Falcon 9 Launch Vehicle NAFCOM Cost Estimates. August 2011 NASA Associate Deputy Administrator for Policy
|
|
|
- Preston Barber
- 10 years ago
- Views:
Transcription
1 Falcon 9 Launch Vehicle NAFCOM Cost Estimates August 2011 NASA Associate Deputy Administrator for Policy 1
2 Falcon 9 Launch Vehicle NAFCOM Cost Estimate The objective of the analysis was to estimate the cost to develop the Falcon 9 launch vehicle using two different approaches: 1) traditional NASA environment/culture, and 2) a more commercial ildevelopment culture approach. The analysis was performed late 2010 early 2011 using the NASA Air Force Cost Model (NAFCOM) with results provided to ESMD in November These results were used for Appendix B of the Commercial Market Assessment for Crew and Cargo Systems and for the Deputy Administrator s presentation at the National Space Symposium. Results: The activity estimated Falcon 9 would cost $3.977B based on NASA environment/culture. NAFCOM predicted $1.695B when all technical inputs were adjusted to a more commercial development approach. Working with different inputs from the preliminary data provided by SpaceX after a trip to the SpaceX facility, NASA recently inputted revised data into the NAFCOM model and a different output was the result. 2
3 Original Cost Estimates versus SpaceX Actuals NASA did not perform a detailed analysis to explain the significant differences between the cost estimates and SpaceX actual costs. However, SpaceX attributed their cost efficiencies to a few primary factors. 1. Workforce Total vehicle DDT&E costs are primarily a product of the total workforce needed to accomplish the effort (SpaceX workforce numbers substantiate their development cost claims), 2. Organizational complexity SpaceX estimates that every dollar sent out of the company actually costs between $3 and $5 based on subcontractor overhead and profit, and 3. Infrastructure Total infrastructure required for the DDT&E effort and infrastructure utilization percentage. These factors suggest that reducing the total workforce; number of management layers and infrastructure can substantially reduce DDT&E costs when compared to traditional NASA environment/culture. 3
4 Update to the Cost Estimates The original estimates were based on technical parameters and inputs supplied by SpaceX in the fall of Provided only a Cost Plus Fee approach Included a single first flight unit NASA personnel subsequently visited the Space X facilities and spoke with SpaceX personnel about the inputs and results of the initial modeling effort. The updated estimates provided both Cost Plus Fee and Firm Fixed Price approaches and included two flight unites The initial and updated cost estimates are not NASA budget estimates. Do not include all costs that would be included in a NASA project budget Are schedule and time phasing independent Both the initial and updated cost estimates are included in this presentation. 4
5 Falcon Falcon 9 NAFCOM 9 Cost Cost Estimates Estimate Trace Comparison Falcon 9 NAFCOM Cost Estimate Comparison (All Costs Are In FY2010 $M) Initial Estimate Updated Estimate Cost Plus Fee Cost Plus Fee Firm Fixed Price Cost Plus Fee Total Total Total Total Elements (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) Falcon 9 Total $1,695 $3,977 $443 $1,383 Assumptions inserted after Space X visit: More heritage from Falcon 1 and use of off the shelf hardware than the initial information Nine redundant controllers and wiring harnesses were not identified in the initial information Structure weights were included in the electronics Separation subsystem mass was included in structure Interstage (composite material) was included in structures (aluminum lithiumlithium material) Falcon 9 test program initially included only one test flight unit Excludes Program Support costs (Firm Fixed Price only). Excludes Contingency costs (Firm Fixed Price only). Excludes Contractor fee (Firm Fixed Price only). 5
6 Modeling Explanation of Difference Primary Differences In Firm Fixed Price Vs. Cost Plus Fee Acquisition Model Input Assumptions Firm Fixed Price Cost Plus Fee 1- Acquisition Strategy No Oversight Oversight 2- Requirements Stability Stable Unstable 3- Team Effeciency Efficient Less Efficient 4- Management Structuret Lean Less Lean 5- Early Phase studies/sys. Engineering Disciplined Less Disciplined 6- Funding Commitment Fixed Annual Note: Order represents relative weighting 6
