Developing a Project Governance Framework
|
|
|
- Ilene Moore
- 9 years ago
- Views:
Transcription
1 Developing a Project Governance Framework Ross Garland 1 Introduction The UK Government lists "decision making failures" as one of the top 5 causes of project failure. Victorian Treasury which runs the Victorian Gateway Review Process lists project governance and stakeholder management as the second and third most common causes of project failure. Effective project governance underpins project success and results in efficient and timely project decision making. And yet, project governance appears to be a haphazard affair with few, if any, established principles, let alone common structures. Most organisations can display a multiplicity of governance arrangements often with little commonality even between projects of a similar type. Few organisations have a principles based project governance policy that defines a common and structured approach to project governance. This paper establishes four key principles designed to avoid the common failures associated with ineffective project governance. It then develops a project governance structure that puts these principles into action. The framework is applicable to most projects in most organisations but focused primarily on high risk projects. Lower risk projects should subscribe to the same principles but their implementation can take different forms to suit the needs of the organisation. The paper provides guidance on how to select the role holders to ensure the correct persons hold the correct positions. The governance framework is applicable to all projects, whether they be ICT, business change or infrastructure. The framework is applicable throughout the full life cycle of a project, commencing at concept development and continuing through to commissioning. 2 Principles Good project governance is based around 4 key principles. 2.1 Identify a single point of accountability It is crucial to identify the person accountable for the success of the project. This determines who is driving the project forward and who is empowered to make key project decisions. Too often this is either left unstated or, worse, is placed in the wrong hands. Equally, all personnel involved in the project governance structure need to know for what they are accountable and responsible. Accountability cannot be shared - more than one person, or a committee, cannot be held accountable for the success of a project - or delegated. Without a single point of accountability, the project lacks clear authority because the validity of any decision is questionable since the authority that lies behind that decision has not been established. This can be particularly noticeable during project initiation, where rather than the
2 project being driven by one person with the necessary authority, it is forced to generate its own momentum by building consensus and support. 2.2 Ensure project governance is service delivery focussed While most people now acknowledge the key difference between service delivery and project delivery, this is not always effectively translated into the project governance structure. Hence key project decision forums are sometimes provider led rather than customer/purchaser led. Good project governance requires the Customer retain the key project decision making responsibility throughout the project since the Customer owns the project Business Case and the project budget. Provider led project governance structures, that is, those led by the project delivery arm of the organisation whether that be a capital works group in the infrastructure sector or an IT group in the ICT/business change sector, are not focussed on service delivery outcomes. This is only natural since the customer/purchaser and the delivery arm/provider each have their own business case. The providers, especially when an in-house provider is used, may well be unstated but it will be implicit and derived from the strategic goals of the provider s organisation. There is always a tension between these two business cases and for the provider to be responsible for delivering both presents a significant problem for the Customer. 2.3 Separate project and organisational governance Project governance, the process by which project decisions are made and issues resolved, is separate and different to organisational governance. Separating these two structures will reduce the number of project decision nodes since the decision path will not follow the organisational line of command. Confusing them will result in multi layered decision making causing three fundamentally negative impacts on the project: Decision making is slowed not only because of the extra decision layers but because organisational governance often relies upon consensus building so at each level of the organisation support is sought for any decision taken. The quality of the decision is impacted since those involved don t necessarily have the prerequisite knowledge and understanding of the project and its issues The authority of the project and its governance body is compromised since decisions are not binding but have to be ratified by the organisation. 2.4 Separate stakeholder management and project decision making Stakeholder management and project decision making are two separate functions and must be addressed separately. When the two are confused, decision making forums become clogged with stakeholders resulting in labored decision making. While many people may need to be aware of a project and have input into shaping it, not everyone needs to participate in each critical project decision. Achieving separation will reduce the number of persons required in project decision forums while maintaining the essential input provided by key stakeholders. The framework establishes a mechanism for addressing the needs of stakeholders.
