Submitted to: Mindoro Resources Limited

Size: px
Start display at page:

Download "Submitted to: Mindoro Resources Limited"

Transcription

1 PRELIMINARY ECONOMIC ASSESSMENT Agata Nickel Project Mindanao Philippines Submitted to: Mindoro Resources Limited REPORT Report Number R-Rev1 Distribution: Jon Dugdale, Mindoro Resources Limited Peter Geddes, Mindoro Resources Limited

2 1.0 TITLE PAGE Mindoro Resources Limited is evaluating the development of the Agata nickel laterite deposit in Northern Mindanao, Philippines. The Agata project site is about 47 km north northwest of Butuan City and 73 km southwest of Surigao City, Mindanao Island, Philippines. Independent Qualified Persons: Peter Onley, MBA, MSc, FAusIMM, CP, MAIG Principal Golder Associates is responsible for geology, Mineral Resource estimation, residue management, water management, and economic analysis. Tony Showell, B App Sc (Metallurgy) FAusIMM Principal Metallurgist Battery Limits Pty Ltd is responsible for metallurgy and process design. Effective Date: 29 March 2011 Report Number R-Rev1 Report No R-Rev1 i

3 2.0 TABLE OF CONTENTS 1.0 TITLE PAGE...i 2.0 TABLE OF CONTENTS...ii 3.0 SUMMARY General Preamble Authors Project Location Scope of Work Geology and Mineral Resource Economic Analysis Capital Costs Operating Costs Sensitivity Analysis Mining Operations Mining Schedule Conclusions Recommendations Processing and Plant Design Mineral Processing Background Plant Design Processing Technology Process Preparation Leach Plant Products Section Major Process Packages Infrastructure Residue Management Port Facilities Utilities Water Power Hydrogeology and Water Management Report No R-Rev1 ii

4 3.7.1 Hydrogeology Water Management Environment and Social Environment Community Engagement Occupational Health and Safety Conclusions and Recommendations Geological Setting Conclusions Recommendations Drilling Conclusions Sampling Method and Approach Conclusions Recommendations Sample Preparation and Security Conclusions Recommendations Data Verification Conclusions Mineral Resource and Mineral Reserve Estimates Conclusions Recommendations Metallurgy Conclusions Recommendations Residue Tailings Management Recommendations Environment Recommendations Community Engagement Recommendations Occupational Health and Safety Report No R-Rev1 iii

5 Recommendations INTRODUCTION Previous Studies Summary Resource Estimation Mine Plan Early Production Acid Leaching Options RELIANCE ON OTHER EXPERTS PROPERTY DESCRIPTION AND LOCATION Location Land Tenure ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY Accessibility Topography, Climate and Vegetation HISTORY GEOLOGICAL SETTING Geology DEPOSIT TYPES MINERALISATION EXPLORATION DRILLING Agata SAMPLING METHOD AND APPROACH Drill Sampling Density Determinations SAMPLE PREPARATION, ANALYSES AND SECURITY Analytical Laboratories Sampling and Analytical QAQC DATA VERIFICATION Independent Review ADJACENT PROPERTIES Report No R-Rev1 iv

6 18.0 MINERAL PROCESSING AND METALLURGICAL TESTING Introduction Testing at Enlin Stainless Steel Corporation Ore Samples Sizing Analyses Ore Slurry Thickening Atmospheric Leaching (AL) HPAL Testing Saprolite Neutralisation CCD Settling Iron Removal Nickel-Cobalt Precipitation Testing at SGS Lakefield Oretest (SGS) Testwork Samples Mineralogy Head Analyses Ore Scrubbing and Head Sizing Heap Leaching Amenability Testing Feed Mineralisation Settling Testwork High Pressure Acid Leach Testing Atmospheric Leach Testing Saprolite Neutralisation Testwork Combined HPAL, AL Slurry Saprolite Neutralisation Testwork AL Slurry Settling Testwork on Saprolite Neutralised Slurry Limestone Calcination and Activity MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES Unfolding Data Preparation Grades Sample Length Geology Model Geology Interpretation Independent Review Report No R-Rev1 v

7 Exploratory Data Analysis Compositing Grade Capping Variography Density Block Model Estimation Validation of Block Models Resource Classification Selectivity, Mineralisation Loss and Dilution Assessment of Reasonable Prospects of Economic Extraction Mineral Resource Statement Mineral Reserve OTHER RELEVANT DATA AND INFORMATION Preliminary Hydrological and Hydrogeological Assessment Mining Plan General Mining Inventory Mining and Plant Feed Schedule Metallurgy Process Plant Introduction Process Selection Development of Process Design Criteria Preparation of Mineralisation High Pressure Acid Leaching Atmospheric Leaching Saprolite Neutralisation Counter-Current Decantation Metal Recovery Mass Balance Calculations Process Description Overview Leach Plant Report No R-Rev1 vi

8 Product Section Plant Services Plant and General Infrastructure Introduction Existing Regional Infrastructure Site Development Process Plant Site Power Supply Power Station Power Usage Summary Power Reticulation System voltage and frequency Water General Water Requirements Concept Design Water Reticulation Water Treatment Seawater Supply Port Bulk Liquid Handling Heavy Fuel Oil Diesel Fuel Bulk Solids Handling Bulk Sulphur Handling and Storage Bulk Limestone Handling and Storage Fuel Tank Farm Liquid and Solid Waste Management Waste Water Treatment Solid Municipal Waste Management Plant Process Control System Buildings Plant Site Buildings Report No R-Rev1 vii

9 Town/Village Access Roads Communications Overview Communications Infrastructure and Equipment Security and Fencing Residue Management Introduction Review of existing Information Residue Management Options Overview Engineering Design Criteria and Assumptions Candidate RSF Locations Cost Estimate Conclusions Preliminary Hydrological and Hydrogeological Assessment Water Management Plan Open Pit Dewatering Environment Summary Overview Environmental Baseline Information Permitting and Approvals Outstanding Environmental Concerns Community Engagement and Social Concerns Summary Performance Review Project Impacts and Community Expectation Community Engagement Environment Health and Safety Summary Overview Site EHS Report No R-Rev1 viii

10 21.0 INTERPRETATION AND CONCLUSIONS Geological Setting Drilling Sampling Method and Approach Sample Preparation and Security Data Verification Mineral Resource and Mineral Reserve Estimates Mining Metallurgy Economic Analysis RECOMMENDATIONS Geological Setting Sampling Method and Approach Sample Preparation, Analyses and Security Drilling Mineral Resources and Mineral Reserves Mining Metallurgy and Process Residue (Tailings) Management Environment Community Engagement Occupational Health and Safety Economic Analysis Risk REFERENCES DATE AND SIGNATURE ADDITIONAL REQUIREMENTS FOR TECHNICAL REPORTS ON DEVELOPMENT PROPERTIES AND PRODUCTION PROPERTIES Mining Operations Recoverability General HPAL Atmospheric Leaching Report No R-Rev1 ix

11 Saprolite Neutralisation Counter-Current Decantation Iron/Aluminium Removal Mixed Hydroxide Product Overall Recoveries Markets Mixed Hydroxide Product Contracts Environment Considerations Taxes Capital Cost Estimate Capital Cost Summary Scope of the Capital Cost Estimate Basis of the Capital Cost Estimates Capital Estimate Exclusions Operating Costs Operating Cost Summary Basis of the Agata Nickel Project Operating Cost Estimates Operating Cost Estimate Exclusions Economic Analysis Economic model input parameters Life of Mine Project Financials Sensitivity Analysis TABLES Table 3-1: Agata Deposit Laterite Mineral Resource (Ni ), September Table 3-3: Capital Cost Estimate for the Agata Nickel Project PEA... 4 Table 3-4: Operating Cost Estimate... 4 Table 3-5: Risk Assessment and Mitigation... 5 Table 3-6: Mining Inventory Estimate... 6 Table 3-7: Plant Feed Summary... 7 Table 3-8: Revised Design Parameters for PEA... 9 Table 3-9: Unit Rates Estimated Table 3-10: Estimated Daily Water Requirements Report No R-Rev1 x

12 Table 13-1: Summary of drilling campaigns Table 18-1: Mineralisation Sample Head Analyses Table 18-2: Limonite Sizing Results Table 18-3: Selected HPAL Test Results Table 18-4: HPAL Discharge Solution Assays Table 18-5: Selected Saprolite Neutralisation Test Results Table 18-6: Selected HPAL Test Results Table 18-7: Source of Metallurgical Test Samples Table 18-8: Head Analyses of Metallurgical Composites Table 18-9: Scrubbing Test Results Table 18-10: Agglomeration Test Results Table 18-11: Mineralisation Slurry Settling - Key Parameters Table 18-12: HPAL Test Results on Limonite Transition Mineralisation Samples Table 18-13: AL Tests on Saprolite Samples Table 18-14: AL Test Solution Composition Table 18-15: Saprolite Neutralisation Testing Table 18-16: Saprolite Neutralisation Test Results- AL Table 18-17: Settling Tests on Saprolite Neutralisation Slurry Table 19-1: Agata Deposit Laterite Resources (Ni ), September Table 20-1: Material Types Table 20-2: Mining Inventory Table 20-3: Plant Feed Targets Table 20-4: Ex-Pit Mined Summary Table 20-5: Mining Schedule Table 20-6: Plant Feed Summary Table 20-7: HPAL Design Criteria Table 20-8: AL Design Criteria Table 20-9: Saprolite Neutralisation Design Criteria Table 20-10: CCD Design Criteria Table 20-11: Power Summary Table 20-12: Water Consumption Summary Table 20-13: Summary of Initial and Deferred Capital Costs included in the Scoping Study Table 21-1: Summary of Financial Analysis Results Table 21-2: Operating Costs Table 22-1: Risk Assessment Table 25-1: Recoveries by Mineralisation Type Report No R-Rev1 xi

13 Table 25-2: Rehabilitation Costs Table 25-3: Capital Cost Estimate for the Agata Nickel Project PEA Table 25-4: Operating Cost Estimate for the Agata Nickel Project PEA Table 25-5: Capital Cost Estimates Table 25-6: Operating Cost Assumptions Table 25-7: Summary Cash Flow Table 25-8: Project Cash Flow Table 25-9: NPV USD m Sensitivity to Economic Assumptions FIGURES Figure 3-1: Sensitivity Analysis... 5 Figure 3-2: Mine Production Schedule... 7 Figure 3-3: Plant Feed and Material Type... 8 Figure 6-1: Site location of the Agata Nickel Project Figure 9-1: Agata Project Area (after Gifford, 2010) Figure 9-2: Agata laterite resource (After Mindoro, 2010) Figure 9-3: Local Geology Map of Northern area of the Agata deposit Project Area (from Gifford, 2010) Figure 9-4: Northern area of the Agata deposit Laterite Profile (After Mindoro, 2010) Figure 13-1: Drill hole plan showing Figure 13-2: Core drilling at Agata Project Figure 13-3: Core recovery from Agata Project Figure 18-1: Acid Bottle Roll Test Results Figure 18-2: Saprolite Neutralisation Test Results - HPAL/AL/SN Figure 19-1: Bedrock, Saprolite, and topography triangulations in cross-section (After Gifford, 2010) Figure 19-2: Probability plots showing Ni% distribution of LF, LA and LB samples within modelled Limonite zone Figure 19-3: Ni% and Mg% distributions for Bolder and Saprolite samples within SAP modelled domain Figure 20-1: Pit Extents Figure 20-2: Pit Areas & High Magnesium zones Figure 20-3: Mining Panels Figure 20-4: Mining Schedule Graphic Figure 20-5: Mining Volumes per Quarter Figure 20-6: Mine Production Schedule by Material Type Figure 20-7: Candidate Valley RSF Locations Figure 21-1: Sensitivity Analysis Figure 25-1: Operating Cost by Cost Centre Figure 25-2: Cumulative Cashflow Figure 25-3: Project Sensitivity Report No R-Rev1 xii

14 APPENDICES APPENDIX A Certificates of Qualified Persons APPENDIX B Consents of Qualified Persons Report No R-Rev1 xiii

15 3.0 SUMMARY 3.1 General Preamble MRL Gold Phils., Inc. is a 100% owned Philippine subsidiary of Mindoro Resources Ltd. (Mindoro), a company incorporated in Alberta, Canada and listed on the TSX Venture Exchange and the ASX. Mindoro is currently investigating the potential to develop its Agata nickel laterite deposit in Northern Mindanao, Philippines. A November 2010 Scoping Study performed by Boyd Willis Hydromet Consulting (BHWC) and Ausenco Vector for Mindoro concluded that the establishment of a hydrometallurgical processing plant to treat the ROM limonite and saprolite materials was viable assuming continued resource growth. This PEA Technical Report summarises the current development options and provides a preliminary economic assessment of the project Authors This PEA Technical Report is prepared by Golder Associates Pty Ltd (Golder) under the direction and supervision of Peter Onley, an independent qualified person with Golder Associates Pty Ltd and Tony Showell, an independent qualified person with Battery Limits Pty Ltd. Golder Associates Pty Ltd have reviewed the geology, mining, metallurgy, process design, residue and water management, environment, community engagement and occupational health and safety and economic analysis included in this PEA Technical Report. Peter Onley and Tony Showell as joint Qualified Persons have authorised the technical information detailed in this Preliminary Economic Assessment (PEA) Technical Report Project Location The Agata Project is located within the northern part of Agusan del Norte province in northeastern Mindanao, Republic of the Philippines. It lies within the Western Range approximately 10 kilometres south of Lake Mainit (Figure 6-1). The Agata Project falls within the political jurisdiction of the municipalities of Tubay, Santiago and Jabonga. The Agata Project is centred at E, 9 17 N Scope of Work Mindoro Resources Ltd (Mindoro) plans to develop the Agata Nickel Project in the Philippines. Golder Associates Pty Ltd (Golder) is requested to provide a cost estimate to prepare a Preliminary Economic Assessment report to conform to Canadian NI and Australian JORC (2004) standards. The scope of work provided by Jon Dugdale of Mindoro in s dated 18 January and 7 February 2011 is auditing and reviewing all relevant information and including the following documents to be provided by Mindoro: Agata Resource Report, (Mark Gifford and QG, September 2010) Scoping Study (Boyd Willis, September 2010) Additional acid leach metallurgy and impact on costs and feed proportions (limonite/saprolite, etc) prepared by Boyd Willis DSO Scoping Study (Peter Geddes) internal Mindoro report Mine and processing schedules based on preliminary modelling (Dallas Cox and Boyd Willis) Economic modelling of preferred project plan (Michael Conan-Davies) Metallurgical review will be undertaken by BatteryLimits Pty Ltd under Golder name for inclusion in the PEA. Report No R-Rev1 1

16 The PEA is a step towards starting the PFS after current exploration and Resource estimation is completed in The PEA will indentify significant issues and conceptual options for development of the Agata Project for evaluation in the PFS The studies provided by Mindoro will be reviewed to a preliminary and not technical audit level to identify possible key issues. The PEA will include a preliminary review, a project development concept based on Mindoro studies and data and recommendations for further work for the following: Exploration Geology, Resource Estimation and grade control Geotechnical Mining, mine planning and estimation of mining inventory for scheduling and scheduling Scoping study metallurgy, processing, additional acid leach metallurgy, test work and metallurgical reports completed since the scoping study Residue (Tailing) Management Water Management: Surface water and hydrogeology Environment Community Engagement Occupational Health and Safety Compliance with JORC and NI , governance and permitting, regulations and for mining, environment and OHS Review economic and sensitivity analysis prepared by Mindoro Significant issues and risk management Geology and Mineral Resource The Agata Nickel Project is based on a tropical nickel laterite typical of the Philippines. The Agata Nickel Project has estimated combined Measured and Indicated Resources of 32.6 Mt at 1.04% Ni, and an inferred resource of 1.7 Mt at 1.04% Ni for a combined t of nickel, as reported in Mindoro s NI compliant Mineral Resource estimate of 8 September 2010, using a cut-off grade of 0.5% Ni for limonite and 0.8% Ni for saprolite. The summary of the NI compliant Mineral Resource is presented in Table 3-1. Report No R-Rev1 2

17 Table 3-1: Agata Deposit Laterite Mineral Resource (Ni ), September 2010 kt (dry) Ni % Co % Fe % Al % MgO % SiO 2 % Measured Limonite Saprolite Sub-Total Indicated Limonite Measured and Indicated Saprolite Sub-Total Limonite Saprolite Total Inferred Limonite Saprolite Total Economic Analysis The PEA economic model prepared by Mindoro indicates a nickel project based on hydrometallurgical processing justifies further investigation. Mindoro has commenced a pre-feasibility study (PFS) on the Agata Nickel Project. An economic analysis using the discounted cashflow (DCF) methodology has been prepared based on the high pressure acid leach (HPAL) and atmospheric leaching (AL) and saprolite neutralisation (SN) hydrometallurgical process described in this report. The project has a net present value (NPV) of USD390 M at a 10% after tax discount rate. Based on the mining schedules, capital and operating costs and a long term nickel price of USD10 per pound. A summary of the PEA financial model is presented Table 3-2. The currency for all estimates is US dollars (USD) Table 3-2: Summary of Financial Analysis Results Nickel Price USD/lb USD8.50 USD10 USD12 NPV (10% discount rate) Post Tax USD M IRR Post Tax % 14% 19% 26% Sensitivity analysis also shows that the project is robust to changes in economic modelling assumptions. The analysis has identified that the project is most sensitive to factors which impact on revenue (nickel price, feed grade and recovery) followed by capital costs. The project is least sensitive to operating cost estimates Capital Costs The project costs are presented in Table 3-3 are estimated in February 2011 US dollar (USD) values. Report No R-Rev1 3

18 Table 3-3: Capital Cost Estimate for the Agata Nickel Project PEA Description Capital Costs (Million USD) Ore Preparation 29.5 Leach Section Products Section 10.1 Sulphuric Acid 92.8 Power Plant 48.0 Other Major Process Packages 7.5 Services and Utilities 26.5 Process Plant Infrastructure General Infrastructure 23.8 Total Direct Cost EPCM 62.8 Other Construction Services 58.8 Total Indirect Cost Direct + Indirect Cost Contingency Total Project Cost Project Cost, USD/annual lb Ni Operating Costs Operating cost estimates are presented in Table 3-4. Table 3-4: Operating Cost Estimate Average Annual USD M USD/lb Ni Mining Labour Sulphuric Acid Processing Utilities Maintenance G&A Marketing Indirects Total Operating Costs before by-products Cobalt by-product Credits 17.3 {0.45} Power by-product Credits 19.6 {0.51} Total Operating Costs after by-products Report No R-Rev1 4

19 3.2.3 Sensitivity Analysis Sensitivity analysis also shows that the project is robust to changes in economic modelling assumptions. The analysis has identified that the project is most sensitive to factors which impact on Revenue (nickel price, feed grade and recovery) followed by capital costs. The project is least sensitive to operating cost estimates. The relative sensitivity of the project to revenue, capital and operating cost estimates is illustrated in the sensitivity chart below. Figure 3-1: Sensitivity Analysis The sensitivity analysis undertaken on the financial model has identified revenue assumptions as the highest risk factor in the financial performance of the Agata Project. A summary of risks identified and strategy to mitigate risk is provided in Table 3-5 Table 3-5: Risk Assessment and Mitigation Revenue Risk Factor Commodity Price Exchange Rate Feed grade Recovery Royalties Capital Cost Exchange Rate Design Mitigant Robust project with significant operating margin Operating costs and Revenue denominated in USD self hedging Undertake additional drilling and resource modelling Mine Scheduling Ore pre-treatment Further metallurgical test work to confirm assumptions Trade-off analysis of acid consumption vs recovery Negotiate agreements with Federal, State & local jurisdictions Hedging of currency at time of purchase Undertake pre-feasibility and feasibility study Report No R-Rev1 5

20 Contingency Risk Factor Operating Cost Sulphuric Acid Price Sulphuric Acid consumption Power Price Labour costs Taxes & compensation Permitting & Approvals Mining Permit Land Access Mitigant Maintain a high level of contingency Installation of a sulphur/pyrite burning sulphuric acid plant which can use multiple sources of sulphur including Mindoro s own pyrite sourced from the Pan de Azucar Project Undertake further metallurgical studies and pilot plant testing Negotiation HoA for power off-take agreement Increased level of detail in manpower requirements and labour costs Negotiate agreements with Federal, State and local jurisdictions Company to continue with permitting and land access applications Golder recommend that the financial model is updated regularly as amended parameters and data comes to hand during the Pre-Feasibility Study. 3.3 Mining Operations Mining Schedule A preliminary mining and plant feed schedule referred to in this PEA as the mining inventory was developed for the first 15 years of operations. The mining inventory input to the mine production schedule (Table 3-6) is a subset of the Mineral Resource from the September 2010 NI estimate. The Mineral Resource was categorised into six material types according to iron grade in the limonite zone and magnesium grade in the saprolite zone for preparation of the mining inventory. The mining inventory includes Measured and Indicated Resources and approximately 5% of the mining inventory is Inferred Resources. No Mineral Reserve is estimated. The estimation of a mining inventory for input to a preliminary economic assessment is considered reasonable for a conceptual study. An open pit optimisation (Lerchs Grossman) evaluation was not completed to define the economic open pit limit. The pit shell used to develop the mining inventory was based on the lower the saprolite contact surface generated from available drill hole data. This method is considered reasonable for a conceptual study. An evaluation of economic cut-off grades and open pit limits is recommended as a further study. Table 3-6: Mining Inventory Estimate Mining Inventory Mbcm Mdmt Ni% Co% Fe% Mg% Al% AiO2% Ore Waste Total The pit shell was split into 63 mining panels generally 250 m 250 m in lateral extents. Three mining areas A, B and C were delineated based on geography and grade characterisation. This level of detail is considered adequate for a preliminary schedule for a conceptual study. The mining panels were scheduled in several iterations (over 60 quarterly periods commencing January 2014) and sequenced to generate a plant feed schedule (V9d) that maximised nickel production in the early Report No R-Rev1 6

21 years, but also maximised mineralisation feed to high pressure acid leach, saprolite neutralisation and Atmospheric Leach circuits. The mine production schedule by quarter and area is shown in Figure 3-2. Mining will be carried by open pit method using excavators, articulated dump trucks and ancillary support fleet. The mining schedule was smoothed over quarterly periods with mine production commencing at a rate of bcm per day, peaking in Year 10 at bcm per day. The average mine production rate over 15 years is bcm per day. Figure 3-2: Mine Production Schedule Table 3-7: Plant Feed Summary Item Total Limonite to HPAL Mdmt 9.5 Ni% 0.95 Saprolite (Low Mg) to HPAL Mdmt 4.7 Ni% 1.20 Saprolite (Medium Mg) to Atmospheric Leach Mdmt 6.0 Ni% 1.15 Saprolite (High Mg) to Saprolite Neutralisation Mdmt 5.2 Ni% 1.03 Plant Feed Mdmt 25.4 Ni% 1.06 Co% 0.06 Fe% 24.4 Mg% 11.0 Contained Metal Ni tonnes Co tonnes Recovered Metal Ni tonnes Co tonnes Report No R-Rev1 7

