Exploring constraints in projects: A construction industry case study
|
|
|
- Emory Golden
- 10 years ago
- Views:
Transcription
1 Exploring constraints in projects: A construction industry case study Maryam Mirzaei, Victoria J. Mabin School of Management Victoria University of Wellington [email protected], [email protected] Abstract Theory of Constraints (TOC) suggests managing a system according to its constraints. Critical Chain Project Management (CCPM), as an application of TOC to project management, defines a project as a chain of activities with duration as its core constraint. However, the project success literature implies that projects have different characteristics and require different approaches. This study is part of broader research that attempts to re-examine CCPM assumptions and identify constraints in different types of projects. This paper presents a case study from the construction industry. Multiple semi-structured interviews and project documents have been used as sources of data. TOC Thinking Process logic tools were used to identify the core constraint. Further investigations are made to examine other CCPM assumptions in the context of the case. CCPM assumes that projects are plagued by uncertainty, that task times are overestimated as an attempt to avoid the undesirable effects of such uncertainty (including project lateness), but that such added safety time is actually wasted. These issues, assumed by CCPM to exist, were found to exist in this case project. The CCPM s solution requires the establishment of centralized priorities for the project and elimination of deterministic start dates. These requirements were found to be challenging in the case project. Key words: Construction, Critical Chain Project Management, Theory of constraints, thinking process tools. Introduction Projects are goal oriented undertakings. Project management primarily attempts to establish a process of achieving goals. Therefore, the use of prescriptive theories is essential (Ahlemann, El Arbi, Kaiser, & Heck, 2012). Theory of Constraints (TOC) has proven its capacity to invoke prescriptive solutions and applications for a diverse range of industries (Balderstone & Mabin, 1998; Gupta & Boyd, 2008; Mabin & Balderstone, 2003; Watson, Blackstone, & Gardiner, 2007). TOC frames this research study, because of its influence on the way the researcher is actively looking to find the constraints of the
2 system, assuming such constraints exist. Within TOC, constraints are defined as anything that limits a system from attaining higher performance towards its goal. TOC has been applied to project management, in order to address the typical issues experienced by project managers that led to project delays and failures (Pittman, 1994). The resulting approach, described by Goldratt (1997) as the Critical Chain method for project management, challenges the flawed assumption that the only way to achieve better performance is through good local performance throughout the system. Thus, he proposed CCPM as a systemic approach which advocated focusing on the longest chain of activities. CCPM seeks to change project team behaviour: encourages reporting early completion of activities and elimination of multitasking. The early literature on CCPM emphasizes issues such as excessive activity duration, failure to pass on positive variation, and delays caused by merging, multitasking, and loss of focus. According to Leach (1999), Goldratt s TOC analysis showed that these are all effects of a core underlying cause: failure to manage uncertainty. Therefore, CCPM, as an application of TOC to project management, defines a project as a chain of activities with duration as its core constraint. There are many published papers on empirical examples of successful applications of CCPM in the literature (Bevilacqua, Ciarapica, & Giacchetta, 2009; Hwang, Chang, & Li, 2010; Leach, 1999; Newbold, 2008; Paseuth, 2003; Realization Technologies, Inc,2010; Smith, 2012; Stratton, 1998; Umble & Umble, 2000; Viljoen, 1997). Despite the record of its application across industry, CCPM has been criticized for its lack of applicability to a wide range of projects (Mckay & Morton, 1998; Raz et al., 2003). According to Goldratt (2009, p. 336) an application makes assumptions (sometimes hidden assumptions) about the environment and we should not expect the application to work in environments for which its assumptions are not valid. Therefore, the assumptions underpinning CCPM need to be supported by evidence within the environment in which it is applied if such application is to be successful. The major assumption of CCPM concerns the definition of the core constraint. As stated above, CCPM suggests the longest chain of activities is the core constraint in all projects. CCPM also assumes that certain behaviours will occur, such as deliberate padding (padding the estimates in order to avoid being late on commitments); Murphy s Law (if anything can go wrong, it will); Parkinson s Law (work extends to fill the time allowed); and student syndrome (the type of procrastination students are prone to when they are assigned a project or are facing a test) (Goldratt, 1997; Leach, 1999; Newbold, 1998). CCPM also suggests that uncertainty is the major obstacle and the core cause of undesirable effects in projects. However, Raz et al. (2003) argue that other obstacles, such as external pressure, internal policies, and distorting estimates, are as important. This paper is a part of a broader study that seeks to examine underpinning assumptions of CCPM in various types of projects. We contend that evidence of the applicability or lack of applicability of CCPM assumptions depends on the context. This is because projects demonstrate fundamental differences in the type of challenges they face. Several empirical studies indicate that applicability of different methods and approaches is not a universal phenomenon
