1 SAMPLE PAPER Architects Accreditation Council of Australia ARCHITECTURAL PRACTICE EXAMINATION (NATIONAL EXAMINATION PAPER) Time allowed: 1 hour (plus 10 minutes extra reading time) Instructions to Candidates This is a closed book examination. NB: The following will not be permitted in the examination room: Reference material, practice notes, building contracts, handwritten notes and any other printed or written material; laptop computers, mobile phones and other electronic equipment. Read the following scenarios and select by marking with a tick in the box ALL statements you consider to be CORRECT. NOTE: In each group of scenarios, one or more than one of the statements may be correct. Marking:. The paper will be marked by template.. If you wish to correct an answer you must do so in the answer box.. White-out will be available in the examination room. The following marking scale applies:. Correct statement selected 2 marks. Incorrect statement selected minus 1 mark. Correct statement missed zero mark 60% is required to pass the National Examination Paper.

2 Candidate s Name Scenario 1 You have recently opened an architectural office which is gradually attracting work of increasing size. Some years ago, as a student you designed alterations and additions to a house. You maintained contact with that client who is now CEO of an IT company. He telephones you and offers you the commission to design his Company s new headquarters. A budget of $2.5 million is discussed and you estimate that a fee of 7% will apply. This is immediately confirmed and accepted by and you are requested to get the job underway immediately. You intended to send an Architect/Client agreement but such is the enthusiasm of your client that the formalities are passed by. Similarly, when the engagement of a structural engineer is canvassed your proposal to engage your usual engineer is readily accepted and you are authorised by to engage the engineer, which you do. The engineer provides an ACEA Engineer/Client agreement which you sign and return. Included in that agreement are two limitations on the engineer s liability for claims. There is a $300, upper limit on liability for any claim and a one year time limit after completion of the service to be provided by the engineer. You hold Professional Indemnity Insurance limited to $1 million per claim. 1. You have no contract with the client because of the absence of a formal signed agreement. 2. If the engineer made a design error resulting in a financial loss to the building owner in excess of $300,000.00, you would not be liable unless you had changed the engineer s design. 3. If the engineer made a design error, which resulted in a $500, financial loss to the building owner, you would be potentially liable for $200, In the above circumstance you may be liable for the full amount of the loss. 5. If a visitor to the building made a $5 million claim, having sustained serious injuries and mental trauma as a result of the collapse of part of the façade due to a shear failure of the supporting façade steelwork, the engineer would be protected by the one year limitation on liability in his/her fee agreement.

3 Scenario 2 You have designed and documented a house. Your fee claims over the last four months of the design/documentation period have been based on an agreed budget, which is set out in absolute terms in the Client Architect Agreement signed by you and your client. Six tenders were received the lowest of which is 50% higher than the construction budget. There is no prospect of a reduction in project quality or the size of the project in order to bring it within the budget. 1. Professional Indemnity Insurance policies do not cover architects for budget over runs. 2. You may be required to forfeit all or part of your fee for this work. 3. Your client has an action in damages for negligent misstatement or deceptive and misleading conduct in contravention with S52(1) of the Trade Practices Act. 4. Your client has no action because it was he who set the budget. 5. You should notify your Professional Indemnity Insurer of the possibility of and circumstances giving rise, to a future claim in accordance with the terms of your policy.

4 Scenario 3 You have designed a small house on a difficult site with highly reactive foundation conditions. It is a condition of your specification that the builder give 48 hours notice prior to pouring concrete. A slab at ground level has been prepared and poured without your knowledge. After consideration of the available information, you reject the possibility of opening up part of the slab because of the likely sub-surface consequences and you issue instructions for the builder to demolish the slab and pour a new one in accordance with the specification. The builder has referred your instruction to your client on the basis that the decision is unfair, will delay the progress of the works and will add a variation for which the proprietor will be responsible. Your client overrules your decision and tells the builder to proceed with the works. Assume that there is no issue of contract interpretation in the following answers. 1. The client has authority as the principal in your agency agreement to overrule your decision. 2. In the event that the builder complied with your instruction and the slab was found to have been properly constructed the builder would have a valid claim for a contract variation. 3. Irrespective of the outcome of the demolition the builder has a valid claim for a variation. 4. If there was a valid variation under the circumstances outlined above the builder would also have a valid claim for an extension of time and costs associated with the time extension. 5. If there was a valid claim for a variation and costs you could be called upon to meet the claim due to your negligence in wrongly instructing the builder.

