NUCOR U.S. High Tension Cable Barrier System INSTALLATION MANUAL
|
|
|
- Christal Robbins
- 10 years ago
- Views:
Transcription
1 NUCOR U.S. High Tension Cable Barrier System INSTALLATION MANUAL
2 CONTENTS INSTALLATION CONSDERATIONS... 3 SYSTEM LAYOUT... 3 Site Preparation... 3 Line Posts... 3 Anchor Posts... 4 INSTALLING POSTS... 5 Anchor Posts... 5 Line Posts... 7 INSTALLING CABLE Cable-to-Post Connections Connecting Cable Ends Field Applied Cable Attachment and Wedge Encasement Wedge Installation Connection Hardware Turnbuckles System Splicing Prestretched Cable Option Tensioning the System Tension Table DELINEATION REPAIR & MAINTENANCE Repeat Impacts Releasing Tension Cutting Cables Overlays Emergency Access Materials for Maintenance INSTALLATION CHECKLISTS Cable Checklist Post Checklist Terminal/Anchor Checklist APPENDIX Tension Log Standard Cable Terminal End Installation Details TECHNICAL SUPPORT AND SALES U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 2
3 INSTALLATION CONSDERATIONS The US High Tension Cable system is strait forward and easy to install and can be safely installed by the use the installation manual alone. This manual should be carefully reviewed prior to construction to ensure proper installation of the US High Tension Cable System. The initial insulation run for any new crew will need to be supervised by a qualified Nucor Distributor or Nucor Steel Marion Inc representative, or properly trained crew that has successfully installed the system. We also strongly recommend that the first run for any new installation crew be completely installed and tensioned before attempting to start other runs. It there is ever a doubt about any part of the installation contact Nucor Steel Marion Inc (800) or your Nucor Distributor immediately. Distributor contact information is listed on the last page of this manual. SYSTEM LAYOUT Site Preparation The initial layout for the US High-Tension System should be free of hazards, obstacles, and debris. The cross-slope should be 6:1 or flatter. Grading may be necessary. It is important to note that the high-tension cable barrier cannot be installed within a range of 1 (305mm) to 8 (2.44m) from the bottom of a median ditch according to FHWA standards. The high-tension cable barrier can be installed in the bottom of the median ditch or within a 1 (305mm) range either side of the median ditch. However, this is not recommended because of potential water drainage issues. Line Posts A string line should be set to aid in properly placing the posts and cables. Mark each run starting with the location of end treatments. Then mark the position for each cable line post to be installed according to project plans to meet required deflections. Please refer to project plans for job specific post spacing. The line post spacing can be varied from 6-6 to 20 (2m to 6m), depending on desired deflection. Please refer to the project plans and specifications to determine which post spacing is required for your installation. Varying post spacing can also be used when necessary due to conflicts with utilities or culverts. It is helpful to mark every 750 (229m) when laying out the system to aid in turnbuckle placement as you pull cable. Mark every 1000 (305m) if using prestretched cable. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 3
4 Anchor Posts Each Cable Barrier Terminal Section consists of 3 (2-part) Cable Release Posts (CRP) at 6 3 post spacing and 6 line posts at 6 6 post spacing. The CRP terminal posts (#1, #2 & #3) are offset from the centerline of the string line. The remaining terminal posts (#4 through #7) and all cable line posts should be centered on the string line. Installation tolerances of the CRP locations are as follows: +/- 12 inches parallel to the system +/- 6 inches perpendicular to the system* *CRP posts may be in contact with cables leading to other posts, but may not cause more than ½ inch deflection. Note that the opposing end treatments on a particular run are mirrored in their layout (see figure below). U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 4
5 INSTALLING POSTS Anchor Posts There are two options for installing CRPs. They can be either cast-in-place in a concrete footing or directly embedded (driven), depending upon project specifications. Option 1: Driven CRP posts with soil plate For permanent or temporary usage or where soil is known to be very strong, there is an option of installing CRP post without a concrete footing. The CRP post base is 72 (1829mm) long and has a 1/4 x 18 x 48 (6mm x 457mm x 1219mm) welded soil plate. Attach the CRP top to the base with the two 5/16 (8mm) breakaway bolts provided. Where soils are weaker than NCHRP 350 strong soil consult the manufacturer for special CRP post anchors that can be designed to appropriately meet the demands of your soil conditions. Option 2: CRP posts cast-in-place In strong soil conditions drill 18 (457mm) diameter x 5-0 (1524mm) deep hole. Place steel reinforcement as detailed on plan standard. Plumb posts and pour concrete. Be sure to not leave more than 4 (102mm) of the CRP post base exposed above the ground line. It is easier to plumb the CRP bases with the CRP top posts attached. Attach the CRP top to the base with the two 5/16 (8mm) breakaway bolts provided. Option 3: Precast CRP posts Use an 18 (457mm) diameter x 5-0 (1524mm) form. Some contractors have found that modifying a standard section of 18 steel culvert pipe works well as a reusable form. Place steel reinforcement as detailed on plan standard. Plumb posts and pour concrete. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 5
6 Be sure to not leave more than 4 (102mm) of the CRP post base exposed above the ground line. It is easier to plumb the CRP bases with the CRP top posts attached. The back fill material needs to be strong soil, compacted in 6 (162mm) lifts with a hydraulic tamper. Soft Soil foundations options for the CRP posts CRP foundations in soft soil should be a minimum of 8 in depth with an 18 diameter shaft; use 12 rebar cage reinforced with #5 s at 6 O.C. with straps. Pouring a monolithic concrete pad for all three CRP post is also a viable option. For embedment less than 5 : Use a 4 wide x 3 deep monolithic concrete pad that spans the length of all 3 of the CRP posts. It will need to extend 2 past each end CRP Post; total length being approximately Use #5 steel reinforcement bars equally spaced at 6 O.C. For embedment depth of 5 to 5.9 : Drill a 48 diameter shaft. Use a 40 rebar cage reinforced with #5 s equally spaced at 6 O.C. with straps. For embedment depth is : Drill a 36 diameter shaft. Use a 30 rebar cage reinforced with #5 s equally spaced at 6 O.C. with straps. Embedment depth is : Drill a 24 diameter shaft. Use an 18 rebar cage reinforced with #5 s equally spaced at 6 O.C. with straps. All concrete should be 3000 psi minimum and should cure for at least 7 days before tension is added to system. Direct Driven CRP foundations are 8 in length with attached soil plate. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 6
