PROJECT MANAGEMENT WITH SIMULATION A critical view on the critical path
|
|
|
- Maryann Kelly
- 9 years ago
- Views:
Transcription
1 PROJECT MANAGEMENT WITH SIMULATION A critical view on the critical path Jaap A. Ottjes and Hans P.M. Veeke, Sub Faculty of Mechanical Engineering and Marine Technology, Fac. OCP Delft University of Technology Mekelweg 2, 2628 CD Delft, the Netherlands [email protected], [email protected] Key words: project planning; decision support; discrete event simulation ABSTRACT A process-oriented simulation approach to project management is proposed which gives realistic statistical information about total project data and about individual activities as a function of contractual completion-time. The proposed method provides the possibility to define a generic activity network, which is simulated. The activities in the network may have any statistical or tabulated completion-time distribution. A project simulation run consists of a large number of sub-runs each simulating a project realisation. A run provides statistical information with respect to project completion-times, individual activities such as the probability of activities being critical and excess probability of contract time, and information for monitoring contract critical activities during project realisation. A case of aircraft maintenance is elaborated in which the model is used to reduce the number of contract time excesses using a simple rule assigning extra capacity to activities. The rule is based on preliminary analyses and information that is obtained during the project progress. INTRODUCTION For many years it has been common practice to support project management by planning techniques such as CPM and Pert (Winston,1991). During recent decades there has been an increase in the use of simulation to support management decisions, including those in the field of project management (Veeke 1982), (Lightfoot 2), (Deschaine 2). One of the main advantages of using simulation is that in addition to providing realistic statistics of the whole project, all the data of every single project-realisation is available and can be used for further analysis. In practice simulation results may be used to determine the contractual completion date of the project during a quotation-process. For each manager it is clear that this contractual duration will not be the shortest time possible, because then the chance of exceeding it would be 1%. In consequence management will decide to offer a project-duration with a specified confidence level of for example 9%. To that end, a realistic project completion-time distribution is needed. After the decision on this project-duration there is a 9% chance of project-duration without any critical path, simply because the finishing time will be shorter than the contractual project-duration. Management of the project will concentrate on those activities that may still cause a late finish. These contract critical activities are not necessarily restricted to the critical path activities of the CPM analysis, but may be activities that were not initially critical at all or only slighty critical. The simulation detects these potentially critical activities providing the means to monitor the right activities during real projectexecution. Next process oriented modelling will be explained (Zeigler, 1985) and the kernel of the network model will be shown in pseudo-code. The actual model is coded in the process-oriented simulation tool TOMAS (Veeke and Ottjes, 2a and b). The model will be further elaborated and applied to a case of aircraft
2 maintenance. The results of the modelling will be discussed from a project manager s point of view. PROCESS-ORIENTED MODEL The process-oriented approach used in this work can be summarised in two steps: (Healy, 1997), (Veeke and Ottjes, 1999). Step 1: decompose the system into relevant classes of elements, preferably patterned on the real-world elements of the system. A class is characterised by its attributes. An instance of a class will be called an element. The state of each element is defined by the value of its attributes. Step 2: distinguish the living element classes and provide their process description. A process governs the dynamic behaviour of each element. The system time during a simulation is called now. In the process description of an element class we use hold t to indicate that an element needs t time units to carry out some task. If such a hold statement is encountered in the process description, the process halts until time t has elapsed and then continues its process. In other words the process is waiting for a specific time event. Analogous to this, it is possible for a process to wait for a state event e.g. for a specific condition to be fulfilled. In pseudo-code this is written as: standby while/until condition. Another time consuming statement