22 The schedule allows for the ramp-up of plant feed throughput over the first 3 years of operation to dmt per annum (Figure 3-3) which is maintained for the duration of the schedule. Plant feed is constrained by a limonite/saprolite ratio of 1:1.67 and a saprolite neutralisation/hpal ratio of Nickel metal production peaks at t per annum in Year 3. Figure 3-3: Plant Feed and Material Type Conclusions The mining inventory representing the estimated mill feed tonnage and quality includes Indicated and Inferred Resources. Approximately 5% of the mining inventory is classified as an Inferred Resource. No Measured Resource is currently reported in this PEA or previous Technical Reports documenting the Mineral Resource estimate. No Mineral Reserve estimate is reported in this PEA prepared as a conceptual level study. Mindoro has committed to proceeding with a PFS. The mineral inventory and scheduling are reasonable for the level of study. The equipment sizing used in the planning is appropriate for the size and style of operation and mining selectivity Recommendations Carry out fleet selection study based on version 9d schedule Carry out marginal cut-off grade study on material type categories based on March 2011 processing and financial models. Develop mining dilution and mineralisation loss criteria for application in future mining studies. Open pit optimisation to be run for future mine planning to improve delineate open pit deposit. Optimise mining and plant feed schedules with consideration to optimise stockpile balancing. Report No R-Rev1 8

23 3.4 Processing and Plant Design Mineral Processing Background A scoping study undertaken in 2010 examined three options for hydrometallurgical processing as follows: Base Case Separate leaching circuits for saprolite and limonite mineralisation followed by solution purification and metal refining. The design total nickel production in this option was 27,400 t/a. Increased Throughput Case (Also identified as Option 1) Similar to the Base Case with a larger throughput to produce 42,000 t/a nickel. Atmospheric Leaching Case (Also identified as Option 2) Saprolite leaching circuit only to produce 14,300 tpa of nickel contained in a mixed hydroxide product (MHP). This PEA includes a review of the 2010 Scoping Study and updated mine schedule and has incorporated changes to the process flowsheet based on metallurgical testwork results from the most recent testwork program. The key design feed and production parameters for the favoured option in the updated study, as adopted for the PEA, are presented in Table 3-8. Table 3-8: Revised Design Parameters for PEA Parameter Design Value for Year 3+ Limonite Mineralisation Feed Throughput tpa Grade Ni% 0.99 Saprolite Feed Co% Fe% 45.4 Mg% 1.06 Total Throughput tpa Low Mg Ore Ni% 1.27 Mg% Medium Mg Ore Ni% 1.22 Mg% High Mg Ore Ni% 1.07 Nickel Production Mg% 19.0 Total MHP Production wt/a dt/a Contained Nickel Production t/a M lb/a Contained Cobalt Production t/a Plant Design Processing Technology In the process plant, limonite mineralisation is treated by conventional high pressure acid leaching (HPAL) and saprolite mineralisation is treated by a parallel atmospheric leach (AL) circuit. The process design for the leach plant will be based largely on the hydrometallurgical route proven at Moa Bay in Cuba for 5 decades and at the Sumitomo/Nickel Asia operated Coral Bay Nickel Project (Coral Bay) in Report No R-Rev1 9

24 the Philippines since The leach flowsheet incorporates high pressure acid leaching and countercurrent decantation. Limonite and low magnesium saprolite mineralisation will be treated by conventional HPAL and medium magnesium saprolite mineralisation will be treated by a parallel atmospheric leach (AL) circuit. The PEA design throughput has been based on 1 Mtpa of mineralisation feed to HPAL (resulting in a HPAL circuit smaller in scale than that employed at Coral Bay). This was chosen because both autoclave trains at Coral Bay had very fast ramp-ups to full production. Autoclave throughput is based on 31% solids in the autoclave feed slurry (after direct steam heating). Additionally, the recent start of construction at the Taganito Nickel Project (a sister company of Coral Bay Nickel Company (CBNC)) in the Surigao District, also employing the HPAL process, is considered to be a major step towards launching the region into the ranks of globally important nickel laterite processing zones. A parallel atmospheric leaching circuit will treat about 38% of the saprolite mineralisation fed to the process. Atmospheric acid leaching is well established technology practised in many industries over several decades. Atmospheric Leaching of nickel laterites has gained recognition recently as an alternative to the high capital cost HPAL route, and was operated in parallel to the HPAL circuit at Ravensthorpe. The process is currently being investigated by Weda Bay Nickel (Eramet) in Indonesia, Berong Mining in the Philippines and BHP Billiton nickel projects to treat their high grade saprolitic material. An innovation in the proposed processing route will be the inclusion of saprolite neutralisation. This will involve pre-neutralisation of the residual free acid in the combined leach discharge streams using high magnesium saprolite ore. This process, performed at atmospheric pressure, will consume much of the free acid while recovering additional nickel and cobalt values from the saprolite ore. Neutralisation of the remaining acid will be achieved using limestone. The concept of saprolite neutralisation was first investigated for laterite ores from the Surigao district in testwork conducted in Recovery of 60 65% of the nickel and cobalt contained in the high magnesium saprolite mineralisation was achieved. In recent years much higher recoveries have been achieved in testwork for the Weda Bay (Indonesia), Sulawesi (Indonesia) and Mindoro (Philippines) nickel projects. Bench-scale testwork at SGS using Agata saprolite has demonstrated that recoveries of 83-89% are achievable. Higher recoveries may be possible and ongoing testwork on the Agata mineralisation may improve upon the PEA assumptions. After saprolite neutralisation, the pregnant solution will be recovered by conventional counter-current decantation (CCD), followed by limestone neutralisation of excess acid and precipitation of iron, aluminium and chromium, prior to metal recovery by mixed hydroxide product or precipitation (MHP). Metal recovery will be by a two-stage MHP circuit similar to that operated for several years at the Cawse Nickel Project (Western Australia) and more recently at Ravensthorpe Nickel Operation (Western Australia) Process Preparation The treatment plant includes separate circuits to treat limonite and saprolite ores. The limonite preparation circuit produces fully de-agglomerated limonite slurry for high pressure acid leaching (HPAL) and the saprolite circuit produces three types of ground saprolite slurry for HPAL, atmospheric leaching (AL) and saprolite neutralisation (SN). The limonite treatment plant comprises the following principal operations: primary crushing to <200 mm by roll sizer limonite de-agglomeration by wet rotary drum scrubbing and rejection of the coarse oversize fraction (>10 mm) by screening single stage, closed circuit ball milling to produce a ground limonite slurry HPAL feed slurry thickening. The saprolite treatment plant consists of the following principal operations: Report No R-Rev1 10

25 primary crushing to <200 mm by roll sizer single stage, closed circuit saprolite semi-autogenous grinding (SAG) milling to produce ground saprolite slurry storage tanks for three types of ground saprolite slurry: low magnesium saprolite, medium magnesium saprolite and high magnesium saprolite thickening of the medium magnesium saprolite and high magnesium saprolite slurries for delivery to atmospheric leaching and saprolite neutralisation Leach Plant HPAL feed is comprised of limonite and low magnesium saprolite slurries, which are combined in the required proportions in the HPAL feed thickener. The HPAL plant includes feed slurry heating, leaching of nickel and cobalt from limonite at high temperature (255 C) and pressure (4425 kpag), and autoclave discharge slurry pressure letdown. Atmospheric leach feed is comprised of medium magnesium saprolite slurry. In the atmospheric leach circuit nickel and cobalt are leached from saprolite at atmospheric conditions ( C and ambient pressure). Sulphuric acid is used as the lixiviant for both HPAL and atmospheric leaching. A recycle leach circuit utilises a small stream of sulphuric acid to re-dissolve nickel and cobalt precipitated in the downstream iron/aluminium removal and second stage MHP circuits. Discharge slurries from the HPAL, atmospheric leach and recycle leach circuits are combined and forwarded to the saprolite neutralisation circuit where the neutralising capacity of the high magnesium saprolite consumes some of the excess free acid. Additional nickel and cobalt are leached from high magnesium saprolite during this process. The resultant slurry flows to the CCD circuit, to separate and wash soluble nickel and cobalt from the leach residue solids. The recovered pregnant liquor is forwarded to two stages of iron/aluminium removal. In the first stage of iron/aluminium removal the majority of the remaining free acid in solution is neutralised with limestone slurry and most of the iron and some of the aluminium are precipitated. In the second stage of iron/aluminium removal the remaining iron and aluminium are precipitated. The pregnant liquor is separated from the precipitated solids by thickening prior to transfer to the MHP area. The thickener underflow slurry is directed to the recycle leach circuit for recovery of co-precipitated nickel and cobalt. The barren leach residue solids from the final stage of counter current decantation (CCD) washing along with barren solution from the MHP circuit report to final neutralisation circuit where most of the remaining metals in solution are precipitated. Treated residue is pumped to the residue storage facility (RSF) Products Section Nickel and cobalt are recovered as a mixed hydroxide precipitate (MHP). The virtually iron/aluminium-free pregnant leach solution (PLS) is forwarded to the first stage MHP reactors to precipitate the nickel and cobalt from the solution by the addition of magnesia slurry. The resulting precipitate contained in the slurry is thickened and forwarded to wash filtration where the precipitate is filtered for further dewatering and washed with demineralised water to displace the chlorides and other sea salts entrained with the precipitates. The filter cake is then repulped with demineralised water and filtered in a pressure filter to achieve the required product moisture specification. The MHP product is packaged in 2 t bulk bags and containerised for shipment and sale. The un-precipitated nickel and cobalt values remaining in solution after first stage MHP are recovered by lime precipitation in the second stage MHP reactors. The resulting precipitate is thickened and recycled back to the recycle leach area to re-dissolve the nickel and cobalt. Report No R-Rev1 11

26 Major Process Packages Major process packages include a sulphur-burning acid plant, a limestone slurrying plant, a lime kiln and lime slaking plant, a magnesia slurrying plant and a RSF. The sulphuric acid plant provides sulphuric acid for the leaching circuit and other process consumers, and high pressure steam for power generation. The acid plant products are up to 2700 t/d of 98.5% sulphuric acid and up to 152 t/h of steam. The limestone plant provides limestone in slurry form for neutralisation of acidic process liquors and crushed limestone for burnt lime production. The limestone plant consists of crushing and slurrying facilities. The lime plant provides lime in the form of milk-of-lime slurry for neutralisation of acidic process liquors and precipitation of nickel and cobalt in the second stage MHP circuit. The plant consists of a fuel-oil fired limestone calciner and lime slaking facilities. The magnesia slurrying plant provides magnesia slurry for the precipitation nickel and cobalt as mixed hydroxides in the first stage MHP circuit. The RSF area includes transport and storage facilities for process residue slurry. The impoundment area consists of a walled coastal valley located a short distance from the mine area. The neutralised tailings are pumped via a slurry pipeline to the RSF. 3.5 Infrastructure The provision of infrastructure is a significant part of the overall development of the project due to the greenfield nature of the proposed site. Existing infrastructure facilities are virtually non-existent in the immediate area of the proposed site except for an existing gravel public road and the exploration camp facilities. The facilities will be located predominantly in a coastal valley west of the mine site, as the topography is relatively flat compared to the steeper inland terrain. The infrastructure facilities to be provided for the project include: water supply and treatment power station and power reticulation port bulk materials handling fuel tank farm solid and liquid waste management plant control system plant site and service buildings and ancillary facilities accommodation village and facilities communications mobile equipment roads, and security services. Report No R-Rev1 12

27 3.5.1 Residue Management Golder has developed quantities for the following residue management approach: Management of residue generated in the first seven years in a valley RSF. Management of the remaining eight years of residue in the pit void, with the perimeter embankment raised as required to provide sufficient capacity. The cost for residue management has been based on unit rates adopted by Golder after a review of available information relating to similar projects in the Philippines. The sources of information include: Unit rates from our internal database, based on Contractor rates provided by our Manila office Unit rates estimated by Golder for a similar project Unit rates estimated by Ausenco Vector, provided by Mindoro Experience-based judgement from Golder personnel who have recently worked on Philippines-based projects. The unit rates adopted for this cost estimate are presented in the table below. Table 3-9: Unit Rates Estimated Item Unit Rate Clear and Grub USD0.50 per m 2 Liner System, including delivery and placement USD10.00 per m 2 Embankment Bulk Fill* USD10.00 per m 3 Liner Bedding Material USD12.50 per m 3 Excavation of Diversion Channel USD4.30 per m 3 * Including winning, hauling, placement, moisture conditioning and compaction Adopting these unit rates, the estimated costs are as follows: Capital Cost of Valley RSF = ~USD120 M This cost will be spent in Year 0 and the RSF provides residue management capacity for seven years or approximately 12.6 Mm 3. Deferred Capital Cost of In-pit RSF = ~USD133 M This cost will be spent in Years 6 and 7, ready for deposition in Year 8, and the RSF provides residue management capacity for an additional eight years or approximately ~14.4 Mm 3. Please note that the accuracy of the cost estimates presented in this PEA is about ±35%. A contingency amount of 40% would therefore typically be included at this level of study. The contingency has not been included in our cost estimate, as Mindoro has applied a contingency to the total capital cost estimate in the PEA. Our review of the Scoping Study indicates that the assumptions and approach appear to be reasonable, with the exception of selection of an above-ground RSF. Based on the survey provided, a suitable site for an above-ground RSF was not considered feasible within the extent of the survey provided. However, a valley RSF location was identified and costed to provide a comparison price. Based on our desktop study, it is recommended that a cost of USD120 M be adopted as the capital cost for residue management for the PEA. A further USD133 M should be allowed as deferred capital, to be spent during Years 6 and 7. Report No R-Rev1 13

28 3.5.2 Port Facilities The port will incorporate the following wharf facilities: the main berth accommodating: DWT liquid tankers for acid, heavy fuel oil and diesel fuel, DWT bulk cargo ships for sulphur and product despatch, and DWT barges a pipeline corridor and pumps for unloading liquid materials (diesel fuel, heavy fuel oil and acid) from the ships to storage tanks a 100 tonne crawler crane for loading and unloading containers admin office and warehouse. A heavy lift ramp is provided for unloading autoclaves and other heavy modules during construction. This ramp will be designed such that it can be utilised as a permanent facility for accessing heavy loads for construction for future expansion and/or for operations. 3.6 Utilities Water The scoping studies (Boyd Willis Hydromet Consulting, 2010 & Mindoro Resources, 2011), indicated that the main water requirements during the construction phase of the project and during mine operations and mine processing would be: Raw water for dust suppression and wash down Seawater for mineralisation slurrying Filtered raw water for general process plant use Raw and potable water for domestic use, and Demineralised water for steam generation and processing. The water requirements were estimated based on the process water balance and typical water demands. The estimated total daily water consumption for the Agata Nickel Project is summarised in Table Table 3-10: Estimated Daily Water Requirements Description Water usage (kl/d) Total Raw Water Filtered Water Demineralised Water Potable Water 100 Seawater The potential water sources include: Direct water abstraction and treatment of water from the Kalinawan River (referred to as the Tubay River in the scoping studies) Groundwater wells established in the alluvial aquifer of the Kalinawan Valley Groundwater wells established in fractured rock aquifers, and Direct abstraction and treatment of seawater with the intake situated in the port area. Report No R-Rev1 14

29 For the purposes of this study, we assumed that raw water will be sourced by means of direct abstraction of water from the Kalinawan River. The conceptual design for the water supply and major distribution system for this project has been divided into the following elements: Raw Water Pump station intake works at the Kalinawan River Pumping station at the Kalinawan River Pipeline from pumping station to raw water storage pond Raw water storage pond. Sea Water Pump station intake works at the proposed port site Pumping station at the proposed port site Pipeline from pumping station to seawater storage pond Seawater storage pond. The approximate capital cost associated with the water supply is about USD12.5 M (±50%) and includes supply and installation of the pump station intake works, pump station, pipeline and water storage facilities. It excludes power supply and reticulation as this has already been accounted for. Water Treatment The proposed raw water treatment system will produce three standards of quality: Filtered raw water for process and general plant use Potable water for human consumption and ablutions, and Demineralised water for boiler feed water and other process water requirements. A small water treatment plant will be required to supply potable water to meet the desirable drinking water standards recommended by the World Health Organisation (WHO) and national Department of Environment and Natural Resources (DENR) standards. The potable treatment system may include: Filtering to remove suspended solids Ultraviolet (UV) treatment to purify and disinfect the water from microbiological contaminants, and Chemical treatment such as chlorination to meet health requirements. Water treatment may also be required for the disposal of water to comply with the World Bank/International Finance Corporation (IFC) guidelines for marine discharge. A preliminary analysis of the water quality in the discharge liquor showed that the discharge water might be acceptable for discharge in the ocean (Boyd Willis Hydromet Consulting, 2010). For the purpose of the study, we assumed treatment would comprise only clarifiers before discharge into the ocean. The estimated costs associated with water treatment are: USD20 M for the filtered water, reverse osmosis (RO) plant required for demineralised water and potable water treatment plant (±100%), and USD9 M for the clarifier treatment of water prior to disposal into the ocean (±50%). Report No R-Rev1 15

30 3.6.2 Power The power station uses steam generators to provide electrical power for the operation of the process plant, services and utilities, as well as for the accommodation village and all other related infrastructure. High pressure steam is produced from two sources. The major source of high pressure steam is from waste heat boilers in the sulphuric acid plant. The secondary source of high pressure steam is from auxiliary boilers that will produce supplementary steam into the same header for the high pressure steam distribution system. The power station is designed to satisfy two main operating scenarios: generation of 30.9 MW of power, including 16.8 MW of power for normal plant operations, with 124 t/h of HP steam imported from the sulphuric acid plant provision of 7.8 MW of power and 16.3 t/h of process steam, to maintain leach plant operation, critical equipment in other areas, and the accommodation village during acid plant outages. The plant configuration comprises two 16 MW condensing steam turbine generators and two 25 t/h package boilers. The two boilers provide significant flexibility to meet varied steam demands. The selection of condensing turbines allows low pressure steam to be extracted for process use. In addition, for emergency conditions and the black start of the power station, there are two diesel powered generators located within the power station complex. These ex-construction generators will be of sufficient capacity for their intended long-term function. 3.7 Hydrogeology and Water Management Hydrogeology The Agata Project is located in a mountainous region with several creeks draining towards the Mindanao Sea on the western side and towards the Kalinawan Valley on the eastern side. The Kalinawan River is situated about 1 km east of the proposed mine area and flows in a southerly direction. Tumanda et al. (2004) report that the average discharge of the Kalinawan River is about 2 M m 3 /day (2000 ML/d) and more than adequate to meet project water requirements. The water quality of this river is very good (Coffey, 2008) with Total Suspended Solids (TSS) concentrations of about 2 mg/l and Total Dissolved Solids (TDS) concentrations of about 70 mg/l. Nutrient levels are low ranging between 0.2 to 1.2 mg/l nitrate. Lake Mainit is a large freshwater lake situated approximately 4 km north of the proposed mine area. The water quality of this lake is very good (Coffey, 2008) with TDS concentrations of about 80 mg/l and low nutrient concentrations. The groundwater potential in the mining region and port is probably poor. The geology is complex and the mine area is bound between two major strands of the Philippine Fault with one or more splays passing through the region. There are at least six different lithologies, each likely to have different aquifer characteristics. In the mining region, the laterites are developed over ultramafic rocks which lie along the Western Range. Groundwater is probably associated with fractured rock aquifers. These aquifers may have the potential to meet potable water supply but would probably not be sufficient for process water requirements Water Management Water associated with any aspect of the mining operation will be managed so that it would not have any detrimental impact on the environment and on mining operations. The water management plan would comprise: Sediment control structures required to capture any sediment-laden runoff from mine affected areas. This will avoid the release of suspended solids into the environment. The proposed sediment control Report No R-Rev1 16

31 structures would comprise earth embankment facilities to capture and store sediment-laden runoff and the release of clear water to the environment. Drains to divert non-impacted runoff from entering the mine workings; and Installation of buffer storage, pumping facilities and pipelines to ensure the site can cope with large rainfall events and subsequent flooding of the mine pits. The mine water management plan will also comprise drains to avoid downstream contamination of rivers, creeks and streams, provide facilities for the storage and disposal of low quality water and manage surface runoff from the process plant and other mine facilities. For the purposes of this study, we assumed that water management would include the following works: Sediment control structures Diversion channels and drains Flood protection earthworks Stormwater drainage systems, and In-pit pumps and pipeline. For the purposes of this PEA, it was assumed that the flood protection earthworks would form part of the mining operations and the stormwater drainage system would form part of the process plant infrastructure requirements. The estimated costs for the sediment control structures and diversion channels and drains is USD20 to 40 M. 3.8 Environment and Social Environment To date Mindoro has met environmental assessment requirements appropriately. Mindoro has also received two key environmental permits to operate. Mindoro now needs to focus on gaining the remaining environmental permits and ensuring all environmental permits apply to the new mine plan. Mindoro also should consider updating environmental information and establishing structured environmental management systems and documentation, as they are important components of meeting permitting requirements. Mindoro has undertaken baseline studies and impact assessments covering all relevant environmental aspects, however these studies were undertaken prior to development of the new 2010 mine plan. Golder reviewed summary information in the environmental impact statement (EIS) (Technotrix Consultancy Services Inc and Mediatrix Business Consultancy 2007) and concludes that studies were appropriate and reasonable Community Engagement Mindoro has demonstrated a comprehensive approach to community consultation and socio-economic impact studies to date as they have related to exploration activities. The existence of current relationships will only assist with the effectiveness of future programming as the project progresses towards feasibility studies and potential operations. The aim of the program appears well aligned to international standards for good practice engagement but no comment can be made on effectiveness until the program is implemented. Report No R-Rev1 17

32 3.8.3 Occupational Health and Safety Mindoro has recognised the importance of environment health and safety (EHS) at a corporate level and now needs to develop an EHS system on site as a matter of priority during all phases of project development. Mindoro is committed to EHS and oversees corporate actions through its corporate board EHS committee. In developing the Agata Nickel Project, Mindoro has identified the need to adhere to both local and international legislation and guidelines such as: World Bank Group Environmental, Health and Safety Standards for Mining including IFC Performance Standards Labour Code of the Philippines including occupational safety and health standards for all mining activities Sanitation Code of the Philippines. In addressing EHS requirements, Mindoro has committed to preparing a Health, Safety, Environment and Community Policy (HSEC) document jointly with the IFC. 3.9 Conclusions and Recommendations Geological Setting Conclusions Mindoro has a good understanding of geology and geomorphology controls on nickel mineralisation in the Agata region. The extent of the laterite, hence nickel mineralisation, is well defined by surface and outcrop mapping by Mindoro. The following items pose potential technical risks to the project: Transition material transition material may occur at the limonite and saprolite contact. In this style of deposit, it may occur over very short distances and thicknesses. Transition material will generally have poorer metallurgical properties than either pure limonite or saprolite. Variable and irregular contacts laterite deposits such as at AGATA DEPOSIT can be variable over short distances. Evidence from costean mapping indicates the potential for a high degree of variation in the limonite and saprolite surface, which may have an impact on mining technique, mining rates, mineralisation selectivity, and process recovery. Presence of boulders in similar deposits elsewhere in the region, poorly weathered boulders have a significant impact on recovery of saprolite ore. Definition of saprock Mindoro define saprock as less intensely weathered saprolite typically with lower nickel grade. In reality, the identification of saprock is by 0.4% Ni grade cut-off. This approach is consistent with industry norms. The nature of this transition from saprolite to saprock results in a highly irregular surface, which may have an impact on mining, mineralisation selectivity, and resource recovery Recommendations Metallurgical test work programs should attempt to identify preferred process streams for transition material. This might include defining parameters such as magnesium and/or iron cut-off grades for each process stream. The nature of contacts between limonite, saprolite, and saprock requires greater understanding. Feasibility programs should attempt to characterise the very short-scale (mining scale) irregularity through one or more of the following: Report No R-Rev1 18