7 Backup Material 7
8 Falcon 9 NAFCOM Cost Estimate Comparison Initial (BothEstimates Are Cost PlusFee) (All Costs Are In FY2010 $M) Cost Plus Fee Cost Plus Fee Space x Approach NASA Approach Weight DDT&E Flight Unit Total DDT&E Flight Unit Total Elements (lbs) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) Stage One (Including Engines) 39,080 $614 $87 $701 $1,535 $206 $1,741 Stage Two (Including Engine) 6,520 $331 $12 $343 $608 $44 $651 Fee (12.5%) $118 $12 $130 $268 $30 $298 Program Support (10%) $107 $4 $111 $241 $21 $263 Contingency (30% Vehicle, 10% Engine)) $251 $11 $262 $674 $68 $741 Vehicle Level Integration (8%) $106 $5 $111 $258 $24 $282 Total 45,600 $1,528 $131 $1,659 $3,584 $393 $3,977 Based on November, 2010 weight estimate and technical data from SpaceX Represents DDT&E and one flight unit Both estimates represent cost plus fee acquisition approach (include fee, program support, and contingency) 8
9 Falcon 9 NAFCOM Updated Cost Estimate Comparison Updated (Cost Plus Fee Vs. Firm Fixed Price) Firm Fixed Price Acquisition Cost Plus Fee Acquisition Weight DDT&E 2 Test Flt Units Total DDT&E 2 Test Flt Units Total Elements (lbs) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) (FY2010 $M) Stage One (Including Engines) 39,080 $188.7 $109.3 $298.0 $370.6 $218.3 $588.9 Stage Two (Including Engine) 6,506 $89.0 $23.6 $112.6 $184.7 $59.6 $244.4 Fee (12.5%) $0.0 $0.0 $0.0 $69.4 $34.7 $104.2 Program Support (10%) $0.0 $0.0 $0.0 $62.5 $31.3 $93.7 Contingency (30% Vehicle, 10% Engine)) $0.0 $0.0 $0.0 $193.2 $91.7 $284.9 Vehicle Level Integration (8%) $22.2 $10.6 $32.8 $44.4 $22.2 $66.7 Total 45,586 $299.9 $143.6 $443.4 $924.9 $457.9 $1,382.7 Based on technical corrections and the additional insight in to the mass summary information as well as hardware heritage gained from a recent trip to the SpaceX facility. Represents DDT&E and two test flight unit Cost plus fee acquisition approach include fee, program support, and contingency where firm fixed price acquisition reflects a space act agreement approach 9
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
Space Flight Project Work Breakdown Structure
APPENDIX G. (WBS) Space Flight Project Work Breakdown Structure G.1 Introduction G.1.1 The Project Work Breakdown Structure (WBS) is a key element of project management. The purpose of a WBS is to divide
CHAPTER 53 COST ACCOUNTING STANDARDS
CHAPTER 53 COST ACCOUNTING STANDARDS A. REQUIREMENTS 0F COST ACCOUNTING SYSTEMS 1. The Defense Business Operations Fund shall have a cost estimating and cost accounting system or, as needed, systems specifically
System Engineering: A Traditional Discipline in a Non-traditional Organization
System Engineering: A Traditional Discipline in a Non-traditional Organization Corporate Overview Founded with the singular goal of providing highly reliable space transportation Tech-style Organization
Space Launch System Status Briefing to NAC Space Operations Committee
National Aeronautics and Space Administration Space Launch System Status Briefing to NAC Space Operations Committee 8 February 2011 Background In response to direction in Section 309 of the NASA Authorization
ESA s Data Management System for the Russian Segment of the International Space Station
iss data management system ESA s Data Management System for the Russian Segment of the International Space Station J. Graf, C. Reimers & A. Errington ESA Directorate of Manned Spaceflight and Microgravity,
System Development and Life-Cycle Management (SDLCM) Methodology
System Development and Life-Cycle Management (SDLCM) Methodology Subject Type Standard Approval CISSCO Program Director A. PURPOSE This standard specifies the content and format requirements for a Software
Systems Development Life Cycle (SDLC)
DEPARTMENT OF BUDGET & MANAGEMENT (SDLC) Volume 1 Introduction to the SDLC August 2006 Table of Contents Introduction... 3 Overview... 4 Page 2 of 17 INTRODUCTION 1.0 STRUCTURE The SDLC Manual consists
How to Write a Software Process Procedures and Policy Manual for YOUR COMPANY