3 phenomenon (Dvir, Lipovetsky, Shenhar, & Tishler, 1998; Ratbe, King, & Young-Gul, 1999; Shenbar & Dvir, 2007; Shenhar, 2001). In fact, disagreements on applicability of many different project management methods stem from the fact that projects are different, and therefore confront different types of constraints. This paper is part of a broader study that seeks to identify the constraints in various types of projects to investigate the implications that the constraints have in applicability of CCPM to this type of project. For this purpose, multiple cases have been studied. The purpose of the broader research project is to: 1. Re-examine the assumptions behind CCPM 2. Assess whether these assumptions hold in a range of case projects 3. Explore the connection between these assumptions and characteristics of the project. This information will be used in order to develop a constraint-oriented classification model for projects. This paper discusses the findings from one of those cases. Research questions pertaining to each case are as follows: What is the core constraint of this project? Is this constraint related to specific characteristics of the project? Do CCPM s assumptions on human behaviour manifest themselves in this project? What are the challenges in implementing CCPM in this project? Methodology This case study involved multiple semi-structured interviews with the project manager and site manager in a construction project. Project documents including project plan and risk register were also used for analysis. In addition, a visit to the site allowed a better understanding of the context and thereby contributed to the triangulation of data. Data was analysed using two of TOC thinking processes: the Goal Tree and Current Reality Tree. The case analysis began by constructing a Goal Tree. A Goal Tree is a graphical, hierarchical representation of a system giving its goal, critical success factors and necessary conditions (Dettmer, 2011). A system is supposed to deliver a goal. Critical success factors are three to five criteria that must be achieved to realise the goal. Information from interviews and project documents was used to identify the goal, success criteria, and necessary conditions in this project. The Goal Tree was then presented to the project manager for further clarification and modification. This process was expected to confirm that the Goal Tree represented the intention of the project as it was perceived by the project manager and his team. To clarify the core constraints which prevent the system from achieving the goal identified in the Goal Tree, a Current Reality Tree is developed. The Current Reality Tree is a tree
4 diagram that employs cause-and-effect logic to identify the constraint (Cox, 2003; Goldratt, 1994; Kim, Mabin, & Davies, 2008; Mabin, 1999; Scheinkopf, 1999). The Current Reality Tree depicts the state of reality as it currently exists and demonstrates the most likely chain of cause and effect between root cause and the problem or undesirable effects. The Current Reality Tree has the ability to portray complex interactions. Undesirable effects (UDE) represent the deviation between the desirable outcome, as depicted in the Goal Tree, and reality. The TOC thinking processes also have a mechanism for verifying the validity of cause and effect logic trees through eight specific tests called the Categories of Legitimate Reservation (Dettmer, 2007). These tests guide the researcher to check that the cause and effect entities and relationships exist, and that they clearly and adequately describe the situation. Introduction to the case The case project was a construction project which aimed at seismic strengthening of an existing building in anticipation of future seismic activity. The building consisted of 15 levels and was located in Wellington City, which is an earthquake prone city. Prior to the project, a detailed seismic assessment had been conducted. The assessment result, indicated the building s seismic performance to be approximately 70% of the New Building Standard (% NBS) in terms of the expected performance for life safety in a 1- in-500 year earthquake. Despite the fact that the building was not classified as earthquake prone or earthquake risk in accordance with the New Zealand Society for Earthquake Engineering (NZSEE) guideline, the building owners intend to strengthen the building so that it could achieve a seismic performance of close to 100% NBS. This strengthening was perceived to increase the tenants interest in the building for a longer term agreement, which in turn was expected to increase the potential value of the building. The project had several stakeholders, each of whom played an important role in the project. The following section describes each stakeholder and their role. Building owner: the building was owned by a legal entity which leased the property for profit. In addition to the rental income the value of the building was also important this is because the legal entity which owned the building intended to sell the property in the near future. This intention also impacted the project. Consultant: The consulting company played a double role: the role of the consultant and the role of project management consultant. As the consultant, they were the advisor and communication facilitator. As the project management consultant, they were expected to manage the project. The project manager was an employee of the consulting company. His role included managing the scope, budget, programme, and risks, while also managing stakeholder expectations. He also managed the engagement and administration of all parties including design consultants and the building contractor. The consulting company also was responsible for all project documentation and reporting.
