INTRODUCTION OF A DIGITAL EARTHWORK CONSTRUCTION SITE
|
|
|
- Peter Tyler Cox
- 10 years ago
- Views:
Transcription
1 INTRODUCTION OF A DIGITAL EARTHWORK CONSTRUCTION SITE Kim Kirchbach 1, Dominik Steuer 2 and Fritz Gehbauer 3 ABSTRACT The concept of the digital factory has already been successfully implemented in the automotive and manufacturing industry. An adaption, following lean principles, to the construction site seems promising. Combining sensors, information technology, and approaches of Building information modeling (BIM) allows a cross-linking of construction machines and therefore offers a higher level of information transparency. This enables construction machines a faster way of discovering changes through the dynamics of the construction process (change of soil class, weather conditions, etc.). Higher transparency and reduced waste can lead not only to a higher utilization of one construction machine but also to a higher efficiency of the whole process chain by the related lean management methods. The collected information can also be used for a new and dynamic type of allocation of the construction machines based on a flexible Kanban system. An improved constructive cooperation and coordination (e.g. reduced waiting or unproductive times) ensures that potentials will be exploited and a value maximization achieved. This paper will show a theoretical model, based on expert interviews and stochastic simulations. It provides an estimation of the implementation cost and running expenses in comparison with the mentioned potential for optimization. KEYWORDS Lean Construction, IT in Lean, standardization, visual management, Last Planner System INTRODUCTION Methods like Target Value Design and the Last Planner System are well developed and tested in the construction sector (Adamu and Howell 2012, Hamzeh et al. 2008, Zimina et al. 2012). To get the maximum outcome from these methods, valid data within the process chains is needed. The complex environment of an earthwork construction site leads to a lack of valid reliable data about the whole process chain (Kirchbach et al. 2012). Therefore companies and workers on those sites are headed towards uncertain situations, which cannot be handled properly with the common Research Fellow. Karlsruhe Institute of Technology (KIT), Institute for Technology and Management in Construction, Am Fasanengarten, Geb , Karlsruhe, Germany, Phone , [email protected] Graduate Student. Karlsruhe Institute of Technology (KIT), Institute for Technology and Management in Construction, Am Fasanengarten, Geb , Karlsruhe, Germany, [email protected] Professor. Karlsruhe Institute of Technology (KIT), Institute for Technology and Management in Construction, Am Fasanengarten, Geb , Karlsruhe, Germany, Phone , [email protected] Enabling Lean with IT 791
2 Kim Kirchbach, Dominik Steuer and Fritz Gehbauer push-based project management and production planning tools. The use of the right IT-systems can change this. Computer integrated construction enables a link between the design, construction and inspection phases by using real-time process data (Jonasson et al. 2002). In the stationary industry the use of modern communication techniques, like Material Requirements Planning (MRP), Enterprise Resource Planning (ERP) or Customer Relationship Management (CRM)-Systems is standard and has long been used with great success (Brynjolfsson and Hitt 2003). As these kinds of systems are depending on constant production systems and the construction process is highly fragmented and complex in comparison (Akinsola et al. 2000). Earlier research has shown that the use of information and communication technology (ICT) on a constructions site can lead to higher Percent Plan Complete rates (PPC) (Sacks et al. 2010). With a total integrated system these effects should become more obvious not only in the stationary but also in construction industry. Thus leads to the following hypotheses: 1. Using Information and Communication Technology on an earthwork construction site fosters the usage of lean methods. 2. The investment in those technologies optimizes the costs. The chosen research methodology combines a literature analysis with several expert interviews. The figures, which are the basis for later calculations, are taken from these interviews, the German construction equipment lists (Central Federation of the German Construction Industry 2007) and the German Federal Statistical Office (Federal Statistical Office 2010, Federal Statistical Office 2012). The figures are also supported by stochastic simulations. This paper presents an approach, which combines BIM, machine control technology and mobile devices to become an integrated production planning tool. In the following paragraphs the technologies for this approach are introduced. The expected costs are presented and the connection between technology and lean methods is built. BIM BUILDING INFORMATION MODEL BIM is the basis for new construction capabilities and changes in the roles and relationships among a project team. When implemented appropriately, BIM facilitates a more integrated design and construction process that results in better quality buildings at lower cost and reduced project duration. (Eastman et al. 2008) To achieve these aims, BIM combines 3D building models with time, cost, and quality schedules also known as 6D models. Even though the management method of lean thinking and the information technology of BIM can be seen separately it seems to be more efficient to use BIM in conjunction with integrated project delivery (IPD) (Eckblad et al. 2007). The use of BIM or so called computer advanced visualization tools has led projects to waste reduction, improved working flow and a more customer centred value generation; all of them are used to be mentioned in the application of lean thinking (Fernández-Solís and Mutis 2009). Despite that, the main issue in which BIM does not fit into the lean construction site is the huge amount of information, which is carried around while creating and using it. Having this huge amount of data at hand might lead to higher complexity and to more difficulties in the process of decision making (Sacks et al. 2010). So far the impact of this data 792 Proceedings IGLC-21, July 2013 Fortaleza, Brazil
