A forecasting model of the economic efficiency of data centre construction project
|
|
|
- Rosamund Gallagher
- 9 years ago
- Views:
Transcription
1 A forecasting model of the economic efficiency of data centre construction project Abstract V Grekul*, L Baydalina National Research University Higher School of Economics, 20 Myasnitskaya Ulitsa, Moscow, , Russia Received 1 June 2014, wwwtsilv Today, a data centre is the main instrument for providing flexible, scalable IT services to business on the basis of distributed or cloud computing technologies Building a data centre is always expensive and resource-intensive project Therefore, during the development of the concept of this project it is extremely important to estimate accurately its economic efficiency This article represents the model for the analysis of the effectiveness of investment in the data centre construction Our model comprises several regressions that show correlations between main characteristics of the project (capital and operational expenditures, Net Present Value) and parameters of the data centre under construction (data centre area and the number of racks) The model is based on the results of the analysis of the current state and trends in the data centre market in Russia Keywords: datacentre, price, project, CAPEX, OPEX 1 Introduction The problem of forecasting a capital expense to build and an operating expense to run and maintain a data centre attracts attention of many experts and organizations In recent years a variety of activities were aimed at developing methodologies and tools for solving this problem [1-5] However, they do not take into account the specifics of the Russian market, and usually do not estimate potential revenue of the data centre In our work we collected and systematized the information about the construction and operation of more than 70 data centres in Russia On this basis we have developed the model for preliminary evaluation of the data centre creation project We presume that any evaluation of the effectiveness of investment consists of comparing the income from the use of the system with the cost of its implementation and support Integrated view on the costs of creating and supporting data centre can be obtained on the basis of TABLE 1 Data of projects of datacentres construction valuation technique Total Cost of Ownership (TCO) [6], which highlights all costs that arise both during the data centre creation and while providing services to consumers Assessing the income of data centre one should take into account features of pricing, as well as the current status and trends in the structure of services provided The final step in the assessment is the discounting of possible cash flows of the data centre project that allows to determine the effectiveness of investment by calculating the most common indicators of Net Present Value (NPV) and Internal Rate of Return (IRR) Initial data for this model were collected from publications, materials of analytical studies and from database "SPARK-Interfax» (SPARK Professional market and company analysis system) A fragment of original table that contains data about 77 projects is listed in Table 1 Missing project data are marked by "-" Company Year City Costs Area, sq m Technical Number of Power Tier area, sq m racks MW level Irkutskenergosvyaz 2014 Irkutsk 25 BN RUR Government of Chelyabinsk region 2014 Chelyabinsk M RUR Vimpelcom 2013 Yaroslavl 4 BN RUR Rostelecom 2013 Moscow 30 M USD sert Inoventica 2012 Vladimir region 90 M RUR ,45 3 Rostelecom 2012 Stavropol Elektronnaya Moscva 2012 Moscow 1145 M RUR UTK M RUR ,5 - М1, Stack 2007 Moscow 15 M RUR Technogorod 2007 Moscow NCA = 10 M RUR * Corresponding author grekoul@hseru 261
2 Cost, USD COMPUTER MODELLING & NEW TECHNOLOGIES (6) As can be seen from this fragment, project data are often incomplete: for example, information can be available about capital expenses and area of datacentre, but there can be no data about quantity of racks In this case it is possible to use relations identified from the market research performed by iks-consulting company (2012): the ratio of the area of datacentre and quantity of racks is usually 35 sq m per rack In some projects in the "cost" column we can meet acronym NCA This means that the cost of the project was not disclosed, but the analysis of the data from the SPARK-Interfax allowed to detect an increase in the cost of Non-Current Assets (NCA) during construction of the data centre As a result, we used different sets of projects to develop different models presented in the article Prices were transferred to a common currency (US dollars), and to the level of prices of 2013 using the index of prices for machinery and equipment used in the construction [7] 2 Estimation of the cost of data centre construction The expenditure part of the project includes the capital and operating costs Summarizing research materials about the cost structure [3, 8-11] we recorded the following components of the data centre construction cost: 1 Construction of the building (~ 10-15%) 2 Electrical power input (~ 20-25%) 3 Diesel Generating Set (DGS) (~ 0-5%) 4 Optical cable (~ 0-5%) 5 Service equipment (~ 60-65%) (Uninterruptible power supply, cooling system, raised floor, networking equipment, etc) To construct a regression model of the data centre construction cost we have collected and processed data of 77 data centres This data included the following parameters: data centre location (Moscow / St Petersburg /other Regions of the Russian Federation), year of construction, data centre space, number of racks, total cost of construction, Tier level In the analysis were included data centres of the most popular in Russia Tier 3 level To estimate the cost of the construction we selected the following indicators as the basic parameters of a data centre: Planned space of a data centre (S) Expected number of racks (N) Then the value of CAPEX (CAPital EXpenditure) can be defined by the following relations obtained in the form of regression models (for all projects in Russia) Dependence of CAPEX on the data centre area: Characteristics of the regression model: R2 = 072, P- value for S is 473E-11 P -value for the free variable 076 This means that, despite the fact that the cost of construction (CAPEX) is negative when datacentre area is smaller than 129 sq m, this coefficient is not significant statistically At the same time, such a small P- value for the coefficient S allows us to state with confidence that the cost of construction per sq m lies between dollars (with a standard error of $ 2339) This result correlates well with the experts estimations of CAPEX: thousand dollars per 1 sq m (iks-consulting company (2012)) Figure 1 shows the model in a graphical form Real cost, USD Forecasted cost, USD FIGURE 1 The regression model of dependence of CAPEX on the area of data centre 262
