Reducing waste through efficient procurement can help reduce the costs of civil engineering and infrastructure projects; this guidance provides
|
|
|
- Hector Bates
- 10 years ago
- Views:
Transcription
1 Implementation guidance for civil engineering and infrastructure projects Civil engineering projects: Waste less and save money Reducing waste through efficient procurement can help reduce the costs of civil engineering and infrastructure projects; this guidance provides practical advice to individuals on the actions to take and the changes that can be achieved.
2 Our vision is a world without waste, where resources are used sustainably. We work with businesses and individuals to help them reap the benefits of reducing waste, develop sustainable products and use resources in an efficient way. Find out more at Contents 1.0 Introduction Executives and senior managers Corporate environment specialists Procurement teams Design managers Design managers checklist of design options Construction project managers Operations managers 20
3 01 Civil engineering projects: Waste less and save money 1.0 Introduction This guide will help managers and specialists in client organisations to ensure that materialefficient practices are adopted by their infrastructure projects. These practices help clients to lower the costs of construction and maintenance projects whilst reducing the amount of waste sent to landfill. Client organisations include local authorities, government agencies and private companies that are delivering services in the highway, railway, flood defence, water, gas, electricity, airport, ports and other infrastructure sectors. Figure 1 summarises the influence that individuals within these organisations can have in driving good practice, measuring performance and securing cost savings, with more detail provided in subsequent guidance. Figure 1: Role of specialists and managers in client organisations in ensuring their supply chain cuts waste on projects Executives and senior managers Corporate environment specialists Procurement teams Design managers Construction project managers Operations managers Policy Set policy and sign Waste to Landfill Commitment Amend standard documentation to reflect policy Review existing contracts to benchmark performance or to embed targets/metrics Preparation and design Set requirements in design team appointments Use Designing out Waste principles Produce outline SWMP Assess design team performance Identify local solutions Draft material logistics plan Pre-construction & construction Set construction tender/contract requirements Update and maintain SWMP Assess contractor performance Set maintenance waste management strategy Handover, postcompletion & use Set maintenance and/or waste management tenders/contract requirements Monitor performance SWMP: Site Waste Management Plan
4 02 Civil engineering projects: Waste less and save money 2.0 Executives and senior managers Figure 2 Executives and senior managers Policy Set policy and sign Waste to Landfill Commitment Standard practice It is common for organisations that own or manage civil engineering infrastructure to have an environmental management policy/system or sustainable development policy, or a corporate social responsibility (CSR) policy which addresses environmental issues. Many organisations have accredited environmental management systems and set procurement requirements for sub-consultants and contractors to have similar systems in place. Environmental management procedures may mention waste, although the focus is commonly office waste and not waste generated by construction works. Good practice Key action: Add performance requirements for waste reduction, reuse and recovery existing policies. Incorporating materials efficiency into policy documents will maximise the likelihood that performance improvements will be delivered. A policy describes the organisation s commitment to minimising the use of materials, reducing waste, and reusing and recovering materials. The policy must be clear, concise and should be fully endorsed by company executives or senior management. The policy provides a mandate for future procurement actions and a clear commitment to measure and improve performance. In particular, including the intention to cut waste and the costs of waste in corporate procurement policy (as well as the environmental management, sustainable development or CSR policy) provides a means for securing action by project teams. The policy should include a clear signal of intent to supply chain partners, and also define the standard requirements that will be used in tender and contract documents (including metrics and target outcomes for waste reduction, reuse and recovery). Model wording can be found in Client and Principal Contractor Actions 1B and 1C, at
5 03 Civil engineering projects: Waste less and save money Best practice Key action: Sign up to the Waste to Landfill Commitment. The sector-wide voluntary agreement Construction Commitments: Halving Waste to Landfill is a commitment to robust implementation: We commit to playing our part in halving the amount of construction, demolition and excavation waste going to landfill by We will work to adopt and implement standards for good practice in reducing waste, recycling more, and increasing the use of recycled and recovered materials. We will: set a target for reducing waste to landfill; embed the target within corporate policy and processes; set corresponding requirements in project procurement and engage with our supply chain; measure performance at a project level relative to a corporate baseline; and report annually on overall corporate performance. It publicly demonstrates your organisation s support for the sector goal of halving the amount of construction, demolition and excavation waste being sent to landfill by 2012 (compared to 2008). This goal supports targets adopted by the Strategy for Sustainable Construction in England and the zero waste ambitions of governments in Scotland and Wales. It is a voluntary agreement in which each organisation sets its own corporate target for improvement. By signing up, you can formalise a more robust approach to managing and measuring performance and thereby drive cost and efficiency savings. For more information on the Commitment, who has signed up and the actions involved, visit and
6 04 Civil engineering projects: Waste less and save money 3.0 Corporate environment specialists Figure 3 Corporate environment specialists Policy Set policy and sign Waste to Landfill Commitment Amend standard documentation to reflect policy Standard practice Within organisations that own or manage civil engineering infrastructure, it is usually a corporate function to operate environmental management policies and systems. Such organisations will often have a director or senior manager that reports to the Board on environment issues, with support staff allocated depending on the size of the organisation. These corporate environment specialists will implement and disseminate changes in legislation and/or good practice, and ensure that the organisation responds by changing policies and practices for example providing training when major changes have occurred. They typically collect and report environmental data, prepare outward-facing environment reports, and liaise with auditors that accredit the management systems. Good practice Key action: Add performance requirements and targets for waste reduction, reuse and recovery to existing policies, procedures and related documentation. Section 2.0 Executives and senior managers explains why and how waste should be included in corporate policies, and signposts model policy wording. In order to deliver a waste reduction, reuse and recovery policy, it is likely that procedures, work instructions, standard procurement questionnaires and other documentation will need to be amended. The corporate environment function should revise the environmental management system accordingly, and support procurement teams in changing standard documentation. Changes to procurement documentation are discussed in more detail in Section 4.0 Procurement teams. Experience suggests that corporate procedures should make explicit reference to reducing construction, demolition and excavation waste through design and construction processes, and reporting on outcomes. Only by including these explicit instructions in internal documentation will the organisation collect the data it needs to assess its performance, make improvements, and quantify and realise cost savings. A model set of project-level requirements for waste reduction, reuse and recovery can be found in Client and Principal Contractor Action 1C, at