33 Close-spaced (5 5 m) drilling programs Long (>20 m) and deep (~5 m) trenches in several orientations Geophysical surveys such as ground penetrating radar (GPR) Small-scale (~50 50m) trial mine The presence, frequency, and extent of boulders in the saprolite horizon also require better definitions. Another component of the feasibility study might include conditional simulation studies to assess potential mineralisation loss and dilution due to boulders and irregular contacts Drilling Conclusions Drilling techniques are industry standard and Golder considers them appropriate for nickel laterite deposits. Core recovery is good and procedures for recording depth and hole location are industry standard Sampling Method and Approach Conclusions Drilling, drill sampling and logging procedures are well documented and industry standard. Golder considers them to be appropriate for nickel laterite deposits. Mindoro also has QAQC systems in place that indicate good quality sampling and assaying. Regular independent verification and audits confirm good compliance with procedures and continuous improvement to methods and protocols. It is Golder s opinion that there are insufficient density measurements to qualify any part of the resource as Measured. Based on our experience, the dry bulk density values for limonite may be too high given the high moisture content and may impact on tonnages reported for Mineral Resources. Similarly, the preferential selection of competent core in saprolite may cause an over statement of saprolite density. However, it does not appear that Mindoro allows any density variation for boulders, which will be higher density than weathered saprolite Recommendations Mindoro should maintain the high standard sampling and QAQC protocols and systems currently in place for all future drilling and assaying programs. Golder recommends increasing the coverage of bulk density sampling. Sample sizes should be as large as practically possible. If Mindoro dig any pits similar to previous density sampling programs, consider measuring volume and weight of the total material from the pit. Mindoro may wish to investigate alternative density measurement methods such as downhole geophysical methods Sample Preparation and Security Conclusions Drilling, drill sampling and logging procedures are well documented and industry standard. Golder considers them as appropriate for nickel laterite deposits. Mindoro also has QAQC systems in place that indicate good quality sampling and assaying. Regular independent verification and audits confirm good compliance with procedures and continuous improvement to methods and protocols. Report No R-Rev1 19

34 Recommendations Mindoro should maintain the high standard sampling and QAQC protocols and systems currently in place for all future drilling and assaying programs. Mindoro should consider developing a suite of matrix-matched standard reference samples from AGATA DEPOSIT sample reject material to monitor the quality of future drilling and assaying programs Data Verification Conclusions Golder has not undertaken any independent data verification Mineral Resource and Mineral Reserve Estimates Conclusions The approach taken to build the geology is standard industry practice. It balances and validates subjective geological logging of drill samples with geochemistry to determine the position of lithology contacts. More than 10% of the modelled saprolite domain is consisted of boulder. This may present mining recovery and metallurgical recovery issues. The search parameters used for estimation are reasonable. The basis for the resource classification used by QG with classes defined by drill spacing is considered by Golder to be reasonable. Further drilling density assessment will be beneficial to the project progression. No Mineral Reserves are estimated in this PEA Recommendations Golder recommends further investigation about the nature of the limonite/saprolite contact. Priority 1 Occurrences of boulder and their associated grades in the saprolite modelled area needs to be further investigated and characterised. Golder believes that presence of boulder within the saprolite layer will present mining recovery and metallurgical recovery issues. Boulder has presently been mixed with saprolite in the current model and there is no indication of amount or grade of such material. It is recommended that conditional simulation studies be carried out. The simulation studies should include the simulation of the likelihood of intersecting boulder runs of various lengths within the saprolite. This will help characterise the risk of recovering saprolite for both mining and metallurgical purposes. Priority 2 Investigate the possibility of separating LF, LA and LB horizons for domaining purposes. Golder notes a lack of use of high grade cutting or high grade restraining. It is recommended that an assessment of high grade outliers be carried out prior to interpolation for the PFS. Investigate possibility of modelling variograms using unfolding techniques. Use variogram maps and directional variography to identify and model orientations of continuity. The 3D integrity of the variogram models need to be assessed to determine whether the models provide a satisfactory fit in other directions. Perform assessment of the smoothing effect associated with the current block model. Report No R-Rev1 20

35 Perform drilling grid analysis to better guide the PFS and DFS studies. Assessment of the uncertainty inherent in the geological model needs to be investigated. Priority 3 Investigate possibility of using m block size to better align with current drill spacing Metallurgy Conclusions Two metallurgical testwork programs have been conducted on mineralisation samples from the Agata deposit. The most recent program of work conducted at SGS Lakefield in Perth has shown that: Limonite mineralisation is amenable to processing by HPAL and has fast leaching kinetics with approximately 97-99% of the nickel extracted within 20 minutes of leaching time. Saprolite mineralisation is amenable to AL with favourable extractions of over 95% Ni in four hours. Other metallurgical characteristics are considered to be typical of tropical nickel-cobalt laterite mineralisation deposits. Further detailed programs of metallurgical testwork including locked cycle and continuous testing, as well as variability testing, should be undertaken in the next phase of testwork Recommendations Metallurgical testwork undertaken to date has been of a scoping nature. More detailed programs of work are required as part of the Feasibility Studies planned for the project. The work should include: Additional bench scale testwork on representative composite samples based on the mine schedule. Comprehensive leach variability testwork using samples from a range spatial pit locations, mineralisation types and grades throughout the deposit. This should include both HPAL and AL testing for the relevant mineralisation types, as well as slurry characterisation. Further evaluation for upgrading of limonite by large scale scrubbing tests and continuous scrubbing piloting. Continuous testwork and piloting of the total proposed circuit with recycling of intermediate streams. It is important that blending of composite samples for piloting reflects the amount of each mineralisation type in the deposit, including the three classifications of saprolite Residue Tailings Management Recommendations Our review of the Scoping Study indicates that the assumptions and approach appear to be reasonable, with the exception of selection of an above-ground RSF. Based on the survey provided, a suitable site for an above-ground RSF was not considered feasible within the extent of the survey provided. However, a valley RSF location was identified and costed to provide a comparison price. Based on our desktop study, it is recommended that an operating cost of USD10.49 per dry tonne of tailings, inclusive of a 25% contingency, be adopted for the PEA. Assuming a 15 year mine life at 1.6 Mtpa, plus a 12.5% contingency, the estimated cost for residue management is estimated to be USD284 M. The capital cost of the residue management is USD253 M excluding the 12.5% contingency summarised above. Mindoro is applying a global 30% contingency on all capital costs. Report No R-Rev1 21

36 3.17 Environment Recommendations Golder considers Mindoro s environmental actions should focus on obtaining outstanding environmental permits. Key factors are likely to be upgrading site environmental information and corporate environmental management systems. Golder recommends: Permitting and Approvals Reviewing the Philippine permitting and approvals process with respect to the new mine plan. Reviewing the existing environmental information against the applicable World Bank standards and identify gaps. Developing an environmental assessment program to address knowledge gaps in meeting both local and international environmental requirements. Undertaking the necessary assessments and updating environmental approval documentation accordingly. Environmental Management Completing an EMP for exploration activities that will provide the basis for a construction and subsequently operations EMP. Establishing an EMS that is upgraded as the project ramps up. The EMS need not be complex at this stage of project development but should refer to all relevant environmental management aspects Community Engagement Recommendations Golder recommends that more emphasis be placed on communicating the negative impacts of an operating mine, and associated environmental and social issues, particularly where those environmental impacts will directly affect current livelihoods and lifestyles. Achieving Free, Prior and Informed Consultation(s) (FPIC) for operations will require evidence that indigenous people understand the potential negative impacts as well as potential benefits of the entire project. This means involving stakeholders in information about the detailed design, operations and environmental impacts as a matter of course. Golder understands there is a particular challenge in the Philippines to reach vulnerable or less powerful groups, where community leaders and more privileged persons can sometimes dominate the attention of proponents. Environmental and social impact assessment should also seek and incorporate community feedback as part of the assessment and mitigation process. The key element of this process will be providing feedback to stakeholders who have been consulted and responding to their concerns in a detailed and effective way. Golder emphasises the limitations of this assessment as a preliminary desktop assessment and strongly recommends a comprehensive audit be conducted to accurately assess and characterise Mindoro s social performance to IFC standard. The scope for such an audit would include field assessments, interviews and a thorough analysis of documentation and reporting Occupational Health and Safety Recommendations We recommend a staged approach to the establishment of an EHS system that can be reviewed, updated and expanded as the project develops. The following core elements should be developed and implemented to assist in the management of key EHS risks for the project: Report No R-Rev1 22

37 Health and Safety Policy Fitness for Work Policy, including travel medicine and malaria risk Site Access and Control Procedures, including site induction, security and travel arrangements Hazard and Risk Management Procedure Incident Reporting and Investigation Procedure Site Health and Safety Plan Emergency Management Plan. These EHS components could be developed as standalone documents and form the basis of an EHS system. We recommend a project hazard workshop be held to inform and develop the scope of the EHS system and to ensure that the key risks are captured and systems are developed to manage them. Report No R-Rev1 23

38 4.0 INTRODUCTION Mindoro proposes to develop the Agata Nickel Project. The nickel laterite mineralisation will be mined by conventional strip mining and hauled to the plant at the coast. The process design is a combination of high pressure acid leach (HPAL), agitated tank atmospheric leach (AL) and saprolite neutralisation (SN) processing, producing a mixed hydroxide product (MHP). This PEA report identifies recommendations for development of the project to undertake a PFS. Mindoro has begun activities including metallurgical test work and resource exploration to support the PFS. 4.1 Previous Studies Summary The following Technical Reports were provided by Mindoro: Agata Resource Report, (Mark Gifford and QG, September 2010). Agata Nickel Project Scoping Study (Boyd Willis, September 2010) Additional acid leach metallurgy and impact on costs and feed proportions (limonite/saprolite, etc) prepared by Boyd Willis DSO Scoping Study (Peter Geddes) internal Mindoro report Mine and processing schedules based on preliminary modelling (Dallas Cox and Boyd Willis) Economic modelling of preferred project plan (Michael Conan-Davies). All references to dollars in this report are in United States Dollars (USD or US$) Resource Estimation The Agata Nickel Project has estimated combined Measured and Indicated Resource of 32.6 Mt at 1.04% Ni, and an Inferred Resource of 1.7 Mt at 1.04% Ni for a combined t of nickel, as reported in Mindoro s NI compliant Mineral Resource estimate of 8 September 2010, using a cut-off grade of 0.5% Ni for limonite and 0.8% Ni for saprolite. The summary of the NI compliant Mineral Resource is presented in Table Total metal contents in the reported resources represent metal in the ground and have not been adjusted for metallurgical recoveries and other factors which will be considered in a later study. Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing or other relevant issues Mine Plan A preliminary mining and plant feed schedule was developed for the Agata Nickel Project for the first 15 years of operations based on the September 2010 Mineral Resource (Cox, 2011). The mine plan estimates a mining inventory and schedule for feed to hydro-metallurgical process as contemplated in this PEA Early Production Direct Shipping Operation A conceptual level study into a direct shipping operation (DSO) of higher grade zones within the Agata resource was also considered as part of the PEA. However, due to the relatively low margins and current market uncertainty associated with DSO. Mindoro is not planning to pursue a stand-alone DSO at this stage. Golder will not consider this concept further in this report and it has not been included in the economic evaluation section of this PEA Report. Report No R-Rev1 24

39 Thermal Upgrading Concept Study Mindoro is examining the potential for thermal upgrading to enhance the value of the shipped product. An October 2010 Concept Study by Hatch Associates investigated thermal upgrading options to produce a value-added DSO product. Unprocessed laterite contains 30-45% moisture. Thermal upgrading is the process of removing moisture from the material, improving blending and handling properties and, most importantly, dramatically reducing the shipping cost, which in combination allows achievement of a premium price over DSO. Further upgrade of the nickel content can be achieved through optional process enhancements. Work is ongoing on this concept. Golder has not considered this further and it is not included in the economic section of this PEA report Acid Leaching Options An acid leaching study undertaken for Mindoro by Ausenco Vector (Vector, 2010) and Gifford (2010) for Mindoro evaluated three development options: Base Case a major integrated high pressure acid leach (HPAL), atmospheric leaching (AL) and saprolite neutralisation (SN) process. This option employs an autoclave of 4.7 metres internal diameter (m ID). The nickel will be recovered by direct solvent extraction (DSX) followed by Electrowinning (EW) to produce a Ni-cathode product. The base case is designed to produce tpa nickel as Ni-cathode. Option 1 a scale-up of the base case which employs the maximum HPAL autoclave size to date (5.4 m ID) as per the Ambatovy Nickel autoclaves in Madagascar. The nickel production for this option is increased to tpa nickel as Ni-cathode. Option 2 AL of saprolitic materials only. The nickel will be recovered by hydroxide precipitation producing an intermediate mixed hydroxide precipitate (MHP) product. The design capacity for this option is tpa nickel contained in MHP. The acid leaching study (Vector, 2010) provided this PEA processing options at ±30-35% accuracy and identified the accompanying issues such as environmental and technological risks. The process plant costs for the three options (with the exception of the refinery area for the Base Case and Option 1) were developed from detailed estimates for similar nickel projects and locations. The applicable data were adjusted for flow or equipment capacity and currency movements. The refinery area of the Base Case and Option 1 were costed separately by Canopean Pty Ltd. This PEA for the Agata Project was prepared for Mindoro by Golder in. The study is based on the scoping study (Mindoro, 2010) and additional work undertaken by Mindoro in resource estimation, mining, metallurgy and process design based on a modified base case processing plan producing 18,000 tpa nickel in mixed hydroxide product (MHP). Golder reviewed previous studies and completed scoping level assessment of the requirements for residue management, water, environment, health and safety and Personal Inspection by Qualified Persons Peter Onley, Golder Principal, visited the principal prospects in Agusan del Norte including the Agata Project from 23 May to 28 May 2010 specifically for the purpose of preparing an Independent Geologist s Report dated October 2010 Report Number R-Rev2. Tony Showell, Principal Metallurgist Battery Limits has not visited the Agata Site. Mr Showell has reviewed the metallurgy and process design prepared by Boyd Willis, Process Consultant Hydrometallurgy at Boyd Willis Hydromet Consulting for Mindoro. Mr Willis most recent visit to the Agata nickel laterite exploration sites located in Northern Mindanao, Philippines was in, for the purpose of identifying potential plant, port, infrastructure and tailings deposition sites for the recently commenced PFS. Report No R-Rev1 25

40 5.0 RELIANCE ON OTHER EXPERTS Jon Dugdale, B.Sc.(Hons), MAusIMM President, CEO, and Director of Mindoro Resources Limited is responsible for direction of Agata exploration and development studies. Tony Climie B.Sc.(Hons), P.Geol COO and Exploration Director of Mindoro Resources Limited is responsible for direction of exploration. Sia Khosrowshahi PhD MSc BSc CPG MAusIMM Principal, Golder Associates completed a review of geology and Mineral Resource Estimation. Dallas Cox, BE (Min) MAusIMM Principal Consultant Crystal Sun Consulting is responsible for mine design and planning. Mr Cox s most recent visit to the Agata nickel laterite exploration sites located in Northern Mindanao, Philippines was in April John MacIsaac MBA BE(Mining) MAusIMM Principal Mining Engineer Golder Associates completed a review of mine design and planning. His most recent visit to the Agata and Bolobolo nickel laterite exploration sites from 9 to 12 December Boyd Willis B App Sc (App Chem), MAusIMM Process Consultant Hydrometallurgy at Boyd Willis Hydromet Consulting is responsible for metallurgy and process design. Peter Chapman BEng BCom CPEng MIEAust Associate and Senior Tailings Engineer Golder Associates completed a review of residue management. Jan Vermaak PhD BSc (Hons) Member, International Mine Water Association, Member, International Association of Hydrogeologists, Associate and Senior Hydrogeologist Golder Associates completed a review of hydrogeology and hydrology. Rob Jessop, BSc, MSc, PhD Senior Ecological Scientist Golder Associates completed a review of environment, occupational health and safety and community engagement. Chris de Guingand, Fellow Certified Practicing Accountants (FCPA) Principal, Mineral Commerce Services Pty. Ltd, Melbourne is responsible for market analysis. Michael Conan-Davies BSc.(Hons) MSc.(Min Econ) MAusIMM, Director of MC-D Geo Pty Ltd prepared the economic modelling on behalf of Mindoro Resources Limited. Report No R-Rev1 26

41 6.0 PROPERTY DESCRIPTION AND LOCATION 6.1 Location The Agata Projects are located within the northern part of Agusan del Norte province in northeastern Mindanao, Republic of the Philippines. It lies within the Western Range approximately 10 kilometres south of Lake Mainit (Figure 6-1). The Agata Project falls within the political jurisdiction of the municipalities of Tubay, Santiago and Jabonga. The Agata Project is centred at E, 9 17 N. Figure 6-1: Site location of the Agata Nickel Project 6.2 Land Tenure The Agata Project is secured by MPSA XIII and Exploration Permit EP XIII registered to Minimax and Estrella Bautista respectively. Application has also been made for the Agata Extension EPA- 107-XIII to the south and east of the Agata MPSA. MPSA XIII was approved on 26 May 1999 and has been reduced from 99 to 66 blocks covering an area of 4995 ha. The fourth two-year exploration period on the tenement was granted on 19 June On 20 May 2008, an Environmental Compliance Certificate (ECC) was issued by the DENR to Mindoro for nickel laterite mineral production covering 600 ha within the Agata MPSA Contract area, including both the Northern area of the Agata deposit and Agata South tenements. In February 2005, the Philippine Supreme Court granted 100% foreign ownership of the mineral tenement under the Financial and Technical Assistance Agreement (FTAA). There are no known environmental liabilities other than those imposed by the Philippine Mining Act of Report No R-Rev1 27

42 The Agata-Bautista Exploration Permit EP XIII covers an area of ha. The EP was approved on 2 October 2006 and application was made for the first renewal on 29 September This was granted on 23 June 2010 and will expire on 22 June Mindoro s interests in the tenements are held by way of agreements with the original tenement holders. Mindoro entered into a Memorandum of Understanding (MOA) with Minimax on 19 January 1997 and Minimax assigned all its rights in the MOA to Mindoro on 27 June Under the terms of the MOA Mindoro has earned a 75% interests in the Agata, Tapian Main, and Tapian San Francisco and the Extension Projects (tenements acquired after the finalisation of the MOA) in the Surigao Mineral District. Mindoro has a further option to acquire an additional 25% direct and indirect participating interest. There are no dwellings within the Agata Project deposit area. Most local villages are populated by nonindigenous peoples but there are some indigenous peoples that live in the surrounding areas both within and close by the MPSA (Sitio Coro, EMorgado, La Paz, Santiago, and Tagmamarkay). Report No R-Rev1 28

43 7.0 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 7.1 Accessibility The Agata Project is located approximately 10 km south of Lake Mainit and 47 km north northwest of Butuan City in Agusan del Norte province, on the island of Mindanao. The site is accessible from either Surigao City or Butuan City via the Pan Philippine Highway which runs parallel to the length of the Agata MPSA, just outside the eastern boundary. A minor road crosses the northern portion of the MPSA area, near the Kalinawan River. Access is gained either by leaving the highway at Bangonay and then along 10 km of partly paved roads to E. Morgado or alternatively by leaving the highway at Santiago and then by 1.5 km of municipal road to La Paz. The latter route requires crossing the Kalinawan River by pump boat to a landing immediately below the project field exploration office. The northern part of the tenement is accessible on foot from E Morgado (approximately 1.5 km). Both Surigao City and Butuan City are major regional centres served by daily jet services from Manila and provide a broad range of services and facilities. 7.2 Topography, Climate and Vegetation The Agata Project is located on the Western Range which runs north northwest parallel to the coast of the Mindanao Sea to the west. The Kalinawan River to the east drains south from Lake Mainit. The western part of the area is rugged with a maximum elevation of 528 m above sea level. The western area has steep slopes and deeply-incised valleys while the floodplain of Kalinawan River to the east is generally flat with an elevation of less than 30 m. Within the project area, the nickel laterite is developed on a broad ridge bounded to the east and west by steep to very steep slopes incised by gullies and ravines. Elevations on the plateau range from 200 to 320 m where nickeliferous laterite is widespread. Climate in the area is wet tropical with no dry season and experiences months with very pronounced rainfall. Climatological Records from 1981 to 2000 show that peak rainfall months are from October to February. The highest mean monthly rainfall is 308 mm during January and the lowest mean monthly rainfall is mm during May while mean annual rainfall is 2027 mm. The plateau on which the laterite is developed was formerly rainforest. Since being logged it is now bracken dominated open grassland with sparse seedlings and saplings of planted species. A few secondary growth trees line the streams along the lower slopes. The floodplain of Kalinawan River is planted with tropical agricultural crops such as rice, corn and bananas. Report No R-Rev1 29

44 8.0 HISTORY The earliest recognised geological work done within the area is mostly from government-related projects including: The Regional Geological Reconnaissance of Northern Agusan reported the presence of gold claims in the region (Teves et al. 1951). Geologists from the former Bureau of Mines and Geosciences Regional Office in Surigao documented the results of regional mapping in the Jagupit Quadrangle. The United Nations Development Program (UNDP, 1982) conducted regional geological mapping at 1: scale and collected stream sediment samples over Northern Agusan. The UNDP report of 1984 described the geological evolution of this region and included a detailed stratigraphic column for the Agusan del Norte region. La Playa Mining Corporation, financed by a German company in the late 1970s, explored within the Agata Project area for chromiferrous laterite developed over weathered ultramafic rocks. There were five (5) test pits dug in the area. In 1987, Minimax conducted reconnaissance and detailed mapping and sampling. Geological mapping at 1:1000 scale was undertaken in the high-grading localities, and an aerial photographic survey was conducted and interpreted. Mindoro established a mining agreement with Minimax in January 1997, and commenced exploration in the same year. Report No R-Rev1 30

