Reliability-based maintenance scheduling of generating units in restructured power systems
|
|
|
- Priscilla Perkins
- 9 years ago
- Views:
Transcription
1 Turkish Journal of Electrical Engineering & Computer Sciences journals. tubitak. gov. tr/ elektrik/ Research Article Turk J Elec Eng & Comp Sci (2014) 22: c TÜBİTAK doi: /elk Reliability-based maintenance scheduling of generating units in restructured power systems Mahmud FOTUHI-FIRUZABAD 1, Farrokh AMINIFAR 1,2,, Abbas SHAHZADEH 3 1 Center of Excellence in Power System Management and Control (CEPSMC), Department of Electrical Engineering, Sharif University of Technology, Tehran, Iran 2 School of Electrical and Computer Engineering, College of Engineering, University of Tehran, Tehran, Iran 3 Aryan Sanat Company, Tehran, Iran Received: Accepted: Published Online: Printed: Abstract: Maintenance scheduling of generating units in restructured power systems is a collaborative and interactive process between independent system operators (ISOs) and generating companies (GENCOs). The ISO should comply with GENCO maintenance preferences subject to targeted system reliability levels. This process might be multistage since the admission of all initial unit outage requests may threaten system reliability. Hence, the ISO accepts some proposals and determines alternatives for the remaining units. The GENCOs are then allowed to confirm the alternatives or revise them. In this paper the ISO problem of generating unit maintenance scheduling is tackled. The objective function is to minimize the deviation of awarded schedule from the requested schedule, as measured in MW weeks. A novel and effective optimization technique is developed to solve the problem at hand. In the proposed methodology, risk leveling and dynamic programming optimization algorithms are concurrently utilized to lessen the computation burden and enhance the solution process. The effectiveness of the proposed method and its applicability to real-life systems are verified by examining the generation section of the IEEE reliability test system (IEEE-RTS). The performance of the new method is also compared with that of the individual risk leveling approach. Key words: leveling Dynamic programming, maintenance scheduling, optimization algorithms, reliability assessment, risk 1. Introduction Generating units in a power system require periodic maintenance during which the unit under maintenance is detached from the grid and can no longer produce electricity. The maintenance of generating units would probably influence the system in 2 ways: increasing the production costs and eroding reliability. In vertically integrated power utilities that own all properties of generation, transmission, and distribution the process of maintenance scheduling is organized by the system administrator while keeping in mind that the aforementioned impacts should be limited as much as possible. In these conventional systems, maintenance scheduling is performed in a single course of action; afterward, the resultant maintenance timetable is announced to unit managers. In restructured power systems, independent system operators (ISOs), which are responsible for ensuring the reliability of power systems, cannot determine the unit outage schedule alone since unit owners are inde- Correspondence: [email protected] 1147
2 pendent entities with specific economic perspectives. Instead, generating companies (GENCOs) compute their preferred maintenance schedules and submit them to the ISO. Acquisition, refining, and coordinating GENCO proposals are then conducted by the ISO. Due to the security/reliability boundaries, the ISO either accepts the schedules or proposes the best alternatives to GENCOs. They can also confirm the alternatives or revise them. As a result, in a restructured environment the problem of maintenance scheduling is resolved through a multistage procedure in which each stage is perceived as an optimization problem. After compilation of the maintenance proposals by GENCOs at the first stage, the ISO executes the second stage to refine the proposals. In the literature, various objective functions have been defined for the ISO optimization problem. In [1], setting unit maintenance time as early as possible and reserve leveling were considered the objectives of the ISO. Reference [2] proposed minimizing operating costs as the optimization criterion. In [3] and [4], the objective of the optimization algorithm was leveling the designated risk measure. In addition to reserve adjustment, reference [5] included the deviation of the final solution from the GENCO timetable in the objective function. Indeed, it was assumed that any deviation from the GENCO-proposed schedule results in a loss in their revenue. The amount of financial loss was supposed to be proportional to the extent of deviation regardless of unit capacities. To be fair, the method proposed in [5] was devised such that the losses associated with all GENCOs are at approximately the same level. In this paper, the objective function of the ISO optimization problem is defined as minimizing the sum of deviations from the scheduled requests of GENCOs in the final solution. The optimization problem is subjected to the system reliability constraint. Therefore, the privileges of GENCOs will be respected by minimizing rejected requests, and system reliability will be preserved within an appropriate range. An innovative hybrid algorithm of risk leveling and dynamic programming techniques was designed to tackle the complicated optimization problem. Numerical case studies are conducted on the IEEE reliability test system (IEEE-RTS). The rest of this paper is organized as follows. In section 2, the mathematical representation of the maintenance scheduling problem is expressed. Then, in sections 3 and 4 the risk leveling method and dynamic programming algorithm are described, respectively. Section 5 presents details of the proposed hybrid optimization method. Numerical studies are conducted in section 6. A comparison between the proposed method and the risk leveling approach is given in section 7. The concluding remarks are drawn in section Mathematical representation of the maintenance scheduling problem As mentioned earlier, the first step in maintenance scheduling in a restructured power system is submission of outage requests by GENCOs. Then the ISO evaluates the proposals to see whether all the GENCO requests can be accepted without any alteration. Otherwise, some unit outage times should be awarded and the remaining modified accordingly. In such a case, the ISO attempts to keep the changes imposed on the remaining units minimal. In this paper the deviation from the requested time schedule associated with each unit is measured in MW weeks. This quantity is calculated by multiplication of unit capacity (in MW) as a weighting coefficient and absolute value of the difference between demanded and appointed outage times (in weeks). As an example, if the outage time of a 400 MW unit is postponed for 3 weeks by the ISO, the respective deviation would be 1200 MW weeks. The philosophy behind consideration of weighting coefficients is that any deviation associated with a large unit would bring a greater loss of revenue than deviation associated with a low-rated generating unit. The set of equations (1) (3) formulate the designated optimization problem, where t k denotes the decision variable. The objective function, (1), is to minimize the sum deviations (in MW weeks) associated with all 1148
