 3 for a worst-case wet day). Weather conditions have a much greater impact on wastewater volume than the time of day, although there are peaks associated with each. Approximately 67% by volume of the sewage flow is from domestic sources (33% of biochemical oxygen demand (BOD) concentration), with the remaining 33% of flow (67% of BOD) coming from industrial and commercial sources. A site map with locations of major items of equipment is shown in Appendix A. Power ratings witnessed for pumps, motors etc. are included in Appendix C. NRSBU BISTP Level 2 Energy Audit 15
18 4.1 Preliminary Treatment Inflow and Screening: At the time of the site visit, the sewage entered Bell Island Wastewater Treatment Plant through two channels, the main 8 mm diameter plastic / polyurethane pipe from Nelson, and a 3 mm steel / polyurethane pipe from Mapua. There is also a 6 mm concrete pipe, although this is currently leaking. The leak has been found and the pipe will be repaired and used again. The inflow valve for the 6 mm pipe was appropriately closed during viewing due to not being in service. There are 2 screens to remove solid material larger than 3mm from the inlet sewage flow. The primary has a rated capacity of 76 litres / second per screen (2,73 m 3 / hour). The secondary screen is added to the process by means of a trip switch when the inlet sewage flow is above 76 L/second. Weir overflow makes the screen rotate and let water through, while the solids are held. The screened solids then pass through a classifier screw. The non-biodegradable solids are transferred into a skip. Flow meters are used to determine the fractions of total inflow that occur through the main pipes and the Mapua pipe. The classifier screw was seen to be on 24/7. Good practice is to operate this on a 2 minute cycle (for which the screen pump is typically on for around 5 minutes and off for 15 minutes), due to there often being few solids to screen. However, staff operate the classifier screw 24/7 as they had problems with the screw being blocked when operated sporadically. Therefore, changing classifier screw operation is not a savings opportunity. Grit Removal: Grit is removed early in the process to prevent damage to pumps / pipes further along in the process. The screened liquid flows via gravity to a grit arrester, which introduces compressed air to the water which is pumped to a grit classifier. This classifier forces dense (inorganic) matter to travel towards its centre and then discharges it to a skip for removal. The grit arrester is only on occasionally, which suggests it receives a signal to switch on given a level indication. This is good practice. The Fring aerators (at the Aeration Basin and the Autothermal Thermophilic Aerobic Digesters (ATAD)) can lose efficiency due to wear from sludge contents. This places importance on the solids screening and grit stages of the process. Wash water: Wash water pumps provide clean effluent to the grit system 24/7. This typically requires one of three pumps which run on a duty cycle. These pumps operate on a variable speed drive (VSD), which is good practice. There appears to be a submersible pump on the water supply. The load of this pump should be determined. NRSBU BISTP Level 2 Energy Audit 16
19 4.2 Primary Treatment Primary Clarifier The Primary Clarifier removes settle-able solids ( sinkers ) and floatable solids ( floaters ) from the wastewater. Waste water flows from the liquid output of the primary screen to the centre of the Primary Clarifier. Clean effluent flows out of the edge of each clarifier due to gravity and this flow is controlled via small weirs. The wash water pumps take the effluent overflow to the aeration basin (or to the grit system as necessary). Primary sludge is removed by a large scrape arm along the radius of the clarifier and paddles beneath which draw sludge to the centre of the clarifier. The two scrape arm motors are controlled together using a variable speed drive and operate at around 5% of full load. The Primary Clarifier is designed to allow bypass for the regulation of water if flows are very high and therefore energy savings (per m 3 of effulent) can be made by utilising this bypass as often as possible. The Primary Clarifier produces (and hence removes) 6-7% (7 tonne/day) of overall sludge production on site. The other 3-4% is removed in the Aeration Basin/ Secondary Clarifier, while the Nelson North sludge is imported. Aeration Basin: The Aeration Basin is positioned between the Primary and Secondary Clarifiers in the effluent flow sequence. The aeration basin is 5 metres deep and grows bugs for the treatment of solids using oxygen. The aeration basin accounts for 92% of the time-of-use meter 48125NTFE5. Flow through the aeration basin is said to peak 7: 1: and 22: 24: each day. The load profile of this meter is shown in Appendix C. The Aeration Basin contains 6 x 75 kw aerators and 5 x 3 kw aerators (6 kw in total), known as Fring aerators (being manufactured by Fring). A typical aerator is shown in Figure 4.2. Aeration operates 24/7, but due to three aerators being out of commission the facility is currently under-aerated. NRSBU BISTP Level 2 Energy Audit 17
