Truth in Negotiations Act (TINA) Essentials
|
|
|
- Tamsin Sims
- 10 years ago
- Views:
Transcription
1 Truth in Negotiations Act (TINA) Essentials Brent Calhoon, CPA and Jamie Sybert Date: June 5, 2012 Time: 12pm - 1:30pm Eastern
2 Discussion Topics Introductions Truth in Negotiations Act (TINA) Background and Overview Applicability & Exemptions What is cost or pricing data? What is certified cost or pricing data? What is data other than certified cost or pricing? Disclosure Government Reliance How to Challenge/Avoid Applicability Compliance Best Practices Defective Pricing Liability Potential Defenses 2
3 TINA Background and Overview Truth-In-Negotiations Act; P.L ; 10 U.S.C. 2306(a) Passed in 1962 and has been amended several times. Most recently amended by 1987 DoD Authorization and Appropriation Acts (P.L , P.L , P.L ) Made applicable to civilian agencies by Competition in Contracting Act, P.L , 41 U.S.C. 254(b) Came to life in the mid-1980s when the Government started treating defective pricing as an indication of criminal fraud Implemented in Regulations at FAR subpart
4 TINA Background and Overview (cont d) TINA is intended to protect the Government when a contractor s cost is a significant factor in negotiating contract price In the absence of some objective indication or price reasonableness e.g., competition the Government needs a mechanism to ensure it pays a fair and reasonable price TINA seeks to put the Government in same position as Contractors regarding access to contractor cost data so that Government can perform an effective, independent evaluation of the reasonableness of the contractor s price proposal However, TINA does not create an equal position between the Government and the contractor. There is no corresponding obligation on the part of Government to disclose anything to the contractor 4
5 TINA Background and Overview (cont d) Implemented in Regulations at FAR subpart 15.4 Describes the contracting officer s responsibility to purchase supplies and services at fair and reasonable prices Establishes requirements for the submission of cost or pricing data (whether or not certified ) Establishes the circumstances under which a contractor must certify the accuracy, completeness and currency of cost or pricing data If certified cost or pricing data is required, establishes: What the contracting officer must do with that data How to document the extent to which the contracting officer relied on the contractor s certified data to negotiate the contract price 5
6 TINA Background and Overview After all this time, considerable confusion remains: What is cost or pricing data? What must be done with it? (contractors and Government) When and under what circumstances can the Government request cost or pricing data and when must a contractor provide it? When and under what circumstances must contractors certify their cost or pricing data? Do contractors certify their proposal? What is the difference between certified cost or pricing data and other than certified cost or pricing data? What risks do contractors face when certification is required and when it isn t but data is nevertheless requested by the Government? 6
7 Exemptions from TINA Adequate Price Competition Prices Set by Law or Regulation Commercial Items Pricing Actions Less Than $700,000 Exceptional Cases - Waiver by Head of Contracting Activity Waivers are Generally Rarely Given 7
8 Applicability of TINA Negotiated prime contracts > $700,000 Prime contract modifications or changes > $700,000 Negotiated subcontracts > $700,000 at any tier, if prime contract and higher-tier subcontract(s) were required to provide certified cost or pricing data Subcontract modifications or changes > $700,000 at any tier, if the prime contractor and higher-tier subcontractor(s) were required to provide certified cost or pricing data 8
9 Applicability (cont d) A prime must obtain cost or pricing data for any covered subcontract greater than $700,000 A prime must submit (or cause submission of) the sub s data to the Government on a covered subcontract with a value that is either a) $12.5 million dollars or more, or b) $700,000 and more than 10% of the prime s proposed price Applies to contract modifications greater than $700,000 A series of unrelated changes issued as a single modification for administrative convenience will not be aggregated to determine threshold. However, related additive and deductive changes cannot be netted to escape the threshold The exercise of an option with previously-agreed pricing scheme is not a contract pricing action subject to TINA requirements 9
10 Applicability (cont d) FAR and Require disclosure and certification of current, accurate, and complete cost or pricing data to the contracting officer Grants government right to audit Specifies proposal format (FAR Table 15-2 Instructions for Submitting Cost/Price Proposals) General information Index and cross reference Identify cost or pricing data Identify forward pricing rates/factors Breakdown of cost elements e.g., material, labor Provide cost or price analysis of subcontractors 10
11 What is Cost or Pricing Data? All facts that, as of the date of price agreement, or, if applicable, an earlier date agreed upon by the parties that is as close as practicable to the date of price agreement, prudent buyers and sellers would reasonably expect to affect price negotiations significantly The concept of significant affect is not defined in the FAR and often is ignored by Government auditors; almost every dollar is considered significant no amount is too small to pursue But, the DCAA Audit manual states that TINA price adjustments of up to 5% of the contract value or $50,000, whichever is less, normally should be considered immaterial 11