How to Write a Software Process for YOUR COMPANY 1. Introduction MicroTools is proposing to assist YOUR COMPANY in improving the existing software process. The purpose of this project is to both improve
CITY OF SALEM DATA CENTER INFORMATION SYSTEMS SPECIALIST SERIES
CITY OF SALEM DATA CENTER INFORMATION SYSTEMS SPECIALIST SERIES 0854 INFORMATION SYSTEMS SPECIALIST 1 0858 INFORMATION SYSTEMS SPECIALIST 5 0855 INFORMATION SYSTEMS SPECIALIST 2 0859 INFORMATION SYSTEMS
NASA s Use of Space Act Agreements
National Aeronautics and Space Administration OFFICE OF INSPECTOR GENERAL NASA s Use of Space Act Agreements OFFICE OF AUDITS IG-14-020 AUDIT REPORT JUNE 5, 2014 (A-13-007-00) Final report released by:
BENCHMARK EVALUATION. Highways and Public Works Information and Communications Technology
Identification Section BENCHMARK EVALUATION Position Title: Supervisor s Title: Department: Branch/Unit: Network Solutions Specialist Network Solutions Architect Highways and Public Works Information and
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION HUMAN CAPITAL PLAN FOR MISSION EXECUTION, TRANSITION, AND RETIREMENT OF THE SPACE SHUTTLE PROGRAM
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION HUMAN CAPITAL PLAN FOR MISSION EXECUTION, TRANSITION, AND RETIREMENT OF THE SPACE SHUTTLE PROGRAM April 14, 2006 1 4/14//2006 EXECUTIVE SUMMARY NASA has prepared
Knowledge Management from a
Knowledge Management from a Human Resources perspective APQC 2010 Members Meeting Tim Bridges Director of Knowledge Management THE BOEING COMPANY BOEING is a trademark of Boeing Management Company. Agenda
How To Understand The Waterfall Model Of Software Development
997 Paper 2 Question 8 Describe the waterfall model of software development and discuss its strengths and weaknesses. [2 marks] For which of the following projects would it be suitable, and why? (a) an
Commercial Crew Program Status
National Aeronautics and Space Administration Commercial Crew Program Status for the NAC Presenter Title Date Philip McAlister of Presentation Acting Director, Commercial Spaceflight Development NASA HQ
MONITORING PERFORMANCE
MONITORING PERFORMANCE Monitoring the performance of the contractor is a key function of proper contract administration. The purpose is to ensure that the contractor is performing all duties in accordance
Maximizing the Utility of Your Tool Set for Project Support
2013 NASA Cost Analysis Symposium Maximizing the Utility of Your Tool Set for Project Support Bob Sefcik, Glenn Research Center Tom Parkey, Glenn Research Center August 28, 2013 www.nasa.gov Glenn Research
Atlas Emergency Detection System (EDS)
Atlas Emergency Detection System (EDS) Jeff A. Patton 1 United Launch Alliance, Littleton, Colorado, 80127-7005 [Abstract] The Atlas Expendable Launch Vehicle Program has been studying safe abort requirements
STSG Methodologies and Support Structure
STSG Methodologies and Support Structure STSG Application Life Cycle Management STSG utilizes comprehensive lifecycle tools that are fully integrated and provide capabilities for most of the roles in its
UNCLASSIFIED. UNCLASSIFIED Office of Secretary Of Defense Page 1 of 16 R-1 Line #145
Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Office of Secretary Of Defense Date: March 2014 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 6: RDT&E Management Support COST
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
NASA Independent Review Team Orb 3 Accident Investigation Report
National Aeronautics and Space Administration NASA Independent Review Team Orb 3 Accident Investigation Report Executive Summary Date of Event: October 28, 2014 Date of Report: October 9, 2015 1 NASA Independent
Criteria for Flight Project Critical Milestone Reviews
Criteria for Flight Project Critical Milestone Reviews GSFC-STD-1001 Baseline Release February 2005 Approved By: Original signed by Date: 2/19/05 Richard M. Day Director, Independent Technical Authority
National Aeronautics and Space Administration (NASA) Fleet Management Plan
National Aeronautics and Space Administration (NASA) Fleet Management Plan FY 2013 Submitted by: Timothy A. Currie NASA Agency Transportation Manager Logistic Management Division NASA Headquarters 300
Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012