3 Introduction of a digital earthwork construction site complexity on the success of the construction site has to be proved and until then as much (helpful) data as possible is required. To investigate in this matter, interviews with an international active construction company have been held. Their experience shows that the use of BIM could and should lead to the standardization of planning processes, providing a potential up to 20% time savings during the planning phase. Despite the fact that whole projects are not as easy to standardize, the efforts made in the planning phase are a success as they lead to a reliable model, which could later be used for visual construction site simulation. So in regards to the main concept of lean, the production process could be simultaneously designed to the building itself. This offers the opportunity of spotting possible interruption before the first machine started on the site therefore the alteration in the project could be done at a lower level of changing costs. The costs for implementing a BIM system to a company on the other hand are difficult to measure, because it is more of a process and not a radical change. Today only a few projects were consequently planned and executed with BIM, mostly high complex buildings like hospitals are planned this way (Lostuvali et al. 2012). According to interviewed experts, producing and working with BIM software, their first experiences with BIM are very promising and they plan its further use. In terms of costs the experts mention that the use of BIM software is a process of at least one and a half years with constant training plus the costs for the software. MACHINE CONTROL AND FLEET MANAGEMENT TOOLS Since the 1990s construction machines like excavators, graders and dozers can be equipped with different machine controls (Stempfhuber 2006). These control techniques link the machines to 3D digital terrain models through which for example the machine operator can see the working progress in real-time on a screen in his machine. This helps to reduce overwork and waste because the operator is fully aware of his task by the visualization (Jonasson et al. 2002). Studies have shown that by using this kind of control there is an increase in efficiency between 20-30% per machine (Adhalsteinsson 2008). These numbers can be confirmed by interviews with sensors developers regarding their trainings measures. Its results in the delivery of better quality due to more accurately excavated or graded terrains and higher productivity. Nowadays most of the large construction companies are using this technology for selected machines, especially when precise surface grades are needed. To implement the digital earthwork construction site it is necessary to equip all machines used on the site with several sensors: GPS-sensors with increased accuracy (supported by tachymeter and laser scanning) and additional sensors to collect e.g. the exact position and orientation of the excavator bucket or the dozer blade and technical data like maintenance intervals, amount of diesel or engine oil pressure. It does need to be analysed whether all machines are to be equipped with the whole sensor system or if in some cases of earthwork it is enough to just make the machines trackable. In any case the sensor equipment is necessary to collect and use data, making a continuous improvement process possible. According to interviews with experts, developers and producers of those sensors, the technology is ready for use but the market penetration is low. One reason for this are the equipment costs which vary between 35,000 and 60,000 depending on machine type and producer. The costs related to repair and maintenance of the sensors are negligibly small. In context Enabling Lean with IT 793
4 Kim Kirchbach, Dominik Steuer and Fritz Gehbauer of lean thinking and the comparison to the digital factory, these technologies can be used to improve the overall process chain of an earthwork construction site. MOBILE DEVICES AND CONSTRUCTION CONTROL CENTER It has already been recognized that the use of mobile devices provides the opportunity for improving the information flow at construction sites (Bowden et al. 2006). Also Augmented Reality, a human-computer interface which combines the real world with context-sensitive information presented by virtual overlays, has been recommended (Shin and Dunston 2008). The use of these techniques can play an important role in the field of Visual Management (Tezel et al. 2009) leading to a higher level of transparency. (Kirchbach and Runde 2012) As described in Kirchbach et al. (2012) a construction site control center, based on the methods of Virtual and Augmented Reality, can be the foundation for optimized construction site logistics especially to adjust truck disposal. The easy visualization reduces the mental load of the user and allows a faster detection of root causes for errors to induce a continuous process improvement system. COMBINING TECHNOLOGIES TO ENABLE LEAN MANAGEMENT By using BIM software a construction model is planned. This model contains all necessary information such as geometric data and process models, enabling the development of the product and the production process simultaneously. Simulation tools and the earlier described Augmented and Virtual Reality technologies allow the visualization of the construction site. It now also becomes possible to detect clashes before the first construction machine has even started its work on the site. This has the effect that the correction of bad planning becomes much cheaper. A communication platform enables a construction site wide information exchange, especially between the machine teams, leading to a digital earthwork construction site (compare figure 1 and (Kirchbach et al. 2012)). As presented in figure 1 the project manager has got the opportunity to get real-time and target-actual comparison of the construction process in the presentation layer. This is based on a logical layer, which combines the BIM model via a communication platform with the machines and their (performance) data. Additionally the data layer offers supporting information, like empirical values throughout the project and older projects. The machine teams have the possibility to partly organize themselves, providing that disturbances can be handled and maybe even solved on the machine level before they are passed on to the control center and thus to the project manager. For example a typical disturbance can be an unexpected change of the soil class, leading to a change in the performance of an excavator so that more or less transport vehicles are needed. In case that the machine teams cannot handle a problem themselves, suggestions for process adjustments are generated automatically and presented to the site manager in the control center. These suggestions are the result of the simulation of possible new schedules, based on the planning model and other information like machine data from die project databases. The complete system with the communication platform can then dynamically allocate the best possible match of excavator and transport vehicles using a Kanbanlike system, where excavators pull empty trucks and dozers pull loaded truck. After dumping an empty truck will be pulled by an excavator. If more than one excavator 794 Proceedings IGLC-21, July 2013 Fortaleza, Brazil
