1 Financing Wind Power Projects Banks risk assessments and some experiences EWEA wind policy framework workshop Riga, 15 June 2012 Hans Jacob Bull-Berg Director Nordea Export & Project Finance
2 Wind Power Project Finance Agenda 1. Off-Balance Sheet Financing the essence of Project Finance and its advantages 2. KPMG 2011 Survey on Lenders preconditions for financing 3. Digging into the risks.. 4. Experiences from past projects 2
3 1. Wind Power Project Finance single asset financing Sponsor(s) Equity Contractor Debt 2-3 Contractors, (time-certain, price-fixed contact types) Public entities Concession, permits, etc. Buyer Power Purchase Agreement (PPA) or a committed hedging strategy Operator Operations and Maintenance Agreement (O&M) Debt repayment is dependent on the cash flow from the asset being financed only no recourse to the Sponsor(s) 3
4 The advantages of off-balance sheet Project Finance Despite higher costs (than a corporate financing) PF is often chosen because: Project debt is not consolidated into the Sponsor s/investor s balance sheet (when the ownership share stays below 50%), Risks-taking is reduced to the equity share in the Project and shared with the lender(s), Practical in the case of a JV multi-party Sponsor/investor group, The financial partner party analyzes and OK s the Project and often introduces mutually beneficiary mitigants (risk reducing measures) A well structured Project Financing may be attractive for refinancing in the bond market or as a Project Finance for other banks 4
5 2. Wind Power Project Finance Lenders preferences KPMG s 2011 conclusions on Lenders major financing preconditions: PPA in place, i.e. limited appetite for merchant risk, minimum PPA for a majority of output for a period in excess of 10 years Quality EPC turnkey contract (Nordea: in wind, 2-3 suppliers acceptable) In addition to: Good relationship with a credible management Solid Sponsor(s) Stable and credible regulation. and. construction risk a concern for off-shore wind In line with Nordea s Wind Credit Principles with additional concerns like; proven technology with reputable suppliers, mitigation of construction risk, comprehensive wind survey etc. Bankable if there is a solid and predictable cash generating ability 5
6 3. Wind Power Project Finance Digging into the risks A. Credit Risks on Sponsors and project Parties B. Wind Resource Risk C. Equipment Risk (pre- and post Completion) D. Price Risk E. Financial Risk F. Political and Legal Risk
7 Risk evalution of wind power projects A. Credit risk on Sponsors and key project parties Reputable Sponsors/Investors with industrial experience Technically able and financially strong suppliers and off-takers B. Wind resource risk To the Banker, the wind resource fuels cash flow and thus debt repayment.. Wind study is key (minimum 1 year of data, preferably two years) Provides analysis on average wind speed, gross and net Annual Energy Production (AEP) (after uncertainties, technical issues linked to site, terrain, icing, wind shear, turbulence, etc.) at P50, P75 and P90 Study to be verified by an Independent Engineer (IE) appointed by the Bank
8 Risk evaluation ctd. C. Technical risk (pre- and post Completion) Reputable turbine supplier with proven technology WTG (experience, financial strength, power curve, track record) Construction risks: Preferably turn-key, fixed price, date certain, EPC contract, or maximum 3 separate contracts well managed Sponsor Guarantee cuts risks and thus cost of financing Buffer for cost overruns Independent Engineer to sign off progress and successful Completion Operational risks: Warranty and Operations and Maintenance Agreement (O&M) with the turbine supplier, incl. availability guarantee (the longer the better) All-risk insurance, including business interruption Maintenance Reserve Account (MRA)
9 Risk evaluation ctd. Wind and operational risks statistical evidence 20,0 % Estimated normal production versus actial production (various wind parks in Norway) 10,0 % 0,0 % -10,0 % ,0 % -30,0 % -40,0 % -50,0 % Source: NVE, Nordea research Source: Moody`s research Breezing Past 50 Moody s survey of 34 US onshore wind projects - median energy production was approximately 9 % below expected case 9