5 Scenario 4 You are asked by a client to provide complete architectural services for a new car showroom. At the request of the client you engage a structural engineer who agrees, in a telephone conversation with you, to provide the necessary structural design services for a fee payable by the client, direct to the engineer, on your authorisation. 1. You are not responsible to the client for the engineer s design, as you did not produce the structural design. 2. You are not responsible to the client for the engineer s design unless you were negligent in selecting the engineer. 3. If the engineer were to make a structural design error, resulting in financial loss to the client, the engineer would not be liable, as the client and the engineer have no contract. 4. If the engineer were to make a structural design error resulting in financial loss to the client, the engineer would be potentially liable to the client on the basis that the client was aware of the engineer s appointment and relied on the engineer to provide a reasonably competent structural engineering service. 5. The client owns the copyright in the design of the showroom because the client commissioned you to undertake the design. 6. The client has an implied licence to build the showroom on the site for which it was designed. 7. The client has no licence to build the showroom on the site for which it was designed because you have no written agreement with the client.

6 Scenario 5 You have designed an apartment building with subterranean car parking and storage areas. You are now administering the building contract. After the proprietor has made the first progress payment in accordance with your certificate, work on the site is delayed by three days of rain which floods the entire basement area. It takes a further five days for the water to drain away. The rain and flooding has prevented all work from continuing on the site. The builder lodges a claim for an extension of time for eight working days plus costs. In considering the claim you form the view that the builder has not taken sufficient steps to drain the site. In your view, had he done so, work could have been recommenced earlier than it did. 1. You should allow the whole of the builder s claim including delay costs. 2. You should allow the whole of the time claimed, but no costs for delay. 3. You should reject the entire claim. 4. You should allow a three day extension of time for the wet weather, plus part of the five days claimed for the effects of the site flooding.

7 Scenario 6 Construction has commenced on a project which you have redesigned several times. The builder has provided your client with two bank guarantees in lieu of having retention deducted from his progress claims. 1. In situations where a bank guarantee is provided in lieu of a retention sum no GST will be applicable to the retention. 2. Retention sums in any form do not attract GST. 3. The builder s assessment of the cost of the work completed must include any GST that is included in the prices the builder has received from his subcontractors and suppliers. 4. In the event that it becomes necessary to draw down all or part of the retention to pay for work rectified by another contractor because the builder refused to do it, GST will be payable when the funds are spent. 5. GST is applicable to the sum drawn down.

8 Scenario 7 Your company has been approached to undertake the design and administration of a major refurbishment of a recent significant building regarded by many members of the profession and the wider community as a modern classic. The original architect has not been approached to undertake this work. The client sees elements of the original building design as a commercial problem and is seeking a fresh approach to the refurbishment. Your company has recently received a number of architectural awards for buildings constructed predominantly of glass. It is this aesthetic that has attracted the owner of the building, the subject of this commission to contact you. It is expected that you will change the nature of the building to reflect the new minimalist aesthetic. Although you have some reservations about this approach the commission is the highpoint of your architectural career and will secure your company s financial viability for years to come. 1. You must decline the commission. 2. You should accept the commission without reservation. 3. You should advise the client about recent changes to the Copyright Amendment (Moral Rights) Act Under the Copyright Amendment (Moral Rights) Act 2000 you are legally bound to contact the original architect and advise him/her of your appointment to refurbish the building and invite his/her comment on your initial design concept.

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

qbcc Insurance Policy Conditions Edition 8 1 queensland building and construction commission

qbcc Insurance Policy Conditions Edition 8 1 queensland building and construction commission qbcc queensland building and construction commission Insurance Policy Conditions Edition 8 1 Effective 1 July 2009 Dear Homeowner, These documents are your Home Warranty Insurance Policy and Insurance

More information

Building Work Contractors Act 1995

Building Work Contractors Act 1995 Version: 21.11.2015 South Australia Building Work Contractors Act 1995 An Act to regulate building work contractors and the supervision of building work; and for other purposes. Contents Part 1 Preliminary

More information

MANAGED BUILDER PROGRAM (MBP) BUILDER AGREEMENT

MANAGED BUILDER PROGRAM (MBP) BUILDER AGREEMENT MANAGED BUILDER PROGRAM (MBP) BUILDER AGREEMENT Mailing Address: PO Box 194, Georges Hall NSW 2198 Ph: (02) 8713 1800 Fax: (02) 8713 1818 Section 1 - Contractor Details (MBP Service Provider) Name Registered

More information

Essex Recruitment Services: Terms of Engagement of Limited Company Contractors to Supply Workers to Clients (Opted Out) 1. Definitions 1.

Essex Recruitment Services: Terms of Engagement of Limited Company Contractors to Supply Workers to Clients (Opted Out) 1. Definitions 1. Essex Recruitment Services: Terms of Engagement of Limited Company Contractors to Supply Workers to Clients (Opted Out) 1. Definitions 1.1 In these terms of engagement the following definitions apply:-

More information

Conditions of Contract

Conditions of Contract Amberley Main Street Upgrade Contract No. 10/21 10/21 - Amberley Main Street Upgrades CC Page 1 of 24 C Contents Conditions of Contract Table of Contents Page GENERAL CONDITIONS OF CONTRACT 3 FIRST SCHEDULE

More information

Explaining an architect s services. General information on the usual tasks undertaken by an architect

Explaining an architect s services. General information on the usual tasks undertaken by an architect Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against