7 Line Posts There are two options for installing the line posts. They can be either directly embedded (driven) or installed in sockets, depending upon project specifications. The system can be installed using either a 4# or 5# Rib-Bak Line Post. 20 TL3 system use 5# Rib-Bak Line Post All other current TL3 system options use 4# Rib-Bak Line Post Option 1: Direct-Driven Line Post The direct embedment method uses 72 (1829mm) Rib-Bak Line Post with no soil plate required. Direct driven line posts are driven into natural soil using a preset string line to depth of 39 (991mm). The top of the line post should be 33 (838mm) above ground after installation. Option 2: Socketed Foundation, Concrete Footing The socketed method utilizes a 12 GA 4 OD x 15 (102mm x 381mm) steel socket set into a 12 diameter x 30 deep [305mm x 768mm] concrete footing. The socket depth is assumed to be in NCHRP 350 strong soil. In weak soil or where the frost line is below 30 (305mm) the depth of the socket should be increased to accommodate. The concrete foundation is strengthened with one #3 steel reinforcing ring and two #4 x 28 steel dowels. The ring is inserted to a depth of 4 ; the dowels are inserted to a depth of 2. The dowels should be installed at approximately 25 degrees off center so that they are in line against oncoming traffic. The steel reinforcement does not need to be tied. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 7
8 Use a socket insertion tool (see photo) to install socket after steel reinforcement has been placed. The top of the socket should normally be flush with the top of the foundation concrete. To prevent runoff debris from entering the socket, the foundation should be finished with up to 3/4" (19mm) taper to the outer edge. This may not be required when the system is installed in a mow strip. For uneven terrain (see picture below), where the potential exists for line posts to be pulled out of their sockets by the tensioning of the cable, set the socket in the concrete with no more than 2 (51mm) above ground level with no less than 13 (330mm) embedment. After concrete has set, drill a 3/8 (10mm) hole as close to the base of the footing as workable to install a 5/16 (8mm) bolt to hold the post in place. The socketed method requires a 48 (1219mm) Rib-Bak Cable Line Post. The top of the line post should be 33 (838mm) above ground after installation. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 8
9 Option 3: Precast Socketed Foundation, Concrete Footing The precast line post socket follows the same detail as the standard socketed concrete footing. Use a 12 diameter x 30 deep [305mm x 768mm] form. Some contractors have found that modifying a standard section of 12 steel culvert pipe works well as a reusable form. Place steel reinforcement as detailed on plan standard. Plumb posts and pour concrete. Be sure not leave more than 2 (51mm) of the line post socket exposed above the ground line. It is easier to plumb the line post socket with a post temporarily inserted in the socket. The back fill material needs to be strong soil compacted in 6 (153mm) lifts with a hydraulic tamper. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 9
10 INSTALLING CABLE The cable used in the U.S. High-Tension System is 3/4 diameter (19mm), 3x7 construction, galvanized cable. It weighs lbs/ft, and is packaged in 2000 or 3000 (915m) per wooden reel. The empty reel weighs 260 lbs (118kg). Shipping weight per reel is 2831 lbs (1284kg) for 3000 reel. Illustrated below are two different methods contractors have used to transport and pull cable. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 10
11 Cable-to-Post Connections Each cable is attached to each post using a 5/16 [8mm] diameter locking hook bolt. Right-side-of-the-road applications have all 3 cables on the travel side of the line posts. When installing the cable barrier in a median, the lower and upper cables should be located on the post side closest to the roadway, and the middle cable should be located on the opposite side. MEDIAN RIGHT-SIDE MEDIAN US High-Tension System cable heights measured at the middle of the cable are as follows: Top Middle Bottom Median & Roadside 29.5 in 25.5 in 21.5 in ±1 ±1 +0 /-2 (750mm) (650mm) (545mm) Please see Cable Terminal End Installation detail in the Addendum for terminal end cable heights which vary on posts #4 -#9. Tolerances for all posts are ±1 for the top and middle cable, and +0 /-2 for the bottom cable. Connecting Cable Ends To connect the cables to the terminal, affix a cable end anchor to the end of each cable. Grease is recommended on all threaded rods to ease tensioning. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 11
12 Insert the cable end anchor into the CRP post and through the L-Bracket, and install double nuts. The bottom cable shall be attached to CRP #3, the middle cable to CRP #2, and the top cable to CRP #1. Before putting final tension in system, ensure the L-Bracket is properly situated as show below. Leave nuts as far down on the threads as possible to leave yourself ample room for tensioning the cables. Run the cable along the ground to the respective turnbuckle location. Cut the cables and affix to one end of the turnbuckle. Attach the other end of the turnbuckle to the adjacent segment of cable and then connect the turnbuckle leaving the maximum amount of threads for tensioning. Repeat for all three cables to end of run. Field Applied Cable Attachment and Wedge Encasement Cable attachment hardware requires the wedge to be properly encased in the cable strands and seated into the casting to insure that the cable will not slip out of the hardware. o The wedge must be seated into the cables such that the flutes in the wedge nest with the three x strands of the cable. If not properly aligned cable slippage is possible. Strands in flute wedge U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 12