20 Figure 4.2 Typical Aerator The aerators suck air and water through tubes, which is then dispersed through the outer prongs. The aeration load is higher during the day, thus requiring more oxygen. If oxygen is below intended levels, an odour event can result. The Fring aerators are rebuilt annually due to their arduous duty. Different parts of the Fring aerators are replaced at different times, as expensive parts are often retained for longer. This is also most likely due to the need to keep the plant operating at maximum capacity for all but a few hours. The annual schedule of maintenance seems to be a reasonable approach. The oxygen (O 2 ) level of the aeration basin is typically kept between.5 and 1.5 ppm, with an alarm being raised when O 2 is below.1 ppm, as at this level odour becomes a problem. During the site visit, the O 2 concentration was.7 ppm (with one 75 kw motor and two 3 kw motors not working). However, since the facultative ponds were receiving ample sunlight, a significant amount of aeration was being performed at the ponds. The aerators are controlled by dissolved oxygen (DO) levels. The Fring aerators operate with an efficiency of around.9 kg O 2 / kw. A diffused air system produces 1.24 kg O 2 / kw, thus using 27% less power for the same result. However installing diffused air is an expensive undertaking, costing around $3.2 million for the entire site compared to $.8 million for Fring motors. Air diffusion systems are currently not on the Nelson Regional Sewerage Business Unit plan. o Even if the diffused air system were only used at the aeration basin, and the 27% saving extended to demand as well as energy efficiency, the payback would be in the order of 3 years given: NRSBU BISTP Level 2 Energy Audit 18
21 An estimated cost for replacing aerators with diffused air at the aeration basin of $2.2 million. 27% savings on $278,/year (the estimated cost of running the aerators in the aeration basin) Therefore, this measure is not economically feasible while the Fring aerators are in good order. However, if at some stage in the future, the Fring aerators have to be replaced, then replacing those with a diffused air system needs to be re-examined as the payback period will be shorter. The Fring motors are 6-speed and are all attached to variable speed drives (VSDs). 5 aeration basin VSDs were read on site, the results of which are shown in Appendix C1. A 75 kw pump is assumed to use 43 kw on average, and a 3 kw pump is assumed to use 19 kw on average. Trickling filters are an alternative solution to the Aeration Basin for the removal of colloidal and dissolved solids (i.e. not settle-able or floatable). For an aeration basin, the removal of biochemical oxygen demand (BOD) from wastewater varies from 75-9 % depending on the amount of time the water is retained. Correspondingly, a low-rate or standard-rate trickling filter (assumed to apply to Bell Island Sewerage Treatment Plant), should remove from 8-85 % of the applied BOD. Therefore, the two approaches have similar BOD removal capabilities. It is recommended that trickling filters be re-examined if favourable information becomes available regarding improved BOD removal efficiency / reduced effluent duration when using a trickling filter. 4.3 Secondary Treatment Secondary Clarifier: The Secondary Clarifier receives gravity fed sludge /and water from the Aeration Basin. The Secondary Clarifier provides additional solids / liquids separation, using a similar configuration to the Primary Clarifier. After the Secondary Clarifier, the effluent can be transferred to the Facultative Ponds (F1, F2 and F3). Remaining sludge is separated into two streams, return activated sludge (RAS) and waste activated sludge (WAS), as detailed in Section 4.5. Whether liquid is transferred to WAS / RAS or to the ponds depends on the concentration of Mixed Liquor Suspended Solids (MLSS). If MLSS concentration is above 2 ppm (g/m 3 ), the liquid goes to WAS / RAS. If it is less than 2 ppm, the liquid goes to the ponds. On average, the waste activated sludge pumps receive 3-4 ppm solids from the secondary clarifier. Energy use of the Aeration Basin (etc.) time-of-use meter is plotted against MLSS in Figure 4.1. Note: This meter does not include the Secondary Clarifier, but is used in this comparison due to being highly energy intensive. NRSBU BISTP Level 2 Energy Audit 19
22 Daily Energy Use vs. MLSS Monthly Energy Use vs. MLSS 12, 25, 1, 2, Energy Use (kwh/day) 8, 6, 4, y =.726x R² =.199 Energy Use (kwh/month) 15, 1, y = -.781x R² =.4 2, 5, 5, 1, 15, 2, 25, 3, 35, 4, 45, MLSS(kg/day) 5, 1, 15, 2, 25, 3, MLSS(kg/month) Figure 4.1 Energy use vs. Mixed Liquor Suspended Solids (MLSS) Only 2% of the variation in Aeration Basin (etc.) electricity consumption can be attributed to changes in MLSS (as indicated by an R² value of 2%). There is almost no relationship between MLSS and Aeration Basin (etc.) energy use according to available monthly figures. Ponds: After secondary treatment, the treated wastewater is split between three facultative ponds (F1, F2 and F3 - formerly called oxidation ponds). These cover 3 hectares in total and are in parallel. Bacteria and nutrient in the waste promote vigorous growths of algae. During the day, near the surface, the algae generate oxygen by photosynthesis, further stabilising the wastes. The remaining solids settle to the bottom and are treated by anaerobic processes. Each pond has a 4 kw aerator. The water travels from these ponds to the Maturation Ponds (two in series M1 and M5). The status of the Facultative Ponds was read on two occasions during the site visit. Results were: Pond Total Flow Date and time Inflow l/s Dissolved oxygen (DO) concentration F1 8,78,335 15/5/12 11: /5/12 14: F2 7,46,24 15/5/12 11: /5/12 14: F3 1,136,5 15/5/12 11: /5/12 14: The ponds vary in DO concentration due to differing types of algae present, with F2 having significantly higher DO concentration than F1 or F3. Daylight savings settings on the SCADA system appeared to have been left on for the winter season with respect to the oxidation pond controls. This should be checked. Maturation Ponds: The two 1ha Maturation Ponds (in series) complete the stabilisation process and reduce bacteria numbers. They also provide storage capacity for intermittent release of the effluent. NRSBU BISTP Level 2 Energy Audit 2