5 Introduction of a digital earthwork construction site requests a truck, the systems analyses the current performance of the excavators, their current allocated trucks and the distances to be travelled and prioritize the Kanban cards in order to optimize the productivity of the whole construction site. Same applies to loaded trucks by dozers but additional in consideration of the loaded material. Another benefit is the continuous flow and availability of information. The complete system provides high data transparency and therefore the opportunity to make reliable decisions based on actual performance data. This assured data basis relieves the construction manager leading to an expected increase in efficiency. By this reasoning and the previous sections, on the basis of interviews and a literature review, the first hypothesis, information technology fostering the usage of lean methods, can be preliminary considered as validated. Figure 1: Combination of BIM, machine sensors and visualization tools COMPARISON OF DIGITAL CONSTRUCTION AND TRADITIONAL SITE Return on invest is the crucial measure for the construction industry when investing in such a technology. The following paragraph compares the production performance of a simple earthwork process regarding differences in lead times and machine costs. In Table 1, a middle-sized excavator with 160 kw motor power and 26,800 kg weight is being taken as the use case. To get a reliable performance comparison the applicable indicator has to be used which in this case is the performance per hour; it is also used to spot bottlenecks in a process chain. The following assumptions are based on German construction equipment lists (Central Federation of the German Construction Industry 2007). Regarding this list the excavator described has a total provision of 65 months and Enabling Lean with IT 795
6 Kim Kirchbach, Dominik Steuer and Fritz Gehbauer every month has 170 hours of provision. These hours include downtimes, moving time, repair time and operating time, basically the amount of time when the machine cannot be used elsewhere (Girmscheid 2010). To spot the impact of the system, described in this paper, it must be differentiated between machines without sensors or with sensors and machines, which are used in a completely connected environment. Table 2: Costs for a medium size excavator Acquisition costs in Euro Without sensors With sensors Complete system Machine 245, , ,500 Sensors 45,000 45,000 Communication platform 4,000 Total 245, , ,500 Table 2 derives the cost per cubic meter of excavated soil from cost per hours and compares them in the above described use cases to identify the needed increase in performance. It is being assumed that the new technology needs to have at least the same price per cubic meter. So the information given in table 2 regard the needed performance per hour marks the break-even point. Table 3: Costs per hour and needed performance per hour Without sensors With sensors Complete system Cost per hour Cost per cbm Needed Performance 40.80cbm 48.27cbm 48.93cbm per hour Needed increase in Performance % 1.7% The calculations revealed that a productivity increase of 18.3 % from non-equipped machines to sensor-equipped machines is necessary and the additional performance increase to use the complete system is at 1.7 %. Researchers at the Reykjavik University found that, using a simple trench construction work, the excavator saved % of time (Adhalsteinsson 2008), which shows that the increase in productivity from non-sensors to sensor-equipped machines is very realistic. It also means less working hours, leading to lower running costs. This technology enables a company to reduce provision time and the machine is available for other projects much faster. Another important aspect is the expected increase in quality: the formation levels and grades show lower deviations from the plan (Sturm and Vos 2008). That consequently results in more stability and steadiness in the process chains; key features for making lean processes possible. The next step from sensor-equipped to connected machines influences the complete process chains and allows an iterative adaption to current conditions. Performed stochastic simulations of dynamic construction machine allocation on construction sites, using the monte-carlo method (Marczyk 1999), are very promising and show improvements of more than 4 % in total working hours and reduction in 796 Proceedings IGLC-21, July 2013 Fortaleza, Brazil
7 Introduction of a digital earthwork construction site waiting times up to 80 %. Implementations of the pull principle and Kanban systems in similar use cases, for example the allocation of trucks to a road paver in road construction, achieved a reduction of truck idle times of 86 % and an increased productivity of 66 % (Kaiser and Zikas 2009). Comparing these numbers to the results of the stochastic simulations, the simulations results seem realistic. The already reached improvement rates in the industrial production through the implementation of lean principles give reason to presume that it could even lead to far higher improvement rates. Not mentioned yet are the costs for implementing the BIM software but regarding Young et al. (2007) a return on investment-rate between 100 and 1000 % is possible. The purchase and use of BIM software is clearly profitable; here it is only being looked at the investments on BIM software regarding the construction machines and their needed performance increase. Taking average prices for modern CAD technology and costs for employee training, small and medium-sized businesses (number of employees ), which take a market share of 44.2 % in the German civil engineering construction market (Federal Statistical Office 2012), are facing costs below 250,000. Taking costs given by software producers and the price for modern standard CAD software, a more precise calculation cannot be given so far. In Germany the amortization period for software is 5 years (Federal Ministry of Finance 2005); depending on the fleet, 60,000 have to be added yearly to the machine costs. In case the constructing company has to create the models itself, the size of the construction machine fleet needs to be estimated. German construction companies have an amortization rate of 2.7 % from their annual turnover (Federal Statistical Office 2010). Divided by the number of companies, there is a yearly depreciation of 755,000 for each company. It needs to be considered that the depreciation time for machines differs from the software as the excavator described above has an amortization period of 8 years. To show the benefits of the defined system the calculation has been simplified and 25 machines are being used for the described company and machine type, even though the real market varies in amount and type of machines. Interviews show that the interest in BIM technology is mainly driven by the planning team so that in case of system compatibility the executive company will receive the already created model from