3 units. Vector-form represented inequalities of (2) guarantee the satisfaction of weekly reliability constraints. Constraints (3) express a technical limitation referring to the fact that the maintenance outage cannot be too soon or too late with respect to the last maintenance course. n min Z = c k t k rt k (1) k=1 subject to: R n R max (2) e k t k l k (3) 3. Risk leveling method In the risk leveling method that was first introduced in [3] and [4], generating units are sorted according to their capacities; in addition, the applicable maintenance times associated with each unit are sorted according to the reliability index. Then the largest unit is selected to go on outage in the most reliable time interval. The procedure is repeated for the remaining units until the outage times of all units are appointed. A more detailed description of this algorithm is as follows: 1. Select the largest remaining unit. 2. Compute the reliability measure for all weeks of the year. 3. Assign the most reliable time interval to detach the unit under consideration. 4. If all units are scheduled, stop and publish the results. Otherwise, restart the algorithm from Step 1. It should be noted that adaptation of the most reliable time interval is subject to constraint (3). For instance, consider a unit detached from the grid for maintenance at the 40th week of the last year, when the time gap between 2 consecutive maintenance periods of this unit is 52 ± 5 weeks. Here, it is technically justifiable to approve any week from the 35th to 45th as the beginning of maintenance procedures. The reliability index of loss of load probability (LOLP) associated with weeks in this hypothetical power system is given in Table 1. If maintenance of this unit lasts 4 weeks, the safest 4-week long period will be the one with the lowest maximum risk within the period. In this example the best period is the one beginning from week 38 and ending in week 41, which is bolded in Table 1. Table 1. LOLP associated with weeks 35 to 48 in the hypothetical power system. Week LOLP (%) Week LOLP (%)
4 The risk leveling method, although it is very simple and fast, would lead to a nonoptimal solution, particularly from the viewpoint of GENCO economical objectives. The reason is that this algorithm emphasizes the selection of most reliable time intervals, i.e. the system reliability criterion is explicitly considered; the GENCO beneficiary preferences are not accounted for at all. Therefore, the risk leveling method is not a suitable solution for scheduling outage times in restructured systems. On the other hand, the solution would very likely be suboptimal even from the system reliability aspect because the straightforward and unintelligent risk leveling method is not strong enough for the maintenance scheduling, which is, mathematically, a nonconvex, large-scale, mixed-integer, and nonlinear optimization problem with a series of intertemporal constraints. It is often possible to attain better results by using other optimization methods at the expense of longer computation time. 4. Dynamic programming A dynamic programming solution to the maintenance scheduling problem can be formulated in various forms. The form presented here is the one suitable for merger with the risk leveling algorithm above. In order to solve the maintenance scheduling problem using a dynamic programming method, the reliability measure of the system is considered the system state. There is one decision to make associated with each unit which specifies the week for starting the maintenance process. Having influenced system reliability, that decision at the current stage determines the system state at the next stage. Since there is one decision per unit, the number of required stages in dynamic programming is equal to the number of generating units. To update the system state after every stage, the effect on the system LOLP of the maintenance outage of unit k at time interval t k is calculated as R(t k ). This value is then added to the last stage LOLP value to form the LOLP index at the present stage. That is, k R k = R k 1 + R (t k ) = R 0 + R(t i ) (4) i=1 To avert schedules violating the system reliability constraints, a penalty function is defined as (5): pf (R k ) = { 0, Rk R max, otherwise (5) If the system generating units are arranged based on their capacities, the largest unit has index 1, whereas the smallest unit corresponds to index n. Then the dynamic programming method can be used to solve the optimization problem by applying the following recursive formula: f k (R k 1 ) = min [c k t k rt k + pf (R k 1 + R(t k )) (R k 1 + R(t k ))] (6) e k t k l k where f 1 (R 0 ) gives the minimum deviation in the optimal solution. The inherent pitfall in the dynamic programming method is that the computation burden dramatically increases as a function of the number of state variables. Owing to the many imaginable states of system reliability in 52 weeks of a year, the volume of computation would be cumbersome; this leads to the inapplicability of the dynamic programming method to practical implementation. 1150
5 5. The proposed method In this section a novel method for the maintenance scheduling of generating units is proposed. This technique is indeed a hybrid version of both risk leveling and dynamic programming approaches. As discussed in section 2, the main idea behind the new model refers to the role of unit capacity in the evaluation of scheduling deviation. This issue also forms the basis for the optimization methodology, which will be discussed following of this section. Reliability constraints, (3), prevent the ISO from accepting all maintenance outage requests with no alteration. After acceptance of 1 or a few unit proposals, it may become impossible to confirm other requests because of the affected system reliability. Therefore, the ISO has to choose among units. Evidently, minimizing the deviation of larger units corresponds to lower GENCO losses. It makes sense that larger units are thus given higher priority for the requested maintenance times. For the sake of illustration, suppose that a 20 MW unit requires 1 week for maintenance while a 400 MW unit requires a 4-week maintenance outage. Both units have submitted week 35 as the requested time for the maintenance commencement. However, because of reliability constraints, the ISO can only approve one of these requests. Therefore, one unit must necessarily go through the maintenance operation after the other. If the request of the 20 MW unit for maintenance at week 35 is granted, maintenance of the 400 MW unit is put off until week 36, i.e. just after the small unit reconnection. In this case, the total deviation would be 400 MW weeks. The reverse allocation of outage times, i.e. maintenance of the 400 MW unit at week 35 and outage of the 20 MW unit at week 39, brings about only a 80 MW week deviation. This observation might not generally be the case, particularly when units do not have such different capacities. For instance, instead of the 20 MW unit above, consider a 350 MW unit that requires 3 weeks for the maintenance. Rejecting the outage request of the 350 MW unit in favor of the 400 MW unit imposes = 1400 MW week deviation, while accepting the outage request of the 350 MW unit results in = 1200 MW week deviation. Considering other factors such as the effect of unit maintenance on system reliability, which in turn depends on the capacity of the unit under maintenance, forced outage rate (FOR) of the unit, and duration of maintenance, among other things, it is obvious that determination of the optimum sequence of GENCO maintenance requests is not an easy task. Either a large number of combinations must be analyzed and compared, or a heuristic intelligent search method or classical optimization programming technique should be employed. The comprehensive search method is not commonly employable, as the number of combinations is intractable even in small-scale systems. The classical mathematical programming methods are not directly applicable either, because the reliability measure cannot be explicitly expressed in terms of problem variables, and a postprocessing computation should be followed. Accordingly, in this paper a heuristic and hybrid optimization method is developed. The new method is an iterative process, and the system generating units are classified into 3 categories associated with each iteration phase: 1. Scheduled units: Units whose outage times have been decided in earlier iterations. This set is empty at the first iteration and is expanded as the algorithm goes forward. 