1 367 MODELLING AN INVENTORY MANAGEMENT IN CONSTRUCTION OPERATIONS INVOLVING ON- SITE FABRICATION OF RAW MATERIALS Do Young Jung 1, Seung Heon Han 2, Keon Soon Im 3, and Chung Kyu Ryu 4 ABSTRACT There are usually plenty of material inventories in a construction site. More inventories can meet unexpected demands, and also they may have an economical advantage by avoiding a probable escalation of raw material costs. On the other hand, these inventories also cause negative aspects to increase costs for storing redundant inventory as well as decreasing construction productivity. Therefore, a proper method of deciding an optimal level of material inventories while considering dynamic variations of resources under uncertainty is very crucial for the economical efficiency of construction projects. This research presents a stochastic modelling method for construction operations, particularly targeting a work process involving on-site fabrication of raw materials like iron-rebar process (delivery, cut and assembly, and placement). To develop the model, we apply the concept of factory physics to depict the overall components of a system. Then, an optimal inventory management model is devised to support purchase decisions where users can make timely actions on how much to order and when to buy raw materials. Also, optimal time lag, which minimizes the storage time for pre-assembled materials, is obtained. To verify this method, a real case is applied to elicit an optimal amount of inventory and time lag. It is found that average values as well as variability of inventory level decreased significantly so as to minimize economic costs related to inventory management under uncertain project condition. KEY WORDS Optimal inventory management, Inventory cost, Reorder point, Optimal time lag INTRODUCTION Material costs constitute more than 40% of the total construction cost, so materials are an important factor for the success of a construction project (Lee, 2004). In general, it is common practice to keep plenty of material inventories in a construction site, because it is too difficult and troublesome to make a small order for construction materials each and every time on demand. These surplus inventories can meet unexpected demands, and also may have economical advantages by avoiding an escalation of raw materials. However, they also have negative aspects; (1) increase financial costs, so-called inventory holding Researcher, Technology Research Institute, Daelim Industrial Corporation, Seoul, , Phone , FAX , [email protected] Associate Professor, Civil and Env. Engineering Department, Yonsei Univ., Seoul, , Korea, Phone , [email protected] Ph.D. Candidate, Daelim Industrial Corporation, Seoul, , Korea, Phone , [email protected] MS student, Civil and Env. Engineering Department, Yonsei Univ., Seoul, , Korea, Phone , [email protected]
2 368 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu costs, and often (2) decrease construction productivity due to excessive storage areas, unnecessary amount of work in process (WIP), and other inefficiencies. Being aware of these facts, a number of researchers have so far presented an application of lean concepts and techniques for efficient management of certain type of materials (Arbulu et al. 2003, Pheng and Chuan 2001, Tommelein and Li 1999). Those concepts and techniques include value-adding, value stream, waste removal, just-in-time, and kanban. Their highest priorities are to attain nearly zero waste and inventory. There also has been research that analyzed the influence of material inventory and experimentally attempted to find out optimal inventory levels (Horman and Thomas 2005, Han et al. 2006, Polat et al. 2007). Construction projects have many changes and variations through the construction process, so a certain level of material inventory is essential. Moreover, construction firms are increasingly adopting a modularization process involving on-site fabrication of raw materials like the iron-rebar process. This is a more complex system composed of a manufacturing factory of raw material, a temporary assembly shop near the construction site, and a construction site that consumes preassembled products. In this process, there are two kinds of inventories: raw materials delivered from a factory and pre-assembled parts in a temporary shop. To the best of our knowledge, there is no modelling effort that optimizes inventory management for this type of projects. By virtue of all previous efforts, this research aims to present a proper method of deciding an optimal level of material inventories for this emerging process while considering dynamic resource variations under uncertainty from the perspective of site managers. RESEARCH METHODOLOGY We conceptualize a construction operation system involving on-site fabrication of raw materials and then identify the essential influencing factors on the system by applying the concept of factory physics. On the basis of system theory, we present an algorithm to investigate an optimal level of raw materials and adequate time lag for storing assembled products. The optimal level of raw material is constructed by the deposition of both statistical inventory model and pulls system. This model is designed to support purchase order decisions on how much and when to order. Also, optimal time lag, which minimizes a storage time for pre-assembled products, queued in an assembly shop, is suggested. To address the uncertain project condition, this research uses Monte Carlo simulation 5 method to obtain an optimal inventory level and to forecast total inventory costs. Finally, this method is applied to the actual rebar fabrication process to demonstrate its effectiveness and validity. THEORETICAL BACKGROUND SYSTEM ANALYSIS System analysis is a structured problem-solving approach with the following characteristics (Hopp and Spearman 2000): (1) The problem is viewed in the context of interacting subsystems. (2) The objective always specified first, and then alternatives are sought and evaluated in terms of this objective. 5 A tool which uses random numbers to measure the effects of uncertainty in a spreadsheet model (Crystal Ball 7.2 user guide)