7 05 Civil engineering projects: Waste less and save money These requirements can be adapted for use in corporate documentation to ensure that targets for waste reduction, reuse and recovery are set on construction and maintenance projects (for example, as part of the Invitation to Tender). For organisations that have signed the Waste to Landfill Commitment (see 2.0 Executives and senior managers), reference to the WRAP Waste to Landfill Reporting Portal should be included ( Example requirements for corporate documentation are: For all projects/contracts over 300k, design, construction and maintenance teams will be required to: implement Site Waste Management Plans throughout the design and construction period that comply with regulatory requirements (where applicable) and include in such Plans project-specific targets for waste recovery and reused and recycled content (see below) and for waste reduction; measure and report progress against the corporate KPIs for the quantity of waste produced and the quantity of waste sent to landfill (measured in tonnes per 100k construction value) using the WRAP Waste to Landfill Reporting Portal and guidance ( where construction value is the price in the accepted tender or, if there is no tender, the cost of labour, plant and materials, overheads and profit; recover at least [70% state value] of construction materials, and aim to exceed [80% state value]; recover at least [80% state value] of demolition, strip-out and excavation materials (where applicable), and aim to exceed [90% state value]; and ensure that at least [15% state value] of total material value derives from reused and recycled content in new construction, select the top opportunities to exceed this figure without increasing the cost of materials, and report actual performance. Project teams shall forecast waste quantities and reused and recycled content and set targets for waste reduction from an early design stage (for instance by using WRAP s Outline Designing out Waste Tools and Net Waste Tool, freely accessible at Before starting on site, the project team shall submit a copy of the Site Waste Management Plan, identifying the actions to be taken to reduce waste, increase the level of recovery and increase reused and recycled content, and quantifying the resulting changes. On completion of the Works, the project team shall submit a copy of the completed Site Waste Management Plan, reporting the forecast and actual performance for waste quantities, disposal routes, and reused and recycled content used in construction. The procurement team will ensure that all relevant tender and contract documentation includes these requirements. It will be the responsibility of project/contract managers to ensure that targets are set which are appropriate to the project, and performance is recorded and reported. Project/contract managers will be required to report back on project performance to the environment team, and quarterly reports will be prepared for the Board. The performance levels quoted above are widely applicable to all construction project types, including infrastructure, but may be adjusted to suit an organisation s portfolio of construction and maintenance works, for example based on evidence of performance to date.
8 06 Civil engineering projects: Waste less and save money Best practice Key action: Sign up to the Waste to Landfill Commitment, set a corporate target, and report annually on performance. Section 2.0 Executives and senior managers provides information on signing up to the Waste to Landfill Commitment. Organisations signing the Waste to Landfill Commitment agree to: set a target for reducing waste to landfill; embed the target within corporate policy and processes; set corresponding requirements in project procurement and engage with our supply chain; measure performance at a project level relative to a corporate baseline; and report annually on overall corporate performance. It will usually be the corporate environment specialists that need to set the corporate target embed corresponding requirements in processes (working with procurement, design, construction and operations teams as appropriate) and then collate data for annual reports. Information and ideas on how to set a target are given in the model action plan for clients at This is supported by benchmarks for target setting at Annual reporting can be completed using WRAP s Waste to Landfill Reporting Portal, which allows you to set and record your baseline and target for corporate performance, and then record annual outcomes for the KPI of waste to landfill (measured in tonnes per 100k of construction spend). Project managers can also register and access the Portal; so project waste totals can be directly uploaded for the environment team to collate and review as required. For more information on the Reporting Portal, go to
9 07 Civil engineering projects: Waste less and save money 4.0 Procurement teams Figure 4 Procurement teams Policy Preparation and design Pre-construction & construction Handover, postcompletion & use Amend standard documentation to reflect policy Review existing contracts to benchmark performance or to embed targets/metrics Set requirements in design team appointments Set construction tender/contact requirements Set maintenance and/or waste management tenders/contract requirements Standard practice Procurement is the key mechanism to ensure that services meet value, cost and technical demands. Procurement can also provide assurance that consultants and contractors understand the objectives of their client organisation and equip themselves to deliver. Many organisations have recognised the power of procurement; for example, organisations in London signing up to the Mayor of London s Green Procurement Code ( However, in many instances, the actions taken may not extend to systematic requirements for waste reduction, reuse and recovery within tenders and contracts; in which case the potential for cost saving may not be maximised (for example, if the design team is not asked to quantify and prioritise the opportunities) and the client is unlikely to share in those savings. Good practice Key action: Add performance requirements and targets for waste reduction, reuse and recovery to standard procurement documentation; include requirements in new tenders and contracts. WRAP has produced procurement guidance to help organisations that own and/or manage civil engineering infrastructure when setting requirements for waste reduction, reuse and recovery in design, construction and maintenance contracts. This guidance includes model wording for pre-qualification questions, invitation to tender clauses and contractual obligations. This information can be accessed at Procurement of design, construction and maintenance services should draw in the experience of design managers, construction managers and operations managers as appropriate. For example, it can be useful to include all of these stakeholders in design team procurement since design issues will influence construction and operation. Construction contractor procurement may also cover design and should include the design team manager, but might also include the operations manager to ensure that maintenance issues are adequately understood and addressed.