23 Discharge: After an average retention time of 5-6 days (since primary inflow), the treated wastewater is discharged from the Maturation Ponds through a gravity driven outfall, into the Waimea Inlet. The treated effluent is typically discharged from high tide until 3 hours after high tide, so as to be taken out with the tide. For the most part the effluent discharge is gravity fed, although a discharge pump has been installed to increase the discharge capacity. The discharge pump is designed to operate during bouts of heavy rain as this is the driver for increased effluent throughput. During the audit process, the discharge pump was adjusted so that it only operates during high discharge flow (caused by high rainfall), with gravity-fed discharge flow becoming the default discharge strategy. Energy savings from this measure are discussed in EMO 2.1. The final effluent quality standards for discharge are shown in Table 4.2. The biochemical oxygen demand (BOD) and suspended solids standards are not as stringent as at North Shore Wastewater Treatment Plant (as an example). Table 4.2: Designed final effluent quality standards Pollution type Outlet Concentration (g/m 3 ) BISTP, Nelson North Shore BOD 5 <4 <1 Suspended Solids <1 <15 Total nitrogen 1-2 Ammonia & Ammonium <2 Pollution type Outlet Concentration (kg/day) Total nitrogen 5 Phosphorus 15 Oysters are known to collect on the discharge diffuser, although this area was not witnessed on site. Currently the approach is to clean the oysters off the discharge diffusers; however there may be ways to do this using ultrasonic technology. For example, boat hulls can be kept free of barnacles by using an ultrasonic device, thus improving the fuel efficiency the boat. Automating discharge diffuser cleaning would save maintenance costs rather than energy costs. 4.4 Solids Treatment Figure 4.3 shows the sludge throughflow for the three main components of digester sludge ever since all three were recorded on a day-to-day basis. Primary sludge accounts for just over 5% of the total sludge sent to the digesters (~63% of on-site sludge); Dissolved Air Flotation (DAF) sludge accounts for just over 3% (~37% of on-site sludge); Nelson North sludge accounts for just under 2% of the digester sludge. NRSBU BISTP Level 2 Energy Audit 21
24 6, 5, 4, 3, 2, 1, 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr m3 Sludge 16-Apr 23-Apr 3-Apr 7-May 14-May 21-May FT638 (Primary Sludge) FT531 (DAF) FT511 (North Nelson) Figure Sludge Flow Meter Volume: 12 March May 212 Primary Sludge The sludge that settles and is removed within the primary clarifiers is called primary sludge. Sludge from the base of the clarifier is pumped to the digesters. The means of measuring sludge concentration at various stages of the process is desired but has not been planned or implemented yet. Primary sludge is currently pumped directly to the sludge storage tank (T22), although there is functionality on the SCADA (Supervisory Control and Data Acquisition) system to send primary sludge to the Gravity Belt Thickener or the Dissolved Air Floatation unit, or to turn the sludge pumping off. The primary clarifier sludge pumps (P618 and P624) operate when there is enough sludge. These pumps run most efficiently at higher speeds; therefore they are on a timed sequencer with one operating on duty and one standby. They can become worn down if the initial grit system lets grit through. This reduces their efficiency. Low density organic matter such as fats (referred to as scum ) float to the surface of the Primary Clarifier. These are scraped away to a scum tank, where they are pumped downwards so as to exit the clarifier at the same point as the settleable solids. Dissolved Air Floatation (DAF) unit In 25, the Dissolved Air Floatation (DAF) process was added as a gravity separation system that uses air bubbles in the wastewater holding tank to help float insoluble materials to the surface so they can be removed. The separation process is aided by dosing the effluent with polyelectrolytes. The polyelectrolytes are introduced to the process early for maximum contact / binding time (1 kg/m 3 of solids). The resulting flocculants cause these materials to join together in clusters that are lighter than water and therefore float. Based on site observations, the DAF is assumed to operate for 5 days a week, 24 hours a day on average, though this can vary from 3 days a week to 24/7, depending on other treatment plant loads. NRSBU BISTP Level 2 Energy Audit 22
25 Part of the clean effluent out of the Dissolved Air Floatation (DAF) unit is pressurised by two 15 kw pumps on VSDs, operating at about 5 kw each, and pumped into the compression tank. An air compressor supplies air at bar to the compression tank. Here the air is absorbed in the high pressure effluent water. This air saturated effluent water is discharged at the bottom of the DAF unit (below the main feed). Once the water pressure is reduced, the absorbed air releases in the form of fine bubbles, which carry sludge to the top of the DAF unit. The sludge is then scraped off the surface to a collection tank using a skimmer and the remaining underflow water is sent to the ponds. The sludge from the DAF is transported to the sludge holding tank. The installed maximum load of the DAF should be reviewed with regards to EMO 3.1. It is believed the Gravity Belt Thickener (GBT) would use less energy than the DAF to perform the same function (though at a greater polyelectrolyte cost). As mentioned in EMO 1.1, an asset register should be established that documents the energy use and intended operation of each item of process equipment. P56 (believed to be the DAF Feed Flow pump) was listed as having 196 Hz frequency on the SCADA (Supervisory Control And Data Acquisition) graphic for the secondary clarifier. This was read elsewhere to be 19.6 Hz. The SCADA graphic should be checked and adjusted accordingly. Return Activated Sludge (RAS) The return activated sludge system takes the sludge from the secondary clarifier and returns it to the Aeration Basin. This increases the contact time of the waste with the micro-organisms required for water treatment and is used to promote the growth of more micro-organisms. Two 11 kw pumps are used in this area (one on / one standby). This return activated sludge was seen to be operating at 74 litres/ second. The pump operation for return activated sludge is very efficient in that pumps operate for a length of time relative to the thickness of the blanket of sludge it is trying to move from the secondary clarifier. The following steps are used: Step Return Level (mm) Total pump min/hour (2 pumps) Waste Activated Sludge (WAS) Waste activated sludge is removed directly from the secondary clarifier and sent to the Dissolved Air Floatation (DAF) unit using the waste activated sludge pump. NRSBU BISTP Level 2 Energy Audit 23