3 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 369 (3) With the objective in mind, the system approach seeks as broad a range of alternative policies as possible. (4) To compare alternatives in terms of the objective, the modelling/optimization step is carried out for quantification. (5) In almost every system, the objectives, alternatives and model are revised repeatedly because real-world systems are complex. There are four basic phases in system analysis. Based on these four phases, a system analysis procedure of an inventory management system in the domain of this research scope is developed as shown in Table 1. Following these steps, the system analysis of a current operation is performed to broadly understand a work process and to seek any insight for improving a current system. Table 1: System Analysis Procedure of Inventory Management System Revised from Hopp and Spearman, 2000) Phase Operation Analysis System Design Implementatio n Evaluation Details Setting Objectives/Constraints, Looking for Problems, Modelling, Looking for Control Factors Look for Alternatives, Optimize Control Levels Implement Policies, Performance Analysis Site Manager Interview, Feedback Associated Tools and Techniques Investigation/Survey, Business Process Design, Influence Diagram Probabilistic Modelling Monte Carlo Simulation Interview/Question PUSH AND PULL SYSTEM A push system schedules the release of work based on demand, while a pull system authorizes the release of work based on system status (Hopp and Spearman 2000). This definition means that a push system release materials or a job to the site precisely when called to do so by an exogenous schedule, and the release time is not modified according to what is happening in the site. In contrast, a pull system only allows ordering materials or a job onto the site when a signal is generated by calling for it. In terms of inventory management, however, a pull system can be more effective in that it is easy to meet unexpected changes and allows low inventory into the system. The concept of a pull system is implemented in the modelling feature on the whole in this paper. STATISTICAL INVENTORY MODEL In the conventional inventory management model, many factors are assumed to be deterministic: thereby are much different from real situations. When there is a possibility to encounter an arbitrary situation, it should be addressed into the model in terms of probabilistic nature. The model that is widely used in manufacturing industry as a Production System Design
4 370 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu production planning tool is the reorder point policy, which classifies issues on inventory control into two parts (Anupindi et al. 2005); (1) the decision on order quantity or inventory quantity that will be either purchased or produced at every time of supplement; and (2) the decision on reorder point or inventory level when a supplement is required. Figure 1 exhibits an inventory pattern under the conditions of such an inventory model. Inventory is to be observed continuously while demand occurs in an arbitrary fashion. In particular, under a situation where everything happens to come together, if the inventory level reaches the reorder point (ROP), the order quantity (Q) needs to be measured based on the lead time (L) and the slope of inventory utilisation (R). Here, the solution is to determine adequate Q and ROP. Also, in determining Q and ROP, a safety level of inventory (I s ) should be considered to avoid any possible stoppage due to lack of inventory. The model to deal with such issues is called the (Q,r) model (Hopp and Spearman 2000). This model, however, primarily deals with the steady and deterministic nature of inventory management. In this paper, optimal order quantity and reorder point that minimizes the inventory management cost is to be sought based on a statistical inventory model, and also the optimal inventory level is elicited accordingly. Inventory I (t) Q Reorder Reorder Reorder ROP -R μ Safety Inventory (Is) Place Order L Receive Order Place Order L Receive Order Time (t) Figure 1: Inventory Pattern in Statistical Inventory Model (Anupindi et al. 2005) ANALYSIS OF EXISTING SYSTEM (OPERATION ANALYSIS) In this section, the inventory management system is analyzed in accordance with the procedure of system analysis presented in the previous section. Then, a method to manage the optimal level of inventory is presented. Following the analysis of existing system operations, system design is conducted to draw the valuable insights. SETTING OBJECTIVES AND CONSTRAINTS As previously stated, the primary goal of this research is to elicit an optimal inventory level in the process of construction operations, involving fabrication/assembling process for raw materials. This research proposes a strategy in order to control inventory up to the optimal inventory level. In order to maintain an optimal inventory level while considering the entire system, detailed works and their interrelationships should be conceptualized.
5 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 371 In general, jobs relating to materials procurement are divided into two sections: (1) largescale procurements performed in the head office (centralized purchases), and (2) ondemand procurements related to work progress (jobsite purchases). In this paper, we focus on the works related to the site material management. Particularly, rebar inventory management that requires the fabrication/assembly process for materials within a temporary processing shop near the site is the focus of our study. This type of material processing has steadily increased in large-scale civil and industrial projects because it can satisfy demands from the relevant construction site in a timely and effective manner in the nature of temporary construction operations. DIAGNOSING PROBLEMS OF THE SYSTEM Considering the objectives and scope of this analysis, problems on the current system are derived through the established process. The current system involving the processing process for raw materials is composed of flows of materials and information among the manufacturing factory; temporary assembly shop for processing raw materials; and the construction site where processed materials are installed. Through site investigations and field observations, it is found that inventory management on such a process has the following problems: 1) In general, the concept of an optimal inventory is deemed lacking, so inventory management primarily relies on the field manager s experience and intuition. It brings difficulties to the management thereof and causes to disburse unnecessary expenses. 2) There is a lack of tools to predict accurate demands in the locale of uncertain construction sites, so that it produces a difficult situation for a temporary assembly shop to timely respond to variable changes in the demand of the works. 3) Theoretically, it is not necessary to store assembled materials because it is on the make-to-order (MTO) basis from the construction site. However, the amount of assembled inventory tends to increase by holding additional products that were processed earlier than the schedule of installation on the site. MODELLING THE SYSTEM Business Process Design (BPD) is used for modelling as exhibited in Figure 2. The basic input in the model is raw materials produced in the manufacturing factory. As seen in the model, total inventory within the system can be regarded as the sum of the inventory of raw materials, WIP (work in process) in the temporary shop, and assembled products that are queued. Production System Design