12 Cost or Pricing Data (cont d) What are facts? Objective, verifiable information Cannot be determined based solely on the type of document. You must consider the nature of the information in the context of the particular negotiation in question. Each disclosure situation should be separately analyzed. Some things as a matter of common sense should be considered data. Other cases are much more difficult to assess Judgments and pure estimates are not cost or pricing data This has always been the law the statutes of implementing regulations have always so provided,and this was affirmed in 1986 amendments to TINA and in the Texas Instruments case 12
13 Cost or Pricing Data (cont d) Cost or pricing data includes more than just historical accounting data; they are all the facts reasonably relevant to evaluate estimates of future costs and to the validity of costs already incurred. This may include, but is not limited to: 1) Vendor quotes; 2) Nonrecurring costs; 3) Information on changes in production methods and in production or purchasing volume; 4) Data supporting projections of business prospects and objectives and related operations costs; 5) Unit-cost trends such yield rates and labor efficiency; 6) Make-or-buy decisions; 7) Estimated resources to attain business goals; and 8) Some information on significant management decisions 13
14 Cost or Pricing Data (cont d) Under some precedent, there may be a duty to disclose information that is a mix of fact and judgment, if judgment is necessary to understand the facts Contractors are not liable for the accuracy of any judgmental estimate included in a price proposal or disclosed in negotiations, but must disclose all underlying data relating to those judgments, even if such data was not actually used in preparing estimates Contractors must disclose all facts necessary for the Government to (a) evaluate contractors estimates, and (b) form its own estimates and judgments The fact that a management judgment has been made may be disclosable e.g., a decision to invest in new equipment, a decision on make vs. buy Your bottom line for negotiations is not cost or pricing data. Similarly, the fact that someone is given a particular negotiation objective is not cost or pricing data subject to disclosure 14
15 Cost or Pricing Data (cont d) Estimates can be cost or pricing data, especially if they essentially are verifiable, mathematical calculations rather than the result of applied judgment Judgmental forecasts of future business are not cost or pricing data The fact that you have other bids outstanding or in the process may be data Forward Pricing Rate Proposals If rates are agreed, a contractor can update via ACO, for significant changes. Technically, the PCO must use the agreed rates. If rates are not agreed, a contractor must update rates for each negotiation, via the PCO unless there is an agreement or clear course of conduct to update another way. Remember: even if rates are agreed, you must advise the ACO of any changes that might impact agreed rates. 15
16 What is Certified Cost or Pricing Data? Cost or pricing data that were required to be submitted in accordance with FAR and and are required to be certified, per FAR See also, 10 U.S.C. 2306a and 41 U.S.C. 254b Certification states that, to the best of the signatory s knowledge and belief, the cost or pricing data are accurate, complete, and current as of a date the date of agreement on contract price (or other agreed-upon date) The obligation to provide certified cost or pricing data creates potential defective pricing liability and increased risk of fraud and false claims allegations for non-compliance 16.
17 What Data other than Certified Cost or Pricing Data means Pricing data, cost data, and judgmental information necessary for the contracting officer to determine a fair and reasonable price or to determine cost realism Such data may include the identical types of data as certified cost or pricing data, but without the certification obligation The data may also include, for example, sales data and any information reasonably required to explain the offeror s estimating process, including, but not limited to 1) The judgmental factors and the mathematical or other methods used in the estimate, including those used in projecting from known data; and 2) The nature and amount of any contingencies included in the proposed price 17
18 When and why Data other than Certified Cost or Pricing Data" may be requested When certified cost or pricing data are not required, contracting officers shall obtain data other than certified cost or pricing data as necessary to establish a fair and reasonable price, generally using the following order of preference in determining the type of data required: i. No additional data from the offeror, if the price is based on adequate price competition ii. Data other than certified cost or pricing data such as A. Data related to prices e.g., established catalog or market prices, sales to non-governmental and governmental entities relying first on data available within the Government; second, on data obtained from sources other than the offeror; and, if necessary, on data obtained from the offeror B. Cost data to the extent necessary for the contracting officer to determine a fair and reasonable price 18