45 9.0 GEOLOGICAL SETTING 9.1 Geology The dominant structural feature in the regional is the Philippine Rift Fault, a major regional structure that extends for 1200 km in a north northwesterly direction over the length of the Philippines from southern Mindanao to northern Luzon. The fault is located approximately 200 km west of the Philippine Subduction System which dips west under the Philippines landmass and provides the main source of Tertiary volcanism and copper and gold mineralisation. It is also the key feature in the development of physiography. There is a close spatial and genetic association between epithermal precious metals and porphyry deposits. Typically, mineralisation is associated with Pliocene to Pleistocene igneous intrusions developed along splay structures to the main fault zone. Primary mineral deposits in the region are dominated by structurally controlled epithermal gold and porphyry copper-gold deposits. Tropical weathering of ultramafic rocks in the basement sequence has resulted in the development of lateritic nickel deposits. While Mindoro continues to explore for copper and gold that activity will not be discussed further in this report. The basement sequence comprises Cretaceous greenschist metamorphic rocks overthrust by Cretaceous Pangulanganan Basalts which themselves are overthrust by Humandum Serpentinite, probably during the Cretaceous. Laterite developed on the Humandum Serpentinite forms the major source of the nickel laterite sequence. The Humandum Serpentinite is overlain by Upper Eocene Mabanog Formation limestone and clastic sediments and Oligocene and Miocene volcanic rocks including conglomeratic andesite, pillow basalt and limestones. Intrusive events associated with the volcanism during this period resulted in the emplacement of plutons and stocks that are associated with porphyry copper-gold and precious metal epithermal mineralisation in the region. Geological mapping in the project area showed favourable development of laterite on the plateau where drilling by Mindoro has focused. Where the topography is steeper, the laterite tends to be thinner. Mindoro recognises two geomorphic features influencing laterite formation with consequent nickel enrichment. The eastern part of the mineralisation is developed on an area of moderate relief and laterite is thinner and contains boulders suggesting transport. The western laterite occurs in an area of low relief resulting in a thick, well developed profile with higher grade mineralisation. Report No R-Rev1 31

46 Figure 9-1: Agata Project Area (after Gifford, 2010) Figure 9-2: Agata laterite resource (After Mindoro, 2010) Report No R-Rev1 32

47 Figure 9-3: Local Geology Map of Northern area of the Agata deposit Project Area (from Gifford, 2010) Report No R-Rev1 33

48 Figure 9-4: Northern area of the Agata deposit Laterite Profile (After Mindoro, 2010) Report No R-Rev1 34

49 10.0 DEPOSIT TYPES The Agata Nickel Project is based on a single nickel laterite resource type that is typical of laterites developed on utramafic rocks in a tropical weathering environment. The nearest analogues to Agata are located on the east coast of Surigao del Norte at Taganito, Hinatuan and Nonoc. Other significant Philippine analogues includes the Coral Bay Operation on Palawan Island in the western Philippines operated by Sumitomo Mining & Metal Corporation. Other world class nickel laterite deposits that are analogous to Agata are located in New Caledonia, Indonesia and Papua New Guinea. Report No R-Rev1 35

50 11.0 MINERALISATION Nickel laterite deposits have developed over the ultramafic rocks. The mineralisation extends over about 520 ha within the tenements. The largest of the laterite areas is developed over the central ultramafic body. About 80% of the nickel laterite in the Agata Project has been tested by drilling to date. Nickel laterites are the products of intense chemical weathering of ultramafic rocks. Silica and other elements are leached from the rock resulting in the concentration of iron, nickel, chrome and cobalt from the parent rock into the weathering profile. Laterites form preferentially in stable terrains in the presence of wet tropical climates. Typical laterite is zoned parallel to the weathering surface. The uppermost horizon is classified as ferruginous laterite underlain by the limonitic zone (both are iron rich hematite, goethite, limonite and clay) which is again underlain by saprolite (magnesium rich clays). The interface between the fresh rock and the saprolite zone is classified as saprolitic rock or saprock and is characterised by the presence of garnierite. For the Agata Project drilling program, the horizons are classified according to nickel and iron content as follows: Ferruginous laterite <0.80% Ni, 30% Fe% Limonite 0.80% Ni, 30% Fe% Saprolite 0.80% Ni, <30% Fe% Saprolitic Rock <0.80% Ni, <30% Fe%. Reconnaissance geological mapping originally outlined an area of laterite covering approximately 600 ha. The southern part of the Agata deposit is the subject of Minimax-Mindoro-Delta agreement. Delta carried out a resource delineation program in the southern area in A regional mapping program was then carried out in 2008 to determine the potential nickel laterite areas throughout the tenement. Further potential for nickel laterite mineralisation was recognised on the adjacent Tapian Main, Tapian SF and Mat-I tenements. Report No R-Rev1 36

51 12.0 EXPLORATION La Playa Mining Corporation mapped the Agata area and dug test pits while exploring for chromiferous laterite beginning in La Playa subsequently withdrew as the mineralisation was not considered economic at that time. Minimax Corporation took up the tenements between 1996 and 1999 and Mindoro established a mining agreement with Minimax in January 1997 and began exploration later that year concentrating on the copper and gold potential. Discovery of lateritic nickel mineralisation within the northern part of the Agata deposit occurred in the early 1990s with grades confirmed by the development of test pits in Exploration of the Agata nickel laterite began in 2004 with Taganito Mining Corporation granted the non-exclusive right to assess the nickel laterite potential of the project. Results were encouraging with surface samples collected from an area of about 300 ha within a more extensive area of nickel laterite mineralisation returning assays up to 2.09%, with most of the values exceeding 0.5%. Mindoro signed an MOU with Queensland Nickel Phils. Inc. (QNPH), a subsidiary of BHP Billiton Ltd (BHPB) to allow QPNH to conduct exploration on the property. Reconnaissance drilling began in 2006 initially at a spacing of 200 m by 200 m later infilled to 100 m grid spacing. A total of 660 m were drilled in 35 holes over an area of approximately 80 ha, however, QNPH subsequently withdrew from the joint venture. Regional mapping indicated additional potential for nickel laterite mineralisation on the adjacent Tapian Main, Tapian SF and Mat-I tenements. Reconnaissance auger drilling indicated several areas warranting follow-up drilling to establish potential Mineral Resources. This evaluation drilling formed the basis of the exploration targets for the Regional Exploration Target of 50 to 70 Mt at a grade of 0.9% to 1.2% Ni. Report No R-Rev1 37

52 13.0 DRILLING 13.1 Agata The following information is summarised from Gifford, 2010 and Mindoro, In the northern part of the Agata deposit drilling is concentrated over about eighty (80) percent of the interpreted nickel laterite extent (Figure 13-1). Figure 13-1: Drill hole plan showing Mindoro has carried out exploration drilling on a progressively smaller drill pattern using small mobile open hole NQ coring rigs (Figure 13-2). Recovery from these drill rigs is high, with losses generally occurring due to changes in the hardness of the drilled material causing disruption at the bit face (Figure 13-3). The major mineralisation zone is generally a softer material and losses within the mineralisation zones have been minimal at all stages of the drilling programs. Report No R-Rev1 38

53 Figure 13-2: Core drilling at Agata Project Figure 13-3: Core recovery from Agata Project Table 13-1 provides summary of various drilling campaigns. Report No R-Rev1 39

54 Mindoro surveys all drill hole collars using a Nikon Total Station DTM-332. The survey reference grid is PRS 92 or WGS 84 with local control from five (5) certified National Mapping and Resource Information Authority benchmarks. Topographic baseline is 51 m RL with approximately survey points providing definition for Digital Terrain Models (DTMs). Table 13-1: Summary of drilling campaigns Drilling Campaign No. Holes Purpose BHP Billiton (2006) 35 Regional Mindoro Phase 1 (2007) 100 DSO Mindoro Phase 2 (2007/8) 48 Better define mineralisation and extend Mindoro Phase 3 (2008) 225 Drill out greater part of Northern area of the Agata deposit Mindoro Phase 4 (2010) 147 To achieve greater accuracy on resource estimate Report No R-Rev1 40

55 14.0 SAMPLING METHOD AND APPROACH The following information is summarised from Gifford, 2010 and Mindoro, Drill Sampling The majority of data in the resource database is from core drilling. During drilling Mindoro provide close supervision of contract drillers and diligently record core recovery, core run, laterite horizons, degree of weathering, boulder size, and colour for all sample intervals. On completion of logging, a geologist marks the core for sampling typically at one metre downhole intervals with sample lengths adjusted for changes in lithology and laterite horizon. Minimum sample length is 0.7 m and maximum is two metres. Mindoro has used slightly different sampling techniques for the different programs: Mindoro Phase 1 whole core samples. Mindoro Phase 2 split core samples where technicians crush the core using a pick, mix the crushed product thoroughly, and quarter the sample pile. The technicians then bag two opposite quarters for assaying with the remainder retained. Mindoro Phase 3 and 4 Technicians split the core in half using a spatula or core saw and bag half the core for despatch to the assay laboratory. In all cases, the technicians label all samples and residual material with hole identification, sample number, and sample interval and secure all sample bags firmly. Mindoro have modified sampling methods and QAQC procedures following regular audits and reviews by independent consultants and industry experts. All drilling and sampling is under the close supervision of Mindoro s Exploration Manager Density Determinations Mindoro collected the majority of samples for dry bulk density determination from test pits. Mindoro collected 30 samples from 15 test pits for the ferruginous laterite horizon; 37 samples from 19 pits for limonite; and 17 pit samples from 6 pits for saprolite. In addition, Mindoro also collected and tested 19 core samples from the saprolite zone. On-site bulk density determinations came from large samples ranging in volume from m 3 to 0.08 m 3 collected from twenty test pits distributed around the drilling area. For the bulk samples, Mindoro measured volume, wet weight, and dry weight. For the drill cores, Mindoro selected relatively solid, less compressed portions of mm lengths of core. Drill holes are spatially distributed and samples coated in paraffin wax to preserve the moisture. Mindoro dispatched these samples to McPhar Laboratories who use the water displacement method for density determinations. Moisture content averages from approximately 20 to 25% in saprolite to 30% in limonite. Mindoro report dry bulk density averages of approximately 1.2 and 1.45 t/m 3 for limonite and saprolite respectively. Report No R-Rev1 41

56 15.0 SAMPLE PREPARATION, ANALYSES AND SECURITY 15.1 Analytical Laboratories McPhar Geoservices (Phil) Incorporated (McPhar) has been the primary laboratory for the Agata Project drilling and assaying programs. McPhar are an ISO accredited laboratory based in Manila. McPhar s sample preparation and assay flow sheet follows standard industry methods. McPhar analyse each sample for nickel, cobalt, iron, magnesium, and aluminium by dissolving a 25 g charge with a two acid digest followed by an Atomic Absorption Spectroscopy (AAS) finish. McPhar also analyse silica and some samples for phosphorous using a gravimetric process Sampling and Analytical QAQC Quality Assurance (QA) is the system and set of procedures used to ensure that the sampling and assay results are of high quality. Quality Control (QC) is the data used to prove the results of sampling, sample preparation, and chemical analyses are fit for purpose. At Agata, Mindoro has stringent quality control and assurance programs in place, which include: Check samples Repeats of coarse rejects Repeat assays of pulp rejects Insertion of standard (certified) reference samples (standards) with each batch of samples. Mindoro sourced 12 types of standards from Geostats Pty Ltd of Australia covering a range of nickel grades from 0.11% to 2% Pulp repeat assays by an umpire laboratory, Intertek Phils (Intertek). Independent reports of QAQC results show check samples and assays all correlate well with original results and variations are within acceptable limits (Gifford, 2010). Gifford, 2000 notes for the two standards, which most closely match Agata samples, McPhar and Intertek consistently underestimate iron content by approximately 3% of the certified value. Full details of results are available in Gifford, Report No R-Rev1 42

57 16.0 DATA VERIFICATION 16.1 Independent Review Mindoro has commissioned an independently review of data for NI Resource reporting. Gifford (2010) reports verification and validation of electronic data matched original Mindoro information, assay certificates, and visual inspection of core samples. Gifford also reports independent analyses of 12 field duplicate samples by pre-2010 resource practitioners had excellent correlation against original assay results. Report No R-Rev1 43

58 17.0 ADJACENT PROPERTIES The Surigao peninsula in northeastern Mindanao, where the Agata project is located, is a significant mining district of the Philippines. There are four commercially significant nickel laterite resources, including Taganito, Cagdianao, Hinatuan and Nonocs. There are also other known but undeveloped nickel laterite resources in the area. Nickel laterite has been mapped beyond the immediate boundaries of Mindoro Tenements. These occurrences may be of future interest to Mindoro but are not contemplated or provided for in the current PEA. In addition both Mindoro and other companies have interests in epithermal gold and porphyry copper-gold projects in the area. Report No R-Rev1 44

59 18.0 MINERAL PROCESSING AND METALLURGICAL TESTING 18.1 Introduction The first phase of metallurgical testing of mineralisation from the Agata nickel deposit was performed by metallurgical laboratory and consultants Enlin Stainless Steel Corporation (ESSC) in Golder was advised that the ESSC Manila Laboratory is not a certified laboratory. The ESSC bench scale testwork program included AL, HPAL, saprolite neutralisation, limestone neutralisation, iron removal and MHP. The available reports by ESSC were found to be lacking test details in some areas. A more comprehensive bench scale program was completed by SGS Lakefield Oretest (ISO 9001:2008 Certified) in Perth in 2010/2011. This program included mineralogy, beneficiation (scrubbing), slurry settling, AL, HPAL, saprolite neutralisation and counter current decantation (CCD) settling on composites of different mineralisation types from the deposit, as well as limestone testing Testing at Enlin Stainless Steel Corporation Ore Samples Six mineralisation samples were tested in the ESSC testing program. The head analyses for the six samples are summarised in Table Table 18-1: Mineralisation Sample Head Analyses Sample Ni % Fe % Co % Mg % Mn % Cr % Samples 1 to 4 were clearly limonite as evidenced by high iron grades of 46 to 50% Fe, and low magnesium grades in the range 0.69 to 0.83% Mg. Sample 5 is transitional material and Sample 6 represents high Mg saprolite Sizing Analyses Size analysis was performed on a limonite sample. The results are presented in Table Table 18-2: Limonite Sizing Results Mesh Mass % Ni % Fe % Co % Mg % Mn % Cr % Al % Ca % The results on the limonite sample showed relatively even distribution of nickel across the size range tested, and ESSC concluded that there was little potential for beneficiation. Report No R-Rev1 45

60 Ore Slurry Thickening ESSC conducted a thickening test on an unidentified mineralisation sample and reported that 50% w/w solids was achieved in just three minutes. It was also concluded by ESSC that flocculation was not required. These results are considered to be uncharacteristic of typical nickel laterite ore, but insufficient test data was published by ESSC to permit a review of procedures and calculations Atmospheric Leaching (AL) No detailed results from the AL testwork program were presented by ESSC. The covering report by ESSC indicated that 90% nickel extraction was obtained from saprolite mineralisation at an acid dosage of 900 kg/t HPAL Testing A range of tests were performed by ESSC to investigate the effects of temperature, acid to ratio, and residence time, on the performance in HPAL. Representative HPAL test results are summarised Table Table 18-3: Selected HPAL Test Results Temp C Duration mins Acid:Ore kg/t Extraction % Ni Fe Co Reported HPAL discharge solution assays are presented in Table Table 18-4: HPAL Discharge Solution Assays Sample Solution Concentration g/l Ni Fe Co Mn Mg Mean These results are considered to be fairly typical of a limonite HPAL solution and thus provide some confidence in the experimental methods applied Saprolite Neutralisation Partial neutralisation of HPAL discharge slurry by the addition of saprolite mineralisation was tested by ESSC. Unfortunately some critical details of this testwork were not reported. These include: the initial and terminal acid concentrations are not stated saprolite dosage was reported in grams per 800 ml of HPAL solution, with no indication of how much limonite mineralisation was leached to produce the HPAL solution. Report No R-Rev1 46

61 The information reported by ESSC suggested that satisfactory metal recoveries from saprolite mineralisation can be achieved in saprolite neutralisation. Representative test results are summarised in Table Table 18-5: Selected Saprolite Neutralisation Test Results Duration min Temp. C % Extraction from Saprolite Ni Fe Co Mg Mn Terminal acidity was reported to be in the range ph Higher extractions may have been achievable if a higher terminal acidity of approximately 5-10 g/l was targeted CCD Settling Settling tests were performed on slurry samples produced during the saprolite neutralisation testwork, however only flocculant rates and settling times were reported. No underflow density data was presented in the ESSC report Iron Removal Iron removal tests were performed by ph adjustment using limestone. The results of testwork at 85 C are presented in Table Table 18-6: Selected HPAL Test Results Final ph Elemental Concentration in Product Liquor (g/l) Fe Al Cr Ni Co Mn Mg The results were considered to compare well with data from other nickel laterite projects. Reconciliations indicated nickel and cobalt co-precipitation of % at ph 3 rising to % at ph Nickel-Cobalt Precipitation Precipitation of mixed nickel-cobalt hydroxides was tested using both sodium hydroxide (NaOH) and magnesia (MgO). ESSC concluded that: the optimum ph for precipitation of mixed hydroxides using sodium hydroxide is ph the optimum ph for precipitation of mixed hydroxides using magnesia is ph two stages of precipitation are required to achieve a satisfactory nickel grade in the product. Report No R-Rev1 47

62 18.3 Testing at SGS Lakefield Oretest (SGS) A program of metallurgical testwork was undertaken in 2010 to investigate the metallurgical characteristics of Agata mineralisation samples. The work was undertaken at the SGS Lakefield (ISO 9001:2008 Certified) metallurgical laboratory in Perth, Western Australia Testwork Samples The samples were sourced as intervals from the walls of three metallurgical test pits located to target three mineralisation types. The intervals used, and test pit identifications, are presented in Table The samples were blended in a manner to target elemental composite grades similar to that of global resource values, especially those elements influencing leaching properties such as iron and magnesium. Table 18-7: Source of Metallurgical Test Samples Location Zone Pail No ID/Pit Interval m Weight kg Total Weight kg AGL 281 Limonite AGL 373 Transition AGL 300 Saprolite Three composites were initially prepared and the composites were identified as limonite, transition and saprolite. In the proposed operations it is planned to treat transition mineralisation with limonite mineralisation in HPAL processing. A fourth composite was therefore prepared as a blend of limonite and transition ore, and was identified in testwork as limonite transition (L/T) blend. The L/T blend sample was mixed in the ratio of 95% limonite and 5% saprolite. Drill samples from the nearby Payong Payong limestone deposit were evaluated by SGS. Two samples identified as Agata LS-01 and Agata LS-02 were received by SGS. The two samples were blended to form a limestone composite sample for testwork Mineralogy Mineralogical examinations of size fractions from the limonite and saprolite composites were undertaken by SGS South Africa. A subsample of each composite was screened into four size fractions (+212 µm down to -38 µm) for examination. The main aim of the work was to investigate mineral liberation and Ni-deportment in the samples. The investigations included qualitative X-ray Diffraction (XRD) analysis; chemical analysis; electron microprobe analysis of the mineral phases present; and QEMSCAN BMA and PMA analyses. Some observations from the work on the limonite sample fractions were: The mineralisation is predominantly of made up of quartz, chromite and Fe-hydroxides. The amount of quartz in size fractions decreases with decreasing screen size. Almost all of the quartz is rimmed by Fe-hydroxides. The amount of chromite decreases with decreasing screen size. The chromite is mostly well liberated. Report No R-Rev1 48

63 The amount of Fe-hydroxides in screen fractions increases with decreasing screen size. The Fe-hydroxides are well liberated in the -75 µm fractions but relatively poorly in the +75 µm fractions. Most of the unliberated Fe-hydroxides in the +75 µm fractions are intergrown with Mn-wad, magnetite-hematite and/or contain silicate inclusions. Most of the nickel is hosted by the Fe-hydroxides. The Mn-wad in limonite is poorly liberated and is closely associated with the Fe-hydroxides. The Mn-wad contains significant nickel. Some observations from the work on the saprolite sample fractions were: The saprolite size fractions consist primarily of altered serpentine and saponite clay (an alteration product of serpentine) The Mg:Si ratios of the serpentine and saponite are on average 1.1 and 0.9 respectively as the Mg is leached from the serpentine during alteration The Fe-hydroxides present in the fractions are poorly liberated in the serpentine Approximately 50-60% of the serpentine is liberated. The saponite is mostly well liberated. Unliberated saponite is mostly associated with Fe-hydroxides as rims. The serpentine is nickel rich The mineralogical work suggests that moderate upgrading may be achieved by rejection of quartz in coarse fractions. Removal of chromite in coarse fractions by magnetic separation was suggested by SGS. SGS also considered that the saprolite sample would be amenable to atmospheric sulphuric acid leaching as none of the fractions were observed to contain excessive Fe oxide/hydroxides or a high Fe-content Head Analyses Head analyses were conducted on the four samples. The samples were subjected to a four acid digest and metal elemental compositions determined by ICP-MS. Analyses for Si and Cr were determined by X-Ray Fluorescence (XRF). The analytical results are presented in Table Table 18-8: Head Analyses of Metallurgical Composites Ni % Co % Al % Mg % Si % Cr % Ca % Fe % Mn % Limonite Saprolite Transition L/T Blend The results are considered to be typical of tropical nickel-cobalt laterite deposits. The sample blends were prepared with the main objective of achieving similar grades to the scoping study mine schedule in species significant to leach chemistry, particularly iron, magnesium and aluminium. The nickel grade in the limonite sample was determined to be 1.32% Ni and is approximately 30% higher than the limonite nickel grade in the current planned mine schedules. The saprolite sample is similar in nickel and iron grade to that reported in the proposed mine schedules, but the test sample is significantly lower in magnesium. Further variability work is recommended to examine effect of head grade and elemental variations on extraction and metallurgical performance. Report No R-Rev1 49

64 Ore Scrubbing and Head Sizing A sub-sample of each composite was lightly scrubbed to assist in removing Fe-hydroxides from silica particles, and then wet screened to examine potential for mineralisation beneficiation by sizing. Scrubbing was achieved by soaking a 10 kg subsample of mineralisation in water overnight and then bottle rolling the slurry for one hour prior to wet screening. The mass, grade and metal recovery in wet screening for a reject screen size of 0.25 mm is summarised in Table Table 18-9: Scrubbing Test Results Sample Limonite Transition Fraction Mass Nickel Cobalt Magnesium % Grade % Ni Distrib % Grade % Co Distrib % Grade % Mg Distrib % mm Feed mm Feed The limonite and transition sample test results showed that some upgrading of nickel could be achieved by rejection of coarse fractions. The upgrading of nickel was accompanied by rejection of magnesium. Cobalt showed a poorer response than nickel. Further large scale scrubbing testwork should be undertaken in the next phase of testwork. Saprolite mineralisation showed no potential for upgrading by beneficiation from scrubbing and sizing Heap Leaching Amenability Testing Agglomeration, percolation and bottle roll acid leaching testwork was conducted on a saprolite sample crushed to finer than 25 mm to evaluate amenability to heap leaching. The agglomeration tests were conducted in a cement mixer with varying additions of concentrated sulphuric acid. Agglomerates were then cured for three days in columns and flooded. After a 48 hour soak period, the mineralisation height slump and column percolation maximum drain rate were determined. Results are presented in Table Table 18-10: Agglomeration Test Results Agglomeration Acid kg/t Slump % Drain Rate L/m 2 /h The results showed that acid additions over 100 kg/t resulted in low drainage rates. The response of mineralisation samples to acid heap leach conditions was investigated by acid bottle roll leaching of 3 kg sub-samples prepared by agglomeration at 50 kg/t acid. The tests were conducted at 30% solids and varying target free-acid concentrations in leach over a period of 50 days. The nickel extraction results with leach time for each target acidity are presented graphically in Figure Report No R-Rev1 50