3 Cost, USD COMPUTER MODELLING & NEW TECHNOLOGIES (6) Dependence of CAPEX on the on the quantity of racks in the data centre: Characteristics of regression model: (R2 = 08, P- value for N is 201E-13 P-value for the free variable is 067) The cost of construction per one rack lies between USD (with the standard error equals to $6757) The resulting cost of construction per one rack is about 35 times more than the cost of construction per one sq m of a data centre area It is practically equal to the ratio adopted in marketing research Figure 2 shows the model in a graphical form Real cost, USD Forecasted cost, USD FIGURE 2 The regression model of dependence of CAPEX on the quantity of racks Separate regression models for groups of data, For other regions of Russian Federation we have got: classified by location of a data centre, were also formed For Moscow city we have got: Characteristics of regression model: R2 = 07, P-value for S is 0002 Characteristics of regression model: R2 = 077, P- value for N is Characteristics of regression model: R2 = 088, P- value for S is 793E-09 Characteristics of regression model: R2 = 099, P- value for N is 538 E-17 Deviations of calculated data from the average values of the entire sample are shown in Table 2 TABLE 2 Cost of building data centre in geographical segmentation Location of a datacentre Moscow Regions Russia Average cost of construction of 1 sq m (total CAPEX of sample / total S) Average cost of construction of 1 rack (total CAPEX of sample / total N) The forecasted cost of construction per 1 sq m The forecasted cost of construction per1 rack Confidence interval for the forecasted cost of construction per1 sq m Confidence interval for the forecasted cost of construction per1 rack Average datacentre area Average quantity of racks Deviation of the cost of construction per 1 sq m 13% 14% -1% Deviation of the cost of construction per 1 rack 16% 11% -2% Due to the lack of representativeness of the sample it was not possible to include in the regression model such parameters as the Tier level and creation time The influence of the Tier level on the cost of a data centre construction can be represented by multiplying the value of obtained CAPEX by the correction coefficient 263
4 (Cc) which values were obtained on the basis of research [12]: Cc = 08 for the Tier 2 level, Cc = 1 for the Tier 3 level, Cc = 18 for the Tier 4 level To take into account the effect of time on the cost it is possible to use the research results presented in [21] It shows that the construction cost of 1 square meter increases by about 30% per year Thus, the cost of building of a data centre in the year G may be defined by the relation: 3 Estimation of the cost of data centre operation There is a considerable difference in the structure of operating costs of Russian [3, 13-15] and overseas data centres [2, 12] (see Figure 3) 8% 5% 9% 19% 11% 15% 24% 20% 10% 15% 7% 16% 36% 36% 25% 35% 42% 17% 9% 19% 40% 40% 25% 25% 15% 5% 30% 42% Croc APC Datadome СNews AboutDC Radius Group Eletrical energy Personnel Rent Technical support Power system Other The differences in OPEX (OPerational EXpenditure) structure are caused by different approaches to clustering subgroups of operating costs, as well as the specifics of the Russian economy (in particular, the difference in wages, energy costs, etc) However, every research includes energy costs, rent, staff and technical support in the cost of data centre operation Other subgroups of operating costs can vary considerably and for our purposes they are integrated into the group of "other expenses" We assume that the operating costs are divided into 5 groups: 1 Electricity payments (~ 40-45%) 2 Rent (~ 15-20%) 3 The salary fund (~ 25-30%) 4 Technical support (~ 10-15%) 5 Other costs (~ 10-15%) (equipment depreciation, insurance, etc) Now operating costs can be calculated on the basis of such indicator as data centre power: we can estimate the FIGURE 3 Structure of a data centre operational expenditures operating costs by defining the cost of electricity consumed Analytical materials include very different estimations of the share of electricity in operating costs: from 25% to 45% We have analysed the financial statements of a number of data centres and have chosen the value 42% as the most acceptable estimate If the project determines the number and capacity of racks in the data centre, the calculation of the consumed energy is trivial But in this case it is necessary to take into account the distribution of energy consumption in data centres (Figure 4) The analysis of the information about the structure of the electricity consumption in some data centres [2, 12, 14] showed that all data centre racks consume about half of the total electricity This means that all data centre racks consume electricity, which makes about 21% of all operating costs At the moment racks for 42 U with 5 kw power are the most popular but the cost of 1 kw of energy in different regions is very different 264
5 60% 55% 50% 57% 40% 30% 33% 30% 27% 34% 20% 10% 0% 18% 9% 10% 5% 5% 6% 3% 3% 1% 1% APC Датадом AboutDC However, if the early stage of the project does not include definitions of equipment specifications, estimation of the power should be performed on the basis of statistical data To forecast the data centre capacity (M, MW / h) we built a regression model identifying the relationship between this index and basic characteristics of a data centre (space and the number of racks): 400 Chiller IT equipment UPS Air conditioning system Power Distribution Units Air humidifier Lighting system FIGURE 4 Distribution of energy consumption in the data centres Characteristics of regression model: R 2 = 093, P- value for N is 661Е-16 Characteristics of regression model: R 2 = 066, P- value for S is 228Е-07 Figures 5 and 6 present these models in a graphical form Real power capacity, MW Predicted power capacity, MW FIGURE 5 Regression model of dependence of datacentre power consumption on the amount racks 265