3 Effective stakeholder management is essential for the success of any project. Supporting the needs of stakeholders requires communication channels to be established and reporting frameworks to be developed. Stakeholders must have the opportunity to have their views heard and their issues and concerns raised and addressed. These tasks can however be done separately to the function of project decision making. The most critical stakeholders of course are, or should be running the project and holding the key roles in the decision making framework. We deal with this shortly. Stakeholders less centrally aligned to the core service delivery outcomes the project is designed to achieve have narrower and more specific interests in the project. Thus the need for such stakeholders to be involved in each and every significant project decision is less and their ability to usefully contribute to all such decisions is constrained. This principle is an acknowledgement of this fact. It does not remove stakeholders from the project. It recognises that they have different needs and that these are better met in a stakeholder forum than in a focused decision making forum. 2.5 Project Governance Framework Figure 1 proposes a core project governance structure to meet the needs of high risk projects based on the above principles. Investment Decision Group decision making path advisory & feedback path Strategic Advisors Group Senior User Project Owner Senior Supplier Chair: Project Owner Project Director Project Board Stakeholder Working Group Chair: Project Director Project Manager Project Team Figure 1 Project Governance Framework 1 Accountability for the success of the project sits with the Project Owner who chairs the Project Board. The structure is completely separate to that of the organisation. Organisational decision making plays no part in project decision making under this arrangement. Note though, that key organisational roles may sit within the Strategic Stakeholders 7KH3URMHFW%RDUGDQGWKHUROHVRI3URMHFW2ZQHU6HQLRU8VHUDQG6HQLRU6XSSOLHUDUHGUDZQIURPDQGVLPLODU WR WKRVH LQ 35,1&( D SURMHFW PDQDJHPHQW PHWKRGRORJ\ XVHG H[WHQVLYHO\ DFURVV WKH 8. *RYHUQPHQW DQG LQFUHDVLQJO\LQ(XURSHDQG$XVWUDOLD,WLVDGPLQLVWHUHGE\WKH8.2IILFHRI*RYHUQPHQW&RPPHUFH2*&
4 Group and provide valuable input to and remain briefed on project developments. The structure recognises however that the decision making path is via the Project Board. Note that this structure does not set out to address the project s communications or reporting needs. There may be many within the organisation structure who will require briefing on the project or who will receive regular project reports. The Project Owner and Project Director will need to establish reporting and communications frameworks to enable this. But, again, this is separate to project decision making. The stakeholder forums and decision making forum (Project Board) are kept separate to ensure that the latter is an efficient size. 2.6 Project Board Membership Project Owner The Project Owner is the person accountable for the success of the project and owns the Business Case. The Project Owner therefore chairs the Project Board which exists to support the Project Owner and assist in the decision making process. However the final say on any decision rests with the Project Owner since that is where the ultimate accountability lies. The Project Owner is normally the person that has project budget responsibility since responsibility for a budget implies responsibility for what the budget is spent on budget responsibility implies project accountability. The Project Owner should appoint Project Board members. The Project Owner chairs the Strategic Advisors Group Senior User The Senior User represents the end users of the delivered service and promotes their concerns and interests. If there is a Project User Group, it is chaired by the Senior User The Senior User may also represent those who have an interest in the project s outcomes and whose activities will be affected by the project. They may share in the benefits of the project or in its investment or operational costs. The Senior User may assist the Project Owner in chairing of the Strategic Advisors Group Senior Supplier The Senior Supplier is a senior representative of the project s suppliers and provides their perspective and expertise. Successful projects maintain a close relationship between the customer and their suppliers and this is reflected in the latter s membership of the Project Board. The holder of the Senior Supplier role may change as the project transitions from the Business Case phase to the construction phase. On large projects, particularly when the client organisation has a project delivery arm that has contracted with an outside delivery entity, more than one Senior Supplier may sit on the Project Board (albeit with individual role statements) Project Director The Project Director is the Project Owner s eyes and ears on the job. This role undertakes day to day management and decisions on behalf of the Project Owner. The Project Director
5 supports the Project Owner and reflects the reality that the Project Owner may not have the time available to devote themselves full-time to the project. The Project Director chairs the Stakeholder Working Group Size of the Project Board The Project Board provides the Project Owner with stakeholder and technical input to decisions affecting the project. Other people s expert opinion may also be sought such as the views of corporate or program management, technical specialists or other key stakeholders (perhaps from other departments). Generally however, this input will be provided via stakeholder groups. There may be valid reasons for having more than one Senior User on a project, particularly when the project is multi-agency. As stated above, there are also circumstances where more than one Senior Supplier may sit on the Project Board. There can only ever be one Project Owner since project accountability cannot be shared, and there should only be one Project Director. As a general rule the Project Board should contain no more than 6 people to maintain decision making efficiency. 2.7 Decision Making The Project Manager and his team will make the vast majority of project decisions, for the sake of argument say 95%. Of the remainder, 4% will be made at the Project Board level. These decisions will be around key project documents such as endorsing the Business Case for Investment Decision Group approval, approving the Project Plan and so on. Issues that the Project Manager is unable to resolve will also be addressed by the Project Board. The Investment Decision Group are required to make project investment decisions which normally involve approving the Business Case and any changes to it. 2.8 Stakeholder Groups Strategic Advisors Group This group represents key stakeholders that have a valid interest in the project yet are not sufficiently central to the project s success to warrant a seat on the Project Board. This group is chaired by the Project Owner thus ensuring the views, concerns and issues in this group have a direct conduit to the Project Board Stakeholder Working Group This group represents the interests of stakeholders operating at a more detailed level. It is chaired by the Project Director thus ensuring this group also has a direct conduit to project decision making.