5 Tenants: the building was occupied by tenants. One major tenant occupied 6 levels of the building and 7 floors were occupied by 3 other tenants, while 2 levels were unaccented. The fact that the building was tenanted introduced a level of complexity. This was because contractors had to work around the constraints imposed by the nature of the tenants businesses. For example, the tenants who occupied 6 floors were engaged in IT and used delicate networking systems. This made movements and replacements much more difficult. Contractors: like most construction projects, multiple contractors were involved in this project. This included the fire engineering group, architects and designers, as well as the building contractor. The building contractor managed several other sub-contractors, each specializing in one area. This included carpentry, demolishing, steel work, electrical work, sprinkler installation, floor grinding work, carpet removal and replacement, and Fibre-Reinforced Plastic work. In addition, other specialists would be employed by the contractor if found to be required. For example, if the pipes were damaged, then they may need to employ plumbers to repair them. Goal Tree Despite the diversity of stakeholders, a set of objectives was agreed upon and signed by project actors in forms of contracts, project plan and risk management plan. This information along with interviews guided the development of the Goal Tree in this study. The Goal Tree is depicted in Figure 1, showing three critical success criteria. The following section describes each success criterion along with a list of necessary conditions as was described by the project manager or as was explained in the project management plan. Figure 1: Goal Tree
6 Critical success factors: On time and within budget delivery Projects with delays and cost overrun are not usually considered as successful projects; this project was no exception. Controlling cost and schedule requires an agreement on cost and duration estimates. Such agreement would be achieved only if all parties had enough information. The contractors and building owner decided to obtain such information by doing a trial floor which was untenanted at the time. Once all parties agreed upon cost and duration, the base line for both cost and schedule was set. The project manager then managed the contractors through channels of written communication and regular site meetings. Channels of written communications included producing documents such as contract instructions and contract query response. Critical success factors: Quality standards As with any other construction project, the scope of the project was defined in the design process and needed to be executed exactly as described by the designers. Despite the uncertainties in the execution process, the scope itself was well defined in advance and was not expected to change during the process. For this reason, rigorous change process documentation was in place. Confirming the delivery of scope involved the issuance of contract instructions and responding to contract queries and regular site meetings. This clearly shows that no decisions regarding the scope and quality were left to be made by the execution crew. Critical success factors: Satisfied customer The last, but not least, success criterion was customer satisfaction. The project manager suggested that this criterion is an important factor that would stimulate obtaining more business in the future. Customer satisfaction involved keeping the customers customers (tenants) satisfied. This was in fact a great challenge due to the nature of the project; the project involved noise, dust, displacement, and destruction. Therefore, inconvenience for the existing tenants was inevitable; the aim was to reduce the negative effect of such inconveniences to a minimum. Thus, a great deal of customer satisfaction was expected to be achieved by reducing noise and disturbance as well as minimizing disruption. It is important to note, that the goal of the system and necessary conditions were depicted as perceived by the project manager. Therefore, fulfilling the necessary conditions of customer satisfaction is described here from the project manager s perspective. According to the earlier citation on the role of the consultant, consultants played the middle role. The consultants therefore were the organisers of communications, and increasing effectiveness of such communications was the core in satisfying all stakeholders including their customers. Other necessary conditions Risk management was another necessary condition that was connected to two success criteria. The project manager reported that a risk management plan which prevents or reduces the risks, would improve customer satisfaction and prevent delays and cost overruns. The process of risk management had started with a risk brainstorming session held early in the project with the contractors. The resulting risks were recorded in the
7 project risk register and regularly reviewed and updated throughout the project. Construction-specific risks were assigned to be managed by the contractor. More general project-specific risks were agreed to be managed by the consultant. The risk management process during the construction phase was expected to be facilitated by the project manager. In addition, ad-hoc risk meetings, as required, were allowed to be organised by the project manager. Updates of Project Risk were included in the monthly report. As such, a well-documented risk process was found to be in place. Three necessary conditions were identified in managing risk. Firstly, risks related to health and safety had been addressed specifically by the Contractor s Safety Plan. This plan was expected to ensure that work they did, did not adversely impact on the tenants of the building or any visitors to the building. While this document was prepared and signed by all contracting companies, managing health and safety of workers was expected to be the duty of contractors for whom they worked. In addition to the Contractor s Safety Plan, further clarification was allowed by contract instructions and contract queries. Secondly, project documentation was considered to be a risk control measure. Well documented decisions were expected to reduce the impact of any forthcoming changes and also provide accurate information for future decisions. Interestingly, all risks were