Nordic Balance Settlement

Size: px
Start display at page:

Download "Nordic Balance Settlement"

Transcription

1 Nordic Balance Settlement Handbook for Market Participants (DRAFT) Business process: Nordic Balance settlement Version: 0 Status: For review and comments Date: December 17st, 2013 Nordic Balance Settlement Handbook for market participants

2 Foreword This handbook is an overview of the Nordic imbalance settlement model. The handbook will be constantly developed and revised so that it always contains the latest available information. Currently, the design and preparation of the NBS model is still ongoing and therefore this first version of the handbook is not yet providing the complete view of the model. The purpose of the first version(s) of the handbook is to serve as a guideline for preparing and adapting to the coming changes in the Nordic imbalance settlement. The purpose is also to keep stakeholders up to date on agreed and open items and on the same time increase knowledge about the model. Some parts of this Handbook include areas and methods of the Nordic imbalance settlement model that have not yet been approved by the concerned stakeholders. These parts have been highlighted with blue background colour. The purpose of the Nordic Balance Settlement Handbook is to collect the essential information of the target state of the Nordic Balance Settlement model from market participant s perspective so that market participants can start preparing for the coming transformation. The handbook collects information about rules, regulations and standards which acts as requirements for market participants operating in different roles. All market participants operating in the countries involved in the Nordic Balance Settlement are to follow the defined rules, standards and regulations as defined in this handbook. It is to be noted that after the implementation of the Nordic Balance Settlement model some national differences in the imbalance settlement may remain. The handbook will be updated with the latest agreed items and enhancements every half a year. All the changes are listed in the change log included at the end of this document. Nordic Balance Settlement Handbook for market participants

3 Terminology Terminology Term Abbrevation Explanation Balance Responsible Party Distribution System Operator Key Performance Indicator Market Balance Area BRP DSO KPI MBA A Balance Responsible Party is a party that has a contract proving financial security and identifying balance responsibility with ISR. Balance Responsibility means obligations to ensure that a balance exists between the supply and withdrawal and for the purchase and sale agreements it has entered into. A Distribution System Operator is the distribution grid owner with the responsibility to distribute electricity from producers to its customers. The DSOs have the responsibility to meter production, consumption, exchange and report the metered data to the involved stakeholders. This responsibility includes also non-concessional grid operators. KPIs are utilized to measure the performance of different market participants. KPIs are a transparent way to display how TSOs, DSOs, BRPs and Res carry out their respective responsibilities. A Market Balance Area is an area that provides (exchange) schedules that represent a basis for monitoring of imbalances. The Elspot price is always the same within a MBA. Market Entity ME A collective term for MBA, MGA, PU and RO. Market Entity Connection MEC Market Entity Connection is a collective term for different kinds of connections either between different MPs (e.g. bilateral trades between parties) or MPs and MEs (e.g. MP s metered consumption in MGA or MP s production plan per PU). The MEC s time series data is the core of the balance settlement. Nordic Balance Settlement Handbook for market participants

4 Market Participants Metered Data Metering Grid Area Nord Pool Spot MGA NPS Market Participants are the main stakeholders in the settlement: the TSOs, DSOs, BRPs and retailers. These enter into transactions in one or more wholesale energy market. Metered (metering) data is, in this Handbook, used as a general term for all the data that the market participants meter, collect and report to ISR for balance settlement purpose. A Metering Grid Area is a physical area where consumption, production and exchange can be metered. It is delimited by the placement of meters for period measurement for input to, and withdrawal from the area. It can be used to establish the sum of consumption and production with no period measurement and network losses. MGAs are decided on national level. The Nordic energy exchange and the company that organises the physical electricity market in the Nordic countries. Operates in Norway, Denmark, Sweden, Finland, Estonia, and Lithuania. Production Unit PU A Production Unit is a generator or a set of generators within same power plant. Regulation Object Retailer Service Provider Imbalance Settlement Responsible Transmission System Operator RO RE SP ISR TSO A Regulation Object is a set of one or more generators and stations within a MBA decided by the respective Transmission System Operator (TSO) and the BRP. One RO can only include production of a certain technology (wind, hydro, nuclear, etc.). There can only be one BRP per RO. A Retailer sells electricity to an end user. It sells and buys electricity directly from a producer, another retailer or via NordPoolSpot. A retailer has to have an agreement with a BRP. A BRP can also have a RE role in the NBS model. The definition of a retailer might be updated in the next version of the handbook. A Service Provider is a party that provides operational balance management and settlement services for the market participants e.g. BRPs, REs and DSOs. According to what services the SP provides to the market participant, the SP performs the corresponding tasks towards ISR and the imbalance settlement system. The organisation with the responsibility to operate the NBS settlement. ISR is responsible for settlement of the difference between the contracted quantities and the realised quantities of energy products for the Balance Responsible Parties in a Market Balance Area. A Transmission System Operator has the responsibility for both the security of supply and the high-voltage grid. In this document TSO refers to following Nordic TSOs: Statnett, Fingrid, and Svenska Kraftnät. Nordic Balance Settlement Handbook for market participants

5 Table of Contents Foreword 1 Terminology 2 Table of Contents 4 1. Introduction 1 2. Nordic Balance Settlement Model 8 3. Settlement Structure Management Settlement Data Metering and Reporting Imbalance Settlement Invoicing Communication Collateral Management Market Behaviour Reporting Appendices 60 Nordic Balance Settlement Handbook for market participants

6 Detailed contents of the chapters Chapter Contents Basic information about Nordic Balance Settlement project 1. Introduction 2. Nordic Balance Settlement Model 3. Settlement structure management 4. Settlement data metering and reporting Purpose of the handbook Essential changes compared to national models Information sources to national regulations Introduction of the balance settlement organization High level description of the model and functions Roles and responsibilities of each market participant Contents of the agreements between ISR and market participants Description of the settlement structure Responsibilities and time schedules for reporting settlement structure information Examples of the settlement structure changes Metering of settlement data Responsibilities and schedules for reporting settlement data Instructions how reporting for production and consumption is done, including calculation examples for profiling Principles of imbalance settlement 5. Imbalance settlement Calculation of production and consumption imbalance Example of imbalance calculation National reconciliation procedures Invoicing process and invoicing of imbalances and reserves 6. Invoicing Calculation of imbalance price components Fee structures Invoicing procedure and schedule Consideration of taxes 7. Communication 8. Collateral management 9. Market behavior reporting Applied data communication standard Services provided by ISR; information service and online service Reports provided by ISR Collateral management model Calculation of collateral demands Monitoring of market behavior including published reports Key performance indicators Sanctions and controls from bad market behavior Instructions for becoming a new BRP 10. Appendices Handling of balance errors after gate closure National changes compared to NBS model Change log Nordic Balance Settlement Handbook for market participants

7 1. Introduction This chapter provides the basic information about the Nordic imbalance settlement model including its benefits and scope as well as the main changes needed when harmonising the settlement procedures in the Nordic countries. Additionally, the purpose and contents of the Nordic Balance Settlement (NBS) Handbook along with information sources for national regulations are presented. There must always be a balance between supply and consumption of electricity. To achieve this, the TSOs use balancing power procured in the balancing power market. Imbalances arise from uncertainties in plans and failures in generation, consumption and grid. Imbalance settlement is therefore a necessary function in a commercial based electricity market. Historically, Fingrid, Svenska Kraftnät and Statnett each have been operating their own imbalance settlement and have been responsible for supervising the balance of the electricity systems in Finland, Sweden and Norway respectively. In 2010, Fingrid, Svenska Kraftnät and Statnett agreed to form a joint project with the objective to establish a harmonised imbalance settlement model for three of the Nordic countries; called Nordic Balance Settlement (NBS). The model provides harmonized operational preconditions for all Nordic balance responsible parties, regardless of the country or market balance area. Nordic level business processes for reporting, performing settlement, invoicing, collateral management and corrections are established. Consequently, similar rules and standards for information exchange are created. The harmonised solution will require changes in all the countries; however, the changes may differ between the countries. The most significant change will be the establishment of a new Imbalance Settlement Responsible (ISR) organisation which is owned by the three TSOs; Fingrid, Statnett and Svenska Kraftnät with equal share. The new common operational unit is responsible for performing imbalance settlement and invoicing BRPs for imbalances and balancing services. Each TSO is still responsible for national settlement according to national regulations and in verifying that the NBS model and ISR fulfils such regulations. In order to compile all the NBS information into one easily accessible source, this Nordic Balance Settlement Handbook has been created. It is the main source of information needed for each market participant to understand their role and responsibility in the settlement process. A market participant can have several roles in the NBS model (e.g. TSO can have roles as BRP, RE and DSO). One of the most important goals of the handbook is to provide the information in a structured and understandable way so that all market participants can adapt and prepare for the NBS model and eventually work equally in the electricity market in all Nordic countries. Inevitably, there will remain some national differences which may not be possible to harmonise in short term and therefore the national regulations are an important source of information, in addition to this handbook. This handbook also 1