19 When and why Data other than Certified Cost or Pricing Data" may be requested (cont d) COs are required to obtain the type and quantity of data necessary to establish a fair and reasonable price, but not more data than is necessary Requesting unnecessary data can lead to increased proposal preparation costs, generally extend acquisition lead time, and consume additional contractor and Government resources If a fair and reasonable price cannot be established by the contracting officer from the analyses of the data obtained or submitted to date, the contracting officer shall require the submission of additional data to support the determination of a fair and reasonable price Such data may include the identical types of data as certified cost or pricing data, but without the certification. The data may also include 1) The judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data; and 2) The nature and amount of any contingencies included in the proposed price 19
20 Disclosure What is Meaningful Disclosure? Affirmative Disclosure Obligation Contractors have an affirmative obligation to root out and produce data; they cannot sit back and wait for the Government to ask the right question Disclosure should be to PCO or his authorized representative unless there s an acknowledged practice to the contrary e.g., disclosure to auditors or ACO Contractors may disclose by actual delivery of cost or pricing data or written disclosure with notice to the Government that the data is available for review Data cannot be buried/cannot just give access to files; must be useful However, contractors have no affirmative obligation to use its cost or pricing data to develop its proposed price(s) What does reasonably available mean? Almost everything, anywhere in your company is assumed to be reasonably available to and known by the contractor s negotiators There are exceptions, however, decided on a case-by-case basis. 20
21 Government Reliance When an offeror is required to disclose and certify its cost or pricing data, the Government is required to Perform a cost analysis of the offeror s individual cost elements (FAR (a)(3)) Review to determine whether any cost data or pricing data, necessary to make the offeror s proposal suitable for negotiation, have not been either submitted or identified in writing by the offeror. If there are such data, the contracting officer shall attempt to obtain and use them in the negotiations or make satisfactory allowance for the incomplete data (FAR (c)(2)(v)) Document in the PNM each major cost element where the determination of a fair and reasonable price was based on a cost analysis (FAR (a)(7)) Possession of a Certificate of Current Cost or Pricing Data is not a substitute for examining and analyzing the contractor s proposal (FAR (d)) 21
22 How to Challenge/Avoid Applicability Contracting officers are not to insist on contractor certified cost or pricing data where competition gives adequate assurances of price reasonableness Therefore Contractors should actively challenge demands by the Government or prime contractors for data/certification where price competition exists demand exemptions Get the exemption in writing. At least document your understanding that the exemption applies **Note: Ultimately the law gives contracting officers discretion to require cost or pricing data in any appropriate circumstance, even where there is indication of price competition. Contractors should emphasize the FAR policy statement that it is not in the Government s best interest to unnecessarily require submission of data 22
23 Compliance Best Practices Challenge/Avoid Applicability Contractors should aggressively pursue cut-off date agreements allowed by regulations. These are not often used, but a good solution for both sides Multiple Certifications (Pre-agreement, Post-agreement) No certifications in blank specify what data is being certified Prepare for Proposal submission, TINA sweeps and certificate submission Submit proposal IAW FAR Table 15-2 Knowledge/education of senior leadership impact of Certificate Clear roles for certificate signatory(s) Established Estimating System/process (See DFAR Business Rules) 23
24 Certificate of Current Cost or Pricing Data (FAR ) This is to certify that, to the best of my knowledge and belief, the cost or pricing data (as defined in Section of the Federal Acquisition Regulation (FAR) and required under FAR subsection ) submitted, either actually or by specific identification in writing, to the Contracting officer or to the Contracting Officer s representative in support of * are accurate, complete, and current as of **. This certification includes the cost or pricing data supporting any advance agreements and forward pricing rate agreements between the offeror and the Government that are part of the proposal. Firm Signature Name Title Date of execution** *Identify the proposal, request for price adjustment, or other submission involved, giving the appropriate identify number (e.g. RFP No.). **Insert the day, month, and year when price negotiations were concluded and price agreement was reached, or, if applicable, an earlier date agreed upon between the parties that is as close as practicable to the date of agreement on price. 24
25 Defective Pricing Liability Government gets price reduction for relying, to its detriment, on defective cost or pricing data. Under current regulations, the Government also may 1) Collect interest from the date of overpayment, and 2) Assess penalties for knowing submission of defective data Liability is statutory. A prime contractor may be liable regardless of whether data was submitted or a certificate was signed. While the law applies to subcontractors, there is no direct liability from subcontractors to the Government The Government may audit subcontractors and assess price reductions but against primes A prime contractor s ability to pass price reductions on to subcontractors depends on whether there are effective flowdowns and indemnities in the subcontract 25