65 Figure 18-1: Acid Bottle Roll Test Results High nickel extractions ranging from 90 to 99% were achieved, but at very high acid addition requirements of 887 to 985 kg acid/ tonne of ore. Both metal extraction and acid consumption increased as target acidity was increased from 25 to 50 g/l Feed Mineralisation Settling Testwork Settling testwork was undertaken on the limonite transition and saprolite samples to investigate requirements for thickening of leach feed. A flocculant screening program was first undertaken resulting in selection of Magnafloc 10 for the settling trials. The settling tests were conducted in 2 metre high raked columns. The key test parameters and test results are presented in Table Table 18-11: Mineralisation Slurry Settling - Key Parameters Parameter Limonite Saprolite Initial Density % Solids Final Density (24 h) % Solids Floc Dosage g/t Thickener Requirement 25% Solids m 2 /tonne/day % Solids m 2 /tonne/day % Solids m 2 /tonne/day The settling tests showed that a slurry density of over 40% solids for limonite mineralisation and over 35% solids for saprolite mineralisation could be achieved with flocculant additions in the range 150 to 200 g/t. Thickener unit area requirements are high at around 0.6 m 2 /tonne/day. Report No R-Rev1 51

66 High Pressure Acid Leach Testing HPAL leaching tests were conducted on the limonite transition composite sample at varying acid additions to examine extraction response with retention time and acid addition. All tests were conducted with slurry made up to 29% solids with a mix of seawater and fresh tap water blended in a ratio of 1.33 of sea to fresh. The target water blend was established by BWHC modelling in METSIM and reflects mineralisation slurrying using seawater adjusted for the impact of mineralisation moisture and process dilution by gland water, screen sprays, flocculant make-up water and condensation of live steam during slurry heating. All tests were conducted in a mechanically stirred laboratory batch autoclave at a temperature of 255 C. Acid addition rates varied between 276 and 351 kg/t. Some key results from the testwork program are presented in Table Table 18-12: HPAL Test Results on Limonite Transition Mineralisation Samples Acid Addition Overpress ure Time Free Acid ORP Extraction kg/t Air, kpa Mins g/l mv Ni% Co% The results show that the mineralisation exhibits very fast leaching kinetics with approximately 97-99% of the nickel, and 95-96% of the cobalt, extracted within 20 minutes of leaching time. Free acid levels at the end of the tests amounted to approximately g/l for acid additions ranging between 276 and 351 kg/t. Ferrous iron concentrations were generally high (up to 9.6 g/l) but with air overpressure in the autoclave the ferrous iron concentration in leach solution was decreased to 4.7 g/l. In a later HPAL test, HPAL.08, conducted as part of the integrated HPAL/AL/SN test SN.03, higher air overpressure (500 kpa) resulted in a ferrous iron concentration of just 270 mg/l. Report No R-Rev1 52

67 Atmospheric Leach Testing AL tests were conducted on saprolite samples in stirred vessels at 95 C and at acid addition rates from 850 to 1000 kg per tonne of feed mineralisation. The samples were prepared using a sea water/fresh water mix in the ratio 3.8:1. The water blend was established by modelling in METSIM and reflects mineralisation slurrying using seawater adjusted for the impact of mineralisation moisture and process dilution by gland water, screen sprays and flocculant make-up water. The results of the atmospheric AL tests are presented in Table Table 18-13: AL Tests on Saprolite Samples Acid Addition Time Free Acid ORP Extraction Kg/t Mins g/l mv Ni% Co% The results indicated favourable leaching kinetics with four hour extractions of around 94 to 98% for nickel and 88 to 94% for cobalt. Final free acid concentrations ranged between 17 and 39 g/l. Solution composition at the terminal 240 minutes leach with an acid addition of 850 kg/t is presented in Table Table 18-14: AL Test Solution Composition Solution Concentration g/l Ni Co Al Mg Fe Fe (II) Report No R-Rev1 53

68 Ferric and ferrous iron concentrations were shown to significantly increase with increasing acid additions. Magnesium concentrations were very high at g/l Saprolite Neutralisation Testwork Combined HPAL, AL Slurry A combined leach pulp for the saprolite neutralisation testwork was prepared from two separate leach tests as follows: AL test on saprolite sample at a pulp density of 35% w/w for 240 minutes at a temperature of 90 C HPAL test on a sample of L/T blend sample for a leach time of 30 min at an acid addition of 350 kg/t and temperature of 255 C and a density of 29% w/w. Saprolite mineralisation for neutralisation was added to sub-samples from the combined pulp in varying ratios. In each test the slurry was agitated for six hours and subsamples taken to monitor solution acidity and elemental concentrations, as well as solids samples to monitor metal extraction. Results from saprolite neutralisation are summarised in Table Table 18-15: Saprolite Neutralisation Testing Ratio L/T:Sap:SN Sap Saprolite Addition kg/t acid Residual Free Acid g/l Total Fe g/l Dissolution 1.00:0.79: :0.79: :0.79: :0.79: :0.79: :0.79: Ni Mg A scoping test (SN.01), during which saprolite mineralisation was progressively added in the SN step to establish the optimal conditions for subsequent confirmatory tests, produced the first four test results shown in Figure The last two tests (SN.02 and SN.03) were confirmatory tests in which all of the SN feed mineralisation was added at the beginning. The confirmatory tests showed that neutralisation of a combined HPAL and AL pulp with saprolite mineralisation resulted in the dissolution of 83-89% of the nickel and 78-87% of the cobalt contained in the neutralising saprolite. Concentrations of total iron in solution decreased with residual free acid due to precipitation of sodium jarosite, a benefit of using seawater for mineralisation slurrying. Final ferrous concentrations ranged from 1.1 to 4.5 g/l. The kinetics of the neutralisation reactions for the test at a ratio of 1.00:0.79:0.36 (L/T:Sap:SN Sap) are plotted in Figure Report No R-Rev1 54

69 % Extraction Ni Ext (%) Mg Ext % Free Acid g/l Fe Total g/l Time (mins) g/l Figure 18-2: Saprolite Neutralisation Test Results - HPAL/AL/SN The reported test results show a high extraction of nickel from saprolite sample used in neutralisation Saprolite Neutralisation Testwork AL Slurry AL tests were undertaken to provide a pulp for saprolite neutralisation at a pulp density of 35% w/w for 240 minutes. Subsamples of the leached pulp were neutralised with varying ratios of saprolite. In each test the slurry was agitated for six hours and subsamples taken to monitor solution acidity and elemental concentrations, as well as solids samples to monitor metal extraction. The results of the AL saprolite neutralisation tests are presented in Table Table 18-16: Saprolite Neutralisation Test Results- AL Saprolite Ratio AL:SN Saprolite Addition kg/t Residual Free Acid g/l Total Fe g/l Ni Dissolution % 1.00: : : : : Mg Approximately 70-84% of nickel and cobalt was leached from the saprolite mineralisation used in neutralisation at a residual acid concentration of 4-8 g/l Settling Testwork on Saprolite Neutralised Slurry Settling testwork was undertaken on the pulp from the saprolite neutralisation testing to investigate slurry thickening characteristics. Tests were conducted in two metre high raked columns. Flocculant used in the testing was Magnafloc 10. Tests were conducted on both HPAL/AL/SN pulp and AL/SN pulp, Table Report No R-Rev1 55

70 Table 18-17: Settling Tests on Saprolite Neutralisation Slurry Sample Flocculant Dose g/t Settled Underflow Pulp Density (% w/w) Thickener Unit Area Requirement (m 2 /t/d) SN.02 Final Diluted to 4% Solids SN.03 Final Diluted to 4% Solids The settling tests showed that a slurry density of 38-40% solids can be achieved for tests with flocculant additions in the range g/t. Settling testwork on the AL neutralised pulp showed lower densities and higher thickener requirements than that for HPAL/AL Limestone Calcination and Activity Drill samples from the limestone deposit at the mine lease were obtained for testwork and a composite sample prepared. A sub-sample of the limestone was crushed to size -25 mm +9 mm and then calcined in a furnace at 1050 C for varying residence times from 30 to 120 minutes. The mass loss of sample was monitored, and the available lime determined. The test results showed that after 60 minutes the mass loss was 44% with an available lime of 92%. The neutralising capacity of the lime was reported at 1.26 t acid/ t hydrated lime. A test on a sub-sample of limestone was undertaken to investigate the neutralisation activity. Tests were undertaken by neutralising a 48 g/l sulphuric acid solution with staged additions of dry ground limestone and ph monitoring. The neutralising capacity of the limestone was reported at 0.94 t acid/ t limestone. Report No R-Rev1 56

71 19.0 MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES The Mineral Resource estimation was completed by Mike Job, Principal Consultant for Quantitative Group (QG) of Fremantle, West Australia. The geological modelling uses a set of points at the contacts of the various layers in each drill hole. These points are triangulated into a surface wireframe to generate the geological model The approach used by QG is to distinguish the limonite layer (LIM) from the saprolite (SAP) layer by the lower magnesium values in the LIM. The SAP to Bedrock (BED) contact was identified by using nickel assay data (generally less than 0.4% Ni) and geological logging. Additional control points were inserted at interpreted locations in-between drill holes in order maintain geological consistency and to account for drill holes finishing before hitting bedrock. The main geology zones modelled are limonite (LIM), saprolite (SAP) and bedrock (BED) Unfolding To assist in proper grade interpolation, the Datamine dynamic search feature was used which allows the orientation of the search neighbourhood ellipse to be defined separately for each block (in this instance, the variogram was also rotated to align with the search, but this does not always need to occur) Data Preparation Grades The following grades are estimated in the resource modelling process: Ni%, Co%, Fe%, SiO 2 %, Mg%, and Al 2 O 3 % Sample Length The drilling database for the Agata deposit provided to Golder contains a range of sample intervals, with approximately 78% of intervals assayed for nickel being less than or equal to 1 m length, 21% on 1 to 2 m length, with the remainder greater than 2 m length. The long samples appear to be predominantly in bedrock material Geology Model Geology Interpretation Gifford, 2010 describes the interpretation process. The abrupt change in geochemistry between limonite and saprolite and the grade decrease from saprolite to bedrock provide the position of these surfaces on each drill hole. The resource analyst used these points in Datamine software to create a triangulated surface of the contacts across the deposit area. These triangulations then become limits for coding cells in the Resource block model. Report No R-Rev1 57

72 Figure 19-1: Bedrock, Saprolite, and topography triangulations in cross-section (After Gifford, 2010) 19.4 Independent Review Exploratory Data Analysis Domaining The geological modelling was used as the input for creating domains for estimation purposes. Interpolation of the various assay elements was done separately for: LIM SAP. Physical or chemical attributes were not estimated for the Bedrock layers. Statistical Analysis Statistical analysis has been carried out by QG on the final drill composited data. This involved generating univariate statistics and histograms. Golder composited the data to 1 m downhole and flagged the composite data to the saprolite and bedrock wireframe surfaces provided. Analysis of cumulative log probability plots of Ni% within the modelled LIM domain shows a difference in lithologies codes of LF, LA and LB horizons. Analysis of Figure 19-2 indicates that the Ni% distribution is somewhat different for the three limonite zones. Fe, Al and Mg show some differences too. Ni% distribution within the modelled SAP domain also shows two distinct populations. One associated with general saprolite material and one associated with boulders. Figure 19-3 provides probability plots of Ni% and Mg% for boulder and saprolite samples within the modelled SAP domain. The Ni% grade is much lower grade for the boulder and with much elevated Mg% than the saprolite material. The relationship between various elements was also examined for the composited data by plotting various scatter diagrams. A moderate positive relationship is noted between Ni% and Fe%. The relationship for Ni% and Mg% is also moderate to strong negative. Mg% increase sharply as the Ni% decreases. Report No R-Rev1 58

73 Figure 19-2: Probability plots showing Ni% distribution of LF, LA and LB samples within modelled Limonite zone Figure 19-3: Ni% and Mg% distributions for Bolder and Saprolite samples within SAP modelled domain Compositing The first part of any resource estimation is to ensure that all data are defined at the same support. Given the raw sample length distribution, the use of 1 m composites for the interpolation process is reasonable. This is also supported by the narrow geometry of some of the geological layers. Splitting of the larger intervals (i.e. 22% of the data) may tend to artificially understate the true variability of the data, by creating 1 m composites that have the same grades. However, as the majority of the large composites sit between 1 m and 2 m in length the impact is expected to be minimal. Report No R-Rev1 59

74 Due to the geometry and position of the some of the regolith horizons, the use of 1 m composites is acceptable. Preparation of the composite map files for grade estimation has been carried out in a diligent manner Grade Capping No outlier or high grade cutting was used Variography Variography was undertaken to provide parameters for Ordinary Kriging grade estimation. QG modelled variograms for all the major elements (Ni%, Co%, Fe%, SiO 2 %, Mg% and Al 2 O 3 %) based on 1 m composites. Nugget effects in the QG variogram models used for estimation appear to be low and reasonable, with overall ranges of influence of the order of 100 m. QG observed consistent spatial trends between the variables. The variography has assumed an isotropic behaviour in horizontal direction with an omni-directional variogram representing both major and semi-major axis. This reflects variography by QG which indicated that there was not anisotropy in the horizontal plane. The directional variograms were not presented by QG to demonstrate that the isotropy assumption was valid. Unlike estimation approach which uses local dip and dip direction (unfolding) the variography has been done horizontally Density Density sampling and determination completed by Mindoro is discussed in Section It is Golder s opinion that there are insufficient density measurements to qualify any part of the resource as Measured. Based on our experience, the dry bulk density values for limonite may be too high given the high moisture content. Similarly, the preferential selection of competent core in saprolite may cause an over statement of saprolite density. However, it does not appear that Mindoro allowed any density variation for boulders, which will be higher density than weathered saprolite Block Model Estimation The Mineral Resource for Agata was estimated using Ordinary Kriging (OK) which is based on variogram parameters that provide the parameters for the spatial continuity. The interpolation of grade was constrained to the geological modelling domains. The domains confining the composited samples were defined using Datamine wireframe triangulations developed for the limonite and saprolite domains. The geology is assigned into blocks of size 20 m 20 m 1 m. The estimation is based on 1 m composited data into these blocks. The grid drilling is nominally 25 m 25 m, 50 m 50 m, 100 m 100 m or larger. In this context a block size of 25 m 25 m would be a better option to keep the drill holes uniformly distributed into the blocks. This however is not expected to alter the final outcome. Grade interpolation by OK was implemented using hard boundary conditions for each of the estimation domains. The search ellipses were oriented according to the local dip and dip direction using the Datamine dynamic search feature. The process of estimation involved three passes. The search distance was doubled for each pass to enable estimation of more blocks into the block model. Implementation of passes for each layer was the same and systematic, with a normal search. A maximum of 40 samples was used for the first and second estimation pass, reducing to 20 for the third pass. Overall the search parameters are reasonable. No outlier or high grade cutting was used. Report No R-Rev1 60

75 Validation of Block Models The 2010 documentation contains statistical and swath plot checks to demonstrate the validity of the resource model. Overall, these validations are well-presented and demonstrate that the model behaves reasonably Resource Classification The procedure adopted by QG to define reporting classes is primarily by the density of drilling. For the majority part of the deposit comprising m or m drilling the model is classified as an Indicated Resource. The only areas of Inferred Resources are around the steep-sided creek systems, where the drilling is on a broader pattern and the laterite horizons thin out. A small amount of Measured Resources has also been introduced where drilling approaches to m density Selectivity, Mineralisation Loss and Dilution No assessment of the block model smoothing is evident in the 2010 documentation. This is necessary as the estimation always incorporates a smoothing effect to account for the change of volume from sample to blocks. The question that need to be addressed if this level of smoothing is a desirable level to account for potential dilution and mineralisation losses based on the expected mining selectivity. The success of the resource model at Agata will to a large extent be dependent on the accuracy of the geological model produced. Therefore the uncertainty inherent in the geological model also needs to be investigated. Golder believes that presence of boulders within the saprolite layer will present mining recovery and metallurgical recovery issues. Boulder has presently been mixed with saprolite in the current model and there is no indication of amount or grade of such material. Golder recommends the evaluation of the saprolite mining recovery using a conditional simulation model with appropriate transfer function Assessment of Reasonable Prospects of Economic Extraction 19.9 Mineral Resource Statement The Agata Nickel Project has estimated combined Measured and Indicated Resources of Mt at 1.04% Ni, and an inferred resource of 1.68 Mt at 1.04% Ni for a combined t of nickel, as reported in Mindoro s NI compliant Mineral Resource estimate of 8 September 2010, using a cut-off grade of 0.5% Ni for limonite and 0.8% Ni for saprolite. The summary of the NI compliant Mineral Resource is presented in Figure Report No R-Rev1 61

76 Table 19-1: Agata Deposit Laterite Resources (Ni ), September 2010 kt (dry) Ni % Co % Fe % Al % MgO % SiO 2 % Measured Limonite Saprolite Sub-Total Indicated Limonite Measured and Indicated Saprolite Sub-Total Limonite Saprolite Total Inferred Limonite Saprolite Total Total metal contents in the reported resources represent metal in the ground and have not been adjusted for metallurgical recoveries and other factors which will be considered in a later study. Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing or other relevant issues Mineral Reserve The mining inventory representing the estimated mill feed tonnage and quality includes Indicated and Inferred Resources. Approximately 5% of the mining inventory is classified as an Inferred Resource. No Measured Resource is currently reported in this PEA or previous Technical Reports documenting the Mineral Resource estimate. No Mineral Reserve estimate is reported in this PEA prepared as a conceptual level study. Mindoro has committed to proceeding with a PFS. Report No R-Rev1 62

77 20.0 OTHER RELEVANT DATA AND INFORMATION 20.1 Preliminary Hydrological and Hydrogeological Assessment The Western Range is located in a mountainous region with several creeks draining towards the Mindanao Sea on the western side and towards the Kalinawan Valley on the eastern side. The Kalinawan River (referred to as the Tubay River in previous studies) is situated about 1 km east of the proposed mine area and flows in a southerly direction. Tumanda et al. (2004) report that the average discharge of the Kalinawan River is about 2 M m 3 /day (2000 ML/d) and more than adequate to meet project water requirements. The water quality of this river is very good (Coffey, 2008) with Total Suspended Solids (TSS) concentrations of about 2 mg/l and Total Dissolved Solids (TDS) concentrations of about 70 mg/l. Nutrient levels are low ranging between 0.2 to 1.2 mg/l nitrate. Lake Mainit is a large freshwater lake situated approximately 4 km north of the proposed mine area. The water quality of this lake is very good (Coffey, 2008) with TDS concentrations of about 80 mg/l and low nutrient concentrations. There is no information on the groundwater potential in the region from previous studies. Groundwater does occur in (probably shallow) alluvial sediments in the Kalinawan Valley. Groundwater is being used for mostly domestic Process Plant 20.2 Mining Plan General The mining inventory and methodology used to develop the Agata Nickel Project Mining and Plant Feed for a hydro-metallurgical process. Schedule V9d.was prepared by Dallas Cox (2011) Principal Consultant Crystal Sun Consulting Limited for Mindoro Scheduling was carried out using three phases and 63 mining panels (approximately 250 m by 250 m). Approximately 5% of the mining inventory is categorised as Inferred Resource but is only mined towards the end of the scheduled periods. Golder considers the impact of the Inferred Resources in the schedule to be not material. Golder recommends future estimates of mining inventories include only Mineral Resources classified as Measured and Indicated or Mineral Reserves if estimated. Excessive stockpile build-up in the latter half of the schedule was flagged by Cox (2011) as an issue to be addressed in future studies. The high quantities of stockpile and rehandling of mineral inventory for plant feed result in higher mining costs. Further mining scheduling is recommended to optimise balancing of grades and quantities to the plant. The present schedule is acceptable for a conceptual study Mining Inventory The Mineral Resource defined by the NI Technical report (September 2010) was the used as a basis to generate a mining inventory. The cut-off grades used to define mineralisation in the mineral inventory were 0.5 Ni% and 0.8 Ni% for limonite and saprolite, respectively. These are arbitrary cut-offs in line with the resource estimate cut-off grades. A "pit base" was generated using the "Base of Saprolite" contact. Future pit design work will incorporate final ramps and batters/berms where necessary (Figure 20-1). Nickel mineralisation in the lower part of the mineralisation profile, namely saprock and boulder saprolite categories, were excluded from the resource base. The mining inventory of 26.1 M dmt represents a 76% of the Mineral Resource of 34.1 M dmt. Report No R-Rev1 63

78 The methods used to delineate the likely open pit extent are considered reasonable. Figure 20-1: Pit Extents The pit was divided into three areas/phases (Figure 20-2) partly based on mineralisation categorisation and to obtain early nickel production. Report No R-Rev1 64

79 Figure 20-2: Pit Areas & High Magnesium zones The Mining Inventory was categorised into six Material types based on Iron Grade (in limonite) and Magnesium grade (in saprolite) as shown in Table Table 20-1: Material Types Material Description Material Code Fe% Mg% % Limonite % Saprolite % Total Limonite High Iron HFE >47 35% - 13% Limonite Medium Iron MFE % - 14% Limonite Low Iron LFE <43 26% - 9% Saprolite Low Magnesium LMG <16-28% 18% Saprolite Medium Magnesium MMG % 23% Saprolite High Magnesium HMG > % 23% 100% 100% 100% Figure 20-3 shows the mining panels used for scheduling. Report No R-Rev1 65

80 Figure 20-3: Mining Panels The Mining Inventory is summarised in Table Table 20-2: Mining Inventory Mining Inventory kbcm kdmt Ni% Co% Fe% Mg% Al% SiO2% Limonite Saprolite Subtotal WASTE TOTAL Moisture contents of 31.7% and 20.6% for limonite and saprolite respectively were used for equipment estimation purposes Mining and Plant Feed Schedule The primary goal of the schedule was to deliver the highest grade nickel mineralisation to the plant in the early years of operation and maintain a balanced feed of material stream feed to the respective HPAL, SN and AL circuits. The mining schedule (V9d) in general meets both plant feed and mining considerations (Table 20-3). However it generates excessive stockpile build-up from Year 6. This issue needs to be addressed in future scheduling studies. Report No R-Rev1 66

81 Table 20-3: Plant Feed Targets Plant Feed/Mined Targets Version 9d Material Code Kdmt/Year Limonite to HPAL HFE, MFE, LFE 670 Saprolite to HPAL LMG 335 Subtotal Saprolite to Atmospheric Leach (AL) MMG 425 Saprolite to Saprolite Neutralisation (SN) HMG 356 TOTAL SN : HPAL ratio 0.35 Limonite: Saprolite ratio 1: 1.67 Limonite kdmt 670 Saprolite kdmt Figure 20-4 illustrates the mining panels that are grouped as either fully or partially mined in each three year period for the current life of mine (LOM) 15 years of operations. There is a requirement to mine from several areas concurrently in order to provide a balanced mineralisation feed to the plant, and to minimise stockpile rehandle. Figure 20-4: Mining Schedule Graphic Table 20-4 gives the summary of mined material in both dmt and bcm. Report No R-Rev1 67