13 o The wedge needs to be at minimum seated inside the cable strands such that the top of the wedge is flush with all three 7 x strands. If one strand of the three 7 x strands is not at minimum flush then the wedge need to be reset. The optimum seating for the wedge is such that there is 1 of cable is beyond the wedge. o o If slippage between the wedge and strands occurs reset the wedge deeper into the strands. It is acceptable for the wedge to protrude up to 1/4 from the bottom of the casting as long as the wedge has been seated properly. If the wedge protrudes more it must be reset. During the initial installation process the three 7x strands should be set in the body of the casting such that the nut has just enough room to be inserted. This will help insure that the wedge is seated below the three 7 x strands. Wedge Installation 1. Some contractors choose to use a screw driver to open up the cable and separate the three 7 x strands in preparation for wedge insertion. Once the wedge is inserted into the cable it should be driven approximately 1 inch below the end of the cable. 2. Other contractors have chosen to insert the cable into the casting and twist the casting until the strands pop open inside the casting opening up the cable lay. The wedge is inserted into cable strands approximately 1 inch below the end of the cable. The casting is then twisted back so that the cable lay is returned to the initial position. 3. Other installation methods are acceptable as long as the wedge placement & cable engagement is correct. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 13
14 Connection Hardware Insert the special locking hook bolts (pictured at left) into the appropriate locations on the line posts to ensure correct cable height and allow them to hang down such that they will accept the cable when it is strung. As the cable is strung, rotate the special hook bolts and attach the nut. Nuts need only be finger-tight. The long hook bolt is used on median applications only. Turnbuckles Turnbuckles are used to achieve the appropriate tension in the system. In a system using standard cable, install one turnbuckle per cable every 750 (229m). If your run is 750 long (229m), install the turnbuckle near the middle. If using prestretched cable, you can install turnbuckles every 1000 (305m). Note: You can install more turnbuckles than the minimum amount above if conditions require this option. Some maintenance crews have successfully used turnbuckles in place of cable splices. We recommend not putting all the turnbuckles between the same two posts. They will be easier to tighten if they are staggered. If a turnbuckle becomes positioned at a post, do not install a special hook bolt at this post. This should be allowed for only one cable per post. If your maintenance crew strongly desires to place all of the turnbuckle in the same bay, the result will have no adverse effect on the crash worthiness of the system. System Splicing A splice may be used where needed. If an open faced splice is needed, use a turnbuckle instead of the standard splice. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 14
15 Prestretched Cable Option Factory prestretched cable can be used in the U.S. High-Tension Cable System; however, it is not required for the system to function as designed. If you are using factory pre-stretched cable, it is allowable to increase the distance between turnbuckles to 1000 feet. Tensioning the System The last step is setting the proper cable tension by using the turnbuckles. The cable tensioning process is a dynamic process. Regardless of the cable type (prestretched or standard) when the cable and cable attachment hardware are brought up to the appropriate tension the following process will occur: o o o o o Cable and wedges will be seated into the cable hardware for the turnbuckles, cable anchor ends, and splices. Cable can temporality hang up on hook bolts or posts creating pinch points. A pinch point is defined when there is difference is cable tension between cable bays. Over time the cable tension will over come these pinch points and be normalized over the entire run. If a pinch point is recognized it can be manually released by adjusting the hook bolt to allow the cable to freely move. Pinch points may become visually evident when a line post is out of plum or a hook bolt is bent. Over time the fact that the cable is under tension will in itself remove the construction stretch from the cable. Time under tension will also physically change the cable in a fashion similar to yield hardening. This process will occur more with standard cable then prestretched. Each of these processes will cause the cable to physically lengthen. Cable lengthening will cause the initial tension to decrease. Because these processes are dynamic it may take a number of temperature cycles/changes of season before the cables consistently hold tension. Longer runs may take more time for this process to occur than shorter runs. The use of pre-stretched cable will decrease the number of temperature cycles to get cable to hold tension, but its use will not eliminate the processes above from occurring. Vehicle impacts may aid in this stabilization process to some degree too. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 15
16 The amount of tension in the cable barrier will affect system performance. The cables should be tensioned to the values given in the Tension Table, based upon the temperature of the cable. The tension in the cables will vary with ambient temperature changes. It is best to use a cable pull to get the majority of the tension into the system. Attach the cable pull to a suitable vehicle (truck, skid steer, etc.), pull the cable taut, install the cable end, and attach to the CRP. An alternate method is to attach both cable ends to the CRPs and make the final connection at the turnbuckles. Using a hydraulic puller, tension the system, install the turnbuckle, and release the hydraulic puller. Plan to pull approx 1 per 1000 from taut to 6000 pounds tension. The final tension is achieved by tightening the turnbuckles. The tension should be checked between every turnbuckle to ensure proper tension has been met throughout system. Be sure to leave a minimum of 6 of clear throw in each turnbuckle after tensioning. Do not bottom out the turnbuckles during initial installation. If using standard (non-prestretched) cable, the initial tension on a new cable installation should be approximately 15% higher than the desired tension indicated in the temperature/tension table below, to allow for cable creep. The tension tolerance is % or up to 2500 lbs. over desired tension maximum. Most tension meters have an accuracy of about lbs. The system should be checked 2 weeks to 3 months after installation, and then periodically over the first year, especially after seasonal changes. After a significant impact it is recommended to check the tension. Also, check tension if an impact occurs close to an end terminal. If tension needs to be taken up, make sure that at least 6-12 of throw is left on the turn buckles. This may require that some length of the cable is removed. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 16