6 372 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu Adjust the date Request for assembled products Production Factory of Raw Materials Temporary Fabrication Shop Construction Site Raw Materia < Make-To-Stock > ls Optimal Level of Inventory Assembled Products Place orders of raw materials < Make-To-Order > Optimal Time Lag process inventory flow of material flow of information Figure 2: BPD of the Inventory Management System Raw material inventory occurs when raw materials delivered from the manufacturing factory have been queued by the temporary shop in order to process those raw materials. As works keep going continuously at the temporary shop, raw materials need to be secured up to a certain level in advance. Thus, during delivery of raw materials to the temporary shop, it is required to maintain a safety buffer against the volatile demands on the make-to-stock (MTS) basis so that the optimal level of raw material can be elicited accordingly. Meanwhile, the inventory of assembled products occurs when they are lined up in the temporary shop prior to delivery to the construction site. Assembled products are usually produced after receiving orders from the construction site in accordance with work schedules and shop drawings. Therefore, production of assembled products can be said of being on a make-to-order (MTO) basis. Here, the important thing is to determine when to begin the assembly job at the shop on the basis of site demand. The earlier the assembly work starts, the more the inventory of assembled products. Conversely, the later the work begins, the higher the site can be stopped due to the lack of inventory. Accordingly, it should be required to elicit an optimal time lag for assembling job while minimizing the inventory of assembled products. IDENTIFYING CONTROL FACTORS To identify control variables after examining the current system through BPD, the influence diagram on inventory is drawn as shown in Figure 3. It is developed using the Influence Diagram technique. When examining the Influence Diagram, lead time variance, demand variance, and temporary shop size have direct influence on the inventory of raw materials. Further, demand variance, variance of daily production in the temporary shop, and size of a temporary shop also affects the inventory amount of assembled products. The high level of inventory affects the economic costs that are related to excessive storage and maintenance costs. Productivity also can decline due to interference and overcrowd of construction site. Likely, low inventory levels affect the possible absence of stock provoking work delays. Since the impact of productivity is ultimately incorporated into
7 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 373 the economic costs, the authors attempt to measure the whole cost influence associated with inventory level through the use of economic costs. Conditions of the Factory Lead Time Variance Demand Variance Inventory of the raw materials Inventory of the assembled products Conditions of the Site Economic Costs Productivity Size of shop Variance of Daily production decision variable uncertain variable deterministic variable influence relationship Figure 3: Inventory Influence Diagram Accordingly, this research presents the optimal level of raw materials and the optimal time lag for assembly jobs, which can minimize the economic costs on the whole. In this process, key control factors such as lead time variance and demand variance are carefully investigated to keep the inventory level as low as possible. OPTIMAL INVENTORY MANAGEMENT MODEL (SYSTEM DESIGN) RAW MATERIAL INVENTORY At first, methods to determine Q and ROP that minimize the economic costs relating to inventory levels of raw materials are presented using Monte Carlo simulation. As for simulation tools, Crystal Ball 6 is used to forecast consequential values under uncertainty based on an Excel spreadsheet model. To perform simulations in Crystal Ball, an Excel spreadsheet model is first constructed, where cells inside the spreadsheet are defined as having one of three attributes, namely, assumption, decision, and forecast. Through the assumption cells, it is possible to include key control variables by giving random distributions to the specified cell. Decision variable refers to the factor that should be decided in the model. By deciding upper and lower limits, decision can be made within such limits. Through assigning forecast attributes, the objective value can be predicted in a probabilistic form according to assumptions and decision variables, employing the objective function to forecast with. The attributes of the model used in this research are shown in Table 2. Input and output information, and framework are also illustrated in Figure 4. Mathematical algorithms embedded in the Excel simulation model for estimating Q, ROP, and total inventory costs are not included here for the sake of brevity. 6 A graphically oriented forecasting and risk analysis program that takes the uncertainty out of decisionmaking using Monte Carlo simulation (Crystal Ball 7.2 user guide) Production System Design
8 374 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu Table 2: Attributes of the Excel Spreadsheet Model (Raw Materials) Assumptions Decisions Forecasts Order Quantity (Q), Lead Time variance, Total Inventory Reorder Point Demand variance Cost (ROP) Figure 4: Input and Output Information and Model Framework (Raw Materials) ASSEMBLED PRODUCTS INVENTORY In a similar way, in the part of assembled products inventory management, a method to determine the optimal time lag that can minimize economic costs related to the assembled products inventory can be developed using Monte Carlo simulation. The optimal time lag aims to decide whether or not to start the assembly job having time buffer to a certain extent before delivery to the designated construction works. Attributes of the model used to control the assembled products inventory are shown in Table 3. Input and output information, and frame work are organized and shown in Figure 5. Table 3: Attributes of the Excel Spreadsheet Model (Manufactured Products) Assumptions Decisions Forecasts Work amount/day, Time lag Total Inventory Variance of daily (Start date of Cost production assembly job)