26 Possible Defenses Show TINA does not apply Show that the data at issue is not factual Show there was disclosure of facts. Show that the Government actually knew the facts, even if you didn t disclose (asserting a government should have known is not a defense) Show that there was no reliance on the defective data Show there would have been no impact on price if data were disclosed Challenge DCAA s use of data in calculating recommended reductions Challenge DCAA sampling techniques Double-check DCAA s math and assumptions for consistency with your own or those established in negotiations Insist on use of negotiated rates, overheads and profits to calculate refunds, rather than proposal rates. This is consistent with the DCAA Audit Manual. 26
27 Possible Defenses (cont d) Establish Offsets No affirmative recovery; just offsets Do your own reverse audits; look for undisclosed, higher data Can only offset for defective facts; not mistaken judgments. Data must have been reasonably available at handshake date No offsets for intentional decisions not to use/disclosure higher priced data No offsets for bottom-line reductions May have offsets for negotiation reductions that are attributed e.g., to labor, material, overhead rates May offset cross category e.g., offset material costs with labor costs No cross-contract offsets; but possible arguments regarding multiple orders handled via single bottom line negotiation. 27
28 Questions, Comments & Banter Brent Calhoon, CPA Partner Jamie Sybert Director Baker Tilly Government Contractor Advisory Services 28
TOPIC 12 CONTRACT COST AND PRICE ANALYSIS
CONTRACT AUDIT GUIDE FRAMEWORK TOPIC 12 CONTRACT COST AND PRICE ANALYSIS Objective To determine whether the agency effectively conducts cost or price analysis to arrive at fair and reasonable prices for
DEFECTIVE PRICING: A VERY SHORT COURSE
Jenner & Block LLP 1099 New York Avenue, NW Suite 900 Washington, DC 20001 Tel 202-639-6000 www.jenner.com Chicago Los Angeles New York Washington, DC DEFECTIVE PRICING: A VERY SHORT COURSE W. Jay DeVecchio
General Terms and Conditions of Purchase
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the materials or products furnished are for use in connection with a U.S.
FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required
FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required This document provides instructions for preparing a contract pricing proposal when cost
COMMUNICATIONS & POWER INDUSTRIES ( CPI ) TERMS AND CONDITIONS OF PURCHASE
COMMUNICATIONS & POWER INDUSTRIES ( CPI ) TERMS AND CONDITIONS OF PURCHASE Supplement 1 U.S. Government Contract Provisions from the Federal Acquisition Regulation (FAR) 1. When the materials or products
Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the products or services furnished are for use in connection with a U.S.
ATTACHMENT A SUPPLIER CERTIFICATIONS PACKAGE
Page 1of 12 SUPPLIER RFQ# P/N# ATTACHMENT A SUPPLIER CERTIFICATIONS PACKAGE FORM $25,000 $100,000 $650,000 1. Cost Accounting Standards and Notices X 2. Certification Regarding Responsibility Matters X
Cost Analysis Key Components Guidance and Checklist
Cost Analysis Key Components Guidance and Checklist A Mandatory Reference for ADS Chapter 300 New Edition Date: 04/02/2013 Responsible Office: M File Name: 300mad_040213 COST ANALYSIS KEY COMPONENTS GUIDANCE
AF Life Cycle Management Center
AF Life Cycle Management Center Subcontract Pricing Shannon Prince AFLCMC/PZF Wright-Patterson AFB 24 March 2014 Overview Intro to Subcontracts Pertinent Thresholds PCO & Prime Responsibilities Prime Analysis
Government Contractor Business Systems and Overview of System Assessments
Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective
UNIT 34: COST ACCOUNTING STANDARDS
UNIT CERTIFICATION Statement of Completion has satisfactorily completed training in the duty of this Unit under the conditions described below and in accordance with the overall standard(s) for this Unit.
Page 1 of 7. Corporate Form CC009 Rev 13, Dated 31 Jan 2015
1. When the materials or products furnished are for use in connection with a U.S. Government contract or subcontract, in addition to the L-3 General Terms and Conditions (Corp Form CC008), the following
REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER REMEDIATION LLC
SRR-PPS-2009-00012 REV. 0 REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER REMEDIATION LLC SECTION A, APPLICABLE TO ALL OFFERS...2 1. Certification and Agreement...2 2. Authorized Negotiators...2 3. Type
How to Survive a DCAA Audit
How to Survive a DCAA Audit www.paulgunn.com 1 How to Survive a DCAA Audit - Overview Areas of interest and expectations of a typical audit: 1. Introduction o 2. The DCAA and Types of audits 3. Preparing
Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT
Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT If the Order involves funds from a Federal government contract or funds from a
Monitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Subcontracts What should a contractor know about subcontracting:
TC-UPDATE (11/10) 52.222-39 252.204-7009. 12. Requirements Regarding Potential Access to Export-Controlled Items
TC-UPDATE (11/10) The following updates reflect changes to various provisions and clauses of U.S. Government acquisition regulations, including the Federal Acquisition Regulations (FAR) and the Department
Chapter 12 Contract Pricing
Chapter 12 Contract Pricing 2014 Contract Attorneys Deskbook THIS PAGE INTENTIONALLY LEFT BLANK CHAPTER 12 CONTRACT PRICING I. INTRODUCTION...1 A. Objectives...1 B. References...1 II. DEFINITIONS...2 A.