8 includes references to information sources to national regulation. As the NBS project is on-going the handbook is considered a draft and its main objective is to give market participants, in different market roles, the possibility to prepare for the coming transformation in relation to NBS model. 1.1 Nordic Balance Settlement Project A common imbalance settlement solution is supported by the governments and regulators in the Nordic countries. Harmonising the imbalance settlement in Finland, Norway and Sweden is regarded as an important step towards a fully functional common end user market. In order to set up this Nordic Balance Settlement model, the NBS project has been initiated. Imbalance settlement is a natural monopoly and a necessary function in a commercial based electricity market. Traditionally Fingrid, Statnett and Svenska Kraftnät have had the role as Imbalance Settlement Responsible as well as System Operator in Finland, Norway and Sweden respectively. This has led to situation where only few retailers operate in more than one country. Due to differences in the national end user markets, a retailer had to have parallel supply functions in all countries it operates through most of the value chain. Imbalance settlement acts as a significant part of the retailer s value chain, and different national rules and routines in this area have created barriers for entry to market. Common imbalance settlement is therefore a prerequisite for a common end user market. Objectives of the NBS model are presented in Table 1 below. Objectives of the Nordic Balance Settlement model Imbalance settlement between different Market Balancing Areas with as similar principles as possible through one Imbalance Settlement Responsible. Design and provide similar operational preconditions for balance responsible parties regardless of Market Balance Area. Harmonise common rules and standards for information exchange. Contribute to the implementation of a common Nordic retailer market. Be a forerunner in imbalance settlement issues on the European level. Table 1. Objectives of the Nordic Imbalance Settlement model Background Regulators in Finland, Norway and Sweden have decided to support the implementation of NBS and started the processes for the needed regulatory changes in the respective countries. The first NBS design report was published in There has been a close communication with the reference group of stakeholders, both industry and regulators, to discuss the development plans of the NBS model. Stakeholders have provided their industry opinions on prevailing issues to help the NBS project group to find the best solution for issues in question. 2

9 As the NBS project work is currently on-going the first version of the handbook is preliminary and it is obvious that there will be changes, additions and more details in the model before the go live of the settlement model Scope The main function encompassed by the NBS model is the common imbalance settlement. The model is based on the present harmonised model with two balances; production and consumption. Imbalance power for production and consumption is calculated and settled separately. The Imbalance Settlement Responsible (ISR) performs the imbalance settlement and manages invoicing as well as collaterals towards the Balance Responsible Parties (BRP) on behalf of the Transmission System Operator (TSO) in each country. All matters directly related to system operations, for example procurement of balancing services, are outside the scope of NBS model. The NBS model will take all necessary volumes into account when calculating the imbalance and furthermore, ISR is responsible for invoicing of the balancing services as a part of the imbalance settlement. In parallel with establishing a common Nordic imbalance settlement several other harmonisation processes have been initiated by NordREG. The long term aim is to create a common Nordic end user market for electricity in the Nordic region. A harmonised imbalance settlement acts as one part of this Nordic harmonisation. This handbook describes the imbalance settlement and does not give answers to all harmonisation necessary to establish a common end user market in the Nordic region. The reconciliation settlement will not be harmonized on Nordic Level at this stage and current national procedures will apply Benefits The model includes several benefits for the electricity market. The Nordic Balance Settlement is the platform for a common balance settlement in Finland, Norway and Sweden. This means that a Balance Responsible Party (BRP) always has a single interface (the imbalance settlement responsible unit) and one set of rules when settling its imbalances in the Nordic electricity market. The main reason for establishing a common imbalance settlement solution is the creation of a competitive end user market. Lack of end-user competition in the Nordic electricity market gives a loss for the society. Increased competition and reduced margins for the electricity providers will give a socioeconomic efficiency gain. Competition through a common Nordic retail market is considered to be essential in order to ensure high quality services at the lowest price, to stimulate innovation and maximise social welfare in the Nordic region. In general, the NBS model will lower the threshold of being a BRP because the model gives one common access to all countries. In addition, the operational procedures of a BRP are simplified. This makes it easier for a retailer to enter the market and also reduces costs as more BRPs are competing and the price for handling an RE s balance could therefore be lower. Besides, an RE can more easily choose to act as a BRP rather than RE. 3

10 In the NBS model, meter data quality will improve as the Distribution System Operators must notify and be responsible for data errors after the imbalance settlement period is closed. Improved data quality will not only improve the quality of the imbalance settlement but also the settlement and invoicing of end customer as both BRPs and REs get access to the same meter data. A larger market with a common rule set will make it more attractive to invest in innovation. BRPs and REs will face a larger potential for innovative solutions, especially for the core IT systems and new payment and credit management solutions. This will also make the vendor market more attractive as the offers from the various service providers will cover a larger market. A common Nordic approach to imbalance settlement procedures will have more influence on the EU development than if there were several different Nordic solutions. NBS will, in the long run, lower the operational costs of imbalance settlement because one organisation with one common IT solution will be more efficient than several separate ones. NBS will also make the related costs more transparent as these will be separated from cost elements at each respective TSO. Such transparency is a condition for operational cost efficiency. 4

11 1.2 Essential Changes in the Balance Settlement NBS model encompasses several changes for the imbalance settlement. Required changes differ by country due to current solutions and processes. A harmonised model will, in overall, require changes in all countries and all levels of the market. Major changes are described in this sub-chapter and more specific changes by country are described later in the chapters. The starting point for NBS model is the common principles agreed in 2009, consisting of two balances with national imbalance power pricing, cost structures, payment components and gate closure times for reporting settlement data. The common Nordic electricity retail market aims to have a common Nordic balance with common imbalance settlement and reporting, single balance agreement and unified gate closure times, though some national differences may apply. The main changes are illustrated in Figure 1 below. Figure 1. The most essential changes in the settlement model. National changes caused by the NBS model have been collected into a table in Appendix Regulation Common rules in the electricity law and secondary legislations in the Nordic countries provide additional information and set requirements for the market participants. This chapter includes the information sources to national legislation and regulations per each respective country Finland In Finland following laws and secondary regulations guide the electricity market: Electricity market act (EMA) (588/2013) (Finnish version) Decrees of the Finnish government and decrees of the ministry of the employment and the economy: o The Finnish Government decree of electricity deliveries settlement and measurement (dated ) 5

12 o The Ministry of the Employment and the Economy decree of the information exchange concerning electricity deliveries settlement (809/2008) ka%5d=809%2f Norway In Norway following laws and secondary regulations guide the electricity market: Primary act: LOV nr 50: Lov om produksjon, omforming, overføring, omsetning, fordeling og bruk av energi m.m. (energiloven) - The Energy Act html Secondary Legislation: FOR nr 301: Forskrift om måling, avregning og samordnet opptreden ved kraftomsetning og fakturering av nettjenester - MAF Sweden In Sweden following laws and secondary regulations guide the electricity market: Energy market act: SFS 1997:857 Ellag Lagar/Lagar/Svenskforfattningssamling/Ellag _sfs / National Energy Authority's regulations and general guidelines on measurement, calculation and reporting of electricity: STEMFS 2007:5 Mätningsföreskrift a%20f%c3%b6reskrifter/statens_energimyndighets_foreskrifter_och_allmanna_rad_om_matning _berakning_och_rapportering_av_overford_el_stemfs_2007_5.pdf Power regulation: SFS 1999:716 Mätnings förordning The Nordic Imbalance Settlement Responsible esett A new operational company, esett, has been established in Finland. The company is owned by Fingrid, Svenska Kraftnät and Statnett. The company will act and operate in the role of Nordic Imbalance Settlement Responsible. It must be noted, that the national regulations stipulate that each national Transmission System Operator (TSO) is still ultimately responsible for balancing operations. The company will operate in English but manages customer services by serving all three countries with their local languages. The company s relations to other market participants are illustrated in Figure 2. 6

13 Figure 2. Relations between esett and the market participants ISR Operations ISR has many operational tasks. Daily processes include collection and verification of data, controlling master data and making collected data available for market participants, conduct preliminary balance settlement, follow up reported data and do final imbalance settlement. Weekly duties for ISR are invoicing of the imbalance settlement, invoicing of other fees on behalf of TSOs, controlling collaterals and followup of BRPs in relation to risk and collaterals, and cash management. On a monthly basis ISR will monitor, publish and follow-up Key Performance Indicator (KPIs) of the imbalance settlement process. Some of the KPIs are also monitored daily or on a weekly basis. ISR does market monitoring, customer support and reporting, and publishing of settlement results (including incoming data) continuously. nbs@fingrid.fi Operating hours: 9:00 16:00 (CET) Most of the ISR operations are done in the ISR s imbalance settlement solution which consists of an imbalance settlement system to be used by ISR personnel and an Online Service and Information Service to be used by external stakeholders. These tools are described in chapter 7. 7