More information

New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions

New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions ACRS Lic No. A021974 Lic No. 192237C New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions *Definitions are in clause 19 1. FORMATION OF AGREEMENT 1.1 Acceptance of Quotation The Customer must accept

More information

Advertising Terms & Conditions

Advertising Terms & Conditions Nova Entertainment Pty Ltd - Advertising Terms and Conditions This document sets out the terms and conditions which apply to the provision of advertising services by any radio station owned or operated

More information

ARTWORK COMMISSION AGREEMENT

ARTWORK COMMISSION AGREEMENT ARTWORK COMMISSION AGREEMENT THIS AGREEMENT is made the day of in the year BETWEEN the Minister for Works of Level 6, 16 Parkland Road, Osborne Park, WA 6017 being the body corporate created under Section

More information

EXTENT OF THE ARCHITECT S LIABILITY ON A BIM PROJECT

EXTENT OF THE ARCHITECT S LIABILITY ON A BIM PROJECT 03 06 EXTENT OF THE ARCHITECT S LIABILITY ON A BIM PROJECT BY PATRICK PERRY AND LAURA COATES BUILDING DESIGN WHITEPAPERS 33 6.1 COLLABORATION AND RISK The use of bim on a construction project raises issues

More information

Becoming an owner-builder

Becoming an owner-builder Becoming an owner-builder An owner builder is an individual who does owner builder work and holds a permit for that work under the authority of a permit issued by NSW Fair Trading. What is owner-builder

More information

Calliden Builder Warranty Insurance. South Australia and Western Australia. About Calliden. The Agent. Privacy Statement. Important Information

Calliden Builder Warranty Insurance. South Australia and Western Australia. About Calliden. The Agent. Privacy Statement. Important Information Low Rise Multi Unit Development Project Application Form Calliden Builder Warranty Insurance (South Australia and Western Australia) About Calliden Calliden Insurance Limited (Calliden) (ABN 47 004 125

More information

Building Act 2000. Ministerial Insurance Order Required Insurance for Building Practitioners 2008

Building Act 2000. Ministerial Insurance Order Required Insurance for Building Practitioners 2008 Ministerial Insurance Order - Required Insurance for Accredited Building Practitioners 2008 approved on 15 July 2008. Published in the Tasmanian Government Gazette on 30 July 2008 and effective 30 August

More information

Professional Indemnity Proposal Form

Professional Indemnity Proposal Form Professional Indemnity Proposal Form IMPORTANT NOTES This insurance cover is based upon representations given to us by you. Should any particulars have changed or be incorrect you must notify us immediately.

More information

1.3 These Conditions may only be amended or varied by written agreement signed by both Parties.

1.3 These Conditions may only be amended or varied by written agreement signed by both Parties. TERMS AND CONDITIONS OF SALE AND PROVISION OF SERVICES 1. Sale of goods / Provision of services 1.1 Monash University ( Monash ) provides the goods and/or services subject to these terms and conditions,

More information

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES GENERAL CONDITIONS OF CONTRACT FOR MINOR WORKS PAGE 1 BASE D ON WA LOCAL GOVERNMENT ASSOCIATION MODEL 2010 TABLE OF CONTENTS 1 INTERPRETATION 2 RISE

More information

PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM

PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM IMPORTANT TICES - `CLAIMS MADE CONTRACTS OF INSURANCE Please read the following carefully before completing this proposal form: Your professional indemnity

More information

CONTRACTOR AND SUPPLIER INSURANCE REQUIREMENTS

CONTRACTOR AND SUPPLIER INSURANCE REQUIREMENTS CONTRACTOR AND SUPPLIER INSURANCE REQUIREMENTS SCOPE This Policy applies to all staff globally. POLICY (Note: Relevant guidelines and procedures are incorporated within or attached as appendices) Comcover

More information

Master Agreement for the Supply of Services - Limited Company

Master Agreement for the Supply of Services - Limited Company Master Agreement for the Supply of Services - Limited Company TERMS AND CONDITIONS DEFINITIONS "The Agent" "The Supplier" "The Contractor" "The End-User" "The Services" Work-Seeker Legislation Fees max20

More information

Tender forms and letters 1. Final accounts 7 Cost items 7 Presenting the final account 9. Retention and defects liability period 11.