17 Cable should be removed adjacent to any of the attachment hardware (turnbuckles, cable anchors or cable splices.) The attachment hardware can be re-used. Once a cable has been in service for approximately one to two years, there is no need to use the 15% creep factor after the cable has stabilized. Tension Table Tension (Lbs Force) /4" Cable - Standard & Pre-Streatched Cable Temperature Degrees Fahrenheit (Not ambient Temp) Degrees F Initial Tension w/ 15% Expected Tension 120 4, , , , , , , , , , , , ,525 10, ,252 10, ,979 11, ,706 11,918 After one year, the system should be tensioned per the table above. When the cables are properly adjusted, the cables will maintain acceptable tension over expected temperature ranges. Tension should be checked annually as a part of a standard maintenance schedule. A Tension Log Sheet is provided in the Appendix for accurate record keeping. We recommend the contractor and DOT keep accurate, signed records of tension for any future reference. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 17
18 DELINEATION System delineation should be as shown on the US High Tension Cable standard drawing or as directed by the engineer. Adhesive delineators shall be 3M High Intensity Prismatic #3931 Reflective Sheeting. Primer shall be 3M #94 Primer. The bonding surface must be relatively clean and dry. Contaminated surfaces should be cleaned with a Isopropyl Alcohol and water mixture. Use a lintfree cloth. Substrate temperature must be above 50 degrees F for proper adhesion. #94 Primer should be shaken well before using. Apply a thin, uniform coating to the bonding surface using the minimum amount that will fully coat the surface. Allow to dry completely before applying tape. Remove backing from pressure-sensitive reflective sheeting and apply pressure by rolling or rubbing to ensure good contact. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 18
19 REPAIR & MAINTENANCE The Nucor US High-Tension System, regardless of installation method, is very easy to repair after an impact. The longitudinal elements (the cables) of the barrier will rarely need to be replaced. Visually inspect the cables, and if necessary, use cable splices to replace damaged cable. Damaged posts and hook bolts should be replaced. In the case of driven posts, the damaged posts must be removed and ground repaired before driving a new post. After a significant impact it is recommended to check the tension. Also, check tension if an impact occurs close to an end terminal. The many factors contributing to increased deflections can also lead to maintenance and performance issues. The US High-Tension System is a low-maintenance cable barrier system. Checking the tension of the cables on an annual basis, or after a severe impact, should be adequate. If impacted, a slack cable will result in increased lateral deflections. If the slack allows for a cable to become incorrectly positioned, the propensity for vehicle under-riding may increase. After all impacts, the system requires inspection and replacement or repair of damaged parts. Repeat Impacts High-Tension Cable barrier systems have shown capabilities of withstanding additional vehicular impacts on a damaged barrier. Due to the high tension, the cables typically do not fall to the ground as is the case with low-tension cable systems. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 19
20 Releasing Tension In certain circumstances, it may be necessary to release the tension in the system. Those may include the need to perform a repair, or a vehicle has become entangled. There are three common ways that you can release the tension in the system. 1. On a short run, in a non-emergency situation, the easiest method to release tension is to open several turnbuckles to their maximum length 1. This method allows the detensioning and the retensioning to be done with hand tools. 2. Using a cable grip and a vehicle of sufficient size, attach the cable grip to the longest end of the run not affected by the accident. Drive the vehicle towards the accident to release tension. You can then take out a turnbuckle or cable splice, unscrew the terminal end connector from the CRP, or cut the cable. 3. Using a ratchet come-along (note capacity 2 ) and two cable grips, pull the cable grips toward each other to release tension. Once tension is safely removed from the section of cable that you intend to repair, you can then take out a turnbuckle or cable splice, unscrew the terminal end connector from the CRP, or cut the cable. 4. In emergency situation, the CRPs can be longitudinally run over (slowly) with a truck. The CRPs will simply lay down and release the tension. The CRP posts can be reused. You will simply need to replace the two 5/16 (8mm) breakaway bolts. 1 Completely unscrewing the turnbuckle or cable anchor end, or unscrewing the cable splice at all, without first removing the tension can be unsafe. The cables will move rapidly when the threads strip out of the connection. This method is not recommended. 2 Most construction come-alongs are only 2000# capacity. Capacity of come-along and cable grip must be equal or greater to the amount of tension in system. Typically 8000# to 12,000# capacity will be needed. Cutting Cables Although it can be done, cutting cables under tension should be done with caution. It is best to first release tension in the cables by using the turnbuckles if at all possible. A vehicle becoming entrapped in the system can create a higher-than-normal tension. In an emergency, the cables CAN be cut, by using great care, with an abrasive wheel saw. Make sure no one is near the cutting point upstream or downstream. Use gloves and safety goggles and cut very carefully. Pay particular attention when there are only a few strands left, at the final stage of cutting. In worst case, use a bolt cutter with long handles. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 20