2. Dynamic units: Units whose optimum outage time is being determined by the dynamic programming technique. In fact, various combinations of these units are examined in order to find the optimum combination. The number of units in this group is adjusted based on computational capability and should not lead to an intractable computation burden. At a minimum, the 2 largest units in the unscheduled units should be accounted for. After each iteration some of the dynamic units are transferred to the 1151
6 category of scheduled units and replaced by some directed units on top of the list. 3. Directed units: Units that do not belong to the above categories. The risk leveling method determines the outage times of directed units merely to discoverer whether there is an acceptable combination of outage times for these units. Upon completion of each iteration and movement of some dynamic units to the scheduled group, some of the direct units are transferred to the dynamic unit category. As a general rule, the algorithm moves some units from one category to another after each iteration. Units of the same size should be moved together between categories. The proposed procedure is as follows: 1. Sort units according to their capacities in descending order so that the largest generating unit is labeled unit 1 and the smallest generating unit is called unit n. 2. Let the units whose outage times have been determined earlier lie in the category of scheduled units. 3. From the remaining unscheduled units, choose 2 or more of the largest as dynamic units. The remaining units belong to the category of directed units. 4. Compute f k (R k 1 ) as follows: (a) If unit k belongs to the category of scheduled units, calculate f k using (7). Note that t k is known for this type of unit. f k (R k 1 ) = c k t k rt k + f k+1 (R k 1 + R(t k )) (7) (b) If unit k belongs to the category of dynamic units, calculate f k using (6). (c) If unit k belongs to the category of directed units, find the maintenance outage time, t k, using the risk leveling algorithm; thereafter, calculate f k by: f k (R k 1 ) = c k t k rt k + f k+1 (R k 1 + R(t k )) + pf (R k 1 + R (t k )) (8) where pf(r k 1 + R (t k )) and t k are computed by (5) and the risk leveling algorithm, respectively. 5. Transfer the largest unit(s) in the category of dynamic units to the category of scheduled units. Additionally, the time specified in this iteration is considered the outage time for the transferred units. 6. Repeat the algorithm from Step 3 until all units lie in the category of scheduled units. The point deserving special emphasis is that by limiting the number of units in the category of dynamic units and reducing the number of possible combinations, a remarkable saving in CPU time is achieved. The rational reason behind the proposed algorithm is that there is no need to deal with all combinations of units at a single stage. It is more efficient to make decisions about larger units without engaging in the details associated with smaller ones. Another benefit of the newly devised methodology is that, depending on the computational power and allowable execution time, the analyst is able to govern the calculation burden through the number of units being handled in the category of dynamic units. At the same time, the production of unsatisfactory combinations can be avoided by examining whether or not any feasible solution exists for smaller units (Step 4.c). To this end, one can deduce that using (8) and owing to the system reliability constraints, it is verified that the intended combination of the dynamic units does not deprive smaller units in the category of directed unit from maintenance outages. In other words, unfeasible combinations would be omitted automatically and in an intelligent manner. 1152
7 6. Case study In this section the IEEE-RTS [6] is examined to demonstrate the efficiency of the proposed algorithm. The implementation and simulations have been carried out in the MATLAB environment [7]. The set of generating units in the IEEE-RTS includes various nuclear, fossil-fueled, and hydro units ranging from 12 MW to 400 MW capacities. The units are partitioned and under the ownership of 3 GENCOs: A, B, and C. Table 2 outlines the GENCO units and the maintenance outage requests submitted to the ISO. The technically allowable time interval for the maintenance outage commencement is 52 ± 5 weeks of the previous year s outage. The generation system LOLP is adopted as the monitored reliability constraint, and it is supposed to be held below 1% for all weeks save the last 5 weeks of the year. Table 2. GENCO units and their associated outage requests submitted to the ISO. GENCO A GENCO B GENCO C Unit Cap Week Unit Cap Week Unit Cap Week Cap = capacity [MW]. In order to solve the maintenance scheduling problem, as shown in Table 3, the units are first sorted with respect to their capacities. In the first iteration the set of scheduled units is empty. Thus, units associated with the 3 largest capacities (400 MW, 350 MW, and 197 MW units) are assumed as the set of dynamic units, and the remaining group is labeled directed units. Thus, the category of scheduled units is empty, the category of dynamic units consists of 6 units, and the direct category encompasses 26 generating units. Technically speaking and owing to the minimum and maximum time distance of the maintenance operation with the last course, if 10 different possibilities are examined for each dynamic unit, a maximum of 1,000,000 combinations have to be examined. By applying the risk leveling method, a schedule for the 26 remaining units is determined for each of these 1,000,000 combinations. Unacceptable schedules, namely those leading to the violation of reliability constraints, are rejected; acceptable ones are kept as candidates for the optimal schedule. The result of the first iteration is outlined in Table 4. In the next iteration, two 400 MW units are moved to the category of scheduled units, and their associated outage times are fixed on the obtained solution at the first iteration. Accordingly, weeks 10 and 34 are adopted for units 1 and 2, respectively. Additionally, the 155 MW units are placed in the dynamic unit category. Hence, the numbers of generating units in the categories of scheduled, dynamic, and directed units are, respectively, 1153
8 Table 3. Generating units listed in order of capacity. Unit Cap LYO RW Cap = capacity [MW], LYO = last year outage, RW = requested week. Table 4. First iteration results of the proposed method: 400 MW, 350 MW, and 197 MW units in the category of dynamic units Total deviation: 7754 MW weeks Unit Cap Dev RW Acc AW YES NO YES NO YES NO NO NO NO NO 16 Cap = capacity [MW], Dev = deviation, RW = requested week, Acc = accepted or not, AW = alternative week.