14 2. Nordic Balance Settlement Model This chapter presents the Nordic Balance Settlement model and its functions in more detail. The roles and responsibilities for the different market participants are described as well as the concept of balance responsibility and legal agreements related to it. The Nordic Balance Settlement model is based on the present harmonised model with separate balances for production and consumption which are calculated and settled separately. At the core of the NBS model is the common operational Imbalance Settlement Responsible unit (esett) which is responsible for settlement of imbalances. The ISR performs services on behalf of the three TSOs. The balance agreement is a legal contract between the balance responsible party and the ISR including liabilities, collateral requirements and procedures for exclusion and legal items such as place of court. The main stakeholders in the NBS model are the Retailers (RE), the Balance Responsible Parties (BRP), the Distribution System Operators (DSO), the Transmission System Operators (TSO), Nord Pool Spot (NPS) and the Imbalance Settlement Responsible (ISR). The role of these stakeholders is presented in the Terminology table in the beginning of this Handbook. The different procedures and operations of the Nordic Balance Settlement model are divided into five core functions: settlement structure management, metering and reporting data, settlement, invoicing and reporting. In addition the NBS model includes own functions for collateral management and market behaviour monitoring. 2.1 NBS Model The main objective of the NBS model is to perform imbalance settlement on Nordic level. The model is based on two balances; production balance and consumption balance. Both are calculated and settled separately. The NBS model ensures a transparent and common imbalance settlement and equal treatment of market participants. The model provides identical and necessary procedures for imbalance settlement in all countries participating in NBS: Settlement structure defines how the information about the imbalance settlement structure and hierarchy (relations) is collected and managed, e.g. information about a new Metering Grid Area (MGA) or the contact information of a market participant. Metering and reporting data handles the imbalance settlement data reception, validation, storing and reporting. 8

15 Settlement handles the production and consumption imbalance settlement calculations, quality assurance and publishing of results. Invoicing function handles the ISR s invoicing of market participants, based on realised imbalances. Reporting includes the creation, distribution and publishing of various reports and files provided by the ISR (esett). Reporting is also done through the online service and information service that is provided to market participants. Collateral management includes control of the BRPs collateral demands, as defined and calculated by ISR, as well as follow-up of the placed collateral deposits in comparison to demands. Market behaviour monitoring is based on the analysis of the BRPs' imbalances. These are analysed by calculating a set of KPIs, which show the BRPs market performance (e.g. quality of reported data, reporting frequency, relative imbalances, absolute imbalances and imbalance costs per unit). The quality of DSOs reporting will also be monitored. All functions in the settlement model are described in Figure 3 below. Figure 3. The NBS model functions. 9

16 2.2 Roles and Responsibilities The main stakeholders (i.e. market participants) in the Nordic Balance Settlement model along with related roles and responsibilities are presented below Imbalance Settlement Responsible (ISR) ISR is responsible for settlement of imbalances: Perform the imbalance settlement and invoice/credit the Balance Responsible Parties for the balancing power. Set the collateral levels so that they cover the imbalance settlement risk exposure. Collect and monitor the BRP s collaterals and take necessary actions to adjust collaterals when needed. Collect fees from BRPs to cover: o o The operational costs of ISR The reserve costs and related operational costs for the TSO. Monitor imbalances and assess whether they are in accordance with published guidelines and regulations. Publish a set of KPIs to provide statistics on reporting and settlement. Operate and provide an imbalance settlement system that the market participants can use to access and report settlement data. Report imbalance settlement data including statistics, KPIs and other market information Transmission System Operator (TSO) TSOs have the responsibility to supervise the balance of the electricity system and take actions to rebalance the system. In the NBS model a TSO has the same responsibilities as a BRP and in addition the following: Balance the production/import with the consumption/export during the delivery hour to meet the overall demand of frequency at 50 Hz. Calculate regulation power prices per hour and determine imbalance prices. Submit necessary information per BRP to the ISR for the imbalance settlement of the BRPs; e.g. production plan and activated regulation power during the operation hour. 10

17 Act as the financial counterpart towards the BRP for all reservations of reserves (ISR is the financial counterpart for the corresponding reserves related to the imbalance settlement Distribution System Operator (DSO) A DSO is a grid operator with the responsibility to connect producers and consumers to its grid. The DSOs have the responsibility to meter production, consumption and exchange with other grids in addition to report the metered data to the entitled parties. This includes also non-concessional grid operators. The DSO has several obligations in relation to imbalance settlement. DSO s responsibilities are the following: Register BRPs and REs metering points in the respective Metering Grid Areas Operate the metering system and submit metering data to the Retailers, Balance Responsible Parties and ISR. Calculate and report load profile shares (according to national guidelines). Calculate the final profiled consumption and the reconciled energy when all metering for a grid area is completed (according to national guidelines, see sub chapter 5.6. Reconciliation). Imbalance corrections after the balance settlement reporting is closed shall be settled between the DSO and RE. See appendix 2 for more details Balance Responsible Party (BRP) A BRP is a party having signed an agreement with the ISR. BRP s responsibilities are following: Have a balance agreement with the ISR and provide the required collaterals. Plan balanced schedules on an hourly basis. Submit production plans to the TSO which will forward them to the ISR. Submit bilateral trade information. Act as the financial counterpart for the settlement of imbalances, activated regulation power and reconciliation according to national guidelines Verify that all relevant data reported by the ISR, and notify deviations. Inform the imbalance settlement responsible of which REs that the BRP is responsible for Retailer (RE) An RE sells electricity to final consumers and balances the sales with purchases in bilateral and organised markets. The RE s responsibility regarding balance settlement is: 11

18 Have an agreement with a BRP Retailer can use one BRP for consumption and one BRP for production in the same MGA and use different BRPs in different MGAs, this division is highlighted in the following Figure 4 where Finland is used as an example. Figure 4. Model for Retailers using different BRPs per MGA Market Operator (Nord Pool Spot) The responsibilities for Nord Pool Spot, in its role as power exchange and in regard to imbalance settlement are following: Report trade data for Elspot- and Elbas trade per BRP/RE and Market Balance Area to ISR (and TSO if needed). Report cross border trade with other power exchanges (market coupling) to TSOs. Report to ISR into which MBA each MGA belongs to. 2.3 Balance Responsibility and Agreements The parties of the balance agreements will be the Imbalance Settlement Responsible and the BRP. Only one balance agreement is required per BRP, regardless of how many countries the BRP is active in. The scope of the balance agreement will be limited to issues regarding the settlement and invoicing of activated regulation power. As before, a BRP shall have an agreement with the TSO if the BRP is providing reserves in the ancillary service markets. 12

19 2.3.1 Agreement between ISR and BRP Only a company that has a valid agreement with the ISR may act as a BRP. This agreement regulates the relations between the parties. The purpose of the balance agreement is to assure financial liability for and planning of imbalances between the generation and consumption of power. The purpose of the balance agreement is to assure financial liability for and planning of imbalances between the generation and consumption of power: Liability of the ISR Collateral requirement Procedures when contract is breached by the BRP Law and place of court Etc. (will be finalised later) Detailed agreement will be published later 13

20 3. Settlement Structure Management Chapter three presents the settlement structure and hierarchy management in the Nordic Balance Settlement model. It describes the reporting responsibilities and the rules and guidelines for reporting changes in the structural information as well as reporting schedules and methods. The settlement structure is one of the key elements in the NBS model. Each market participant is responsible for informing and updating structural information. Structural information is information about market participants and their relations to each other (e.g. the relationship between a BRP and an RE) and to the market entities and market entity connections (e.g. the relationship between a BRP and a MGA). Every party in the market has to register for acceptance to operate in the market. The parties themselves are responsible for registering and keeping their information up to date. Distribution System Operators will be responsible for updating the structure of the Metering Grid Area they are accountable for (e.g. MGA exchange per MGA per adjacent MGA) and Balance Responsible Parties and Retailers will control their own information (e.g. which RE in the different MGA they are responsible for). The market participants shall send the information of changes in the settlement structure to the ISR either electronically in a market message or by entering the changes via the NBS Online Service. Market message for settlement structure shall be defined later. In exceptional situations, the changes can also be reported by or phone. When the changes are entered into the imbalance settlement system of the ISR, the changes are validated and approved. Once the changes are approved they will be used in the balance settlement. The structure information is published on the NBS Online Service where market participants can view the up to date settlement structure information. The viewing of the settlement structure is restricted with access rights in accordance with legislation. 3.1 Settlement Structure Up-to-date structural information is essential to manage the reporting and other imbalance settlement functions. Settlement structure contains the information related to different market participants: TSOs, DSOs, BRPs and Res, and information on the relationship between the market participants. Information regarding who the BRP is for an RE in all MGAs, and during which period of time, is essential to enable correct reporting of data to ISR. One common structure information overview for the market is therefore developed and maintained in the ISR s imbalance settlement system. 14

