University Website Development Project
|
|
|
- Meagan Chandler
- 10 years ago
- Views:
Transcription
1 Information Services Knowledge Strategy Committee 16 June 2009 University Website Development Project Brief description of the paper This paper provides an update to KSC on project progress for the University Website. Charts are attached to give an indication of timeframes for rollout. Action requested For information Resource implications Does the paper have resource implications? No Risk Assessment Does the paper include a risk analysis? No Equality and Diversity Does the paper have equality and diversity implications? No Originator of the paper [Name and function; date of preparation- these should also occur on the paper itself.] Freedom of information Can this paper be included in open business? Yes June 2009
2 University Website Development Project Project progress since the 13/1/2009 KSC update School and unit progress (charts attached) The Project team is pleased to report that progress is generally good. Two MVM, one HSS and six support group (CSG and SASG) sites have gone live since the last update in January One more HSS school site is due to go live mid-june. Six more CSG sites will be live by end June. Good progress is being made with all groups in CSG with many more units now in the population phase of their new sites. ISG has a solid plan in place, the group is committed to delivering an initial release by end August. Momentum is strong in the support groups with the academic units beginning to come on board. The Project Team is now engaging with remaining schools (those not featured on the attached charts) to confirm commitment and ensure an agreed time slot with them for engagement, planning and training during Clarity of vision and measurable goals for the final year of the Project The Project Team has set about defining more measurable goals for schools rollout which should help with the assessment of the Project s success at close of play Timeframes for delivery of sites for remaining schools are very tight. The Project should have a clearer view of feasible deliverables in by the end of June. User centred content management, the challenges The Project Team continues to meet the challenges of working with very limited resource and having to push on in order to meet extremely demanding delivery targets. We recognise that there is no one way to conduct a rollout with schools. A series of models is being developed with early adopters. This takes in to consideration influencing factors such as other web technologies in use, the depth and breadth of ownership across the site and current information architecture. By engaging with the Project, Heads of School are beginning to appreciate the need for the involvement of their key management colleagues on site content assessment and prioritisation. This is leading to an understanding of the need for resource commitment on their part. This is not a content migration exercise. New websites should: Meet the expectations of target audiences Deliver the school s key online business objectives Reflect a certain level of consistency with the rest of the University Evolving content management tool Polopoly continues to be developed bringing enhancements to the publishing tool, as requested by early users of the software. The University-wide Technical Peer Group is now fully engaged in the development consultation process. Decisions around all new developments will have had input from the Group and, as a consequence, the Project Team should have a deeper understanding of school and unit needs. June 2009 Page 1 of 2
3 Training and support Training is being delivered with an edited, more user-friendly training manual now in place. The Polopoly user support website provides the focal point for communications around training and development support. Current Polopoly users are consulted via this wiki for their thoughts on enhancement requirements. Their input feeds in to the design evolution of the tool, complementing engagement with the Technical Peer Group. EUCLID coordination It was agreed at the last KSC that we would establish more formal coordination between the two major University Projects. EUCLID is now represented on the University Website Project Board by Morag Hunter, Deputy Director of EUCLID. Jeff Haywood represents the Website Project on the EUCLID board. A new theme for the website A group has been established to deliver a new theme to the University website, supporting the University s Internationalisation strategy. A paper outlining the content and approach for Edinburgh Global was