in a process description is suspend meaning that an element becomes passive when this statement is encountered. A passive element can only be restarted by the resume command given from the process of another element. Because several elements may be active at the same time a sequencing mechanism is needed to synchronise the activities and to manage the event calendar. This mechanism must be supported by the simulation package that is used. Additional features are queues or sets, which may contain elements and, in the case of stochastic behaviour, distributions, modelling for example execution duration. Queues and sets and distributions may be used as attributes of element classes. The kernel of the network model and its dynamics will now be described in terms of a process-oriented model in pseudo-code and in Tomas-code. THE NETWORK MODEL We distinguish two element classes: the activity class and the monitor class. The main element class is the activity class. We use the activity on node description. The activity class owns several attributes such as a preactivityset and postactivityset as shown in Figure 1. These sets contain the preceding and succeeding activities respectively. In this way any directed activity network can be defined. PreActivitySet PostActivitySet ControlActivitySet ExecTimeDistribution exectime {=sample exectimedistribution} earlieststart latestfinish PROCESS Figure 1. attributes of class activity in pseudo-code. put all activities of preactivityset into controlactivityset standby until controlactivityset is empty earlieststart= NOW exectime=sample of exectimedistribution hold exectime leave controlactivityset of the all activities in postactivityset leave scheduledactivityset suspend {next reverse simulation: break down the project} put all activities of postactivityset into controlactivityset standby until controlactivityset is empty latestfinish = completiontime-now hold exectime leave ControlActivitySet of all activities in preactivityset leave scheduledactivityset Figure 2. Process description of class activity in pseudo-code. procedure Class_activity.Process; begin while simulation_on do begin suspend; prepare(preactivityset); while controlactivityset.getlength> do begin standby; end; earlieststart:= tnow-subrunstarttime; exectime:=drawexectime(distrtype); hold(exectime); leaveactivitysets(postactivityset); leavequeue(scheduledactivityset); suspend; {next reverse simulation: break down the project} end;{while simulation_on} finish; end; Figure 3. Part of the process of the class activity in Tomas and Delphi-code. Typical Delphi key words are bold. Tomas key words are italic.
3 The controlactivityset is used for run control purposes. In addition to this an activity owns its execution time distribution, which can be of any type for each instance, and typical data such as earliest start time and latest completion-time, which have to be determined during simulation. An activity owns a PROCESS that takes care of its own timely execution. In other words: the activity waits until it is allowed to be executed. It then executes itself using a sample from its execution time distribution as activity-duration. After execution it leaves the scheduledactivityset. If all the activities of the project are finished (scheduledactivityset= empty), the make span and all early start times are known. Then the simulation is performed in reverse. In other words the project is broken down. This provides the latest finish data for all activities. The activity slack (also called total float) is defined as: slack=latest finish executiontime - earliest start. An activity with slack= is called critical. The process of the activity class is described in Figure 2. Figure 3 shows part of the code of the model implementation in Tomas. For number of sub-runs Do: Put all activities into the scheduledactivityset Start processes of all activities Standby until scheduledactivityset is empty CompletionTime=NOW {prepare and start the reverse simulation } Put all activities back into the scheduledactivityset Resume processes of all activities Standby until scheduledactivityset is empty Figure 4. Process description of the class monitor in pseudo-code. 2 inspect casco repair casco inspection large wheels repair large wheels repair retrack mechanism clean and dismount inspection nose wheel repair nose wheel test retrack mechanism 25 load emergency unit 1 prepare for inspection 9 grease check greasing 26 final check dismount for greasing 1 testing instruments repair instruments clean port 17 inspect port repair port dismount s inspect fire extinguish eq repair fire extinguish eq act.nr activity name lb av ub 12 clean starboard 19 inspect starboard repair starboard Figure 5. Case: Aircraft maintenance activity network with activitie NRs, name and activity-duration data: lb: lower bound, av: average and ub: upper bound.