21 Every entity of structural information has a validity period, defining the period of time during which the entity is considered active. Detailed information on how the structural information will be managed will be added later. 3.2 Market Entity Connections A large amount of settlement information is exchanged between market participants within the Nordic imbalance settlement. The information is organised into so called Market Entity Connections (MEC). The MECs are very central in the balance settlement structure. Market Entity Connections (MECs) are different kinds of connections either between different market participants (e.g. bilateral trades between parties) or between market participants and market entities (e.g. market participant s metered consumption in MGA or market participant s production per Production Unit). The Market Entity Connection s time series data is the core of the balance settlement. Table 2 explains the MECs utilized in the NBS model. Market Entity Connections Name Abbrevation Description Market Balance Area Metering Grid Area MBA MGA Market Balance Area means an area that provides (exchange) schedules that represent a basis for monitoring of imbalances. It is always the same Elspot price within a MBA. A Metering Grid Area is a physical area where consumption, production and exchange can be metered. It is delimited by the placement of meters for period measurement for input to, and withdrawal from the area. It can be used to establish the sum of consumption and production with no period measurement and network losses. MGAs are decided on national level. Production Unit PU Generator or a set of generators within same power plant. Regulation Object Preliminary Profiled consumption Metered Consumption RO PPC N/A A Regulation Object (RO) is a set of one or more generators and stations within a MBA decided by the respective Transmission System Operator (TSO) and the BRP. One RO can only include production of a certain technology (wind, hydro, nuclear, etc.). There can only be one BRP per RO. Estimate of profiled consumption per RE on hourly basis used in imbalance settlement. Estimated as the RERE share of load profile. Metered consumption per MGA per RE on hourly basis used in imbalance settlement. Metered Production N/A Metered production per PU on hourly basis used in imbalance settlement. MGA Exchanges Elspot Trades Elbas Trades N/A N/A N/A The exchange of energy sum that occurs between Metering Grid Areas adjacent to each other. Measured in the border points and reported hourly. Day-Ahead-based market. The Nordic auction-based market for transactions in physical power for each hour during the subsequent 24-hour trading period. Intraday market. The continuous hourly market for transactions in physical power for the present 24-hour period, until one hour before delivery. Trading for the 15

22 following 24-hour period cannot start until after the Elspot trading has concluded. Elspot Flows N/A Planned flow between the MBAs resulting from the day ahead Elspot price calculation (see Elspot Trades). Elbas Flows N/A The net planned flow between MBAs in the Elbas market (see Elbas trades). Bilateral Trade N/A An electricity trade that has been agreed upon between two market participants on hourly basis. Production Plans N/A BRPs reported plans for production, on RO basis. Imbalance adjustment up N/A Imbalance Adjustment means the correction applied to the Position of a Balancing Service Provider or a Balance Responsible Party by Transmission System Operator for the calculation of the Imbalance Volume. Imbalance adjustment down N/A Imbalance Adjustment means the correction applied to the Position of a Balancing Service Provider or a Balance Responsible Party by Transmission System Operator for the calculation of the Imbalance Volume. MGA Imbalance Supportive Power Sold N/A N/A Sum of reported input to, and withdrawals (including network losses) from one MGA. The sum is zero when reporting is correct. Supportive power is power that adjacent TSOs can exchange reciprocally as an element of the regulation of balance in the respective subsystems. Exchanges are made specifying the power, price, link and time to the exact minute of the start and finish of the exchange. Supportive power is settled as the hourly average value. Table 2. Market Entity Connections. 3.3 Settlement Structure Management Function The Settlement Structure Management function handles the collection and management of the imbalance settlement structure information. The balance settlement structure is formed as part of this function. In short, the activities are the following: the ISR receives a message from one of the market participants containing balance settlement structure information that should be added, updated, or closed in the imbalance settlement system. The message is either sent directly electronically from the participants system to the system or entered via the NBS Online Service (described more detailed in chapter 7), or in abnormal situations by or phone to ISR personnel. The new or changed structure information is validated by the ISR s imbalance settlement system or ISR employee where needed. When the settlement structure has been updated, ISR publishes the settlement structure to market participants in the Online Service and the Information Service. 16

23 3.4 Reporting Responsibilities and Schedules Every participant in the electricity wholesale market will have to apply for acceptance into the settlement structure from the ISR. The parties themselves are responsible for registering and verifying that their information is up-to-date. Responsibilities regarding the settlement structure information management are explained in the following sub-chapters ISR ISR hosts the common settlement structure information. The related responsibilities are the following: Setting BRPs as active when the balance agreement is set into force. o This includes all prerequisites for a valid balance agreement as e.g. complying with the collateral requirements. Setting BRPs as inactive when the balance agreement has been terminated. Setting DSOs as active when they fulfill all requirements as DSO. Setting DSOs as inactive when DSOs activity has ended. o The DSO has for example been merged with another DSO. Setting REs as active when they fulfill the requirements set upon them by the regulators. o o Since an RE may have a different BRP in every MGA it's most efficient that ISR perform this control instead of many DSOs or BRPs controlling the same RE. An active retailer will be able to handle consumption, trade and production. Setting REs as inactive when their activity has ended. Manage MECs for MGA imbalance. Manage MECs for MGA exchange trade RE RE is responsible for reporting the following structure information to ISR: Registering company as an RE. Retailer initiates the switch of supplier process. This process can only be initiated when the RE has a valid BRP in the MGA where the delivery will take place. Update own contact information. 17

24 3.4.3 BRP BRPs are responsible to report their bilateral trades and connections between production units and Regulation objects. BRP is responsible of reporting following structure information to ISR: Registering company as a BRP. Registering for which REs they take on the responsibility for production imbalance, and in which MGAs. It is the new BRP that is responsible for applying the correct structure. Registering for which REs they take on the responsibility for consumption/trade imbalance, and in which MGAs. It is the new BRP that is responsible for applying the correct structure. Manage MECs for bilateral trade for REs that they are responsible for. The BRP representing the seller and the BRP representing the buyer must both register the bilateral trade. Assigning production units (PU) to correct regulation object (RO). Update own contact information DSO DSOs have the main responsibility in maintaining the correct and up-to-date settlement structure. DSO is responsible for reporting the following structure information to ISR: Registering company as a DSO. Manage MECs for consumption. Manage MECs for production. Manage MECs for MGA exchange. Both DSOs must register the MEC. The DSO must for every MGA select one RE that handles the DSOs losses, end-users without supplier, MGA-imbalance and MGA-exchange trade. Update own contact information NPS NPS is required to register as a BRP in the settlement structure. In addition NPS is responsible of reporting occurred Elspot and Elbas trades. NPS is responsible of reporting following structure information to ISR: Registering company as a BRP. 18

25 Manage MECs for Elspot. Manage MECs for Elbas. Relationship between MBAs and MGAs. Update own contact information. Informing ISR if any market participant is misusing the market or is behaving abnormally TSO TSOs have, in addition to below mentioned responsibilities, the similar responsibilities as BRPs (if applicable): Determine the Metering Grid Areas (MGAs). Determine which MGAs make up each Market Balance Area (MBA). The TSO must for its MGAs select an RE that handles the TSOs losses, end-users without supplier, MGA-imbalance and MGA-exchange trade. The TSO may register as an RE itself. Manage MECs for imbalance adjustment. Manage MECs for production plans Reporting Schedule Different settlement structure information needs to be reported according to different schedules and different parties are responsible for updating the structure information. The gate closure times (presented in Table 3 below) are administered and defined by the ISR. Gate closure times are not final and therefore shown with blue background. Structure information Gate closure times for updating structure information Prerequisites/remarks Responsible party Gate closure time Consumption metering points RE must be valid RE must have agreement with BRP DSO Three days before the day of operations 19

26 Production metering points Must be aligned with the change in RO DSO New BRP Old BRP Three days before the day of operations TSO Exchange metering points May require changes in the MGA structure itself DSO (Finland) TSO (Norway, Sweden) Three days before the day of operations MGA structure Structure consists consumption, production and exchange metering points DSO Three days before the delivery day Bilateral trade structure Must be in place to enable reporting from the BRPs Before the day of operation Regulation objects TSO to decide Notify ISR TSO 3 days before the day of operation RE -> BRP structure Must be known which BRP will be responsible for consumption and production in every MGA, where RE will have activity BRP (The RE s new BRP) 14 days before the day of operation MECs cannot be created in MGAs where the RE is without valid BRP. MGA -> MBA structure Up to TSO to decide TSO 14 days before the changes are set active Validity of market participants Will be set valid after all documents have been received by ISR ISR No later than 14 days after documents have been received Table 3. Gate closure times for reporting structure information. 20

27 4. Settlement Data Metering and Reporting Chapter four presents the settlement data metering and reporting activities. It contains information about the reporting responsibilities and time schedules for each of the market entities. Moreover, management of bilateral trade corrections and metering grid area exchange corrections are described. The metered data shall be reported to the Imbalance Settlement Responsible (ISR) by the DSOs. The metered data is reported either via market messages or via the NBS Online Service. The reported data is further aggregated by ISR in order to establish the consumption and production imbalances. All metered data is organized per Metering Grid Area (MGA). One MGA can only be situated in one market balance area (MBA). Aggregated meter data should be aggregated per MGA on BRP level or/and Retailer level. The gate closure times for reporting data and the related reporting requirements are defined in the NBS model. Gate closure times differ depending on what data that is reported. The BRPs are responsible for reporting bilateral trade to ISR. They shall report production plans and bids for up and down regulation to the TSOs. They are also obliged to keep their production plans updated, i.e. report updated values. Nord Pool Spot (NPS) reports Elspot and Elbas trade results to the TSO and ISR. Metered data for production per PU and aggregated metered consumption data per RE and MGA are reported after the delivery to ISR. ISR performs validations on the received metered data and publishes the data in the NBS Online Service. The settlement calculations and the weekly invoicing are then performed as automated processes in the imbalance settlement system. TSOs check the consistency of the data reported by BRPs and report all activated regulation power between BRP(s) and TSO(s). TSOs also report binding production plans to ISR. The verification of the bilateral trades and MGA exchanges is performed by verifying that values reported by the two counterparts are equal. If the values do not match, they will be changed according to predefined correction rules and a notification will be sent to both counterparts. In the NBS model the hourly data is collected weekly and within the stipulated 13 days, this data should be used in the balance settlement. However, if the hourly data is collected less frequently than weekly this part of the consumption will be included in the load profile. This rule is applicable for all consumption without respect to level of yearly consumption or the size of the main fuse. Production used only in exceptional situations can be handled in the consumption balance, this is clarified in chapter