perceived to be managed using some form of communication. Implications of the Goal Tree The above Goal Tree depicts success criteria as implied by project documents and as perceived by the project manager. Elattar (2009) suggests differentiating success criteria as perceived by owner, designer, and contractor. It is interesting to note that the success criteria as described above had elements of all three, and this is because the project manager was an employee of the consulting company. In this project, the project manager was detached from both the executors of the project and the owners. And since the execution was contracted to another company, both managing time and budget were, in fact, elements of contractor management. Perhaps for the same reason, all control measures were claimed to be achievable via a communication process. In fact, the project manager indicated that contract instructions, and query responses were the key to the achievement of health and safety, controlled budget, controlled quality, and control of contractors. Similarly, he indicated that the schedule was controlled by producing and updating the Gantt chart, submitting regular reports, and conducting regular meetings, all of which are means of communication. This, it turn out, is in accordance with job dispatching theory in manufacturing. Job dispatching theory consists of deciding and communicating the assignment to the job station, and in project management the first part falls within planning and therefore the execution is reduced to mere communication (Koskela & Howell, 2002). Similarly, in this project, most necessary conditions at the bottom were means of communication. Current reality tree After defining the system and its goal, possible Undesirable Effects (UDE) were predicted. A summary of Current reality tree is depicted in figure 2. At core the predicted undesirable effects were triggered by wasting the excess time. While several reasons for uncertainty are beyond the span of control of the project crew, it is assumed that adding
8 safety time (padding) to each individual task will protect the project from delay. For this reason, padding is added to each estimate. Even though padding is meant to prevent delays due to uncertain events, it is more likely to be wasted. This is because contractors are engaging in other projects. They juggle their tasks based on predefined schedules and attempt to maximize working days of their crew. Therefore, they are unlikely to be available prior to the set dates. Wastage of this safety time leads to both delays and increased inconvenience of tenants. In particular, the convenience of tenants was emphasised as very important by the project manager. Several issues such as working hours and sequence of the floors were adjusted to reduce the inconvenience. Nevertheless, longer work in progress could seriously jeopardise customer satisfaction. Figure 2: Current reality tree Applicability of Critical Chain Project Management In this section, the evidence concerning CCPM assumptions and applicability of such assumptions to this project, are discussed. The first assumption of CCPM is that projects are controlled by a schedule. In this project arrival of each contractor was organised by the schedule. This case project also strongly supports the CCPM claims concerning overestimation of time via individual task buffer and wastage of such buffer in practice. Another assumption of CCPM, which is influenced by job dispatching theory, is division between decision makers and executors of the project, and communication as a mechanism of execution. This project clearly shows such a division exists and all execution processes are claimed to be achieved through means of communication. In essence this project does not appear to deviate much from CCPM s assumed project characteristics.
9 However, in order to implement CCPM one important prerequisite of CCPM is the establishment of centralized priorities. This project was executed by contractors. It was not possible to centralize the contractors priorities. Another challenge was that with no start date, as suggested by CCPM, it was difficult to tie an array of people into a contractual agreement. While early supply of material can be accommodated to some extent early arrival of contractors is not. This is because in most cases, tasks are dependent on preceding tasks. So if they arrive early, they have to wait idle until the preceding tasks are completed. Since the contractors are only paid for the work they do, arriving early is a loss for contractors. However, arriving late may not encounter direct cost to the contractor. In fact, preventing early arrival of the contractors is maybe the motive for calculating buffers within each task. Unity of purpose not only is an importance pre-requisite to CCPM implementation, but it prevents counterproductive activities, which in turn produces mutual benefits to all parties involved. Some types of contractual arrangements can facilitate achieving unity of purpose. For example, various types of Relationship Contracting, Partnering, or Alliancing (Quick, 2002; Rahman & Kumaraswamy, 2004) are particularly developed to align project parties. Conclusions This case study provides evidence consistent with some of the basic assumptions of CCPM. Some of these assumptions are: considering uncertainty as the core cause for projects undesirable effects, overestimation of task time in the form of buffers, and wastage of such safety time. Nevertheless, the case indicated that the absence of centralised priorities for the project was a challenge in adopting CCPM. Particularly elimination of deterministic start dates would negatively impact contractor s throughput rate. This is because contractors are involved in multiple projects and their throughout would increase only by increasing working days of their crew. Therefore, they would not risk having their crew waiting. It is argued here, in the context of this project, that CCPM has identified the core problem. However, implementation of the CCPM solution requires unity of purpose across project actors, in order to be able to prioritize several contractors across several projects. If unity of purpose could be achieved, then this would facilitate CCPM application and bring mutual benefits to all parties involved. References Ahlemann, F., El Arbi, F., Kaiser, M. G., & Heck, A. (2012). A process