CHAPTER 8. Table of Contents
July 29, 2015 8(1) Paragraph CHAPTER 8 Table of Contents 8-000 Cost Accounting Standards Page 8-001 Scope of Chapter... 801 8-100 Section 1 --- Overview - Cost Accounting Standards Board (CASB) Rules and
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM
Presenting the Numbers: Accounting Systems for Government Contractors
Presenting the Numbers: Accounting Systems for Government Contractors William D. Craven, CPA Senior Cost/Price Analyst CH2M HILL Plateau Remediation Company William D. Craven, CPA, CMA, CIA Cost/Price
Contractor Purchasing System Review (CPSR)
Contractor Purchasing System Review (CPSR) Presentation References FAR 44.3 and DFARS 244.3 -- Contractors Purchasing Systems Reviews Consent to Subcontract FAR 44.2 2 What is a CPSR Contractor purchasing
2014 Technical Data Rights Forum
2014 Technical Data Rights Forum Technical Data Rights Challenges from the Small Business Perspective Moderator: Holly Emrick Svetz, Womble Carlyle Alison Brown, NAVSYS Corporation Devon Elizabeth Hewitt,
DCAA Audit R 4 Rights to Records, Requirements & Remedies
San Diego Chapters Present DCAA Audit R 4 Rights to Records, Requirements & Remedies A Seminar with Panel Discussion and Audience Participation February 18, 2009 This Morning s Agenda 8:30 Introduction
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients Who is this guide for? This guide is for all HUD grantees and funding recipients that contract for services and/or supplies
DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence
DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of
CERTIFICATION OF COMPLIANCE WITH SMALL, DISADVANTAGED, MINORITY, WOMEN-OWNED, AND HISTORICALLY UNDERUTILIZED BUSINESS POLICY
EXHIBIT 1 TO ATTACHMENT CERTIFICATION OF COMPLIANCE WITH SMALL, DISADVANTAGED, MINORITY, WOMEN-OWNED, AND HISTORICALLY UNDERUTILIZED BUSINESS POLICY The undersigned certifies on behalf of the Contractor
The Cost Accounting Standards and Consequences of Noncompliance
The Cost Accounting Standards and Consequences of Noncompliance Breakout Session E05 Greg Bingham, Vice President, The Kenrich Group LLC Mike LaCorte, Principal, The Kenrich Group LLC Tuesday, December
Construction Industry Workers Compensation Coverage Act. Approved by the NCOIL Executive Committee on November 22, 2009.
Construction Industry Workers Compensation Coverage Act Approved by the NCOIL Executive Committee on November 22, 2009. Table of Contents Page Numbers Section 1. Summary (1) Section 2. Definitions (1)
How to Develop a FAR-Compliant Cost or Price Proposal
How to Develop a FAR-Compliant Cost or Price Proposal May 21, 2014 Presenter: Paul H. Calabrese Rubino & Company, CPAs & Consultants Senior Manager Tel: 301-214-4137 [email protected] www.linkedin.com/in/pcalabrese
Bell Standard Purchase Order Terms and Conditions - FAR/DFARS Clause Flow-Downs in Fulfillment of a U.S. Government Contract
Section I FEDERAL ACQUISITION REGULATION (A) Seller agrees to negotiate with Buyer to incorporate additional provisions herein or to change provisions as Buyer reasonably deems necessary to comply with
Flexible Circuits Inc. Purchase Order Standard Terms and Conditions
Flexible Circuits Inc. Purchase Order Standard Terms and Conditions 1. Acceptance- This writing, together with any attachments incorporated herein, constitutes the final, complete, and exclusive contract
Attachment 32c THE FOLLOWING PROVISIONS APPLY: Applies to orders of any amount
Attachment 32c FEDERAL PROVISIONS APPLICABLE WHEN SUBCONTRACTOR (COMMERCIAL ENTITY) IS IN POSSESSION OF GOVERNMENT PROPERTY GOVERNMENT SUBCONTRACT PROVISIONS INCORPORATED IN ALL SUBCONTRACTS/PURCHASE ORDERS
Government Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
NCMA MEETING PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011
NCMA MEETING 1 PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011 Denise M. Hunt DCAA LM Mt. Laurel Resident Office Forward Pricing Technical Specialist DCAA OVERVIEW AND PRICE PROPOSAL AUDIT PROCESS
Introduction and DCAA Overview
Introduction and DCAA Overview Industry Engagement Session 10/29/2015 The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations DCAA 1965-2015:
Lawrence Livermore National Laboratory