28 4.1 Validation of Reported Data The data is either sent electronically from the market participant s system directly to the imbalance settlement system of ISR or entered via the Online Service. In abnormal situations the data can be reported by or phone directly to ISR personnel. Before aggregation, the syntax and content of the incoming data is validated by the ISR s imbalance settlement system in order to ensure that the data can be used in the settlement calculations. The reporting parties are informed about the validation result (e.g. via acknowledgement messages). After the validation the data is stored in the ISR s imbalance settlement system and the imbalance settlement calculations are performed. Both the data sent by market participants and the final calculated settlement data is published on the Online Service, so that it can be verified and so that possible errors can be reported to the ISR. In addition, the market participants are given the possibility to utilise the Information Service, which provides the market participants such settlement data (time series data) that they are entitled to see. The Information Service (presented in chapter 7.2) is established as a machine-to-machine interface and made available to market participants authorised by ISR. Market participants themselves are responsible for the accuracy and quality of the reported data. ISR sends and publishes the data received from the parties and is not able to verify the correctness of the received data. 4.2 Reporting Responsibilities and Schedules for Reporting The basis for the reporting schedule is a 13 day period during which the settlement data must be reported to ISR. The ISR conducts preliminary balance settlement based on the reported data every day starting from the second day after the deliver until 13 days afterwards. The final settlement report can be done at the latest 13 days after delivery. During the next working day after the final reporting day, ISR publishes the final result of the imbalance settlement. The data reporting period has been defined in number of days in order to harmonize the delivery schedule within the NBS countries. An illustrative picture of the settlement data reporting schedule for one delivery day in September is presented in Figure 5. In the picture, metered data for Sunday in week 1 should be updated at the latest 13 days after delivery day, i.e. on Saturday week 3 in the illustration below. On Saturday all metered data for the whole week 1 is considered to be final and the final settlement is performed. Invoicing of week 1 is done on the first working day after the final reporting day (see more information about the invoicing in chapter 6). 22

Nordic Imbalance Settlement Handbook. Instructions and Rules for Market Participants 12.12.2014

Nordic Imbalance Settlement Handbook. Instructions and Rules for Market Participants 12.12.2014 Nordic Imbalance Settlement Handbook Instructions and Rules for Market Participants Business process: Nordic Imbalance Settlement Version: 2.0 Status: For implementation Date: December 12st, 2014 2 Foreword

More information

Nordic Imbalance Settlement Handbook

Nordic Imbalance Settlement Handbook Nordic Imbalance Settlement Handbook Instructions and Rules for Market Participants Business process: Nordic Imbalance Settlement Version: 2.01 Status: For implementation Date: April 24th 2015 2 Foreword

More information

Nordic Imbalance Settlement Model

Nordic Imbalance Settlement Model Nordic Imbalance Settlement Model Contents Executive Summary Nordic Imbalance Settlement Model Settlement Structure Management Metering Settlement Data Reporting Imbalance Settlement Invoicing Communication

More information

Nordic Balance Settlement (NBS)

Nordic Balance Settlement (NBS) Nordic Balance Settlement (NBS) Common Balance & Reconciliation Settlement Design December 22 nd, 2011 Content Terminology...4 Executive Summary...6 1 Introduction... 8 1.1 Scope of the Nordic Balance

More information

Invitation for participating in consultation for a joint Nordic Balance Settlement

Invitation for participating in consultation for a joint Nordic Balance Settlement CONSULTATION NBS DESIGN REPORT 1 (2) Date 2011-01-26 Invitation for participating in consultation for a joint Nordic Balance Settlement The Nordic TSOs hereby invite your organisation to a consultation

More information

NordREG Common Nordic end-user market

NordREG Common Nordic end-user market NordREG Common Task Force Balance Settlement Outline for a common Nordic Balance Settlement (NBS) Consultation Paper May 17 th, 2010 Content 1 Introduction... 3 2 Main requirements for a Nordic Balance

More information

The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market

The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market 1 The market When the electricity market is liberalized, electricity becomes a commodity like, for instance, grain

More information

Common Balance & Reconciliation Settlement. Report

Common Balance & Reconciliation Settlement. Report I Common Balance & Reconciliation Settlement Report December 18 th, 2009 Content O Executive Summary... 3 1 Terminology... 7 2 Background... 10 2.1 Ambition for COBS... 10 2.2 Benefits for the Norwegian

More information

Suggested agreement structure for imbalance settlement agreement. Minnakaisa Ahonen

Suggested agreement structure for imbalance settlement agreement. Minnakaisa Ahonen Suggested agreement structure for imbalance settlement agreement Minnakaisa Ahonen esett TSO BRP agreements Participating as a balance responsible party in the electricity markets that are settled by esett

More information

[BRP] Imbalance Settlement Agreement Main Agreement [29.5.2015]

[BRP] Imbalance Settlement Agreement Main Agreement [29.5.2015] [BRP] Imbalance Settlement Agreement Main Agreement [29.5.2015] 2 Table of contents 1 Parties 3 2 Definitions 3 3 Contract Documents 5 4 Background and purpose 5 5 BRP's Rights and Obligations 6 6 esett's

More information

The Liberalized Electricity Market

The Liberalized Electricity Market 1. The market When the electricity market is liberalized, electricity becomes a commodity like, for instance, grain or oil. At the outset, there is as in all other markets a wholesale market and a retail

More information

FI/RU electricity exchange area setup

FI/RU electricity exchange area setup FI/RU electricity exchange area setup Daily routines at Nord Pool Spot Time (CET) Action 9:30 Transmission capacities published on NPS web Daily at 9:30 CET the relevant TSOs submit the available transmission

More information

DEVELOPMENT OF A COMMON NORDIC BALANCE SETTLEMENT

DEVELOPMENT OF A COMMON NORDIC BALANCE SETTLEMENT DEVELOPMENT OF A COMMON NORDIC BALANCE SETTLEMENT Report 3/2006 DEVELOPMENT OF A COMMON NORDIC BALANCE SETTLEMENT Nordic Energy Regulators - NordREG 2006 Report 3/2006 NordREG c/o Energimarknadsinspektionen

More information

Harmonised Model for Supplier Switching. Report 4/2013

Harmonised Model for Supplier Switching. Report 4/2013 Harmonised Model for Supplier Switching Report 4/2013 1 Harmonised Model for Supplier switching Report 4/2013 NordREG c/o Norwegian Water Resources and Energy Directorate Middelthunsgate 29, 0301 Oslo,

More information

Nordic Balance Settlement. Reference Group Meeting November 6 th -7 th, 2012 Hilton Hotel (Helsinki Airport)

Nordic Balance Settlement. Reference Group Meeting November 6 th -7 th, 2012 Hilton Hotel (Helsinki Airport) Nordic Balance Settlement Reference Group Meeting November 6 th -7 th, 2012 Hilton Hotel (Helsinki Airport) Agenda Nov. 6 th, 2012 November 6 th Time What Com. 12:00 13:00 Lunch at Hilton Hotel 13:00 13:20

More information

Imbalance Settlement Agreement Appendix 2. Collaterals [29.5.2015]

Imbalance Settlement Agreement Appendix 2. Collaterals [29.5.2015] Imbalance Settlement Agreement Appendix 2 Collaterals [29.5.2015] 2 Table of contents 1 Provision of collateral 3 2 Use of collateral 3 3 Calculation of collateral requirement 4 4 Communicating and responding

More information

Payment requirements with combined billing

Payment requirements with combined billing Payment requirements with combined billing FINAL REPORT 30.4.2013 Marika Bröckl, Laura Hakala, Erkka Ryynänen, Iivo Vehviläinen Gaia Consulting Oy Index Executive Summary... 3 1 Introduction... 6 1.1 Background...