10 08 Civil engineering projects: Waste less and save money A pre-qualification questionnaire (PQQ) enables an organisation to rapidly assess the capability of bidders to deliver against specified performance requirements, whether through design services, construction execution, maintenance contracts, or material supply. The PQQ can be supplemented by more detailed discussion at subsequent interviews, or can be used as an initial filter to rapidly eliminate unsuitable organisations. A PQQ should assess the consultants and/or contractors ability to reduce waste (for example, by design improvements), to manage waste efficiently (such as segregation on site) and to maximise waste reuse and recovery (for example, by using recycled materials or reusing in-situ materials). Requirements for data collection and reporting should be embedded in the invitation to tender and in the contract, so that the organisation s design, construction and operations managers are readily able to report internally and externally. Performance targets (for example, for % recovery of materials or recycled content by value) should be specified in tender invitations for design and construction services and in the project briefs issued to partner or framework organisations, so that only companies able to address these expectations will be contracted to deliver the work. Although the core actions for procurement teams will include setting requirements in appointments for design teams and contractors, it is possible that other procurement processes will require amendments. For example, the role of site investigations and potential changes to reporting requirements are discussed in 5.0 Design managers. Best practice Key action: Review existing contracts to introduce waste reduction, reuse and recovery performance targets and reporting requirements. It is always easier to implement changes in practice through new contracts, but where relationships with existing contractors are very good, and where there is a long time yet to run on a contract, it is worth discussing win-win changes. These can include more robust measurement and reporting to help the client organisation and supply chain partners to demonstrate progress against their Waste to Landfill Commitments, and quantifying and sharing the savings from waste reduction, reuse and recovery. It is possible that design, construction and operations managers have already identified key projects where waste and cost savings would be worth targeting. They may also be able to quickly identify projects where contractual changes should be possible; for example, on a maintenance contract that has recently been let and the maintenance contractor is still establishing working practices, or in framework contracts with design consultancies where good working relationships exist. Close liaison with the design, construction and operations managers will be needed to implement these contract amendments, which will help them to meet their internal reporting requirements. Amendments to existing contracts can draw on the same clauses used for new contracts, accessible at
11 09 Civil engineering projects: Waste less and save money 5.0 Design managers Figure 5 Design managers Review existing contracts to benchmark performance or to embed targets/metrics Preparation and design Set requirements in design team appointments Use Designing out Waste principles Produce outline SWMP Assess design team performance Identify local solutions Pre-construction & construction Draft material logistics plan Set construction tender/contact requirements Assess contractor performance Standard practice The design phase presents some of the greatest opportunities to influence waste. As the scale of materials used in an infrastructure project is so large, designing to achieve a cut and fill balance is considered by most engineers to be an integral part of the design process, to minimise material movements and associated costs. However, design teams do not often think systematically about all the major opportunities to reduce waste, reuse and recover materials and cut costs. Moreover, unless the design team quantifies the potential to save money through design actions and factors this into tender invitations or partnering agreements, the client organisation is unlikely to share in savings achieved by the contractor on site. The design process sets the size, shape and materials required by the works. It is crucial to design out waste to reduce the quantity of waste before it arises on site. Failure to think about waste at the design stage means that the contractor is often unable to reduce some of the wasteful elements which have been locked in by the designer. Therefore, empowering design teams to identify and act upon the top opportunities to eliminate waste and recover materials is important. The use of recycled materials is generally considered to be a routine part of infrastructure works, but may be constrained by: volume availability for example, because the demand for materials in infrastructure projects is so large, quantities of recycled aggregates needed may not be available locally within the specified time schedule; early identification of the potential quick wins to increase the use of recycled materials will help to identify suppliers (and supply constraints) and set realistic targets for recycled content of components; and engineering need for example, slower-setting concrete made using high levels of cement replacement materials may not be acceptable if very early trafficking of a surface is required.
12 10 Civil engineering projects: Waste less and save money WRAP s Designing out Waste Tool for Civil Engineering can be used at an early design stage to quickly estimate and select the top opportunities and actions to reduce waste and reuse and recover materials. WRAP s more detailed Net Waste Tool helps further in identifying the quick win opportunities to increase reused and recycled content at no extra cost. Both tools are freely accessible via Good practice Key action: Embed design for waste reduction, reuse and recovery in design practice, including early site investigation. During the design process there are numerous opportunities to reduce waste; WRAP has developed a systematic approach to Designing out Waste in Civil Engineering and a supporting tool, which are freely available at By focusing on waste minimisation in the earliest stages of a project as an explicit part of the design development process, the greatest opportunities for waste elimination, reuse and recycling can be prioritised, and corresponding actions included in the design stage Site Waste Management Plan (SWMP). The five principles which are recommended by WRAP to guide the attention of design teams are: Design for Reuse and Recovery; Design for Off Site Construction; Design for Materials Optimisation; Design for Waste Efficient Procurement; and Design for Deconstruction and Flexibility. WRAP s Designing out Waste methodology provides a practical means of identifying and prioritising design actions, and quantifying their waste, cost and carbon savings. In civil engineering projects, the most significant opportunities to reduce waste are by improving reuse and recovery; and by design for waste-efficient procurement. Generally, Design for Reuse and Recovery means using: materials on site to better effect; materials reclaimed from other construction sites; and/or new products with higher than average recycled content. A site investigation early in the project/design phase ensures that any materials already on the site are taken into account during the design. In civil engineering projects, there may often be an option of material retention and/or improvement of on site materials; but this must be confirmed by a site investigation and may require mixture/material development and testing. Case study evidence suggests that it is the retention and recycling of on site materials that offer the most significant cost savings to infrastructure projects. Some organisations require that all site investigation reports include a section on the potential to reuse and recover on site materials such a requirement should be embedded in the procurement process. Understanding the quality of the formation layer can be an important first step in ensuring that designs maximise the value of in-situ materials. It should not be assumed that the formation layer is inadequate without site investigation, and options for maximising the value of this existing material should be considered. Use of on site materials can include processing marginal excavated materials for use as fill; but higher value applications include enhancing the value/engineering properties of on site materials, for example, by manufacturing hydraulically bound mixtures or by using geosynthetic materials. Such higher value uses may require development and testing and so consideration during the design phase is essential to ensure there is adequate time for this work.