9 2, 8, and 22 associated with the second iteration. The results obtained in the second iteration are presented in Table 5. Table 5. Second iteration results of the proposed method: 350 MW, 197 MW, and 155 MW units in the category of dynamic units. Total deviation: 7754 MW weeks Unit Cap Dev RW Acc AW YES NO YES NO NO NO NO NO NO NO 36 Cap = capacity [MW], Dev = deviation, RW = requested week, Acc = accepted, AW = alternative week. Since the outage time of the 350 MW unit is established at the third iteration, this unit leaves the dynamic unit category, and three 100 MW units enter. At this iteration, various combinations of 197 MW, 155 MW, and 100 MW are examined for determination of the maintenance schedule. This procedure goes forward until, at the last iteration, various combinations of 50 MW, 20 MW, and 12 MW units are inspected in the category of dynamic units, and the algorithm is terminated. In this last iteration the directed unit category is empty since all units are processed, and their maintenance times are determined. At this stage the algorithm turns into ordinary dynamic programming. The reliability index for 52 weeks of the year is updated incorporating the maintenance outages of 17 larger units; thereafter, various combinations of the 15 smaller units are examined to find the optimum schedule. The final solution is given in Table 6. As observed, the scheduled maintenance outage times of all units lie within the declared allowable interval, i.e. 52 ± 5 weeks from the previous year s outage. 7. Comparing the proposed method with other techniques In the literature a variety of methods have been used or devised to solve the maintenance scheduling problem [8]. They differ both in unit maintenance scheduling procedure and in the algorithm utilized to find the optimum solution. A few other algorithms are briefly introduced in this section, and a comparison between the proposed algorithm and these alternative algorithms is given. Employing the proposed algorithm, the CPU execution time on a 1.5 GHz Intel Celeron processor is about 2 h for the maintenance scheduling of the IEEE-RTS generation system. The proposed method generates a schedule with 5801 MW week total deviation from the requested outage times. The system average LOLP, incorporating the effect of maintenance outages, is about 0.75%. For the sake of comparison, the problem is solved using the individual risk leveling method as well. The computation time elapsed is negligible against that of the hybrid algorithm; however, the introduced deviation equals 8007 MW weeks, which is much greater than the 5801 MW weeks of the hybrid method. Considering the scheduled outages, the system average LOLP was about 0.72%. Based on the aforementioned explanations, it can 1155
10 Table 6. The final solution: maintenance outage schedule of all generating units. Total deviation: 5801 MW weeks Unit GENCO Cap Dev RW Acc AW 1 B YES - 2 C NO 34 3 C YES - 4 B NO 32 5 C YES - 6 C NO 14 7 A NO 40 8 B NO 6 9 B NO B NO A YES - 12 B NO B YES - 14 A YES - 15 A NO B NO 8 17 C NO 7 18 A NO A NO A NO B NO B NO C NO A YES - 25 A YES - 26 A YES - 27 C NO A YES - 29 A NO A NO C YES - 32 C NO 39 Cap = capacity [MW], Dev = deviation, RW = requested week, Acc = accepted, AW = alternative week. be deduced that the risk leveling method cannot solely be an effective solution for the maintenance scheduling in multiagent restructured electric power systems. Although it is very fast and has a trivial computational load, this method does not consider GENCO preferences and results in very large deviations from the requested maintenance schedules. Some research has utilized mixed integer linear programming (MILP) to solve the maintenance scheduling problem. In order to apply this powerful optimization programming, it is a prerequisite to express the objective function and all constraints in a linear fashion. To this end, a simple reliability index was used. In [9], the ratio of the net reserve to the gross reserve is used as an index to measure system reliability. Since the proposed method in this paper exploits dynamic programming as the core algorithm, no specific limitations regarding the objective function or constraint form are imposed. Hence, LOLP, which accurately reflects system reliability, is used as the reliability index. 1156
11 Nonlinear constraints and objective functions in the maintenance scheduling problem have led to increasing implementation of artificial intelligence methods to solve the problem in [5] and [10] [12]. Among these methods, genetic algorithm is the most popular. Genetic algorithm mainly relies on random mutations and crossovers between best candidates in every generation, hoping that the offspring will be better than the parents, and that an evolution will occur after several stages. Random mutations are a means to explore more possible solutions and avoid a suboptimal outcome. When the number of units increases, either larger populations or more mutations must be used to sufficiently cover the search space, and this requirement dramatically increases the computation time. Therefore, the main issue impeding the application of genetic algorithm in the maintenance scheduling problem is that it is a very time consuming process, particularly when the problem dimension is rather large, which is the case here. In contrast to the genetic algorithm, in the proposed method the search space is limited, and a large number of possible solutions are enumerated in a systematic manner. Along with some hybrid methods devised to improve the genetic algorithm performance such as [11] and [12], an idea similar to what we have applied here to dynamic programming could be utilized to accelerate the evolution process of genetic algorithms. That is, at the beginning stages of optimization the focus should be on genes associated with larger units. After achieving a set of best combinations for these units, the optimization of other genes representing smaller units is initiated. This approach might result in convergence in a shorter time; however, further research should be devoted to this subject. Another method applied to the maintenance scheduling problem is dynamic programming [13]. major drawback associated with this technique is the excessive computation burden, particularly in large-scale systems. For the numerical example investigated in this paper any attempt to solve the problem solely with the dynamic programming method failed due to the cumbersome computational effort. The proposed method is an effort to improve dynamic programming by limiting the search space. The 8. Conclusions A novel methodology for coordinating GENCO outage requests by ISOs was introduced in this paper. Using this technique, in addition to maintaining the system weekly reliability indices below prespecified thresholds, the deviation of the final solution from GENCO proposals was minimized in order to lessen GENCO profit losses. The new algorithm is a hybrid optimization technique based on concurrent utilization of dynamic programming and risk leveling methods. The proposed method is applicable in restructured environments as it takes the reliability criteria into consideration while respecting the interests of GENCOs. Classifying generating units into scheduled, dynamic, and directed units restricts the dimension of dynamic programming to just a few units. This attribute, as shown in the numerical studies, makes the developed model tractable within a reasonable execution time. Furthermore, by adjusting the number of dynamic units, the overall execution time can be governed. Nomenclature c k capacity of unit k d k duration of maintenance outage of unit k e k earliest applicable time to begin maintenance outage of unit k ik generating unit indices l k latest applicable time to begin maintenance outage of unit k n number of units requesting maintenance outages rt k outage time of unit k requested by the relevant GENCO 1157