Tender forms and letters 1. Final accounts 7 Cost items 7 Presenting the final account 9. Retention and defects liability period 11. Contents Tender forms and letters 1 Final accounts 7 Cost items 7 Presenting the final account 9 Retention and defects liability period 11 Summary 14 Tender forms and letters Often clients/architects require

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

TERMS & CONDITIONS 1. DEFINITIONS & INTERPRETATION DEFINITIONS

TERMS & CONDITIONS 1. DEFINITIONS & INTERPRETATION DEFINITIONS This Agreement governs the supply of any Goods and Services by AV 24/7 Pty Ltd or any of its Related Bodies Corporate ( AV 24/7 ) to you ( the Customer ). Unless otherwise specifically agreed in writing

More information

NAB Equity Lending. Facility Terms

NAB Equity Lending. Facility Terms NAB Equity Lending Facility Terms This document contains important information regarding the terms and conditions which will apply to your NAB Equity Lending Facility. You should read this document carefully

More information

Professional Indemnity Insurance Specialist Supplier Presentation

Professional Indemnity Insurance Specialist Supplier Presentation Bespoke Ready-Mix insurance Professional Indemnity Insurance Specialist Supplier Presentation EXCLUSIVE FOR MEMBERS OF THE SOUTHERN AFRICAN READY MIX ASSOCIATION ("SARMA") So what is a Professional Indemnity

More information

Home Warranty Insurance Claim Form

Home Warranty Insurance Claim Form Home Warranty Insurance Claim Form General WFI Insurance Limited (ABN 24 000 036 279) trading as Lumley Insurance offers Builders Home Warranty Insurance to owner Builders and Licensed Builders in the

More information

Low Rise Multi Unit Development Project Application Form RBUA Builder Warranty Insurance (South Australia and Western Australia)

Low Rise Multi Unit Development Project Application Form RBUA Builder Warranty Insurance (South Australia and Western Australia) Low Rise Multi Unit Development Project Application Form RBUA Builder Warranty Insurance (South Australia and Western Australia) About the Insurer This insurance is underwritten by Great Lakes Reinsurance

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Motor Equity Insurance. Product Disclosure Statement and Policy Document.

Motor Equity Insurance. Product Disclosure Statement and Policy Document. Motor Equity Insurance Product Disclosure Statement and Policy Document. Table of contents About this Insurance page Our Product Disclosure Statement 3 Understanding your policy and its important terms

More information

15 For clarification and other details Please contact: 1. Asst. Manager - 8978027919 Please Note:

15 For clarification and other details Please contact: 1. Asst. Manager - 8978027919 Please Note: TENDER NOTICE 1 Name of the work and place Electrical works at sbi.intouch BRANCH (KADAPA), Y.S.R. District, Andhra Pradesh. 2 Estimated Cost Rs.9,51,186/- 3 Date of issue of tender through 23/06/16 Bank

More information

Employer s Liability. Accident report form. Policyholder details. Injured employee. Please return this form to:

Employer s Liability. Accident report form. Policyholder details. Injured employee. Please return this form to: Employer s Liability Accident report form Please return this form to: Please: Read this form fully before filling it in and where possible answer all questions in CAPITALS. Do not take any action in connection

More information

CUBS SUPERANNUATION FUND Trust Deed. The Trust Company (Superannuation) Limited (Trustee)

CUBS SUPERANNUATION FUND Trust Deed. The Trust Company (Superannuation) Limited (Trustee) CUBS SUPERANNUATION FUND Trust Deed The Trust Company (Superannuation) Limited (Trustee) Table of contents Part 1A - The Cubs Superannuation Trust... 1 Section 1 - Normal Operation of the Fund... 1 1 Joining

More information

Commercial Terms of Business Agreement

Commercial Terms of Business Agreement Commercial Terms of Business Agreement The purpose of this document is to set out our professional relationship and the services we will provide to you. This is our standard client agreement upon which

More information

NZIA Standard Construction Contract

NZIA Standard Construction Contract New Zealand Institute of Architects Incorporated NZIA Standard Construction Contract NZIA SCC 2014 Between The Principal Norrie Family Trust And The Contractor For Contract Norrie Home At

More information

SOFTWARE DEVELOPMENT AGREEMENT

SOFTWARE DEVELOPMENT AGREEMENT SOFTWARE DEVELOPMENT AGREEMENT THIS AGREEMENT dated the day of 20. BETWEEN: AND: ACN of (the Customer ; 1iT Pty Ltd ACN 092 074 247 of 41 Oxford Close West Leederville (the Contractor. BACKGROUND A. The

More information

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS RBI Asset Management (Pty) Ltd P O Box 7192 Halfway House 1685 Tel: 011 805 7933 Fax: (086) 675-9194 E-mail: geoff@rbi.co.za RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS 1. DEFINITIONS These Conditions,

More information

CHAPTER 43-03 ARCHITECTS AND LANDSCAPE ARCHITECTS

CHAPTER 43-03 ARCHITECTS AND LANDSCAPE ARCHITECTS CHAPTER 43-03 ARCHITECTS AND LANDSCAPE ARCHITECTS 43-03-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Architect" means an individual who is registered as an architect under

More information

1.1 The following words and expressions have the following meanings, unless they are inconsistent with the context:

1.1 The following words and expressions have the following meanings, unless they are inconsistent with the context: Terms and Conditions 1 Interpretation 1.1 The following words and expressions have the following meanings, unless they are inconsistent with the context: Applicant means a company or business registered

More information

Contract Terms and Conditions Of Engagement Of Limited Company Suppliers

Contract Terms and Conditions Of Engagement Of Limited Company Suppliers 1. DEFINITIONS In these terms of engagement the following definitions apply:- NP The Client The Company The Contractor The Assignment The Terms means Nationwide People Limited. means the person, firm or

More information

CIVIL DISBURSEMENTS FUND GUIDELINES

CIVIL DISBURSEMENTS FUND GUIDELINES CIVIL DISBURSEMENTS FUND GUIDELINES TABLE OF CONTENTS: Introduction... 2 Definition... 2 1. Selection of Cases... 2 2. Assessment of Applications... 2 3. Means Test... 3 4. Merits Test... 4 5. Contribution...