10 Risk evaluation ctd. D. Price risk with respect to electricity and certificates Long-term Power Purchase Agreement (PPA) / El. Certificate Purchase Agreement with creditworthy off-taker if no «feed-in tariff, as in Latvia» Substantial portion of price risk should be hedged Maturity equal to, or longer than, loan maturity Fixed price, preferably inflation adjusted (with escalator) or, Market price secured by market instruments Nord Pool instruments (up to 5 years rolling hedge possible) Zero cost collar, defining a price floor and a price ceiling, the price moving within this tunnel Other commodity market derivatives, some of which may also cover volume risk
11 Risk evaluation ctd. E. Financial risk Strong DSCR in Base Case based on projected cash flow (P-75 production assumption), normally Average DSCR of min Tenor and repayment period Debt Service Reserve Account (DSRA), normally equalling 6 months of debt service Maintenance Reserve Account (MRA) Hedging of interest rate Hedging of FX exposure F. Political and legal risk: to be acceptable
12 4. Experiencing risks and their mitigation Pre-Completion Høg-Jæren Project (2011): Foundation no. 32 placed 6 meters wrongly removal implied: Destruction and new construction, i.e. delays Extra costs for contractor requires financial strength Havøygavlen Project (2003): Three days after issued «acceptance certificate» a turbine crashed to the ground Completion-definition not affected by this Sponsor gty s expired 3 months later (bad definition!) Requires financial strenght of insurance / supplier 12
13 Experiencing risks and their mitigation ctd. Post-Completion Havøygavlen, location of the site Maintenance with a crane only possible April- September because of limited weather window Closest crane in Tromsø, about 600 km away Havøygavlen, wind / wind-direction(s) «Good» wind may be too much. Puts strain on the equipment, which has to be especially adapted Puts pressure on the supplier and on the operator, needing to be well organized, be good on logistics and have financial strength 13
14 Conclusions Project Financing puts focus on the ability of the Project to withstand risks in order to produce a cash flow which may repay debt KPMG study shows that Banks are fairly united on what they require of a Wind Power Project Finance Digging into the risks the devil lies in the detail the solution in putting the risks on strong participants Experience shows that things will go wrong then one needs to have taken the precautions ahead of time Flash on the current loan market: Basel III rules under implementation project rating (i.e. high quality in terms of risks) is key to obtain good pricing from the Banks Banks still provide 15 yr amortization plans, but will seek repricing rights after 5 7 yrs Banks will seek to provide loan financing with exteral funding, if possible. 14
15 Project financing team and credentials EPF in Nordea has an extensive competence and knowledge in financing of wind parks The EPF wind team Hans Jacob Bull-Berg, EPF Oslo Deal Manager Henrik Brink, EPF Copenhagen Head of Wind Energy Juha Sulkanen, EPF Helsinki Deal Manager Niclas Ringblom, EPF Stockholm Deal Manager Selected transactions Borrower Country Nordea role Sign ed VindIn Sweden Arranger 2011 Arise Windpower, Idhult Sweden Arranger 2011 TuuliWatti Finland Arranger 2011 Wallenstam, Rålanda Sweden Arranger 2010 Wallenstam, Vettåsen Sweden Arranger 2010 Jæren Energi Norway Co-arranger 2010 INPO 5 Latvia Arranger 2010 Arise Wind Power Sweden Arranger 2010 Tooma Tuulepark Estonia Co-arranger 2009 Vader Piet B.V. Aruba Lender 2009 Gudny Eysturoy, EPF Copenhagen Deal Manager Lars Nybom, EPF Stockholm Deal Manager Havøygavlen (Arctic Wind) Norway Co-arranger many more projects 15
16 16
PROJECT FINANCE UNCDF October 2014 Dar Es Salaam
Project Finance PROJECT FINANCE UNCDF October 2014 Dar Es Salaam AGENDA History and Definition Structure of Project Finance Transactions Key Players Milestones Role of Debt in PF transactions Risk Management
Power Project - Debt Financing. Bill Sutherland Senior Managing Director Project Finance April 9, 2014
Power Project - Debt Financing Bill Sutherland Senior Managing Director Project Finance April 9, 2014 Project Finance Investment Manulife Project Finance Defined Principal Risks / Mitigates Challenges
Financing in the Energy Sector. EDMUNDO S. SORIANO Executive Vice-President & Head Corporate Banking Group BDO Unibank, Inc.