12 R 0 R k R max t k vector of weekly LOLP index before maintenance scheduling vector of weekly LOLP index considering maintenance outage of units 1, 2,..., k in various weeks vector of maximum acceptable weekly LOLP outage time of unit k assigned by ISO R (t k ) vector representing the effect on weekly LOLP of maintenance outage associated with unit k from weeks t k to t k + d k References [1] N. Mohammadi Tabari, A new approach for maintenance scheduling in restructured power systems, PhD Dissertation, Science and Research Branch of Azad University, Tehran, Iran, [2] M. Shahidehpour, M. Marwali, Maintenance Scheduling in Restructured Power Systems, Massachusetts, USA, Kluwer Academic Publishers, [3] H. Khatib, Maintenance scheduling of generating facilities, IEEE Transactions on Power Apparatus and Systems, Vol. 98, pp , [4] R. Billinton, A. Abdulwhab, Short-term generating unit maintenance scheduling in a deregulated power system using a probabilistic approach, IEE Proceeding on Generation, Transmission, and Distribution, Vol. 150, pp , [5] Y. Wang, E. Handschin, Unit maintenance scheduling in open systems using genetic algorithm, IEEE Transmission Distribution Conference, Vol. 1, pp , [6] R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L. Goel, E. Khan, P. Kos, G. Nourbakhsh, J. Oteng- Adjei, A reliability test system for educational purposes-basic data, IEEE Transactions on Power Systems, Vol. 4, pp , [7] last access date: , Matlab. [8] G. Lu, F. Wen, C.Y. Chung, K.P. Wong, Generation unit maintenance scheduling in electricity market environment, Third International Conference on Electric Utility Deregulation and Restructuring and Power Technologies, pp , [9] A.J. Conejo, R. Garcia-Bertrand, M. Diaz-Salazar, Generation maintenance scheduling in restructured power systems, IEEE Transactions on Power Systems, Vol. 20, No. 2, pp , [10] R. Eshraghnia, M.H.M. Shanechi, H.R. Mashhadi, Generation maintenance scheduling in power market based on genetic algorithm, Power Systems Conference and Exposition, pp , [11] N. Kumarappan, P. Suriya, Hybrid GA/SA based generation maintenance scheduling with line flow constraints in power market, Joint International Conference on Power Electronics, Drives, and Energy Systems, pp. 1 8, [12] J. Shu, L. Zhang, B. Han, X. Huang, Global generator and transmission maintenance scheduling based on a mixed intelligent optimal algorithm in power market, International Conference on Power System Technology, pp. 1 5, [13] T.N. Mohammadi, S.B. Hassanpour, S.A. Hassanpour, M. Pirmoradian, A new approach for generation maintenance scheduling in a deregulated power system, IEEE TENCON, pp. 1 5,
International Journal of Software and Web Sciences (IJSWS) www.iasir.net
International Association of Scientific Innovation and Research (IASIR) (An Association Unifying the Sciences, Engineering, and Applied Research) ISSN (Print): 2279-0063 ISSN (Online): 2279-0071 International
A Genetic Algorithm Approach for Solving a Flexible Job Shop Scheduling Problem
A Genetic Algorithm Approach for Solving a Flexible Job Shop Scheduling Problem Sayedmohammadreza Vaghefinezhad 1, Kuan Yew Wong 2 1 Department of Manufacturing & Industrial Engineering, Faculty of Mechanical
CHAPTER 3 SECURITY CONSTRAINED OPTIMAL SHORT-TERM HYDROTHERMAL SCHEDULING
60 CHAPTER 3 SECURITY CONSTRAINED OPTIMAL SHORT-TERM HYDROTHERMAL SCHEDULING 3.1 INTRODUCTION Optimal short-term hydrothermal scheduling of power systems aims at determining optimal hydro and thermal generations
HYBRID GENETIC ALGORITHMS FOR SCHEDULING ADVERTISEMENTS ON A WEB PAGE
HYBRID GENETIC ALGORITHMS FOR SCHEDULING ADVERTISEMENTS ON A WEB PAGE Subodha Kumar University of Washington [email protected] Varghese S. Jacob University of Texas at Dallas [email protected]
A Binary Model on the Basis of Imperialist Competitive Algorithm in Order to Solve the Problem of Knapsack 1-0
212 International Conference on System Engineering and Modeling (ICSEM 212) IPCSIT vol. 34 (212) (212) IACSIT Press, Singapore A Binary Model on the Basis of Imperialist Competitive Algorithm in Order
A Reactive Tabu Search for Service Restoration in Electric Power Distribution Systems
IEEE International Conference on Evolutionary Computation May 4-11 1998, Anchorage, Alaska A Reactive Tabu Search for Service Restoration in Electric Power Distribution Systems Sakae Toune, Hiroyuki Fudo,
Revenue Management for Transportation Problems
Revenue Management for Transportation Problems Francesca Guerriero Giovanna Miglionico Filomena Olivito Department of Electronic Informatics and Systems, University of Calabria Via P. Bucci, 87036 Rende
A Brief Study of the Nurse Scheduling Problem (NSP)
A Brief Study of the Nurse Scheduling Problem (NSP) Lizzy Augustine, Morgan Faer, Andreas Kavountzis, Reema Patel Submitted Tuesday December 15, 2009 0. Introduction and Background Our interest in the
A Hybrid Tabu Search Method for Assembly Line Balancing
Proceedings of the 7th WSEAS International Conference on Simulation, Modelling and Optimization, Beijing, China, September 15-17, 2007 443 A Hybrid Tabu Search Method for Assembly Line Balancing SUPAPORN
A Shift Sequence for Nurse Scheduling Using Linear Programming Problem
IOSR Journal of Nursing and Health Science (IOSR-JNHS) e-issn: 2320 1959.p- ISSN: 2320 1940 Volume 3, Issue 6 Ver. I (Nov.-Dec. 2014), PP 24-28 A Shift Sequence for Nurse Scheduling Using Linear Programming
XOR-based artificial bee colony algorithm for binary optimization
Turkish Journal of Electrical Engineering & Computer Sciences http:// journals. tubitak. gov. tr/ elektrik/ Research Article Turk J Elec Eng & Comp Sci (2013) 21: 2307 2328 c TÜBİTAK doi:10.3906/elk-1203-104
Solving Method for a Class of Bilevel Linear Programming based on Genetic Algorithms
Solving Method for a Class of Bilevel Linear Programming based on Genetic Algorithms G. Wang, Z. Wan and X. Wang Abstract The paper studies and designs an genetic algorithm (GA) of the bilevel linear programming
International Journal of Advanced Research in Electrical, Electronics and Instrumentation Engineering
DOI: 10.15662/ijareeie.2014.0307061 Economic Dispatch of Power System Optimization with Power Generation Schedule Using Evolutionary Technique Girish Kumar 1, Rameshwar singh 2 PG Student [Control system],
Chapter 13: Binary and Mixed-Integer Programming
Chapter 3: Binary and Mixed-Integer Programming The general branch and bound approach described in the previous chapter can be customized for special situations. This chapter addresses two special situations:
Memory Allocation Technique for Segregated Free List Based on Genetic Algorithm
Journal of Al-Nahrain University Vol.15 (2), June, 2012, pp.161-168 Science Memory Allocation Technique for Segregated Free List Based on Genetic Algorithm Manal F. Younis Computer Department, College
M. Sugumaran / (IJCSIT) International Journal of Computer Science and Information Technologies, Vol. 2 (3), 2011, 1001-1006
A Design of Centralized Meeting Scheduler with Distance Metrics M. Sugumaran Department of Computer Science and Engineering,Pondicherry Engineering College, Puducherry, India. Abstract Meeting scheduling
Introduction To Genetic Algorithms
1 Introduction To Genetic Algorithms Dr. Rajib Kumar Bhattacharjya Department of Civil Engineering IIT Guwahati Email: [email protected] References 2 D. E. Goldberg, Genetic Algorithm In Search, Optimization
Integrated support system for planning and scheduling... 2003/4/24 page 75 #101. Chapter 5 Sequencing and assignment Strategies
Integrated support system for planning and scheduling... 2003/4/24 page 75 #101 Chapter 5 Sequencing and assignment Strategies 5.1 Overview This chapter is dedicated to the methodologies used in this work