the planners and only needs to get a proper interface, which means there is no need to buy the full BIM software. Law and payment issues have to be considered handing over and using the model. The following table 3 is depicting a full cost scenario to cover the highest possible financial burden for a company. Combining the results from table 2 and 3 the amount of 1.45 per hour needs to be added (to the complete system), based on the circumstance that the planning team has got a lack of useful models and the executing company therefore needs to buy the whole BIM software. As a result the hourly machine costs amount to and the desired performance to m³ per hour, which means that, compared to the sensor equipped machines, an efficiency increase of 7.8 % is needed. That leads to a discrepancy between needed performance increase and simulated performance increase of 3.8 %. A possible explanation for this are the uncertainties regarding the amount of 25 machines used, which seems to be low for a company employing around 300 people. Therefore this is considered a lower bound. Enabling Lean with IT 797
8 Kim Kirchbach, Dominik Steuer and Fritz Gehbauer A calculation with 77 machines leads to 0.47 additional costs per hour instead of 1.45, this implicates overall costs of per hour and a needed performance of m³/hour. Compared to the sensor equipped machines the needed performance increase is 4 %, which puts the needed performance increase and the costs for the technology to an equal, marking the break-even point. Table 3: Costs for integrated Software solution Average turnover 27,975,000 company employees Average depreciation 2.7% 755,000 Acquisition costs machine 245,500 Amount machines 25 Yearly machine hours 1381,25 Yearly cost of software 50,000 Additional Cost per machine hour 1.45 The calculations in this paper are only laid out for an excavator as it is often the bottleneck on the construction site. Its work cycle is the most difficult to optimize and control. Mapping the whole process chain of excavator, transportation vehicles and graders or dozers does promise much more potential for optimization, which also indicates that this result counts as a lower bound. Research on a road construction site has shown that by the use of machine sensors the cooperation of dozers and graders gains a performance increase of 101 % (Caterpillar Inc. 2006). It has not been possible yet to verify the second hypothesis due to missing data, but there are indications to its truthfulness. The increase of performance seems a bit low compared to other Kanban and machine sensor implementations. Also economies of scale should be regarded. This leads to further research questions: Which performance increase can really be achieved? How does a construction site have to be structured or which specific boundary conditions of different types of construction sites promote additionally the use of this system? CONCLUSION This paper shows the opportunities of an integrated IT-system to the earthwork construction site. Its use fosters the lean principles in terms of a global view at the construction site, the reduction of waste, in terms of waiting times and needed rework, and a higher level of transparency. The system also allows an easier quantification of the work processes, which enables the implementation of a continuous cycle of improvement. Using actual figures, the paper demonstrates that the combination of machine sensors, a communication platform and visualization technology promises higher work efficiency and costs for implementing the system can be covered even regarding the most expensive construction machine (sensor to machine cost ratio), the excavator. The already existing increases in productivity for graders and dozers show the necessity for companies to invest in this new technology. Further research is essential to picture the whole impact of this new approach. Effects like fuel savings, personnel savings or the savings in construction material could not be shown in this paper. It is expected that the productivity will show far 798 Proceedings IGLC-21, July 2013 Fortaleza, Brazil
9 Introduction of a digital earthwork construction site more increase if those savings are included as well. Also the overall impact of enabling lean methods needs to be quantified by field tests. First test runs of such a system are conducted in spring REFERENCES Adamu, I. and Howell, G. (2012). Applying Last Planner in the Nigerian Construction Industry. Proceedings of the 20 th Conference of the International Group for Lean Construction, San Diego, California, USA, Adhalsteinsson, D.H. (2008). GPS machine guidance in construction equipment, Final Project BSc. University of Reykjavik, Island. Akinsola, A, Dawood, N. and Hobbs, B. (2000). Construction planning process improvement using information technology tools.cib W078 International Conference: Construction Information Technology 2000 Bowden, S., Dorr, A., Thorpe, T., and Anumba, C. (2006). Mobile ict support for construction process improvement. Automation in Construction, 15(5): Brynjolfsson, E. and Hitt, L.M. (2003) Computing Productivity: Firm-Level Evidence. MIT Sloan Working Paper No Caterpillar Inc. (2006). Road Construction Production Study. Central Federation of the German Construction Industry. (2007). Baugeräteliste 2007 (Technical and Economic Construction Machinery Data), Bauverlag Bv Gmbh, Berlin, Germany. Eastman, C., Teicholz, P., Sacks, R. and Liston, K. (2008). BIM handbook: a guide to building information modeling for owners, managers, designers, engineers, and contractors John Wiley and Sons. Eckblad, S., Bedrick, J. and Rubel, Z. (2007). The Possibilites of an Integrated Approach. Presentation to the AIA California Council Change Conference, June 25-26, San Francisco, USA. Federal Ministry of Finance. (2005). Bilanzsteuerrechtliche Beurteilung von Aufwendungen zur Einführung eines betriebswirtschaftlichen Softwaresystems (ERP-Software) (Fiscal assessment of expenses to the introduction of business software systems (ERP-software)), Official letter of the ministry, 17th October 2005, IV B 2, S 2172, 34/05, Germany. Federal Statistical Office. (2010). Kostenstruktur der Unternehmen im Baugewerbe (cost structure of companies in the construction industry), Fachserie 4, Reihe 5.3, Germany. Federal Statistical Office. (2012). Tätige Personen und Umsatz der Betriebe im Baugewerbe (Employed persons and turnovers of companies in the construction industry), Fachserie 4, Reihe 5.1, Germany. Fernández-Solís, J. L. and Mutis, I. (2009). The Idealization of an Integrated BIM, Lean, and Green Model (BLG). In: Underwood, J. and Isikdag, U. Handbook of Research on Building Information Modeling and Construction Informatics: Concepts and Technologies, pages Girmscheid, G. (2010). Leistungsermittlungshandbuch für Baumaschinen und Bauprozesse (Manual for the determination of performance for construction machines and processes). Springer Berlin Heidelberg. Hamzeh, F.R., Ballard, G. and Tommelein, I.D. (2008). Improving Construction Work Flow - The Connective Role of Lookahead Planning. Proceedings Enabling Lean with IT 799