More information

National Report 2015 to the Agency for the Cooperation of Energy Regulators and to the European Commission

National Report 2015 to the Agency for the Cooperation of Energy Regulators and to the European Commission Ref: 1842/601/2015 10.7.2015 National Report 2015 to the Agency for the Cooperation of Energy Regulators and to the European Commission Finland National Report 2015 - Energy Authority, Finland 1 CONTENT

More information

TRADING APPENDIX 1. Trading Appendix 1. Definitions. Nord Pool Spot Market. Issued by Nord Pool Spot AS COPYRIGHT NORD POOL SPOT AS 1(11)

TRADING APPENDIX 1. Trading Appendix 1. Definitions. Nord Pool Spot Market. Issued by Nord Pool Spot AS COPYRIGHT NORD POOL SPOT AS 1(11) Trading Appendix 1 Definitions Nord Pool Spot Market Issued by Nord Pool Spot AS COPYRIGHT NORD POOL SPOT AS 1(11) Version 1 Effective from: NWE/PCR go-live 2014 DEFINITIONS This document sets out the

More information

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries TERMS OF ELECTRICITY SALES 2010 as recommended by Finnish Energy Industries Content: A. General, concluding an electricity sale contract, the prerequisites for electricity sales, commencement of electricity

More information

1 SERVICE DESCRIPTION

1 SERVICE DESCRIPTION 1 (5) 1 SERVICE DESCRIPTION According to the Electricity Market Act, Fingrid is tasked with developing the information exchange required for electricity trade and imbalance settlements. Fingrid's information

More information

National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission

National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission Ref: 1602/601/2014 10.7.2014 National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission Finland National Report 2014 - Energy Authority, Finland 1 CONTENT

More information

How To Create A Power Market In European Power Markets

How To Create A Power Market In European Power Markets THEMA Report 2011-15 ISBN no. 978-82-93150-07-7 Market design and the use of FTRs and CfDs A report prepared for Energy Norway September 2011 CONTENT 1 SUMMARY AND CONCLUSIONS...3 2 INTRODUCTION...4 3

More information

Rights and obligations of DSOs and suppliers in the customer interface

Rights and obligations of DSOs and suppliers in the customer interface Rights and obligations of DSOs and suppliers in the customer interface Report 4/2011 Rights and obligations of DSOs and suppliers in the customer interface Nordic Energy Regulators 2011 Report 4/2011

More information

Business Requirement Specification

Business Requirement Specification Nordic Ediel Group Business Requirement Specification for a Harmonised Nordic Retail Market Business processes, message format, content and interface Status: Final version, including comments after public

More information

THE STRUCTURE OF AN ELECTRICITY MARKET

THE STRUCTURE OF AN ELECTRICITY MARKET THE STRUCTURE OF AN ELECTRICITY MARKET Lectures 1-2 in EG2200 Power Generation Operation and Planning Mikael Amelin 1 COURSE OBJECTIVE To pass the course, the students should show that they are able to

More information

TRADING PLATFORM CLEARING AND SETTLEMENT MEMBERSHIP

TRADING PLATFORM CLEARING AND SETTLEMENT MEMBERSHIP TRADING PLATFORM CLEARING AND SETTLEMENT MEMBERSHIP TRADING PLATFORM Wilhelm Söderström, Nord Pool Spot Ante Mikulić, CROPEX European day ahead market A fair and transparent calculation of dayahead power

More information

DSM in competitive market. Seppo Kärkkäinen, VTT, Finland TAIEX Workshop on Demand Side Management in Energy Efficiency Ankara - 22-23/11/2007

DSM in competitive market. Seppo Kärkkäinen, VTT, Finland TAIEX Workshop on Demand Side Management in Energy Efficiency Ankara - 22-23/11/2007 DSM in competitive market Seppo Kärkkäinen, VTT, Finland TAIEX Workshop on Demand Side Management in Energy Efficiency Ankara - 22-23/11/2007 Definitions: DSM/DR/LM/ The term Demand Side Management, DSM,

More information

CONGESTION MANAGEMENT POLICY

CONGESTION MANAGEMENT POLICY 1 (8) CONGESTION MANAGEMENT POLICY Contents 1 General... 2 2 Principles of congestion management... 2 3 Congestion management in the Finnish transmission grid... 3 3.1 Normal situation... 3 3.2 Planned

More information

Product Specifications

Product Specifications Trading Appendix 3 Product Specifications Physical Markets Issued by Nord Pool Spot AS Effective from: 1 July 2014 1(5) PRODUCT SPECIFICATIONS - PHYSICAL MARKET 1 INTRODUCTION 1.1 General The following

More information

DSM experiences in Nordic countries

DSM experiences in Nordic countries DSM experiences in Nordic countries Seppo Kärkkäinen, VTT, Finland TAIEX Workshop on Demand Side Management in Energy Efficiency Ankara - 22-23/11/2007 Content Nordic Electricity market DSM/Demand Response

More information

ELECTRICITY MARKET ACT

ELECTRICITY MARKET ACT 1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is

More information

GLOSSARY. Issued by Nord Pool Spot

GLOSSARY. Issued by Nord Pool Spot GLOSSARY Issued by Nord Pool Spot Date: September 29, 2011 Glossary Nord Pool Spot Area Price Balancing market Bidding area Bilateral contract Block bid Whenever there are grid congestions, the Elspot

More information

Report on regulation and the electricity market

Report on regulation and the electricity market Report on regulation and the electricity market 2011 Norway Norwegian Water Resources and Energy Directorate (NVE) 31 st of July 2011 1 Table of contents 1 Foreword 3 2 Main developments in the electricity

More information

TABLE OF CONTENTS. Page

TABLE OF CONTENTS. Page 3 TABLE OF CONTENTS Page 1 INTRODUCTION...5 1.1 BACKGROUND AND SCOPE...5 1.2 EXCHANGE OF RESERVES BETWEEN SEPARATE SYNCHRONOUS SYSTEMS...6 2 DEFINITIONS...10 2.1 IMBALANCE...10 2.2 BALANCING CONTROL...11

More information

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Specific amendments to the Capacity Allocation and Congestion Management Network Code Annex: Specific amendments to the Capacity Allocation and Congestion Management Network Code I. Amendments with respect to entry into force and application The Network Code defines deadlines for several

More information

SWEDISH COMPETITION AUTHORITY. Deregulation of the Swedish Electricity Market

SWEDISH COMPETITION AUTHORITY. Deregulation of the Swedish Electricity Market SWEDISH COMPETITION AUTHORITY Deregulation of the Swedish Electricity Market Swedish Competition Authority November 1996 ISSN 1401-8438 Tryckgruppen AB, Stockholm 1996 Contents: 1 Rules for the Swedish

More information

NordREG s work towards a harmonised Nordic retail market - Roadmap update and national implementation monitoring

NordREG s work towards a harmonised Nordic retail market - Roadmap update and national implementation monitoring NordREG s work towards a harmonised Nordic retail market - Roadmap update and national implementation monitoring NordREG Report 5 2014 Published: 2014-09-08 1 NordREG s work towards a harmonised Nordic

More information

Feedback from Nordenergi on PCG target model and roadmap propositions

Feedback from Nordenergi on PCG target model and roadmap propositions Our ref. CHS PCG/ERGEG Regional Initiatives Group, pcg@ergeg.org ERI Northern region bld@ks.dk Copenhagen, 30 October 2009 Feedback from Nordenergi on PCG target model and roadmap propositions Dear Madam/Sir,

More information

The Norwegian-Swedish Electricity Certificate Market ANNUAL REPORT 2013

The Norwegian-Swedish Electricity Certificate Market ANNUAL REPORT 2013 The Norwegian-Swedish Electricity Certificate Market ANNUAL REPORT 2013 2 Contents Preface 3 The Nordic electricity market 5 Key figures for 2013 6 How the electricity certificate market works 7 Goal fulfilment

More information

Full opening of the Estonian electricity market

Full opening of the Estonian electricity market Full opening of the Estonian electricity market SEPTEMBER 2012 Contents Introduction...02 Transition to the open electricity market...02 Electricity bill...04 Electricity price factors...04 Estonia s power

More information

7: The electricity market

7: The electricity market 7: The electricity market 94 : Facts 2008 : Energy and Water Resources in Norway The power sector in Norway is regulated by the Energy Act. Market-based power trading is one of the principles incorporated

More information

Electricity Market Management: The Nordic and California Experiences

Electricity Market Management: The Nordic and California Experiences Electricity Market Management: The Nordic and California Experiences Thomas F. Rutherford Energy Economics and Policy Lecture 11 May 2011 This talk is based in part on material pepared by Einar Hope, Norwegian

More information

2014 National Report To the European Commission Denmark

2014 National Report To the European Commission Denmark 2014 National Report To the European Commission Denmark Table of contents 1 Foreword... 3 2 Main developments in the gas and electricity markets... 4 2.1 The electricity market... 4 2.1.1 Wholesale...