6 Real power capacity, MW Predicted power capacity, MW FIGURE 6 Regression model of dependence of the datacentre power consumption on the area To obtain more accurate results it is better to use the number of racks (N) Proceeding from the previous analysis of the structure of the operating costs, an estimation of the value of OPEX (during the year) may be performed using the following relations: [ ] [ ],, where e is the cost of electricity, $ / kw / h It is necessary to note that the price of energy differs in different regions of Russia is and this will lead to a certain error in estimation Degree of conformity between calculated and actual values of operating costs is illustrated for several Russian data centres in Table 3, TABLE 3 Comparison of actual and calculated data centre operating costs Data centre Safedata ОBIT Parkingru ОРЕХ/racks deviation 31% 34% 14% ОРЕХ/sqm deviation 9% 31% 14% For modelling future cash flows we should take into account changes in the prices of the main components of operating costs In particular, in case of constant parameters of capacity, electricity payment costs will rise according to electricity prices, payroll - according to the real wages, etc Deep analysis requires not only consideration of the cost structure, but also assessment of the dynamics of changes in the future This requires understanding of how prices will vary for each subgroup of costs (as the number in each group will have the same characteristics if data centre doesn t change) So, we use the following forecasts of the Ministry of Economic Development [16] (Figure 7) 266
7 We constructed the forecast of the structure of operating costs, using the following assumptions: The base year (average year in used researches) The original structure of operating costs is calculated as the average result of used researches Personnel costs increase in proportion to the growth of real wages The cost of electricity is rising in proportion to the price of electricity for all consumers The cost of renting the building increases in proportion to the growth of prices in construction market 30% Real wages Rising of electricity prices Inflation Construction FIGURE 7 Forecast of macro economical indicators, % All other costs are rising in proportion to the average annual inflation rate The result is the forecast presented in Figure 8 As can be seen, the overall structure of operating costs does not change significantly, but we can note the increase of the share of energy costs and reducing of the share of personnel costs in the total cost These data can be used in the process of specification of forecasted costs As a generalized estimation of future changes in operating costs, it is possible to use the weighted average of the growth rate of operating costs equal to 6% 25% 20% 15% 10% 5% Payments for electricity Staff Space rental Technical service Power supply systems Others FIGURE 8 Forecast of changes in the structure of operating costs 267
8 The average annual growth of the components of operating costs was determined using forecasts of macroeconomic indicators of Russian economy, published by the Ministry of Economic Development of Russian Federation [16] Weighted average annual growth of operating costs (including the share of each group in operating expenses) is 6% Now operating costs of a data centre in the year G can be determined by the following relation: 4 Forecasting the revenue of a data centre To calculate cash flows such indicators as revenue per rack and revenue per square meter of the data centre space are usually used FIGURE 9 Forecast of revenue per sq m in geographical terms As a basis for our analysis we have used the results of revenue forecasts from the data centre market research of iks-consulting company (2012) (Figure 9, 10) Absolute values of revenue presented in these research significantly differ from our results because iks- Consulting company used generalized data (total number of racks, total area of data centres in Russia, summarized declared income etc), not the data of concrete projects But this data are quite enough to analyse the behaviour of revenue indicators We have used trend estimation technique to make and justify some statements about tendencies in these data As we can see, the values of the coefficients of determination for the linear trends are within This indicates the absence of explicit changes in the data over time The variability of indicators is mainly determined by other factors It allows us to conclude that these indicators are quite stable in nature and will not change significantly in the foreseeable future y = 3458x R² = 006 y = -3344x R² = 019 y = 3267x R² = 009 y = -8444x R² = Revenue per sqm, Moscow, USD Revenue per sqm, Sankt-Petersbourg, USD Revenue per sqm, regions, USD Revenue per sqm, Russia, USD y = 10395x R² = 041 y = 12807x R² = 014 y = -099x R² = y = -4572x R² = Revenue per 2013 rack, Moscow, 2014USD Revenue per rack, Sankt-Petersbourg, USD Revenue per rack, regions, USD Revenue per rack, Russia, USD FIGURE 10 Forecast of revenue per one rack in geographical terms 268
9 Due to significant differences in accounting policies in different companies information about revenue of data centres is very heterogeneous and often contradictory (for example, stated in the reports values of revenue per sq m differ by times for data centres with the same location) Therefore, for the analysis we selected the data of several Moscow typical data centres with relatively clear accounting system Finally, we have got the following average indices: revenue in Moscow and Moscow region is $ / sq m or $ / rack For St Petersburg and other Russian regions these values can be adjusted with the help of the above mentioned forecasts (report of iks-consulting company (2012)) It is necessary to consider the impact of the degree of occupancy of a data centre on revenues We assume that the average time to achieve the level of normal occupancy of a commercial data centre is two years [17] We believe that the filling of a data centre proceeds linearly It means that at the end of the first year the level of occupancy will reach 50% and the average level of occupancy for the first year will be 25% At the end of the second year occupancy will reach its normal