21 Overlays Cable heights are critical to performance of the system. If the roadway has experienced an overlay, ensure cable heights are correct, and that the slope to the barrier does not exceed the maximum allowed. For significant overlays, it may be necessary to install extra-height posts. Emergency Access A temporary crossover for emergency vehicles or temporary traffic control can be made at any location of the installed cable barrier by removal of the special locking hook bolts and allowing the cables to slacken. The number of posts necessary for removal depends on the tension and temperature, but normally posts will be enough. The weight of the cable will provide enough slack for passing over with vehicles. Materials for Maintenance Your distributor may carry an inventory of replacement parts for the Nucor U.S. High Tension Barrier System. However, we recommend that DOT s keep repair parts on hand for quick repair of an impacted system. A general rule of thumb is for DOTs to stock 2% to 4% of the total project, rounded up to the minimum order quantities (below). Line Posts = 50 piece bundles Small Hook Bolts = 100 pieces Large Hook Bolts = 50 pieces CRP posts = 3 pairs Turnbuckles = 3 pairs Cable Anchor Ends = 3 pieces Cable Spool = 2000 ft. Please contact your distributor for up to date quotes on products. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 21
22 INSTALLATION CHECKLISTS Cable Checklist Is there anything in front of the cable barrier that might cause a vehicle to vault the barrier or make the barrier ineffective? Items to look for include vegetation, rough ground, debris, or hard packed snow. These items should be removed if present. Has the roadside grading been completed correctly? Is there enough clearance between the barrier and the hazard for the expected barrier deflection? Minimum clearance is dependent upon post spacing. Is the cable barrier the correct height? Cable heights measured to the middle of the cable are as follows: Top Middle Bottom Median & Roadside 29.5 in 25.5 in 21.5 in [750 mm] [650 mm] [545 mm] Are the cables properly tensioned? Are there irregular curves or joints where an errant vehicle might snag? Is there evidence of corrosion or damage to the cable? The cable should be scheduled for repair if either of these circumstances exist. Check to see that nuts are installed on the special locking hook bolts. Post Checklist Is there sufficient soil behind the posts to prevent them from being pushed out when the barrier is hit? Eroded or disturbed soil should be replaced and recompacted. Is the post spacing correct? Is there evidence of corrosion or damage to the posts? The posts should be replaced if either of these circumstances exist. U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 22
23 Terminal/Anchor Checklist Is there soil erosion around the end anchor? Eroded or disturbed soil should be replaced and recompacted. Was the L-bracket installed with the CRP Posts? Did the CRP foundation move after tensioning the cable? Is the embankment depth such that no more than 4 of the base of the CRP post is exposed above ground level? U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 23
24 APPENDIX U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 24
25 Tension Log U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 25
26 Standard U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 26
27 Cable Terminal End Installation Details U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 27
28 Technical Support and Sales Contact Information Manufacturer NUCOR Steel Marion, Inc. Corporate Headquarters Steve Conway Sales Manager Highway Products Division (800) ext. 260 Mailing Address: 912 Cheney Ave. Marion, OH Manufacturer Representatives NUCOR Steel Marion, Inc. Rick Mauer National Sales Representative (603) Kevin Mally Outside Sales Representative (800) ext. 211 Mailing Address: PO Box 837 Greenland, NH Mailing Address: 912 Cheney Ave. Marion, OH Distributors Bryson Products Inc. Alabama, Georgia, Florida, Louisiana, Mississippi, South Carolina, Tennessee William Bryson (800) (610) fax GSI High Tension Cable LP Arkansas, Colorado, Kansas, Nebraska, Texas, Oklahoma, Wyoming Steve Kessler (866) (972) fax U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 28
29 TECHNICAL SUPPORT AND SALES (cont.) Highway Safety Corporation Roy Riedl (860) (860) fax Highway Supply Arizona, New Mexico Denis Ridefford (505) (505) fax John Thomas Inc. Illinois John Dvorak (888) (888) fax U.S. High Tension Cable Barrier System Revised Jan-08 V. 4.2 Page 2
SKT-SP Tangent Terminal
Assembly Instructions for SKT-SP Tangent Terminal & FLEAT-SP Flared Terminal SP Standard Post System Guardrail Terminals ROAD SYSTEMS, INC. P. O. Box 2163 Big Spring, Texas 79721 Phone: (432) 263-2435
HIGH TENSION CABLE BARRIER
Special Provision September 11, 2006 SECTION 02845 S HIGH TENSION CABLE BARRIER PART 1 GENERAL 1.1 SECTION INCLUDES A. Cable barrier materials and installation procedures. 1.2 RELATED SECTIONS A. Section
X-Tension TM Guardrail End Terminal
Installation and Maintenance Manual X-Tension TM Guardrail End Terminal Step by Step Instructions for the Tangent, Flared and Median Applications Barrier Systems Sales and Service 3333 Vaca Valley Pkwy,
HEART Product Description Assembly Manual
HEART Product Description Assembly Manual Part No. 620293B Revised February 25, 2009 2525 2525 Stemmons Stemmons Freeway Freeway Dallas, Dallas, Texas Texas 75207 75207 IMPORTANT: These These instructions
SECTION 02845 GUARDRAILS
SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein
Guidelines for Earthquake Bracing of Residential Water Heaters
Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)
AZEK Rail Install Guide
TRIM MOULDING DECK PORCH RAIL PAVERS AZEK Rail Install Guide Installing AZEK Rail with CableRail by Feeney... 1 Installing CableRail by Feeney for AZEK Rail... 7 Installing AZEK Rail Stairs with CableRail
Session 3: Guardrail Design and Sitespecific. Considerations
FHWA Roadway Departure Technology Transfer Roadside Safety Systems Installer Training : Guardrail Design and Sitespecific Installation Considerations 3-1 Course Topics Session 2 Testing Requirements and
CHAPTER 14: GUARDRAIL and BARRIERS
CHAPTER 14: GUARDRAIL and BARRIERS If you have any questions regarding guardrail, end treatments and/or pay items included in your plan, please contact the Project Design Services Unit or the Design Standards
Best Practices for Removing Vehicles from Cable Barrier for the NC Guardrail Committee
Best Practices for Removing Vehicles from Cable Barrier for the NC Guardrail Committee Since the last Committee Meeting on March 15, 2006 we have been sending out emails to the AASHTO TIG-CMB team members
Guidelines for Earthquake Bracing Residential Water Heaters
Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
RadianceRail Installation Guide
RadianceRail Installation Guide Installing RadianceRail with CableRail by Feeney... 2 Installing CableRail by Feeney for RadianceRail... 7 Installing RadianceRail Stairs with CableRail by Feeney... 10