26 This pump is controlled with a variable speed drive. The waste activated sludge was seen to be operating at 4.4 litres/ second (a small fraction of the return activated sludge flow). The waste activated sludge is about.6-1% solids when it reaches the Dissolved Air Floatation (DAF) unit. Solids Dewatering Building (SDB) There is currently provision for the primary solids to be sent to the Solids Dewatering Building where they can be processed for removal to landfill. The Solids Dewatering Building dewaters the digested sludge for bio-solids disposal. Several potential practical uses for digested bio-solids exist including soil regeneration, but these usages usually have to overcome political and health barriers. This facility is currently inactive due to the consistent and safe use of solids for fertilising trees on Rabbit Island. There is also an activated carbon filter external to the Solids Dewatering Building, which only operates when the Solids Dewatering Building is operating. The Solids Dewatering Building currently uses its own meter resulting in significant annual cost. This is discussed further in EMO 1.2. Gravity Belt Thickener (GBT) plant: The Gravity Belt Thickener is currently not in operation as the DAF has been seen to be sufficient for the separation of solids. It could act as an alternative to the DAF and is still set up for sludge separation. Like the DAF, the Gravity Belt Thickener is polymer dosed. It is said to have only been in operation for 2 months after which it was not required. During the site visit, it was noted the Gravity Belt Thickener could potentially use significantly less energy than the DAF to thicken sludge due to much reduced pumping equipment. This is discussed in EMO 2.3. Sludge Storage Tank: Sludge from the bottom of the primary clarifier (pumped by P618 and P624) and sludge from the DAF (pumped using a 7.5 kw worm pump ), go to the sludge storage tank. The Nelson North sludge tank receives (by truck) sludge unable to be used at the Nelson North water treatment plant. This is also pumped to the main sludge tank. The Nelson North sludge pump only operates when required to by Nelson North. This can be anywhere from once a day to twice a month. The power used by the associated pump should reflect this variance. The amount of sludge fed to the sludge storage tank is monitored carefully. The age of sludge that reaches the storage tank can vary from 1 to 3 days (longer in a few cases). Sludge is on average around 5 days old when it reaches the storage tank. Autothermal Thermophilic Aerobic Digesters (ATAD): The two-stage ATAD process uses heat released by microbial activity to achieve and sustain optimal temperature range for thermophilic digestion. The digesters are fed sludge from the sludge storage tank and deliver it to the Bio-solids tank to be pumped to Rabbit Island. Two pumps operating in duty/standby feed the pipes which split the sludge between the A, B and C trains. Each train has a valve and actuator. A heat exchanger was installed to pre-heat NRSBU BISTP Level 2 Energy Audit 24
WASTEWATER TREATMENT OBJECTIVES
WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater
More informationCHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES
CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality
More informationMUNICIPAL WASTEWATER TREATMENT PLANT ENERGY EVALUATION FOR ITHACA AREA WASTEWATER TREATMENT FACILITY
MUNICIPAL WASTEWATER TREATMENT PLANT ENERGY EVALUATION FOR ITHACA AREA WASTEWATER TREATMENT FACILITY Agreement No. 7185 Prepared for THE NEW YORK STATE ENERGY RESEARCH AND DEVELOPMENT AUTHORITY Albany,
More informationBay Park Sewage Treatment Plant Super Storm Sandy Recovery
County of Nassau Department of Public Works Bay Park Sewage Treatment Plant Super Storm Sandy Recovery Edward P. Mangano County Executive Shila Shah-Gavnoudias, P.E. Commissioner of Public Works Bay Park
More informationAppendix F Use of spill basin to further reduce final effluent variability - report
Appendix F Use of spill basin to further reduce final effluent variability - report yry (November 2008) Use of the emergency basin to further reduce the variability of final effluent quality. Report prepared
More informationDescription of the Water Conserv II Facility
Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has
More informationOasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS
Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS The evolution continues in decentralised wastewater technology... The Process Decentralised wastewater treatment systems are defined
More informationHow To Recover From A Flood In Bundaberg
BUNDABERG FLOODS NOW THE MUD HAS DRIED FLOOD RECOVERY AT MILLBANK Paper Presented by: Kym Kneebone Author: Kym Kneebone, Assistant Coastal Treatment Co-ordinator, Bundaberg Regional Council 37th Annual
More informationWastewater Nutrient Removal
Wastewater Nutrient Removal An overview of phosphorus and nitrogen removal strategies Presented by: William E. Brown, P.E. Peter C. Atherton, P.E. Why are nutrients an issue in the environment? Stimulates
More informationExperts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service
Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components
More informationCambridge Wastewater Treatment Facility
Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working
More informationThe City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
More informationPRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems
PRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems PACKAGE SEWAGE TREATMENT SYSTEM Clearwater treatment plants are ideal for single houses and employ the well proven aerobic biological