Audit of the Data Center Consolidation Initiative at NARA OIG Draft Audit Report No. 12-09 May 10, 2012 Table of Contents Executive Summary... 3 Background... 4 Objectives, Scope, Methodology... 7 Audit
Surviving a DCAA. Audit. Nicole Mitchell, CPA Director Aronson LLC. March 29, 2011
Surviving a DCAA Incurred Cost Submission Audit Nicole Mitchell, CPA Director Aronson LLC March 29, 2011 2011 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200
2015 Small Satellite Market Observations. Copyright 2015, SpaceWorks Enterprises, Inc. (SEI)
2015 Small Satellite Market Observations 2015 Small Satellite Market Observations Point of Contact: Dr. John Bradford President / COO [email protected] 1+770.379.8007 Published by: SpaceWorks Enterprises,
GENERAL SERVICES ADMINISTRATION Federal Supply Schedule Authorized Federal Supply Schedule
GENERAL SERVICES ADMINISTRATION Federal Supply Schedule Authorized Federal Supply Schedule On line access to contract ordering information, terms and conditions, up-to-date pricing, and the option to create
Guidance for Applicants
Charter School Business Plan Guidance for Applicants Charter Schools Institute The State University of New York Charter School National Authorizing Leader Business Plan Guidance Introduction As part of
MANAGEMENT AUDIT REPORT DISASTER RECOVERY PLAN DEPARTMENT OF FINANCE AND ADMINISTRATIVE SERVICES INFORMATION TECHNOLOGY SERVICES DIVISION
MANAGEMENT AUDIT REPORT OF DISASTER RECOVERY PLAN DEPARTMENT OF FINANCE AND ADMINISTRATIVE SERVICES INFORMATION TECHNOLOGY SERVICES DIVISION REPORT NO. 13-101 City of Albuquerque Office of Internal Audit
ATTACHMENT 1: CONTRACTOR PAST PERFORMANCE REPORT CONSULTING SERVICES Note: Continuation sheets may be used if more space is required.
1. Consultant Name and Address: 2. MCA Entity: Country: Point of Contact (POC) 3. [ ] Final Report From: To: [ ] Interim Report From: To: Name: POC Position: 4. Contract Number: 8. Total Value of Base
A Characterization Taxonomy for Integrated Management of Modeling and Simulation Tools
A Characterization Taxonomy for Integrated Management of Modeling and Simulation Tools Bobby Hartway AEgis Technologies Group 631 Discovery Drive Huntsville, AL 35806 256-922-0802 [email protected]
Improving the Life-Cycle Cost Management of Planetary Missions (Finding Summary)
National Aeronautics and Space Administration Improving the Life-Cycle Cost Management of Planetary Missions (Finding Summary) Planetary Science Division / /Lunar Science Program Office June 2008 0 Program
DRAFT Publication 4812 State of Security (SoS) Package
DRAFT Publication 4812 State of Security (SoS) Package Contractor Security Controls Handling and Protecting Information or Information Systems ***This Package Pertains to IT Assets Owned and Managed at
OVERHEAD, GENERAL, AND ADMINISTRATIVE COSTS
Chapter Nine OVERHEAD, GENERAL, AND ADMINISTRATIVE COSTS INTRODUCTION Much of the attention to improvements in the factory goes to the most obvious source of cost, the actual production process, which
Position Descriptions. Aerospace
Position Descriptions Aerospace Aerospace Engineering? Aeromechanics / Flight Control / Flight Qualities Engineer Predict, analyze, and verify air vehicle flight dynamics including aircraft aerodynamics,
In today s acquisition environment,
4 The Challenges of Being Agile in DoD William Broadus In today s acquisition environment, it no longer is unusual for your program to award a product or service development contract in which the vendor
Master Document Audit Program
Activity Code 11510 B-1 Planning Considerations Information Technology General System Controls Audit Specific Independence Determination Members of the audit team and internal specialists consulting on
Software Test Plan (STP) Template
(STP) Template Items that are intended to stay in as part of your document are in bold; explanatory comments are in italic text. Plain text is used where you might insert wording about your project. This
Department of Commerce National Institute of Standards and Technology (NIST)
Department of Commerce National Institute of Standards and Technology (NIST) Response to Request for Information on Quantum Information Science and the Needs of U.S. Industry Posted Date: April 8, 2015