2100 AD 015 0009 Mirror Elevator Ball Nut Replacement Procedure
2100 AD 015 0009 Mirror Elevator Ball Nut Replacement Procedure Derek Guenther 1/28/2015 Rev. Purpose The purpose of this document is to describe the procedure necessary to replace one of the ball nuts
March 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
Embedded Parts Introduction - Anchors
In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical
How To Use A Tracc Crash Cushion
TRACC Family Product Description Assembly Manual Part No. 620297B Revised January 2007 TRinity Attenuating Crash Cushion TRACC-Family System Manual - 2005 Model - TRACC FasTRACC WideTRACC ShorTRACC A Family
ENERGY ABSORPTION SYSTEMS
SRT-350 8 POST Guardrail End Treatment Assembly Manual Part No. 620296B Revised June 24, 2008 ENERGY ABSORPTION SYSTEMS SRT-350 8 POST System Guardrail End Treatment Installation, Maintenance, and Repair
16 April 2012 1032011-F 1994-2002 Dodge Adjustable Track bar with Relocation Bracket 1
16 April 2012 1032011-F 1994-2002 Dodge Adjustable Track bar with Relocation Bracket 1 BD Adjustable Track Bar w/bracket Dodge 2500-3500 4WD Models 1994-2002 Dodge 1500 4WD Model 1994-2001 P/N# 1032011-F
11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions
11 Guardrail W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use Modified Guardrail End Treatments and Transitions Footings and Anchors Impact Attenuators Measurement and Payment
TECHNICAL MEMORANDUM SUMMARY REPORT:
Texas Transportation Institute The Texas A&M University System 3135 TAMU College Station, TX 77843-3135 979-845-6375 Fax: 979-845-6107 http://tti.tamu.edu TECHNICAL MEMORANDUM Contract No.: T4541-AO Test
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
CABLE MEDIAN BARRIER
A Focus Technology of the American Association of State Highway and Transportation Officials (AASHTO) Technology Implementation Group (TIG) CABLE MEDIAN BARRIER Why Median Barriers 23,139 Road Departure
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
92-00 Civic/ 94-01 Integra/ 93-97 Del Sol/ 92-95 CRX Rear Kit Part No. 75540
92-00 Civic/ 94-01 Integra/ 93-97 Del Sol/ 92-95 CRX Rear Kit Part No. 75540 www.airliftperformance.com MN-514 (06409) NPR 4762 Please read these instructions completely before proceeding with installation
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
TABLE OF CONTENTS. I. TROUBLESHOOTING... 2 - Section 1.01: Common Problems/Solutions... 2
BAL Accu-Slide System I. Table of Contents TABLE OF CONTENTS I. TROUBLESHOOTING... 2 - Section 1.01: Common Problems/Solutions... 2 II. GETTING STARTED... 5 - Section 2.01: Tools You Will Need... 5 - Section
STORAGE SYSTEMS PUSH BACK RACK SYSTEMS. Innovative Solutions for Storage and Material Handling Systems
STORAGE SYSTEMS PUSH BACK RACK SYSTEMS Innovative Solutions for Storage and Material Handling Systems Konstant.com PUSH BACK OVERVIEW Konstant patented Push Pack rack system provides selectivity in the
Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996
CITY OF SAN JOSE BUILDING DIVISION POLICY Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 All new and replacement water heaters installed
Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.
P-5 The P-5 is hot forged from carbon steel. The formed head provis spherical seating that the Lifting Eye engages, while a disc-shaped foot is embedd in the concrete. Due to its being a forged part, the
Navico-Northstar 2kW JRC Radar Package, Scanner Cable Removal and Replacement
Navico-Northstar 2kW JRC Radar Package, Scanner Cable Removal and Replacement This work instruction describes the methods and means for which to remove and reinstall optional scanner cable configurations
UPLIFT Height Adjustable Standing Desk (T-Frame) DIRECTIONS FOR ASSEMBLY AND USE - - ALSO - - Watch our assembly video
UPLIFT Height Adjustable Standing Desk (T-Frame) DIRECTIONS FOR ASSEMBLY AND USE - - ALSO - - Watch our assembly video http://bit.ly/9ywwh! CAUTION MAKE SURE NO OBSTACLES ARE IN THE DESK S PATH AND ALL
Elo Touch Solutions Wall-mounting Kit for the 5501L IDS Touchmonitors
Installation Manual Elo Touch Solutions Wall-mounting Kit for the 5501L IDS Touchmonitors SW602206 Rev B Table of Contents Chapter 1: Safety Warning... 3 Chapter 2: Kit Contents... 4 Included in Kit...
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
Service Manual Rol-Lift
R 2000 Service Manual Rol-Lift Series: T and E Developed by Generic Parts Service This manual is intended for basic service and maintenance of the Rol-Lift pallet jack. The pallet jacks you are servicing
TRANS-05, Torque Tube Removal, Rebuilding, and Installation
TRANS-05, Torque Tube Removal, Rebuilding, and Installation Tools Metric Wrench Set Metric Socket Set Jack Stands (6 minimum) Floor Jack 8mm Cheesehead socket (also referred to as 12 point internal socket
I BEAM TRACK INSTALLATION
PDQ 0/700 FESTOON SYSTEM INSTALLATION AND MAINTENANCE INSTRUCTIONS INTRODUCTION The PDQ Festoon System was designed to run on one of three sizes of I-beams: S x., S8 x 8. and S x.. System trolleys must
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
EZ-48-3AB-125-35 Weather Station Mounting Tripod and Mast
EZ-48-3AB-125-35 Weather Station Mounting Tripod and Mast EZ-125-35M 35 Mast Extension (Optional) EZ-125-SK Stake Kit (Optional) EZ-46-3 Tar Pad Kit (Optional) EZ-GWA Guy Wire Kit (Optional) Ambient Weather
CP2 Buried Cable Pedestal Initial & Rehab Installation Instructions
Printing 3 March 2008 CP2 Buried Cable Pedestal Initial & Rehab Installation Instructions This instruction is intended for CP2 cable pedestal installations and replacements. The following tools will be
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,
E-Line and Braided Line. E-Line Open Hole wireline
E-Line and Braided Line E-Line Open Hole wireline Braided Line More strength Less feel Harder to seal Much harder to fish Braided line stronger (2800 to 3500 lb working strength, but less feel when fishing
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Working at Heights and Fall Protection
Standard Operating Procedures Working at Heights and Fall Protection Last Modified: JAN 2013 1 of 6 Working at Heights and Fall Protection I Purpose Serious accidents can result from falls. All employees
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
Team Skills Challenge Event # 1 Plant Layout Score Sheet
Team Skills Challenge Event # 1 Plant Layout Score Sheet State Name: Team Members: 1. 2. 3. 4. Placement of Plant Material 25 Deduct 5 points/plant not placed within 6 inches +/- of correct placement to
Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc.