6 2.9 The Role of the Investment Decision Group The Investment Decision Group has the following responsibilities: Approves project investment decisions. This primarily revolves around the Business Case however an earlier investment decision justifies the work required in undertaking development of the Business Case. This decision is normally based on a project brief or proposal and is also taken by the Investment Decision Group. Approves any changes that subsequently impact the project investment decision or any changes to the project Business Case. Responsible for those project decisions, raised by the Project Board, that potentially impact organisational policy or strategy. Responsible for the resolution of issues elevated by the Project Board. 3 Implications for the organisation The project governance framework exerts a positive influence on both Customers/Purchasers and Supplier/Provider. The Customer/Purchaser business is driven down a path of greater sophistication in order to respond to the accountability needs imposed by the framework. The framework requires the Customer to become more involved in projects and requires them to accept ownership of the project. The concept of hand-over of a project does not exist in this framework. Consequently, the Customer focussed business needs the resources to operate to this new paradigm. Commonly, when organisations are faced with a large increase in capital works, the standard and natural response is to increase resourcing in the Provider/Supplier function of the business. This framework drives an increase in Customer/Purchaser resources as well. A common impact of this framework on organisations is they find the Customer/Purchaser business is insufficiently resourced to fulfil the role demanded of it. A clear sign of this is when a single Project Owner is named for a string of high risk projects more than they could reasonably be expected to manage. There is great potential for the Supplier/Provider business to also benefit from these arrangements. In order to successfully deliver to the Customer/Purchaser, the Supplier/Provider must be presented with a detailed brief and ongoing project involvement and ownership to ensure delivery success. The alternative path, where the Supplier/Provider takes an ill-defined brief and delivers a project with little or no Customer/Purchaser involvement is fraught with difficulty. This framework requires the ongoing involvement of the Customer/Purchaser and necessitates a commensurate degree of sophistication thereby enhancing the opportunity for delivery success. When the framework works effectively in an organisation, it tends to strengthen the relationship between the Customer/Purchaser and the Supplier/Provider as they work together to deliver successful outcomes.
7 4 Implementation Challenges Implementing the project governance framework is a business change management exercise. Problems likely to be encountered include: The separation of project governance from organisational governance is difficult. An example is approval of the Project Plan which you would think implies approval of project resourcing since it is an integral part of that plan. However, most organisations have detailed approval processes for the hiring of staff and contractors and have difficulty aligning them with a project s approval under its governance structure. Another example is the approval by the Project Board of the Business Case. This framework explains that the people who best understand the needs of the project have signed off on the Business Case and it may therefore proceed directly to the Investment Decision Group. Some organisations will have difficulty with this approach given the importance of that document and will still expect the Business Case to be approved via the organisations chain of command. The project governance structure is only as strong as the Project Board and to be effective it needs to be populated with the right caliber of people who understand projects. Without this, the project board will lack authority and project decision making will be poor. The framework requires the Customer to be resourced to meet the increased needs of their ongoing role in the project. There is likely to be a need to increase resources in the Customer/Purchaser side of the business. In organisations with both Customer/Purchaser and Supplier/Provider functions, there can be a perception by the Supplier/Provider of a loss of power. This is particularly evident if old project governance structures have been chaired by the Supplier/Provider as is sometimes the case. The reality is that the framework will enhance the ability of the Supplier/Provider to deliver to the Customer s expectations and this is the message that needs highlighting. <end>
Improving Project Governance
Improving Project Governance By Phil Mann 31 October 2012 Overview This whitepaper provides a synopsis of the Victorian Government s Ombudsman s Own motion investigation into ICT-enabled, November 2011.