Lawrence Livermore National Laboratory Supply Chain Management Department Attention: To All Offerors June 16, 2016 Subject: Request for Proposal (RFP) Number B617524 Lawrence Livermore National Security,
COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATIONS
COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATIONS Usage: For Cost Accounting Standards Covered Subcontracts Certain representations and certifications must be made by the Offeror and must be submitted
Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers
Curtis Matthews, Managing Partner Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers Findley Gillespie, Senior Manager May 18, 2011 1 The material appearing in this presentation
Arkansas Workers Compensation Commission Arkansas Insurance Department Arkansas Contractors Licensing Board
Arkansas Workers Compensation Commission Arkansas Insurance Department Arkansas Contractors Licensing Board JOINT BULLETIN To: Interested Parties Date: August 20, 2007 From: Subject: Arkansas Workers Compensation
Review of Consultant/Professional Services Cost Accounts
Review of Consultant/Professional Services Cost Accounts 1 Table of Contents Risk Assessment Research and Planning Entrance Conference Preliminary Analytical Procedures Results from Preliminary Analytical
Business Associate Agreement
This Business Associate Agreement Is Related To and a Part of the Following Underlying Agreement: Effective Date of Underlying Agreement: Vendor: Business Associate Agreement This Business Associate Agreement
Certificate of Accounting, Billing and Property System Adequacy
Certificate of Accounting, Billing and Property System Adequacy This certifies that, to the best of my knowledge and belief, Contractor s Accounting, Billing and/or Property System and related internal
SCHEDULES OF CHAPTER 40B MAXIMUM ALLOWABLE PROFIT FROM SALES AND TOTAL CHAPTER 40B COSTS EXAMINATION PROGRAM
7/30/07 SCHEDULES OF CHAPTER 40B MAXIMUM ALLOWABLE PROFIT FROM SALES AND TOTAL CHAPTER 40B COSTS Instructions: EXAMINATION PROGRAM This Model Program lists the major procedures and steps that should be
WorkLink Workforce Investment Board (effective July 1, 2015 WorkLink Workforce Development Board)
WorkLink Workforce Investment Board (effective July 1, 2015 WorkLink Workforce Development Board) Workforce Innovation & Opportunity Act Website Maintenance, Updates, & SEO Hosting Request for Quotes (RFQ)
Terms and Conditions for Tax Services
Terms and Conditions for Tax Services In the course of delivering services relating to tax return preparation, tax advisory, and assistance in tax controversy matters, Brady, Martz & Associates, P.C. (we
Risk Mitigation and Subcontract Management
Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm
February 3, 2016 12(1) CHAPTER 12
February 3, 2016 12(1) CHAPTER 12 Table of Contents Paragraph Page 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment Proposals or Claims 12-001 Contract Terminations and
Letters for Underwriters and Certain Other Requesting Parties
Letters for Underwriters 2341 AU Section 634 Letters for Underwriters and Certain Other Requesting Parties (Supersedes SAS No. 49.) Source: SAS No. 72; SAS No. 76; SAS No. 86. See section 9634 for interpretations
Policy Number: 3-803 Policy Name: Bidding and Source Selection Procedures
Page 1 3-803 Bidding and Source Selection Procedures A. Definitions In ABOR Policies 3-803 (Bidding and Source Selection Procedures) and 3-804 (Professional Services and Construction Services Procurement):
CERTIFICATION OF COMPLIANCE WITH SMALL, DISADVANTAGED, MINORITY, WOMEN OWNED, AND HISTORICALLY UNDERUTILIZED BUSINESS POLICY
Exhibit 1 CERTIFICATION OF COMPLIANCE WITH SMALL, DISADVANTAGED, MINORITY, WOMEN OWNED, AND HISTORICALLY UNDERUTILIZED BUSINESS POLICY The undersigned certifies on behalf of the Contractor or Subcontractor
REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER NUCLEAR SOLUTIONS, LLC
REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER NUCLEAR SOLUTIONS, LLC SECTION A, APPLICABLE TO ALL OFFERS... 2 1. Certification and Agreement... 2 2. Authorized Negotiators... 2 3. Type of Business
Procurement Standards 2 CFR 200.317-326
2 CFR 200 Uniform Guidance Procurement Standards Kris Rhodes, Director Sponsored Project Services 1 Procurement Standards 2 CFR 200.317-326 200.317 Procurement by states 200.318 General procurement standards