SWP (6) FALL PROTECTION PROGRAM The following information on Fall Protection has been based around the BC OHS Regulations, standards, policies and guidelines. Prior to starting work outside of BC, the
Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.
Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION
Installation information. METTLER TOLEDO MultiRange Floor scales / Pit scales
Installation information METTLER TOLEDO MultiRange Floor scales / Pit scales KC300/KCS300 KC600/KCS600 KD600/KD1500 KE1500/KE3000 KES1500/KES3000 KG3000/KG6000 KN1500 Floor scales / Pit scales Contents
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
STORAGE, INSTALLATION AND MAINTENANCE PROCEDURES
GATE VALVE O.S. & Y 1.0 Periodic Inspections 1.1 The valve stem packing should be inspected at least monthly. If the stem packing shows signs of leakage, simply tighten the adjusting nuts to compress the
OSHA 1910.66 Remove impacted systems and components. Inspect systems prior to use.
Q: When do I remove my harness from service? A: ANSI (American National Standards Institute) A10.32-2004 states the service life of fall protection equipment manufactured of synthetic fiber shall be 5
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code
LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900
STEERING HANDLEBAR/FRONT WHEEL/ FRONT SHOCK ABSORBER
14 14 STEERING HANDLEBAR/FRONT WHEEL/ SCHEMATIC DRAWING ------------------------------------------------- 14-1 SERVICE INFORMATION------------------------------------------------ 14-2 TROUBLESHOOTING-----------------------------------------------------
Auxiliary Rams USERS MANUAL
Auxiliary Rams 2007 Chief Automotive Technologies, Inc. Chief s Limited One-Year Warranty & Liability CHIEF'S LIMITED ONE-YEAR WARRANTY & LIABILITY Chief Automotive Technologies, Inc. warrants for one
Fiberstars Lighted Laminar Flow Fountain Installation Manual
Fiberstars Lighted Laminar Flow Fountain Installation Manual 79-15037-00 REV Xx http://www.fiberstars.com Page 1 of 8 SAVE THESE DIRECTIONS! These directions are provided to ensure the proper installation
In-Track Repair of Concrete Ties. Deland Humpherys, Director Track Mtce
In-Track Repair of Concrete Ties Deland Humpherys, Director Track Mtce Concrete tie repairs: Shoulder repair process Normally the result of a derailment Lag removal and replacement process Broken lags
42U/45U 28" Wide Rack Installation & Service Guide
42U/45U 28" Wide Rack Installation & Service Guide 96-00171-005 Rev B Important Information Information in this document is subject to change without notice and does not represent a commitment on the part
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
Step-by-step instructions:
Spark plug thread repair for Ford Triton cylinder heads Step-by-step instructions: Identification Installation Verification Specifically designed and tested for 4.6L, 5.4L, and 6.8L 2 and 4 valve heads,
HYDRAULIC TABLE CART 500-LB.
HYDRAULIC TABLE CART 500-LB. OWNER S MANUAL WARNING: Read carefully and understand all MACHINE ADJUSTMENT AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic
BRAKE DRUM AND ROTOR SERVICE INFORMATION
SERVICE INFORMATION To achieve maximum drum life and optimum performance, proper brake maintenance and brake balance are essential. Consult your truck or trailer manufacturer s maintenance manual for proper
SUPERCHIPPER CASTING MAINTENANCE
INTRODUCTION By design, the Superchipper Rotor is clad in castings which wear during crushing. The castings wear at different rates depending on their location on the rotor, material feed rate, material
HAND CRIMP TOOL Specification Sheet Order No. 63819-0900
HAND CRIMP TOOL Specification Sheet Order No. 63819-0900 FEATURES TYPE 4D Œ A full cycle ratcheting hand tool ensures complete crimps Œ Ergonomic soft grip handles for comfortable crimping Œ A precision
High Tension Cable Median Barrier: A Scanning Tour Report
Civil Engineering Studies Transportation Engineering Series No. 142 Traffic Operations Lab Series No. 18 UILU-ENG-2006-2002 ISSN-0917-9191 High Tension Cable Median Barrier: A Scanning Tour Report By Juan
Summary of ET Plus Guardrail End Treatment Inspections
Summary of ET Plus Guardrail End Treatment Inspections 12/16/2015 Maine Department of Transportation Prepared by Brian Burne, Atlee Mousseau, Clark Sulloway, Doug Gayne, Ulrich Amoussou Guenou & Dale Peabody
NUCOR STEEL MARION, INC. HIGHWAY PRODUCTS Saving Money. Saving Lives.