10 Kim Kirchbach, Dominik Steuer and Fritz Gehbauer Sixteenth Annual Conference of the International Group for Lean Construction, IGLC-16, Manchester, United Kingdom, pages Jonasson, S., Dunston, P., Ahmed, K. and Hamilton, J. (2002). Factors in Productivity and Unit Cost for Advanced Machine Guidance. Journal of Construction Engineering and Management, 128(5), Kaiser; J. and Zikas, T. (2009). Lean Management in Road and Underground Construction. BauPortal, 121(5) , May Kirchbach, K., Bregenhorn, T. and Gehbauer, F. (2012). Digital Allocation of Production Factors in Earth Work Construction. Proceedings of the 20th Conference of the International Group for Lean Construction, San Diego, California, USA, Kirchbach, K. and Runde, C. (2012). Augmented Reality for Construction Control, Proceedings of the 16th International Conference on Information Visualization, Montpellier, France, pages Lostuvali, B., Alves, T.d.C.L and Modrich, R.-W. (2012). Lean Product Development at Cathedral Hill Hospital Project. Proceedings of the 20 th Conference of the International Group for Lean Construction, San Diego, California, USA, Marczyk, J. (1999). Principles of Simulation-Based Computer-Aided Engineering. FIM Publications. Sacks, R., Koskela, L., Dave, B., and Owen, R. (2010). Interaction of Lean and Building Information Modeling in Construction. Journal of Construction Engineering and Management, 136(9), Shin, D. H. und Dunston, P.S. (2008). Identification of application areas for augmented reality in industrial construction based on technology suitability. Automation in Construction, 17(7): Stempfhuber, W. (2006). 1D and 3D Systems in Machine Automation, FIG 3rd IAG / 12th FIG Symposium, Baden, Germany. Sturm, A. and Vos W. (2008). New Technologies for Telematics and Machine Control- Proceedings 1st International Conference on Machine Control & Guidance, Zurich, Switzerland. Tezel, A., Koskela, L., and Tzortzopoulos, P. (2009). Visual management - a general overview, 5th International Conference on Construction in the 21st Century (CITC-V), Istanbul, Turkey. Young, N.W., Jones, S. A., Bernstein, H. M. (2007). Interoperability in the Construction Industry. SmartMarket Report. McGraw Hill Construction. Zimina, D., Ballard, G. and Pasquire, C. (2012). Target value design: using collaboration and a lean approach to reduce construction cost. Construction Management & Economics, Taylor and Francis Journals, 30 (5) Proceedings IGLC-21, July 2013 Fortaleza, Brazil
How To Implement Lean And Bim On An Infrastructure Project
CHALLENGES AND OPPORTUNITIES IN IMPLEMENTING LEAN AND BIM ON AN INFRASTRUCTURE PROJECT Bhargav Dave 1, Stefan Boddy 2 and Lauri Koskela 3 ABSTRACT: It has been realised through research and practice that
EGLC Conference 2015. Incentive System to Support Collaboration in Public Construction Projects
EGLC Conference 2015 Incentive System to Support Collaboration in Public Construction Projects Annett Schöttle 19. March 2015 INSTITUTE FOR TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, DEPARTMENT OF CIVIL
Synergy: Building Information Modeling and
: Building Information Modeling and Assoc. Professor Rafael Sacks BIM Handbook Symposium Georgia Tech Atlanta, GA, 13 th March 2008 Introduction Both and BIM are deep process changes, in thinking and in
Road Construction. Production Study. AccuGrade GPS & ATS Systems. MALAGA Demonstration & Learning Center
AccuGrade GPS & ATS Systems Road Construction Production Study MALAGA Demonstration & Learning Center December 2006 2 TABLE OF CONTENTS ABSTRACT... 4 1 INTRODUCTION... 5 PERSONNEL... 6 EQUIPMENT... 6 2
Leica MC200 Digger The guidance solution for excavators. >Fast >Accurate >Flexible
Leica MC200 Digger The guidance solution for excavators >Fast >Accurate >Flexible MC200 Digger Solution MC200 Digger provides excavator operators with real-time depth, slope and reach information, in relation
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS Antonio Sergio Itri Conte 1 ABSTRACT The paper describes the experience of a civil engineering company of a small town in São Paulo State
APPLICATION OF ADVANCED SEARCH- METHODS FOR AUTOMOTIVE DATA-BUS SYSTEM SIGNAL INTEGRITY OPTIMIZATION
APPLICATION OF ADVANCED SEARCH- METHODS FOR AUTOMOTIVE DATA-BUS SYSTEM SIGNAL INTEGRITY OPTIMIZATION Harald Günther 1, Stephan Frei 1, Thomas Wenzel, Wolfgang Mickisch 1 Technische Universität Dortmund,
REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN
212 REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN ABSTRACT Sangwoo Cho 1 and Martin Fischer 2 Supply chain management in construction has evolved in response to various
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2 Hyun Cho 1, Ki Hwan Lee 1, Song Hyon Lee 1, Ta Lee 1, Hyun Jun Cho 1, Sung Hoon Kim 2 and
A PRODUCTION PLANNING SUPPORT SYSTEM FOR CONSTRUCTION PROJECTS
A PRODUCTION PLANNING SUPPORT SYSTEM FOR CONSTRUCTION PROJECTS Luis F. Alarcón 1 and Rodrigo Calderón 2 ABSTRACT This paper describes a computer system developed by the Production Management Center of
A Guide to Resolving Key Mobile Workforce Challenges in the oil and gas sector
A Guide to Resolving Key Mobile Workforce Challenges in the oil and gas sector Managing a mobile workforce in the Oil and Gas industry is not easy. Whether it is liquid transportation, pipeline and facility
Model based quality assurance process in a infra construction. Case Riippa-Eskola RU2 double rail project
Model based quality assurance process in a infra construction project Case Riippa-Eskola RU2 double rail project M. Jaakkola a and P. Toppi a a Destia Ltd, Development of Infra construction, Finland E-mail:
A HYBRID GROUND DATA MODEL TO SUPPORT INTERACTION IN MECHANIZED TUNNELING
A HYBRID GROUND DATA MODEL TO SUPPORT INTERACTION IN MECHANIZED TUNNELING F. HEGEMANN P. MANICKAM K. LEHNER M. KÖNIG D. HARTMANN Department of Civil and Environmental Engineering, Ruhr-University of Bochum,44780
THE OOPS GAME: HOW MUCH PLANNING IS ENGOUGH?
THE OOPS GAME: HOW MUCH PLANNING IS ENGOUGH? ABSTRACT Gregory Howell 1 & Min Liu 2 The future is unknown and unknowable. In the face of this reality, planning tries to assure an outcome certain. The Oops
Construction Equipment Fleet Management
International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) Construction Equipment Fleet Management Sujay Dandwate *(Civil Engineering Department, D.Y.Patil College of Engineering, Akurdi,
Adaptive demand planning in a volatile business environment
2012 International Conference on Economics, Business and Marketing Management IPEDR vol.29 (2012) (2012) IACSIT Press, Singapore Adaptive demand planning in a volatile business environment Romana Traxler