4 f1 f2 lb av ub Figure 6: General execution time distribution for an activity. Three numbers are given: lb: lower bound, av: the average and ub: the upper bound. In order to obtain the average av it is demanded that f1*(av-lb)=f2*(ub-av) The monitor class governs the simulation runs. Its process is described in Figure 4. The monitor is responsible for the preparation, start and analysing of a simulation run. One simulation run consists of a number of simulation sub-runs. Every sub-run simulates one realisation of the project giving a completion-time and all data of the individual activities. The data of each sub-run is stored for further analysis. Table 1. Critical path analysis with fixed average activity execution times (av) given in Figure 5. Activity-NR Slack Eeriest Start Latest Finish Project completion-time: 66 hours One run consequently provides statistical data about project completion-times and the probabilty of activities that are critical. In this work a run consist of 1-5 sub-runs. With the approach described multiproject simulation can be obtained by creating a monitor for each project and starting it at the proper time. In such cases no reverse simulation is performed. Further it is possible to allocate scarce resources (Ottjes and Veeke 2). This paper focuses on a single project. APPLYING THE MODEL: A CASE The use of the model will be illustrated by a simplified case concerning aircraft maintenance (Veeke, 1997). Figure 5 shows the activity network. The activities are named and also identified by a number. The durations of the activities indicated apply to a general distribution explained in Figure 6. Any other distribution function may be applied including functions defined by a table. Table 2. critical path analysis. The project was simulated 5 times using activity execution times drawn from the distribution according to the data in Figure 5 and shaped as Figure 6. The last column shows the percentage of sub-runs that the activity was critical in the case of a project completion-time exceeding the contract time. The contract time was set at hours being the 9% percentile of the project completion-time distribution. Activity- NR Av.Slack % Critical % Contract Critical Average project completion-time: hours Experiments One run with one sub-run was done using the average activity execution times from Figure 5 as fixed
5 execution times. Table 1 shows the activities ranked to their slack. The first 6 activities are critical. Figure 7 shows the completion-time distribution as a result of one run of 5 sub-runs in which activity execution times are drawn from the individual activity distribution functions. The average completion-time amounts to hours, which appears to be substantially more than the completion-time determined with average execution times. To emphasis the effect of activity-duration distribution, a "worse case" run was performed using exponential distributed activity execution times with the same averages as those given in Figure 5. frequency Entries 5 9% Percentile Average % Percentile 86.4 Stand.Dev Maximum project completion times (h) Figure 7. Completion-time distribution as a result of one run of 5 sub-runs in with activity execution times drawn from the individual activity distribution functions defined by Figure 6 using the parameters of Figure 5. frequency Entries 5 9% Percentile Average % Percentile Stand.Dev Maximum project completion times (h) Figure 8. Completion-time distribution as a result of one run of 5 sub-runs in which activity execution times are drawn from the individual activity distribution functions. Here negative exponential distribution functions were applied with average indicated in Figure 5. The results are shown in Figure 8, and give an average project completion-time of 97.5 hours and a 9% completion-time percentile of 154 hours. It can be concluded that the completion-time distribution and its average strongly depend on the execution time distributions of the activities. If (some) activity execution time distributions are unknown in practice, experiments with several distribution types provide insight in the influence on completion-time. All further runs in this paper refer to the general distribution type of Figure 6. Table 2 represents the same run as Figure 7 and shows the results for all activities sorted on average slack. In column 3 the percentage of the sub-runs in which the activity was critical is indicated. The project contract time was chosen as the 9% percentile of Figure 8, this being hours. The last column shows the percentage in which the activity was critical if the contract time was exceeded. We will call that contract critical. Some activities, for example activity 23, are not critical with fixed average execution times but appear to be critical to some extent when using the execution time distributions, and are highly critical if the contact time is exceeded. These activities have to be monitored carefully during the project. From the point of view of a project manager it is very important to know what decisions have to be made during the project. It is necessary to appreciate how to use additional information gained during progress of the project. After activity 19: check starboard, there may be a pretty accurate estimate of the duration of activity 23, the repair time of the. How to use this extra information! For example, the manager needs to know wether to apply extra resources, speeding up activity 23 in order to avoid project tardiness. Consequently he needs to know at what execution time level activity 23 will be contract critical. To answer this question runs were performed for a number of pre-set execution times of activity 23. The results are shown in Figure 9. %contract-critical execution times of activity 23 Figure 9. Relation between activity 23 being contract critical and its execution time. As a contract time the 9% percentile of the project completion-time distribution was taken this being hours. Each measuring point represents a run with 1 sub-runs.