Contractor Purchasing System Review (CPSR) Guidebook
DEPARTMENT OF DEFENSE (DOD) Contractor Purchasing System Review (CPSR) Guidebook November 02, 2015 DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) This revision supersedes all previous versions. Table of Contents
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
Ch 1 - Conduct Market Research for Price Analysis
Ch 1 - Conduct Market Research for Price Analysis 1.0 - Chapter Introduction 1.1 - Reviewing The Purchase Request And Related Market Research o 1.1.1 - How Was The Estimate Made? o 1.1.2 - What Assumptions
Assignment of Claims. FUPWG Spring 2015 Kay Sommerkamp, Corps of Engineers & Scott Foster, Bostonia. US Army Corps of Engineers BUILDING STRONG
Assignment of Claims FUPWG Spring 2015 Kay Sommerkamp, Corps of Engineers & Scott Foster, Bostonia US Army Corps of Engineers BUILDING STRONG 1 Assignment of Claims Act 31 U.S.C. 3727(b) An assignment
DCAA Audits of Compliance Systems and the Implications of Changes in the False Claims Act for Universities
DCAA Audits of Compliance Systems and the Implications of Changes in the False Claims Act for Universities SCCE s Higher Education Compliance Conference Kwamina Thomas Williford Partner, Holland & Knight
RFQ No. 4856B-0-2016/MD. REQUEST FOR QUOTATION City of Norfolk. Vendor: Issued: 11/06/2015 Due: 11/11/2015@ 2:00 PM
REQUEST FOR QUOTATION City of Norfolk (Please include your company name and address below) Vendor: Issued: 11/06/2015 Due: 11/11/2015@ 2:00 PM Mail or fax reply to: Office of the Purchasing Agent Attn:
Request for Proposal RFP #201501. Printing & Mailing Services
Request for Proposal Printing & Mailing Services Date of Issue: 03/24/2015 For period beginning: 05/01/2015 Due Date/Time for Receipt of Proposals: 04/06/2015 @ 2:00 p.m. (EDT) RFP Number: 201501 Date
10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest
Requirements Procurement under the New Requirements 1 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
Acquiring a Federal Government Contractor: Avoiding Pitfalls
Acquiring a Federal Government Contractor: Avoiding Pitfalls Erin L. Toomey, Foley & Lardner LLP, with Practical Law Commercial This Practice Note highlights common pitfalls to avoid in an acquisition
AUSTIN COMMUNITY COLLEGE DISTRICT (ACC) SMALL BUSINESS DEVELOPMENT PROGRAM SBDP FORM A - SLBE PARTICIPATION COMMITMENT. Name of Offeror/Proposer:
AUSTIN COMMUNITY COLLEGE DISTRICT (ACC) SMALL BUSINESS DEVELOPMENT PROGRAM SBDP FORM A - SLBE PARTICIPATION COMMITMENT Name of Offeror/Proposer: Address: Contracting Agency/Owner: Contract (Project) Title
Are You Looking to Sell Your Products & Services to the US Government? Overview
Are You Looking to Sell Your Products & Services to the US Government? What You Need to Know About Accounting, Compliance, and Reporting! 1 FICPA Overview The US Government is the largest consumer of goods
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
Standard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out
Federal Acquisition Regulation Subcontract Flowdown Provisions
Federal Acquisition Regulation Subcontract Flowdown Provisions Clause Title Title Applicability 52.203-6, Alt 1 Restrictions on Subcontractor Sales to the (if subcontract over $150,000) Government (SEP
Carmel Unified School District. Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School
Carmel Unified School District Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School January 4, 2016 1 NOTICE REGARDING PREQUALIFICATION FOR BLEACHER AND PRESSBOX
The Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
Multifamily Cost Estimator Contractor
INFORMAL SOLICITATION Minnesota Housing Finance Agency Multifamily Cost Estimator Contractor Description of Project Minnesota Housing Finance Agency (Minnesota Housing), a mortgagee authorized to submit
AHCA MEMBER GUIDANCE IMPLEMENTING THE FALSE CLAIMS ACT EDUCATIONAL PROVISIONS OF THE DEFICIT REDUCTION ACT
AHCA MEMBER GUIDANCE IMPLEMENTING THE FALSE CLAIMS ACT EDUCATIONAL PROVISIONS OF THE DEFICIT REDUCTION ACT THE TOPIC: Section 6033 of the Deficit Reduction Act of 2005 ( DRA ) requires entities that make
INSURANCE REQUIREMENTS FOR FEDERAL CONTRACTORS