More information

Operational Security Network Code

Operational Security Network Code Amstelveenseweg 998 1081 JS Amsterdam Phone: + 31 20 520 7970 Fax: + 31 346 283 258 Email: secretariat@efet.org Website: www.efet.org Operational Security Network Code Public consultation 3 November 2012

More information

How To Enforce The Nordic Balance Settlement Agreement

How To Enforce The Nordic Balance Settlement Agreement Nordic Imbalance Settlement Agreement on Pledge and Right of Disposal of Cash Account between [name of Balance Responsible Party] and esett Oy and [name of Settlement Bank] based on agreement template

More information

CAPACITY MECHANISMS IN EU POWER MARKETS

CAPACITY MECHANISMS IN EU POWER MARKETS CAPACITY MECHANISMS IN EU POWER MARKETS Can we progress to bilateral energy options? Simon Bradbury Ultimately, European renewable targets mean that prices and dispatch patterns will be dictated by wind

More information

Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM-18-04 7 December 2010

Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM-18-04 7 December 2010 Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM-18-04 7 December 2010 European Regulators Group for Electricity and Gas Contact: Council of European Energy Regulators ASBL 28 rue

More information

Forward Risk-Hedging Products PC_2012_E_13

Forward Risk-Hedging Products PC_2012_E_13 Answer to public consultation Petteri Haveri 26.10.2012 1(5) Agency for the cooperation of energy regulators consultation2012r08@acer.europa.eu Forward Risk-Hedging Products PC_2012_E_13 The Finnish Energy

More information

Main variations of business models for Flexible Industrial Demand combined with Variable Renewable Energy

Main variations of business models for Flexible Industrial Demand combined with Variable Renewable Energy Innovative Business Models for Market Uptake of Renewable Electricity unlocking the potential for flexibility in the Industrial Electricity Use Main variations of business models for Flexible Industrial

More information

Nordic Market Report 2014 Development in the Nordic Electricity Market. Report 4/2014

Nordic Market Report 2014 Development in the Nordic Electricity Market. Report 4/2014 Nordic Market Report 2014 Development in the Nordic Electricity Market Report 4/2014 Preface The Nordic Market report describes on a yearly basis status and developments in the Nordic electricity market

More information

Balance Responsibility Agreement for electricity between the Svenska Kraftnät Public Utility ("Svenska Kraftnät") and. ("Balance Responsible Party

Balance Responsibility Agreement for electricity between the Svenska Kraftnät Public Utility (Svenska Kraftnät) and. (Balance Responsible Party AGREEMENT/1960 Balance Responsibility Agreement for electricity between the Svenska Kraftnät Public Utility ("Svenska Kraftnät") and. ("Balance Responsible Party /BRP") Corporate number... VAT Registration

More information

Financial Transmission Rights in the Nordic Electricity Market

Financial Transmission Rights in the Nordic Electricity Market Financial Transmission Rights in the Nordic Electricity Market 2 What is the purpose of issuing FTRs FTRs allow market parties to hedge the area price spread risk => This makes it potentially easier for

More information

Market Entrant Processes, Hurdles and Ideas for Change in the Nordic Energy Market - the View of the Market

Market Entrant Processes, Hurdles and Ideas for Change in the Nordic Energy Market - the View of the Market A report commissioned by Nordic Energy Regulators (NordREG) Market Entrant Processes, Hurdles and Ideas for Change in the Nordic Energy Market - the View of the Market Writer: Dr Philip Lewis VaasaETT

More information

Table of contents 1 Foreword... 1 2 Main developments in the gas and electricity markets... 2 3 The electricity market... 3 4 The gas market...

Table of contents 1 Foreword... 1 2 Main developments in the gas and electricity markets... 2 3 The electricity market... 3 4 The gas market... Table of contents 1 Foreword... 1 2 Main developments in the gas and electricity markets... 2 3 The electricity market... 3 3.1 Network regulation... 3 3.1.1 Unbundling... 3 3.1.2 Technical functioning...

More information

and A Regional Reference Model for the Change-of-Supplier Process

and A Regional Reference Model for the Change-of-Supplier Process and A Regional Reference Model for the Change-of-Supplier Process Version/release: Final 1.0 (EURELECTRIC) Date: May 20 th, 2008 C O N T E N T 1 INTRODUCTION... 3 1.1 ABOUT THIS DOCUMENT... 3 1.2 EURELECTRIC

More information

Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example

Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example Peny Panagiotakopoulou, Senior Power Systems Consultant, Energy Exemplar Europe Overview

More information

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public Overview of the IESO-Administered Markets IESO Training Updated: January, 2014 Public Overview of the IESO-Administered Markets AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the

More information

Cost Benefit Analysis for Electricity Balancing ISP harmonisation scoping paper

Cost Benefit Analysis for Electricity Balancing ISP harmonisation scoping paper Cost Benefit Analysis for Electricity Balancing ISP harmonisation scoping paper A paper for consultation Prepared by Frontier Economics and Consentec 20 February 2015 1. Contents 1. Contents... 2 2. Introduction...

More information

Energy Trading. Jonas Abrahamsson Senior Vice President Trading. E.ON Capital Market Day Nordic Stockholm, July 3, 2006

Energy Trading. Jonas Abrahamsson Senior Vice President Trading. E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Energy Trading Jonas Abrahamsson Senior Vice President Trading E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Agenda The Nordic Power Market The Role of Energy Trading within E.ON Nordic Page 2

More information

European Distribution System Operators for Smart Grids

European Distribution System Operators for Smart Grids European Distribution System Operators for Smart Grids Response to the European Commission s public consultation on a new energy market design October 2015 Executive summary The European Distribution System

More information

Electricity retail market business processes in Datahub

Electricity retail market business processes in Datahub Electricity retail market business processes in TABLE OF CONTENTS Table of Contents... 2 Figures... 6 Tables... 8 Definitions and abbreviations... 10 1 Introduction... 16 1.1 General... 16 1.2 Development

More information

market design policy paper

market design policy paper market design policy paper 15 September 2014 1 introduction Ensuring economic growth, jobs, secure coverage of basic needs at an affordable and competitive price, and sustainable use of limited resources

More information

DPM. Acquiring and terminating programme responsibility & financial consequences

DPM. Acquiring and terminating programme responsibility & financial consequences DPM Acquiring and terminating programme responsibility & financial consequences Published by EDSN Author WMWG Version number 3.0 Version date 12 June 2013 Status Final Version management Versi Name Date

More information

Dual Purpose Transmission Rights

Dual Purpose Transmission Rights Dual Purpose Transmission Rights The pros and cons of physical and financial transmission capacity rights and a recommended EFET approach for a pan European model DISCUSSION PAPER November 2008 Executive

More information

SERVICE AGREEMENT ON THE ELECTRICITY MARKET INFORMATION EXCHANGE SERVICE

SERVICE AGREEMENT ON THE ELECTRICITY MARKET INFORMATION EXCHANGE SERVICE 1 (5) SERVICE AGREEMENT ON THE ELECTRICITY MARKET INFORMATION EXCHANGE SERVICE 1 PARTIES TO THE AGREEMENT NN, business ID xxx (hereinafter "the Electricity Market Party") Address [Supplier's party ID:]

More information

BUSINESS RULES FOR CHAPTER VII DAILY IMBALANCE CHARGES

BUSINESS RULES FOR CHAPTER VII DAILY IMBALANCE CHARGES BUSINESS RULES FOR CHAPTER VII DAILY IMBALANCE CHARGES 1. General 1.1. The TSO shall publish its imbalance charge methodology and update it accordingly as any changes are made. This methodology must contain:

More information

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION

More information

Client Asset Requirements. Under S.I No.60 of 2007 European Communities (Markets in Financial Instruments) Regulations 2007

Client Asset Requirements. Under S.I No.60 of 2007 European Communities (Markets in Financial Instruments) Regulations 2007 Client Asset Requirements Under S.I No.60 of 2007 European Communities (Markets in Financial Instruments) Regulations 2007 Instructions Paper November 2007 1 Contents 1 Contents 2 Introduction 1 2.1 Scope

More information

Invoicing, payments and currency treatment. Fredrik Åström

Invoicing, payments and currency treatment. Fredrik Åström Invoicing, payments and currency treatment Fredrik Åström Topics 1. Invoicing 2. Payments 3. Currency treatment 2 Key aspects of the settlement model - Invoice Weekly invoicing, invoices sent on Monday

More information

European Distribution System Operators for Smart Grids

European Distribution System Operators for Smart Grids European Distribution System Operators for Smart Grids Data Management: The role of Distribution System Operators in managing data June 2014 1 Executive Summary The European Union (EU) has set ambitious

More information

The Swedish-Norwegian Electricity Certificate Market ANNUAL REPORT 2012

The Swedish-Norwegian Electricity Certificate Market ANNUAL REPORT 2012 The Swedish-Norwegian Electricity Certificate Market ANNUAL REPORT 2012 2 Contents Preface 3 The Nordic electricity market 4 Key figures for 2012 6 How the electricity certificate market works 7 Goal fulfilment

More information

How To Integrate Renewable Energy With Smart Grids

How To Integrate Renewable Energy With Smart Grids Challenges for the Market Integration of Renewables with Smart Grids IEEE PES ISGT 2012 Europe Conference Session: Economics of Smart Grids With Renewables 16.10.2012 Anke Weidlich 16 Oktober 2012 Economics

More information

The Nordic electricity market continued success or emerging problems? 1

The Nordic electricity market continued success or emerging problems? 1 1 The Nordic electricity market continued success or emerging problems? 1 Lars Bergman 2 Stockholm School of Economics Abstract Between 1996 and 2000 the national electricity markets in Denmark, Finland,

More information

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES 1 (6) GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES GENERAL CONDITIONS prepared by Svensk Energi 1. Introductory provisions 1.1 These general conditions

More information

Nordic System Operation Workshop 13 April 2010, Arlanda, Sweden. Reima Päivinen, Fingrid