More informationSewerage Management System for Reduction of River Pollution
Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from
More informationA HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS
GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management
More informationFacility Classification Standards
Facility Classification Standards Approval Date: April 3, 2009 Effective Date: April 3, 2009 Approved By: Nancy Vanstone, Deputy Minister Version Control: Replaces Facility Classification Standards dated
More informationlforrnation Requir C -INF lucture & OPER eraf - Drawing No. 5270-2910 - Drawing No. 5270-2911
C -INF eraf - lucture & OPER lforrnation Requir Outline Description of the Treatment Process at Kiicioon WWTP 8 Agglomeration - Drawing No. 5270-2910 Co n se nt o f c Fo op r i yr ns ig pe ht ct ow ion
More informationMinutes of a meeting of the Nelson Regional Sewerage Business Unit. Held in Ruma Marama, Civic House, Trafalgar Street, Nelson
Minutes of a meeting of the Nelson Regional Sewerage Business Unit Held in Ruma Marama, Civic House, Trafalgar Street, Nelson On Friday, commencing at 9.04am Present: In Attendance: Apology: Councillors
More informationUpper Occoquan Service Authority Centreville, Virginia A Case Study
Upper Occoquan Service Authority Centreville, Virginia A Case Study Dennis Clough, Managing Director Energy Systems Group Upper Occoquan Service Authority About the Upper Occoquan Service Authority 54
More informationANAEROBIC/ANOXIC TANKS
PROCESS DESCRIPTION In the anaerobic/anoxic tanks, wastewater is prepared for further treatment in the biological reactors. Denitrification and luxury uptake of phosphorus take place by mixing a food source
More informationWASTE WATER TREATMENT SYSTEM (OPERATING MANUALS )
Page 1 of 76 1.0 PURPOSE The purpose of the Wastewater Treatment System is to remove contaminates from plant wastewater so that it may be sent to the Final Plant Effluent Tank and eventually discharged
More informationA NOVEL ION-EXCHANGE/ELECTROCHEMICAL TECHNOLOGY FOR THE TREATMENT OF AMMONIA IN WASTEWATER
A NOVEL ION-EXCHANGE/ELECTROCHEMICAL TECHNOLOGY FOR THE TREATMENT OF AMMONIA IN WASTEWATER ABSTRACT Leonard P. Seed, M.Sc., P.Eng., Enpar Technologies Inc. * Daren D. Yetman, A.Sc.T., Enpar Technologies
More informationAdvanced Wastewater Treatment and Disposal Systems. Water and Wastewater Utility Operation and
Advanced Wastewater Treatment and Disposal Systems Water and Wastewater Utility Operation and Management for Tribes Preliminary Treatment Primary Treatment Secondary Treatment Tertiary Treatment Disinfection
More informationADVANCED LAGOON TREATMENT TECHNOLOGIES FOR WASTEWATER TREATMENT
ADVANCED LAGOON TREATMENT TECHNOLOGIES FOR WASTEWATER TREATMENT ABSTRACT by Vikram M Pattarkine*, Randall C Chann**, Charles E Tharp** *Brinjac Engineering Inc, 114 North 2 nd Street, Harrisburg, PA 1711
More informationSource Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water
United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows
More informationProcess and Energy Audits at Water and Wastewater Facilities. Thomas Devine, CAP, CEM, LEED AP April 25 2012
Process and Energy Audits at Water and Wastewater Facilities Thomas Devine, CAP, CEM, LEED AP April 25 2012 Presentation Outline Types of Audits Benchmarking Submetering Data Collection/Information Gathering
More informationAeration Efficiency Guide
Aeration Efficiency Guide Environmental Dynamics InTernational EDI specializes in the research, development, and application of advanced technology aeration and biological treatment solutions for municipal
More informationSt. John s Harbour Clean-Up Phase 2. Project Description
St. John s Harbour Clean-Up Phase 2 Project Description February 2003 NEWFOUNDLAND DESIGN ASSOCIATES LIMITED 1 Introduction The City of St. John s, the adjoining City of Mount Pearl and the Town of Paradise
More informationEnergy Audits Waste Water Treatment Plants
Energy Audits Waste Water Treatment Plants Ohio Water Environment Association Conference June 20, 2012 Presented by: Samuel J. Morgan, P.E., LEED AP CT Consultants, Inc. World Energy Trend US Total Energy
More informationTHE MARSHALL STREET ADVANCED POLLUTION CONTROL FACILITY (CLEARWATER, FLORIDA) CONVERSION TO 4-STAGE BARDENPHO TO IMPROVE BIOLOGICAL NITROGEN REMOVAL
THE MARSHALL STREET ADVANCED POLLUTION CONTROL FACILITY (CLEARWATER, FLORIDA) CONVERSION TO 4-STAGE BARDENPHO TO IMPROVE BIOLOGICAL NITROGEN REMOVAL ABSTRACT Timur Deniz, Ph.D., Thomas W. Friedrich, P.E.
More informationEquipment and Instrument Tagging Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Equipment and Instrument Tagging Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted
More informationPractice Tests Answer Keys
Practice Tests Answer Keys COURSE OUTLINE: Module # Name Practice Test included Module 1: Basic Math Refresher Module 2: Fractions, Decimals and Percents Module 3: Measurement Conversions Module 4: Linear,
More informationDOMESTIC WASTEWATER SYSTEMS
Environmental PROTECTION Systems DOMESTIC WASTEWATER SYSTEMS Highest quality sewage treatment systems from the name you can trust Hynds Aerated Wastewater Systems Hynds Lifestyle Systems are an elite range
More informationNAYADIC TROUBLE-SHOOTING CHECKLIST
(IMPORTANT: Disconnect power to compressor or alarm before attempting repairs.) I. COMPRESSOR A. New compressor will not start but 1. Rotary assembly is locked up due 1. Remove internal filters, muffler
More informationEXISTING WASTEWATER TREATMENT FACILITIES
Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City.
More information10 Strategic Steps to Reducing Your Energy Costs AEE Regional Chapter Meeting February 2, 2005
10 Strategic Steps to Reducing Your Energy Costs AEE Regional Chapter Meeting February 2, 2005 Presented by: Gary A. Swanson, PE President Energy Management Solutions (612) 819-7975 10 Step Summary 1.
More informationOPTIMIZING BIOLOGICAL PHOSPHORUS REMOVAL FROM AN SBR SYSTEM MIDDLEBURY, VT. Paul Klebs, Senior Applications Engineer Aqua-Aerobic Systems, Inc.