Financing in the Energy Sector EDMUNDO S. SORIANO Executive Vice-President & Head Corporate Banking Group BDO Unibank, Inc. 1 Status of local banking 10-15 years ago Local banks could not compete with
Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy
Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy Louis Bélanger, CFA, FRM Managing Director, Stonebridge Infrastructure Debt Fund The Stonebridge
B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org
"INOGATE Technical Secretariat & Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives" Project B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment
INSURANCE BANKABILITY
INSURANCE BANKABILITY Innovative Insurance Solutions for Renewable Energy Special Enterprise Risks, Green Tech Solutions Álvaro Núñez Andrada Underwriter Munich Re SER is a unit within Corporate Insurance
Public-Private Partnerships
Public-Private Partnerships Closing Critical Issues Washington, Background In limited recourse finance, the primary source of debt service is the cash flow generated by the Project will evaluate all factors
Wind Power Finance School
Part of www.greenpoweracademy.com Wind Power Finance School Wind Power An intensive and demanding 5-day course combining all aspects of wind power financing from financial modelling, project economics,
Financing Renewables and Energy Efficiency Projects in Developing Countries
Mobilising Private Capital to reduce Climate Change Instruments and Policies to mobilise International Green Energy Investment Berlin June 29-30, 2010 Financing Renewables and Energy Efficiency Projects
Funding wind power: the view from a financial institution
Funding wind power: the view from a financial institution TPWind Nicolas Gourvitch - 24 September 2013 GGEB - A specialist advisory boutique focused on renewable energy At the heart of the energy transition
ABENGOA. 2014: Financial Review. Barbara Zubiria. 8th Annual Analyst and Investor Day. EVP, Capital Markets & IR
Innovative Technology Solutions for Sustainability ABENGOA 2014: Financial Review Barbara Zubiria EVP, Capital Markets & IR 8th Annual Analyst and Investor Day April 3 & 4, 2014 Forward-looking Statement
Community and Renewable Energy Scheme Project Development Toolkit
Community and Renewable Energy Scheme Project Development Toolkit Balance Sheet Equity Investment Community Bond Issues Community Vehicle Crowd Funding Debentures a form of bond Debt Debt Service Cover
Clean Energy Project Financing. March 5, 2012
Clean Energy Project Financing March 5, 2012 Disclaimer This presentation is solely for discussion purposes. In preparing this presentation, we, KASIKORNBANK PLC. ( KBank ) have made crucial assumptions
Key learning points I
Key learning points I What do banks do? Banks provide three core banking services Deposit collection Payment arrangement Underwrite loans Banks may also offer financial services such as cash, asset, and
2009 Ghana PPP Conference
2009 Ghana PPP Conference Public-Private Partnership for Social Services and Infrastructure 10 September 2009 An Authorised Financial Services Provider Agenda: Introduction to Rand Merchant Bank Debt &
Canadian Wind Market 03/27/2013. Natixis Global Infrastructure & Projects
Canadian Wind Market 03/27/2013 Natixis Global Infrastructure & Projects Groupe BPCE 2 nd largest banking group in France 50% 50% 72.3%: BPCE Majority Owner of Natixis 27.7%: Public Float BPCE Figures
DBSA RENEWABLE ENERGY FINANCING
DBSA RENEWABLE ENERGY FINANCING Development Bank of Southern Africa Presented by Madalo Minofu Project Preparation Specialist: DBSA Project Preparation Funds Division 2 June 2014 1 DBSA s Product Offering
IFC ESMAP- RENEWABLE ENERGY TRAINING PROGRAM. Wind Module. II. Wind Project Development, Implementation, and Financing
IFC ESMAP- RENEWABLE ENERGY TRAINING PROGRAM Wind Module II. Wind Project Development, Implementation, and Financing Washington DC, June 16th 2014 Index Wind Project Development, Implementation, and Financing
Financing PPPs: Project Finance June 2006
Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:
Ethiopian Institute of Financial Studies (EIFS) PROJECT FINANCE
PROJECT FINANCE With the growth in the economy and the revival in the industrial sector coupled with the increasing role of private players in the field of infrastructure, more and more Ethiopian banks
Capital Structure and Project Finance Mark Williamson and Peter Barlow
Capital Structure and Project Finance Mark Williamson and Peter Barlow Capital structure overview Very secure capital structure strong liquidity at parent cash of 357m at 30 June 2008 low debt at parent
China Trade & Export Finance Conference Commodity Finance in PRC
China Trade & Export Finance Conference Commodity Finance in PRC JOLYON ELLWOOD-RUSSELL Jolyon Ellwood Russell, Partner James Willcock, Registered Foreign Lawyer Gulong Ren, Legal Officer Agenda Commodity
Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building
Financing Nuclear Power Projects: Challenges and Assistance in Capacity Building International Framework for Nuclear Energy Cooperation Finance Workshop London, 9-10 May 2012 Nadira Barkatullah International
Financing of Wind Projects: IFC s Perspective. Walid Labadi 2nd IEL-ANADE May, 2012
Financing of Wind Projects: IFC s Perspective Walid Labadi 2nd IEL-ANADE May, 2012 IFC was established in 1956 to promote private sector development and is a member of the World Bank Group IFC Power Sector
The Value of Public-Private Partnerships
The Value of Public-Private Partnerships How Risk Transfer and Performance Security Influence a Deal Aaron Toppston Director, Aon Infrastructure Solutions Baker & McKenzie International is a Swiss Verein
Improved Bankability. The Ecofys position on LiDAR use. Summary
Improved Bankability The Ecofys position on LiDAR use Summary A key goal of a wind measurement campaign is to reduce project uncertainty, as this will improve bankability in terms of better financing terms
Specialized Financing in the Oil & Gas Industry
Specialized Financing in the Oil & Gas Industry How to proceed? What are our needs when starting a project? What are our objectives when we approach financings? Why we can rely on banking financings? 1
FINANCIAL RESULTS Q1 2016
FINANCIAL RESULTS Q1 2016 CFO Hallvard Granheim 28 th April 2016 Highlights Q1 Increase in underlying results (EBITDA) - Nordic prices are down 15% Q-on-Q - High production from Nordic hydropower assets
Overview of Rooftop Solar PV Green Bank Financing Model
Overview of Rooftop Solar PV Green Bank Financing Model Sponsored by The Connecticut Clean Energy Finance and Investment Authority and The Coalition for Green Capital Developed by Bob Mudge & Ann Murray,
Cash Drivers and Enterprise Value
Cash Drivers and Enterprise Value Global Investor Forum 2009, Broughton, 1 st & 2 nd April 2009 Gérard Adsuar Corporate Executive Finance & Treasury, EADS 1 1 Safe Harbour Statement Disclaimer This presentation
ABENGOA. Financial Review. Completing Transformation. Ignacio Garcia Alvear. Innovative Technology Solutions for Sustainability
Innovative Technology Solutions for Sustainability ABENGOA Financial Review Completing Transformation Ignacio Garcia Alvear Co-CFO for IR & Capital Markets 9th Annual Analyst and Investor Day New York
Asset-Backed Securities. Project Financing. Prof. Ian Giddy. Stern School of Business New York University. Asset-Backed and Project Financing
Project Financing/1 Asset-Backed Securities Project Financing Prof. Ian Giddy Stern School of Business New York University Asset-Backed and Project Financing Collateralized debt Securitized loans Non-recourse
Wind Power Business Models:
Wind Power Business Models: Deal Structures and Economics Project Financing Overview Mohammed Alam Alyra Renewable Energy Finance LLC Steve Krebs Baker Botts L.L.P. Wind Power Development Tutorial Hotel
Solar Power Purchase Agreements & Leases
Solar Power Purchase Agreements & Leases Angela Lipanovich, Esq. March 7, 2012 Copyright 2012, Estriatus Law. All rights reserved. Conditions of Usage and Disclaimer 1 Estriatus Law grants the following