6 It can be concluded that if the execution time of activity 23 is kept under 52.7 hours, it will not become critical. The critical activity-duration depends on the used contract time according to Figure 1. exec.time of act project Contract Time Figure 1. Critical levels of duration of activity 23 as a function of the project contract time. The contract time values correspond with percentiles of 8%, 85%, 9% and 95% (see also Figure 7). Capacity Another aspect for which simulation offers added value is the assignment of finite capacity. Most networks only reflect the technical limitations imposed on the activitysequence. So two activities that have no technical dependencies may be executed in parallel in the network. Limited capacity may prevent or delay parallel execution. However, it is clear that at each moment the need for capacity is determined by the duration of the preceding activities and the actual need for capacity. Simulation offers a natural way of dealing with limited capacities by dynamically assigning capacity to activities according priority rules. if (exectime>ultimatevalue) then begin if mechanic available then begin claim mechanic exectime:=exectime*2/3 end end hold exectime eventually release mechanic Figure 11. Pseudo-code capacity claiming rule replacing "hold exectime" statement in Figure 2 To illustrate this the case under consideration will be further elaborated. We will focus on the two repair activities 21 and 23. The duration of these activities is based on two mechanics working per activity. We assume these two mechanics are available for each. As shown in Figure 9, activity 23 may have to be speeded up to remain under an ultimate value (52.7 hours). To this end the rule is that an additional mechanic is brought in if the repair time, as predicted in the preceding inspection activity, exceeds the ultimate value. It is necessary to determine how many additional mechanics are needed and how the rule influences the completion-times. First the ultimate value of activity 21 is determined in a way similar that used for activity 23. The rule was implemented in the activity process as indicated in Figure 11. Two types of experiments were performed: 1: infinite capacity; in this case two extra mechanics are available 2: restricted capacity: one extra mechanic is available The results are shown in Table 3 and Figure 12. Table 3. Experiments with capacity rule. Each run consists of 5 sub-runs. The contract time applied was 84.15, this being the 9% percentile of the completiontime distribution without the rule given in Figure 7. infinite extra capacity finite extra capacity No extra capacity % exceeding 1 1 contract time %interventions average project completion-time std. Deviation max completiontime Entries 5 9% Percentile Average % Percentile 8.25 Stand.Dev Maximum frequency project completion times (h) Figure 12. Completion-time distribution as a result of one run of 5 sub-runs with one extra mechanic who is assigned to activity 21 or 23 according the rule explained in Figure 11. The experiments indicated that the risk of contract time excess can be reduced from 1% to 1% with one extra mechanic scheduled according the rule. Of course evaluation of cost should determine wether such a measure is indeed profitable.
7 CONCLUSIONS Process-oriented simulation offers a natural way for project planning, especially with respect to uncertainty about the duration of activities and all kinds of specific constraints in and between activities. If activityduration distributions are known, simulation provides realistic statistics on project duration and information about the chance of individual activities being critical. A case relating aircraft maintenance shows a very large influence of activity-duration distribution functions on average project completion-time and its distribution. If the distribution functions of one ore more activity durations are unknown, experiments with several distribution types supplies insight in completion-time distributions. From the completion-time distribution function a project contract time with known probability can be derived. When this contract time is aggreed, further experiments indicate contract critical activities. Analysing the influence of these activities provides criteria for when and how to intervene during the progress of the project in order to force the completion of the project within the contract time. Further research will focus on the allocation of capacity and resource allocation. REFERENCES Deschaine, L.M., Pack, S.R., Zafran, F.A., Patet, J.J. 2. Project Risk Quantifier and optimal Project Accelerator- Using Machine Learning and Stochastic Simulation to Optimize Project Completion Dates and Costs. In Proceedings of Advanced Simulation Technology Conference (ASTC2). April 16-2, 2, Washington, D.C. pp The Society for Computer Simulation International (SCS), ISBN: , Washington, D.C. pp The Society for Computer Simulation International (SCS), ISBN: Veeke, H.P.M "Process simulation as a management Tool, Proceedings of the IASTED International Symposium Applied Modelling and Simulation, Paris, Veeke, H.P.M Customer based production control. MB-Produktietechniek( in Dutch), vol:63:8/9 pp , Veeke, H.P.M. and Ottjes, J.A Problem oriented modelling and simulation, Proc Summer computer Simulation Conference (SCS 99) Chicago, Illinois pp , ISBN Veeke, Hans P.M., Jaap A. Ottjes, 2a. TomasWeb: web site: Veeke, Hans P.M., Jaap A. Ottjes, 2b. Tomas: Tool for Object-oriented Modelling And Simulation. In proceedings of Advanced Simulation Technology Conference (ASTC2). April 16-2, 2, Washington, D.C. pp The Society for Computer Simulation International (SCS), ISBN: Winston, W.L Operations Research Applications and Algorithms, 2ed., PWS-KENT Publishing Company Boston, ISBN: Zeigler, B.P Theory of Modeling and Simulation. Krieger, Malaba. Healy, J. R.A. Kilgore "Silk,: A Java-Based Process Simulation Language". in Proceedings of the 1997 Winter Simulation Conference, IEEE, Lightfoot, J. 2. Wing Structure Assembly Processes Using Simulation. In proceedings of Advanced Simulation Technology Conference (ASTC2). April 16-2, 2, Washington, D.C. pp The Society for Computer Simulation International (SCS), ISBN: Ottjes, Jaap A. and Hans P.M. Veeke. 2. Production scheduling of complex jobs with simulation. In proceedings of Advanced Simulation Technology Conference (ASTC2) April 16-2,
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Problems, Methods and Tools of Advanced Constrained Scheduling
Problems, Methods and Tools of Advanced Constrained Scheduling Victoria Shavyrina, Spider Project Team Shane Archibald, Archibald Associates Vladimir Liberzon, Spider Project Team 1. Introduction In this
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
EdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Modeling Stochastic Inventory Policy with Simulation
Modeling Stochastic Inventory Policy with Simulation 1 Modeling Stochastic Inventory Policy with Simulation János BENKŐ Department of Material Handling and Logistics, Institute of Engineering Management
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Devising new Software Project Risk Management Model: MARUNA
Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Analysis of the critical path within a project with WinQSB software
Analysis of the critical path within a project with WinQSB software GURAU MARIAN ANDREI, MELNIC LUCIA VIOLETA Faculty of Engineering and Technological Systems Management, Faculty of Mechanical Engineering
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Winter : Lecture # Project Time Management Homework Discussion Homework
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN
Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
A Generalized PERT/CPM Implementation in a Spreadsheet
A Generalized PERT/CPM Implementation in a Spreadsheet Abstract Kala C. Seal College of Business Administration Loyola Marymount University Los Angles, CA 90045, USA [email protected] This paper describes
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used
A SIMULATION STUDY FOR DYNAMIC FLEXIBLE JOB SHOP SCHEDULING WITH SEQUENCE-DEPENDENT SETUP TIMES
A SIMULATION STUDY FOR DYNAMIC FLEXIBLE JOB SHOP SCHEDULING WITH SEQUENCE-DEPENDENT SETUP TIMES by Zakaria Yahia Abdelrasol Abdelgawad A Thesis Submitted to the Faculty of Engineering at Cairo University
PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK
PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK M Nazrul, ISLAM 1, Eugen, DRAGHICI 2 and M Sharif, UDDIN 3 1 Jahangirnagar University, Bangladesh, [email protected] 2 Lucian Blaga University
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
Dimensioning an inbound call center using constraint programming
Dimensioning an inbound call center using constraint programming Cyril Canon 1,2, Jean-Charles Billaut 2, and Jean-Louis Bouquard 2 1 Vitalicom, 643 avenue du grain d or, 41350 Vineuil, France [email protected]
CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?
EXECUTIVE SUMMARY PURPOSE: This paper is a comparison and contrast of two project management planning and execution methodologies: critical path methodology (CPM) and the critical chain project management
CHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS B. Kanagasabapathi 1 and K. Ananthanarayanan 2 Building Technology and Construction Management Division, Department of Civil
Implementing Resource Scheduling Techniques
Implementing Resource Scheduling Techniques A Guide for Planners and Scheduler s By Raphael M Düa FAICD, MACS(Snr),PCP, CP, GradDISC Owner & CEO Micro Planning International Asia Pacific Pty Ltd Micro
Leaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
APPLYING PERT AND CRITICAL PATH METHOD IN HUMAN RESOURCE TRAINING
APPLYING PERT AND CRITICAL PATH METHOD IN HUMAN RESOURCE TRAINING Eugen ROT RESCU * Abstract: The subject of the article is referring to the modelling and simulating of the formation of human resources
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
Another Look at Sensitivity of Bayesian Networks to Imprecise Probabilities
Another Look at Sensitivity of Bayesian Networks to Imprecise Probabilities Oscar Kipersztok Mathematics and Computing Technology Phantom Works, The Boeing Company P.O.Box 3707, MC: 7L-44 Seattle, WA 98124
BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis
Modeling Page 1 To BPEL or not to BPEL? 5:56 PM To BPEL or not to BPEL? BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 2 A tale of two strategies 5:57
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
A Hybrid Heuristic Rule for Constrained Resource Allocation in PERT Type Networks
World Applied Sciences Journal 7 (10): 1324-1330, 2009 ISSN 1818-4952 IDOSI Publications, 2009 A Hybrid Heuristic Rule for Constrained Resource Allocation in PERT Type Networks Siamak Baradaran and S.M.T.
SWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
THE BENEFITS OF SIGNAL GROUP ORIENTED CONTROL
THE BENEFITS OF SIGNAL GROUP ORIENTED CONTROL Authors: Robbin Blokpoel 1 and Siebe Turksma 2 1: Traffic Engineering Researcher at Peek Traffic, [email protected] 2: Product manager research
The Trip Scheduling Problem
The Trip Scheduling Problem Claudia Archetti Department of Quantitative Methods, University of Brescia Contrada Santa Chiara 50, 25122 Brescia, Italy Martin Savelsbergh School of Industrial and Systems
Resource Scheduler 2.0 Using VARCHART XGantt
Resource Scheduler 2.0 Using VARCHART XGantt NETRONIC Software GmbH Pascalstrasse 15 52076 Aachen, Germany Phone +49 (0) 2408 141-0 Fax +49 (0) 2408 141-33 Email: [email protected] www.netronic.com Copyright
Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions
Rochester Institute of Technology RIT Scholar Works Theses Thesis/Dissertation Collections 2009 Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions Radhamés
ICT Project Management. Software Project Planning By J. Ogutu
ICT Project Management Software Project Planning By J. Ogutu Overview Step Wise project planning framework Preparation of a software project plan Planning and scheduling the activities in software project
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
PERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.
Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION Fitria H. Rachmat 1, Lingguang Song 2, and Sang-Hoon Lee 2 1 Project Control Engineer, Bechtel Corporation, Houston, Texas, USA 2
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Priori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
Prof. Olivier de Weck
ESD.36 System Project Management + Lecture 9 Probabilistic Scheduling Instructor(s) Prof. Olivier de Weck Dr. James Lyneis October 4, 2012 Today s Agenda Probabilistic Task Times PERT (Program Evaluation
A-1. Chapter 1. Project planning. Chapter 1. Festo Didactic Mechatronics
A-1 Project planning A-2 Mechatronics specialists are responsible for the complete service life of an industrial machine, from the initial planning phase through to its disassembly and disposal. This cycle
How project management software can smooth the way
How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended
Analysis of a production-inventory system with unreliable production facility
Analysis of a production-inventory system with unreliable production facility Katrien Ramaekers Gerrit K Janssens Transportation Research Institute Hasselt University - Campus Diepenbeek Wetenschapspark
A Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
March 30, 2007 CHAPTER 4
March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
15. How would you show your understanding of the term system perspective? BTL 3
Year and Semester FIRST YEAR II SEMESTER (EVEN) Subject Code and Name BA7201 OPERATIONS MANAGEMENT Faculty Name 1) Mrs.L.SUJATHA ASST.PROF (S.G) 2) Mr. K.GURU ASST.PROF (OG) Q.No Unit I Part A BT Level
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
Deployment of express checkout lines at supermarkets
Deployment of express checkout lines at supermarkets Maarten Schimmel Research paper Business Analytics April, 213 Supervisor: René Bekker Faculty of Sciences VU University Amsterdam De Boelelaan 181 181
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Research on Task Planning Based on Activity Period in Manufacturing Grid
Research on Task Planning Based on Activity Period in Manufacturing Grid He Yu an, Yu Tao, Hu Da chao Abstract In manufacturing grid (MG), activities of the manufacturing task need to be planed after the
Project management Project Management
Project management Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar A project is a temporary endeavour to produce a unique product, service, or result (PMI
A Model-driven Approach to Predictive Non Functional Analysis of Component-based Systems
A Model-driven Approach to Predictive Non Functional Analysis of Component-based Systems Vincenzo Grassi Università di Roma Tor Vergata, Italy Raffaela Mirandola {vgrassi, mirandola}@info.uniroma2.it Abstract.
Integrated support system for planning and scheduling... 2003/4/24 page 75 #101. Chapter 5 Sequencing and assignment Strategies
Integrated support system for planning and scheduling... 2003/4/24 page 75 #101 Chapter 5 Sequencing and assignment Strategies 5.1 Overview This chapter is dedicated to the methodologies used in this work