Offsets in Defense Trade
Offsets in Defense Trade Sixteenth Study Conducted Pursuant to Section 723 of the Defense Production Act of 1950, as Amended U.S. Department of Commerce Bureau of Industry and Security January 2012 Table
PDS (The Planetary Data System) Information Technology Security Plan for The Planetary Data System: [Node Name]
PDS (The Planetary Data System) Information Technology Security Plan for The Planetary Data System: [Node Name] [Date] [Location] 1 Prepared by: [Author] [Title] Date Approved by: [Name] [Title] Date 2
Ms. Sally Ericsson Program Associate Director Office of Management and Budget New Executive Office Building Washington, DC 20503. Dear Ms.
National Aeronautics and Space Administration Office of the Administrator Washington. DC 20546-0001 April 7, 2011 Ms. Sally Ericsson Program Associate Director Office of Management and Budget New Executive
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Space Communications and Navigation: NASA s Management of the Space Network
National Aeronautics and Space Administration OFFICE OF INSPECTOR GENERAL Space Communications and Navigation: NASA s Management of the Space Network OFFICE OF AUDITS IG-14-018 AUDIT REPORT APRIL 29, 2014
Innovation and Technology Department
PERFORMANCE AUDIT Innovation and Technology Department IT Inventory Asset Management January 11, 2016 Office of the City Manager Internal Audit Division Cheryl Johannes, Internal Audit Manager PERFORMANCE
PROPOSALS REQUESTED THE TOWN OF OLD ORCHARD BEACH POLICE DEPARTMENT FOR IP-BASED VOICE COMMUNICATION SYSTEM
PROPOSALS REQUESTED BY THE TOWN OF OLD ORCHARD BEACH POLICE DEPARTMENT FOR IP-BASED VOICE COMMUNICATION SYSTEM The Town of Old Orchard Beach will receive sealed bids for an IP based phone system. The project
STATEMENT OF WORK FOR SUPPORT SERVICES FOR THE OFFICE OF HUMAN CAPITAL MANAGEMENT AT THE GODDARD SPACE FLIGHT CENTER DECEMBER 2012
Contract # NNG13VB30B Attachment #1: Office of Human Capital Management Statement of Work for Support 1 STATEMENT OF WORK FOR SUPPORT SERVICES FOR THE OFFICE OF HUMAN CAPITAL MANAGEMENT AT THE GODDARD
Lessons Learned during the Refurbishment and Testing of an Observatory after Longterm
Lessons Learned during the Refurbishment and Testing of an Observatory after Longterm Storage GSFC 2015 John Hawk, Sharon Peabody, and Richard Stavely NASA Goddard Space Flight Center Background The Triana
SYSTEMS ENGINEERING FUNDAMENTALS 4/10/2003 1
SYSTEMS ENGINEERING FUNDAMENTALS 1 WHAT S A SYSTEM? DOD : An integrated composite of people, products, and processes that provide a capability to satisfy a stated need or objective. NASA: A set of interrelated
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
INTRODUCTION TO DIGITAL PHOTOGRAPHY
INTRODUCTION TO DIGITAL PHOTOGRAPHY Description Digital Photography will explore electronic imaging through the use of digital cameras, scanners and printers. This course will cover basic technical information
SOFTWARE ASSURANCE STANDARD
NOT MEASUREMENT SENSITIVE National Aeronautics and NASA-STD-8739.8 w/change 1 Space Administration July 28, 2004 SOFTWARE ASSURANCE STANDARD NASA TECHNICAL STANDARD REPLACES NASA-STD-2201-93 DATED NOVEMBER
PROJECT CHARTER GUIDE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Technology PROJECT CHARTER GUIDE February 1999 Chief Information Officer Branch
NASA s Intelligent Synthesis Environment Program Revolutionizing the Agency s Engineering and Science Practice
The Voice of the Customer NASA s Intelligent Synthesis Environment Program Revolutionizing the Agency s Engineering and Science Practice An AES PAL Technical Quarterly Journal Robert D. Braun, Ph.D., Chief
Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION
Project management 1 Objectives 2 Organizing, planning and scheduling software projects DISCUSSION Project Managers? To introduce software project management and to describe its distinctive characteristics
U.S. ELECTION ASSISTANCE COMMISSION OFFICE OF INSPECTOR GENERAL
U.S. ELECTION ASSISTANCE COMMISSION OFFICE OF INSPECTOR GENERAL FINAL REPORT: U.S. Election Assistance Commission Compliance with the Requirements of the Federal Information Security Management Act Fiscal
Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck?
Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck? Breakout Session #: F05 Presented by: Gail Guseman Deloitte Consulting, LLP Date: July 23, 2013 Time: 4:00 pm
WORKFORCE COMPOSITION CPR. Verification and Validation Summit 2010
WORKFORCE COMPOSITION CPR PEO IEW&S Organizational Assessment VCSA Brief Date 2010 October 13, 2010 This briefing is UNCLASSIFIED/FOUO PREDECISIONAL LIMITED DISTRIBUTION AS OF: 11 Sep 2010 Verification
Statement. Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation. Before
Statement of Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation Before THE UNITED STATES SENATE ARMED SERVICES COMMITTEE (SUBCOMMITTEE ON READINESS AND MANAGEMENT SUPPORT)
Federal Business Opportunities (FedBizOpps.gov) Change Management Plan (CMP)
GSA OFFICE OF GOVERNMENTWIDE POLICY Federal Business Opportunities (FedBizOpps.gov) Change Management Plan (CMP) Issued on October 18, 2002 by the FedBizOpps Program Management Office in consultation with
PART ONE OVERVIEW. ESMD - Integrated Collaborative Environment
Exhibit 300 (BY2010) PART ONE OVERVIEW 1. Date of Submission: 2008-09-08 2. Agency: 026 3. Bureau: 00 4. Name of this Capital Asset: 5. Unique Project Identifier: ESMD - Integrated Collaborative Environment
DATA REQUIREMENTS DESCRIPTION (DRD)
DATA REQUIREMENTS DESCRIPTION (DRD) 1. DPD NO.: XXX ISSUE: Draft 2. DRD NO.: STD/EDAL 3. DATA TYPE: 3 4. DATE REVISED: 5. PAGE: 1/3 6. TITLE: Engineering Drawings and Associated Lists 7. DESCRIPTION/USE:
PROVIDER MONITORING TOOL FOR NEW PROVIDERS
OFFICE OF DEVELOPMENTAL PROGRAMS PROVIDER MONITORING TOOL FOR NEW PROVIDERS (FY 2011-12) Note: This tool is intended for use by new Providers enrolled after 7/01/2011 1 Provider Monitoring Tool Instructions
Putting Business Capabilities to Work
Putting Capabilities to Work Jeff Scott VP/ & Technology Strategy OMG Webinar January 15, 2014 Who is Accelare? Innovative Process Thought Leadership Powerful Technology Experts in strategy execution and
Project Procurement Management
Project Procurement Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
2. Please describe the project s alignment with the Common System Principles (Appendix 1).
Project Name Project Summary Please provide the project charter with this request. Please note any changes to the scope or schedule, or budget in this section and any other information you feel necessary.
Business Unit CONTINGENCY PLAN
Contingency Plan Template Business Unit CONTINGENCY PLAN Version 1.0 (Date submitted) Submitted By: Business Unit Date Version 1.0 Page 1 1 Plan Review and Updates... 3 2 Introduction... 3 2.1 Purpose...