CONSTRUCTION TECHNOLOGY FOR HEAVY AND HIGHWAY CONTRACTORS
CONSTRUCTION TECHNOLOGY FOR HEAVY AND HIGHWAY CONTRACTORS THE CONNECTED JOBSITE. YOUR PRODUCTIVITY MAXIMIZED. SITE POSITIONING SYSTEMS Developed specifically for the needs of heavy and highway contractors,
INTERACTIVE VISUAL LEAN SYSTEM FOR RESOURCE PLANNING OF EARTHWORK OPERATIONS
652 INTERACTIVE VISUAL LEAN SYSTEM FOR RESOURCE PLANNING OF EARTHWORK OPERATIONS Nashwan Dawood 1, Rajiv Chavada 2, Claudio Benghi 3 and Romeu Sanches 4 ABSTRACT Poor resource planning and low productivities
Feasibility Analysis of Initiating Building Information Modeling (BIM) for HVAC systems by General Contractors
Feasibility Analysis of Initiating Building Information Modeling (BIM) for HVAC systems by General Contractors Hussein Abaza, Ph.D. Southern Polytechnic State University, 1100 South Marietta Parkway, Marietta
Automated construction schedule creation using project information model
Automated construction schedule creation using project information model Aleš Mrkela Faculty of civil engineering, University of Maribor, Maribor, Slovenia Danijel Rebolj Faculty of civil engineering,
THE INTELLIGENT CONTAINER - AN ESTIMATION OF BENEFITS AND COSTS
THE INTELLIGENT CONTAINER - AN ESTIMATION OF BENEFITS AND COSTS Marius Veigt, Patrick Dittmer, Rasmus Haass, Franziska Wittig BIBA - Bremer Institut für Produktion und Logistik GmbH Hochschulring 20 28359
Fleet Optimization with IBM Maximo for Transportation
Efficiencies, savings and new opportunities for fleet Fleet Optimization with IBM Maximo for Transportation Highlights Integrates IBM Maximo for Transportation with IBM Fleet Optimization solutions Offers
TRIMBLE ATS TOTAL STATION ADVANCED TRACKING SYSTEMS FOR HIGH-PRECISION CONSTRUCTION APPLICATIONS
TRIMBLE ATS TOTAL STATION ADVANCED TRACKING SYSTEMS FOR HIGH-PRECISION CONSTRUCTION APPLICATIONS BY MARTIN WAGENER APPLICATIONS ENGINEER, TRIMBLE EUROPE OVERVIEW Today s construction industry demands more
Efficiency Through Information. CONSTRUCTION Equipment AND
Efficiency Through Information CONSTRUCTION Equipment AND ASSET MANAGEMENT SOLUTIONS A Complete Solution for the Construction Industry Trimble Construction Manager software One Solution for Managing All
European truck aftersales 2030
European truck aftersales 2030 Securing the most profitable business Study Munich, December 2015 Management summary Why react? Pressure points within the aftermarket environment for OEMs What to do? OEMs
SOCIAL NETWORK ANALYSIS OF INFORMATION FLOW IN AN IPD-PROJECT DESIGN ORGANIZATION
SOCIAL NETWORK ANALYSIS OF INFORMATION FLOW IN AN IPD-PROJECT DESIGN ORGANIZATION Gernot Hickethier 1, Iris D. Tommelein 2 and Baris Lostuvali 3 ABSTRACT Lean Construction recommends concurrent development
Understanding Manufacturing Execution Systems (MES)
Understanding Manufacturing Execution Systems (MES) Presented by: Shirley Schmidt Freedom Technologies 10370 Citation Dr., Suite 200 Brighton, MI 48116 Phone: 810-227-3737 www.freedomcorp.com What is a
LEET CAT MINESTAR SYSTEM INTEGRATED FLEET MONITORING & MANAGEMENT FOR MINING
CAT LEET MINESTAR SYSTEM INTEGRATED FLEET MONITORING & MANAGEMENT FOR MINING FLEET TRACK, MANAGE AND ASSIGN ALL TYPES OF EQUIPMENT With real-time machine tracking, assignment and productivity management,
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
How To Use Leica Dozernav Plus
Leica DozerNav Plus High precision GPS dozer guidance More than a guidance system Leica DozerNav Plus > helping you drive productivity with ease Leica DozerNav Plus the benefits at a glance Real-time feedback
Consulting. Planning. Managing.
Consulting. Planning. Managing. Your wishes meet our solutions Consulting Corporate success attaining goals through competence Dürr is a world leader in the construction and supply of plant and machinery.
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Last Planner in Lean Construction
BIM Pilot Getting Started Guide. For Construction Professionals. next
BIM Pilot Getting Started Guide For Construction Professionals Moving to BIM can seem like a daunting task. This guide provides a simple framework that helps you get started putting BIM into practice in
ON-SITE LOGISTICS SIMULATION IN EARLY PLANNING PHASES
ON-SITE LOGISTICS SIMULATION IN EARLY PLANNING PHASES Markus König Ruhr-University Bochum [email protected] Ilka Habenicht SimPlan AG [email protected] Sven Spieckermann SimPlan AG [email protected]
QUICK GUIDE. Resolving Key Mobile Workforce Challenges. in the Oil and Gas Sector. Resolving Key Mobile Workforce Challenges in the Oil and Gas Sector
QUICK GUIDE Resolving Key Mobile Workforce Challenges in the Oil and Gas Sector 1 Resolving Key Mobile Workforce Challenges Managing a mobile workforce in the Oil and Gas industry is not easy. Whether
The 8th International Conference on e-business (inceb2009) October 28th-30th, 2009
A STUDY ON THE REQUIREMENTS AND TOOLS FOR REAL TIME FLEET MANAGEMENT E-BUSINESS SYSTEMS IN THAILAND Sirilak Borirug 1, Chun Che Fung 2, Wudhijaya Philuek 3 School of Information Technology, Murdoch University
Construction Economics & Finance. Module 4 Lecture-1
Construction Economics & Finance Module 4 Lecture-1 Equipment costs:- For construction firms, it is important to accurately estimate the equipment cost as part of the total cost of the construction project.
Leica icon grade Intelligent grading systems NEW. igd4 SP System. i n telligent COnstruction
Leica icon grade Intelligent grading systems NEW igd4 SP System i n telligent COnstruction Leica icon grade Maximize productivity, speed & flexibility The Leica icon grade solutions can revolutionize your
Construction Equipment Fleet Management: Case Study of Highway Construction Project
Construction Equipment Fleet Management: Study of Highway Construction Project 1 Saurabh Rajendra Kadam, 2 Prof. Dhananjay S Patil 1 P.G.Scholar, Department of Civil Engineering, Rajarambapu Institute
RisqLabs ICRM: Integrated Currency Risk Management
RisqLabs ICRM: Integrated Currency Risk Management Case Study Teramark Technologies GmbH, 2014 ICRM Case Study 1 :: 12 The customer Shipping company N.N is one of the three biggest shipping companies worldwide.
OPTIMIZING FLEET MAINTENANCE WITH WIRELESS VEHICLE MANAGEMENT
OPTIMIZING FLEET MAINTENANCE WITH WIRELESS VEHICLE MANAGEMENT Table of Contents 3 3 3 4 8 Overview Reduced Vehicle Maintenance Costs Monitoring Engine Performance with Networkfleet Vehicle Management System
Optimizing Supply Chains for Improved Performance
Optimizing Supply Chains for Improved Performance In Nigeria, a transport optimization analysis provided critical input into the design of a new vendor managed inventory distribution system. Here, workers
integrated operational management
VISIONLINK integrated operational management The VisionLink fleet, asset and site productivity management solution from Trimble tells you where your equipment is, what it's doing and how it's performing.