approved by the Website Project Board in May Below is an extract from the paper delivered to the Project Board: The Edinburgh Global website will support the University s Internationalisation Strategy. It will demonstrate a step-change in the communication of the University s global influence and perception. The University s position as a global leader in education and research will be palpable from the outset. This part of the University of Edinburgh website will stand apart from the rest in that it will provide an international focal point for visitors. The content will tell a story in a language which is accessible to all (whatever their native language or area of professional or research expertise). It will provide a home for the sharing of information on the University s international activities and give the space to showcase our international achievements. Project exit strategy The Project Director has been asked to create an exit strategy for She will develop possible scenarios and present them to Professor Haywood for reflection and comment. The University community will need to be clear about where to seek support for all ongoing website development activities from a/y Possible solutions will be delivered for discussion towards the end of the year. June 2009 Page 2 of 2
4 Activity Forecast, June 2009 Page 1 of 3
5 Activity Forecast, June 2009 Page 2 of 3
6 Activity Forecast, June 2009 Page 3 of 3
REQUEST FOR PROPOSAL. WEB SITE DESIGN and DEVELOPMENT. Native Health News Alliance. August 19, 2013
Native American Journalists Association University of Oklahoma Gaylord College 395 W. Lindsey Norman, OK 73019 Office Phone: 405-325-1649 Fax: 405-325-6945 www.naja.com @najournalists REQUEST FOR PROPOSAL
Career proposition for software developers and web operations engineers
Career proposition for software developers and web operations engineers Introduction The Government Digital Service is at the centre of the digital transformation of government, making information and
RESPONSIBILITY BEYOND SOFTWARE
RESPONSIBILITY BEYOND SOFTWARE Q&A with Richard Kirby, Product Director, cr360 In June 2015, leading sustainability software company cr360, formerly CRedit360, launches its new vision: Responsibility beyond
MUSEUM VICTORIA ONLINE STRATEGY
MUSEUM VICTORIA ONLINE STRATEGY November 2007 VISION A dynamic online presence that integrates and coordinates knowledge sharing, discoverability and access. BACKGROUND Museum Victoria s online presence
Campaign Visioning Project & Integrated Marketing Strategy
Campaign Visioning Project & Integrated Marketing Strategy June 4, 2013 1 Agenda Introduction Campaign Visioning Project Overview Reputation Situation Analysis Integrated Marketing Recommendations 2 Campaign
The University of Tasmania Library Future Vision to 2025
The University of Tasmania Library Future Vision to 2025 Great universities have great libraries Vice-Chancellor, Professor Peter Rathjen Address to the Council of Australian University Librarians, September
Skills Audit for Researchers
Skills Audit for Researchers Date: Section 1: Research Management Skills 1) Research management to be able to: Project management 1.1) Apply effective project management through the setting of research
The Art of CRM. A white paper by cloudfortyseven Limited. Author: Michael Fleming DipM ACIM
The Art of CRM A white paper by cloudfortyseven Limited Author: Michael Fleming DipM ACIM Copyright 2010 by cloudfortyseven Limited all the text, graphics, design, and other works are the copyrighted works
The PMO as a Project Management Integrator, Innovator and Interventionist
Article by Peter Mihailidis, Rad Miletich and Adel Khreich: Peter Mihailidis is an Associate Director with bluevisions, a project and program management consultancy based in Milsons Point in Sydney. Peter
Risk Management. National Occupational Standards February 2014
Risk Management National Occupational Standards February 2014 Skills CFA 6 Graphite Square, Vauxhall Walk, London, SE11 5EE T: 0207 0919620 F: 0207 0917340 E: [email protected] www.skillscfa.org Skills
How to organise / structure an e-commerce team
How to organise / structure an e-commerce team This note has been written by Michael de Kare-Silver Michael has been involved in the digital technology, e-commerce and Mobile world for some 15 yrs. He
Introduction. Contents. Introducing the DSDM Agile Project Framework. Introducing DSDM
Contents Introduction... 2 Introducing the DSDM Agile Project Framework... 2 Introducing DSDM... 2 Introducing Scrum... 3 The DSDM Agile Project Framework for Scrum... 4 Philosophy... 4 Values... 4 Principles...