13 11 Civil engineering projects: Waste less and save money Priority should be given to retaining materials in their current condition, avoiding unnecessary excavation and treatment where possible. This might include retaining layers of capping and subbase which provide adequate bases for new works. Good practice site clearance and demolition should account for the retention of these materials, and their processing as appropriate; which is also facilitated by identification within the design phase to ensure appropriate scheduling. Design for Waste Efficient Procurement directs design teams to specify low-waste designs and work sequences, and set targets on contractors to reduce waste. Procurement guidance is available at and is referenced in 4.0 Procurement teams. In delivering waste efficient design, designers should assess the most significant wastes produced by the design and identify if these can be reduced by alternative design solutions or build-ability solutions. WRAP s Designing out Waste Tool for Civil Engineering (early design stage) and the Net Waste Tool (later design stage) can help designers to identify the main sources and types of waste associated with their project. Reviewing designs using these tools helps designers and clients to set realistic targets in construction procurement processes, and assists contractors in defining their own procurement of subcontractors, specialist contractors, waste management contractors and materials suppliers. Both tools are freely accessible via Design teams should discuss the designing out waste actions and SWMP with principal contractors and specialist subcontractors, see 6.0 Construction project managers, especially where there is the opportunity for early contractor involvement. In addition, designers should identify any specifications which may restrict the scope for waste reduction. If departures from standard specifications are required to reduce waste, these are more readily implemented if identified by the design team and discussed with the client and contractor. Design actions to reduce waste, and forecasts for the most significant wastes along with potential recovery routes, should be recorded in an outline/design phase SWMP. This Plan can record estimates of the waste eliminated through the design process, to help design managers with internal reporting processes. WRAP have produced a SWMP template which includes a section to record Designing out Waste decisions. The template can be accessed via The outputs of the SWMP, or reports produced from the Designing out Waste Tool for Civil Engineering or Net Waste Tool can all be used to demonstrate the reductions in waste and associated potential cost savings. Best practice Key action: Implement all Designing out Waste principles and, where appropriate, benchmark performance on current designs and assess design team performance in reducing waste. To implement best practice waste reduction through design, all five Designing out Waste principles should be considered. Work with building projects clearly indicates that Design for Off Site Construction, where there is factory production, has the potential to significantly reduce waste. However, it can also result in changes to on site practice and may require different teams of specialist contractors: for example, compare operational needs on site to place large precast concrete components (handling areas, cranes and operators) with the demands of cast in-situ concrete (erection and striking of shuttering, temperature monitoring/control of large pours). To gain the waste benefits of off site construction, and to facilitate the resulting construction process, consideration at the design stage is important.
14 12 Civil engineering projects: Waste less and save money There are fewer immediate opportunities for off site construction within civil engineering projects, although precast component use is increasing. In addition to this, increasing numbers of innovative off site products are becoming available, and it is important that designers take note of these and remember to include them as options: for example, asphalt surfacings on a carpet roll, geosynthetics as structural materials in trackbeds, and preassembled traffic islands. Identifying innovative solutions using off site/on site construction early in the project enables research into previous performance and location-specific developments/trials to be completed in a timely manner. It is possible for large civil infrastructure projects to use on site technology to essentially provide off site manufacturing on site. For example, anecdotal evidence suggests that site batching of concrete can reduce wastage rates by providing improved responsiveness and flexibility to construction demands; on site precasting reduces lead times and ensures on-time delivery; on site (in-plant) production of hydraulically bound mixtures ensures a high quality and consistent product for large-scale applications; on site soil manufacturing can reduce the excavated material taken away for recovery. However, to take advantage of such on site technology, early consideration and planning is essential. The use of such technology must be identified at the design stage, and the potential costs and benefits quantified, to aid decisionmaking and inform construction planning. Design for Materials Optimisation demands that explicit consideration is given to material consumption and waste inherent in the design so that the design uses less material and results in less waste in the construction process all without compromising the design. Key elements in materials optimisation are: simplification and standardisation of materials and component choices to ensure that learning developed for certain aspects of the project is transferable; and dimensional coordination designing to include components in readily available sizes. Standardisation of materials and component choices can be important where innovative solutions are used or where unfamiliar (although not unusual) materials are specified. For example, if cement replacement materials are being used, this can affect the colour of the concrete without affecting quality (and potentially enhancing durability). Hence, using a consistent concrete mixture with consistent cement replacement levels will ensure that loads are not rejected simply because of a colour difference; it will also ensure that all mixtures are given adequate curing times before striking. Standardisation of joints, bearings and other structural details can reduce the need for rework as standard practice develops over time on site. In such instances, material optimisation should acknowledge the role of contractors in considering build-ability of works. In general, dimensional coordination has a more limited role in civil engineering than in buildings, and can be more readily applied to precast concrete components (such as kerbs, pavers, blocks) and drainage (such as pipes, chambers, gullies) than to other types of construction (for example, earthworks). Most civil engineering structures are constructed to meet demanding service lives and to fulfil specific functions, so Design for Deconstruction and Flexibility may not be a significant waste reduction option. However, design for maintenance should be considered wherever possible, particularly for such long-life structures. Examples of design for maintenance include installing access chambers/points that facilitate inspections or routine testing (for example, assessment of reinforcement corrosion) without needing to close or divert network users, and coordinating access to components with similar life cycles so that they can be replaced in a single closure. To maximise the waste reduction benefits of design for maintenance, discussions with operations managers and maintenance contractors are highly recommended.
15 13 Civil engineering projects: Waste less and save money Design managers should consider benchmarking design team performance on current projects, using the tools available from WRAP. This will help to quantify what is already being achieved as routine practice, and where more effort to reduce waste should be focussed. Such reviews will also help in setting targets that respond to the Halving Waste to Landfill Commitment. A selection of designs where design alternatives have been selected can be used for these benchmarking processes. It should be made clear that the design team (whether in-house or contracted) will be assessed against their performance in reducing waste and reporting on this reduction. Without such performance assessment, changes in practice that embed all five Designing out Waste principles may not be made. Where this requires a change in contract, amendments should be discussed with the procurement team (see 4.0 Procurement teams).
16 14 Civil engineering projects: Waste less and save money 5.1 Design managers checklist of design options This checklist aims to help design managers ensure that waste reduction is central to the design team s approach and that options for waste reduction are being considered and implemented by the team. It also prompts design managers to collect evidence of the process, so that learning is transferable between projects. More information on many of these design actions can be found in WRAP s Designing out Waste in Civil Engineering guidance at Design actions Relevant to the project Design team implemented Evidence acceptable Standard practice Determine if the design is likely to require import/export of materials and if a cut/fill balance can be achieved on site. Confirm if contaminated land is present, the appropriate options to remediate it (preferably on site) and agree the preferred option with the regulatory authorities. Confirm whether ground improvement techniques are likely to be required (when weak foundation soils are present). Review availability of recycled aggregates and other materials on site and in the local area and compare to project demands. Identify the probable significant wastes and input this information into the Site Waste Management Plan (SWMP). Identify any special contract conditions requiring review by client s legal advisors. Highlight design options which address planning or environmental impact assessment requirements. Ensure that any relevant information related to the construction and maintenance of the infrastructure works is recorded in the Health and Safety file. Identify any constraints on using recycled materials (such as, need for very early trafficking of concrete surfaces). Good practice Develop the requirements for the preliminary site investigation to enable decisions to be made on the options for ground improvement (including insitu reuse) and provide adequate time for designs, testing and trials. Investigate opportunities to avoid or minimise excavation on site. Identify existing foundations, structures, pavements, floor slabs or services that can be reused as they exist on site. Identify existing materials and quantities that can be recycled for use in the new construction choose between on site and off site recycling. Determine if treatment of unsuitable soils is possible and what options might be used (such as in-situ stabilisation, producing hydraulically bound mixtures ex-situ, or using geosystems).