More information

PROFESSIONAL PRACTICE EXAM 27 MARCH 2014

PROFESSIONAL PRACTICE EXAM 27 MARCH 2014 PROFESSIONAL PRACTICE EXAM 27 MARCH 2014 PAPER 1: This is closed book paper. Answer all questions Total marks for this paper - 100 marks Time allowed for Paper 1-3 hours Pass mark for the examination -

More information

Macquarie Rewards Program. Terms and Conditions

Macquarie Rewards Program. Terms and Conditions Macquarie Rewards Program Terms and Conditions EFFECTIVE 20 NOVEMBER 2015 1 Contents 1. When do these Terms and Conditions apply to me? 1 2. How does the Macquarie Rewards Program work? 2 3. Administration

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

DOMAIN NAME REGISTRATION SERVICES TERMS AND CONDITIONS

DOMAIN NAME REGISTRATION SERVICES TERMS AND CONDITIONS DOMAIN NAME REGISTRATION SERVICES TERMS AND CONDITIONS 1. INTERPRETATION 1.1 In this Agreement the following terms shall have the following meanings: Agreement Bundled Services Domain Names Fees Initial

More information

Bankwest Qantas Rewards

Bankwest Qantas Rewards Credit Cards Bankwest Qantas Rewards Terms and Conditions 1 October 2014 making banking easier Customer enquiries Please call 13 17 19 or visit bankwest.com.au. Where to report lost or stolen cards or

More information

GOVERNANCE COMMITTEE 16 JULY 2014

GOVERNANCE COMMITTEE 16 JULY 2014 23 GOVERNANCE COMMITTEE 16 JULY 2014 3 STATE GOVERNMENT LEGISLATIVE REVIEW - WORK HEALTH & SAFETY ACT 2011; WORK HEALTH AND SAFETY REGULATION 2011; WORKERS COMPENSATION AND REHABILITATION ACT AND WORKERS

More information

ASDEFCON Handbook. (Shortform Services)

ASDEFCON Handbook. (Shortform Services) ASDEFCON Handbook (Shortform Services) Table of Contents 1 When should you use ASDEFCON (Shortform Services)?...1 2 Is ASDEFCON (Shortform Services) suitable for your particular Simple Procurement?...1

More information

CONTRACT WORKS INSURANCE MADE TO MEASURE

CONTRACT WORKS INSURANCE MADE TO MEASURE CONTRACT WORKS INSURANCE MADE TO MEASURE If you are considering any type of renovation, alteration, demolition or extension to your home, it is important to realise the effect that this has on your household

More information

Bankwest Qantas Rewards Program for the Bankwest Qantas Transaction Account

Bankwest Qantas Rewards Program for the Bankwest Qantas Transaction Account Page 1 bankwest.com.au Bankwest Qantas Rewards Program for the Bankwest Qantas Transaction Account Terms and Conditions 30 November 2015 This booklet covers the terms and conditions that apply to the Bankwest

More information

Special Terms and Conditions for Savings/Deposit Accounts Opening and Closing Accounts Applications 3. Payments from your Account

Special Terms and Conditions for Savings/Deposit Accounts Opening and Closing Accounts Applications 3. Payments from your Account Special Terms and Conditions for Savings/Deposit Accounts (Please note that these Special Terms and Conditions apply in addition to the General Terms and Conditions for Business. In the event of a conflict

More information

Motor Equity Insurance. Policy Document (Product Disclosure Statement) 216469 POL373 Alph cov_d1.indd 2 6/03/13 12:47 PM

Motor Equity Insurance. Policy Document (Product Disclosure Statement) 216469 POL373 Alph cov_d1.indd 2 6/03/13 12:47 PM Motor Equity Insurance Policy Document (Product Disclosure Statement) 216469 POL373 Alph cov_d1.indd 2 6/03/13 12:47 PM Preparation Date: 01/03/2013. 216469 POL373 Alph cov_d1.indd 3 6/03/13 12:47 PM Table

More information

STR Builders Pty Ltd. The 7 things you MUST ask BEFORE signing your Building Contract

STR Builders Pty Ltd. The 7 things you MUST ask BEFORE signing your Building Contract STR Builders Pty Ltd The 7 things you MUST ask BEFORE signing your Building Contract STR Builders Pty Ltd 2 Buying a new home will likely be the largest purchase you ever make. You may be embarking on