82 Table 20-4: Ex-Pit Mined Summary Mining Inventory Mbcm 19.1 Mdmt 26.1 Waste Mbcm 5.2 Mdmt 8.3 Totals Mbcm 24.3 Mdmt 34.4 Mindoro has assumed that mining will be carried by tonne hydraulic excavators loading tonne payload articulated dump trucks. Life of Mine production rate averages bcm per day, ramping up from bcm/day in the first year and peaking at bcm per day in Year 10. Figure 20-5 provides a summary of material mined by area on a quarterly basis. Figure 20-5: Mining Volumes per Quarter The mine production by mineralisation type over the life of the project and the resultant feed grade (Ni%) to the process plant that forms the basis of the financial evaluation is illustrated in Figure Report No R-Rev1 68

83 Mine Production DMT 3,500,000 3,000,000 2,500,000 2,000,000 1,500,000 1,000, ,000 0 %Ni in DMT 1.40% 1.20% 1.00% 0.80% 0.60% 0.40% 0.20% - Low Mg saprolite Mid Mg Saprolite Hi Mg Saprolite Waste Mined Limonite to HPAL HPAL Feed Grade Figure 20-6: Mine Production Schedule by Material Type Table 20-5 shows the mining schedule by year. Report No R-Rev1 69

84 Table 20-5: Mining Schedule Mining Summary TOTAL ORE kbcm , kdmt kwmt WASTE kbcm kdmt kwmt TOTAL kbcm kdmt kwmt Strip ratio v:v Production rate bcm/day Report No R-Rev1 70

85 Table 20-6 shows the total plant feed by material to the process circuit. Plant recovery for nickel and cobalt has been assumed to be 90.8% and 91.7% respectively. The plant feed is approximately 700 kdmt less than the mining inventory due to material on stockpile being unable to be scheduled to meet grade targets. Table 20-6: Plant Feed Summary PLANT FEED SUMMARY TOTAL Limonite to HPAL kdmt Ni % 0.95 Co % 0.11 Fe % 45.6 Mg% 1.2 Saprolite LMG to HPAL kdmt Ni % 1.20 Co % 0.03 Fe % 14.2 Mg% 14.1 Saprolite MMG to AL kdmt Ni % 1.15 Co % 0.03 Fe % 11.6 Mg% 17.1 Saprolite HMG to SN kdmt Ni % 1.03 Co % 0.02 Fe % 9.7 Mg% 19.1 Plant Feed kdmt Ni % 1.06 Co % 0.06 Fe % 24.4 Mg% 11.0 Contained Metal Ni tonnes Co tonnes Recovered Metal Ni tonnes Co tonnes Golder considers the estimation of the mineral inventory and scheduling reasonable Metallurgy Two metallurgical testwork programs have been conducted on samples from the Agata deposit. The most recent program of work conducted at SGS Lakefield in Perth has shown that: Limonite mineralisation is amenable to processing by HPAL and has fast leaching kinetics with approximately 97-99% of the nickel extracted within 20 minutes of leaching time. Saprolite mineralisation is amenable to AL with favorable extractions of over 95% Ni in four hours. Report No R-Rev1 71

86 Other metallurgical characteristics are considered to be typical of tropical nickel-cobalt laterite mineralisation deposits The metallurgical testwork undertaken to date is considered to be of a scoping nature only. More detailed programs of work are required as part of the planned project Feasibility Studies. It is recommended that future work programs include: Additional bench scale testwork on representative composite samples based on the latest mine schedules. Comprehensive leach variability testwork using samples from a range of spatial pit locations, mineralisation types and grades throughout the deposit. This should include both HPAL and AL testing for the relevant mineralisation types, as well as slurry characterisation. Further evaluation for upgrading of limonite by large scale scrubbing tests and continuous scrubbing piloting. Continuous testwork and piloting of the total proposed circuit with recycling of intermediate streams. It is important that blending of composite samples for piloting reflects the amount of each mineralisation type in the planned mine schedule Process Plant Introduction A Scoping Study to evaluate hydrometallurgical processing of the limonite and saprolite mineralisation types from the Agata deposit was issued in The processing aspects of the Scoping Study were jointly undertaken by Boyd Willis Hydromet Consulting (BWHC) and engineering company Ausenco Vector, under management of BHWC. The Scoping Study evaluated a number of options for the project involving HPAL and AL. In 2011 BHWC has undertaken further process and engineering studies as part of this PEA based on a preferred option involving parallel HPAL and AL circuits Process Selection Limonite and low magnesium grade saprolite mineralisation will be treated in a dedicated HPAL circuit. The process design for the HPAL leach plant is based largely on the hydrometallurgical route proven at Moa Bay in Cuba for five decades, and at the Sumitomo/Nickel Asia operated Coral Bay Nickel Project (Coral Bay) in the Philippines since Medium grade magnesium saprolite mineralisation will be treated in a parallel AL circuit. The AL circuit option has recently gained recognition as an alternative to the high capital cost HPAL route. An AL circuit was operated by BHP Billiton at their Ravensthorpe operations. The process is currently being investigated by Weda Bay Nickel (Eramet) in Indonesia, Berong Mining in the Philippines and BHP Billiton nickel projects to treat their high grade saprolite mineralisation types. An innovation in the Agata proposed processing route will be the inclusion of saprolite neutralisation (SN). This will involve pre-neutralisation of the residual free acid in the combined leach discharge streams using high magnesium saprolite ore. This process, performed at atmospheric pressure, will consume much of the free acid while recovering additional nickel and cobalt values from the saprolite ore. Neutralisation of the remaining acid will be achieved using limestone. After SN, the pregnant solution will be recovered by conventional counter-current decantation (CCD), followed by limestone neutralisation of excess acid and precipitation of iron, aluminium and chromium, prior to metal recovery. Report No R-Rev1 72

87 Metal recovery will be by a two-stage MHP circuit similar to that operated for several years at the Cawse Nickel Project (Western Australia) and more recently at Ravensthorpe Nickel Operation (Western Australia). The MHP will be exported Development of Process Design Criteria Preparation of Mineralisation Separate mineralisation preparation facilities are proposed for limonite and saprolite mineralisation types. The slurry settling tests at SGS demonstrated that limonite could be settled to 40% solids and saprolite to 34-36% solids. Testwork at SGS included preliminary scrubbing and screening. This work demonstrated that scrubbing a sample of limonite/transition mineralisation blend followed by screening at mm would recover about 90% of the nickel while rejecting 18-19% of the total mass, 36-38% of the silica and 37-40% of the magnesium. Based on these results additional equipment has been included in the design to allow for de-agglomeration (scrubbing/screening) to potentially liberate nickel bearing fines from barren coarse material, however no upgrade or rejection has been included in the PEA mass balance High Pressure Acid Leaching Design criteria for the HPAL section was selected from the SGS test results, supplemented where necessary by metallurgical response data typical for South East Asian nickel laterites. The key design parameters adopted from the SGS testwork are summarised in Table Table 20-7: HPAL Design Criteria Criteria SGS Results Selected Value Residence Time (min) Temperature ( C) Acid Addition (kg/t ore) * Residual Free Acid (g/l H 2 SO 4 ) ** Extractions (%): Ni Co Mg Terminal Concs (g/l): Fe(III) Al < * calculated using METSIM, includes impact of low magnesium saprolite in HPAL feed ** to better deal with higher Mg grade resulting from inclusion of low magnesium saprolite in HPAL feed Atmospheric Leaching Design criteria for the HPAL section was selected from the SGS results, supplemented where necessary by metallurgical response data typical for South East Asian nickel laterites. The key design parameters adopted from the SGS testwork are summarised in Table Report No R-Rev1 73

88 Table 20-8: AL Design Criteria Criteria SGS Results Selected Value Residence Time (h) 4 4 Temperature ( C) Acid Addition (kg/t ore) * Residual Free Acid (g/l H 2 SO 4 ) Extractions (%): Ni Co Fe Al Mg * calculated using METSIM, based on processing medium magnesium saprolite Saprolite Neutralisation Design criteria for the SN section was selected from the SGS results, supplemented where necessary by metallurgical response data typical for South East Asian nickel laterites. The key design parameters adopted from the SGS testwork are summarised in Table Table 20-9: Saprolite Neutralisation Design Criteria Criteria SGS Results Selected Value Residence Time (h) 6 6 Temperature ( C) Residual Free Acid (g/l H 2 SO 4 ) Extractions (%): Ni Co Terminal Concs (g/l): Fe(III) Al Counter-Current Decantation Design criteria have been assumed based on the metallurgical response of similar South East Asian laterites and are summarised in the following table. Table 20-10: CCD Design Criteria Criteria SGS Results Selected Value Number of CCDs - 7 * Underflow % solids CCD-1 Flocculant Dosage (g/t solids) Thickener unit area (m 2 /t/d) Soluble Ni recovery across CCD train (%) * based on METSIM modelling to achieve <1% soluble nickel loss across CCD circuit Metal Recovery No testing of the hydrometallurgical process downstream of the CCD circuit was performed in the scoping study testwork program at SGS. The recovery of nickel and cobalt to MHP in downstream processing has been operated at Cawse and Ravensthorpe, and extensively piloted for several other projects including Report No R-Rev1 74

89 Ramu, Marlborough and Wingellina. Design criteria for the downstream processing steps were selected from database information for these projects Mass Balance Calculations The process flowsheets, process design criteria and the testwork data from the SGS metallurgical testwork program were used to develop a process mass and energy balance. The simulation software used for the PEA process model was METSIM, and the model was developed by BWHC. The METSIM model was developed using the selected flowsheet, including the major equipment items. METSIM employs a comprehensive component database, including detailed thermodynamic properties, to balance the mass and energy flows, and to simulate the performance of a full scale operating plant. The inputs into the model included: plant feed tonnages head grades chemical reactions and reaction extents reagent composition and utilisation operating conditions (temperature, pressure, etc). The objective of the METSIM model was to generate: mass balance energy balance reagent consumptions product tonnages waste/effluent quantities. The METSIM model generated stream mass and volume flows, which were used in developing the capital and operating cost estimates Process Description Overview The processing plant consists of the following operations: Leach Plant: Preparation of Mineralisation High Pressure Acid Leach Atmospheric Leach Recycle Leach Saprolite Neutralisation CCD Circuit Iron/Aluminium Removal Stages 1 and 2 Final Neutralisation Stages 1 and 2. Report No R-Rev1 75

90 Product Section: Mixed Hydroxide Precipitation Stages 1 and 2. Process Services: Sulphur Handling Sulphuric Acid Plant Limestone Plant Lime Plant Reagent Preparation Leach Plant The mineralisation treatment plant includes separate circuits to treat limonite and saprolite ores. The limonite mineralisation preparation circuit produces de-agglomerated limonite slurry for HPAL and the saprolite circuit produces three types of ground saprolite slurry for HPAL, AL and SN. The limonite mineralisation treatment plant comprises the following principal operations: primary crushing to <200 mm by roll sizer limonite de-agglomeration by wet rotary drum scrubbing and rejection of the coarse oversize fraction (>10 mm) by screening single stage, closed circuit ball milling to produce a ground limonite slurry HPAL feed slurry thickening. The saprolite mineralisation treatment plant consists of the following principal operations: primary crushing to <200 mm by roll sizer single stage, closed circuit saprolite SAG milling to produce ground saprolite slurry storage tanks for three types of ground saprolite slurry: low magnesium saprolite, medium magnesium saprolite and high magnesium saprolite thickening of the medium magnesium saprolite and high magnesium saprolite slurries for delivery to atmospheric leaching and saprolite neutralisation. HPAL feed comprises limonite and low magnesium saprolite mineralisation slurries, which are combined in the required proportions in the HPAL feed thickener. The HPAL plant includes feed slurry heating, leaching of nickel and cobalt from limonite mineralisation at high temperature (255 C) and pressure (4425 kpag), and autoclave discharge slurry pressure letdown. Atmospheric leach feed comprise medium magnesium saprolite slurry. In the atmospheric leach circuit nickel and cobalt are leached from saprolite mineralisation at atmospheric conditions ( C and ambient pressure). Sulphuric acid is used as the lixiviant for both HPAL and atmospheric leaching. The HPAL circuit maximises heat recovery by recycling steam flashed during depressurisation of the slurry back to the preheat circuit. A recycle leach circuit uses a small stream of sulphuric acid to re-dissolve nickel and cobalt precipitated in the downstream iron/aluminium removal and second stage MHP circuits. Discharge slurries from the HPAL, atmospheric leach and recycle leach circuits are combined and forwarded to the saprolite neutralisation circuit where the neutralising capacity of the high magnesium saprolite mineralisation consumes some of the excess free acid. Additional nickel and cobalt are leached from high magnesium saprolite during this Report No R-Rev1 76

91 process. The resultant slurry flows to a seven-stage CCD circuit, to separate and wash soluble nickel and cobalt from the leach residue solids. The recovered pregnant liquor (CCD-1 overflow) is forwarded to two stages of iron/aluminium removal. In the first stage of iron/aluminium removal the majority of the remaining free acid in solution is neutralised with limestone slurry and most of the ferric iron and some of the aluminium in solution are precipitated. The product slurry is thickened and the precipitated solids are directed to CCD-3 for recovery of soluble nickel and cobalt across the back half of the CCD circuit. In the second stage of iron/aluminium removal the remaining iron and aluminium are precipitated. The pregnant liquor is separated from the precipitated solids by thickening prior to transfer to the MHP area. Some nickel and cobalt are co-precipitated so the thickener underflow slurry is directed to the recycle leach circuit for recovery of the metal values. The barren leach residue solids from the final stage of CCD washing along with barren solution from the MHP circuit report to final neutralisation (FN) circuit where limestone and lime slurries are added sequentially to raise the ph of the slurry and precipitate most of the remaining metals from solution. An air stream is used as an oxidant in this process to aid manganese precipitation. The discharge slurry is thickened and the clear overflow solution is returned to the CCD circuit as wash water. Treated residue is pumped, at about 30% solids content, through an approximately 6 km long slurry pipeline to the residue storage facility (RSF). At the RSF, the residue is hydraulically deposited behind the retaining wall. Consolidation of residue over time produces a decant liquor which is returned via a decant pipeline to the process plant. The excess RSF decant is discharged to ocean outflow and is closely monitored to ensure compliance with the environmental discharge standards Product Section The virtually iron/aluminium-free pregnant leach solution (PLS) is forwarded to the first stage MHP reactors to precipitate the nickel and cobalt from the solution by the addition of magnesia slurry. The resulting precipitate contained in the slurry is subsequently directed to thickening. A portion for the thickener underflow slurry is recycled as seed to the first stage MHP reactors and the balance is forwarded to wash filtration. In wash filtration, the precipitate is filtered for further dewatering and washed with demineralised water to displace the chlorides and other sea salts entrained with the precipitates. The filter cake is then repulped with demineralised water and filtered in a pressure filter to achieve the required product moisture specification. The MHP product is packaged in 2 t bulk bags and stored in standard 6 m containers for shipment and sale. The un-precipitated nickel and cobalt values present in the first stage MHP thickener overflow are further recovered by lime precipitation in the second stage MHP reactors. The resulting precipitate is thickened and recycled back to the recycle leach area to re-dissolve the nickel and cobalt Plant Services Major process packages include a sulphur-burning acid plant, a limestone slurrying plant, a lime kiln and lime slaking plant, a magnesia slurrying plant and a residue storage facility. The sulphuric acid plant provides sulphuric acid for the leaching circuit and other process consumers, and high pressure steam for power generation. The acid plant products are up to 2700 t/d of 98.5% sulphuric acid and up to 152 t/h of HP steam. The limestone plant provides limestone in slurry form for neutralisation of acidic process liquors and crushed limestone for burnt lime production. The limestone plant consists of crushing and slurrying facilities. The limestone slurry at 30% solids is pumped to the process plant via a limestone slurry ring main. The lime plant provides lime in the form of milk-of-lime slurry for neutralisation of acidic process liquors and precipitation of nickel and cobalt in the second stage MHP circuit. The plant consists of a fuel-oil fired limestone calciner and lime slaking facilities. The milk-of-lime is pumped to the process plant via a ring main. Report No R-Rev1 77

92 The magnesia slurrying plant provides magnesia slurry for the precipitation nickel and cobalt as mixed hydroxides in the first stage MHP circuit. The magnesia slurry is pumped into the MHP reactors under dosage control Plant and General Infrastructure Introduction The provision of infrastructure is a significant part of the overall development of the project due to the green field nature of the proposed site. Existing infrastructure facilities are virtually non-existent in the immediate area of the proposed site except for an existing gravel public road and the exploration camp facilities. Key factors affecting the layout of infrastructure for the project include: the location of the mineralisation bodies the site topography access to site for equipment, operating personnel and reagents the position of the industrial and port sites. The facilities will be located predominantly in a coastal valley west of the mine site, as the topography is relatively flat compared to the steeper inland terrain. The infrastructure facilities to be provided for the project include: water supply and treatment power station and power reticulation port bulk materials handling fuel tank farm solid and liquid waste management plant control system plant site and service buildings and ancillary facilities accommodation village and facilities communications mobile equipment roads security Existing Regional Infrastructure A substantial population base exists within a short distance of the project area. The municipalities of Santiago and Jabonga, located within 10 km of the project area, each have populations of around people. Situated about 35 km by road to the south, Cabadbaran City has a population of over Report No R-Rev1 78

93 Butuan City, located about 65 km by road to the south, has a population of approximately , and Surigao City, located about 80 km by road to the north, has a population of approximately Facilities and services in Cabadbaran City include: hospital (Cabadbaran District Hospital) rescue service (Rescue 085) fire station police station electrical utility (ANECO: Agusan del Norte Electric Cooperative) elementary and high schools university (a campus of Caraga State University) Site Development Process Plant Site The process plant site is proposed to be located on a coastal site to the southwest of the mine site. The advantages of this location are: It has excellent access to the port facilities and the sea. It largely avoids land currently under agriculture. It provides an opportunity to locate the plant at a level above any likely tsunami effect created by seismic activity. It provides a platform to locate very heavy plant items on a cut bench therefore reducing foundation costs and potential impacts of differential settlement. The site is proposed to be located about 200 m inland in order to place the heavier plant on solid ground at an elevation of m above MSL. The process plant pad will be approximately 650 m in length and 400 m in width in a north south orientation. Some of the lighter plant equipment will be located in fill areas. Surface drainage is directed from a central elevated part of the site towards the northeast. Vehicle access to and from the plant site is from the north. The plant site will be cleared of all vegetation, tree roots grubbed and topsoil stripped from the site will be stored in stockpiles for later reuse as topsoil on the completed earthworks. Cut material shifted from the more elevated areas of the plant site will be used as fill in the lower areas of the plant site and in the port area to meet a minimum plant floor level above MSL. This cut to fill construction will include nearby facilities such as: mineralisation stockpile areas, port facilities areas, process plant offices, laboratories and control room pads Power Supply Power Station The power station uses steam generators to provide electrical power for the operation of the process plant, services and utilities, as well as for the accommodation village and all other related infrastructure. High pressure steam is produced from two sources. The major source of high pressure steam is from waste heat boilers in the sulphuric acid plant. The secondary source of high pressure steam is from auxiliary boilers that will produce supplementary steam into the same header for the high pressure steam distribution system. Report No R-Rev1 79

94 The power station is designed to satisfy two main operating scenarios: generation of 30.9 MW of power, including 16.8 MW of power for normal plant operations, with 124 t/h of HP steam imported from the sulphuric acid plant provision of 7.8 MW of power and 16.3 t/h of process steam, to maintain leach plant operation, critical equipment in other areas, and the accommodation village during acid plant outages. The plant configuration comprises two 16 MW condensing steam turbine generators and two 25 t/h package boilers. The two boilers provide significant flexibility to meet varied steam demands. The selection of condensing turbines allows low pressure steam to be extracted for process use. In addition, for emergency conditions and the black start of the power station, there are two diesel powered generators located within the power station complex. These ex-construction generators will be of sufficient capacity for their intended long-term function. Electric power will be generated at 13.8 kv 60 Hz with the generators connected to a main distribution substation for supply to the various process and infrastructure substations. The substations will contain switch gear, transformers and motor control centres for the connected loads Power Usage Summary The estimated power requirements for the project are summarised in Table Table 20-11: Power Summary Project Area Connected Power (MW) Absorbed Power (MW) Preparation Plant Leach Plant Product Section Major Process Packages Process Services and Utilities Plant Infrastructure General Infrastructure Allowances Total Power Reticulation The power station complex will contain the Main High Voltage Distribution Room from which will originate the feeders to all areas of the facility. High voltage distribution from the power station main switchboard will be via 13.8 kv cable. For major load centres within the process plant area the cables will go to the relative step down transformers for local distribution. For sites remote to the process plant, the cables will be connected to open wire 13.8 kv overhead transmission lines once they are outside the plant area. These areas include the accommodation facilities/camp, river water supply and similar areas. The transmission lines generally follow either roads or service corridors to the respective load centres. Ex-construction generators will be used at the mine site and at the limestone quarry. Report No R-Rev1 80

95 System voltage and frequency System voltages and frequency shall be as follows: 13.8 kv, 3 phase, 60 Hz, 3 wire supply shall be used for Primary Distribution from 13.8 kv Main Switchgear at Power Plant 4.16 kv, 3 phase, 60 Hz, 3 wire supply shall be used for selected applications 460 V, 3 phase, 60 Hz, 3 wire supply shall be used for distribution to motor control centres and related loads 220 V, 3 phase, 60 Hz, 4 wire, shall be used for lighting panel boards 220 V, 3 phase, 60 Hz, 4 wire, shall be used for receptacle panel boards, and miscellaneous single-phase loads 220/110 V, 3 phase, 60 Hz, 4 wire, or 110 V, 1 phase 60 Hz, shall be used for critical duty, Uninterruptible Power Supply (UPS) loads 24 V DC, 2 wire, shall be used for motor control circuitry. In general, utilisation voltages for motors shall be as follows: motors less than 350 kw: 460 V, three-phase, 60 Hz motors 350 kw and less than 1500 kw: 4.16 kv, three-phase, 60 Hz motors kw and larger: 13.8 kv, three-phase, 60 Hz. Motors will be direct on line (DOL) system Water General The project has significant water requirements for mining, processing and other uses. The main water requirements are: raw water for dust suppression seawater for ore slurrying filtered raw water for general process plant use potable water for domestic use demineralised water for steam generation and processing. Seawater and river water sources were identified as two potential water supply sources for this Project. Coffey 1 ( Consulting Services for the Conduct of Preliminary Baseline Environmental Studies, Volume 3: Water ) established that there was ample fresh water available from the Kalinawan River system, approximately 4 km to the northeast of the process plant site. The Water Supply system will consist of the following: main raw water supply to the process plant, port area and accommodation facilities seawater supply to the process plant. Report No R-Rev1 81

96 Water Requirements The water requirements were estimated based on the process water balance and typical potable water demands. The total raw water requirement has been assessed at approximately 9330 kl per day. For design purposes, an additional 15% allowance was added to this flow requirement. The overall water consumption for the project is summarised in the following table. Table 20-12: Water Consumption Summary Water Quality Daily Consumption (kl) Total raw water Filtered water Demineralised water Potable water 100 Seawater Concept Design The conceptual design for the water supply and major distribution system for this Project has been divided into the following elements: pump station intake works at the Kalinawan River major pumping station at the Kalinawan River pipeline from pumping station to raw water storage pond raw water storage pond pipeline from storage pond to process plant and water treatment plant balance tanks Water Reticulation The water reticulation system will provide water for the following uses: filtered raw water, potable water, demineralised water and firewater. Treated water will be reticulated throughout the site including to the process plant, port and accommodation facilities Water Treatment The water treatment system produces water to three water quality standards: filtered raw water for process and general plant use including gland seal water, cooling water and fire water potable water for human consumption and ablutions demineralised water for boiler feed water and other process water requirements. The primary source of water supply will be the Kalinawan River. The Coffey report states that the river water quality is generally good, with little suspended solids and turbidity. The proposed treatment consists of the following processes: coagulation/settlement for treatment of filtered raw water Report No R-Rev1 82