17 15 Civil engineering projects: Waste less and save money Design actions Relevant to the project Design team implemented Evidence acceptable Good practice (continued) Identify suitable materials for soil manufacture with PAS 100 compost (either on site or off site) and use PAS100 compost in soils manufacture and landscaping. When working platforms are required, determine if they can be integrated into the permanent works and if they can be constructed using in-situ and/or recycled materials. Review piling designs to determine if rotary or displacement piles (rather than replacement) can be considered. Use the Designing out Waste Tool and/or Net Waste Tool to identify key ways to reduce waste on the project. Record design decisions and outline quantities of waste in the project Site Waste Management Plan from an early design stage, and set preliminary targets for waste reduction, reuse and recovery. Identify opportunities for small scale components (such as manholes) to be manufactured using off site construction. Embed waste reduction and recovery initiatives in drawings, specifications and contracts. Ensure that no materials are used that will be difficult to recycle in the future and record assessment in the project Health and Safety file. Consider the sequence of work and how this can reduce waste. Include Designing out Waste on the agenda for design team meetings and design reviews. Review existing drawings, specifications and contracts to ensure that they do not limit waste reduction, reuse and recovery. Identify the potential costs/cost savings made by Designing out Waste and good practice on site waste management and ensure that this is shown transparently in construction tenders/pricing. Best practice Design site layout to use existing topography and features to minimise earthworks. Use geosystems to reduce overall material use in pavements, structures and earthworks. Use in-situ remediation or encapsulation of contaminated land in preference to excavation and treatment. Use innovative materials to reduce demand for primary resources, for example, tyre bales or plastic piles. Standardise similar elements (for example, geosystems) so that repeatability of the process leads to manufacturing and installation efficiencies including waste reduction. Identify if future expansion or modification of the construction is likely to be required and if measures need to be included in the design to facilitate this.
18 16 Civil engineering projects: Waste less and save money Design actions Relevant to the project Design team implemented Evidence acceptable Best practice Assess the opportunities for off site construction of key components and compare to on site construction methods and the cost of any testing and certification required. Consider structural solutions that use less material and simplify the structural solutions as much as possible (for example, the use of post tensioned concrete instead of cast in-situ reinforced concrete). Provide wording to embed all of the design options to be pursued into the SWMP, project briefings and procurement. Include specific measures to enable future expansion or upgrading if required. Identify opportunities for large-scale components (such as panels) to be manufactured using off site construction. Identify opportunities to bring manufacturing on site. Consider opportunities for dimensional coordination of small-scale elements (such as kerbs, gullies, and chambers). Highlight opportunities for the design to enable longer-term maintenance with reduced waste. Benchmark design team performance on projects to enable future performance assessment.
19 17 Civil engineering projects: Waste less and save money 6.0 Construction project managers Figure 6 Construction project managers Review existing contracts to benchmark performance or to embed targets/metrics Preparation and design Set requirements in design team appointments Use Designing out Waste principles Produce outline SWMP Assess design team performance Identify local solutions Draft material logistics plan Pre-construction & construction Set construction tender/contact requirements Update and maintain SWMP Assess contractor performance Set maintenance waste management strategy Handover, postcompletion & use Set maintenance and/or waste management tenders/contract requirements Monitor performance Standard practice Meeting regulatory requirements (in England) for site waste management should be standard practice for all construction projects. To use the Site Waste Management Plan (SWMP) effectively, it should be considered as early in the project as possible and involve all members of the supply chain. WRAP has produced leaflets which summarise the role of each supply chain member, available at Standard practice should include review and update of the SWMP.
20 18 Civil engineering projects: Waste less and save money Good practice Key action: Develop and update the SWMP to reduce and reuse wastes as well as managing their recovery, starting at an early stage of design, and use this information to direct and assess contractor performance; require design teams and contractors to identify with their supply chains how to use in-situ and reused materials and higher recycled content products, and recover more waste materials. Construction project managers have a key role in informing design processes (see 5.0 Design managers) and working with operation managers to ensure construction projects have wasteefficient maintenance strategies (see 7.0 Operations managers). The influence of contractor thinking in design is particularly evident in some forms of procurement, such as Design and Build or Early Contractor Involvement, but construction managers within client organisations should be involved in all design processes irrespective of the procurement route. They may also be involved in benchmarking current waste management performance within ongoing projects; this may be facilitated by the WRAP Site Waste Management Plan Template, visit Although it is a mandatory requirement (in England) for the Principal Contractor to update a SWMP every six months at least, organisations can benefit from more regular reviews to ensure that unexpectedly high waste levels are recognised and tackled; and surprisingly low wastage rates are understood and good practice shared across the supply chain. Identifying and capturing good waste management practice will help organisations transfer learning between projects. The SWMP can be used to assess contractor performance on an ongoing basis and at the end of the contract. As discussed in 5.0 Design managers, designers have a key role to play in identifying options for waste reduction, on site reuse and import of recovered or recycled content materials. However, contractors will need to use local (or national) supply chains to deliver against these options. Organisations that procure significant works in particular regions may wish to identify suppliers able to support the range of projects undertaken. WRAP provides information on suppliers of recycled products, recycled aggregates, recycled wood, and reclaimed products (such as pavers) which might be of use in civil engineering projects. The supplier directories for recycled aggregates and for recycled wood also identify organisations that accept these materials for recycling. For more details, go to: WRAP has also recommended good practice standard terms and conditions for waste management companies that will help them identify themselves as good practice providers, as well as tender and contract clauses specifically for clients and contractors to procure waste management services. For more details, visit:
21 19 Civil engineering projects: Waste less and save money When using recycled materials, it is important that everyone involved is confident in the use of these materials, including inspectors and clerks of works. Without sufficient training and experience, it is possible that some recycled materials may be turned away as they look different. For example, concrete containing cement replacement materials may look different to traditional Portland cement concrete (see 5.0 Design managers); recycled aggregates may contain wood, plastic or metal contamination without affecting performance. WRAP provides additional guidance for client project managers at Best practice Key action: Develop and implement a Material Logistics Plan. Multiple handling of materials on site costs money and increases the likelihood of damage and wastage. In addition, construction logistics can reduce the waste generated on site; by, for example, effective delivery scheduling, creating materials handling areas or consolidation centres off site, back-hauling materials following deliveries and effective use of information technology. Considering materials logistics during design will help to facilitate effective site practices (such as on site manufacturing see 5.0 Design teams), but the key influence will be when construction supply chains are established. WRAP has produced extensive guidance on developing Materials Logistics Plans which can be downloaded from
22 20 Civil engineering projects: Waste less and save money 7.0 Operations managers Figure 7 Operations managers Preparation and design Review existing contracts to benchmark performance or to embed targets/metrics Set requirements in design team appointments Use Designing out Waste principles Pre-construction & construction Set maintenance waste management strategy Handover, postcompletion & use Set maintenance and/or waste management tenders/contract requirements Monitor performance Standard practice Site Waste Management Planning for major maintenance projects will be commonplace; but such plans may not be applied to small works, even where these are undertaken by a single supplier. However, it will be reasonably common for some form of waste analysis to be in place on all works so that the maintenance contractor can understand and manage their waste arisings to minimise costs. These cost savings may not be visible to the client organisation, and formal procedures for reporting on waste arisings and reductions may not be in place. Good practice Key action: Set formal reporting requirements and monitor performance. For large maintenance projects where Site Waste Management Plans (SWMP) are used, waste management will resemble that of construction projects (see 5.0 Design managers and 6.0 Construction project managers). For smaller projects, there may be no formal waste management process in place dictated by the client. At minimum, contract requirements should be set to measure and report waste arisings and their destinations since this will influence cost. The WRAP Site Waste Management Plan Template may be helpful in this recording and reporting process; it can be downloaded from Benchmarking current projects will provide data for target setting in future contracts. WRAP provides guidance for programmes of minor works, including a simple template for reporting key actions and outcomes to the client in the absence of a SWMP available at
23 21 Civil engineering projects: Waste less and save money Best practice Key action: Support design and construction processes to minimise waste in operation and use design and construction information to develop a maintenance waste management strategy. Operations Managers may be asked to become involved in best practice design and construction processes that consider maintenance implications (see 5.0 Design managers and 6.0 Construction project managers). Accounting for the waste generated by the long-term management of civil engineering works may be facilitated by a formal waste management strategy. The strategy should complement any asset management strategy and, like an asset management strategy, should provide a consistent approach to maintenance wastes over the lifetime of the asset even though the managing personnel will change during that time. The life span of civil engineering assets can be tens, if not hundreds of years. The strategy could begin by identifying the significant wastes expected and their occurrence with time. The disposal and recovery options for such wastes can be identified and should be periodically reviewed and updated as technologies and local markets change. However, it should be recognised that developing such a strategy may only add value if the wastes being generated from existing operations are quantified and understood.
24 While steps have been taken to ensure its accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading. This material is copyrighted. It may be reproduced free of charge subject to the material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must not be used to endorse or used to suggest WRAP's endorsement of a commercial product or service. For more detail, please refer to our Terms & Conditions on our website - Waste & Resources Action Programme The Old Academy 21 Horse Fair Banbury, Oxon OX16 0AH Tel: Fax: [email protected] Helpline freephone
Procurement requirements for reducing waste and using resources efficiently
Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction
Designing out Waste: a design team guide for buildings
Uniclass A42: N462 CI/SfB (Ajp) (T6) Designing out Waste: a design team guide for buildings Less Waste, sharper design Halving Waste to Landfill Clients are making construction waste reduction a priority
Site waste it s criminal A simple guide to Site Waste Management Plans
Site waste it s criminal A simple guide to Site Waste Management Plans Introduction 10m tonnes of construction products are wasted every year, at a cost of 1.5 billion Much of this site waste is harmful
Manchester United Old Trafford Stadium
WRAP Resource Management Plan Online Tool for Events Manchester United Old Trafford Stadium The WRAP Resource Management Plan (RMP) for events is a free online tool which can be used by event organisers
Presentation Overview. Site Waste Management Plans: A missed opportunity?
Site Waste Management Plans: A missed opportunity? Presenter: Derek Duckett (CEnv, MIEMA) Project Manager Company: Mabbett & Associates (EH&S Consultants & Engineers) [email protected] Presentation Overview
Recycling of Mineral Wool Composite Panels Into New Raw Materials
Case Study: Mineral Wool/Steel Composite Panel Recycling Recycling of Mineral Wool Composite Panels Into New Raw Materials Eurobond have developed a method for recycling mineral wool composite panels.
Choosing the right recycling collection system
Choosing the right recycling collection system WRAP s role in relation to the design of recycling systems is to help practitioners by gathering and sharing knowledge and understanding about the relevant
Compactable Construction Waste Collection from Developments with Limited Storage Space
Waste Logistics Case Study Compactable Construction Waste Collection from Developments with Limited Storage Space The movement, storage and subsequent removal of mixed construction waste on space-limited
Asset Management Policy March 2014
Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and
Sustainable procurement of mobile phone service contract
Sustainable procurement of mobile phone service contract Summary Key Facts WRAP delivered a programme of providing technical procurement support to public sector organisations on behalf of Defra during
Comparing the cost of alternative waste treatment options
1 Comparing the cost of alternative waste treatment options WRAP s (Waste and Resources Action Programme) sixth Gate Fees report summarises the gate fees charged for a range of waste treatment, recovery
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
Product damage and returns Electrical and Electronic products
Product damage and returns Electrical and Electronic products Note Product damage and returns Electrical and Electronic products Product returns are estimated to cost the Electrical and Electronic Equipment
ARID (Accelerating Reprocessing Infrastructure Development) External Programme Evaluation: Summary Report (February 2015)
ARID (Accelerating Reprocessing Infrastructure Development) External Programme Evaluation: Summary Report (February 2015) Background ARID (Accelerating Reprocessing Infrastructure Development) was a 14
Corporate Risk Management Policy
Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
Engineering Policy 146. Severe Weather Management Plans
Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...
Planning waste management for events in Trafalgar Square
Planning waste management for events in Trafalgar Square Trafalgar Square is one of the UK s most iconic destinations and the Greater London Authority (GLA) manages events held there throughout the year.