More information

Blackpool & The Fylde College SICK PAY POLICY. Agreed Date: April 2013

Blackpool & The Fylde College SICK PAY POLICY. Agreed Date: April 2013 Blackpool & The Fylde College SICK PAY POLICY Agreed Date: April 2013 Review Date: April 2015 Contents 1. Scope and Policy 3 2. Accountability 3 3. Learner Involvement 3 4. Statutory Sick Pay 4 5. Entitlement

More information

Chartered Accountants Australia & New Zealand Professional Indemnity and Management Liability Proposal Form

Chartered Accountants Australia & New Zealand Professional Indemnity and Management Liability Proposal Form Chartered Accountants Australia & New Zealand Professional Indemnity and Management Liability Proposal Form SECTION 1: Professional Indemnity 1. Insured Details 1.1 Is at least one principal, director

More information

NIBA College of Insurance Brokers and Risk Professionals Membership Rules

NIBA College of Insurance Brokers and Risk Professionals Membership Rules NIBA College of Insurance Brokers and Risk Professionals Membership Rules 1. Role of the College 1.1 The NIBA College of Insurance Brokers and Risk Professionals (College) aims to provide high quality

More information

SCHEDULE: TERMS OF AGREEMENT

SCHEDULE: TERMS OF AGREEMENT TR Doc Ref: AB/1234/56789/100/Schedule/v1.00 Schedule to the SCHEDULE: TERMS OF AGREEMENT FOR CONTRACTOR SERVICE SUPPLY AGREEMENT NO: SCHEDULE NO: 1.00 BETWEEN: Technology Resourcing

More information

Companies Regulations (COR)

Companies Regulations (COR) Appendix 9 In this appendix underlining indicates new text and striking through indicates deleted text. N.B. As mentioned in paragraph 7 of this consultation paper, these regulations are made under the

More information

4.1 The property and any copyright or other intellectual property rights in any Input Material shall belong to the Subscriber.

4.1 The property and any copyright or other intellectual property rights in any Input Material shall belong to the Subscriber. 1 Interpretation 1.1 In these Conditions: THE SERVICE PROVIDER means Cutec Remote Backup Terms and Conditions THE SERVICE PROVIDER S STANDARD CHARGES means the charges shown in the Order Sheet or other

More information

STANDARD MORTGAGE TERMS AND CONDITIONS

STANDARD MORTGAGE TERMS AND CONDITIONS STANDARD MORTGAGE TERMS AND CONDITIONS The terms and conditions on the following pages are the standard terms and conditions that apply to each memorandum of mortgage signed. The Registrar-General of Land

More information

2. GENERAL RULES. 2.1 Operator's Decision or Determination

2. GENERAL RULES. 2.1 Operator's Decision or Determination 2. GENERAL RULES 2.1 Operator's Decision or Determination If any circumstance arises which is not provided for by these Rules, it shall be subject to the Operator's decision or determination. 2.2 Discretion

More information

CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES.

CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES. CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES. Licensed Building Practitioners skills maintenance If you are a Licensed Building Practitioner (LBP) you can gain skills

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

Standard Conditions of Appointment. Architect s Copy ONLINE VERSION ONLINE VERSION ONLINE VERSION. for an Architect (CA-S-07-A)

Standard Conditions of Appointment. Architect s Copy ONLINE VERSION ONLINE VERSION ONLINE VERSION. for an Architect (CA-S-07-A) Standard Conditions of Appointment for an Architect (CA-S-07-A) Architect s Copy Royal Institute of British Architects RIBA Agreements are produced in association with: the Royal Incorporation of Architects

More information

Standard conditions of purchase

Standard conditions of purchase Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out

More information

Business Insurance Proposal

Business Insurance Proposal Business Insurance Proposal Important Notices You must read the notices below. If you have any questions please contact GWS Genco Group (AFSL No. 231210) Duty of Disclosure This Policy is subject to the

More information

No amendments will be made to any of the conditions in this Building Agreement

No amendments will be made to any of the conditions in this Building Agreement No amendments will be made to any of the conditions in this Building Agreement RESIDENTIAL BUILDING AGREEMENT BETWEEN: MASTERTON HOMES PTY LIMITED Builder s Licence 35558C 76 Heathcote Road, Moorebank

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

How To Make A Contract Between A Client And A Hoster

How To Make A Contract Between A Client And A Hoster Web Hosting Terms & Conditions Please read these web-hosting terms carefully, as they set out our and your rights and obligations in relation to our web hosting services. AGREEMENT: Whereas: (1) The Ruby

More information

Parkes Lees Architects Ltd

Parkes Lees Architects Ltd Parkes Lees Architects Ltd Working with an architect guide Cornwall 01566 772 035 Exeter 01392 311 940 Parkes Lees Architects Ltd 4 Broad Street, LAUNCESTON Cornwall PL15 8AD contents what an architect

More information

Welcome to Toozly. These Employer Terms apply to You if You place any Job Ads on Toozly.