Words from the President and CEO 3 Financial highlights 4 Highlights 5 Export lending 5 Local government lending 6 Funding 6 Results 6 Balance sheet
Words from the President and CEO 3 Financial highlights 4 Highlights 5 Export lending 5 Local government lending 6 Funding 6 Results 6 Balance sheet 7 Events after the balance sheet date 8 Income statement
Technical Risks in Wind Project Development
Technical Risks in Wind Project Development Kevin J. Smith Global Segment Director Renewable Energy Services May 21, 2012 Discussion Objectives Introduction to project risks How to quantify risks Project
Financing Environmental Exports
Export-Import Bank of the United States EXPORT-IMPORT BANK of the UNITED STATES Jobs Through Exports Financing Environmental Exports 10 th Annual LMOP Conference and Project Expo Baltimore, Maryland January
CP FOR THE DRAFT RTS ON ASSIGNING RISK WEIGHTS TO SPECIALISED LENDING EXPOSURES EBA/CP/2015/09. 11 May 2015. Consultation Paper
EBA/CP/2015/09 11 May 2015 Consultation Paper Draft Regulatory Technical Standards on Assigning Risk Weights to Specialised Lending Exposures under Article 153(9) of Regulation (EU) No 575/2013 (Capital
Nuclear Power Financing in Finland Past experiences and future challenges. Jean-Francois Tapprest 07.10.2010
Nuclear Power Financing in Finland Past experiences and future challenges Jean-Francois Tapprest 07.10.2010 Agenda The experience of financing OL3 Financing of new plants in Finland Case Lithuania Visaginas
HSH Nordbank AG. Financing of Wind Projects in Germany. Current Market Situation and Future Challenges
Financing of Wind Projects in Germany Current Market Situation and Future Challenges HSH Nordbank AG Lars Quandel ENERGY& UTILITIES HUSUM 16 SEPTEMBER 2015 Our Profile Renewable Energy Business model PRODUCTS
Renewable Project Business Models:
Renewable Project Business Models: Deal Structures and Economics Project Financing Overview Mohammed Alam Alyra Renewable Energy Finance LLC Steve Krebs Baker Botts L.L.P. Infocast s Renewable Power Project
Public Policy and Innovation: Partnering with Capital Markets through Securitization. Antonio Baldaque da Silva November 2007
Public Policy and Innovation: Partnering with Capital Markets through Securitization Antonio Baldaque da Silva November 2007 Agenda 1. Motivation: Innovation and Public Policy 2. Traditional tools 3. Alternatives:
Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.
Financing of Renewable Energy in India: Implications for Policy Gireesh Shrimali Climate Policy Initiative [email protected] CPI analyzes the effectiveness of policies relevant to climate change
A strong third quarter
A strong third quarter Interim presentation for the third quarter 2015 Stockholm, 5 November 2015 Anders Nissen, CEO Liia Nõu, CFO Today s agenda Introduction Financial review Business model and value
Nordex SE. Analyst Presentation Preliminary Figures FY 2011. Hamburg 28/02/2012
Nordex SE Analyst Presentation Preliminary Figures FY 2011 Hamburg 28/02/2012 Overview Order intake, sales and EBIT before one-off items in line with most recent forecast as of 14 Nov. Guidance 2011p Order
A QUICK GUIDE TO PREPARING A FINANCING PROPOSAL
A QUICK GUIDE TO PREPARING A FINANCING PROPOSAL FOR PRINCE EDWARD ISLAND SMALL BUSINESS Page1of5 Bankers are just like other entrepreneurs; they seek new clients and would not stay in business if they
Financing Drivers and Funding Rapid Growth
Financing Drivers and Funding Rapid Growth IDEA International District Cooling Symposium October 2007 Mohamed Elshentenawy Palm District Cooling [email protected] Presentation outline GCC
Renewable Energy Finance Fundamentals
Renewable Energy Finance Fundamentals The US Partnership for Renewable Energy Finance (US PREF) has prepared the following brief summary of the basics of renewable energy project finance. An appreciation
Prologue: Green Banking. Capacity Building on Green Energy and Climate Finance. Alexander Boensch, 6 th June 2016, Manila. www.renac.