Responsibility Deal between Government and the waste and resource management sector. June 2011
www.defra.gov.uk www.esauk.org Responsibility Deal between Government and the waste and resource management sector June 2011 Department for Environment, Food and Rural Affairs Nobel House 17 Smith Square
How to do Business with the London. Borough of Sutton
How to do Business with the London Borough of Sutton February 2013 1 About this guide This guide has been developed to assist businesses wishing to sell their goods and services to the Borough. Contents
Building a sustainable future together
Please consider the environment and do not print this document PCSA Building a sustainable future together 2009 Guidance Note Guidance Note Building asustainable future together Published February 2009
HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM
HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM September 2011 OUR HEALTH, SAFETY AND ENVIRONMENT POLICY OUR PRINCIPLE OF DUE CARE We care about the wellbeing of our people and our impact on the environment.
Review of contract practice in construction waste management
Final Report Review of contract practice in construction waste management Including a summary of the current practice of contracting waste management companies by construction contractors, this report
Aggregates for Path Construction
Aggregates for Path Construction Technical Information Note No. 7 October 2011 About Sustrans Sustrans makes smarter travel choices possible, desirable and inevitable. We re a leading UK charity enabling
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
The London Waste and Recycling Board business plan 2015-2020. November 2014. London Waste and Recycling Board 169 Union Street London SE1 0LL
The London Waste and Recycling Board business plan 2015 2020 November 2014 London Waste and Recycling Board 169 Union Street London SE1 0LL [email protected] www.lwarb.gov.uk 2015 2020 Business Plan Contents
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
scotland s zero waste plan
scotland s zero waste plan REDUCE REUSE RECYCLE scotland s zero waste plan The Scottish Government, Edinburgh 2010 Crown copyright 2010 ISBN 978-0-7559-8306-3 The Scottish Government St Andrew s House
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)
Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership
Volunteer Managers National Occupational Standards
Volunteer Managers National Occupational Standards Contents 00 Forward 00 Section 1 Introduction 00 Who are these standards for? 00 Why should you use them? 00 How can you use them? 00 What s in a Standard?
Department of Public Works. Recycling policy for buildings and civil infrastructure
Department of Public Works Recycling policy for buildings and civil infrastructure A whole-of-government recycling policy for buildings and civil infrastructure Policy statement The Queensland Government
Technical Journal. Paper 142
Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager
MANAGEMENT SYSTEMS CERTIFICATION
MANAGEMENT SYSTEMS CERTIFICATION VCA - Delivering a Safer Environment VCA - Delivering a Safer Environment 1 Contents Pg 2 Formal Certification - Burden or Benefit? 4 Why VCA? 6 ISO 14001 8 Acorn (A Phased
SD10: HIGHWAY NETWORK MANAGEMENT BEST VALUE REVIEW. (reproduced review document)
SD10: HIGHWAY NETWORK MANAGEMENT BEST VALUE REVIEW (reproduced review document) Highway Network Management Best Value Review Report of the Member Panel Summary of Key Findings Leicestershire County Council
Capita Symonds Real Estate Sustainability Report 2012 Royal London Asset Management Portfolio
Capita Symonds Real Estate Sustainability Report 2012 Royal London Asset Management Portfolio Highlights Over 10,000 tonnes CO2 equivalent saved from entering the atmosphere Carbon Saver Gold Standard
Site Waste Management Plan Tracker User Guide
Site Waste Management Plan Tracker User Guide User Guide Project code: WAS770-002 Date: December 2009 Introduction The SWMP Tracker is an online tool that allows users to collate, aggregate and analyse
Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014
for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application
Achieving Excellence in Construction. A manager s checklist. Construction projects
Achieving Excellence in Construction A manager s checklist Construction projects Construction projects A manager s checklist This document outlines the key questions that a Senior Responsible Owner (SRO)
The Designing out Waste Tool for Civil Engineering Projects
Reference guide August 2010 The Designing out Waste Tool for Civil Engineering Projects Guide to Reference Data, Version 1.0 WRAP s vision is a world without waste, where resources are used sustainably.
Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information
Royal Borough of Kensington and Chelsea Data Quality Framework ACE: A Framework for better quality data and performance information March 2010 CONTENTS FOREWORD 2 A CORPORATE FRAMEWORK FOR DATA QUALITY
How are companies currently changing their facilities management delivery model...?
Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy
SMS0045 Construction Health and Safety Policy and Procedures
SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April
Operations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
Modern Methods of Construction (MMC)
Improving resource efficiency in construction product manufacture BeAware Supply Chain Resource Efficiency Sector Report Modern Methods of Construction (MMC) BeAware is a TSB 1 and industry funded project
How To Write A Sustainable Resource Management Framework
FORTH REPLACEMENT CROSSING M9 Junction 1a Project Quality Plan: Volume 4 Sustainable Resource Management Framework Construction Issue RSMF 02: May, 2012 FORTH REPLACEMENT CROSSING M9 JUNCTION A1 SUSTAINABLE
Quality Management Manual
Quality Management Manual CONTENTS 1 Introduction... 1 2 Scope... 1 3 Company quality policy... 1 4 The fundamentals of quality management... 2 4.1 The principles...2 4.2 Plan - Do - Check - Act...3 4.3
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
Construction Resources and Waste Roadmap
A short guide to the Construction Resources and Waste Roadmap A roadmap is a tool that helps us visualise... ... how to get from A In England, construction, demolition and refurbishment activities produce
JOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff
JOB DESCRIPTION Facilities Manager Soft Services DIRECTORATE: Merlin Works DEPARTMENT: Facilities Management SALARY: 44,880 RESPONSIBLE TO: Head of Facilities Management RESPONSIBLE FOR: Team Leaders and
PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS
PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0
Environment Committee 11 January 2016
Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment
Procurement and Contract Management Strategy 2013-2017
Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date
Tapping the benefits of business analytics and optimization
IBM Sales and Distribution Chemicals and Petroleum White Paper Tapping the benefits of business analytics and optimization A rich source of intelligence for the chemicals and petroleum industries 2 Tapping
MANAGEMENT SYSTEMS CERTIFICATION FROM AUTOMOTIVE SPECIALISTS
MANAGEMENT SYSTEMS CERTIFICATION FROM AUTOMOTIVE SPECIALISTS VCA - Delivering a Safer Environment VCA - Delivering a Safer Environment 1 Contents Pg 2 Formal Certification Burden or Benefit? 3 Why VCA?