Welcome to Toozly. These Employer Terms apply to You if You place any Job Ads on Toozly. Employer Terms Welcome to Toozly. These Employer Terms apply to You if You place any Job Ads on Toozly. By accepting these Employer Terms, You also accept the Site Terms. We may vary the Site terms and

More information

Guide to lodging a certified building permit application (form BA1)

Guide to lodging a certified building permit application (form BA1) Guide to lodging a certified building permit application (form BA1) If you lodge an incomplete application to the permit authority, it can be refused and you may lose your fees. These notes are to assist

More information

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance SC 01 - Contract Performance Guarantee Insurance For contracts equal to or exceeding 750,000 in value the Contractor shall, within 28 days of the date of the award of the Contract, obtain and provide to

More information

HSBC s Credit Card Rewards Program. Terms and Conditions HSBC Classic Credit Card and HSBC Platinum Credit Card

HSBC s Credit Card Rewards Program. Terms and Conditions HSBC Classic Credit Card and HSBC Platinum Credit Card HSBC s Credit Card Rewards Program Terms and Conditions HSBC Classic Credit Card and HSBC Platinum Credit Card As at 1 March 2014 Rewards Plus Program The meaning of words printed like this and some other

More information

ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS 4905 2002. Part A

ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS 4905 2002. Part A ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS 4905 2002 Part A This Annexure shall be completed and issued as part of tender documents and subject to

More information

RTI Statement for New Starters Please tick the relevant box below:

RTI Statement for New Starters Please tick the relevant box below: EXTERNAL ID Application to become a HYDRA PAYE Operative First Name: Address: Middle Name(s): Surname: Date of Birth: Town: N.I Number: Postcode: Nationality: Mobile Number: Email: Bank Details Bank Name

More information

UCC Supplementary Life Assurance Scheme Member s Booklet

UCC Supplementary Life Assurance Scheme Member s Booklet UCC Supplementary Life Assurance Scheme Member s Booklet Sub-Title taking care of you... Introduction University College Cork (UCC) has established the UCC Supplementary Life Assurance Scheme (the Scheme)

More information

Application for Credit (Business Account)

Application for Credit (Business Account) Application for Credit (Business Account) APPLICANT INFORMATION Structure Public Company Proprietory Company Sole Proprietor Partnership Company Trading As Trustee for ACN / ABN Phone Fax Mobile Email

More information

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES Names of Parties 1. (Company Name) of (Company Address) ( Consultancy ). 2. Redline Group Ltd of 26-34 Liverpool Road, Luton. Beds LU1

More information

IMPORTANT NOTICES: Your duty, however, does not require disclosure of matter:

IMPORTANT NOTICES: Your duty, however, does not require disclosure of matter: IMPORTANT NOTICES: CLAIMS MADE POLICY This Proposal is for a policy issued by ProRisk on a claims made and notified basis. This means that the policy only covers claims first made against you during the

More information

BUILDING AND CONSTRUCTION AUTHORITY SINGAPORE CONDITIONS OF TENDER

BUILDING AND CONSTRUCTION AUTHORITY SINGAPORE CONDITIONS OF TENDER BUILDING AND CONSTRUCTION AUTHORITY SINGAPORE CONDITIONS OF TENDER TENDER NO : TENDER DESCRIPTION : THE LICENCE OF STORAGE PLOT AT THE PULAU PUNGGOL AGGREGATE TERMINAL EVALUATION CRITERIA 1. Unless otherwise

More information

Macquarie Bank Rewards Program. Terms and Conditions

Macquarie Bank Rewards Program. Terms and Conditions Macquarie Bank Rewards Program Terms and Conditions Effective December 2012 1 Contents 1. When do these Terms and Conditions apply to me? 31 2. How does the Macquarie Bank Rewards Program work? 3 3. Rewards

More information

Software Support and Maintenance Terms

Software Support and Maintenance Terms Software Support and Maintenance Terms 1. Definitions and interpretation 1.1 This agreement uses some terms with special meanings. These terms are set out in schedule 1 to this agreement. The schedule

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

Professional Indemnity Insurance Proposal Form Miscellaneous

Professional Indemnity Insurance Proposal Form Miscellaneous Commercial & General Insurance Brokers (Aust) Pty Ltd Suite 4, 1016 Doncaster Road Doncaster East Victoria 3109 Phone: 1300 764 244 Fax: 03 8841 4299 Email: pi@cgib.com.au Web: www.cgib.com.au AFS License:

More information

Consumer Code. for Home Builders

Consumer Code. for Home Builders Consumer Code for Home Builders This document contains the Consumer Code requirements together with non-mandatory good practice guidance for Home Builders Second Edition January 2010 Contents Meaning of

More information

ATCO Gas Australia Commercial Gas Connection Request (CGR) Terms and Conditions Version Jan2015

ATCO Gas Australia Commercial Gas Connection Request (CGR) Terms and Conditions Version Jan2015 ATCO Gas Australia Commercial Gas Connection Request (CGR) Terms and Conditions Version Jan2015 1. Definitions ATCO Gas Australia means ATCO Gas Australia Pty Ltd ACN 089 531 975 Authorised Representative