2004 Networks UK Publishers. Reprinted with permission.
Riikka Susitaival and Samuli Aalto. Adaptive load balancing with OSPF. In Proceedings of the Second International Working Conference on Performance Modelling and Evaluation of Heterogeneous Networks (HET
Research Article Service Composition Optimization Using Differential Evolution and Opposition-based Learning
Research Journal of Applied Sciences, Engineering and Technology 11(2): 229-234, 2015 ISSN: 2040-7459; e-issn: 2040-7467 2015 Maxwell Scientific Publication Corp. Submitted: May 20, 2015 Accepted: June
A Power Efficient QoS Provisioning Architecture for Wireless Ad Hoc Networks
A Power Efficient QoS Provisioning Architecture for Wireless Ad Hoc Networks Didem Gozupek 1,Symeon Papavassiliou 2, Nirwan Ansari 1, and Jie Yang 1 1 Department of Electrical and Computer Engineering
Standardization and Its Effects on K-Means Clustering Algorithm
Research Journal of Applied Sciences, Engineering and Technology 6(7): 399-3303, 03 ISSN: 040-7459; e-issn: 040-7467 Maxwell Scientific Organization, 03 Submitted: January 3, 03 Accepted: February 5, 03
Student Project Allocation Using Integer Programming
IEEE TRANSACTIONS ON EDUCATION, VOL. 46, NO. 3, AUGUST 2003 359 Student Project Allocation Using Integer Programming A. A. Anwar and A. S. Bahaj, Member, IEEE Abstract The allocation of projects to students
[Refer Slide Time: 05:10]
Principles of Programming Languages Prof: S. Arun Kumar Department of Computer Science and Engineering Indian Institute of Technology Delhi Lecture no 7 Lecture Title: Syntactic Classes Welcome to lecture
Path Selection Methods for Localized Quality of Service Routing
Path Selection Methods for Localized Quality of Service Routing Xin Yuan and Arif Saifee Department of Computer Science, Florida State University, Tallahassee, FL Abstract Localized Quality of Service
Integer Programming: Algorithms - 3
Week 9 Integer Programming: Algorithms - 3 OPR 992 Applied Mathematical Programming OPR 992 - Applied Mathematical Programming - p. 1/12 Dantzig-Wolfe Reformulation Example Strength of the Linear Programming
Compact Representations and Approximations for Compuation in Games
Compact Representations and Approximations for Compuation in Games Kevin Swersky April 23, 2008 Abstract Compact representations have recently been developed as a way of both encoding the strategic interactions
OPRE 6201 : 2. Simplex Method
OPRE 6201 : 2. Simplex Method 1 The Graphical Method: An Example Consider the following linear program: Max 4x 1 +3x 2 Subject to: 2x 1 +3x 2 6 (1) 3x 1 +2x 2 3 (2) 2x 2 5 (3) 2x 1 +x 2 4 (4) x 1, x 2
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES JULIA IGOREVNA LARIONOVA 1 ANNA NIKOLAEVNA TIKHOMIROVA 2 1, 2 The National Nuclear Research
A Service Revenue-oriented Task Scheduling Model of Cloud Computing
Journal of Information & Computational Science 10:10 (2013) 3153 3161 July 1, 2013 Available at http://www.joics.com A Service Revenue-oriented Task Scheduling Model of Cloud Computing Jianguang Deng a,b,,
INTEGER PROGRAMMING. Integer Programming. Prototype example. BIP model. BIP models
Integer Programming INTEGER PROGRAMMING In many problems the decision variables must have integer values. Example: assign people, machines, and vehicles to activities in integer quantities. If this is
When to Refinance Mortgage Loans in a Stochastic Interest Rate Environment
When to Refinance Mortgage Loans in a Stochastic Interest Rate Environment Siwei Gan, Jin Zheng, Xiaoxia Feng, and Dejun Xie Abstract Refinancing refers to the replacement of an existing debt obligation
Email: [email protected]. 2Azerbaijan Shahid Madani University. This paper is extracted from the M.Sc. Thesis
Introduce an Optimal Pricing Strategy Using the Parameter of "Contingency Analysis" Neplan Software in the Power Market Case Study (Azerbaijan Electricity Network) ABSTRACT Jalil Modabe 1, Navid Taghizadegan
A Robust Method for Solving Transcendental Equations
www.ijcsi.org 413 A Robust Method for Solving Transcendental Equations Md. Golam Moazzam, Amita Chakraborty and Md. Al-Amin Bhuiyan Department of Computer Science and Engineering, Jahangirnagar University,
SIMULATING CANCELLATIONS AND OVERBOOKING IN YIELD MANAGEMENT
CHAPTER 8 SIMULATING CANCELLATIONS AND OVERBOOKING IN YIELD MANAGEMENT In YM, one of the major problems in maximizing revenue is the number of cancellations. In industries implementing YM this is very
ECONOMIC GENERATION AND SCHEDULING OF POWER BY GENETIC ALGORITHM
ECONOMIC GENERATION AND SCHEDULING OF POWER BY GENETIC ALGORITHM RAHUL GARG, 2 A.K.SHARMA READER, DEPARTMENT OF ELECTRICAL ENGINEERING, SBCET, JAIPUR (RAJ.) 2 ASSOCIATE PROF, DEPARTMENT OF ELECTRICAL ENGINEERING,
New Hash Function Construction for Textual and Geometric Data Retrieval
Latest Trends on Computers, Vol., pp.483-489, ISBN 978-96-474-3-4, ISSN 79-45, CSCC conference, Corfu, Greece, New Hash Function Construction for Textual and Geometric Data Retrieval Václav Skala, Jan
Penalized regression: Introduction
Penalized regression: Introduction Patrick Breheny August 30 Patrick Breheny BST 764: Applied Statistical Modeling 1/19 Maximum likelihood Much of 20th-century statistics dealt with maximum likelihood
EM Clustering Approach for Multi-Dimensional Analysis of Big Data Set
EM Clustering Approach for Multi-Dimensional Analysis of Big Data Set Amhmed A. Bhih School of Electrical and Electronic Engineering Princy Johnson School of Electrical and Electronic Engineering Martin
Index tracking UNDER TRANSACTION COSTS:
MARKE REVIEWS Index tracking UNDER RANSACION COSS: rebalancing passive portfolios by Reinhold Hafner, Ansgar Puetz and Ralf Werner, RiskLab GmbH Portfolio managers must be able to estimate transaction
PROCESS OF LOAD BALANCING IN CLOUD COMPUTING USING GENETIC ALGORITHM
PROCESS OF LOAD BALANCING IN CLOUD COMPUTING USING GENETIC ALGORITHM Md. Shahjahan Kabir 1, Kh. Mohaimenul Kabir 2 and Dr. Rabiul Islam 3 1 Dept. of CSE, Dhaka International University, Dhaka, Bangladesh
Linear Programming for Optimization. Mark A. Schulze, Ph.D. Perceptive Scientific Instruments, Inc.