Career Management. Making It Work for Employees and Employers
Career Management Making It Work for Employees and Employers Stuck in neutral. That s how many employees around the world would describe their career. In fact, according to the 2014 Global Workforce Study,
Data Visualization on Istat's Web site. Giulia Mottura Vincenzo Patruno
on Istat's Web site Giulia Mottura Vincenzo Patruno Istat - Aula Magna 26 Aprile 2010 Value of Data Visualization Latest web technologies and the expectations they create amongst the user community are
Computing & Communications Services
2010 Computing & Communications Services 2010 / 10 / 04 Final Kent Percival, M.Sc., P.Eng. Defining the Value of the Business Analyst In achieving its vision, key CCS partnerships involve working directly
developing an action plan Implementing change: Implementing change: developing an action plan
Implementing change: developing an action plan Implementing change: developing an action plan Implementing change: developing an action plan Implementing change overview The change process through which
Manage Release and Deployment
Manage Release and Deployment Description Once development is complete, new and enhanced services need to be made operational. Effective requires planning, scheduling and controlling the implementation
Improving Accountability: Developing an Integrated Performance System
OCCASIONAL PAPER No. 11 Improving Accountability: Developing an Integrated Performance System This paper was prepared as part of the State Services Commission's "Improving Accountability" project, and
MARKETING & COMMUNICATIONS MANAGER CULTURAL SKILLS & CREATIVE ECONOMY
. MARKETING & COMMUNICATIONS MANAGER CULTURAL SKILLS & CREATIVE ECONOMY This Marketing & Communications Manager leads on the development and delivery of marketing and communications for the Cultural Skills
Martyn Wade National Librarian and Chief Executive National Library of Scotland Edinburgh, Scotland, United Kingdom
http://conference.ifla.org/ifla78 Date submitted: 6 June 2012 Re-inventing the Library the role of strategic planning, marketing and external relations, and shared services at the National Library of Scotland
International Society of Exposure Science (ISES) Strategic Plan: Creating a Safer and Healthier World by Advancing The Science of Exposure 2008 2011
International Society of Exposure Science (ISES) Strategic Plan: Creating a Safer and Healthier World by Advancing The Science of Exposure 2008 2011 Executive Summary Changes in the field of exposure have
Board of Member States ERN implementation strategies
Board of Member States ERN implementation strategies January 2016 As a result of discussions at the Board of Member States (BoMS) meeting in Lisbon on 7 October 2015, the BoMS set up a Strategy Working
IBM Enterprise Content Management Product Strategy
White Paper July 2007 IBM Information Management software IBM Enterprise Content Management Product Strategy 2 IBM Innovation Enterprise Content Management (ECM) IBM Investment in ECM IBM ECM Vision Contents
Helen Featherstone, Visitor Studies Group and University of the West of England, Bristol
AUDIENCE RESEARCH AS A STRATEGIC MANAGEMENT TOOL Sofie Davis, Natural History Museum Helen Featherstone, Visitor Studies Group and University of the West of England, Bristol Acknowledgements: The authors
This image cannot currently be displayed. D-G4-L4-241 Predictive analytics (software as service) Deloitte LLP Service for G-Cloud IV
This image cannot currently be displayed. D-G4-L4-241 Predictive analytics (software as service) Deloitte LLP Service for G-Cloud IV September 2013 Contents 1 Service Overview 1 2 Detailed Service Description
OXMS. Oxford Management Solutions Ltd. Project Management Training Portfolio. For. High Technology Companies
OXMS LIBERATE YOUR BUSINESS POTENTIAL Project Management Training Portfolio For High Technology Companies Project & Programme Management Training This portfolio is targeted at high technology companies
Financial Conduct Authority. The FCA Data Strategy - How we will manage and use the data we collect
Financial Conduct Authority The FCA Data Strategy - How we will manage and use the data we collect September 2013 Contents 1. Overview 2 2. Our vision for the future of FCA data 4 3. Our strategy to deliver
Human Resources. Values for Working Together and Professional Behaviours
Human Resources Values for Working Together and Professional Behaviours A message from the Vice-Chancellor The new Human Resources Strategy, Working Together: A Strategy for Success, in tandem with the
Introduction... 2 Introducing the DSDM Agile Project Framework (AgilePF)...2 Introducing DSDM...2 Introducing Scrum...3
Contents Introduction... 2 Introducing the DSDM Agile Project Framework (AgilePF)...2 Introducing DSDM...2 Introducing Scrum...3 AgilePF for Scrum... 4 Philosophy...4 Agile Values...4 Principles...5 Variables...8
BENEFITS REALIZATION ENSURES CHANGE DELIVERS GREATER BUSINESS VALUE
BENEFITS REALIZATION ENSURES CHANGE DELIVERS GREATER BUSINESS VALUE Focusing on the delivery of value-adding benefits is an excellent way to achieve greater ROI from change. Benefits & Value Management