9 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 375 Figure 5: Input and Output Information / Framework (Manufactured Products) CASE STUDY: IRON-REINFORCED BAR FABRICATION PROCESS The case project was the inventory management system of the temporaryshop to produce iron-reinforced bars in the light-rail transit construction site around the Seoul metropolitan area in Korea. Construction work was performed in an urban area crossing the heart of the city and commercial district so there was a high likelihood of changes in time schedules due to permits as well as public resistance or complaints on the project. Also, the storage area for material inventory was very limited. The rate of indirect costs of inventory management is relatively higher than that of rural area s. Therefore, it can be noted that this site necessitates efficient management of material inventory. To analyze the actual situation of inventory control, a survey on material flows during the last six months was conducted, primarily based on field reports that informed the daily inflow and outflow of raw materials and assembled products. By applying these actual data to the model proposed, a comparative analysis is performed to draw any advantage over conventional experience-based method. ASSUMPTIONS OF INVENTORY COSTS Costs related to material management can vary depending on the construction site and work process. Cost assumptions were set up on the basis of interviews with the field manager who has been working at the temporary assembling shop at the construction site. Inventory costs can be divided into: (1) delivery and maintenance cost of raw materials, and (2) stockout cost when stocks of assembled products are dried out. Delivery and maintenance costs of raw materials are those costs required for delivering, storing and keeping materials at the shop after issuance of purchase orders. Stockout cost refers to the acceleration costs required when stock materials are lacking and additional compression costs are necessary to avoid the delay of construction duration, including such cost as rushing, overtimes, and overhead costs. OPERATION ANALYSIS The sample project tended to keep a safety stock large enough to hold a cache of more than one month s worth of raw materials due to the lack of optimal inventory concepts. Production System Design
10 376 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu They could not even grasp the exact amount of inventory within the premises of the temporary fabrication shop. Also, despite the fact that it is not necessary to keep additional assembled products, it was found that, actually, they were queued for 4 to 7 days, largely due to inconsistencies between production schedules of the temporary shop and actual work schedules at the construction site. Table 6 (As-Is) shows an ineffective arrangement of the amount of inflow and outflow of material per month, measured at the temporary shop. OPTIMAL RAW MATERIAL INVENTORY In this part, a simulation was performed having outflow materials as actual demands at the temporary shop. Probability distributions of monthly demands were derived from data fitting based on daily variations of each month by using data gathered through field observations. Procurement lead time was also assumed to have a Poisson distribution because lead time values should be random as well as positive on a monthly basis (integer values). Through the simulation process as depicted in Figure 4, monthly optimal order quantity and reorder point were elicited. Table 4 indicates results of the simulation. As compared to Table 6 (As-Is), March and April values, when work progress rates were not productive, were found to be relatively low while those of May and June were at a higher level having high progress rates. During the rainy season (July and August), order quantities are lower due to the slow work pace, but reorder points are relatively high. That can be explained by the fact that the stock inventory of a previous month (June) was very high so reorder points of July and August were also elicited as high to reflect the circumstances of the previous month. Table 4: Monthly Optimal Order Quantity and Reorder Point (unit: ton) Month March April May June July August Order Quantity (Q) Reorder Point (ROP) OPTIMAL ASSEMBLED MATERIAL INVENTORY In another part of the assembled products inventory, the optimal time lag was elicited using the method as presented in Figure 5. Also, the total inventory cost was forecasted by applying those values. Table 5 is an arrangement of the simulation results of monthly optimal time lags. Similar to results of Table 4, it was found that time lags (lag between actual delivery time to the work site and pre-assembling time at the factory shop) were the highest during May and June when the progress rates were most productive. These time lags aim to shield against the variable demands of the job site. Table 5: Monthly Optimal Time Lag (unit: day) Month March April May June July August Time lags
11 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 377 ANALYSIS OF PERFORMANCE Results from the application of the model (to-be) is compared to the as-is state. Figure 6 shows the flow of inventory quantity before and after the application of the optimal inventory management method. Table 6 also shows the monthly inflow and outflow of materials as well as average inventory quantity. As seen in Figure 6, the flow of inventory is levelled to display a narrow range of variation comparing to the as-is state. The proposed model can keep the stability of inventory at levels below 500 tons. Also, Table 6 explains that the monthly average amount of inflow material can be kept at an optimal inventory level in association with the amount of outflow of each month (demands). The primary benefits of this model are not only the reduction of average inventory amounts, but also the flatness of standard deviations. It implies that the inventory quantity in the construction site can be reduced in a more stable fashion. Accordingly, inventory management costs of the temporary shop has been decreased by a level of 25% comparing to the as-is state. Even though, this is the result obtained by the simulated situation, it can be the fruit that distinctly shows the effect of decreased inventory management costs, being achieved through means of applying the optimal inventory management strategy ton as-is state optimized to-be state based on the proposed model 0 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Month Figure 6: Flow of Inventory Quantity before and after Application Table 6: States of Material Inventory (As-Is & To-Be) (unit: ton) Average Inflow (Receiving) Average Outflow (Releasing) Average Inventory Standard Deviation (daily variations) As-is To-be As-is To-be As-is To-be As-is To-be March April May 2, , Production System Design