Prologue: Green Banking Capacity Building on Green Energy and Climate Finance Alexander Boensch, 6 th June 2016, Manila Renewables Academy (RENAC) AG RENAC is a Berlin-based training and capacity building
Note 24 Financial Risk Management
Note Financial Risk Management Risk management principles and process Stora Enso is exposed to several financial market risks that the Group is responsible for managing under policies approved by the Board
How KASIKORNBANK Plans to Support Green Projects
How KASIKORNBANK Plans to Support Green Projects Clean Power Asia 29-30 April 2013, Bangkok Thongchai Kangvanchai KASIKORNBANK Pcl. 1 Content Government s Policy of Promoting Green Energy KBank s Green
Trade Finance Update for Multinationals and Financial Institutions
Trade Finance Update for Multinationals and Financial Institutions A Discussion on Recent Developments in Trade Finance Presented by: Ricardo Martinez, Partner, New York Lloyd Winans, Partner, New York
eeef European Energy Efficiency Fund
eeef European Energy Efficiency Fund Agenda 1 introduction to eeef - key elements 2 eeef investments: eligibility, process and project structures 3 Case studies 4 Final Remarks 2 1a eeef at a glance Objective
RESULTS FOR THE THREE MONTH PERIOD ENDING 31 MARCH 2015 AND AUDITED RESULTS FOR THE TWELVE MONTH PERIOD ENDING 31 DECEMBER 2014
RESULTS FOR THE THREE MONTH PERIOD ENDING 31 MARCH 2015 AND AUDITED RESULTS FOR THE TWELVE MONTH PERIOD ENDING 31 DECEMBER 2014 4finance Holding S.A. (the Group ), rated B3 by Moody and B+ by Standard
Tipco Asphalt Public Company Limited
Q1/2015 Analysts Meeting 26 th May 2015 1 Agenda 1 Q1/2015 Highlight 2 Performance Highlights 3 Q2/2015 Outlook 2 Q1/2015 Highlights: Total sales volumes Sales volumes by quarters Unit: Mil tons Sales
Financing Renewables in Turkey
Financing Renewables in Turkey Symposium of the Deutsch Türkischen Industrie- und Handelskammer Florian Mahiny Head of Austrian/ German International Desk Yapı ve Kredi Bankası A.Ş. Istanbul, 22. February
FHA Home Loans 101 An Easy Reference Guide
FHA Home Loans 101 An Easy Reference Guide Updated for loans on or after January 26, 2015 Congratulations on Starting Your Journey to Home Ownership This guide offers a quick look at vital information
Mitigation of Investment Risk
1of 37 F A O P o l i c y L e a r n i n g P r o g r a m m e Module 3: Investment and Resource Mobilization Mitigation of Investment Risk 2of 38 Mitigation of Investment Risk By Calvin Miller, Senior Officer,
Case Study More Money Please
Case Study More Money Please Question Appeared in: ModelOff 2015 Round 2 Time allocated: 35 minutes INTRODUCTION You work for a Project Company that has an existing senior debt facility which is due to
Innovative Technology Solutions for Sustainability ABENGOA. Market Update
Innovative Technology Solutions for Sustainability ABENGOA Market Update November, 2014 Forward-looking Statement This presentation contains forward-looking statements (within the meaning of the U.S. Private
BANKERS GUIDE TO SECURE LENDING
BANKERS GUIDE TO SECURE LENDING WAREHOUSE RECEIPTS, ORDER OR STRAIGHT BILLS OF LADING, OTHER NEGOTIABLE AND NON-NEGOTIABLE DOCUMENTS OF TITLE, INCLUDING WAREHOUSE AND BAILEE OR DOCK RECEIPTS Lending Rationale
FSIN POWER GENERATION WORKSHOP. Building strong Nations through modern finance.
FSIN POWER GENERATION WORKSHOP Building strong Nations through modern finance. CONTACT Sean McCoshen, President & Chairman CELL: 1-204-999-1847 EMAIL: [email protected] Scott Carleton, Chief Executive
Management of Receivables
Management of Receivables Different costs involved in maintaining the debtors: 1. Interest. 2. Discount. 3. Collection Charges. 4. Bad Debts. Different approaches of calculating Interest: Total Cost approach.(priority)
Credit Risk. Loss on default = D x E x (1-R) Where D is default percentage, E is exposure value and R is recovery rate.
Credit Risk Bank operations involve sanctioning of loans and advances to customers for variety of purposes. These loans may be business loans for short or long term commitments and consumer finance for
Management Discussion and Analysis of Financial Position and Operating Results
Management Discussion and Analysis of Financial Position and Operating Results The purpose of this analysis is to provide the reader with an overview of how the financial position of Héroux-Devtek Inc.
FINAL TERM SHEET. Scatec Solar ASA Senior Unsecured Bond Issue 2015/2018 (the Bonds or the Bond Issue )
11 November 2015 FINAL TERM SHEET Scatec Solar ASA Senior Unsecured Bond Issue 2015/2018 (the Bonds or the Bond Issue ) ISIN: NO001 075229.8 Issuer: Group: Currency: Borrowing Amount: Coupon Rate: Scatec
SAMA GENERAL DEPARTMENT OF FINANCE COMPANIES CONTROL. Prudential Returns Handbook (Finance Companies)
SAMA GENERAL DEPARTMENT OF FINANCE COMPANIES CONTROL Prudential Returns Handbook (Finance Companies) 1. Introduction Submission schedule All licensed finance companies in Saudi Arabia are required to submit
ENERGY INDUSTRY INSURANCE SOLUTIONS
Summer 11 ENERGY INDUSTRY INSURANCE SOLUTIONS ELECTRICITY PRICE & FORCED POWER OUTAGE COVERAGE WEATHER DERIVATIVES SYSTEM PERFORMANCE INSURANCE TRADE CREDIT INSURANCE ACCOUNTS RECEIVABLE PUTS NON CANCELLABLE
CITIGROUP INC. BASEL II.5 MARKET RISK DISCLOSURES AS OF AND FOR THE PERIOD ENDED MARCH 31, 2013
CITIGROUP INC. BASEL II.5 MARKET RISK DISCLOSURES AS OF AND FOR THE PERIOD ENDED MARCH 31, 2013 DATED AS OF MAY 15, 2013 Table of Contents Qualitative Disclosures Basis of Preparation and Review... 3 Risk
Gebze Izmir Motorway & Izmit Bay Crossing Project
Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey
2013 Second Quarter Review July 26, 2013 1
213 Second Quarter Review July 26, 213 1 Panalpina Group Basel, July 26, 213 213 Second Quarter Review 213 Second Quarter Review July 26, 213 2 Highlights and key figures Operating and financial review
Success in Renewables. Glossary of Terms Investment and Renewables
Success in Renewables Glossary of Terms Investment and Renewables If you re new to renewable energy or investment, then it can be a minefield of new language and terminology. What seems totally normal
Home Buying Seminar. A presentation by The Summit Federal Credit Union
Summit Branches are located in Rochester (7), Seneca Falls (1), Buffalo (3), Syracuse (5) and Cortland (2) Home Buying Seminar A presentation by The Summit Federal Credit Union What We Will Cover Today
Capital G Bank Limited. Interim Pillar 3 Disclosures 30th June, 2012
Capital G Bank Limited Interim Pillar 3 Disclosures 30th June, 2012 CONTENTS 1. CAUTIONARY STATEMENTS....1 2. INTRODUCTION...2 2.1 Background...2 2.2 Basis of Disclosure...3 2.3 Media and Location...3
Performance Food Group Company Reports First-Quarter Fiscal 2016 Earnings
NEWS RELEASE For Immediate Release November 4, 2015 Investors: Michael D. Neese VP, Investor Relations (804) 287-8126 [email protected] Media: Joe Vagi Manager, Corporate Communications (804) 484-7737
Research. What Impact Will Ballooning Government Debt Levels Have on Government Bond Yields?
Research What Impact Will Ballooning Government Debt Levels Have on Government Bond Yields? The global economy appears to be on the road to recovery and the risk of a double dip recession is receding.
Debt Policy. I. Purpose of the Debt Policy
Debt Policy I. Purpose of the Debt Policy In support of its mission, (University) maintains a long term strategic plan. The strategic plan establishes University wide priorities as well as divisional programmatic
Introduction to Project Finance Analytic Methods
Introduction to Project Finance Analytic Methods Renewable Energy and Project Development and Financing for California Tribes Sacramento, CA Jack Whittier, McNeil Technologies January 2008 Why? Use a model
Queen Alia International Airport Project, Jordan
Queen Alia International Airport Project, Jordan Case Study Madhavi Gosavi, Partner Norton Rose LLP 11 September 2009 The Project 25-year concession for the rehabilitation, expansion and operation of the
Accounting for securitizations treated as a financing (on-balance sheet) verses securitizations treated as a sale (off-balance sheet)
Accounting for securitizations treated as a financing (on-balance sheet) verses securitizations treated as a sale (off-balance sheet) The hypothetical example below is provided for informational purposes