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
JOB DESCRIPTION GBS 1 ST DRAFT DRAFT V02 DRAFT V03 GBS GBS
JOB DESCRIPTION JOB TITLE: SERVICE DESK MANAGER DOCUMENT CONTROL VERSION DATE OF ISSUE AUTHOR REASON FOR REVISION DRAFT V0.1 1 ST NOVEMBER 2013 GBS 1 ST DRAFT DRAFT V02 DRAFT V03 31ST MARCH 2014 3 JULY
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Relationship Manager (Banking) Assessment Plan
1. Introduction and Overview Relationship Manager (Banking) Assessment Plan The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It forms a key
Data controllers and data processors: what the difference is and what the governance implications are
ICO lo : what the difference is and what the governance implications are Data Protection Act Contents Introduction... 3 Overview... 3 Section 1 - What is the difference between a data controller and a
How To Manage A Contract
Contract Management Checklist Preparation This section deals with laying good foundations before a contract is let. The contract should be actively managed. You should have a plan for doing this, which
Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors
Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table
U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER
U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER As at 31 March 2014 BOARD CHARTER Contents 1. Role of the Board... 4 2. Responsibilities of the Board... 4 2.1 Board responsibilities... 4 2.2 Executive
PRINCE2 and governance
PRINCE2 and governance Andy Murray, lead author of PRINCE2 (2009) and Director of Outperform UK Ltd White Paper November 2011 2 PRINCE2 and governance Contents 1 Purpose of this white paper 3 2 What is
Project Governance. New Corporations Unit (NewCo) PWC Structural Separation Program
New Corporations Unit (NewCo) Department of the Chief Minister Level 14, NT House, 22 Mitchell Street, Darwin PWC Structural Separation Program Project Governance January 2014 Table of Contents 1. Introduction...
Chapter 2. Key issues and committee view
Chapter 2 Key issues and committee view 2.1 The submissions received by the inquiry overwhelmingly supported the establishment of the ASBFE Ombudsman position, and its proposed role of supporting small
An Introduction to PRINCE2
Project Management Methodologies An Introduction to PRINCE2 Why use a Project Methodology and What Does PRINCE2 Enable? PRINCE - PRojects IN Controlled Environments - is a project management method covering
INTERNAL AUDIT FRAMEWORK
INTERNAL AUDIT FRAMEWORK April 2007 Contents 1. Introduction... 3 2. Internal Audit Definition... 4 3. Structure... 5 3.1. Roles, Responsibilities and Accountabilities... 5 3.2. Authority... 11 3.3. Composition...
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
Infratil Limited - Board Charter. 1. Interpretation. 1.1 In this Charter:
Infratil Limited - Board Charter 1. Interpretation 1.1 In this Charter: Act means the Companies Act 1993. Board means the Board of Directors of Infratil Limited. Business means the business of Infratil
Reporting of Taxable Payments to Contractors in the Building and Construction Industry. Consultation Paper
Reporting of Taxable Payments to Contractors in the Building and Construction Industry Consultation Paper The Department of Treasury Australian Government Submission of The Recruitment and Consulting Services
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
Chapter 11: ORGANIZATIONAL STRUCTURES: CONCEPTS AND F0RMATS
Montana, P. and Charnov, B. Management: A Streamlined Course for Students and Business People. (Hauppauge, New York: Barron s Business Review Series, 1993), pp. 155-169. Chapter 11: ORGANIZATIONAL STRUCTURES:
2015 19 Strategic Plan
2015 19 Strategic Plan humanservices.gov.au The strategic plan outlines our vision, mission, strategic themes and strategic priorities. 2 Strategic Plan 2015 19 Table of Contents Message from the Secretary
Audit and risk assurance committee handbook
Audit and risk assurance committee handbook March 2016 Audit and risk assurance committee handbook March 2016 Crown copyright 2016 This publication is licensed under the terms of the Open Government Licence
A Guide to Corporate Governance for QFC Authorised Firms
A Guide to Corporate Governance for QFC Authorised Firms January 2012 Disclaimer The goal of the Qatar Financial Centre Regulatory Authority ( Regulatory Authority ) in producing this document is to provide
CONSULTATION PAPER CP 41 CORPORATE GOVERNANCE REQUIREMENTS FOR CREDIT INSTITUTIONS AND INSURANCE UNDERTAKINGS
CONSULTATION PAPER CP 41 CORPORATE GOVERNANCE REQUIREMENTS FOR CREDIT INSTITUTIONS AND INSURANCE UNDERTAKINGS 2 PROPOSAL 1.1 It is now widely recognised that one of the causes of the international financial
TERMS OF REFERENCE - MAJOR EVENTS PANEL
TERMS OF REFERENCE - MAJOR EVENTS PANEL OVERVIEW The Major Events Panel is a specialist advisory body to the UK Sport Board and its Major Events Team. Its main purpose is to represent the interests of
Annex B: Payment and Expenses for Governors
A REVIEW OF FURTHER EDUCATION AND SIXTH FORM COLLEGE GOVERNANCE Annex B: Payment and Expenses for Governors JULY 2013 Annex B: Payment and Expenses for Governors Introduction 1. This document has been
HANDY HINTS...... FOR IN-HOUSE COUNSEL. Law Society of New South Wales Corporate Lawyers Committee
HANDY HINTS...... FOR IN-HOUSE COUNSEL Law Society of New South Wales Corporate Lawyers Committee AIM In-house lawyers are subject to the same ethical rules as private practitioners. However, in-house
The Audit Committee self-assessment checklist
GOOD PRACTICE The Audit Committee self-assessment checklist 2nd edition January 2012 Financial Management and Reporting 2 The Audit Committee self-assessment checklist Our vision is to help the nation
(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and
Agenda Item No. 7 Governance Committee 23 November 2015 Partnership Governance for Contract Management Report by Director of Law Assurance and Strategy Executive Summary This report sets out some areas
Application of King III Corporate Governance Principles
APPLICATION of KING III CORPORATE GOVERNANCE PRINCIPLES 2013 Application of Corporate Governance Principles This table is a useful reference to each of the principles and how, in broad terms, they have
BUILDING A HIGH PERFORMING SYSTEM. A business improvement plan for the Department for Education and Child Development
BUILDING A HIGH PERFORMING SYSTEM A business improvement plan for the Department for Education and Child Development BUILDING A HIGH PERFORMING SYSTEM 1 Contents Executive summary 3 Increasing local decision-making
PUBLIC SERVICE COMMISSION AUDIT REPORTS 2012
PUBLIC SERVICE COMMISSION AUDIT REPORTS 2012 All of the audit work in this publication was conducted in accordance with the legislative mandate and audit policies of the Public Service Commission of Canada.
KING III CORPORATE GOVERNANCE COMPLIANCE REGISTER
KING III CORPORATE GOVERNANCE REGISTER CHAPTER 1: ETHICAL LEADERSHIP AND CORPORATE CITIZENSHIP NON 1.1. The board should provide effective leadership based on an ethical foundation 1.2. The board should
Benefits realisation. Gate
Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland
Application of King III Corporate Governance Principles
Application of Corporate Governance Principles Application of Corporate Governance Principles This table is a useful reference to each of the principles and how, in broad terms, they have been applied
European Security Standards Reference Implementation Initiative (ESSRII)
European Security Standards Reference Implementation Initiative (ESSRII) A Proposal for Action in Europe on International Information Security Standards Brian Gladman, European Technical Director, Trusted
Hon Nikki Kaye Minister for ACC December 2015
Currently accident compensation appeals before the District Court have an average age of 669 days. This is far too long for people waiting for their accident compensation claim to be resolved. As part
e-colt Services Recruitment Process Outsourcing (RPO)
e-colt Services Recruitment Process Outsourcing (RPO) Introduction Recruitment Process Outsourcing (RPO) offers executives a potential competitive advantage in the marketplace as it provides organizations
Housing Association Regulatory Assessment
Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08
Performance Detailed Report May 2008 Review of Performance Management Audit 2007/08 External audit is an essential element in the process of accountability for public money and makes an important contribution
Please contact me on 0207 213 4378 or [email protected] if you would like to discuss this further.
House of Commons Public Bill Committee, Scrutiny Unit, 7 Millbank, London, SW1P 3JA. 8 September 2014 Dear Sirs, Modern Slavery Bill call for written evidence We appreciate the opportunity to respond to
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Update on Programme Management Controls & Risks
Committee and Date Audit Committee 26/06/14 Update on Programme Management Controls & Risks Responsible Officer George Candler Director of Commissioning e-mail: [email protected] Tel: 01743
CJS Data Standards Forum Terms of Reference. Version 2.0
CJS Data Standards Forum Terms of Reference Criminal Justice System Data Standards Forum Terms of Reference 1 Table of Contents 1 Introduction 2 1.1 Purpose 2 1.2 ToR Principles 2 1.3 Technical Remit of
Document management concerns the whole board. Implementing document management - recommended practices and lessons learned
Document management concerns the whole board Implementing document management - recommended practices and lessons learned Contents Introduction 03 Introducing a document management solution 04 where one
RISK MANAGEMENT FRAMEWORK
RISK MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Manager Organisational Development
Australian Safety and Quality Framework for Health Care
Activities for HEALTH SERVICE EXECUTIVES and BOARDS Australian Safety and Quality Framework for Health Care Putting the Framework into action: Getting started Contents Principle: Consumer centred Area
January 2016. Brand and Campaigns Executive: Information for Candidates
January 2016 Brand and Campaigns Executive: Information for Candidates Thank you for expressing interest in the role of Brand and Campaigns Executive. We have compiled this information pack to tell you
Managing Outsourcing Arrangements
Guidance Note GGN 221.1 Managing Outsourcing Arrangements 1. This Guidance Note provides further detail on the requirements for managing material outsourcing arrangements (refer Prudential Standard GPS
The Role and Function of a Data Protection Officer in the European Commission s Proposed General Data Protection Regulation. Initial Discussion Paper
The Role and Function of a Data Protection Officer in the European Commission s Proposed General Data Protection Regulation 1. Introduction Initial Discussion Paper The data protection officer ( DPO )
Service Management and ICT Monitoring and Reporting Advisory and Implementation Services
Service Management and ICT Monitoring and Reporting Advisory and Implementation Services G-Cloud Service 1 1. An overview of the G-Cloud Service Arcus can assist you with a review and advice on the effectiveness
Health Consumers Council - Strategic Plan 2013-2015
Health Consumers Council - Strategic Plan 2013-2015 Vision: Western Australian health consumers achieve the best possible outcomes from WA s public and private health services. HCC works to support the
SINGLE RESOLUTION BOARD VACANCY NOTICE ICT PROJECT MANAGER AND BUSINESS ANALYST (SRB/AD/2015/017)
SINGLE RESOLUTION BOARD VACANCY NOTICE ICT PROJECT MANAGER AND BUSINESS ANALYST (SRB/AD/2015/017) Type of contract Temporary agent Function group and grade AD6 Duration of contract 3 years (renewable)
SECURITY ORGANISATION Security Awareness and the Five Aspects of Security
SECURITY ORGANISATION Security Awareness and the Five Aspects of Security Shift Security simply used to protect information vs. Enabling business initiatives with security Bolt-on/add-on structure to business
National Principles for Disaster Recovery
National Principles for Disaster Recovery Introduction Recovery is a significant component within Australia s comprehensive approach to emergency management (Prevention, Preparedness, Response, and Recovery).
UNSOLICITED PROPOSALS
UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
. Board Charter - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1. Interpretation 1.1 In this Charter: Act means the Companies
CORPORATE GOVERNANCE - BOARD CHARTER PART A DEFINING GOVERNANCE ROLES
CORPORATE GOVERNANCE - BOARD CHARTER PART A DEFINING GOVERNANCE ROLES 1. ROLE OF THE BOARD 1.1 Function The Board of Directors of Exalt Resources Limited have approved the following charter formalising
Recruitment Outsourcing:
Recruitment Outsourcing: Look Before You Leap The Benefits & Pitfalls of Recruitment Process Outsourcing (RPO) Introduction The outsourcing of administratively intensive HR functions is not new, and for
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
How To Improve Training In Australia
New Arrangements for Training Product Development for Australian Industry ED15-0079 1 Key messages The Government aims to enhance Australia s economic prosperity by ensuring the future and emerging skills
CORPORATE GOVERNANCE ROLE OF THE BOARD OF GOVERNORS
CORPORATE GOVERNANCE The Board is a corporate body. This means it is a body composed of a number of individuals who are empowered to act as a single person with a separate identity from that of its individual
Feedback on the Inquiry into Serious Injury. Presented to the Road Safety Committee of the Parliament of Victoria. 08 May 2013
Feedback on the Inquiry into Serious Injury Presented to the Road Safety Committee of the Parliament of Victoria 08 May 2013 About the APA The Australian Physiotherapy Association (APA) is the peak body
WORK HEALTH AND SAFETY CONSULTATION, CO-OPERATION AND CO-ORDINATION
WORK HEALTH AND SAFETY CONSULTATION, CO-OPERATION AND CO-ORDINATION Code of Practice DECEMBER 2011 Safe Work Australia is an Australian Government statutory agency established in 2009. Safe Work Australia
CIMA E1 Course Notes. Chapter 1. Introduction to Organisations
CIMA E1 Course Notes Chapter 1 Introduction to Organisations 1. Organisations Introduction An organisation is a social group of people that is organised and managed in a way that aims to follow a corporate
Trust Board Report. Review of the effectiveness of the IM&T Committee
1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments
Briefing Paper. How to Compete on Customer Experience: Six Strategic Steps. www.syn gro.c om SynGro SynGro 2013 2013 Tel: +44 (0 ) 15 06 5 92 2 24
Briefing Paper How to Compete on Customer Experience: Six Strategic Steps How to Compete on Customer Experience: Six Strategic Steps Voice of the Customer as a term has come to reflect the growing understanding
WHITE PAPER. From Building Information Management to Facilities Management
October 2011 WHITE PAPER. Management to Facilities Management A look at the benefits to be found by fostering the links between Building Information Modelling (used by the construction industry) and Computer
Symposium report. The recruitment and retention of nurses in adult social care
Symposium report The recruitment and retention of nurses in adult social care Overview 1. Social care employers providing nursing care services have been raising concerns about nursing recruitment and
Chiropractic Boards response 15 December 2008
NATIONAL REGISTRATION AND ACCREDITATION SCHEME FOR THE HEALTH PROFESSIONS Chiropractic Boards response 15 December 2008 CONSULTATION PAPER Proposed arrangements for accreditation Issued by the Practitioner
BUSINESS FOCUSED PROJECT MANAGEMENT
BUSINESS FOCUSED PROJECT MANAGEMENT By Dennis Comninos & Enzo Frigenti Synopsis This article addresses the concepts and issues of business project management. It aims to assist organizations in making
FSDF SPATIAL INFORMATION MANAGEMENT POLICIES - CUSTODIANSHIP
FSDF SPATIAL INFORMATION MANAGEMENT POLICIES - CUSTODIANSHIP Objective: To provide consistent custodial arrangements so that spatial information is managed to appropriate standards and made available in
Advisory Note - October 2005. Disclosure and management of conflict of interest for advisers
Advisory Note - October 2005 Disclosure and management of conflict of interest for advisers The Secretary Department of Treasury and Finance 1 Treasury Place, Melbourne Victoria 3002 Australia Telephone:
WorkCover Medical Advisory Panel tender Briefing. 4 October 2013
WorkCover Medical Advisory Panel tender Briefing 4 October 2013 Agenda - Corporate objectives - Overview - Industry alignment and value added services - Service level standards - Health benefits of work
Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development)
Meeting: Cabinet Date: 6 October 2005 Subject: Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development) Contact Officer: Portfolio Holder: Key
Schroders Investment and Corporate Governance: Schroders Policy
January 2013 Schroders Investment and Corporate Governance: Schroders Policy Contents Investment and Corporate Governance: Schroders Policy 2 Corporate Governance: The Role and Objectives of Schroders
Local Healthwatch and NHS Complaints Service. Cabinet member: Cllr John Thomson - Adult Care, Communities and Housing
Wiltshire Council Cabinet 23 October 2012 Subject: Local Healthwatch and NHS Complaints Service Cabinet member: Cllr John Thomson - Adult Care, Communities and Housing Key Decision: Yes Executive Summary