12 378 Do Young Jung, Seung Heon Han, Keon Soon Im and Chung Kyu Ryu June 1, , July 1, , Aug , Total 5, ,690 3, , , CONCLUSIONS This paper developed a probabilistic optimal inventory management model on the process of construction works that involves on-site fabrication of raw materials like the iron-rebar process. It is a unique system composed of a manufacturing factory of raw material, a fabrication or assembly shop, and a construction site. This process is characterised by distinctive inventory flows. To reduce inventory quantity and costs, it is required to maintain an optimal level of raw materials at the temporary shop. More to the storage of raw materials, the inventory of assembled products occurs when they are lined up in the temporary shop prior to delivery to the construction site. Accordingly, it should be required to elicit an optimal time lag for the start of assembly jobs that can minimize the inventory of assembled products. The proposed model was applied to an actual case to verify its performance and advantages. Without a systemized tool, the current inventory flow was ineffective with the irregular patterns by displaying unnecessary large quantities of raw materials as well as higher levels of time lag buffers. This inefficiency was significantly improved by the proposed model. Results from the case application are summarized as follows; (1) By applying the pull system to the phase of raw material inventory management, the amount of inflow and outflow iron-bars at the temporary shop achieved a balance, and accordingly, average inventory quantity and inventory management costs were also evidently reduced, and (2) By eliciting optimal time lags relating to the start of fabrication/assembly works, it was possible to reduce the holding time of assembled products, and accordingly, inventory management costs could be reduced around a total of 25%. However, there were many assumptive views in relation to such cost factors as inventory storage cost, delivery cost, and additional costs when the materials are exhausted. It is recommended to conduct future research to quantify those cost aspects under different project conditions in a more realistic way. Moreover, such areas to reduce the level of variance of influential factors that affect the level of inventory will be central parts of our future research. ACKNOWLEDGEMENTS The authors would like to thank the Korean Ministry of Construction and Transportation for funding (05 CIT D05-01) that made this research possible. REFERENCES Anupindi, R., Chopra, S., Deshmukh, S. D., Mieghem, J. V. and Zemel, E. (2005). Managing Business Process Flows. 1st edition, Prentice Hall, New Jersey
13 Modelling an Inventory Management in Construction Operations Involving On-Site Fabrication of Raw Materials 379 Arbulu, R.J., Ballard G.H. and Harper, N. (2003). "Kanban in Construction.", Proceedings of the 11th Annual Conference of the International Group for Lean Construction, Blacksburg, Virginia Han, S.H., Ryu, H.D., Chae, M.J. and Im, K.S. (2006). "Six- Sigma based Approach to Improve Productivity for Construction Processes and Operations", Journal of Civil Engineering, KSCE, Vol. 26, No. 4 Hopp, W.J. and Spearman, M.L. (2000). Factory Physics: Foundations of Manufacturing Management. 2nd edition, Irwin/McGraw-Hill, Boston Horman, M.J. and Thomas, H.R. (2005). "Role of inventory buffers in construction labour performance.", Journal of Construction Engineering and Management, Vol. 131, No. 7 Lee, S. B. (2004). "A Study on Optimal Lead Time Selection Measure of the Construction Materials. ", Korean Journal of Architecture Engineering, Vol. 4, No. 1 Pheng, L.S. and Chuan, C.J. (2001). "Just-in-Time Management of Pre-cast Concrete Components. ", Journal of Construction Engineering and Management, Vol. 127, No. 6 Polat, G., Arditi, D. and Mungen, U. (2007). "Simulation-Based Decision Support System for Economical Supply Chain Management of Rebar", Journal of Construction Engineering and Management, Vol. 133, No. 1 Tommelein, I.D. and Li, A.E. (1999). "Just-in-Time Concrete Delivery: Mapping Alternatives for Vertical Supply Chain Integration", Proceedings of the 7th Annual Conference of the International Group for Lean Construction, Berkeley, California Production System Design
Simulation and Lean Six Sigma
Hilary Emmett, 22 August 2007 Improve the quality of your critical business decisions Agenda Simulation and Lean Six Sigma What is Monte Carlo Simulation? Loan Process Example Inventory Optimization Example
Six Sigma-Based Approach to Improve Performance in Construction Operations
Six Sigma-Based Approach to Improve Performance in Construction Operations Seung Heon Han, M.ASCE 1 ; Myung Jin Chae, Ph.D., P.E. 2 ; Keon Soon Im, P.E. 3 ; and Ho Dong Ryu 4 Abstract: Many researchers
Management of Uncertainty In Supply Chain
Management of Uncertainty In Supply Chain Prof.D.P.Patil 1, Prof.A.P.Shrotri 2, Prof.A.R.Dandekar 3 1,2,3 Associate Professor, PVPIT (BUDHGAON), Dist. Sangli(M.S.) [email protected] [email protected]
Introduction. How Important Is Inventory Control?
PUBLICATION 420-148 Lean Inventory Management in the Wood Products Industry: Examples and Applications Henry Quesada-Pineda, Assistant Professor, Wood Science and Forest Products, and Business and Manufacturing
A Programme Implementation of Several Inventory Control Algorithms
BULGARIAN ACADEMY OF SCIENCES CYBERNETICS AND INFORMATION TECHNOLOGIES Volume, No Sofia 20 A Programme Implementation of Several Inventory Control Algorithms Vladimir Monov, Tasho Tashev Institute of Information
Synergy: Building Information Modeling and
: Building Information Modeling and Assoc. Professor Rafael Sacks BIM Handbook Symposium Georgia Tech Atlanta, GA, 13 th March 2008 Introduction Both and BIM are deep process changes, in thinking and in
Inventory Management - A Teaching Note
Inventory Management - A Teaching Note Sundaravalli Narayanaswami W.P. No.2014-09-01 September 2014 INDIAN INSTITUTE OF MANAGEMENT AHMEDABAD-380 015 INDIA Inventory Management - A Teaching Note Sundaravalli
School of Management and Languages Capacity Planning
School of Management and Languages Capacity Planning Dr Neil Towers 1 Learning Objectives a. To understand Capacity Planning and Control b. To manage the supply chain capabilities effectively Dr Neil Towers
A Cross-Functional View of Inventory Management, Why Collaboration among Marketing, Finance/Accounting and Operations Management is Necessary
A Cross-Functional View of Inventory Management, Why Collaboration among Marketing, Finance/Accounting and Operations Management is Necessary Richard E. Crandall, Appalachian State University, John A.