framework for theoretically grounded prescriptive research in the project management field. International Journal of Project Management, 3 (1), Balderstone, S. J., & Mabin, V. J. (1998). A Review of Goldratt s Theory of Constraints (TOC) Lessons from the international literature. Proceedings of the 33th Annual Conference of the Operations Research Society of New Zealand. Bevilacqua, M., Ciarapica, F. E., & Giacchetta, G. (2009). Critical chain and risk analysis applied to high risk industry maintenance: A case study. International Journal of Project Management, 27(4), Cox, J. F. (2003). Managing operations: a focus on excellence. Great Barrington, MA: North River Press. Dettmer, H. W. (2007). The logical thinking process: a systems approach to complex problem solving. Milwaukee, WI: ASQ Quality Press. Dettmer, H. W. (2011). Strategic navigation. In The Constraint Management Model Proceedings of the APICS International Conference Las Vegas, Nevada (USA) October (pp. 6 9). Dvir, D., Lipovetsky, S., Shenhar, A., & Tishler, A. (1998). In search of project classification: a nonuniversal approach to project success factors. Research Policy, 27(9), Elattar, S. M. S. (2009). Towards developing an improved methodology for evaluating performance and achieving success in construction projects. Scientific Research and Essay, 4(6),
10 Goldratt, E. M. (1994). It s Not luck. Great Barrington, MA: North River Press. Goldratt, E. M. (1997). Critical Chain. Great Barrington, MA: The North River Press. Goldratt, E. M. (2009). Standing on the shoulders of giants: production concepts versus production applications. The Hitachi Tool Engineering example. Gestão & Produção, 16(3), Gupta, M. C., & Boyd, L. H. (2008). Theory of constraints: a theory for operations management. International Journal of Operations & Production Management, 28(10), Hwang, Y. J., Chang, Y. M., & Li, R. K. (2010). Using TOC CCPM S&T tree to rapidly improve performance of new product development projects: a case study in Taiwan. Project Management and Systems Engineering Republic of China, 4 (95). Kim, S., Mabin, V. J., & Davies, J. (2008). The theory of constraints thinking processes: retrospect and prospect. International Journal of Operations & Production Management, 28(2), Koskela, L. J., & Howell, G. (2002, June). The underlying theory of project management is obsolete. In Proceedings of the PMI Research Conference, Leach, L. P. (1999). Critical Chain Project Management Improves Project Performance. Project Management Journal, 30(002), 39. Mabin, V. (1990). Goldratt's Theory of Constraints thinking processes: A systems methodology linking soft with hard.. Proceedings of the 17 th International Conference of the System Dynamics Society and 5 th Australian and New Zealand Systems Conference. Wellington: 1999 Mabin, V. J., & Balderstone, S. J. (2003). The performance of the theory of constraints methodology: Analysis and discussion of successful TOC applications. International Journal of Operations & Production Management, 23(6), Mckay, K. N., & Morton, T. E. (1998). Review of: Critical Chain Eliyahu M. Goldratt The North River Press Publishing Corporation, Great Barrington, MA, ISBN IIE Transactions, 30(8), Newbold, R. C. (1998). Project Management in the Fast Lane: Applying the Theory of Constraints (1 st ed.). Boca Raton, FL: CRC Press. Newbold, R. (2008). Billion Dollar Solution: Secrets Of Prochain Project Management. Lake Ridge, VA: ProChain Press. Paseuth, S. (2003, January 1). An analysis of critical chain project management application. Unpublished MCA Thesis. Wellington: Victoria University of Wellington. Pittman, P. H. (1994). Project management: A more effective methodology for the planning and control of projects. Unpublished PhD Dissertation. Athens, GA: University of Georgia at Athens. Quick, R. (2002). Introduction to Alliancing and relationship contracting. In QLS/BAQ Symposium. Rahman, M. M., & Kumaraswamy, M. M. (2004). Contracting Relationship Trends and Transitions. Journal of Management in Engineering, 20(4), Ratbe, D., King, W. R., & Young-Gul, K. (1999). The fit between project characteristics and application development methodologies: A contingency approach. The Journal of Computer Information Systems, 40(2), 26. Raz, T., Barnes, R., & Dvir, D. (2003). A Critical Look at Critical Chain Project Management. Project Management Journal, 34(4), 24. Realization Technologies, Inc. (2010). Getting Durable Results with Critical Chain -- A Field Report (Chapter 4 of Theory of Constraints Handbook). New York: McGraw-Hill. Scheinkopf, L. J. (1999). Thinking for a Change: Putting the TOC Thinking Processes to Use (1st ed.). Boca Raton, FL: CRC Press. Shenbar, A. J., & Dvir, D. (2007). How projects differ and what to do about it. In The Wiley guide to project, program & portfolio management. Hoboken, N.J.: J. Wiley & Sons. Shenhar, A. J. (2001). One Size does not Fit All Projects: Exploring Classical Contingency Domains. Management Science, 47(3), Smith, D. G. (2012, July). Theory of Constraints Project Management Improving Cost, Schedule, Performance, and Overall Effectiveness. Northcentral University. Stratton, R. (1998). Critical chain project management theory and practice. Project Management and Systems Engineering, 4, 149. Umble, M., & Umble, E. (2000). Manage your projects for success: An application of the theory of constraints. Production and Inventory Management Journal, 41(2), Viljoen, P. J. (1997). A strategic projects management solution developed from theory of constraints concepts. Projects Management and Systems Engineering, 2, 111. Watson, K. J., Blackstone, J. H., & Gardiner, S. C. (2007). The evolution of a management philosophy: The theory of constraints. Journal of Operations Management, 25(2),
Gaining Competitive Advantage through Reducing Project Lead Times Duncan Patrick, CMS Montera Inc. Jack Warchalowski, CMS Montera Inc.
Gaining Competitive Advantage through Reducing Project Lead Times Duncan Patrick, CMS Montera Inc. Jack Warchalowski, CMS Montera Inc. Introduction We all know that any successfully completed project has
CCPM: TOC Based Project Management Technique
CCPM: TOC Based Project Management Technique Prof. P.M. Chawan, Ganesh P. Gaikwad, Prashant S. Gosavi M. Tech, Computer Engineering, VJTI, Mumbai. Abstract In this paper, we are presenting the drawbacks
Is Critical Chain Project Management Really a Novel Technique?