1. Introduction Linear Programming for Optimization Mark A. Schulze, Ph.D. Perceptive Scientific Instruments, Inc. 1.1 Definition Linear programming is the name of a branch of applied mathematics that
Optimising Patient Transportation in Hospitals
Optimising Patient Transportation in Hospitals Thomas Hanne 1 Fraunhofer Institute for Industrial Mathematics (ITWM), Fraunhofer-Platz 1, 67663 Kaiserslautern, Germany, [email protected] 1 Introduction
Multiple Linear Regression in Data Mining
Multiple Linear Regression in Data Mining Contents 2.1. A Review of Multiple Linear Regression 2.2. Illustration of the Regression Process 2.3. Subset Selection in Linear Regression 1 2 Chap. 2 Multiple
Evolutionary Detection of Rules for Text Categorization. Application to Spam Filtering
Advances in Intelligent Systems and Technologies Proceedings ECIT2004 - Third European Conference on Intelligent Systems and Technologies Iasi, Romania, July 21-23, 2004 Evolutionary Detection of Rules
Math Review. for the Quantitative Reasoning Measure of the GRE revised General Test
Math Review for the Quantitative Reasoning Measure of the GRE revised General Test www.ets.org Overview This Math Review will familiarize you with the mathematical skills and concepts that are important
Wireless Sensor Networks Coverage Optimization based on Improved AFSA Algorithm
, pp. 99-108 http://dx.doi.org/10.1457/ijfgcn.015.8.1.11 Wireless Sensor Networks Coverage Optimization based on Improved AFSA Algorithm Wang DaWei and Wang Changliang Zhejiang Industry Polytechnic College
STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL
Session 6. Applications of Mathematical Methods to Logistics and Business Proceedings of the 9th International Conference Reliability and Statistics in Transportation and Communication (RelStat 09), 21
Social Media Mining. Data Mining Essentials
Introduction Data production rate has been increased dramatically (Big Data) and we are able store much more data than before E.g., purchase data, social media data, mobile phone data Businesses and customers
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
What mathematical optimization can, and cannot, do for biologists. Steven Kelk Department of Knowledge Engineering (DKE) Maastricht University, NL
What mathematical optimization can, and cannot, do for biologists Steven Kelk Department of Knowledge Engineering (DKE) Maastricht University, NL Introduction There is no shortage of literature about the
Integrating Benders decomposition within Constraint Programming
Integrating Benders decomposition within Constraint Programming Hadrien Cambazard, Narendra Jussien email: {hcambaza,jussien}@emn.fr École des Mines de Nantes, LINA CNRS FRE 2729 4 rue Alfred Kastler BP
An Efficient load balancing using Genetic algorithm in Hierarchical structured distributed system
An Efficient load balancing using Genetic algorithm in Hierarchical structured distributed system Priyanka Gonnade 1, Sonali Bodkhe 2 Mtech Student Dept. of CSE, Priyadarshini Instiute of Engineering and
Clustering and scheduling maintenance tasks over time
Clustering and scheduling maintenance tasks over time Per Kreuger 2008-04-29 SICS Technical Report T2008:09 Abstract We report results on a maintenance scheduling problem. The problem consists of allocating
Branch-and-Price Approach to the Vehicle Routing Problem with Time Windows
TECHNISCHE UNIVERSITEIT EINDHOVEN Branch-and-Price Approach to the Vehicle Routing Problem with Time Windows Lloyd A. Fasting May 2014 Supervisors: dr. M. Firat dr.ir. M.A.A. Boon J. van Twist MSc. Contents
SINGLE-STAGE MULTI-PRODUCT PRODUCTION AND INVENTORY SYSTEMS: AN ITERATIVE ALGORITHM BASED ON DYNAMIC SCHEDULING AND FIXED PITCH PRODUCTION
SIGLE-STAGE MULTI-PRODUCT PRODUCTIO AD IVETORY SYSTEMS: A ITERATIVE ALGORITHM BASED O DYAMIC SCHEDULIG AD FIXED PITCH PRODUCTIO Euclydes da Cunha eto ational Institute of Technology Rio de Janeiro, RJ
A joint control framework for supply chain planning
17 th European Symposium on Computer Aided Process Engineering ESCAPE17 V. Plesu and P.S. Agachi (Editors) 2007 Elsevier B.V. All rights reserved. 1 A joint control framework for supply chain planning
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2 Abstract In construction scheduling, constraints among activities are vital as they govern the
LOOKING FOR A GOOD TIME TO BET
LOOKING FOR A GOOD TIME TO BET LAURENT SERLET Abstract. Suppose that the cards of a well shuffled deck of cards are turned up one after another. At any time-but once only- you may bet that the next card
Abstract Title: Planned Preemption for Flexible Resource Constrained Project Scheduling
Abstract number: 015-0551 Abstract Title: Planned Preemption for Flexible Resource Constrained Project Scheduling Karuna Jain and Kanchan Joshi Shailesh J. Mehta School of Management, Indian Institute
International Journal of Advances in Science and Technology (IJAST)
Determination of Economic Production Quantity with Regard to Machine Failure Mohammadali Pirayesh 1, Mahsa Yavari 2 1,2 Department of Industrial Engineering, Faculty of Engineering, Ferdowsi University
NEW VERSION OF DECISION SUPPORT SYSTEM FOR EVALUATING TAKEOVER BIDS IN PRIVATIZATION OF THE PUBLIC ENTERPRISES AND SERVICES
NEW VERSION OF DECISION SUPPORT SYSTEM FOR EVALUATING TAKEOVER BIDS IN PRIVATIZATION OF THE PUBLIC ENTERPRISES AND SERVICES Silvija Vlah Kristina Soric Visnja Vojvodic Rosenzweig Department of Mathematics
Optimal PID Controller Design for AVR System
Tamkang Journal of Science and Engineering, Vol. 2, No. 3, pp. 259 270 (2009) 259 Optimal PID Controller Design for AVR System Ching-Chang Wong*, Shih-An Li and Hou-Yi Wang Department of Electrical Engineering,
A Fast and Elitist Multiobjective Genetic Algorithm: NSGA-II
182 IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, VOL. 6, NO. 2, APRIL 2002 A Fast and Elitist Multiobjective Genetic Algorithm: NSGA-II Kalyanmoy Deb, Associate Member, IEEE, Amrit Pratap, Sameer Agarwal,
A Constraint Programming based Column Generation Approach to Nurse Rostering Problems
Abstract A Constraint Programming based Column Generation Approach to Nurse Rostering Problems Fang He and Rong Qu The Automated Scheduling, Optimisation and Planning (ASAP) Group School of Computer Science,
A Multi-Objective Performance Evaluation in Grid Task Scheduling using Evolutionary Algorithms
A Multi-Objective Performance Evaluation in Grid Task Scheduling using Evolutionary Algorithms MIGUEL CAMELO, YEZID DONOSO, HAROLD CASTRO Systems and Computer Engineering Department Universidad de los
Keywords: Single-vendor Inventory Control System, Potential Demand, Machine Failure, Participation in the Chain, Heuristic Algorithm
Indian Journal of Fundamental and Applied Life Sciences ISSN: 31 63 (Online) An Open Access, Online International Journal Available at www.cibtech.org/sp.ed/jls/01/03/jls.htm 01 Vol. (S3), pp. 1781-1790/Valiporian
A Fast Computational Genetic Algorithm for Economic Load Dispatch
A Fast Computational Genetic Algorithm for Economic Load Dispatch M.Sailaja Kumari 1, M.Sydulu 2 Email: 1 [email protected] 1, 2 Department of Electrical Engineering National Institute of Technology,
Constraints Propagation Techniques in Batch Plants Planning and Scheduling
European Symposium on Computer Arded Aided Process Engineering 15 L. Puigjaner and A. Espuña (Editors) 2005 Elsevier Science B.V. All rights reserved. Constraints Propagation Techniques in Batch Plants
Efficient Data Structures for Decision Diagrams
Artificial Intelligence Laboratory Efficient Data Structures for Decision Diagrams Master Thesis Nacereddine Ouaret Professor: Supervisors: Boi Faltings Thomas Léauté Radoslaw Szymanek Contents Introduction...