INSURANCE REQUIREMENTS FOR FEDERAL CONTRACTORS This document is provided to supply you with information regarding insurance requirements on Government contracts. Please be advised that the samples are
HOURLY CONSULTING AGREEMENT
4245 Kemp Blvd., Suite 1007 Wichita Falls, Texas 76308 HOURLY CONSULTING AGREEMENT This is an agreement between Personal Money Planning ( Advisor ), and ( Client ). By this agreement, Client retains Advisor
CAS. Combined Air Support Cost Accounting Standards. Cost Impact Statements
CAS Combined Air Support Cost Accounting Standards Cost Impact Statements Cost Impact Statements Presenter: Anthony J. Nicolella References 48 CFR 9903 CON 252 Fundamentals of CAS FAR Parts 30, 31 and
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63)
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Pat Fitzgerald Director Defense Contract Audit Agency The views expressed in this presentation
STATE OF NEW JERSEY. SENATE, No. 1988. 213th LEGISLATURE. Sponsored by: Senator JEFF VAN DREW District 1 (Cape May, Atlantic and Cumberland)
SENATE, No. STATE OF NEW JERSEY th LEGISLATURE INTRODUCED JUNE, 00 Sponsored by: Senator JEFF VAN DREW District (Cape May, Atlantic and Cumberland) SYNOPSIS "New Jersey Fair Debt Collection Practices Act."
Broward County False Claims Ordinance. (a) This article shall be known and may be cited as the Broward County False Claims Ordinance.
Broward County False Claims Ordinance Sec. 1-276. - Short title; purpose. (a) This article shall be known and may be cited as the Broward County False Claims Ordinance. (b) The purpose of the Broward County
Business Opportunities: A Guide to Winning Federal Contracts
Business Opportunities: A Guide to Winning Federal Contracts Text File Slide 1 Business Opportunities: A Guide to Winning Federal Contracts Welcome to SBA s online training course, Business Opportunities:
SECTION I (Applies to all offers)
REPRESENTATIONS & CERTIFICATIONS FOR GOVERNMENT ORDERS (Form 119-48 Rev. 8/15) Procurement of material, services and supplies for a United States Government contract requires that prime contractors, subcontractors
... 10 ... 2 ... 4 ... 8 ... 9 ... 11
... 1... 2... 4... 8... 9... 10... 11... 11 SHA Solicitation No. 811326 Page 1 of 14 SHA Solicitation No. 811326 Page 2 of 14 SHA Solicitation No. 811326 Page 3 of 14 SHA Solicitation No. 811326 Page 4
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran
CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS
7-1 CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS The "Public Purchasing Law" applies to every expenditure of public funds by a governmental body, unless specifically
REQUEST FOR PROPOSALS FOR Franchise Fees, Sales and Use Tax Audits
REQUEST FOR PROPOSALS FOR Franchise Fees, Sales and Use Tax Audits The City of Louisville, Colorado is accepting proposals for the purpose of performing sales and use tax, and franchise fee compliance
January 2004 5(1) CHAPTER 5. Table of Contents
January 2004 5(1) Paragraph CHAPTER 5 Table of Contents 5-000 Audit of Policies, Procedures, and Internal Controls Relative to Accounting and Management Systems Page 5-001 Scope of Chapter... 501 5-100
DCAA Contract Audits: Current Trends and Issues
DCAA Contract Audits: Current Trends and Issues Presented to: NCMA Huntsille, AL Chapter August 25, 2011 Darryl L. Walker, CPA Technical Director Beason & Nalley, Inc. Copyright 2011 Beason & Nalley, Inc.
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA
AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA To amend the District of Columbia Procurement Practices Act of 1985 to make the District s false claims act consistent with federal law and thereby qualify
Joint Venture Summary By John Ford and David Lundsten (Cherry,Bekaert and Holland)
Joint Venture Summary By John Ford and David Lundsten (Cherry,Bekaert and Holland) How joint ventures are defined and treated by the FAR, SBA, and DCAA for their purposes, as well as an in-depth discussion
Terms and Conditions of Purchase TC-03 (Government Contract Flowdown Provisions Fixed Price Procurement)
Applicable to all Purchase Orders Supporting a US Government Contract/Subcontract: The following clauses from the Federal Acquisition Regulations (FAR), the Department of Defense (DOD) FAR Supplement (DFARS),