Testing Websites with Users
3 Testing Websites with Users 3 TESTING WEBSITES WITH USERS Better Practice Checklist Practical guides for effective use of new technologies in Government www.agimo.gov.au/checklists version 3, 2004 Introduction
Key Steps Before Talking to Venture Capitalists
Key Steps Before Talking to Venture Capitalists Some entrepreneurs may not be familiar with raising institutional capital to grow their businesses. Expansion plans beyond common organic growth are typically
Scotland Your project business plan
Scotland Your project business plan Scotland Your project business plan Further copies available from: Email [email protected] Phone 0870 240 2391 Textphone 0141 242 1500 Our website
Model-driven Business Intelligence Building Multi-dimensional Business and Financial Models from Raw Data
Model-driven Business Intelligence Visual analytics software receives a lot of well-deserved attention these days because it has advanced to the point where it allows business users to make sense out of
Logan City Council. Strategic Planning and Performance Management Framework
Logan City Council Strategic Planning and Performance Management Framework 1 Table of contents 1. Overview 3 a) Purpose 3 b) Key Features 3 2. Context 4 a) National Framework for Sustainability 4 b) Elements
Job Description Senior Accountant
Job Description Senior Accountant Name Reports to Start date Permanent staff Business Services Manager TBA YES A Senior Accountant is a highly productive and functioning member of the team, managing work
Enterprise Content Management (ECM)
Business Assessment: A Quick-Reference Summary Intro to MIKE2 methodology and phase 1 The methodology that will be used throughout the specialist track is based on the MIKE2 methodology. MIKE stands for
The Result & Development Cycle
The Result & Development Cycle Guide for members of staff and supervisors TU Delft 101122 Foreword Dirk Jan van den Berg President of the Executive Board Nynke Jansen HR Director It is our ambition to
January 2016. Communications Manager: Information for Candidates
January 2016 Communications Manager: Information for Candidates Thank you for expressing interest in the role of Communications Manager. We have compiled this information pack to tell you more about The
JOB DESCRIPTION. Organisation Chart. Customer BI Lead. Business Insight Lead. Business Insight Manager
JOB DESCRIPTION DIRECTORATE: DEPARTMENT: JOB TITLE: BAND: BASE: REPORTS TO: IT and Business Intelligence Business Intelligence Business Insight Lead 8a Various Customer BI Lead RESPONSIBLE FOR: Business
Statement of Direction
Microsoft Dynamics NAV Statement of Direction Product strategy and roadmap for Microsoft Dynamics NAV Date: May 2012 www.microsoft.com/dynamics/nav Page 1 CONTENTS Welcome... 3 Overview of Microsoft Dynamics
National Framework for Doctoral Education
National Framework for Doctoral Education CoNtExt Ireland enjoys a centuries-old tradition in scholarship. today, it is one of the most globalised and open economies in the world. These characteristics
The Key to a Successful KM Project
Introduction An integrated PKM methodology enables organizations to maximize their investments by ensuring initiatives are on time and within budget, while sharing project challenges and successes that
Appendix 1: Performance Management Guidance
Appendix 1: Performance Management Guidance The approach to Performance Management as outlined in the Strategy is to be rolled out principally by Heads of Service as part of mainstream service management.
SAP Predictive Analysis Overview & demo SAPSA 2014. yann chagourin [email protected]
SAP Predictive Analysis Overview & demo SAPSA 2014 yann chagourin [email protected] Content Predictive analytics: what is it? SAP Predictive Analysis: solution overview Demo: customer churn prediction
Change Management Office Benefits and Structure
Change Management Office Benefits and Structure Author Melanie Franklin Director Agile Change Management Limited Contents Introduction 3 The Purpose of a Change Management Office 3 The Authority of a Change
Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager
Middlesbrough Manager Competency Framework + = Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework Background Middlesbrough Council is going through significant
Sustainable Development Strategy
Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for
Sorrento Group. Sorrento Group Caters for four main services: Sorrento Electrical Contracting, Sorrento Data Centre Consultancy
Company Profile Table of Contents About Sorrento Group 3 Sorrento Educational Consultancy 4 About Educational Consulting 5 Mission, Vision and Our Aims 6 Our services 7 Services 8 Specialised Services
UNIVERSITY OF CUMBRIA LEADERSHIP AND MANAGEMENT DEVELOPMENT STRATEGY HUMAN RESOURCES SERVICE
UNIVERSITY OF CUMBRIA LEADERSHIP AND MANAGEMENT DEVELOPMENT STRATEGY HUMAN RESOURCES SERVICE NB. This strategy is available on the University of Cumbria website and it should be noted that any printed
COMMUNICATION STRATEGY FOR THE UNIVERSITY OF GOTHENBURG