OPTIMIZING BIOLOGICAL PHOSPHORUS REMOVAL FROM AN SBR SYSTEM ABSTRACT MIDDLEBURY, VT Paul Klebs, Senior Applications Engineer Aqua-Aerobic Systems, Inc. The Middlebury Wastwater Treatment Plant, located
More informationAsset Management Answering the 5 Core Questions
Asset Management Answering the 5 Core Questions by Timothy Taber, PE Barton & Loguidice Page 1 Drivers Asset Management Case Study 1. What is the current state of my assets? 2. What is my required sustainable
More informationSEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.
SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage
More informationBest Practice Guide BPGCS007
Best Practice Guide BPGCS007 ENERGY MANAGEMENT Introduction: With rising fuel costs, opening of electricity and gas markets to alternate suppliers and climate change, the requirement to monitor and reduce
More informationTown of New Castle Utility Department Introduction
Town of New Castle Utility Department Introduction Town of New Castle Utility Department Mission Statement Our commitment is to ensure that our customers receive high quality water and wastewater treatment
More informationSeptic Tank Use & Maintenance Tips
Yellowhead County Hamlet of Cadomin Septic Tank Use & Maintenance Tips This guide gives an overview of the responsibilities for property owners in Cadomin. For Seasonal, Permanent & Vacationing Cadomin
More informationSYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS
SYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS Published in Water and Waste Digest membrane issue, November 2008 Miroslav Colic; Chief Scientist, Clean Water Technology
More informationHolistic Aeration and Chemical Optimization Saves Big Money from 1 MGD to 600 MGD. Trevor Ghylin, PE PhD
Holistic Aeration and Chemical Optimization Saves Big Money from 1 MGD to 600 MGD Trevor Ghylin, PE PhD Outline Background Case Study: Sterno, Sweden (~1.8 MGD) 65% Aeration Energy Reduction Case Study:
More informationTALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa
TALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa Tallinn is the capital of Estonia. It has approximately 450,000 inhabitants and the town area is about 150 km 2. Tallinn Water Ltd., owned by the City
More informationWastewater Asset Management Plan 2012-2022
Wastewater Asset Management Plan 2012-2022 WASTEWATER Asset Management Plan 2012-2022 Author: Phil Ruffell, Principal Adviser Utilities and Chloe Light, Engineering Adviser Review and Approval: Michael
More informationIowa DNR Wastewater Treatment Technology Assessment No. 09-01
Iowa DNR Wastewater Treatment Technology Assessment No. 09-01 Evaluation of Full-Scale LemTec Biological Treatment Facilities for Wastewater Design Review Considerations by the Iowa Department of Natural
More informationEngineers Edge, LLC PDH & Professional Training
510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 Engineers Edge, LLC PDH & Professional Training Copyright, All Rights Reserved Engineers Edge, LLC An Introduction to Advanced
More information31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE
31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE Edited 21/12/01 Wyong Shire Council has many non sewered areas that
More informationPROPAK AquaBio Complete Water Restoration Systems
PROPAK AquaBio Complete Water Restoration Systems Conserving natural resources and lowering operating expenses is no longer an option, it is a necessity. Water, sewer and discharge fees are continuing
More informationOrange County Sanitation District
Orange County Sanitation District The Orange County Sanitation District operates large wastewater treatment plants in Fountain Valley and Huntington Beach, CA. These plants treat about 230 million gallons
More informationModule 16: The Activated Sludge Process - Part II Instructor Guide Answer Key
Unit 1 Process Control Strategies Exercise Module 16: The Activated Sludge Process - Part II Instructor Guide Answer Key 1. What are the six key monitoring points within the activated sludge process? Ans:
More informationHomeowners and Home Buyers Guide to Wells and Private Sewage Systems
Homeowners and Home Buyers Guide to Wells and Private Sewage Systems What every homeowner should know about living with a well and a private sewage system. YOUR ENVIRONMENTAL SYSTEMS Out of sight out of
More informationDuring the past decade, the city of
An Advanced Pollution Control Facility s Conversion to Four-Stage Bardenpho to Improve Biological Nitrogen Removal Timur Deniz, Thomas W. Friedrich, and John Milligan During the past decade, the city of
More informationTexas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems
Texas Commission on Environmental Quality Page 1 217.31. Applicability. SUBCHAPTER B: TREATMENT FACILITY DESIGN REQUIREMENTS 217.31-217.39 Effective August 28, 2008 This subchapter details the design values
More informationProvided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system.
II. PROCESS OVERVIEW Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system. II.1. Wastewater Generation A typical
More informationGrit Removal Identification and Removal Methods
Grit Removal Identification and Removal Methods ERIN FLANAGAN, P.E. Northeast Biennial WEAT Conference May 7, 2014 Presentation Outline True Grit Particle Size Grit Material Comparison Settling Characteristics
More informationCity of Charlottetown Wastewater Treatment Expansion & Upgrading
City of Charlottetown Wastewater Treatment Expansion & Upgrading Background As Canada s smallest provincial capital, the City of the Charlottetown has a population of approximately 34,000 residents and
More information26th Ward Wastewater Treatment Plant Wet Weather Operating Plan
26th Ward Wastewater Treatment Plant Prepared by: New York City Department of Environmental Protection Bureau of Wastewater Treatment July 2010 TABLE OF CONTENTS Page 1.0 INTRODUCTION... 1-1 1.1 BACKGROUND...