Manufacturing Flow Management
Manufacturing Flow Management Distribution D Distribution Authorized to Department of Defense and U.S. DoD Contractors Only Aim High Fly - Fight - Win Supply Chain Management Processes Information Flow
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Building and Using Spreadsheet Decision Models
Chapter 9 Building and Using Spreadsheet Decision Models Models A model is an abstraction or representation of a real system, idea, or object. Models could be pictures, spreadsheets, or mathematical relationships
TOOLS OF MONTE CARLO SIMULATION IN INVENTORY MANAGEMENT PROBLEMS
TOOLS OF MONTE CARLO SIMULATION IN INVENTORY MANAGEMENT PROBLEMS Jacek Zabawa and Bożena Mielczarek Institute of Industrial Engineering and Management Wrocław University of Technology 50-370, Wrocław,
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Demand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish
Demand forecasting & Aggregate planning in a Supply chain Session Speaker Prof.P.S.Satish 1 Introduction PEMP-EMM2506 Forecasting provides an estimate of future demand Factors that influence demand and
University Of California, Berkeley Department of Mechanical Engineering. ME 204: Advanced Manufacturing Systems Analysis, AMS (3 units)
University Of California, Berkeley Department of Mechanical Engineering ME 204: Advanced Manufacturing Systems Analysis, AMS (3 units) CATALOG DESCRIPTION Graduate Course Syllabus This course is designed
Glossary of Inventory Management Terms
Glossary of Inventory Management Terms ABC analysis also called Pareto analysis or the rule of 80/20, is a way of categorizing inventory items into different types depending on value and use Aggregate
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
Business Process Management of Telecommunication Companies: Fulfillment and Operations Support and Readiness Cases
Business Process of Telecommunication Companies: Fulfillment and Operations Support and Readiness Cases Byeong-Yun Chang School of Business Administration, Ajou University [email protected] Abstract In
Analysing and Improving Manufacturing Operations using Production and Inventory Control SIMulator (PICSIM)
LINKÖPING INSTITUTE OF TECHNOLOGY Department of Mangement and Engineering TPMM06 Analysing and Improving Manufacturing Operations Helene Lidestam March 2015 Analysing and Improving Manufacturing Operations
Case Study on Forecasting, Bull-Whip Effect in A Supply Chain
International Journal of ISSN 0974-2107 Systems and Technologies Vol.4, No.1, pp 83-93 IJST KLEF 2010 Case Study on Forecasting, Bull-Whip Effect in A Supply Chain T.V.S. Raghavendra 1, Prof. A. Rama Krishna
EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY
EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY Introduction Inventory is considered the necessary evil of the supply chain. In fact, there has been a whole movement; lean manufacturing that has tried to reduce
Risk Analysis Overview
What Is Risk? Uncertainty about a situation can often indicate risk, which is the possibility of loss, damage, or any other undesirable event. Most people desire low risk, which would translate to a high
MCQ: Unit -2: Operation processes
MCQ: Unit -2: Operation processes 1.What type of process would a Cement plant be most likely to use? a. Continuous flow b. Project c c. Job shop d. Flow shop 2. Process selection is primarily considered
APPROACHES FOR PERFORMANCE MEASUREMENT OF URBAN RENEWAL MEGAPROJECTS
APPROACHES FOR PERFORMANCE MEASUREMENT OF URBAN RENEWAL MEGAPROJECTS Heedae Park Combined Master s & Doctoral Program Student Dept. of Civil Engineering, Yonsei University [email protected] Seung
PRINCIPLES OF INVENTORY AND MATERIALS MANAGEMENT
PRINCIPLES OF INVENTORY AND MATERIALS MANAGEMENT Fourth Edition Richard J. Tersine The University of Oklahoma TEGHNISCHE HOCHSCHULE DARMSTADT Fochbereich 1 Gesonr> 11-. ib I iothek Betiier >wi rtschottsiehre
Using simulation to calculate the NPV of a project
Using simulation to calculate the NPV of a project Marius Holtan Onward Inc. 5/31/2002 Monte Carlo simulation is fast becoming the technology of choice for evaluating and analyzing assets, be it pure financial
Going Lean the ERP Way
Going Lean the ERP Way Somnath Majumdar Abstract: Lean concepts and techniques are widely used all over the world today to eliminate waste in all processes. These are applicable for all organizations,
Lean Kitting: A Case Study
Lean Kitting: A Case Study Ranko Vujosevic, Ph.D. Optimal Electronics Corporation Jose A. Ramirez, Larry Hausman-Cohen, and Srinivasan Venkataraman The University of Texas at Austin Department of Mechanical
Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I
Index Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1 EduPristine CMA - Part I Page 1 of 11 Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting
BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 -
BSCM Sample TEST. 1. Which of the following demand fulfillment approaches typically provides the longest delivery time? A) Engineer-to-order. B) Make-to-order. C) Assemble-to-order. D) Make-to-stock. 2.
Industry Environment and Concepts for Forecasting 1
Table of Contents Industry Environment and Concepts for Forecasting 1 Forecasting Methods Overview...2 Multilevel Forecasting...3 Demand Forecasting...4 Integrating Information...5 Simplifying the Forecast...6
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 36 Location Problems In this lecture, we continue the discussion
Case study of a batch-production/inventory system E.M.M. Winands 1, A.G. de Kok 2 and C. Timpe 3
Case study of a batch-production/inventory system E.M.M. Winands 1, A.G. de Kok 2 and C. Timpe 3 The plant of BASF under consideration consists of multiple parallel production lines, which produce multiple
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT. Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ
THE UTILISATION OF STATISTICAL METHODS IN THE AREA OF INVENTORY MANAGEMENT Petr BESTA, Kamila JANOVSKÁ, Šárka VILAMOVÁ, Iveta VOZŇÁKOVÁ, Josef KUTÁČ VSB Technical University of Ostrava, Ostrava, Czech
SUPPLY CHAIN MODELING USING SIMULATION
SUPPLY CHAIN MODELING USING SIMULATION 1 YOON CHANG AND 2 HARRIS MAKATSORIS 1 Institute for Manufacturing, University of Cambridge, Cambridge, CB2 1RX, UK 1 To whom correspondence should be addressed.
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
WORKING CAPITAL MANAGEMENT
CHAPTER 9 WORKING CAPITAL MANAGEMENT Working capital is the long term fund required to run the day to day operations of the business. The company starts with cash. It buys raw materials, employs staff
Operations Management Part 12 Purchasing and supplier management PROF. NAKO STEFANOV, DR. HABIL.