97 R.O. for demineralised water chlorination treatment for potable water. The water treatment plant will be located on a designated site at the south of the process plant Seawater Supply Seawater for the process plant is harvested near the wharf. The water is screened and then pumped from a pumping station near the barge loading area to the sea water storage tank for distribution. Most of the seawater is used for ore preparation and in the HPAL vent scrubber Port The wharf is located on the northeastern side of the plant area. The water depths beyond 50 m offshore are unknown at this stage as well as the seabed geotechnical properties. Assumptions have been made for the design and cost estimate for the underwater structures/foundations. The main wharf measures approximately 500 m 35 m. Concrete caissons foundation type will be used in shallow water and steel tubular piles in deeper water. The estimate has allowed for piles with maximum length of 40 m. The following wharf facilities provide the functional requirements of port operations: the main berth accommodating: DWT liquid tankers for acid, heavy fuel oil and diesel fuel, DWT bulk cargo ships for sulphur and product despatch, and DWT barges pipeline corridor and pumps for unloading liquid materials (diesel fuel, heavy fuel oil and acid) from the ships to storage tanks a 100 t crawler crane for loading and unloading containers admin office and warehouse. A heavy lift ramp is provided for unloading autoclaves, at up to 700 t, and other heavy modules during construction. This ramp will be designed such that it can be utilised as a permanent facility for accessing heavy loads for construction for future expansion and/or for operations. An access road, with maximum slope 6% and a road width of 6 m, accommodates multi-wheeler trailers with due allowance to minimise curves Bulk Liquid Handling The quantities of petroleum products to be consumed by the mining and process operations are sufficiently large to make bulk tankers the most cost effective solution. The main storage area will be located at the port with service (day) tanks located at the process plant and the mine sites, etc. Supply is from either within the Philippines or from Singapore, and it is anticipated that vessels will be DWT. Products that will be delivered by these vessels are heavy fuel oil (power generation, lime kiln) and diesel fuel (mobile equipment fleet, etc) Heavy Fuel Oil Heavy fuel oil (HFO) will be pumped ashore by the ship s on-board pumps through a flexible hose to the wharf product piping contained in a gallery on the back of the wharf. Product will be metered during delivery to bunded storage tanks located onshore adjacent to the wharf. The HFO will be pumped from the port storage tanks to the process plant day tank at the rate of 25 m 3 /hr using pumps situated adjacent to the port tanks. A stand-by pump will be provided in case of a breakdown. Report No R-Rev1 83

98 Diesel Fuel Diesel Fuel will be pumped ashore by the ship s on-board pumps through a flexible hose to the wharf product piping contained in a gallery on the back of the wharf. Product will be metered during delivery to bunded storage tanks located onshore adjacent to the wharf. Diesel fuel will be pumped from the port storage tanks to the day storage tanks at the vehicle refueling facilities adjacent to the process plant at the rate of 25 m 3 /h using pumps situated adjacent to the port tanks. Stand-by pumps will be provided in case of a breakdown. A road tanker loading facility will be located adjacent to the port storage tank farm. Diesel fuel will then be transported to mine site day storage tanks. At these facilities the tanker will be unloaded into the day tank using flexible hoses between tanker and unloading pump manifold. At the mine site fuelling facilities, diesel fuel will be independently pumped from day storage tank to heavy and light vehicle fuel dispensing equipment according to the required demand. A marine fuelling facility will be located at the barge unloading wharf where provision is made to meter and control refuelling of marine vessels such as the tugs and line boats. It may be possible for this facility to be gravity fed from the port storage tanks Bulk Solids Handling Bulk Sulphur Handling and Storage Bulk prilled sulphur will be delivered in geared Handymax vessels ( DWT), and will be unloaded using the ships gear and mechanical grabs of 7.5 m 3 capacity. The grabs will discharge to rubber tyred hoppers at the wharf. The hoppers will incorporate a variable speed belt feeder discharging to cross-wharf conveyors. The cross-wharf conveyors will also be mounted on rubber tyres. Sulphur will be transported by a wharf conveyor and transfer conveyor to a radial stacker that will discharge to a rectangular stockpile of t capacity. The stockpile will be located close to the port area. Sulphur will be reclaimed from the stockpile by front-end loader for feed to the plant Bulk Limestone Handling and Storage Limestone will be quarried from a deposit regional to the process plant. Limestone will be delivered by quarry trucks to a ROM hopper adjacent to the quarry. The ROM hopper will incorporate a fixed grizzly and a hydraulic rock breaker mounted on the hopper at the grizzly level for secondary breakage of any oversize material delivered to the ROM hopper. Limestone will then be trucked from the ROM hopper to the process plant site for further crushing and processing. For details of this process, please refer to the Process Description section of this report Fuel Tank Farm The main storage area will be located at the port with service (day) tanks located at the process plant and the mine sites, etc. The size of the storage required is governed by the size of the bulk ships which are readily available for charter. It is anticipated that vessels would be up to DWT. Products that would be delivered by these vessels are Heavy Fuel Oil (power generation, lime kiln) and diesel fuel (mining fleet and mobile equipment fuelling). The storage tank capacities are sized on the basis of the compartment volumes of the sea tankers likely to be used to deliver bulk liquids and the need to have service storage at the site to cover any interruption to supply. This interruption could be in the form of a delay in the arrival of a tanker to a break down or failure in the transfer pumping system. The storage tanks will be located on-shore, adjacent to the wharf facilities. Report No R-Rev1 84

99 Tanks will be fabricated from mild steel and placed inside separate earth bunds at the port and mine sites, and inside bunding appropriate to the location in the process plant. The size of tanks at the process plant and mine site is based on daily consumption estimates Liquid and Solid Waste Management Waste Water Treatment In order to meet the appropriate environmental standards for the disposal of sewage effluent from the facility, it is proposed to construct a centralised sewage reticulation system to cater for the administration centre, change house and other buildings. A packaged sewage treatment plant to handle domestic type waste water will be installed. As the service buildings are scattered over a wide area it may not be practical to connect some of the more remote buildings with only one or two toilets to the central sewage reticulation system. In these cases septic tanks with transpiration beds to absorb the partially treated effluent would be provided. Alternatively the septic tanks could be increased in size to form holding tanks and the influent could be pumped out to a tanker and carted on a daily basis to the main sewage treatment plant for further processing Solid Municipal Waste Management Infrastructure facilities will be developed to provide for the disposal of solid wastes generated by the process plant and the accommodation village facilities and construction camp, in separate sites. These solid waste disposal facilities will most likely be located in a remote valley close to the mine area. They will be provided with secure access to ensure safe and efficient operation and storage Plant Process Control System The process control system is a vital element in achieving safety of personnel and plant as well as efficiency and reliability of plant operation. It will be designed to maximise the operability and availability of the respective operating areas, while minimising the operator intervention required to control the plant. However, in accordance with normal operating procedures, sufficient full time operators are still required to handle potential plant upsets. All plant devices are to be operated and controlled from a single Central Control Room (CCR) by Operator Interface Stations (OIS) via a Distributed Control System (DCS). All interlocking and sequencing will be performed by the DCS. The DCS will be capable of upward data integration to a Management Information System (MIS) and a Maintenance Management System (MMS). A secure internet connection will also be included to allow remote plant monitoring. Sufficient measuring devices are to be installed to enable the operator to have a total view of the plant. This will allow the operator to control all aspects of the plant, such that faults and hazardous occurrences can be detected and monitored, and the consequences minimised. The parts of the processing plant supplied as vendor packaged equipment are, in some cases, essentially stand-alone and may be controlled locally by the vendor supplied control panel. The stand alone control systems will form part of and be supervised by the plant control system. Control of the entire plant is possible from the CCR, which is interconnected via a dual redundant fibre-optic data highway to substations and field auxiliary rooms located around the plant. A telemetry system for monitoring of remote sites (i.e. the residue storage facility) is integrated with the plant DCS system. Each control room operator works on a control panel of multiple OISs. An additional OIS is provided for engineering activities and can be used as an operator station in the event of an emergency. The control panels are adjacent to each other to allow efficient interaction of the operators. Each panel is capable of controlling all areas of the plant, but will typically display the control screens for only part of the plant. The CCR is to be located in the leach plant to allow a high interaction between the control room operator and the field operators in this area. The control room operators will be in communication with the field operators chiefly by hand held radios. Closed circuit television (CCTV) will be installed to allow the control room Report No R-Rev1 85

100 operators to visually monitor critical equipment. The field operators will perform all other visual equipment monitoring. The system provides fully redundant main processor modules operating in parallel. The processor units operate independently from each other and any failure detected during internal diagnostic routines will not degrade operation of the system. Failure of any one of these processors will cause the system to switch over to the back-up module and an alarm to be initiated. Communications between different modules on the DCS network will be via a dual redundant data highway. Communications between the substation/field auxiliary rooms control system modules will be via a dual redundant fibre optic network. The DCS controller electronics will be supported by a UPS which will provide 30 minutes of continuous operations in the event of a power system failure. As the exception to this rule several large equipment items and package plants such as the power station, water treatment plant, HPAL feed pumps and process filters may be supplied with their own PCS/PLC control equipment. These vendor-supplied systems will form part of, and be supervised by, the plant control system and shall be supplied in accordance with the project selection requirements and design criteria. Suitable graphic/control group displays will be configured on the OISs in the DCS to monitor the operating conditions on each of the above packages. Interlocking between these packages and other process equipment will be performed by the plant control system. All motors shall have a MANUAL/LOCAL condition reported on the DCS and some motors shall have AUTO/MANUAL selection on the DCS. An emergency bus will supply the emergency lighting distribution boards, UPSs, critical plant instruments (including the DCS) and critical equipment such as thickener rake mechanisms, the autoclave agitator seal water system and certain utilities Buildings Plant Site Buildings A number of buildings will be constructed at the plant site to support operational activities. Below is the list of buildings and infrastructures: Main Admin Office Building two-storey building Canteen, Clinic and Change House two-storey building Workshop Spare Parts Storage Building Product Storage Building Laboratory Process Control Room Chemical Storage Building Bulk Limestone Storage Shelter Bulk Sulphur Storage Shelter. Office, canteen, clinic and change house, and laboratory buildings will be reinforced concrete structure with brick walling and corrugated metal sheet roofing. Report No R-Rev1 86

101 Workshop, storage, shelter buildings will be steel framed structures with corrugated metal sheet walling and roofing. Foundations will be reinforced concrete spread footings with a maximum depth of 1.5 m from ground level. No allowance has been applied for pile foundation. The estimate has allowed for furniture, kitchen/laundry equipment and mechanical equipment such as overhead crane at the workshop, HVAC, pumps, etc Town/Village A town/village will be built as the main accommodation facilities to support plant operations. The village has been designed to accommodate approximately 50% of the project workforce, with the balance of the personnel commuting to site daily from local towns. The accommodation village is located about 1 km from the plant area. A dedicated access road will connect the village and plant. The town consists of the following: four units at 14 personnel expatriate/senior staff accommodation four units at 10 personnel national staff accommodation six units at 48 personnel non-staff accommodation 300-seat mess hall and kitchen emergency clinic building can accommodate four patients laundry building general storage building admin building recreation hall Indoor Sport Hall to accommodate table tennis and badminton outdoor sport fields comprise of three lawn tennis courts, one football field, two volley ball/basket ball fields sewage treatment plant complete with catch basin two generators: silent type at 750 kva complete with 5000 L diesel day tanks. All buildings at the town/village will be constructed from reinforced concrete structure, brick walling and corrugated metal sheet roofing. Foundations will be reinforced concrete spread footings with max depth of 1.0 m from ground level. No allowance has been made for pile foundations. The cost estimate has allowed some assumptions as below: a water supply pipeline, 1000 m long 150 nominal bore (NB), to transport potable water from the plant allowances for culverts crossing the internal road at the town landscaping furniture, kitchen/laundry equipment and general mechanical equipment, e.g. pumps, High Voltage AC (HVAC), etc. Report No R-Rev1 87

102 Access Roads Access roads are provided to link various coastal infrastructure facilities with the process plant site. These facilities include the permanent accommodation facilities and construction camps, port, construction industrial area, water and sewerage treatment plants, limestone quarry, waste tips, etc. The site access roads will consist of a 6 m wide unsealed crushed rock pavement (i.e. 4 m wide travel lane with 2 m wide shoulder allowance). The maximum grades will be limited to 1:8 (12.5%) to allow truck access for maintenance purposes Communications Overview Communications are vital for both the construction and the operation of a large plant such as that proposed for the Agata Nickel Project. The key focus of this stage of the study has been to produce an estimate for a solution that will provide a good compromise between functionality and cost. The proposed communications system integrates telephone, facsimile, UHF radio and computer data requirements on a VSAT satellite circuit linked to the public network. For mobile communications, a multi-channel trunked radio system will provide mobile voice communication. A broadband cable will be provided to link the plant area into the main system Communications Infrastructure and Equipment The scope of the project communications includes: voice communications, both fixed and mobile data communications including network infrastructure and hardware desktop hardware and software (excludes business software and hardware for sulphuric acid plant, etc) security video system satellite television for the permanent accommodation facilities Security and Fencing Chain link fencing complete with security posts at access gates will be installed at the perimeter of process plant site, village, port, mine camp, mine industrial area and magazine-explosive storage area. A concrete wall fence will also be installed at the magazine-explosive storage area for blast containment. The fences shall be constructed from: posts: galvanised steel pipe 75 mm 2 m high, at 3 m spacing galvanised steel chain link 50 mm diamond mesh three lines of galvanised barbed wire on top of fence post-bracing: galvanised steel pipe 50 mm with 45 angle, to be installed at corners or at 12 m spacing for straight fence foundation: reinforced concrete with minimum 0.5 m post-embedment gates shall be made of the same material as the fence, and may be either swing or slide operated. Report No R-Rev1 88

103 20.6 Residue Management Introduction As part of the PEA review, Golder has reviewed the sections of the Agata Nickel Project Scoping Study (Boyd, USVC RevC, 2010) that relate to residue management. This section presents the results of our review and provides a revised cost estimate, based on option to store the first seven years of residue generated by the process plant in a valley located to the southwest of the main pit, with subsequent storage in an above-ground facility located within the pit footprint Review of existing Information A review of the residue management section of the Scoping Study, presented in: Process Plant Description Base Case and Option 1, Residue Storage Facility Process Plant Description Option 2, Residue Storage Facility Capital Costs, Table 9-1 and Table 9-2 Capital Costs, Residue Storage Facility and Site Development Costs Environmental and Social, Solid Residue Storage Information relating to residue management is also referenced in other sections. The pertinent information resulting from the review, with commentary from Golder, is presented below. A representative residue sample was not available and hence, the physical properties were assumed based on the authors previous experience. Physical testing of the residue was recommended by the authors of the Scoping Study. This approach is reasonable for this level of study. Two alternatives were considered for the RSF: a valley RSF located in the coastal range or above-ground impoundments constructed on level ground to the east of the project area. The authors indicate that further work is required to identify suitable valleys and hence, the above-ground impoundment was costed for the study. Golder has carried out a desktop study to identify candidate valley RSF locations (see Section ). A retaining structure was designed for the first eight years of operation, with future expansions allowed for as deferred capital. The tailings would be delivered at 23% solids through a 5 km pipeline, with hydraulic deposition into the above-ground RSF. This approach seems reasonable provided that sufficient level ground is available for the above-ground RSF. No figures or drawings were available for review. It is assumed that the RSF is raised in the downstream direction. The RSF proposed for Option 2 is consistent with the Base Case and Option 1. This approach appears reasonable for this level of study. The costs associated with the RSF were based on earthworks data provided by Mindoro and estimates prepared by Ausenco Vector for a similar project in Northern Philippines. The RSF cost was developed assuming three phases of development. This approach appears reasonable. Earthworks data were not available for review, however, costs were included in Tables 9-1 and 9-2 and are reproduced in Table Report No R-Rev1 89

104 The phases presented in Table 9-2 are not consistent with the phases presented in Section of the Scoping Study. The RSF is acknowledged as being one of the higher risk components of mining. The authors indicated that the RSF should be designed to conventional tailings standards, should make a provision for water management and should include other engineering controls such as a liner (geomembrane and/or compacted clay), leachate collection systems to minimise hydraulic head on the liner, subsurface drains beneath the liner to address groundwater upwelling and aggressive surface water controls to divert flows from the TSF. The inclusion of a liner will be dependent on the environmental compliance criteria for the project and the points of measurements. However, it appears reasonable to include provision for a liner at this level of study. A leachate collection system and subsurface drains are supported by Golder. It is agreed that surface water management will be critical to the success of the project. Incident rainfall, non-diverted surface water and supernatant water will be treated prior to discharge into the ocean. This approach is reasonable, provided that sufficient studies are carried out to assess the feasibility. Costs for the RSF estimated in the scoping study (2010) are presented in Table Table 20-13: Summary of Initial and Deferred Capital Costs included in the Scoping Study Phase of RSF Development Estimated Cost from Scoping Study Phase 1 USD Phase 2 USD Phase 3 USD Phase 4 (Base Case and Option 1 only) USD Total USD There was no specific information relating to the capacity of this RSF. Assuming a mine life of 20 years (reference Section of the Scoping Study) and assuming a tailings tonnage of 1.6 Mtpa (estimated based on the solids deposition rate per day presented in Appendix 1.3) the cost per dry tonne of residue is estimated to be USD2.79. This cost per dry tonne of residue appears to be on the low end for residue management in the Philippines. No allowance for discounting using a net present value approach has been included in this calculation Residue Management Options Overview As part of our review, Golder carried out a desktop study to identify candidate locations for the RSF. The initial focus was to identify the level ground location referenced in the Scoping Study, to allow the earthworks volumes to be estimated and a meaningful cost comparison to be made. Candidate locations for a valley-fill RSF were also considered Engineering Design Criteria and Assumptions The following information and assumptions were used in the desktop study. The currently available topographic survey represents the extent of the available leases and candidate RSF locations are required to be within this extent Report No R-Rev1 90

105 The facility will lined with a geomembrane or similar A leachate collection system and subsurface drainage system will be required Surface water diversion structures will be required A 5 m freeboard has been allowed for management of supernatant water and stored incident rainfall / runoff The tailings beaches have been assumed to be horizontal There are no constraints (e.g. wildlife reserves, townships, etc.) within the area covered by the topographic survey Approximately 1.6 Mt of tailings will be generated annually for 15 years (provided by Boyd Willis Hydromet Consulting via on 22 February 2011) An allowance of 12.5% in addition to the above tonnage is recommended to account for possible increases in plant through-put (provided by Boyd Willis Hydromet Consulting via on 22 February 2011) The tailings will achieve a dry density of about 1 t/m 3 in the longer term, indicating that a total volume of 27 Mm 3 is required to be stored The mined out pit will initially not be available for storage of residue due to scheduling constraints Based on the above information, candidate RSF locations were identified within the extents of the survey Candidate RSF Locations The candidate valley RSF locations identified in the desktop study are presented in Figure Report No R-Rev1 91

106 Figure 20-7: Candidate Valley RSF Locations For each valley location, the storage capacity and embankment fill volume is presented in Figure Construction of an above-ground RSF located within the pit footprint has also been identified as an option. A review of these options indicates that a combination of Option A and an above-ground RSF located within the pit footprint would be required to meet the capacity requirements. This combination is considered to be economically attractive as it makes use of already disturbed ground, after the mining operations have ceased. For the purposes of this study, a cost estimate has been prepared for this combination. Key aspects of this option include: There will be a need to install surface water diversion measures to reduce the volume of water to be managed on the valley RSF The proposed haul road alignment will need to be revised to allowed the RSF embankments to be raised to a sufficient elevation to provide the target storage capacity The footprint area of the valley TSF will need to be cleared, grubbed and prepared for installation of a subsurface drains, followed by a liner Water from the RSFs is assumed to be treated and discharged to the ocean (the costs for this are assumed to be addressed elsewhere) Report No R-Rev1 92

Paladin Energy. Development & Expansion of the Langer Heinrich Operation in Namibia. June 2009

Paladin Energy. Development & Expansion of the Langer Heinrich Operation in Namibia. June 2009 Paladin Energy Development & Expansion of the Langer Heinrich Operation in Namibia June 2009 1 Disclaimer This presentation includes certain statements that may be deemed forward-looking statements. All

More information

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME African Gold Group, Inc. TSX-V: AGG Yonge & Richmond Centre 151 Yonge Street, 11th Floor. Toronto Canada M5C 2W7 Tel: +1 647 775 8538 website : www.africangoldgroup.com AFRICAN GOLD GROUP, INC. DEFINITIVE

More information

Savannah North Scoping Study Looking into the future 3 February 2016

Savannah North Scoping Study Looking into the future 3 February 2016 Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement

More information

ALCYONE REPORTS JORC SILVER RESOURCES

ALCYONE REPORTS JORC SILVER RESOURCES ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR

More information

Update on Heap Leach potential of the Murchison gold project

Update on Heap Leach potential of the Murchison gold project 3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and

More information

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW NEWS RELEASE February 11, 2008 Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW INTERNATIONAL MINERALS ANNOUNCES 6.2 MILLION OUNCES OF MEASURED AND INDICATED GOLD RESOURCES AND RESULTS

More information

Mako Project, Eastern Senegal Completion of Scoping Study

Mako Project, Eastern Senegal Completion of Scoping Study Toro Gold Ltd Trafalgar Court Admiral Park, Guernsey. GY1 3EL. News Release: 18 th April 2013, Guernsey Mako Project, Eastern Senegal Completion of Scoping Study Toro Gold Ltd ( Toro Gold or the Company

More information

For personal use only

For personal use only 10 May 2011 ASX: GRR Grange Resources Limited Australia s leading magnetite producer Successful Completion of Southdown Project PFS Grange Resources Limited ( Grange or the Company ) is pleased to announce

More information

For personal use only

For personal use only Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT

POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT Highlights: POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT Positive Scoping Study confirms technical and economic viability of the Salamanca Project; Initial mine life of 11 years,

More information

For personal use only

For personal use only ASX Release 28 January 2016 QUARTERLY ACTIVITIES REPORT For the quarter ended 31 December 2015 Level 1, 672 Murray Street West Perth WA 6005 Locked Bag 8 West Perth WA 6872 t. +61 8 9322 1182 f. +61 8

More information

Feasibility Study shows low cost battery grade lithium hydroxide production possible using ELi Technology

Feasibility Study shows low cost battery grade lithium hydroxide production possible using ELi Technology ASX RELEASE 11 July 2016 Feasibility Study shows low cost battery grade lithium hydroxide production possible using ELi Technology Highlights Positive results for Feasibility Study ( FS ) on producing

More information

Detour Gold Provides New Life of Mine Plan for Detour Lake

Detour Gold Provides New Life of Mine Plan for Detour Lake January 25, 2016 NEWS RELEASE Detour Gold Provides New Life of Mine Plan for Detour Lake Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) is pleased to announce a new life of mine plan

More information

SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST

SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST JULY 30, 2015 TSX: FM; LSE: FQM CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT Certain statements and information herein, including all statements that

More information

BAUXITE RESOURCES LIMITED

BAUXITE RESOURCES LIMITED BAUXITE RESOURCES LIMITED POSITIVE EXPORT DSO BAUXITE SCOPING STUDY RESULTS RECEIVED FOR 100% BRL FORTUNA PROJECT Highlights Existing Mineral Resource and rail logistic chain can support a Direct Shipping

More information

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Toronto, Ontario, November 17, 2014 - Continental Gold Limited (TSX:CNL; OTCQX:CGOOF) ("Continental" or the

More information

For personal use only

For personal use only Mawson Iron Project PERTH 21 ST NOVEMBER 2015 Dr Gavin England General Manager DISCLAIMER AND COMPETENT PERSONS STATEMENT Slogan XXXX URBANISATION & INDUSTRIALISATION Chinese urbanisation and industrialisation

More information

INVESTOR PRESENTATION JULY 2013

INVESTOR PRESENTATION JULY 2013 INVESTOR PRESENTATION JULY 2013 DISCLAIMER This presentation contains only a brief overview of Millennium Minerals Limited. The contents of this presentation, including matters relating to the geology

More information

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note

More information

Cannon Big Pit Given the Green Light

Cannon Big Pit Given the Green Light ASX Release Tuesday 3 November 2015 Cannon Big Pit Given the Green Light Southern Gold maintains 50% profit share on Cannon Metals X estimate open pit recovered gold +270% to ~50koz Significant cash flow

More information

For personal use only

For personal use only 27 January 2016 Savannah North Scoping Study Positive results demonstrate robust, long life, Ni-Cu-Co Project Highlights Mining Inventory of 6.07Mt @ 1.26%Ni, 0.64% Cu and 0.09% Co for 76,500t Ni, 38,600t

More information

Outotec HIGmills; A Fine Grinding Technology

Outotec HIGmills; A Fine Grinding Technology 23 rd International Mining Congress & Exhibition of Turkey 16-19 April 2013 ANTALYA Outotec HIGmills; A Fine Grinding Technology H. Lehto Outotec Finland Oy A. Paz Outotec Pty Ltd, Perth, Australia I.

More information

MINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE

MINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE Issue No. 128 June 2015 MINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE Issue No. 95 (March 2009) of this publication, formally known as Pincock Perspectives, has been one of our most requested and referenced

More information

For personal use only

For personal use only DECEMBER 2011 Issued 31 January 2012 HIGHLIGHTS INDIAN IRON ORE MINING PROJECT Significant on-site work completed and installation of phase one processing infrastructure underway at Kurnool iron beneficiation

More information

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%

More information

BACANORA MINERALS ANNOUNCES SONORA LITHIUM PROJECT UPDATE, FILING OF PRE-FEASIBILITY STUDY AND AMENDED MINERAL RESOURCE ESTIMATE

BACANORA MINERALS ANNOUNCES SONORA LITHIUM PROJECT UPDATE, FILING OF PRE-FEASIBILITY STUDY AND AMENDED MINERAL RESOURCE ESTIMATE TSX-V/AIM Symbol: BCN April 15, 2016 NEWS RELEASE BACANORA MINERALS ANNOUNCES SONORA LITHIUM PROJECT UPDATE, FILING OF PRE-FEASIBILITY STUDY AND AMENDED MINERAL RESOURCE ESTIMATE BACANORA MINERALS LTD.

More information

Candelaria and Ojos del Salado Chile

Candelaria and Ojos del Salado Chile TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 124,000-128,000 tonnes copper Cash costs of $1.45 per lb copper after by-product credits

More information

Sorby Hills Silver Lead Project

Sorby Hills Silver Lead Project ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

2015/01/04. New SAMREC Representative. Ken Lomberg. Group. Pr.Sci.Nat. Senior Principal Consultant. with Coffey. 30 years experience in South Africa

2015/01/04. New SAMREC Representative. Ken Lomberg. Group. Pr.Sci.Nat. Senior Principal Consultant. with Coffey. 30 years experience in South Africa New SAMREC Representative Ken Lomberg Chairman of the SAMREC Working Group Pr.Sci.Nat. Senior Principal Consultant with Coffey 30 years experience in South Africa 1 THE SOUTH AFRICAN CODE FOR THE REPORTING

More information

For personal use only

For personal use only ASX Release 27 September 2012 OPTION TO ACQUIRE 560,000oz PEAK HILL GOLD PROJECT RESOURCE AND INVESTMENT NL (ASX: RNI) (RNI or the Company) has reached agreement with Montezuma Mining Company Limited for

More information

Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation

Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation Foreword Appendix A serves as support documentation within the Best Practice Guidelines for Mineral Processing (BPGMP). It supplements

More information

Monitoring Program Waste

Monitoring Program Waste Procedure Document No. 2792 Document Title Monitoring Program Waste Area HSE Issue Date Major Process Environment Sub Process Authoriser Darryl Cuzzubbo Asset President Version Number 14 TABLE OF CONTENTS

More information

Fast Tracking to Production

Fast Tracking to Production Fast Tracking to Production THE ABU DABBAB TANTALUM-TIN-FELDSPAR PROJECT, EGYPT THE 400K DEVELOPMENT. Gippsland Ltd (February 2015)) 1 Important Notices Competent Persons Compliance Statement The information

More information

Positioned for Production: Exploring for Growth

Positioned for Production: Exploring for Growth ASX Code: AYN Positioned for Production: Exploring for Growth Andrew King, Managing Director May 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors

More information

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE:

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE: QUARTERLY REPORT Three Months Ending: 30 September 2012 ASX CODE: MZM ISSUED SHARES: 67.66M 52 WEEK HIGH: $0.80 52 WEEK LOW: $0.16 CASH ON HAND: $6.13M CONTACT: JUSTIN BROWN Managing Director +61 8 6315

More information

ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT

ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT NEWS RELEASE JANUARY 30, 2014 ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT VANCOUVER, CANADA. Sarama Resources Ltd. ( Sarama or the Company ) is pleased

More information

Resources Rising Stars

Resources Rising Stars ASX Code: AYN Resources Rising Stars Andrew King, Managing Director September 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors of Alcyone Resources

More information

ANNUAL GENERAL MEETING 2015. 30 November 2015

ANNUAL GENERAL MEETING 2015. 30 November 2015 ANNUAL GENERAL MEETING 2015 30 November 2015 Disclaimer Competent Person Statement This presentation may contain some references to forecasts, estimates, assumptions and other forward-looking statements.

More information

CIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves

CIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves CIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves Prepared by the CIM Standing Committee on Reserve Definitions Adopted by CIM Council on November 27, 2010 FOREWORD CIM Council, on

More information

Interim Financial Report for the half-year ended 31 December 2011

Interim Financial Report for the half-year ended 31 December 2011 Interim Financial Report for the half-year ended 31 December 2011 Note: The information contained herein should be read in conjunction with the most recent annual report. Aura Energy Limited Level 4, 66

More information

For personal use only

For personal use only dmin1138 27 January 2016 Key Points Corporate and Operational Update Savannah - decision made to preserve the value of the remaining Savannah orebody and to move the operation onto care and maintenance

More information

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies Sergei Sabanov, PhD, CEng MIMMM Date:10 December 2013 Location: Almaty, Kazakhstan SRK Consulting

More information

Q4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016

Q4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016 Q4 & FY2015 OPERATING HIGHLIGHTS January 29, 2016 1 FORWARD-LOOKING STATEMENTS This presentation contains certain statements that constitute forward-looking information within the meaning of applicable

More information

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ASX ANNOUNCEMENT & MEDIA RELEASE 25 November 2010 ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ENTITLEMENT OFFER TO FUND FURTHER EXPLORATION, ACQUISITION OF LONG-LEAD

More information

Chapter 5. Rules and Policies

Chapter 5. Rules and Policies Chapter 5 Rules and Policies 5.1.1 NI 43-101 Standards of Disclosure for Mineral Projects, Form 43-101F1 Technical Report and Related Consequential Amendments NATIONAL INSTRUMENT 43-101 STANDARDS OF DISCLOSURE

More information

D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t

D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t 29 January 2016 ASX Release ASX Code: CXX D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t Highlights Final stage Pilot Plant progressing well Definitive Feasibility Study on track

More information

For personal use only

For personal use only 29 January 2016 ASX Announcement December 2015 Quarterly Activities Report Summary New Satimola Limited Sale and Purchase Agreement Signed Financing to Acquire Satimola Limited Secured Revised Consulting

More information

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015 ANNUAL GENERAL MEETING Investor Presentation 24 November 2015 Corporate Structure ASX Code: OVR Shares on Issue 205.4 million Top 20 133.0 million (64.8%) Market Capitalisation $1.23 million (share price

More information

How To Mine And Treat Ore From Castle Hill Stage 1

How To Mine And Treat Ore From Castle Hill Stage 1 ` Dated: 5 th August 2014 NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ASX: PXG, PXGOA HIGHLIGHTS Development of Castle Hill Stage 1 with Norton Gold Fields potentially adds a

More information

Economic Highlights (In US$ unless otherwise indicated)

Economic Highlights (In US$ unless otherwise indicated) TSX.V TSX Venture Exchange Symbol: AME Suite 615-800 West Pender Street Vancouver, B.C. V6C 2V6 Canada Tel: 604.682.0301 Fax: 604.682.0307 email: info@amemining.com website: www.amemining.com Abacus announces

More information

Iron Ore Processing for the Blast Furnace (Courtesy of the National Steel Pellet Company)

Iron Ore Processing for the Blast Furnace (Courtesy of the National Steel Pellet Company) Iron Ore Processing for the Blast Furnace (Courtesy of the National Steel Pellet Company) The following describes operations at the National Steel Pellet Company, an iron ore mining and processing facility

More information

Irvine Island: Location. Irvine Island: Location

Irvine Island: Location. Irvine Island: Location 1 Board and Management Malcolm Macpherson Non-executive Chairman Director of Mineral Resources, Range River Gold Titanium Corp. Past CEO Iluka Resources and director of Portman Ltd. Tony Schoer Managing

More information

FIRST BAUXITE CORPORATION Suite 1220 1066 West Hastings St. Vancouver, B.C., V6E 3X1 604-806-0916 Fax: 604-806-0956 www.firstbauxite.

FIRST BAUXITE CORPORATION Suite 1220 1066 West Hastings St. Vancouver, B.C., V6E 3X1 604-806-0916 Fax: 604-806-0956 www.firstbauxite. FIRST BAUXITE CORPORATION Suite 1220 1066 West Hastings St. Vancouver, B.C., V6E 3X1 604-806-0916 Fax: 604-806-0956 www.firstbauxite.com October 6, 2011 NEWS RELEASE Symbol: FBX: TSX V FBI: FWB/BER FIRST

More information

For personal use only

For personal use only Investor Presentation August 2012 Disclaimer/Competent Person s Disclaimer: This presentation has been prepared by Buxton Resources ( Buxton ). The information contained in this presentation is a professional

More information

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO BUILDING A COPPER COMPANY IN BRAZIL PDAC Feb - 2014 - TORONTO CORPORATE & GOALS Shares on Issue 1.355B Significant Shareholders Share Price ~Au$0.07* Glencore 15% Market Cap ~Au$95m* BlackRock 5% Cash

More information

Barkerville Gold Mines Investor presentation q1 2016. The last great Canadian gold mining camp controlled by a junior mining company.

Barkerville Gold Mines Investor presentation q1 2016. The last great Canadian gold mining camp controlled by a junior mining company. Barkerville Gold Mines Investor presentation q1 2016 The last great Canadian gold mining camp controlled by a junior mining company. 1 Forward Looking statement This presentation and the material contained

More information

Condor Gold plc. (''Condor'' or "the Company") Whittle Consulting's Optimisation Study Significantly Enhances Economics

Condor Gold plc. (''Condor'' or the Company) Whittle Consulting's Optimisation Study Significantly Enhances Economics RNS Number : 7465C Condor Gold PLC 20 October 2015 7.00am on 20 October 2015 Condor Gold plc 7 th Floor 39 St. James's Street London SW1A 1JD Telephone +44 020 74081067 Fax: +44 020 74938633 Condor Gold

More information

Mines and Money Presentation

Mines and Money Presentation ASX:BCI 24 Mar 15 Mines and Money Presentation Morgan Ball Managing Director 2 DISCLAIMER This document has been prepared by BC Iron Limited ( BC Iron ) to provide an update regarding the companies to

More information

DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015

DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 CONTENT GLOBAL OPERATIONS WHERE WE VE COME FROM REVERSING THE TREND TRANSFORMATION

More information

Report for the Quarter Ended 30 September 2015

Report for the Quarter Ended 30 September 2015 Report for the Quarter Ended 30 September 2015 ASX: KIS Market Capitalisation $18.2 million Shares on Issue 165.3 million 52 Week High 16.5 cents 52 Week Low 8.9 cents Share Price Board of Directors Johann

More information

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS No. 7/2015 News release KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS BAAR, SWITZERLAND, August 12, 2015 Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its financial

More information

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

New Discoveries in the Relationship Between Macro and Micro Grindability

New Discoveries in the Relationship Between Macro and Micro Grindability Paper for the CIM AGM, Toronto, ON May 13, 29 11:2AM Page 1 of Authors: John Starkey, Starkey & Associates Inc. and Mike Samuels, Fortune Minerals Limited ABSTRACT New Discoveries in the Relationship Between

More information

TORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION

TORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION B-1 APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION 1.0 INTRODUCTION The disclosure of the results of exploration and development activity on mineral

More information

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS).

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS). ASX ANNOUNCEMENT Monday 1 st February 2016 Hot Chili to Raise A$1.6m via Placement to Strategic Shareholders Hot Chili Limited (ASX Code: HCH) is pleased to announce that it has received commitments from

More information

In-Pit Crushing and Conveying Phil Morriss

In-Pit Crushing and Conveying Phil Morriss In-Pit Crushing and Conveying Phil Morriss AGENDA 1. Introduction - what is In-Pit Crushing and Conveying (IPCC)? 2. What does a quarry need from IPCC? 3. Why and when should we consider using it? 4. How

More information

QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012

QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 Metals Finance Limited (ASX: MFC) is pleased to provide its Quarterly Activities Report for the three month period ending 31 May 2012. HIGHLIGHTS Separate

More information

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited (IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]

More information

Two stage nickel development strategy, gold resource growth and copper-gold discovery upside

Two stage nickel development strategy, gold resource growth and copper-gold discovery upside A successful explorer with pathway to production Two stage nickel development strategy, gold resource growth and copper-gold discovery upside Established license to operate in the world class mining districts

More information

The Unparalleled Opportunity of Colluli the Colluli Potash Project presented by Danakali

The Unparalleled Opportunity of Colluli the Colluli Potash Project presented by Danakali The Unparalleled Opportunity of Colluli the Colluli Potash Project presented by Danakali James Durrant Colluli Project Manager September 2015 Formerly South Boulder Mines ASX:DNK The growing world needs

More information

6 CONSIDERATION OF ALTERNATIVES

6 CONSIDERATION OF ALTERNATIVES 6 CONSIDERATION OF ALTERNATIVES 6.1.1 Schedule 4 of the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011 sets out the information for inclusion in Environmental Statements

More information

This discussion and analysis contains forward-looking statements. Please refer to the cautionary language on page 19.

This discussion and analysis contains forward-looking statements. Please refer to the cautionary language on page 19. This discussion and analysis of financial condition and results of operation of Thompson Creek Metals Company Inc. ( Thompson Creek or the Corporation ) is prepared as at August 7, 2008, and should be

More information

MEDIA RELEASE OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES

MEDIA RELEASE OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES MEDIA RELEASE 16 July 2012 OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES (MELBOURNE) OceanaGold Corporation (ASX: OGC, TSX: OGC, NZX: OGC) (the Company ) is pleased

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 ASX RELEASE ASX:AWV 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS Pit optimisation and final mine design completed Metallurgical test work completed Engineering

More information

PNG Mining & Petroleum Investment Conference December 2010. Geoff Day Executive General Manager PNG and Indonesia

PNG Mining & Petroleum Investment Conference December 2010. Geoff Day Executive General Manager PNG and Indonesia PNG Mining & Petroleum Investment Conference December 2010 Geoff Day Executive General Manager PNG and Indonesia Disclaimer Competent Persons Statement The information in this presentation that relates

More information

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016 Mining Indaba Presentation Capetown, South Africa 8 th 10 th February 2016 www.birimiangold.com 1 Disclaimer This presentation has been prepared by Birimian Gold Limited (BGS) for general information purposes

More information

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE KEFI Minerals Plc Doğu Akdeniz Mineralleri San. Tic. Ltd. Şti. Cemal Gürsel Cad. Yalı Apt. No:304 K:4 D:9 Karşıyaka İZMİR Tel: +90 232 381 9431 Fax: +90 232 381 9071 Email: info@kefi-minerals.com AIM:

More information

Construction Services

Construction Services Construction Services Construction Turning innovative ideas into delivered solutions At Golder Associates we strive to be the most respected global company providing consulting, design, and construction

More information

Establishing the feasibility of your proposed mining venture

Establishing the feasibility of your proposed mining venture RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing

More information

Outotec Gold Processing Solutions

Outotec Gold Processing Solutions Finland, September 2013. Outotec provides leading technologies and services for the sustainable use of Earth s natural resources. As the global leader in minerals and metals processing technology, Outotec

More information

WELCOME TO MINERAÇÃO PARAGOMINAS. José Flávio Alves - General Manager of Operational Support November 7, 2012

WELCOME TO MINERAÇÃO PARAGOMINAS. José Flávio Alves - General Manager of Operational Support November 7, 2012 WELCOME TO MINERAÇÃO PARAGOMINAS José Flávio Alves - General Manager of Operational Support November 7, 2012 What is bauxite? Rock composed mainly of aluminum oxide and aluminum hydroxide minerals Other

More information

Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM

Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM PRESS RELEASE Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM SILVERCORP ANNOUNCES POSITIVE PRELIMINARY ASSESSMENT FOR THE SILVERTIP SILVER-LEAD-ZINC PROJECT, BRITISH COLUMBIA, CANADA VANCOUVER, British

More information

RECYCLING AND UPCYCLING SPENT LITHIUM-ION BATTERIES

RECYCLING AND UPCYCLING SPENT LITHIUM-ION BATTERIES RECYCLING AND UPCYCLING SPENT LITHIUMION BATTERIES The Growing Lithium ion Battery Market Creates Parallel Disposal Problem Advances in the commercial development of lithium ion batteries have spawned

More information

Ivanhoe Mines announces an accelerated infill drilling program at the Kamoa copper project s Kakula Discovery in the D.R. Congo

Ivanhoe Mines announces an accelerated infill drilling program at the Kamoa copper project s Kakula Discovery in the D.R. Congo April 6, 2016 Ivanhoe Mines announces an accelerated infill drilling program at the Kamoa copper project s Kakula Discovery in the D.R. Congo SANTIAGO, CHILE Robert Friedland, Executive Chairman of Ivanhoe

More information

AngloGold Ashanti La Colosa Site Visit November, 2011

AngloGold Ashanti La Colosa Site Visit November, 2011 AngloGold Ashanti La Colosa Site Visit November, 2011 Colombia Jorge Tapia Disclaimer Certain statements made in this communication, including, without limitation, those concerning the economic outlook

More information

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS ASX / MEDIA RELEASE 18 September 2015 HIGHLIGHTS: ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS St George acquires 100% of the Hawaii and Mt Alexander North nickel sulphide exploration projects from BHP

More information

Condor Gold plc. (''Condor'' or "the Company") Whittle Consulting's Optimisation Study Significantly Enhances Economics

Condor Gold plc. (''Condor'' or the Company) Whittle Consulting's Optimisation Study Significantly Enhances Economics RNS Number : 6571M Condor Gold PLC 22 January 2016 22 January 2016 Condor Gold plc 7 th Floor 39 St. James's Street London SW1A 1JD Telephone +44 020 74081067 Fax: +44 020 74938633 Condor Gold plc (''Condor''

More information

Corporate Presentation October 2015

Corporate Presentation October 2015 TSX.V: GBB OTC PK: GBBFF THE GRANADA GOLD PROPERTY IN ROUYN - NORANDA QUEBEC a Corporate Presentation October 2015 GoldBullionDevelopmentCorp.com A Compelling Value Proposition High-grade rolling start

More information

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves 2001 Edition (as referred to in the Joint Ore Reserves Committee Code ( The JORC Code ) 1999 edition) Prepared

More information

THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES. Craig Roberts National Bank Financial

THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES. Craig Roberts National Bank Financial THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES Craig Roberts National Bank Financial ABSTRACT While various methods are available to estimate a mining project

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 ASX RELEASE ASX:AWV 29 January 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 HIGHLIGHTS Review of updated pit optimisation undertaken Metallurgical testwork report received confirming

More information

Silver Mine Project Investment Opportunity in Scandinavia

Silver Mine Project Investment Opportunity in Scandinavia Silver Mine Project Investment Opportunity in Scandinavia KPMG Corporate Finance ( KPMG ) has been retained by Sotkamo Silver as exclusive Financial and Strategic adviser in connection with the Project

More information

2015 Third Quarter Results Webcast October 29, 2015

2015 Third Quarter Results Webcast October 29, 2015 2015 Third Quarter Results Webcast October 29, 2015 Speaker Randall Oliphant Executive Chairman 2 Cautionary statements ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED CAUTIONARY NOTE REGARDING FORWARD-LOOKING

More information

For personal use only

For personal use only ASX Release 5 August 205 Colluli potassium rich brines to supplement process water ASX Code: Issued Capital Share Price Market Capitalisation Shares on issue Company options Cash Board of Directors Mr

More information

Prepared and Submitted by

Prepared and Submitted by Technical Feasibility Study Report of Proposed Sulfuric Acid and Phosphoric Acid Unloading Facilities, Acid Storage Tanks at the existing Wharf and Acid Transfer Pipeline Falling within the CRZ area &

More information

TIGER RESOURCES LTD ACN 077 110 304

TIGER RESOURCES LTD ACN 077 110 304 TIGER RESOURCES LTD ACN 077 110 304 1st Floor, 8 Parliament Place, West Perth WA 6005 PO Box 1618, West Perth WA 6872 Tel: (08) 9481-7833 Fax: (08) 9481-7835 Email: tiger@tigerez.com Website: www.tigerez.com

More information

Trevor Lloyd Director

Trevor Lloyd Director Trevor Lloyd Director Qualifications Environmental Toxicology and Health Risk Assessment Course - Qld Centre for Public Health (1998) Quality Assurance Auditing Training Course - Bywater plc (1994) University

More information

Project update April 2008 Eastern States Roadshow

Project update April 2008 Eastern States Roadshow NiWest Nickel Laterite Project Project update April 2008 Eastern States Roadshow An Emerging Australian Nickel Company Developing the NiWest Nickel Laterite Project, Western Australia (100%) World-class

More information