Is Critical Chain Project Management Really a Novel Technique? Mario Špundak VIPnet usluge d.o.o. Vrtni put 1, 10000 Zagreb, Croatia [email protected] Krešimir Fertalj, Damir Kalpić University of Zagreb
THEORY OF CONSTRAINTS AS AN EFFECTIVE TOOL FOR SUPPLY CHAIN MANAGEMENT JOANNA NOWAKOWSKA-GRUNT 1 EWA MOROZ 2
Advanced Logistic Systems, Vol. 7, No. 1 (2013), pp. 71 78. THEORY OF CONSTRAINTS AS AN EFFECTIVE TOOL FOR SUPPLY CHAIN MANAGEMENT JOANNA NOWAKOWSKA-GRUNT 1 EWA MOROZ 2 Abstract: Supply chain management
How To Compare Six Sigma, Lean and the Theory of Constraints
P R O C E S S M P R O V E M E N T How To Compare Six Sigma, Lean and the Theory of Constraints A framework for choosing what s best for your organization WTHN THE AMERCAN business community a multitude
50% task time estimate A task time estimate that has a 50% probability of being achieved.
1 2 nd edition CC terms 50% task time estimate A task time estimate that has a 50% probability of being achieved. Perspective: The distribution of task times is generally viewed as an asymmetrical positive
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction
A Critical Look at Critical Chain Project Management
A Critical Look at Critical Chain Project Management Tzvi Raz, Faculty of Management, Tel Aviv University Robert Barnes, Consultant, The ie3 Group Ltd, Auckland, New Zealand Dov Dvir, Business School,
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
Multi-Project Management using Critical Chain Project Management (CCPM) The Power of Creative Engineering
Multi-Project Management using Critical Chain Project Management (CCPM) The Power of Creative Engineering Prof. Siddesh K. Pai Assistant Professor & Research scholar National Institute of Construction
Project Management Simple Answers to Simple Questions
Project Management Simple Answers to Simple Questions Originally I wrote this for one of my clients in 1991. The idea was to develop a brochure to promote project management in one of the client's departments.
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
Critical Chain Project Management The Basics
Critical Chain Project Management The Basics Marcia Pasquarella, Jonah, CFPIM, CIRM 310-416-3035 [email protected] BOEING is a trademark of Boeing Management Company. Copyright 2009 Boeing.
An analysis of Critical Chain concepts in the context of their possible application to traditional project management
An analysis of Critical Chain concepts in the context of their possible application to traditional project management Peter Schneider-Kamp (Supervisor: Peter Bollen) June 13, 2002 Abstract Critical Chain
NFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
Issues in Information Systems
TAXONOMY OF MULTIPLE LEVELS OF SWOT ANALYSIS IN PROJECT MANAGEMENT Ganesh Vaidyanathan, Indiana University South Bend, [email protected] Asghar Sabbaghi, Indiana University South Bend, [email protected]
Program Management. Turning Many Projects into Few Priorities with TOC
Program Management Turning Many Projects into Few Priorities with TOC Francis. Patrick Focused Performance 908-874-8664 [email protected] The way to get something done is quoting the wellknown
Software Project Scheduling under Uncertainties
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Answers to Review Questions
Tutorial 2 The Database Design Life Cycle Reference: MONASH UNIVERSITY AUSTRALIA Faculty of Information Technology FIT1004 Database Rob, P. & Coronel, C. Database Systems: Design, Implementation & Management,
Abstract Number: 002-0427. Critical Issues about the Theory Of Constraints Thinking Process A. Theoretical and Practical Approach
Abstract Number: 002-0427 Critical Issues about the Theory Of Constraints Thinking Process A Theoretical and Practical Approach Second World Conference on POM and 15th Annual POM Conference, Cancun, Mexico,
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
A Step-by-Step Approach for Planning Your Small Project
A Step-by-Step Approach for Planning Your Small Project Dohn Kissinger, MBA, PhD, PMP Planning for a small project is difficult. The PMBOK Guide (PMI, 1996) is an impressive document, which thoroughly
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two. By Eli Schragenheim and Daniel P. Walsh
vector strategies The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two By Eli Schragenheim and Daniel P. Walsh The floor looks similar to any other manufacturing floor.
CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?