24. The Branch and Bound Method
24. The Branch and Bound Method It has serious practical consequences if it is known that a combinatorial problem is NP-complete. Then one can conclude according to the present state of science that no
Categorical Data Visualization and Clustering Using Subjective Factors
Categorical Data Visualization and Clustering Using Subjective Factors Chia-Hui Chang and Zhi-Kai Ding Department of Computer Science and Information Engineering, National Central University, Chung-Li,
A Tool for Generating Partition Schedules of Multiprocessor Systems
A Tool for Generating Partition Schedules of Multiprocessor Systems Hans-Joachim Goltz and Norbert Pieth Fraunhofer FIRST, Berlin, Germany {hans-joachim.goltz,nobert.pieth}@first.fraunhofer.de Abstract.
A Mathematical Programming Solution to the Mars Express Memory Dumping Problem
A Mathematical Programming Solution to the Mars Express Memory Dumping Problem Giovanni Righini and Emanuele Tresoldi Dipartimento di Tecnologie dell Informazione Università degli Studi di Milano Via Bramante
Effect of Using Neural Networks in GA-Based School Timetabling
Effect of Using Neural Networks in GA-Based School Timetabling JANIS ZUTERS Department of Computer Science University of Latvia Raina bulv. 19, Riga, LV-1050 LATVIA [email protected] Abstract: - The school
Effect of Remote Back-Up Protection System Failure on the Optimum Routine Test Time Interval of Power System Protection
Effect of Remote Back-Up Protection System Failure on the Optimum Routine Test Time Interval of Power System Protection Y. Damchi* and J. Sadeh* (C.A.) Abstract: Appropriate operation of protection system
Effect of Remote Back-Up Protection System Failure on the Optimum Routine Test Time Interval of Power System Protection
Effect of Remote Back-Up Protection System Failure on the Optimum Routine Test Time Interval of Power System Protection Y. Damchi* and J. Sadeh* (C.A.) Abstract: Appropriate operation of protection system
Long-Term Security-Constrained Unit Commitment: Hybrid Dantzig Wolfe Decomposition and Subgradient Approach
IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 20, NO. 4, NOVEMBER 2005 2093 Long-Term Security-Constrained Unit Commitment: Hybrid Dantzig Wolfe Decomposition and Subgradient Approach Yong Fu, Member, IEEE,
The Trip Scheduling Problem
The Trip Scheduling Problem Claudia Archetti Department of Quantitative Methods, University of Brescia Contrada Santa Chiara 50, 25122 Brescia, Italy Martin Savelsbergh School of Industrial and Systems
IMPROVED NETWORK PARAMETER ERROR IDENTIFICATION USING MULTIPLE MEASUREMENT SCANS
IMPROVED NETWORK PARAMETER ERROR IDENTIFICATION USING MULTIPLE MEASUREMENT SCANS Liuxi Zhang and Ali Abur Department of Electrical and Computer Engineering Northeastern University Boston, MA, USA [email protected]
A New Interpretation of Information Rate
A New Interpretation of Information Rate reproduced with permission of AT&T By J. L. Kelly, jr. (Manuscript received March 2, 956) If the input symbols to a communication channel represent the outcomes
D-optimal plans in observational studies
D-optimal plans in observational studies Constanze Pumplün Stefan Rüping Katharina Morik Claus Weihs October 11, 2005 Abstract This paper investigates the use of Design of Experiments in observational
Parallel Computing for Option Pricing Based on the Backward Stochastic Differential Equation
Parallel Computing for Option Pricing Based on the Backward Stochastic Differential Equation Ying Peng, Bin Gong, Hui Liu, and Yanxin Zhang School of Computer Science and Technology, Shandong University,
WITH the growing economy, the increasing amount of disposed
IEEE TRANSACTIONS ON ELECTRONICS PACKAGING MANUFACTURING, VOL. 30, NO. 2, APRIL 2007 147 Fast Heuristics for Designing Integrated E-Waste Reverse Logistics Networks I-Lin Wang and Wen-Cheng Yang Abstract
Optimization of Preventive Maintenance Scheduling in Processing Plants
18 th European Symposium on Computer Aided Process Engineering ESCAPE 18 Bertrand Braunschweig and Xavier Joulia (Editors) 2008 Elsevier B.V./Ltd. All rights reserved. Optimization of Preventive Maintenance
Index Terms- Batch Scheduling, Evolutionary Algorithms, Multiobjective Optimization, NSGA-II.
Batch Scheduling By Evolutionary Algorithms for Multiobjective Optimization Charmi B. Desai, Narendra M. Patel L.D. College of Engineering, Ahmedabad Abstract - Multi-objective optimization problems are
Generating Personnel Schedules in an Industrial Setting Using a Tabu Search Algorithm
Generating Personnel Schedules in an Industrial Setting Using a Tabu Search Algorithm Pascal Tellier 1 and George White 2 1 PrairieFyre Software Inc., 555 Legget Dr., Kanata K2K 2X3, Canada [email protected]
Chapter 15: Dynamic Programming
Chapter 15: Dynamic Programming Dynamic programming is a general approach to making a sequence of interrelated decisions in an optimum way. While we can describe the general characteristics, the details
This paper introduces a new method for shift scheduling in multiskill call centers. The method consists of
MANUFACTURING & SERVICE OPERATIONS MANAGEMENT Vol. 10, No. 3, Summer 2008, pp. 411 420 issn 1523-4614 eissn 1526-5498 08 1003 0411 informs doi 10.1287/msom.1070.0172 2008 INFORMS Simple Methods for Shift