Corporate Procurement Strategy 2014-2017
Strategy 2014-2017 Strategy 2014-2017 Introduction The Brighton & Hove community is distinctive for its strong international flavour and vibrant diversity of cultures. The make-up of the local population,
Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218
Copyright in the material is owned by the State of New South Wales. Apart from any use as permitted under the Copyright Act 1968 and/or as explicitly permitted below, all other rights are reserved. You
Waste management and disposal:
Waste management and disposal: A best practice business guide An ebook produced by FCC Environment 01 Waste management and disposal: a strategy for success Introduction Your guide to waste management FCC
Sustainable Development Strategy
Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for
PROCUREMENT & LOGISTICS DEPARTMENT
PROCUREMENT & LOGISTICS DEPARTMENT Tender/OJEU Procedure Overview This procedure applies to all purchases over 50,000 not covered by existing contracts and should be followed in conjunction with the Tender/OJEU
University of Brighton Sustainable Procurement Strategy 2011-2015
University of Brighton Sustainable Procurement Strategy 2011-2015 Sustainable procurement in a challenging environment Introduction There is widespread recognition that climate change and the use of dwindling
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement
Acceptance on the Approved List of contractors cannot however guarantee that any work orders will be issued to that contractor.
PROPERTY MANAGEMENT INTRODUCTORY GUIDANCE NOTES FOR THE APPLICATION TO THE APPROVED LIST OF CONTRACTORS CONTRACTORS GUIDANCE NOTES APPLICATION FORM ISSUED BY: PROPERTY MANAGEMENT UNIT WEST YORKSHIRE FIRE
Smarter Resources Smarter Business Recycling
Smarter Resources Smarter Business Recycling Best Practice Waste and Recycling Contracts for Business February 2014 Best Practice Waste and Recycling Contracts for Business A three step process There is
Procurement of Goods, Services and Works Policy
Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Tendering to Public Sector Organisations
Tendering to Public Sector Organisations Introduction Authorities have to meet contract regulations and must ensure they provide equal opportunity and achieve the best value for money. Other factors include
Competence Criteria for Associate (ACIBSE)
Competence Criteria for Associate (ACIBSE) FACTSHEET A21 The competence criteria for the Associate grade of CIBSE (ACIBSE) is directly aligned to the Competence Statements issued by the Engineering Council,
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
Procurement and contract strategies
Achieving Excellence in Construction Procurement Guide 06 Procurement and contract strategies 06 Contents 01 The Achieving Excellence Procurement Guides 02 Introduction 02 Principles 05 Process 18 Annex
Sustainable Supply Chain Policy
Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles
MAKING YOUR ORGANISATION S INFORMATION ACCESSIBLE FOR ALL IMPLEMENTING THE GUIDELINES FOR ACCESSIBLE INFORMATION
MAKING YOUR ORGANISATION S INFORMATION ACCESSIBLE FOR ALL IMPLEMENTING THE GUIDELINES FOR ACCESSIBLE INFORMATION project has been funded with support from the European Union. publication reflects the views
CORPORATE PERFORMANCE MANAGEMENT GUIDELINE
-001 CORPORATE PERFORMANCE MANAGEMENT GUIDELINE -001 TABLE OF CONTENTS 1 Introduction... 3 1.1 Scope... 3 1.2 Purpose... 3 2 Performance Management Framework Overview... 4 3 Performance Management Framework...
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
Benefits of reusing & recycling bulky waste
Benefits of reusing & recycling bulky waste Introduction Reuse and recycling of bulky waste brings benefits to the local authority, the local community and the environment. Local authority benefits of
Quality Management Subcontractor QM Guide-Section Two
SECTION TWO QUALITY MANAGEMENT SYSTEMS Version No 1. PREFACE This document has been developed to assist subcontractors to meet Monaco Hickeys (MHPL) Quality Management (QM) requirements whilst working
Internal Audit Quality Assessment Framework
Internal Audit Quality Assessment Framework May 2013 Internal Audit Quality Assessment Framework May 2013 Crown copyright 2013 You may re-use this information (excluding logos) free of charge in any format
Monitoring Highways England The monitoring framework
Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document
Information Management Strategy. July 2012
Information Management Strategy July 2012 Contents Executive summary 6 Introduction 9 Corporate context 10 Objective one: An appropriate IM structure 11 Objective two: An effective policy framework 13
RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.
RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as
Preparation of a Rail Safety Management System Guideline
Preparation of a Rail Safety Management System Guideline Page 1 of 99 Version History Version No. Approved by Date approved Review date 1 By 20 January 2014 Guideline for Preparation of a Safety Management
The anglo american Safety way. Safety Management System Standards
The anglo american Safety way Safety Management System Standards 2 The Anglo American Safety Way CONTENTS Introduction 04 Anglo American Safety Framework 05 Safety in anglo american 06 Monitoring and review
Chapter 6: Design Management
Chapter : Design Management Department of Main Roads Chapter Design Management June 2005 i Department of Main Roads Chapter : Design Management Manual Contents Chapter 1 Planning and Design Framework Chapter
Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy
Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal
Drainage and Grease Management for the Commercial Kitchen
Drainage and Grease Management for the Commercial Kitchen ACO. The future of drainage. The ACO system chain provides drainage solutions to meet the needs of tomorrow s food service facilities. Hostile
RISQS FAQs. About RISQS. services provided by
services provided by RISQS FAQs About RISQS RISQS, formerly known as Achilles Link-up, supports the GB Rail industry in the management of supply chain risk. The scheme has been developed to provide a service
REPORT 4 FOR DECISION. This report will be considered in public
REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director
Steel procurement in major projects: Guidance on the application of social issues. Purpose
Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.
Improving information to support decision making: standards for better quality data
Public sector November 2007 Improving information to support decision making: standards for better quality data A framework to support improvement in data quality in the public sector Improving information
SUSTAINABILITY CHARTER. May 2012. 1 R&CA Sustainability Charter V1
SUSTAINABILITY CHARTER May 2012 1 R&CA Sustainability Charter V1 Introduction By their very nature, restaurant and catering businesses are significant users of energy, water and raw materials. Cooking
Resource efficiency in the UK whisky sector
Case Study: UK Drinks Sector Resource efficiency in the UK whisky sector Reducing water, material and packaging use in the whisky sector. Resource efficiency in the UK whisky sector 2 WRAP s vision is