EXECUTIVE SUMMARY PURPOSE: This paper is a comparison and contrast of two project management planning and execution methodologies: critical path methodology (CPM) and the critical chain project management
STRATEGIES FOR AVOIDING ASYMMETRIC INFORMATION IN CONSTRUCTION PROJECT MANAGEMENT
Journal of Business Economics and Management 2008 9(1): 47 51 STRATEGIES FOR AVOIDING ASYMMETRIC INFORMATION IN CONSTRUCTION PROJECT MANAGEMENT Martin Schieg Technical University of Munich, Arcisstraße
Basics Workshop: Project and Multi-Project Management (English)
Basics Workshop: Project and Multi-Project Management (English) Presented By: James R. Holt, Ph.D., PE FE, BSCI, PMCI, SCLCI, TPCI Date: June 2013 If you have already implemented Critical Chain Project
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Name Chapter 1: Introduction to Project Management Description Instructions
Name Chapter 1: Introduction to Project Management Description Instructions Modify Question 1 / 0 points Modify Remove Question Until the 1980s, project management primarily focused on providing schedule
Summary of the Master Thesis. Masters Degree International Project Management
Summary of the Master Thesis Masters Degree International Project Management in the Building Process Chain Stakeholder Contribution to the Strategic Direction of a Construction Project Submitted by: Dipl.-Ing.
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
THE RELATIONSHIP BETWEEN CONTRACT ADMINISTRATION PROBLEMS AND CONTRACT TYPES Bill Davison and Richard J. Sebastian*
INTERNATIONAL PUBLIC PROCUREMENT CONFERENCE PROCEEDINGS 21-23 September 2006 THE RELATIONSHIP BETWEEN CONTRACT ADMINISTRATION PROBLEMS AND CONTRACT TYPES Bill Davison and Richard J. Sebastian* ABSTRACT.
Project Management. [Student s Name] [Name of Institution]
1 Paper: Assignment Style: Harvard Pages: 10 Sources: 7 Level: Master Project Management [Student s Name] [Name of Institution] 2 Project Management Introduction The project management also known as management
B.2.2. Project Management Principles
B.2.2. Project Management Principles Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations
Strategies and Methods for Supplier Selections - Strategic Sourcing of Software at Ericsson Mobile Platforms
Strategies and Methods for Supplier Selections - Strategic Sourcing of Software at Ericsson Mobile Platforms Caroline Raning & Johanna Vallhagen February 2007 Department of Industrial Management and Logistics,
SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP
SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
ENTERPRISE RISK MANAGEMENT POLICY
ENTERPRISE RISK MANAGEMENT POLICY TITLE OF POLICY POLICY OWNER POLICY CHAMPION DOCUMENT HISTORY: Policy Title Status Enterprise Risk Management Policy (current, revised, no change, redundant) Approving
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
7 Conclusions and suggestions for further research
7 Conclusions and suggestions for further research This research has devised an approach to analyzing system-level coordination from the point of view of product architecture. The analysis was conducted
APPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE
APPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE Badr O. Johar, Northeastern University, (617) 3737635, [email protected] Surendra M. Gupta, Northeastern University,
In initial planning phases In monitoring and execution phases
Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar
Introduction. Book Structure
Fundamentals of Project Management, 4 th Edition Simple Solutions for Busy People By Joseph Heagney (A Book review by R. Max Wideman, FPMI) The views expressed in this article are strictly those of Max
Dynamic Change Management for Fast-tracking Construction Projects
Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations
A Study of Using Critical Chain Project Management Method for Multi-Project Management Improvement
A Study of Using Critical Chain Project Management Method for Multi-Project Management Improvement Chia-Ling HUANG Department of Logistics and Shipping Management, Kainan University, No. 1, Kainan Road,
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
High-Mix Low-Volume Flow Shop Manufacturing System Scheduling
Proceedings of the 14th IAC Symposium on Information Control Problems in Manufacturing, May 23-25, 2012 High-Mix Low-Volume low Shop Manufacturing System Scheduling Juraj Svancara, Zdenka Kralova Institute
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
Implementation of a Quality Management System for Aeronautical Information Services -1-
Implementation of a Quality Management System for Aeronautical Information Services -1- Implementation of a Quality Management System for Aeronautical Information Services Chapter IV, Quality Management
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
Benefits Realization from IS & IT, and Change Management of roles and the working practices of individuals and teams.