level, TABLE 4 Comparison of actual and calculated data centre revenue and the average level for this period will be 75% of normal As a result the revenue (Rev) of future periods (since the moment of commissioning data centre) can be represented by the following relations:,, where: RPR (Revenue per rack) - index of revenue per rack in every given year RPM (Revenue per square meter) - index of revenue per square meter of data centre space in every given year Per - period for which the analysis is performed (number of years) The degree of compliance of real and calculated revenues of several data centres [18] is shown in Table 4 Data centre Safedata Dataline DEMOS-Internet OBIT Revenue per rack, deviation 12% 14% 17% -6% Revenue per sq m, deviation 12% 17% 24% -11% 5 Estimation of financial performance of a project The final step in the evaluation of the effectiveness of investment in a data centre is to build a discounted cash flows model It includes income and expenses of future periods, loans needed for starting the project and the future payment of interest on them As a result the net cash flows will be obtained and finally they must be discounted The estimations of NPV and ROI allow us to receive a final evaluation of the effectiveness of the project During the preplanning of the project the following parameters should be defined: Space of a data centre (in the ideal case - the number and power of racks, as well) Period of construction of a data centre (usually about 2 years) Duration of the data centre lifecycle The Net Present Value of a data centre creation project, launched in the year G, can be determined (using data about technical space) by the relation: [ ] [ ] [ ] where: q - serial number of the year of project, i - discounting coefficient, D - duration of the data centre lifecycle 6 Conclusion Of course, every data centre is unique, so there can t be a universal tool that would exactly forecast cash flows Our model provides a reasonably accurate estimate baized on the most aggregated data centre characteristics space and number of racks In comparison with the data of real projects the errors of our model lie within following ranges: for the capital expenditures COPEX(N) - 2%-16% COPEX(S) - 1%-14% for the operational expenditures ОРЕХ/racks - 14%-34%, ОРЕХ/sq m - 9% -31%, for the revenue RPR - 6%-17% RPM - 11%-24% 269
10 Parameters of the model depend considerably on the place of the data centre construction (Moscow, St Petersburg or other regions of the Russian Federation) As an example, let us consider the project of typical data centre in the Moscow area (of the Tier 3 level, with the area of square meters) Using the proposed model we obtain the following results: CAPEX = *S = thousand rubles = thousand dollars References [1] Datacentre downtime: How much does it really costs? rts/aberdeendatacentredowntimecostpdf [2] Determining Total Cost of Ownership for Data Centre and Network Room Infrastructure White paper # 6 Revision [3] Economics of data centre// Radius Group [4] Hamilton J 2010 Overall Data Centre CostsPerspectives James Hamilton's Blog stsaspx [5] Patel C, Shah A 2005 Cost Model for Planning, Development and Operation of a Data Centre Internet Systems and Storage Laboratory - HP Laboratories Palo Alto, [6] Total Cost of Ownership (TCO): Definition, Meaning and Use Encyclopedia of Business Terms and Methods 2013 ISBN [7] Information about prices of acquired basic construction materials, components and structures [8] Data centre: expenditures structure Radius Group [9] Pavlov A, Basistiy D, Kusakin D 2012 Business plan and financial assessment of creating a data centre with high level of reliability OPEX = (0,24 + 0,003*S)*20857*e = thousand rubles = thousand dollars Rev = thousand rubles = thousand dollars (exceeds the volume of operating costs by thousand rubles or by 2919 thousand dollars) In case of constant CAPEX payback period will be 68 years, IRR = 8% These figures are broadly in line with the estimates of different experts [3, 19, 20] and confirm the correctness of relations obtained by us [10] Samoylov Y 2010 What does it take to build a data centre?! [11] System of professional analysis of markets and companies SPARK- Interfax [12] Data centre statistics 2011 AboutDCru [13] Khoroshikh D 2010 All advantages of external data centre [14] Pavlov A 2007 Engineering solutions for reducing the operating cost of the data centre [15] Volchaninov L, Ilyin S 2008 The crisis will force introducing technologies of optimization data centre [16] Ministry of Economical Development [17] Gabrielyan V 2009 How to build private data centre Byte Russia [18] Soukhov R 2008 How to estimate expenditures of data centre? [19] Data-centres are growing as mushrooms [20] Pavlov A 2011 Data centre Checklist [21] Orlov S 2008 Data centre: Russian realities Authors Vladimir Grekul, born on September 15, 1949, Sakhalin, Russia Current position, grades: Professor, Head of the Department of Corporate Information Systems National Research University Higher School of Economics, Moscow University studies: Kiev Higher Engineer Aviation Training School of the Air Force Scientific interest: IT management Publications: 90 Experience: 40 years experience in design and implementation of information systems Liubov Baydalina, born on January 4, 1990, Chelyabinsk, Russia Current position, grades: Junior Business Analyst, Schneider Electric, Business Development department University studies: MA degree, Magna Cum Laude (Honors degree) Scientific interest: business processes modelling and optimization, modelling of market development, estimate of NPV of IT project Publications: 6 Experience: Datacentres market research 270
The market of commercial data centers 1, Russia October, 2011
The market of commercial data centers 1, Russia October, 2011 J'son & Partners Consulting presents brief results of the recently completed study of the Russian commercial data centers market. Usable area
Determining Total Cost of Ownership for Data Center and Network Room Infrastructure
Determining Total Cost of Ownership for Data Center and Network Room Infrastructure White Paper #6 Revision 3 Executive Summary An improved method for measuring Total Cost of Ownership of data center and
A Business Case for Scaling the Next-Generation Network with the Cisco ASR 9000 System: Now with Converged Services. Key Takeaways.
A Business Case for Scaling the Next-Generation Network with the Cisco ASR 9000 System: Now with Converged Services Executive Summary In a previous whitepaper ACG Research described the business case for
Innovative textile - industrial cluster of the Ivanovo region
[land of prospects] [ land of possibilities Innovative textile - industrial cluster of the Ivanovo region [ Ivanovo region] For development of the Innovative textile - industrial cluster of the Ivanovo
Russian customers projects realization examples on the basis of DEAC data centers infrastructure
Russian customers projects realization examples on the basis of DEAC data centers infrastructure Conference Data center world 2011" Moscow Oleg Naskidaev Head of marketing and development department, DEAC,
PORT REFORM TOOLKIT WORLD BANK
WORLD BANK FINANCIAL MODEL MANUAL Concession Project in the port sector 1/ PRELIMINARY ADVICE Required Software : Excel 2000 for PC Data & parameters of modelling : It appears in blue colour and exclusively
Common mistakes in datacentre planning
Common mistakes in datacentre planning White Paper Last edited: March 2013 Document Control Document Information Title Author Common mistakes in datacentre planning Nick Ewing This document is based upon
J son & Partners Consulting company presents the results of the research of Russian market of cloud IaaS solutions.
J son & Partners Consulting company presents the results of the research of Russian market of cloud IaaS solutions. Infrastructure-as-a-Service (IaaS) is the automatic or on demand provision of data-center
The North American Data Centre Pricing 2014 to 2019 Report
The North American Data Centre Pricing 2014 to 2019 Report Published: November 2014 Number of Tables and Charts: 81 Coverage: 338 N. American Data Centre providers identified with some 1,171 Data Centre
Analysis of the Brazilian Data Center Power Supplies Market
Analysis of the Brazilian Data Center Power Supplies Market IT Infrastructure Outsourcing Services Compel New Trends for this Growing Market ND27-14 September 2013 Contents Section Slide Numbers Executive
Results of Reevaluations of Fixed Assets and Tasks of Improvement of Appraisals of and Accounting for Fixed Assets
As was agreed during the consultations that were held during an OEC delegation visit to Moscow on April 1, 1999, the Russian State Statistics Committee hereby sends a report concerning the results of reevaluations
A COST MODEL FOR THE IT DEPARTMENT
A COST MODEL FOR THE IT DEPARTMENT Marius MIHUT 1 Economic Informatics Department, Babeş-Bolyai University of Cluj-Napoca, Cluj-Napoca, Romania. E-mail: [email protected] Nicolae TOMAI 2 Economic
THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES. Craig Roberts National Bank Financial
THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES Craig Roberts National Bank Financial ABSTRACT While various methods are available to estimate a mining project
03 The full syllabus. 03 The full syllabus continued. For more information visit www.cimaglobal.com PAPER C03 FUNDAMENTALS OF BUSINESS MATHEMATICS
0 The full syllabus 0 The full syllabus continued PAPER C0 FUNDAMENTALS OF BUSINESS MATHEMATICS Syllabus overview This paper primarily deals with the tools and techniques to understand the mathematics
Paper 7 Management Accounting
Technician Level Paper 7 Management Accounting Extended Syllabus INTRODUCTION Extended Syllabuses are part of a comprehensive package of support materials offered by SIAT. This package includes past question
Introduction to Project Finance Analytic Methods
Introduction to Project Finance Analytic Methods Renewable Energy and Project Development and Financing for California Tribes Sacramento, CA Jack Whittier, McNeil Technologies January 2008 Why? Use a model
Monetary policy rules and their application in Russia. Economics Education and Research Consortium Working Paper Series ISSN 1561-2422.
Economics Education and Research Consortium Working Paper Series ISSN 1561-2422 No 04/09 Monetary policy rules and their application in Russia Anna Vdovichenko Victoria Voronina This project (02-230) was
O KEY GROUP ANNOUNCES AUDITED FINANCIAL RESULTS FOR 2014
Press Release 19 March 2015 O KEY GROUP ANNOUNCES AUDITED FINANCIAL RESULTS FOR 2014 O KEY Group S.A (LSE: OKEY), a leading food retailer in Russia, today released audited consolidated financial results
CHAPTER 4 APPLICATIONS IN THE CONSTRUCTION INDUSTRY
CHAPTER 4 APPLICATIONS IN THE CONSTRUCTION INDUSTRY This chapter introduces some topics that are related to the economic evaluation of alternatives such as the depreciation, breakeven analysis and the
RECOMMENDATIONS ON BUSINESS PLAN PREPARATION
RECOMMENDATIONS ON BUSINESS PLAN PREPARATION 1. General provisions Business plan must contain: name of the investment project, as well description of its essence and feasibility; substantiation of the
Executive Summary. Abstract. Heitman Analytics Conclusions:
Prepared By: Adam Petranovich, Economic Analyst [email protected] 541 868 2788 Executive Summary Abstract The purpose of this study is to provide the most accurate estimate of historical
Juniper Networks QFabric: Scaling for the Modern Data Center
Juniper Networks QFabric: Scaling for the Modern Data Center Executive Summary The modern data center has undergone a series of changes that have significantly impacted business operations. Applications
Sberbank Group s IFRS Results for 6 Months 2013. August 2013
Sberbank Group s IFRS Results for 6 Months 2013 August 2013 Summary of 6 Months 2013 performance: Income Statement Net profit reached RUB 174.5 bn (or RUB 7.95 per ordinary share), a 0.5% decrease on RUB
Step 1: Determine the Size, Parameters and Construction Timeline for the Property
The Real Estate Development Process While real estate development models may look complex, the actual concepts are simpler than what you see for normal companies. Real estate development modeling is different
An Analysis of Price Determination and Markups in the Air-Conditioning and Heating Equipment Industry
LBNL-52791 An Analysis of Price Determination and Markups in the Air-Conditioning and Heating Equipment Industry Larry Dale, Dev Millstein, Katie Coughlin, Robert Van Buskirk, Gregory Rosenquist, Alex
Financial Projections
Financial Projections Introduction Any business plan must include a section detailing the financial projections, because these projections are a forecast of the future economic-financial results of the
Financing Entrepreneurial Ventures Part 1 Financial Plan & Statements
Financing Entrepreneurial Ventures Part 1 Financial Plan & Statements Barbara Peitsch Program Director, Univ. of Michigan Peter Scott Professor of Entrepreneurship/Consultant August 2015 Economic Empowerment
Electrical Efficiency Modeling for Data Centers
Electrical Efficiency Modeling for Data Centers By Neil Rasmussen White Paper #113 Revision 1 Executive Summary Conventional models for estimating electrical efficiency of data centers are grossly inaccurate
Optimization of the physical distribution of furniture. Sergey Victorovich Noskov
Optimization of the physical distribution of furniture Sergey Victorovich Noskov Samara State University of Economics, Soviet Army Street, 141, Samara, 443090, Russian Federation Abstract. Revealed a significant
Electrical Efficiency Modeling of Data Centers
Electrical Efficiency Modeling of Data Centers By Neil Rasmussen White Paper 113 Executive Summary The conventional models used to estimate electrical efficiency of data centers are grossly inaccurate
Comprehensive Business Budgeting
Management Accounting 137 Comprehensive Business Budgeting Goals and Objectives Profit planning, commonly called master budgeting or comprehensive business budgeting, is one of the more important techniques
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
Don't Confuse CRM Benefits With ROI
Tutorials, B. Eisenfeld, E. Kolsky, J. Grigg Research Note 29 April 2003 Don't Confuse CRM Benefits With ROI In recent customer relationship management surveys, 52 percent of respondents claimed return
Module 10: Assessing the Business Case
Module 10: Assessing the Business Case Learning Objectives After completing this section, you will be able to: Do preliminary assessment of proposed energy management investments. The measures recommended
Chapter 4: Liquor Store Business Valuation
Chapter 4: Liquor Store Business Valuation In this section, we will utilize three approaches to valuing a liquor store. These approaches are the: (1) cost (asset based), (2) market, and (3) income approach.
Data Center Colocation Build vs. Buy
Data Center Colocation Build vs. Buy Comparing the total cost of ownership of building your own data center vs. buying third-party colocation services Executive Summary As businesses grow, the need for
II. TOMATO CANNING A. START COMFAR
II. TOMATO CANNING This exercise is intended to introduce a new user to the basic concepts and procedures of COMFAR III Expert. Only financial analysis is performed. Data are kept to a minimum to concentrate
Power Purchase Agreement Financial Models in SAM 2013.1.15
Power Purchase Agreement Financial Models in SAM 2013.1.15 SAM Webinar Paul Gilman June 19, 2013 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT. Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ VSB Technical University of Ostrava, Ostrava, Czech
Calculate ROI or Your Program is a Roll of the Dice
2007 International Software Measurement & Analysis Conference Calculate ROI or Your Program is a Roll of the Dice September 12, 2007 Stasia Iwanicki, PMP Sheila Dennis, CFPS David Consulting Group www.davidconsultinggroup.com
USING BIG DATA FOR OPERATIONS & ENERGY MANAGEMENT IN HOSPITALITY
www.wiproecoenergy.com USING BIG DATA FOR OPERATIONS & ENERGY MANAGEMENT IN HOSPITALITY ANALYZE. ACHIEVE. ACCELERATE Table of Content 03... Abstract 04... Need for Operational & Energy Efficiency 04...
Revitalising your Data Centre by Injecting Cloud Computing Attributes. Ricardo Lamas, Cloud Computing Consulting Architect IBM Australia
Revitalising your Data Centre by Injecting Attributes Ricardo Lamas, Consulting Architect IBM Australia Today s datacenters face enormous challenges: I need to consolidate to reduce sprawl and OPEX. I
How To Design A Data Center
Approaches to Achieve Next-Generation Data Center Joe Li Business Head of Mission Critical Infrastructure Solutions What CIOs should know.. High way to Next-Generation Data Center Energy-Efficiency Scalability
6. FINANCIAL MANAGEMENT
6. FINANCIAL MANAGEMENT Syllabus Financial Management: Investment-need, Appraisal and criteria, Financial analysis techniques-simple pay back period, Return on investment, Net present value, Internal rate
Procurement Model Analysis: CAPEX vs OPEX. In partnership with the Netherlands
1 In partnership with the Netherlands Procurement Model Analysis: CAPEX vs OPEX 2 Contents 1. Executive summary.p3 2. What are the different procurement models: p3 i. Illustration of CAPEX model...p4 ii.
OUTSOURCE or INSOURCE A Datacentre Buy or Build Guide
White Paper OUTSOURCE or INSOURCE A Datacentre Buy or Build Guide Yidan Wang V1.1 Oct 2013 A MATHEMATICAL APPROACH [ F - ( R + M + T )] x C = S Executive Summary The datacentre industry, which is a component
Methods for Project Evaluation
Methods for Project Evaluation March 8, 2004 1 Alternative Methods Present worth (PW) method Future worth (FW) method Annual worth (AW) method Benefit-cost ratio (BC) method Internal rate of return (IRR)
A Primer on Forecasting Business Performance
A Primer on Forecasting Business Performance There are two common approaches to forecasting: qualitative and quantitative. Qualitative forecasting methods are important when historical data is not available.
MBA350 INTEGRATIVE CAPSTONE COURSE
MBA350 INTEGRATIVE CAPSTONE COURSE Individual Assignment Spring 2008 Raffaello Curtatone Team # 6 Index Introduction and general drivelines... 3 S&A Report... 4 Marketing Research... 4 Cost of Goods Sold...
Section 1.5 Linear Models
Section 1.5 Linear Models Some real-life problems can be modeled using linear equations. Now that we know how to find the slope of a line, the equation of a line, and the point of intersection of two lines,
Simple Linear Regression Inference
Simple Linear Regression Inference 1 Inference requirements The Normality assumption of the stochastic term e is needed for inference even if it is not a OLS requirement. Therefore we have: Interpretation
Engineering Economics
Engineering Economics Overview and Application in Process Engineering Industry 10.490 ICE Kangyi MAO 02 OCT 2006 WHAT IS ECONOMICS? Economics is the study of how people and society choose to employ scarce
SBERBANK GROUP S IFRS RESULTS. March 2015
SBERBANK GROUP S IFRS RESULTS 2014 March 2015 SUMMARY OF PERFORMANCE FOR 2014 STATEMENT OF PROFIT OR LOSS Net profit reached RUB 290.3bn (or RUB 13.45 per ordinary share), compared to RUB 362.0bn (or RUB
Improving Data Centers Energy Reliability & Efficiency. December 2015
Improving Data Centers Energy Reliability & Efficiency December 2015 Background The challenges Alternative solutions SATEC approach Advantages Cases Summary Data Centers Energy Challenges Worldwide Data
Fundamentals Level Skills Module, Paper F9. Section A. Monetary value of return = $3 10 x 1 197 = $3 71 Current share price = $3 71 $0 21 = $3 50
Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2014 Answers Section A 1 A Monetary value of return = $3 10 x 1 197 = $3 71 Current share price = $3 71 $0 21 = $3 50 2
- centred on human factors (ie. ergonomics, desire to have a new computer system) - Are there unused computer terminals in the company now?
Feasibility and Cost-Benefit Analysis Feasibility Operational Feasibility - centred on human factors (ie. ergonomics, desire to have a new computer system) - Is the problem worth solving? - How do the
ROI CASE STUDY NETSUITE REDBUILT
ROI CASE STUDY NETSUITE REDBUILT THE BOTTOM LINE RedBuilt used NetSuite ERP to avoid a costly one-time fee from SAP, eliminate staff dedicated to manual data entry, reduce report building costs, and improve
I. Basic concepts: Buoyancy and Elasticity II. Estimating Tax Elasticity III. From Mechanical Projection to Forecast
Elements of Revenue Forecasting II: the Elasticity Approach and Projections of Revenue Components Fiscal Analysis and Forecasting Workshop Bangkok, Thailand June 16 27, 2014 Joshua Greene Consultant IMF-TAOLAM
Iceland s competitive advantages as a global Data Centre location
Iceland s competitive advantages as a global Data Centre location Introduction BroadGroup has undertaken an independent analysis of Iceland as a global data centre hub, comparing it using a wide variety
What is a business plan?
What is a business plan? A business plan is the presentation of an idea for a new business. When a person (or group) is planning to open a business, there is a great deal of research that must be done
Jean Van der hasselt CEO Russia and the Nordics
Jean Van der hasselt CEO Russia and the Nordics Market Overview Russia Population 140.4 million Language(s) Russian Currency Ruble Capital City Moscow GDP US$1.465 trillion Source: IMF Russia is the largest
Univariate Regression
Univariate Regression Correlation and Regression The regression line summarizes the linear relationship between 2 variables Correlation coefficient, r, measures strength of relationship: the closer r is
The Elasticity of Taxable Income: A Non-Technical Summary
The Elasticity of Taxable Income: A Non-Technical Summary John Creedy The University of Melbourne Abstract This paper provides a non-technical summary of the concept of the elasticity of taxable income,
How To Calculate Discounted Cash Flow
Chapter 1 The Overall Process Capital Expenditures Whenever we make an expenditure that generates a cash flow benefit for more than one year, this is a capital expenditure. Examples include the purchase
MEASURING ECONOMIC IMPACTS OF PROJECTS AND PROGRAMS
Economic Development Research Group April 1997 MEASURING ECONOMIC IMPACTS OF PROJECTS AND PROGRAMS GLEN WEISBROD, ECONOMIC DEVELOPMENT RESEARCH GROUP BURTON WEISBROD, ECONOMICS DEPT., NORTHWESTERN UNIV.
Investing in International Financial Markets
APPENDIX 3 Investing in International Financial Markets http:// Visit http://money.cnn.com for current national and international market data and analyses. The trading of financial assets (such as stocks
Building the Business Case for a Cloud-Based Contact Center Solution Sponsored by:
Building the Business Case for a Cloud-Based Contact Center Solution Sponsored by: - 1 - DMG Consulting LLC Table of Contents Why a Cloud-Based Contact Center is Likely in Your Future... 1 Building the
Breakeven Analysis. Breakeven for Services.
Dollars and Sense Introduction Your dream is to operate a profitable business and make a good living. Before you open, however, you want some indication that your business will be profitable, if not immediately
The Macroeconomic Situation and Monetary Policy in Russia. Ladies and Gentlemen,
The Money and Banking Conference Monetary Policy under Uncertainty Dr. Sergey Ignatiev Chairman of the Bank of Russia (The 4 th of June 2007, Central Bank of Argentina, Buenos Aires) The Macroeconomic
Part 7. Capital Budgeting
Part 7. Capital Budgeting What is Capital Budgeting? Nancy Garcia and Digital Solutions Digital Solutions, a software development house, is considering a number of new projects, including a joint venture
Premium Data Centre Europe - 2012 Pricing, Business Model & Services
Premium Data Centre Europe - 2012 Pricing, Business Models & Services Premium Data Centre Europe - 2012 Pricing, Business Model & Services Table of Contents A list of figures used in this report 5 Methodology
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
SIMPLIFIED PERFORMANCE MODEL FOR HYBRID WIND DIESEL SYSTEMS. J. F. MANWELL, J. G. McGOWAN and U. ABDULWAHID
SIMPLIFIED PERFORMANCE MODEL FOR HYBRID WIND DIESEL SYSTEMS J. F. MANWELL, J. G. McGOWAN and U. ABDULWAHID Renewable Energy Laboratory Department of Mechanical and Industrial Engineering University of
Legal Salary Survey, 2012
INTRODUCTION regularly releases a salary survey to advise our clients and candidates on the Moscow legal market. This report provides a salary review current to the end of August 2012 covering private
WHITE PAPER Using SAP Solution Manager to Improve IT Staff Efficiency While Reducing IT Costs and Improving Availability
WHITE PAPER Using SAP Solution Manager to Improve IT Staff Efficiency While Reducing IT Costs and Improving Availability Sponsored by: SAP Elaina Stergiades November 2009 Eric Hatcher EXECUTIVE SUMMARY
Course 3: Capital Budgeting Analysis
Excellence in Financial Management Course 3: Capital Budgeting Analysis Prepared by: Matt H. Evans, CPA, CMA, CFM This course provides a concise overview of capital budgeting analysis. This course is recommended
Best Practice Procurement Guide
1 Best Practice Procurement Guide Bangladesh 2 Contents Executive Summary... 5 Introduction... 6 1. Principle of Sustainable Procurement... 6 2. Sustainable Procurement Process Flow... 6 3. Different Procurement
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Learning Objectives: Quick answer key: Question # Multiple Choice True/False. 14.1 Describe the important of accounting and financial information.
0 Learning Objectives: 14.1 Describe the important of accounting and financial information. 14.2 Differentiate between managerial and financial accounting. 14.3 Identify the six steps of the accounting
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Financial Evaluation
1 What, Why and How? Best Management Practice: BMP D: Create a Long- Term Financial Plan. Meaning of Terms
Best Management Practice: BMP D: Create a Long- Term Financial Plan 1 What, Why and How? What is a long- term financial plan? A long- term financial plan estimates what your revenues and expenses will
How the Port Density of a Data Center LAN Switch Impacts Scalability and Total Cost of Ownership
How the Port Density of a Data Center LAN Switch Impacts Scalability and Total Cost of Ownership June 4, 2012 Introduction As data centers are forced to accommodate rapidly growing volumes of information,
The HP IT Transformation Story
The HP IT Transformation Story Continued consolidation and infrastructure transformation impacts to the physical data center Dave Rotheroe, October, 2015 Why do data centers exist? Business Problem Application
WHY WRITE A BUSINESS PLAN?
KANSAS SMALL BUSINESS DEVELOPMENT CENTER PITTSBURG STATE UNIVERSITY PITTSBURG, KS 66762 PHONE: 620 235 4920; FAX: 620 235 4919 e mail: [email protected] WHY WRITE A BUSINESS PLAN? A business plan is
NCC5010: Data Analytics and Modeling Spring 2015 Practice Exemption Exam
NCC5010: Data Analytics and Modeling Spring 2015 Practice Exemption Exam Do not look at other pages until instructed to do so. The time limit is two hours. This exam consists of 6 problems. Do all of your
SOCIAL SPHERE MODELING BASED ON SYSTEM DYNAMICS METHODS
SOCIAL SPHERE MODELING BASED ON SYSTEM DYNAMICS METHODS Abstract Natalia N. Lychkina State University of Management 99 Ryazansky Avenue, Moscow, Russia, 109542 Tel: +7 (495) 749-71-77 / Fax: +7 (495) 371-05-28
Statistics 151 Practice Midterm 1 Mike Kowalski
Statistics 151 Practice Midterm 1 Mike Kowalski Statistics 151 Practice Midterm 1 Multiple Choice (50 minutes) Instructions: 1. This is a closed book exam. 2. You may use the STAT 151 formula sheets and
MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
Survey of Macroeconomics, MBA 641 Fall 2006, Quiz 4 Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) The central bank for the United States
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS Phil Thompson Business Lawyer, Corporate Counsel www.thompsonlaw.ca Rules of thumb and financial analysis
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION January 2008 C O N T E N T S Page No. 1. Overview 1 2. Introduction 3 3. RIC s Regulatory Framework
DELPHIX CIGA ROI CASE STUDY. ROI: 194% Payback: 6 months Average annual benefit: $294,555. Document O111 June 2014
ROI CASE STUDY June 2014 DELPHIX CIGA THE BOTTOM LINE California Insurance Guarantee Association (CIGA), chose Delphix as its enterprise standard for data management. Nucleus found that moving to Delphix
Analyst Presentation. for the year ended 28 February 2014
Analyst Presentation for the year ended 2014 Agenda 1. General commentary on the period Kevin Hodgson 2. Financial commentary Cobus Loubser 3. Questions Page 2 General Commentary Review of the period Group
business statistics using Excel OXFORD UNIVERSITY PRESS Glyn Davis & Branko Pecar
business statistics using Excel Glyn Davis & Branko Pecar OXFORD UNIVERSITY PRESS Detailed contents Introduction to Microsoft Excel 2003 Overview Learning Objectives 1.1 Introduction to Microsoft Excel