More information

Second report on the costs of the Australian Government s Run-Off Cover Scheme for midwife professional indemnity insurers. 2011-12 financial year

Second report on the costs of the Australian Government s Run-Off Cover Scheme for midwife professional indemnity insurers. 2011-12 financial year Second report on the costs of the Australian Government s Run-Off Cover Scheme for midwife professional indemnity insurers 2011-12 financial year Commonwealth of Australia 2014 ISBN 978-0-642-74954-3 Ownership

More information

Unibet Tipping Competition Terms and Conditions

Unibet Tipping Competition Terms and Conditions Unibet Tipping Competition Terms and Conditions 1. Conditions of Entry (a) By entering this competition entrants accept these Terms and Conditions. (b) Entry is open to Australian residents aged 18 years

More information

How often do you see that?

How often do you see that? 5 % AER* variable Interest and Instant Access How often do you see that? The Access Plus Deposit Account *4.92% gross variable Access Plus not your everyday deposit account It pays you 5%* AER (4.92% Gross)

More information

Policy of Insurance under the HBCF (Home Building Compensation Fund)

Policy of Insurance under the HBCF (Home Building Compensation Fund) Policy of Insurance under the HBCF (Home Building Compensation Fund) How to read the policy (i) The policy covers you for the types of loss, and for the amounts of loss, described in clause 1. (ii) Clause

More information

Employer commencement as a self-insurer

Employer commencement as a self-insurer External Guideline #21 Employer commencement as a self-insurer Version 4 1 April 2015 Contents 1 Overview... 4 2 Employer election... 4 3 Election to assume tail claims... 5 3.1 Transfer date... 5 3.2

More information

Terms and Conditions for Certification, Assessment Services and TradeMark Licence

Terms and Conditions for Certification, Assessment Services and TradeMark Licence Terms and Conditions for Certification, Assessment Services and TradeMark Licence To be read in conjunction with your application. For contact information, please refer to the back page. Terms and Conditions

More information

Directions for Using Electronic Duties Return (EDR)

Directions for Using Electronic Duties Return (EDR) Directions for Using Electronic Duties Return (EDR) December 2012 Index What is Electronic Duties Returns? 3 Special tax arrangement 3 Conditions of approval 3 Introduction to Electronic Duties Returns

More information

(INDIVIDUALS ONLY) IndContPkge Version: 1.7 Updated: 18 Jul. 03

(INDIVIDUALS ONLY) IndContPkge Version: 1.7 Updated: 18 Jul. 03 INDEPENDENT CONTRACTOR PACKAGE (INDIVIDUALS ONLY) IndContPkge Version: 1.7 Updated: 18 Jul. 03 Contents Preface 2 Checklist 3 Helpful Hints 4 Frequently Asked Questions 5 Agreement with an Independent

More information

How To Write A Water Meter

How To Write A Water Meter Template of Agreement between Scottish Water and Utility Connection Provider A signed agreement between Scottish Water and the Utility Connection Provider and is part of the accreditation process. Work

More information

Workers compensation insurance. Application

Workers compensation insurance. Application Workers compensation insurance Application Workers compensation insurance Please complete this application carefully to ensure that it meets your needs. How to complete this form 1. Read the important

More information

GlaxoSmithKline Consumer Healthcare Australia Pty Ltd (ABN: 68 603 310 292) TERMS AND CONDITIONS OF SALE (Effective as at 7 th September 2015)

GlaxoSmithKline Consumer Healthcare Australia Pty Ltd (ABN: 68 603 310 292) TERMS AND CONDITIONS OF SALE (Effective as at 7 th September 2015) GlaxoSmithKline Consumer Healthcare Australia Pty Ltd (ABN: 68 603 310 292) TERMS AND CONDITIONS OF SALE (Effective as at 7 th September 2015) 1. DEFINITIONS In these terms and conditions: (1) Adverse

More information

Appendix A. Call-off Terms and Conditions for the Provision of Services

Appendix A. Call-off Terms and Conditions for the Provision of Services Appendix A Call-off Terms and Conditions for the Provision of Services Where an Order Form is issued by the Authority that refers to the Framework Agreement, the Contract is made between the Authority

More information

PROPERTY OWNERS INSURANCE PROPOSAL

PROPERTY OWNERS INSURANCE PROPOSAL PROPERTY OWNERS INSURANCE PROPOSAL Please use BLOCK CAPITALS and tick boxes where applicable. Where requested enter further details in the space provided. If there is insufficient space please continue

More information

Architects and Intellectual Property: Protecting Your Building Plans and Designs

Architects and Intellectual Property: Protecting Your Building Plans and Designs Architects and Intellectual Property: Protecting Your Building Plans and Designs Michael Bampton, Partner 1 Introduction Architects are engaged to provide a wide range of services including preparing drawings,

More information