STYRDOKUMENT Dnr F V 2014/71 COMMUNICATION STRATEGY FOR THE UNIVERSITY OF GOTHENBURG Published Decision-maker Responsible body medarbetarportalen.gu.se/styrdokument Vice-Chancellor Kommunikationsenheten
The profile of your work on an Agile project will be very different. Agile projects have several things in common:
The Agile Business Analyst IT s all about being Agile? You re working as a Business Analyst in a traditional project environment, specifying the requirements for IT Developers to build. Suddenly everyone
SEARCH PROFILE. Executive Director Policy, Planning and Legislative Services. Alberta Seniors and Housing. Executive Manager I
SEARCH PROFILE Executive Director Policy, Planning and Legislative Services Alberta Seniors and Housing Executive Manager I Salary Range: $125,318 - $164,691 ($4,801.47 $6,310.03 bi-weekly) Limited Competition
Handling Requirements in Agile: BA vs. PO. April 14 th, 2011 - Agile NYC Pecha Kucha Presentation By Gene Gendel, PMP, CSM, CSP
Handling Requirements in Agile: BA vs. PO April 14 th, 2011 - Agile NYC Pecha Kucha Presentation By Gene Gendel, PMP, CSM, CSP 1 What Do We Need To Look At Today? Defining Business Analyst (BA) Defining
Our unique perspective on brand and comms tracking
Our unique perspective on brand and comms tracking Hamish Asser Research Director Introducing BrandBox A powerful, flexible and transparent brand tracking tool that monitors brand performance and identifies
Strategy 2012 2015. Providing resources for staff and students in higher and further education in the UK and beyond
Providing resources for staff and students in higher and further education in the UK and beyond Strategy 2012 2015 EDINA is a JISC National Datacentre Table of Contents Introduction... 1 Vision... 1 Mission
The overall aim for this project is To improve the way that the University currently manages its research publications data
Project Plan Overview of Project 1. Background The I-WIRE project will develop a workflow and toolset, integrated into a portal environment, for the submission, indexing, and re-purposing of research outputs
Certified Nonprofit Consultant (CNC)
Certified Nonprofit Consultant (CNC) WHY DO EXECUTIVES SECURE THE CNC CREDENTIAL?...to validate their professional achievements and personal commitment to advance the common good. Certified Fundraising
Five Steps to Android Readiness
Five Steps to Android Readiness Android State of the Union Ready or not, Android is coming to the enterprise. The rise of Google s Android operating system has ushered a new wave of mobile devices and
Applies from 1 April 2007 Revised April 2008. Core Competence Framework Guidance booklet
Applies from 1 April 2007 Revised April 2008 Core Competence Framework Guidance booklet - Core Competence Framework - Core Competence Framework Core Competence Framework Foreword Introduction to competences
Digital Industries Trailblazer Apprenticeship. Software Developer - Occupational Brief
Digital Industries Trailblazer Apprenticeship Software Developer - Occupational Brief Table of Contents Contents 1 Software Developer Trailblazer Apprenticeship Introduction... 1 2 Software Developer Trailblazer
Five Core Principles of Successful Business Architecture. STA Group, LLC Revised: May 2013
Five Core Principles of Successful Business Architecture STA Group, LLC Revised: May 2013 Executive Summary This whitepaper will provide readers with important principles and insights on business architecture
Document management concerns the whole board. Implementing document management - recommended practices and lessons learned
Document management concerns the whole board Implementing document management - recommended practices and lessons learned Contents Introduction 03 Introducing a document management solution 04 where one
Enterprise Architecture (Re)Charter Template
Enterprise Architecture (Re)Charter Template To learn more about this full research or to inquire about membership, contact us: +1-866-913-8101 IT.Support@ executiveboard.com www.cebglobal.com/it CEB Enterprise
The Advanced Program in
The Advanced Program in Project Leaders from Alberta for the World The Advanced Program in Project provides a comprehensive learning opportunity for those who are seeking to take their project management
Strategic Plan. Valid as of January 1, 2015
Strategic Plan Valid as of January 1, 2015 SBP 00001(01/2015) 2015 City of Colorado Springs on behalf of Colorado Springs Page 1 of 14 INTRODUCTION Integrated and long-term strategic, operational and financial
28 th Annual Visitor Studies Association Conference
1 Taking Action for Improvement, Growth, and Social Change 28 th Annual Visitor Studies Association Conference July 14-18, 2015 Indianapolis, IN Workshop Schedule and Descriptions Tuesday, July 14 9:00
Whatever your company s advertising needs may encompass, Silver Barrel delivers the creative solutions that are functional and look great.
Website Content Creation Silver Barrel Solutions http://www.silverbarrel.com Welcome! Silver Barrel Solutions is a creative advertising agency based in Victoria, British Columbia that takes the difficulty