: Delivering Value from IS & IT Investments John Ward and Elizabeth Daniel John Wiley & Son Ltd ISBN: 9780470094631, 399 pages Theme of the Book This book explores a process and practical tools and frameworks
Level 1 Articulated Plan: The plan has established the mission, vision, goals, actions, and key
S e s s i o n 2 S t r a t e g i c M a n a g e m e n t 1 Session 2 1.4 Levels of Strategic Planning After you ve decided that strategic management is the right tool for your organization, clarifying what
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Bottlenecks in Agile Software Development Identified Using Theory of Constraints (TOC) Principles
Master thesis in Applied Information Technology REPORT NO. 2008:014 ISSN: 1651-4769 Department of Applied Information Technology or Department of Computer Science Bottlenecks in Agile Software Development
LEAN PROJECT MANAGEMENT Assessment of project risk management processes NEUS ALCARAZ BOSCÀ
LEAN PROJECT MANAGEMENT Assessment of project risk management processes NEUS ALCARAZ BOSCÀ Master of Science Thesis Stockholm, Sweden 2012 LEAN PROJECT MANAGEMENT Assessment of project risk management
The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain
The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain Variability Is A Fact Of Life Presentation Delivered by: Gerald Leonard, PMP, MCTS, CQIA, ITIL Objective Define Theory
9 TH INTERNATIONAL ASECU CONFERENCE ON SYSTEMIC ECONOMIC CRISIS: CURRENT ISSUES AND PERSPECTIVES
Matilda Alexandrova Liliana Ivanova University of National and World Economy,Sofia, Bulgaria CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT: EMPIRICAL EVIDENCE FROM PROJECTS SUPPORTED BY EU PROGRAMMES
Understanding Principles and Concepts of Quality, Safety and Environmental Management System Graham Caddies
Understanding Principles and Concepts of Quality, Safety and Environmental Management System Graham Caddies Owner / Principal Advance Profitplan Understanding Principles & Concepts Page 1 of 10 Revision
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
3 Traditional approach
The Unified Approach to Modeling of Software Project Management Processes Šárka Květoňová 1, Zdeněk Martínek 1 1 Dept. of Information Systems, Faculty of Information Technology, Brno University of Technology,
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
LEADERSHIP IN PROFESSIONAL SERVICES
LEADERSHIP IN PROFESSIONAL SERVICES Enhancing Business Performance of Leading Professional Service Firms First in a series on Innovations in Professional Services by Bede Boyle and Brad Shields Louern
Efficiency Criteria in Software Project Management
124 Economy Informatics vol. 13, no. 1/2013 Efficiency Criteria in Software Project Management Cecilia CIOLOCA, Mihai GEORGESCU, Mihai CURTEANU Academy of Economics Studies, Bucharest, Romania [email protected],
EFFECTIVE ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PROCESS
JOURNAL OF ENGINEERING MANAGEMENT AND COMPETITIVENESS (JEMC) Vol. 1, No. 1/2, 2011, 16-20 EFFECTIVE ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PROCESS Branislav TOMIĆ 1, Vesna SPASOJEVIĆ BRKIĆ 2 1 Bombardier
Risk and Contingency Planning. Today s Topics. Key Terms. A Vital Component of Your ICD-10 Program
Risk and Planning A Vital Component of Your ICD-10 Program Today s Topics Key Terms Why is Risk Management Critical for ICD-10? Effective Risk Management and Best Concepts ICD-10 Risk Management Examples
Project Management Topics
S E C T I O N II T W O Project Management Topics SECTION II: PROJECT MANAGEMENT TOPICS TABLE OF CONTENTS Introduction 3 1. PROJECT TRIAGE 5 1.1 Gather the Data 7 1.2 Review and Analyze the Data 10 1.3
INDECO Management Solutions
INDECO Management Solutions Learning to manage projects as though they mattered: implementing strategy, adding value, and delivering benefits through project management Peter W.G. Morris Professor of Construction
6500m HOV Project Stage 1: A-4500 HOV
6500m HOV Project Stage 1: A-4500 HOV Systems Engineering, Integration & Testing Plan Document Control No.: 0000000 01-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Overview.
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Andersen Consultng 1600 K Street, N.W., Washington, DC 20006-2873 (202) 862-8080 (voice), (202) 785-4689 (fax) [email protected]
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER Responsible for performing entry level engineering analysis, design, plan, review and inspection for small to medium projects and/or designated segments of
A software for project management process
MPRA Munich Personal RePEc Archive A software for project management process Logica Banica and Doina Rosca and Cristian Stefan University of Pitesti, Faculty of Economics, University of Craiova, Faculty
NASCIO EA Development Tool-Kit Solution Architecture. Version 3.0
NASCIO EA Development Tool-Kit Solution Architecture Version 3.0 October 2004 TABLE OF CONTENTS SOLUTION ARCHITECTURE...1 Introduction...1 Benefits...3 Link to Implementation Planning...4 Definitions...5
How To Manage A Project
Professor A. Jaafari, ME, MSc, PhD, CPEng, FIEA Online Project Diagnostics: A Tool for Management of Project Complexities There is evidence that the current project management models and practices do not
jobs that obey the norms must ensure the load balancing qualities. Load balancing should be interpreted as releasing a balanced mix of jobs to the
Summary The term job shops is used to indicate companies that produce customer-specific components in small batches. Jobs (production orders) in a job shop are characterised by a large variety of routings
PRINCE2:2009 Glossary of Terms (English)
accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
Value chains, value networks and supply chain management
RELEVANT TO ACCA QUALIFICATION PAPER P3 Value chains, value networks and supply chain management Sections A4, E2 and E3 of the Syllabus and Study Guide relate to value chains and value networks, and Sections
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
Managing Successful Programs (2007) Page 2 of 11. Book Structure
Managing Successful Programs (2007) Published for Office of Government Commerce, UK (A book review by R. Max Wideman) (Note: North American spelling has been adopted throughout.) 2/1/09 Introduction Managing
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking