1 IV. MANAGEMENT-IN-USE PHASE Introduction. The Management- In-Use Phase includes the Steps an agency should take to manage and evaluate the continued viability of an acquired capital asset as part of the agency portfolio. STEP IV.1. OPERATIONAL ANALYSIS Agencies should establish a system to measure the performance and cost of an operational asset against the baseline established in the Planning Phase. The tracking method is called operational Management- In-Use Budgeting Planning Operational Analysis Execution of Operation and Maintenance Plan Post-Implementation Review Execution of Asset Disposal Plan Procurement analysis. This information will allow agency resource managers to optimize the performance of capital assets. Additionally, operational analysis may indicate the need for the acquisition of a new capital asset. The system established should have the capability to provided simple, easy to understand information that can be used by managers to make sound management decisions. Analysis of operations can be used to minimize the cost of asset ownership while simultaneously improving the function the asset performs. The cost of asset ownership is defined as the total of all costs incurred by the owners and users to obtain the benefits of a given acquisition. While great emphasis is often placed on meeting the budget, scope, and schedule for the acquisition of a capital asset, these are only a fraction of the asset s total life-cycle costs. Ownership costs, such as operations, maintenance, including service contracts, and disposition, can easily consume as much as 80 percent of the total life-cycle costs. A disciplined assessment of the condition and usability of the asset, and of trends over time, should be included. Operations is a critical area where improved effectiveness and productivity can have the greatest net measurable benefit in cost, performance, and mission accomplishment. If life-cycle cost criteria are given serious consideration during the Planning, Budgeting, and Procurement Phases, total life-cycle costs can be greatly reduced. Once an asset has been acquired and is in use, operational analysis should take place in accordance with a schedule of fixed milestones or on a cyclical basis. This should be a formal analysis to determine whether the asset is meeting program objectives and the needs of the owners and users, as well as performing within baseline cost, schedule, and performance goals. An automated system Management-In-Use/ 51
2 could flag the need, on an exception basis, to view the status of a capital asset before it becomes a problem. Figure 11 describes operational analysis at the Department of Energy. Operational analysis may indicate a need to redesign or modify an asset if previously undetected faults in the design, construction, or installation are discovered during the course of operations, if O&M costs are higher than anticipated, or if the asset fails to meet program requirements. Such analysis may also help to identify where faulty operations are eroding the asset s ability to perform its function. Figure 11. Operational Analysis at the Department of Energy The Department of Energy (DOE) has established an operations assessment program to formalize and standardize a method by which the safety and effectiveness of facility operations are evaluated. The program requires Operations offices to schedule and perform operations assessments at six month intervals. Assessments focus on identifying operational weaknesses requiring management corrective action rather than on identifying lists of individual deficiencies. Corrective actions are tracked and implemented, and the results of assessments are reported to line managers. This program has resulted in strong improvement in operations oversight and operational improvements at a number of the operations offices, including changes in nuclear fuel handling procedures; development of standardized operations policies and procedures; decrease in design deficiencies; development of complex-wide well-drilling procedures using lessons learned from all the sites; more efficient and effective lockout/tagout systems; better control of equipment and system status; and improved radiological controls. This program allows DOE managers to target improvement actions and more effectively utilize scarce resources. Operational analysis will lose much of its value-added benefits to the capita l programming process if an opportunity to make a course correction is missed due to inattention to early warning indicators. Analysis of such indicators may show a need to apply an improvemen t methodology, such as value management, to identify if there are better ways for the asset to meet its lifecycle cost and performance goals. Operational indicators for a given asset may include any of the following: effectiveness efficiency productivity availability energy usage reliability maintainability security STEP IV.2. EXECUTION OF OPERATION AND MAINTENANCE PLAN If not properly maintained, a capital asset s useful life can be shortened dramatically, thereby reducing the return on the taxpayers investment. Day-to-day operation and maintenance of any asset must be carefully planned. In addition, the projected costs associated with the day-to-day operation and maintenance of the asset must be factored into the asset s procurement -- to make a best value Management-In-Use/ 52