More information5. TREATMENT FACILITIES
5. TREATMENT FACILITIES 5.1. Background... 1 5.2. Nine Springs Wastewater Treatment Plant... 1 5.2.1. Liquid Treatment Facilities... 3 5.2.2. Biosolids Disposal Facilities... 6 5.2.3. Operation and Maintenance
More informationGUIDELINES FOR LEACHATE CONTROL
GUIDELINES FOR LEACHATE CONTROL The term leachate refers to liquids that migrate from the waste carrying dissolved or suspended contaminants. Leachate results from precipitation entering the landfill and
More informationType of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
More informationThe Flow Regulator. Flow regulation
Flow regulation Overloading in sewerage works and drainage systems can be avoided by using an attenuation reservoir, or by directing flow to a less sensitive area. Automatic flow control in gravity fed
More informationIMPACT OF CHEMICALS ADDITION IN WATER/WASTEWATER TREATMENT ON TDS CONCENTRATION AND SLUDGE GENERATION Jurek Patoczka, PhD, PE Hatch Mott MacDonald 27 Bleeker Str., Millburn, NJ 07041 (973) 912 2541 jurek.patoczka@hatchmott.com
More informationMALAYSIA S REQUIREMENTS ON INDUSTRIAL EFFLUENT TREATMENT SYSTEMS -The WEPA Workshop and Annual Meeting 18-21 February 2013 Siem Reap, Combodiaby
MALAYSIA S REQUIREMENTS ON INDUSTRIAL EFFLUENT TREATMENT SYSTEMS -The WEPA Workshop and Annual Meeting 18-21 February 2013 Siem Reap, Combodiaby enforcement DIVISION DEPARTMENT OF ENVIRONMENT, MALAYSIA
More informationGlossary of Wastewater Terms
Glossary of Wastewater Terms Activated Sludge Sludge that has undergone flocculation forming a bacterial culture typically carried out in tanks. Can be extended with aeration. Advanced Primary Treatment
More informationaquateam Aquateam - Norwegian Water Technology Centre A/S Report no: 02-051 Project no: O-02033 Project manager: Dr. Bjørn Rusten.
Feasibility study of biological wastewater treatment plants with Salsnes Filter fine mesh sieve primary treatment compared to plants without primary treatment Aquateam - Norwegian Water Technology Centre
More informationSEPTIC TANK SYSTEMS. Single purpose septic tank receives toilet wastes (blackwater) or sullage (greywater) only.
SEPTIC TANK SYSTEMS There are three common types of septic tank systems in Tasmania Single purpose septic tank receives toilet wastes (blackwater) or sullage (greywater) only. Dual purpose (or all-waste)
More informationBest Practice Guide NO. BPGCS002. Wastewater Treatment Activated Sludge Process
Best Practice Guide NO. BPGCS002 Wastewater Treatment Activated Sludge Process The following is intended to provide a first check for those involved in the operation, management and monitoring of the activated
More informationTECHNICAL BULLETIN. Location of the system. Percolation tests for drainage fields. Cesspool sizing. Suggested Information notices
TECHNICAL BULLETIN Issue 1 Market leaders Whichever product is most suitable for your needs you can be assured of Klargester s quality. Klargester is an accredited company under BS EN ISO 9001 2000 quality
More informationTackling London s Sewer Overflows
Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Tackling London s Sewer Overflows Doc Ref: 8.2.5 Solutions Working Group
More informationProperly maintaining your septic system will help reduce the. It s Your Septic System. Homeowner s Guide. Here s How to Take Care of It
Homeowner s Guide for Maintenance and Care of On-Site Sewage Systems It s Your Septic System Here s How to Take Care of It Properly maintaining your septic system will help reduce the possibility of health
More informationUnderstanding and Living With Your Septic System
Chapter 9 Understanding and Living With Your Septic System Rural versus urban sewage treatment One of the big difference between rural and city life is how sewage is dealt with. Cities usually have community
More informationPlumbing for retail food businesses
Plumbing for retail food businesses Every day, thousands of food outlets in Sydney produce waste, such as cooking oil, grease and food solids. If that waste is discharged directly into our sewers, it can
More informationCapital Improvement Program Monthly Status Report for June 2014
Capital Improvement Program Monthly Status Report for June 2014 August 7, 2014 This report provides a summary of the progress and accomplishments of the Capital Improvement Program (CIP) for the San José-Santa
More informationFundamentals of Asset Management. Step 10. Build Asset Management Plan A Hands-On Approach
Fundamentals of Asset Management Step 10. Build Asset Management Plan A Hands-On Approach Tom s bad day Fundamentals of Asset Management 2 AM plan 10-step process Develop Asset Registry Assess Performance,
More informationWASTE WATER Solutions
Huber Technology is a leading supplier of stainless steel waste water treatment equipment. Our extensive experience enables us to offer high quality solutions for all your waste water treatment needs for
More informationProducts, systems and services for water and wastewater treatment plants Enhanced plant performance, efficiency and reliability
Products, systems and services for water and wastewater treatment plants Enhanced plant performance, efficiency and reliability Treating water efficiently A global challenge Water and wastewater treatment
More informationWilliam E. Dunn Water Reclamation Facility. Facility Overview & Information
William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa
More informationGeorgia Department of Public Health. Georgia Onsite Sewage Management Systems. Background and Use of Onsite Wastewater Treatment Systems in Georgia
Georgia Department of Public Health Georgia Onsite Sewage Management Systems Background and Use of Onsite Wastewater Treatment Systems in Georgia Background On-site sewage management systems are designed
More informationENERGY MANAGEMENT. for INDUSTRY AND BUSINESS
ENERGY MANAGEMENT for INDUSTRY AND BUSINESS [Principles of Energy Management] Denis Cooke Denis Cooke & Associates Pty Limited Phone + 61 2 9871 6641 Fax +61 2 9614 1723 Email: denis@decoa.com.au Web Site
More informationseptic systems What is a Septic System? How does a Septic System Work?
septic systems What is a Septic System? A septic system is a private sewage treatment system. They are common in rural areas where there are no municipal sewage pipes for homes, farms, businesses or other
More informationINDEX. Introduction 3. The Septic System 3. What Does The Septic Tank Do? 4. Where It All Goes 5. Problems 7. Some Dontʼs 8
1 INDEX Introduction 3 The Septic System 3 What Does The Septic Tank Do? 4 Where It All Goes 5 Problems 7 Some Dontʼs 8 Management of Your On-Site System 9 Tank Maintenance 9 Disposal Field Area 10 Appendix
More informationToronto s Wet Weather Flow Master Plan
Toronto s Wet Weather Flow Master Plan 1. The Master Plan 2. The Don And Waterfront Study 3. What the Individual Can Do Wet Weather Flow Management Master Plan 2000 Storm Presentation to Don Mouth Naturalization...
More informationUnderstanding and Caring for Your Septic System
Understanding and Caring for Your Septic System Summit County Public Health 1867 W. Market Street Akron, Ohio 44313 330-926-5600 www.scphoh.org The purpose of a home's subsurface septic system is to dispose
More informationOutline. Background. NFPA 820 Applicability to Wastewater Treatment Facilities. Hazardous Area Classifications. Treatment Plant Area Classifications
Outline Background NFPA 820 Applicability to Wastewater Treatment Facilities Hazardous Area Classifications Treatment Plant Area Classifications Locations of Concern Background NFPA 820 Standard for fire
More informationWWTP RETROFIT. Smith & Loveless Inc. www.smithandloveless.com. Also in this issue: Do You Have Emergency Backup? Aging Clarifiers Retrofit to Like New
Winter 2010 Issue #04-06-759 Rehabilitate your aging infrastructure quickly and increase your treatment capacity. Also in this issue: Do You Have Emergency Backup? Aging Clarifiers Retrofit to Like New
More informationLooking after your Septic Tank System
Looking after your Septic Tank System Name: Bought to you by Address: File this in your property file. 0800 TO FLUSH Call 0800 TO FLUSH 1 What do you know about your septic tank system? Just like your
More informationEnhancing Nitrification in an Oil Refinery WWTP with IFAS
Enhancing Nitrification in an Oil Refinery WWTP with IFAS Wayne J. Flournoy (2), Russ Grillo (1), *Sarah B. Hubbell (2), Ramesh Kalluri (3), Casey Mueller (1) (1) Frontier Refining, Inc. (2) Entex Technologies
More informationUnderstanding Septic Tank Systems
Understanding Septic Tank Systems Sewage and effluent can contain a variety of human disease-causing microorganisms and parasites. Disease can be spread to humans from this material by direct contact or
More informationOn-site Treatmentt for Domestic Wastewater in Thailand Suwanna. K. Boontanon Mahidol Univ. 2
WEPA International Workshop 2013 Cambodia On-site Treatment for Domestic Wastewater in Thailand Suwanna Kitpati Boontanon Assistant Professor, Faculty of Engineering Mahidol University February 18, 2013
More informationA guide to using variable-speed drives and motors in swimming pool halls
A guide to using variable-speed drives motors in swimming pool halls Meeting the energy CO 2 reduction challenge Swimming pool halls are expensive to run, consuming large amounts of electricity. They are
More informationEXISTING WASTEWATER TREATMENT FACILITIES
Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City
More informationRETICULATED RECYCLED WATER SCHEMES OPERATIONAL CONSIDERATIONS. Duncan Wallis. RM Consulting Group
RETICULATED RECYCLED WATER SCHEMES OPERATIONAL CONSIDERATIONS Paper Presented by: Duncan Wallis Author: Duncan Wallis, Senior Consultant, RM Consulting Group 72 nd Annual Water Industry Engineers and Operators
More informationAfter the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.
After the Flush Published: July 14, 2011 Sewage or wastewater is something we rarely think or talk about. The wastewater from our toilets, showers, washing machines and dishwashers quickly departs our
More informationALL YOU NEED TO KNOW...
ALL YOU NEED TO KNOW... What do you know about your septic tank system? For the purposes of this booklet, a septic tank system refers to any kind of on-site sewage management system including traditional
More informationHomeowner s Guide to Maintaining a Sewage Treatment System
Homeowner s Guide to Maintaining a Sewage Treatment System Warren County Combined Health District 416 South East Street Lebanon, OH 45036 513-695-1220 Sewage Treatment Systems Septic Tank and Soil Absorption
More informationCONDENSED CATALOG WWW.DELTAENVIRONMENTAL.COM
DELTA ENVIRONMENTAL RESIDENTIAL TREATMENT CONDENSED CATALOG WWW.DELTAENVIRONMENTAL.COM DELTA ENVIRONMENTAL The Difference is Clear Introduction to Delta Environmental Founded in 1985, Delta Environmental
More informationCOD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens
COD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens Removal of particulate material from wastewater Eco-efficient use of capital Water pollution control through maximum COD/BOD 5 reduction Service
More informationCompact Sewage Systems in France A technical and cost comparison
2010 Sewage System Approvals Introduction The methods of evaluating systems are fixed by a decree dated 7 th September 2009. All companies wishing to have a system approved must submit a file to the appropriate
More information