Nordic System Operation Workshop 13 April 2010, Arlanda, Sweden. Reima Päivinen, Fingrid Nordic System Operation Workshop 13 April 2010, Arlanda, Sweden Reima Päivinen, Fingrid ENTSO-E: a pan-european TSO platform, fully operational since 1 July 2009 Represents 42 TSOs from 34 countries, responsible

More information

Ei R2015:15. An information management model for the future Swedish electricity market

Ei R2015:15. An information management model for the future Swedish electricity market Ei R2015:15 An information management model for the future Swedish electricity market The Swedish Energy Markets Inspectorate Box 155, 631 03 Eskilstuna, Sweden The Swedish Energy Markets Inspectorate

More information

EUROPEAN ELECTRICITY MARKET INTEGRATION: THE NORDIC EXPERIENCES

EUROPEAN ELECTRICITY MARKET INTEGRATION: THE NORDIC EXPERIENCES EUROPEAN ELECTRICITY MARKET INTEGRATION: THE NORDIC EXPERIENCES Lars Bergman Stockholm School of Economics Box 6501 SE-113 83 Stockholm, Sweden Abstract During the 1990s the electricity markets in Norway,

More information

Service description. Corporate Access Payables

Service description. Corporate Access Payables Service description Corporate Access Payables Table of contents Page 2 of 12 1 INTRODUCTION... 3 2 STRUCTURE OF DOCUMENTATION... 4 3 AGREEMENT SET-UP... 4 4 AVAILABLE MESSAGE TYPES... 5 5 OFFERED PAYMENT

More information

Nord Pool Spot Årskonference FSE Det frie energimarked 2015 El-indkøb Nye muligheder for optimering fleksibelt forbrug /demand response

Nord Pool Spot Årskonference FSE Det frie energimarked 2015 El-indkøb Nye muligheder for optimering fleksibelt forbrug /demand response Nord Pool Spot Årskonference FSE Det frie energimarked 2015 El-indkøb Nye muligheder for optimering fleksibelt forbrug /demand response 10. September København Henrik Hansen Køber du for dyrt ind? 2 100915

More information

EcoGrid EU NEWSLETTER No 1

EcoGrid EU NEWSLETTER No 1 EcoGrid EU NEWSLETTER No 1 February 2012 EcoGrid EU POWER MARKET OPERATION IN REAL TIME The objective of EcoGrid EU is ambitious to develop a prototype of a European Smart Grid market platform. The demonstration

More information

Report: Electricity retail markets in Europe division of duties between suppliers and DSOs

Report: Electricity retail markets in Europe division of duties between suppliers and DSOs LAPPEENRANTA UNIVERSITY OF TECHNOLOGY LAPPEENRANTA UNIVERSITY OF TECHNOLOGY ELECTRICAL ENGINEERING Report: Electricity retail markets in Europe division of duties between suppliers and DSOs M.Sc. Salla

More information

ENTSO-E Network Code on Emergency and Restoration

ENTSO-E Network Code on Emergency and Restoration ENTSO-E Network Code on Emergency and Restoration Notice 25 March 2015 This Network Code represents ENTSO-E s final proposals in line with the ACER Framework Guidelines on Electricity System Operation

More information

Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs

Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs Respondents information Name Ina Lehto Name of organisation Finnish Energy Industries Type of organisation Other

More information

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch ESRI Research Note The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch Research Notes are short papers on focused research issues. They are subject

More information

AGREEMENT (Translation) regarding operation of the interconnected Nordic power system (System Operation Agreement)

AGREEMENT (Translation) regarding operation of the interconnected Nordic power system (System Operation Agreement) 2006-06-13 1 (13) AGREEMENT (Translation) regarding operation of the interconnected Nordic power system (System Operation Agreement) 1 The Parties etc Energinet.dk (Energinet.dk) corporate registration

More information

European Power Exchanges Challenges for market integration

European Power Exchanges Challenges for market integration Mikael Lundin CEO Nord Pool Spot AS European Power Exchanges Challenges for market integration Helsinki, March 17 th 2011 About Nord Pool Spot Nord Pool Spot runs the largest market for power in the world

More information

BUSINESS TERMS FOR SECURITIES TRADING

BUSINESS TERMS FOR SECURITIES TRADING SAXO LEGAL BUSINESS TERMS FOR SECURITIES TRADING SERIOUS TRADING. WORLDWIDE. 1 Business Terms for Securities Trading at Saxo Bank A/S Saxo Bank aims to provide its Clients with the highest level of flexibility

More information

Most household services provide you with a fixed monthly bill: Broadband Internet service

Most household services provide you with a fixed monthly bill: Broadband Internet service Predict-a-Bill Natural Gas Most household services provide you with a fixed monthly bill: Cell phone service Broadband Internet service And now... your natural gas supply! Predict-a-Bill advantage: Developed

More information

Market Entrant Processes, Hurdles and Suggestions in the Nordic Energy Market - the View of the Market

Market Entrant Processes, Hurdles and Suggestions in the Nordic Energy Market - the View of the Market A report commissioned by Nordic Energy Regulators (NordREG) Market Entrant Processes, Hurdles and Suggestions in the Nordic Energy Market - the View of the Market Writer: Dr Philip Lewis VaasaETT Draft

More information

Nord Pool Spot s FTP-server - directories and contents

Nord Pool Spot s FTP-server - directories and contents Nord Pool Spot s FTP-server - directories and contents Updated April 7, 2014 This document lists the various types of information available for downloading from Nord Pool Spot s FTP-server. Access to the

More information

Role of Power Traders in enhancing market dynamics

Role of Power Traders in enhancing market dynamics Role of Power Traders in enhancing market dynamics Date: 08 th March 2011 Sunil Agrawal (Head GMR Energy Trading) & Tanmay Pramanik (Assoc. Mgr GMR Energy Trading) Evolution of Power Trading business Internationally

More information

STATUTORY INSTRUMENTS. CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48(1)) CLIENT ASSET REGULATIONS 2015 FOR INVESTMENT FIRMS

STATUTORY INSTRUMENTS. CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48(1)) CLIENT ASSET REGULATIONS 2015 FOR INVESTMENT FIRMS STATUTORY INSTRUMENTS. S.I. No. )04, of 2015 CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48(1)) CLIENT ASSET REGULATIONS 2015 FOR INVESTMENT FIRMS S.I. No. (74 of 2015 CENTRAL BANK (SUPERVISION

More information

Regulation. ABOUT THE AUTHORS and Markets Review. Law Business Research. Third Edition. Editor David L Schwartz

Regulation. ABOUT THE AUTHORS and Markets Review. Law Business Research. Third Edition. Editor David L Schwartz The Appendix Energy 1 Regulation ABOUT THE AUTHORS and Markets Review Third Edition Editor David L Schwartz Law Business Research 551 The Energy Regulation and Markets Review The Energy Regulation and

More information

Unofficial translation. The Electricity (Capacity) Market Rules

Unofficial translation. The Electricity (Capacity) Market Rules Chapter I General Provisions Article 1. Scope of Activity Unofficial translation The Electricity (Capacity) Market Rules These Rules regulate: a) Functioning of Electricity and Guaranteed Capacity Market

More information

AN OVERVIEW OF INTERNATIONAL ENERGY AGENCY DEMAND SIDE MANAGEMENT PROGRAM TASK XIII: DEMAND RESPONSE RESOURCES PREPARED FOR:

AN OVERVIEW OF INTERNATIONAL ENERGY AGENCY DEMAND SIDE MANAGEMENT PROGRAM TASK XIII: DEMAND RESPONSE RESOURCES PREPARED FOR: AN OVERVIEW OF INTERNATIONAL ENERGY AGENCY DEMAND SIDE MANAGEMENT PROGRAM TASK XIII: DEMAND RESPONSE RESOURCES PREPARED FOR: FEDERAL ENERGY REGULATORY COMMISSION S TECHNICAL CONFERENCE ON DEMAND RESPONSE

More information

Terms of Access to Payment Systems

Terms of Access to Payment Systems 1 Terms of Access to Payment Systems The Different Positions of Small and Large Banks English summary of Swedish Competition Authority report 2006:1 2 Summary The Swedish banking market is dominated by

More information

Code of Practice on Electronic Invoicing in Europe

Code of Practice on Electronic Invoicing in Europe Code of Practice on Electronic Invoicing in Europe 24 th March 2009 Version 0.17 Approved by Expert Group Plenary on 24 th March 2009 This Code of Practice on Electronic Invoicing in Europe is recommended

More information

Code of Practice on Electronic Invoicing in Europe

Code of Practice on Electronic Invoicing in Europe Code of Practice on Electronic Invoicing in Europe 24 th March 2009 Version 0.17 Approved by Expert Group Plenary on 24 th March 2009 This Code of Practice on Electronic Invoicing in Europe is recommended

More information

Financial Services Authority. Guide to Client Money for General Insurance Intermediaries

Financial Services Authority. Guide to Client Money for General Insurance Intermediaries Financial Services Authority Guide to Client Money for General Insurance Intermediaries March 2007 Contents Introduction 3 Part 1 Making arrangements to hold client money 1.1 What is client money? 4 1.2

More information