Construction automation and productivity - Industry perspective
Construction automation and productivity - Industry perspective Vice President R&D, Ilkka Romo Skanska Oy 22.1.2013 1 22.1.2013 Ilkka Romo Skanska in short One of the world s leading companies in construction
Trackunit Telematics Solution. for OEM
Trackunit Telematics Solution for OEM Trackunit Telematics is an indispensable tool for improving your business through a deeper understanding of machine usage and customer behaviour. It enables you to
QUEST The Systems Integration, Process Flow Design and Visualization Solution
Resource Modeling & Simulation DELMIA QUEST The Systems Integration, Process Flow Design and Visualization Solution DELMIA QUEST The Systems Integration, Process Flow Design and Visualization Solution
MDM AS A PROCESS MAPPING TOOL IN LEAN CONSTRUCTION
12 TH INTERNATIONAL DEPENDENCY AND STRUCTURE MODELLING CONFERENCE, DSM 10 22 23 JULY 2010, CAMBRIDGE, UK MDM AS A PROCESS MAPPING TOOL IN LEAN CONSTRUCTION Fabian Furtmeier 1, Martin Graebsch 1, Fatos
QUICK GUIDE. How to Use GPS to Improve Fleet Utilization. How to Use GPS to Improve Fleet Utilization
QUICK GUIDE How to Use GPS to Improve Fleet Utilization 1 How to Use GPS to Improve Fleet Utilization One of the key functions for fleet managers is to ensure their fleet has the right mix of equipment
Inventory Management in Small and Medium-Sized Manufacturing Companies and Its Main Dilemmas
Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 9, 2014 Inventory Management in Small and Medium-Sized Manufacturing Companies
OPTIMIZING FLEET MAINTENANCE WITH WIRELESS VEHICLE MANAGEMENT
OPTIMIZING FLEET MAINTENANCE WITH WIRELESS VEHICLE MANAGEMENT Table of Contents 3 Overview 3 Reduced Vehicle Maintenance Costs 3 Monitoring Engine Performance with Networkfleet Vehicle Management system
29082012_WF_reporting_bro_UK. www.tomtom.com/telematics
29082012_WF_reporting_bro_UK www.tomtom.com/telematics T E L E M AT I C S WEBFLEET Reporting Let s drive business WEBFLEET Reporting Difficult business decisions are much more straightforward with TomTom
Agile Project Portfolio Management
C an Do GmbH Implerstr. 36 81371 Munich, Germany AGILE PROJECT PORTFOLIO MANAGEMENT Virtual business worlds with modern simulation software In view of the ever increasing, rapid changes of conditions,
Construction Planning, Equipment, and Methods
CHAPTER Construction Planning, Equipment, and Methods EQUIPMENT COST Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 3a By Dr. Ibrahim Assakkaf ENCE 420
Data Analysis Methods for Library Marketing in Order to Provide Advanced Patron Services
Data Analysis Methods for Library Marketing in Order to Provide Advanced Patron Services Toshiro Minami 1,2 and Eunja Kim 3 1 Kyushu Institute of Information Sciences, 6-3-1 Saifu, Dazaifu, Fukuoka 818-0117
Fleet Management Best Practices for Equipment Distributors
www.equip-soft.com > Resources > White Papers Fleet Management Best Practices for Equipment Distributors How Technology Can Help you Maximize Profits in Fleet Management www.equip-soft.com Fleet Management
THE ROLE OF CHANGE MANAGEMENT IN A MANUFACTURING EXECUTION SYSTEM
THE ROLE OF CHANGE MANAGEMENT IN A MANUFACTURING EXECUTION SYSTEM Johannes Cottyn 1,2,*, Hendrik Van Landeghem 2, Kurt Stockman 1 and Stijn Derammelaere 1 1 Department GKG, University College of West Flanders
GPS Machine Control Grading & BIM (Building Information Modeling)
GPS Machine Control Grading & BIM (Building Information Modeling) Shawn Herring ProSoft Civil Applications Engineer Training & Support Manager Follow us on any of these media sites Facebook ProSoft Twitter
SUPPLY CHAIN MODELING USING SIMULATION
SUPPLY CHAIN MODELING USING SIMULATION 1 YOON CHANG AND 2 HARRIS MAKATSORIS 1 Institute for Manufacturing, University of Cambridge, Cambridge, CB2 1RX, UK 1 To whom correspondence should be addressed.
6.3 Structured identification of business improvement opportunities using Life Cycle Assessment: A case study in the gas turbine industry
6.3 Structured identification of business improvement opportunities using Life Cycle Assessment: A case study in the gas turbine industry P. Martínez-Caballero 1, B. Basdere 1, J. Richter 1, F. Parthey
of The New England Water Works Association
Journal Our 132nd Year of The New England Water Works Association Volume 127 No. 2 June 2013 PUTNAM WATER TREATMENT PLANT AQUARION WATER COMPANY OF CONNECTICUT GREENWICH, CONNECTICUT New England Water
How To Use Blue Yonder'S Predictive Analytics Software
Blue Yonder in practice Successfully realize Industry 4.0 s potential with accurate forecasts and automated decision-making Examples of applications of Blue Yonder Predictive Analytics in industry Blue
MORE THAN DOTS ON A MAP. Optimizing Business Intelligence by Automating Fleet Management. 2014 MotionLink motionlink.com
MORE THAN DOTS ON A MAP Optimizing Business Intelligence by Automating Fleet Management 2014 MotionLink motionlink.com GPS technology is increasingly transforming the way thousands of business and government
Simulation of processes in a mining enterprise with Tecnomatix Plant Simulation
Simulation of processes in a mining enterprise with Tecnomatix Plant Simulation Vladimir Medvedev Simulation of ore extraction on the open mountain works Page 2 Simulation objective To verify current control
CYBER PHYSICAL SYSTEMS@FRAUNHOFER IIS
F R A U N H O F E R I N S T I T U T E F O R I N T E G R AT E D C I R C U I T S I I S CYBER PHYSICAL SYSTEMS@FRAUNHOFER IIS CPS@FRAUNHOFER IIS Cyber physical systems: it is no longer possible to separate
Planning and Scheduling Consideration and Constraints in Automated Construction Environment. Chotchai Charoenngam, Ph.D. ABSTRACT
Planning and Scheduling Consideration and Constraints in Automated Construction Environment Chotchai Charoenngam, Ph.D. Assisatant Professor, School of Civil Engineering, Asian Institute of Technology,
SUPPORTING LOGISTICS DECISIONS BY USING COST AND PERFORMANCE MANAGEMENT TOOLS. Zoltán BOKOR. Abstract. 1. Introduction
SUPPORTING LOGISTICS DECISIONS BY USING COST AND PERFORMANCE MANAGEMENT TOOLS Zoltán BOKOR Department of Transport Economics Faculty of Transportation Engineering Budapest University of Technology and
Functional Modelling in secondary schools using spreadsheets
Functional Modelling in secondary schools using spreadsheets Peter Hubwieser Techn. Universität München Institut für Informatik Boltzmannstr. 3, 85748 Garching [email protected] http://ddi.in.tum.de
Managing Your Fleet Is Easy With FleetForce
Managing Your Fleet Is Easy With FleetForce New Holland Construction s FleetForce is a telematics system that collects information on your machine s performance and location and makes it available to you
Nexus GPS Tracking. Advanced GPS Monitoring System
Nexus GPS Tracking Advanced GPS Monitoring System What is Nexus GPS Tracking? Nexus GPS Tracking is a GPS tracking and fleet management system which is meant to improve the transport operations quality
The Digital Mine Concept and perspectives
The Digital Mine Concept and perspectives PSI Production GmbH, Aschaffenburg, Germany Table of Content 1. Introdu ctio n... 3 2. Targets o f a Digital Mine... 6 3. Main co ntrol fun ction s of th e Digital
INFORMATION TECHNOLOGIES AND MATERIAL REQUIREMENT PLANNING (MRP) IN SUPPLY CHAIN MANAGEMENT (SCM) AS A BASIS FOR A NEW MODEL
Bulgarian Journal of Science and Education Policy (BJSEP), Volume 4, Number 2, 2010 INFORMATION TECHNOLOGIES AND MATERIAL REQUIREMENT PLANNING (MRP) IN SUPPLY CHAIN MANAGEMENT (SCM) AS A BASIS FOR A NEW
Chapter 10. Hauling Equipment
Chapter 10 Hauling Equipment The most common hauling equipment used for Army construction work are the 5- and 20-ton dump trucks, both of which are organic to most engineer units. Equipment trailers are
Is load testing during initial acceptance inspection still the contemporary method?