Operations Management Part 12 Purchasing and supplier management PROF. NAKO STEFANOV, DR. HABIL. Introduction basic terms Supply management describes the methods and processes of modern corporate or institutional
Dynamic Simulation and Supply Chain Management
Dynamic Simulation and Supply Chain Management White Paper Abstract This paper briefly discusses how dynamic computer simulation can be applied within the field of supply chain management to diagnose problems
Job Manager for Metal Fabrication
Job Manager for Metal Fabrication What makes Metal Fabrication unique? First, most metal shops are building to unique specifications. The Jobs are service type jobs, not production type jobs. Mass Production
Simple Inventory Management
Jon Bennett Consulting http://www.jondbennett.com Simple Inventory Management Free Up Cash While Satisfying Your Customers Part of the Business Philosophy White Papers Series Author: Jon Bennett September
Analysis of Load Frequency Control Performance Assessment Criteria
520 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO. 3, AUGUST 2001 Analysis of Load Frequency Control Performance Assessment Criteria George Gross, Fellow, IEEE and Jeong Woo Lee Abstract This paper presents
Course Supply Chain Management: Inventory Management. Inventories cost money: Reasons for inventory. Types of inventory
Inventories cost money: Inventories are to be avoided at all cost? Course Supply Chain Management: Or Inventory Management Inventories can be useful? Chapter 10 Marjan van den Akker What are reasons for
THE INTEGRATION OF SUPPLY CHAIN MANAGEMENT AND SIMULATION SYSTEM WITH APPLICATION TO RETAILING MODEL. Pei-Chann Chang, Chen-Hao Liu and Chih-Yuan Wang
THE INTEGRATION OF SUPPLY CHAIN MANAGEMENT AND SIMULATION SYSTEM WITH APPLICATION TO RETAILING MODEL Pei-Chann Chang, Chen-Hao Liu and Chih-Yuan Wang Institute of Industrial Engineering and Management,
TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling
TU-E2020 ADVANCED OPERATIONS MANAGEMENT Demand management Sales & Operations Planning Master Production Scheduling 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999
Collaborative Supply Chain Management Learning Using Web-Hosted Spreadsheet Models ABSTRACT
Collaborative Supply Chain Management Learning Using Web-Hosted Spreadsheet Models Don N. Pope Abilene Christian University, ACU Box 29309, Abilene, Texas 79699-9309 Phone: 325-674-2786 Fax: 325-674-2507
Sales and Operations Planning in Company Supply Chain Based on Heuristics and Data Warehousing Technology
Sales and Operations Planning in Company Supply Chain Based on Heuristics and Data Warehousing Technology Jun-Zhong Wang 1 and Ping-Yu Hsu 2 1 Department of Business Administration, National Central University,
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Overview.
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Andersen Consultng 1600 K Street, N.W., Washington, DC 20006-2873 (202) 862-8080 (voice), (202) 785-4689 (fax) [email protected]
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by
A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method
Send Orders for Reprints to [email protected] 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo
DIRECT MAIL: MEASURING VOLATILITY WITH CRYSTAL BALL
Proceedings of the 2005 Crystal Ball User Conference DIRECT MAIL: MEASURING VOLATILITY WITH CRYSTAL BALL Sourabh Tambe Honza Vitazka Tim Sweeney Alliance Data Systems, 800 Tech Center Drive Gahanna, OH
Risk Analysis and Quantification
Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk
Management Information System Prof. Biswajit Mahanty Department of Industrial Engineering & Management Indian Institute of Technology, Kharagpur
Management Information System Prof. Biswajit Mahanty Department of Industrial Engineering & Management Indian Institute of Technology, Kharagpur Lecture - 02 Introduction Part II Welcome to all of you
Business Process Optimization w/ Innovative Results
Business Process Optimization w/ Innovative Results Sam DiSalvatore Introduction The principle of continuous process improvement is based on the belief that even excellent products and services can be
A Conceptual Approach to Data Visualization for User Interface Design of Smart Grid Operation Tools
A Conceptual Approach to Data Visualization for User Interface Design of Smart Grid Operation Tools Dong-Joo Kang and Sunju Park Yonsei University [email protected], [email protected] Abstract
Production Planning Process in a Flexible Manufacturing Cell
ISBN 978-1-84626-xxx-x Proceedings of 2011 International Conference on Optimization of the Robots and Manipulators (OPTIROB 2011) Sinaia, Romania, 26-28 Mai, 2011, pp. xxx-xxx Production Planning Process
TRAVERSE Manufacturing
Manufacturing TRAVERSE Manufacturing from Open Systems, Inc. is the perfect solution for smaller growing to larger progressive manufacturers Managing profitability, cost control, inventory control, purchasing
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
Lean, Six Sigma, and the Systems Approach: Management Initiatives for Process Improvement
PREPRINT Lean, Six Sigma, and the Systems Approach: Management Initiatives for Process Improvement Robert B. Pojasek Pojasek & Associates, Boston, USA This paper will be published as a featured column
Reliability Modeling Software Defined
Reliability Modeling Software Defined Using Titan Reliability Modeling Software May 30, 2014 Prepared by: The Fidelis Group 122 West Way, Suite 300 Lake Jackson, TX 77566 Fidelis Group, LLC All Rights
A System Dynamics Approach to Reduce Total Inventory Cost in an Airline Fueling System
, June 30 - July 2, 2010, London, U.K. A System Dynamics Approach to Reduce Total Inventory Cost in an Airline Fueling System A. Al-Refaie, M. Al-Tahat, and I. Jalham Abstract An airline fueling system
Logistics Management SC Performance, SC Drivers and Metrics. Özgür Kabak, Ph.D.
Logistics Management SC Performance, SC Drivers and Metrics Özgür Kabak, Ph.D. Outline Supply Chain Performance: Achieving Strategic Fit and Scope Competitive and supply chain strategies Achieving strategic
Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow
TPPE37 Manufacturing Control Agenda Lecture 2 Inventory Management 1. Inventory System Defined 2. Inventory Costs 3. Inventory classification 4. Economic order quantity model 5. Newsboy problem 6. Reorder
CHOICES The magazine of food, farm, and resource issues
CHOICES The magazine of food, farm, and resource issues 4th Quarter 2005 20(4) A publication of the American Agricultural Economics Association Logistics, Inventory Control, and Supply Chain Management
APPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE
APPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE Badr O. Johar, Northeastern University, (617) 3737635, [email protected] Surendra M. Gupta, Northeastern University,
Monte Carlo analysis used for Contingency estimating.
Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4
STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL
Session 6. Applications of Mathematical Methods to Logistics and Business Proceedings of the 9th International Conference Reliability and Statistics in Transportation and Communication (RelStat 09), 21
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
tutor2u Stock Control The Importance of Managing Stocks AS & A2 Business Studies PowerPoint Presentations 2005
Stock Control The Importance of Managing Stocks AS & A2 Business Studies PowerPoint Presentations 2005 What Are Stocks? Three main categories of stocks Raw Materials Work in Progress Finished Goods Types
Plan forecast optimise
Plan forecast optimise Don t Forecast the future, CONTROL IT Reflex Business Forecasting breaks new ground. This is sales forecasting software with unique features that allow you to create real value for
Lean Six Sigma Lean 201 Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY
TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY Before we begin: Turn on the sound on your computer. There is audio to accompany this presentation. Audio will accompany most of the online
Chapter 12 Inventory Control and Management
Chapter 12 Inventory Control and Management Learning Outcomes Describe the functions and costs of an inventory system. Determine the order quantity and Economic Order Quantity. Determine the reorder point
Five Tips to Achieve a Lean Manufacturing Business
Five Tips to Achieve a Lean Manufacturing Business Executive Overview Introduction The more successful manufacturers today are those with the ability to meet customer delivery schedules while maintaining
Inventory Management and Risk Pooling
CHAPTER 3 Inventory Management and Risk Pooling CASE JAM Electronics: Service Level Crisis JAM Electronics is a Korean manufacturer of products such as industrial relays. The company has five Far Eastern
2 Organizations and Organizational Structures 2.1 Functional and Project Organizations, Typical Goals and Performance Measures
2 Organizations and Organizational Structures 2.1 Functional and Project Organizations, Typical Goals and Performance Measures The history of organizations is probably as long as the history of mankind.
Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions
Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Chapter 6 Working Capital Management Concept Check 6.1 1. What is the meaning of the terms working
It is concerned with decisions relating to current assets and current liabilities
It is concerned with decisions relating to current assets and current liabilities Best Buy Co, NA s largest consumer electronics retailer, has performed extremely well over the past decade. Its stock sold
NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE
NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE Marinela INŢĂ 1 and Achim MUNTEAN 1 ABSTRACT: Currently, Lean Manufacturing is a recognized topic in many research fields, which
Job Manager for Tool and Die Shops
Job Manager for Tool and Die Shops What makes Tool and Die Shops unique? First, most orders are for a unique Tool or Die. No two Jobs are alike. The Job is a one of a kind job, not a mass production type
Problems, Methods and Tools of Advanced Constrained Scheduling
Problems, Methods and Tools of Advanced Constrained Scheduling Victoria Shavyrina, Spider Project Team Shane Archibald, Archibald Associates Vladimir Liberzon, Spider Project Team 1. Introduction In this
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
Min/Max Inventory Planning for Military Logistics
21st International Congress on Modelling and Simulation, Gold Coast, Australia, 29 Nov to 4 Dec 2015 www.mssanz.org.au/modsim2015 Min/Max Inventory Planning for Military Logistics S. Shekh Defence Science
Lecture No. 12: Delivery Improvement and Inventory System. Takahiro Fujimoto
Business Administration Lecture No. 12: Delivery Improvement and Inventory System 1.Reduction of Production Period 2.Variety and Function of Inventory 3.Fixed-Quantity Order and Fixed-Period Order 4.Kanban
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION Fitria H. Rachmat 1, Lingguang Song 2, and Sang-Hoon Lee 2 1 Project Control Engineer, Bechtel Corporation, Houston, Texas, USA 2
Business Intelligence and Decision Support Systems
Chapter 12 Business Intelligence and Decision Support Systems Information Technology For Management 7 th Edition Turban & Volonino Based on lecture slides by L. Beaubien, Providence College John Wiley
Strategic Framework to Analyze Supply Chains
Strategic Framework to Analyze Supply Chains 1 Andy Guo A Strategic Framework for Supply Chain Design, Planning, and Operation Part I: Understand the supply chain Part II: Supply chain performance Part
KANBAN IN CONSTRUCTION
KANBAN IN CONSTRUCTION Roberto Arbulu 1, Glenn Ballard 2 and Nigel Harper 3 ABSTRACT Kanban is a lean approach developed in the automotive industry to pull materials and parts through production systems
ICT Project Management
THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE PUBLIC SERVICE MANAGEMENT ICT Project Management A Step-by-step Guidebook for Managing ICT Projects and Risks Version 1.0 Date Release 04 Jan 2010 Contact
Modeling Stochastic Inventory Policy with Simulation
Modeling Stochastic Inventory Policy with Simulation 1 Modeling Stochastic Inventory Policy with Simulation János BENKŐ Department of Material Handling and Logistics, Institute of Engineering Management
5 Unexpected Ways Continuous Improvement With Lean Six Sigma Can Improve Your Company
A Whitepaper from Juran Global The Source for Breakthrough Lean Six Sigma 5 Unexpected Ways Continuous Improvement With Lean Six Sigma Can Improve Your Company 0 Juran Global Our expertise has been developed
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
A Fuel Cost Comparison of Electric and Gas-Powered Vehicles
$ / gl $ / kwh A Fuel Cost Comparison of Electric and Gas-Powered Vehicles Lawrence V. Fulton, McCoy College of Business Administration, Texas State University, [email protected] Nathaniel D. Bastian, University
Diagnosis of production system of marine frozen products by inventory management theory - A case of blue fins
International Journal of Intelligent Information Systems 215; 4(2-1): 18-24 Published online February 6, 215 (http://www.sciencepublishinggroup.com/j/ijiis) doi: 1.11648/j.ijiis.s.215421.14 ISSN: 2328-7675