NUCOR STEEL MARION, INC. HIGHWAY PRODUCTS Saving Money. Saving Lives. Contact us for the Nucor Steel Marion, Inc. Highway Products distributor partner serving your area. Nucor Steel Marion, Inc. Highway
INSTALLATION MANUAL UNIVERSAL TAU-II. NCHRP 350 TL-3 Redirective, Non-Gating, Crash Cushion
INSTALLATION MANUAL UNIVERSAL TAU-II NCHRP 350 TL-3 Redirective, Non-Gating, Crash Cushion INTRODUCTION STANDARD LIMITED WARRANTY Lindsay Transportation Solutions, Inc. LTS ( formerly Barrier Systems )
ETL listed for installations within 5 ft. (1.5M) of outer edge of water www.srsmith.com 79-15152-00 Rev E2 9.14 Page 1 of 10
Color Light Streams Large Laminar Installation Manual (CLSLL) Input Power: Total Power: 12V AC 5W 4008814 ETL listed for installations within 5 ft. (1.5M) of outer edge of water 79-15152-00 Rev E2 9.14
SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General
SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,
System. Stability. Security. Integrity. 150 Helical Anchor
Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair
Owner s Manual Gantry Cranes
Owner s Manual Gantry Cranes Fixed Height Gantry Crane MODEL NUMBER: SERIAL NUMBER: CAPACITY IN TONS: Telescoping Gantry Crane Bushman AvonTec 262-790-4200, 800338-7810, Fax 262-790-4200 www.bushmanavontec.com
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures
City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards
Operations and Instruction Manual Might Swivel - Part # 310273 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn
Safety.. Operations and Instruction Manual Might Swivel - Part # 310273 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn Description: Technical: Zinc plated forged heat treated steel,
LG G5 Chassis Brace Gen 5 Camaro THE MOST POWERFUL HEADERS ON THE PLANET Brought to you by LG Motorsports 972-429-1963
LG G5 Chassis Brace Gen 5 Camaro THE MOST POWERFUL HEADERS ON THE PLANET Brought to you by LG Motorsports 972-429-1963 Thank you for purchasing LG Motorsports products for your Gen 5 Camaro. Parts Inventory:
In-Ground Basketball System Owners Manual
In-Ground Basketball System Owners Manual Customer Service Center N53 W4700 South Corporate Circle Sussex, WI 53089 U.S.A. Write Model Number From Box Here: WARNING! 3 Capable Adults REQUIRED TOOLS AND
Super Slider ADJUSTABLE FROM 3.5-12 Model #HD26229
Super Slider ADJUSTABLE FROM 3.5-12 Model #HD26229 IMPORTANT!!! ALL PERSONS USING THIS EQUIPMENT MUST READ AND UNDERSTAND ALL INSTRUCTIONS. FAILURE TO DO SO MAY RESULT IN SERIOUS INJURY OR DEATH. USERS
Installation instruction CASAFLEX - Connecting piece DN 100
1 CASAFLEX - 11 10 114,3 x 4,5 3 5 2 4 1 7 6 8 12 9 Do not begin work until you have read the installation instruction carefully. 1 internal backing sleeve 2 graphite packing 3 connecting piece 4 thrust
James M. Pleasants Company
James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:
Installation PowerPoint for Grasscrete Formers
Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold
WARNING! Failure to follow these inspection procedures can cause personal injury and property damage.
GARDNER-DENVER TECHNICAL MANUAL CPTEN-136 07/03 Hoist Inspection and Maintenance Guide Inspection Record For: Hoist Model.: Hoist Serial.: WARNING! Failure to follow these inspection procedures can cause
STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13
STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 (See Supplemental Instructions for trailers with heavy duty round footplates and/or Power Leveling Systems) PHONE SUPPORT
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
PBX Series Quick Fit Connector Bimetallic Steam Traps
6262100/6 IM-P626-01 ST Issue 6 PBX Series Quick Fit Connector Bimetallic Steam Traps Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning
Set-Up Instructions. (Liner-Based System) UL LISTED. Important Read set-up instructions before assembly. Report any shortages within 72 hours
INDUSTRIAL POWER Set-Up Instructions (Liner-Based System) UL LISTED Important Read set-up instructions before assembly. Report any shortages within 72 hours Specializing in Environmental and Fire-Life
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
Assembly and Usage Instructions
Assembly and Usage Instructions A Product 5885 West Van Horn Tavern Road Columbia, MO 65203 www.caldwellshooting.com Instruction #1001667 Limited Warranty Every Caldwell product is warrantied to be free
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
Chapter 10 - Scaffolding Systems
Chapter 10 - Scaffolding Systems Contents Chapter 10 - Scaffolding Systems... 10-1 Check and Oil the Pump Jacks... 10-4 Set Pump Jack Brackets... Error! Bookmark not defined. Set Pump Jack Poles... 10-5
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything
Trillium 40 Axis Spring Tensioner Wire Replacement Instructions
Trillium 40 Axis Spring Tensioner Wire Replacement Instructions 1 Overview The objective is to replace the broken axis spring tensioner wire. This requires the following tasks: 1. Remove the seismometer
www.huskietools.com 71
www.huskietools.com 71 S-Series Hydraulic Handheld Cutters P. 75 Ratchet Cable Cutters P. 73 Low Pressure Cable Cutter P. 79 SP-Series Hydraulic Handheld Cutter Heads P. 77 Cable and Insulation Strippers
Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049
Sports and High Mast Lighting Poles 4 High Mast Lighting Poles General American LitePole offers a raising and lowering system that allows for ease of maintaining the lighting system at ground level. Ideal
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
SECTION 03300 CAST-IN-PLACE CONCRETE
SECTION 03300 PART 1 GENERAL 1.01 DESCRIPTION This section describes materials and methods for formwork, reinforcement, mixing, placement, curing and repairs of concrete, and the use of cementations materials