3 determination when selecting between competing proposals -- and tracked throughout its life cycle (see Planning Phase, Steps I.5. and I.6.). The elements of an O&M plan include: For scheduled preventive maintenance; Sign-offs to instill personal responsibility; Training of user staff; and Tracking of labor and material costs. For predictable corrective maintenance; Budget expenditure for minor maintenance and repair; and Maintenance contracts. STEP IV.3. POST-IMPLEMENTATION REVIEW (PIR) Whereas operational analysis is a control mechanism during the operational life cycle of an asset, PIR is a diagnostic tool to evaluate the overall effectiveness of the agency s capital planning and acquisition process. The primary objective of a PIR is to identify whether the asset is performing as planned, ensure continual improvement of an agency s capital programming process based on lessons learned, and minimize the risk of repeating past mistakes. Where agencies have multiple requirements for reviews, one system to consolidate all PIRs should be established. Three to twelve months after a new asset becomes operational, the planning and procurement process should be evaluated to determine whether they accurately predicted the benefits to be derived from the new asset. These benefits could include lowered cost, reduced cycle time, increased quality, additional quantity of services, or increased speed of service delivery. Such an assessment is done by conducting project PIRs that compare actual results against planned cost, returns, and risks. The PIR results are used to calculate a final return on investment, determine whether any additional project modifications may be necessary, and provide "lessons learned" input for changes to the organization's capital programming processes and strategy. Agencies should be able to document and report on the performance benefits achieved by their investments and explain how those benefits support the accomplishment of agency goals. Specifically, there should be mechanisms in place that take the lessons learned from the PIR and use them to update the Planning Phase decision criteria and Procurement and Management-In-Use processes. The PIR should be conducted by individuals not directly involved in the acquisition of the asset. The PIR team can be composed of owners and users of the asset or other personnel and consultants. Management-In-Use/ 53
4 Factors to be considered in the PIR include: Customer/User Satisfaction Partnership/involvement Business process support Investment performance Usage Internal Business Project performance Infrastructure availability Standards and compliance Maintenance Security issues and internal controls Evaluations (accuracy, timeliness, adequacy of information) Strategic Impact and Effectiveness System impact and effectiveness Alignment with mission goals Portfolio analysis and management Cost savings Innovation Workforce competency Advanced technology use Methodology expertise Employee satisfaction/retention Program quality To ensure that each project is evaluated consistently, the organization should have a documented methodology for conducting these reviews. The methodology chosen must be in alignment with the organization's planning process and must build on the organization s memory. The organization should determine whether there may be better cost, benefit, and risk measures that could be established that would improve the monitoring of future projects. STEP IV. 4. EXECUTION OF ASSET DISPOSAL PLAN Disposal of an asset is the culmination of the processes discussed earlier in this Guide. Projected costs of asset disposal are critical elements in the planning and budgeting for asset acquisition. The decision to dispose of an asset may be triggered by any number of events; most will be part of a systematic plan formulated in advance that integrates the asset into the agency s broader capital resource management plan. Beginning with mission analysis and planning for the purpose of matching capabilities to mission requirements, and continuing with ongoing operational analysis, criteria are established and monitored to determine how well an asset is performing. At any time that the asset becomes uneconomical to keep in service or fails to meet performance criteria, the agency should critically assess the asset to determine whether it should be retired or replaced. Once the decision to dispose is made, a number of issues must be considered, including how to remove the asset from service, planning for transition to a replacement if required, redeployment elsewhere in the agency where it may continue to provide a benefit greater than the cost, or final removal of the asset from the agency s property inventory. Depending on the type of asset, disposal may be as simple as transferring the item to another agency, turning it over to GSA as excess, or demolishing it and selling it as scrap. Disposal of complex assets or systems may involve a multi-year process requiring significant effort and funding to execute. For example, when the FAA replaces a Management-In-Use/ 54
5 navigation system for commercial and private air traffic, it must communicate the details of the plan to thousands of system users worldwide and ensure that the transition to the new system is seamless, timely, and coordinated. Figure 12 discusses disposal of an IT system. The procedure for disposing of an asset will depend upon the type of asset, as well as existing agency guidelines and any laws and regulations governing the disposal of that particular asset (e.g., E.O , authorizing federal agencies to donate excess computers and related peripheral tools directly to schools). Hazardous material disposal would most likely be performed by a specialized contractor following environmental laws monitored by EPA, while disposing of an office building might be carried out by GSA following real property regulations. In all cases, agency property specialists, guided by internal policy and applicable laws and regulations, should work closely with agency executives to ensure costeffective and timely asset disposal. Figure 12. Example of Asset Disposal Disposal of an IT system typically requires the phase out of obsolete equipment and a transition to a new system. This process can take years to accomplish and requires extensive planning and coordination. For IT systems, the transition actually begins early in the planning stages for the new system. Acquisition planners have to work with prospective contractors to establish timeliness and devise a transition plan. After the new system has been acquired, developed, and tested, deployment takes place according to the plan developed early in the acquisition phase. The elements of the transition may include: converting data from the old system to the new; operating both the old and new systems concurrently; validating that the new system has converted old data properly; ensuring users are trained on the new equipment and software; keeping the customers informed of transition progress; and outlining these actions and agreements in a memorandum of understanding, signed by representatives from all parties affected by the conversion. A select group of users will test the system using real data and real situations to identify bugs and develop solutions. Any problems that occur will be documented in a lessons learned report and be resolved before the final, organization-wide transition to the new system. The transition team completes all system integration and testing to ensure that the new IT environment meets design requirements, and that office workloads will fit into the new environment as planned and perform to the users satisfaction. Upon formal acceptance, the old system is de-installed and final property disposal actions are executed as required. Management-In-Use/ 55
Enterprise Performance Life Cycle Management. Guideline
Enterprise Performance Life Cycle Management Guideline Version 2.1 PREPARED BY THE ENTERPRISE PROGRAM MANAGEMENT OFFICE MAY 2011 Table of Contents Document Control...i 1. Introduction... 2 1.1 Purpose...
VA Office of Inspector General
VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Audit of Office of Information Technology s Strategic Human Capital Management October 29, 2012 11-00324-20
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
U.S. Department of Education. Office of the Chief Information Officer
U.S. Department of Education Office of the Chief Information Officer Investment Review Board (IRB) CHARTER January 23, 2013 I. ESTABLISHMENT The Investment Review Board (IRB) is the highest level IT investment
Module 1 Study Guide Introduction to PPO. ITIL Capability Courses - Planning, Protection and Optimization
Module 1 Study Guide Introduction to PPO ITIL Capability Courses - Planning, Protection and Optimization Introducing PPO Welcome to your Study Guide. This document is supplementary to the information available
Real Property Portfolio Optimization
Real Property Portfolio Optimization Improving and Modernizing Management of the Federal Real Property Portfolio to Optimize Space, Financial Resources and Energy Impact www.pwc.com/publicsector Contents
Software Asset Management on System z
Software Asset Management on System z Mike Zelle Tivoli WW IT Asset Management Marketing SAM in SHARE Project Manager [email protected] Agenda Why Software Asset Management (SAM) The Discipline of Software
TOP MANAGEMENT CHALLENGES MOST FREQUENTLY IDENTIFIED December 2000
TOP MANAGEMENT CHALLENGES MOST FREQUENTLY IDENTIFIED December 2000 Agency Information Technology Management & Security GPRA Compliance, Implementation & Accountability Financial Management & CFO Statements
PRESIDENT S COUNCIL on INTEGRITY & EFFICIENCY
PRESIDENT S COUNCIL on INTEGRITY & EFFICIENCY F O R E W O R D In September 1999, key Congressional leaders requested selected Offices of Inspector General (OIG) to identify the "Top Management Challenges"
Technology Lifecycle Management. A Model for Enabling Systematic Budgeting and Administration of Government Technology Programs
Technology Lifecycle Management A Model for Enabling Systematic Budgeting and Administration of Government Technology Programs Even as technology improves, government s fundamental IT challenge remains
HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
Introduction to Cost Accounting
Introduction to Cost Accounting Learning Objectives By the end of this chapter, you should be able to: Define cost accounting. State the five areas in which cost accounting can assist management. List
GAO DATA CENTER CONSOLIDATION. Strengthened Oversight Needed to Achieve Cost Savings Goal. Report to Congressional Requesters
GAO United States Government Accountability Office Report to Congressional Requesters April 2013 DATA CENTER CONSOLIDATION Strengthened Oversight Needed to Achieve Cost Savings Goal GAO-13-378 April 2013
U.S. Nuclear Regulatory Commission
U.S. Nuclear Regulatory Commission 2011 Data Center Consolidation Plan and Progress Report Version 2.0 September 30, 2011 Enclosure Contents 1 Introduction... 2 2 Agency Goals for Data Center Consolidation...
Information Technology Asset Management: Control and Compliance
Information Technology Asset Management: Control and Compliance Information Technology Asset Management is the oversight and management of an organizations IT assets hardware, software and associated service
Systems Development Life Cycle (SDLC)
DEPARTMENT OF BUDGET & MANAGEMENT (SDLC) Volume 1 Introduction to the SDLC August 2006 Table of Contents Introduction... 3 Overview... 4 Page 2 of 17 INTRODUCTION 1.0 STRUCTURE The SDLC Manual consists
GENERAL SERVICES ADMINISTRATION Federal Acquisition Service Mission Oriented Business Integrated Services (MOBIS) SCHEDULE PRICE LIST
GENERAL SERVICES ADMINISTRATION Federal Acquisition Service Mission Oriented Business Integrated Services (MOBIS) SCHEDULE PRICE LIST SIN 874-7 Interior Systems, Inc., dba ISI Professional Services 1201
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
DLA Corporate Intern Program
DLA Corporate Intern Program The Program is a 2-year corporate training program designed to train entry-level personnel for subsequent advancement to the journey-level in professional, administrative,
Capital Projects. Providing assurance over effective delivery of projects
Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects
PULSE SECURE CARE PLUS SERVICES
DATASHEET PULSE SECURE CARE PLUS SERVICES Service Overview In today s dynamic marketplace, organizations are under constant pressure to meet market demand while maintaining or increasing return on investment.
WORKFORCE AND SUCCESSION PLANNING
2012 WORKFORCE AND SUCCESSION PLANNING Toolkit to Identify and Address Strategic Talent Gaps Workforce Management Office NOAA 1/1/2012 Table of contents Introduction... 3 Workforce Planning... 3 Step 1:
Ch.2 Logistics System Engineering.
Part 1 : System Management. Ch.2 Logistics System Engineering. Edited by Dr. Seung Hyun Lee (Ph.D., CPL) IEMS Research Center, E-mail : [email protected] Definition of System. Definition of System An
Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience
Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience Management Model (CERT-RMM), both developed at Carnegie
Position Classification Standard for Industrial Property Management Series, GS-1103. Table of Contents
Position Classification Standard for Industrial Property Management Series, GS-1103 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 4 PART I - INDUSTRIAL
NASA OFFICE OF INSPECTOR GENERAL
NASA OFFICE OF INSPECTOR GENERAL OFFICE OF AUDITS SUITE 8U71, 300 E ST SW WASHINGTON, D.C. 20546-0001 April 14, 2016 TO: SUBJECT: Renee P. Wynn Chief Information Officer Final Memorandum, Review of NASA
V. FLEET MANAGEMENT AT THE SMITHSONIAN: USING NEW TOOLS TO ADVANCE SUSTAINABILITY AND EFFICIENCY *
V. FLEET MANAGEMENT AT THE SMITHSONIAN: USING NEW TOOLS TO ADVANCE SUSTAINABILITY AND EFFICIENCY * OVERVIEW The Smithsonian Institution operates a widely diverse fleet of 1,500 vehicles to support its
Service Lifecycle Management Solutions
Service Lifecycle Management Solutions Complete Visibility & Control of Your Service Supply Chain The service landscape is shifting. Customer demands continue to increase. It is no longer enough to just
GENERAL SERVICES ADMINISTRATION
GSA CONTRACT NO.: GS-00F-047CA GENERAL SERVICES ADMINISTRATION Federal Acquisition Service Authorized Federal Supply Schedule Price List On-line access to contract ordering information, terms and conditions,
Migration Planning Guidance (Draft)
Financial Management Line of Business Migration Planning Guidance (Draft) Section 1.1 Overview The purpose of the Migration Planning Guidance document is to help agencies prepare for, and manage, a migration
Maintenance Plan. Many of the individual components of a comprehensive maintenance program are listed below, along with brief descriptions.
Maintenance Plan Introduction Maintenance is the cornerstone of asset sustainability. An effective preventive maintenance program, combined with good operational practices, will reduce the need for much
MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES
MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES FROM: SUBJECT: Peter R. Orszag Director Managing the Multi-Sector Workforce Federal agencies use both federal employees and private sector contractors
TTC AUDIT COMMITTEE REPORT NO.
Form Revised: February 2005 TTC AUDIT COMMITTEE REPORT NO. MEETING DATE: July 14, 2009 SUBJECT: INTERNAL AUDIT REPORT MATERIALS & PROCUREMENT INVENTORY PLANNING INFORMATION ITEM RECOMMENDATION It is recommended
Position Classification Flysheet for Inventory Management Series, GS-2010. Table of Contents
Position Classification Flysheet for Inventory Management Series, GS-2010 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 2 TITLES... 6 GRADING POSITIONS... 6 U.S.
Cascading KPIs using the 9 Steps to Success
Cascading KPIs using the 9 Steps to Success BSA uses the proven, disciplined framework, Nine Steps to Success, to systematically develop, implement, and sustain a strategic scorecard systems (see Figure
Electronic Healthcare Maturity Model (ehmm)
Quintegra Solutions Limited Electronic Healthcare Maturity Model (ehmm) A White Paper by Balaji Sharma Head, Healthcare Practice June 2008 168, Eldams Road, Teynampet, Chennai - 600018, Tamilnadu, India
Focused on your goals SERVICES AND SUPPORT CAPABILITIES OVERVIEW
Focused on your goals SERVICES AND SUPPORT CAPABILITIES OVERVIEW Laboratories today face complex scientific and business challenges that require the support of a true service partner a service partner
GAO. Inventory System Checklist Systems Reviewed Under the Federal Financial Management Improvement Act of 1996. Financial Management Series
GAO United States General Accounting Office Financial Management Series May 1998 Inventory System Checklist Systems Reviewed Under the Federal Financial Management Improvement Act of 1996 GAO/AIMD-98-21.2.4
TIER II STANDARD FOR FINANCIAL MANAGEMENT SPECIALISTS
Job Classification Manual Page 1 of 60 TIER II STANDARD FOR FINANCIAL MANAGEMENT SPECIALISTS INTRODUCTION 1. This grade level standard illustrates the application of the ICSC Master Standard (Tier I) to
Accenture Federal Fleet Management. Improving Fleet Efficiency and Compliance through Best Practices
Accenture Federal Fleet Management Improving Fleet Efficiency and Compliance through Best Practices 1 Rationalizing Your Fleet 10.5 Years: The average age of the federal fleet. With effective fleet rationalization,
LARGE PROJECT MANAGEMENT AND OVERSIGHT
LARGE PROJECT MANAGEMENT AND OVERSIGHT Report to The Senate Subcommittee on Transportation, Treasury and General Government The House Subcommittee on Transportation, Treasury and Independent Agencies Prepared
IT General Controls Domain COBIT Domain Control Objective Control Activity Test Plan Test of Controls Results
Acquire or develop application systems software Controls provide reasonable assurance that application and system software is acquired or developed that effectively supports financial reporting requirements.
U.S. Nuclear Regulatory Commission. Plan of Action Strategic Workforce Planning
U.S. Nuclear Regulatory Commission Plan of Action Strategic Workforce Planning January 19, 2001 Strategic Workforce Planning Plan of Action January 19, 2001 Content Overview This plan of action outlines
How To Recruit At The Afa
ACQUISITION WORKFORCE STRATEGY 15-0046 2015 TABLE OF CONTENTS TABLE OF CONTENTS 1 EXECUTIVE SUMMARY 2 1. FAA S ACQUISITION MANAGEMENT SYSTEM (AMS) 6 2. TODAY S ACQUISITION WORKFORCE 8 3. CURRENT SITUATION:
Accenture Federal Services. Federal Solutions for Asset Lifecycle Management
Accenture Federal Services Federal Solutions for Asset Lifecycle Management Assessing Internal Controls 32 Material Weaknesses: identified in FY12 with deficiencies noted in the management of nearly 75%
CITY OF MINNEAPOLIS GREEN FLEET POLICY
CITY OF MINNEAPOLIS GREEN FLEET POLICY TABLE OF CONTENTS I. Introduction Purpose & Objectives Oversight: The Green Fleet Team II. Establishing a Baseline for Inventory III. Implementation Strategies Optimize
Business & Technology Applications Analyst
NC 12234 OSP 6/2004 Business & Technology Applications Analyst DESCRIPTION OF WORK: This is technical and analytical work in developing, designing, and/or supporting applications for the business, research,
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal
IBM and the IT Infrastructure Library.
IBM Global Services September 2004 IBM and the IT Infrastructure Library. How IBM supports ITIL and provides ITIL-based capabilities and solutions Page No. 2 Contents ITIL Planning for Service 2 Executive
Management of Assets Policy
CREST Management of Assets Policy Version No: Reason for Update Date of Update Updated By 1 Policy introduced April 2012 Finance Office 2 Review incorporates IT Security Internal Audit review February
APPENDIX 3 TO SCHEDULE 8.1
APPENDIX 3 TO SCHEDULE 8.1 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT 1.0 Transition Services and Affected Employees The highest priority in the design of Northrop Grumman s transition plan is to transfer
Statement. Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation. Before
Statement of Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation Before THE UNITED STATES SENATE ARMED SERVICES COMMITTEE (SUBCOMMITTEE ON READINESS AND MANAGEMENT SUPPORT)
ENERGISTICS E&P BUSINESS PROCESS REFERENCE MODEL
ENERGISTICS E&P BUSINESS PROCESS REFERENCE MODEL Access, receipt, or use of the E&P Business Process Reference Model is subject to the Energistics Product License Agreement found on the Energistics website.
SOFTWARE LICENCE MANAGEMENT
SOFTWARE LICENCE MANAGEMENT MANAGING SOFTWARE COMPLIANCE AND COSTS DOESNʼT HAVE TO BE DIFFICULT Software Lifecycle Services from Computacenter Managing software compliance and costs doesnʼt have to be
Juniper Care Plus Services
Juniper Care Plus Services Service Overview In today s dynamic marketplace, organizations are under constant pressure to meet market demand while maintaining or increasing return on investment. IT departments
How To Manage It Asset Management On Peoplesoft.Com
PEOPLESOFT IT ASSET MANAGEMENT KEY BENEFITS Streamline the IT Asset Lifecycle Ensure IT and Corporate Compliance Enterprise-Wide Integration Oracle s PeopleSoft IT Asset Management streamlines and automates
DEFENSE TRAVEL MANAGEMENT OFFICE. Defense Travel Management Office FY 2012 FY 2016 Strategic Plan
DEFENSE TRAVEL MANAGEMENT OFFICE Defense Travel Management Office FY 2012 FY 2016 Strategic Plan December 2011 Table of Contents 1. Introduction... 1 2. DTMO Overview... 1 3. DTMO Strategy... 6 4. Measuring
PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR
Page 1 of 5 PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR 1.0 PURPOSE This evidence provides an overview of the nuclear operations project portfolio and other related project work. The project portfolio includes
ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY
ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY The Telecommunications Industry Companies in the telecommunications industry face a number of challenges as market saturation, slow
Central Project Office: Charter
Central Project Office: Charter ITCS: Central Project Office EAST CAROLINA UNIVERSITY 209 COTANCHE STREET, GREENVILLE, NC 27858 1 Table of Contents INTRODUCTION... 3 PURPOSE... 3 EXPECTED BENEFITS... 3
National Research Council Canada IP Prosecution and IP License Management Solution Project
National Research Council Canada IP Prosecution and IP License Management Solution Project Appendix 1 Statement of Work Version 6.0, 10 December 2013 ii Table of Contents 1. Instructions to Bidders...
Department of Human Resources
Workforce Services Workforce Policy and Planning Department Management/ Human Resource Information Systems Employee Relations Employment Compensation and Workforce Analysis Employee Benefits Organizational
REQUEST FOR PROPOSAL FOR IT ASSET MANAGEMENT SERVICES
KENYA AIRWAYS TENDER NO. T/026/14 REQUEST FOR PROPOSAL FOR IT ASSET MANAGEMENT SERVICES Release Date: 25 th April 2014 Closing date: 23 rd May 2014 1 INVITATION TO TENDER TENDER NO.T/026/14: PROVISION
Software Development Risk Assessment
Software Development Risk Assessment Note: The purpose of this prompt list is to provide project managers with a tool for identifying and planning for potential project risks. It is process-based and supports
How To Improve Mainframe Software Asset Management
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Internal Revenue Service Should Improve Mainframe Software Asset Management February 20, 2014 Reference Number: 2014-20-002 This report has cleared
Quality Management Plan
Quality Management Plan 6666 West Quincy Avenue Denver, Colorado 80235-3098 Telephone (303) 347-6100 September 1, 2011 CONTENTS Page APPROVALS ACRONYMS AND ABBREVIATIONS ii vi 1 INTRODUCTION 1 2 FOUNDATION
INFORMATION SYSTEMS SPECIALIST 8 1488
INFORMATION SYSTEMS SPECIALIST 8 1488 SERIES DESCRIPTION The INFORMATION SYSTEMS SPECIALIST (ISS) classification series has eight levels that describe technical and professional non-supervisory positions
License management service
License management service Service definition License Management Service is a service provided by HP Software Licensing & Management Solutions, which allows enterprise customers to effectively monitor
IT Service Provider and Consumer Support Engineer Position Description
Engineer Position Description February 9, 2015 Engineer Position Description February 9, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...
Pharmaceutical Sales Certificate
Pharmaceutical Sales Certificate Target Audience Medical representatives Objective The objective of this program is to provide the necessary skills and knowledge needed to succeed as medical representatives.
PROACTIVE ASSET MANAGEMENT
PROACTIVE ASSET MANAGEMENT A pathway to optimized reliability and world-class business performance Oracle Utilities Work and Asset Management 2 Effective work and asset management ensures mission-critical
Grant Thornton LLP 333 John Carlyle St., Suite 500 Alexandria, VA 22314 Phone: 703-837-4400 Fax: 703-837-4455 www.grantthornton.
Federal Supply Service Authorized Federal Supply Schedule Price List On-line access to contract ordering information, terms and conditions, up-to-date pricing, and the option to create an electronic delivery
INFORMATION TECHNOLOGY PROJECT REQUESTS
INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...
California Department of Corrections and Rehabilitation Enterprise Information Services. Business Information System Project
California Department of Corrections and Rehabilitation Enterprise Information Services Business Information System Project Initiation: January 2001 Completion: December 2012 2013 NASCIO Recognition Award
BPA Policy 434-1 Cyber Security Program
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Policy Table of Contents.1 Purpose & Background...2.2 Policy Owner... 2.3 Applicability... 2.4 Terms & Definitions... 2.5 Policy... 5.6 Policy
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
FEDERAL SOFTWARE LICENSES
United States Government Accountability Office Report to the Chairman, Committee on Homeland Security and Governmental Affairs, U.S. Senate May 2014 FEDERAL SOFTWARE LICENSES Better Management Needed to
INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Sustainability Remains an Issue
INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Audit Report OIG-A-2015-010 May 19, 2015 This page intentionally left blank. NATIONAL RAILROAD PASSENGER CORPORATION
REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information
REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information Report No. OIG-A-2013-015 June 12, 2013 NATIONAL RAILROAD PASSENGER CORPORATION The Inspector
L-3 Army Fleet Support is an Equal Opportunity Employer We encourage minorities, women, protected veterans, and disabled individuals to apply.
L-3 Army Fleet Support is an Equal Opportunity Employer We encourage minorities, women, protected veterans, and disabled individuals to apply. L-3 Army Fleet Support Fort Rucker, Alabama JOB ANNOUNCEMENT
Ellipse The Enterprise Asset Management (EAM) solution for asset intensive industries
Ellipse The Enterprise Asset Management (EAM) solution for asset intensive industries Ellipse is a fully-integrated Enterprise Asset Management (EAM) application suite providing complete visibility and
U.S. GENERAL SERVICES ADMINISTRATION STRATEGIC PLAN
U.S. GENERAL SERVICES ADMINISTRATION STRATEGIC PLAN Fiscal Year 2014 2018 STRATEGIC PLAN Fiscal Year (FY) 2014 2018 CONTENTS Agency Information... 1 Overview... 1 Mission, Vision and Goals... 1 GSA Priorities...
DIRECTIVE TRANSMITTAL
U.S. NUCLEAR REGULATORY COMMISSION DIRECTIVE TRANSMITTAL TN: DT-07-08 To: Subject: Purpose: Office and Division of Origin: NRC Management Directives Custodians Transmittal of Management Directive 2.8,
Quality Assurance Program Plan. July 2006. U.S. Department of Energy Office of Legacy Management
U. S. Department of Energy Office of Legacy Management July 2006 July 2006 Page i DOE-LM Policy Statement The U.S. Department of Energy (DOE) Office of Legacy Management (LM) performs long-term surveillance