Is load testing during initial acceptance inspection still the contemporary method? Alfons Petry TUV Industry Service TUV South Group, Germany Key words: Safety, commissioning test, load test, ADIASYSTEM,
OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING
OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING *Ram Prasad Choudhary Department of Mining Engineering, National Institute of Technology Karnataka, Surathkal-575025
THE CONCEPT OF HIERARCHICAL LEVELS; AN OVERALL CONCEPT FOR A FULL AUTOMATIC CONCRETE DESIGN INCLUDING THE EDUCATION OF CONCRETE.
THE CONCEPT OF HIERARCHICAL LEVELS; AN OVERALL CONCEPT FOR A FULL AUTOMATIC CONCRETE DESIGN INCLUDING THE EDUCATION OF CONCRETE. THE CASE MatrixFrame VERSUS EuroCadCrete. ABSTRACT: Ir. Ron Weener 1. The
Lean Construction A New Path for the Construction Industry
Lean Construction A New Path for the Construction Industry Peter Meijnen Porsche Consulting GmbH Oslo, 20 May 2015 Source: www.fosterandpartners.com Porsche Consulting - 20 years experience in consulting
FLEET. Telematics Fleet Solutions
FLEET Telematics Fleet Solutions Redtail is a global leader in the design, manufacture and distribution of quality customized telematics products Any organization that owns a fleet of vehicles can use
Daily Equipment Inspection Programs
Daily Equipment Inspection Programs Matt Beinlich, Komatsu America Corp. Fred Fakkema, Zonar Systems Kerry Sudrla, Kiewit Corporation A Look Back at Telematics and Safety Implications 1 This image cannot
Adapting to Change in the 4th Industrial Revolution. Graham Conlon Global Vice President, Extended Supply Chain, SAP
Adapting to Change in the 4th Industrial Revolution Graham Conlon Global Vice President, Extended Supply Chain, SAP Business Strategies Translating Business Realities to Business Strategies Personalized
Traceability Data Integrity: Challenges and Solutions By Mitch DeCaire, Cogiscan, Inc.
Traceability Data Integrity: Challenges and Solutions By Mitch DeCaire, Cogiscan, Inc. The electronics manufacturing industry is experiencing increased demands for material traceability. Competitive pressures
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3 7EH,
Lean Kitting: A Case Study
Lean Kitting: A Case Study Ranko Vujosevic, Ph.D. Optimal Electronics Corporation Jose A. Ramirez, Larry Hausman-Cohen, and Srinivasan Venkataraman The University of Texas at Austin Department of Mechanical
ENABLING LEAN SUPPLY WITH A CLOUD COMPUTING PLATFORM AN EXPLORATORY CASE STUDY
ENABLING LEAN SUPPLY WITH A CLOUD COMPUTING PLATFORM AN EXPLORATORY CASE STUDY Marcelo Azambuja 1, Thomas Schnitzer 2, Meral Sahin 3 and Felix Lee 4 ABSTRACT Traditional supply practices usually generate
The Combination of Last Planner System and Location-Based Management System
Seppänen, Olli, Glenn Ballard & Sakari Pesonen (2010) The Combination of Last Planner System and Location- Based Management System Lean Construction Journal 1 2010 pp 43-54 Abstract The Combination of
Intelligent Lifecycle Asset Management Cradle to Grave Data Utilization in Transportation
Intelligent Lifecycle Asset Cradle to Grave Data Utilization in Transportation Presented by Max Mckay, [email protected] Systems Engineer Intelligent Data Intelligent Lifecycle Lifecycle Asset Infrastructure
Inventory visualization and management. VEGA Inventory System
Inventory visualization and management VEGA Inventory System Measurements without borders The basis for a fully functioning inventory management system, whether global or regional, Supplier 1 Houston is
BPM and Simulation. A White Paper. Signavio, Inc. Nov 2013. Katharina Clauberg, William Thomas
BPM and Simulation A White Paper Signavio, Inc. Nov 2013 Katharina Clauberg, William Thomas Table of Contents 1. Executive Summary... 3 2. Setting the Scene for Process Change... 4 3. Identifying the Goals
How To Implement Ppc In Korea
IMPLEMENTING PPC IN KOREA S CONSTRUCTION INDUSTRY Chul-woo Lim 1, Jung-ho Yu 2, and Chang-duk Kim 3 ABSTRACT Developed by the Lean Construction Institute, the Last Planner System (LPS) consists of four