Behind the Meter Generation Common Issues Meeting. September 27, 2016

Size: px
Start display at page:

Download "Behind the Meter Generation Common Issues Meeting. September 27, 2016"

Transcription

1 Behind the Meter Generation Common Issues Meeting September 27, 2016

2 Purpose Purpose and Key Takeaways Educate stakeholders on behind the meter generation treatment in MISO processes Key Takeaways Processes have evolved over time MISO wants to collaborate with Stakeholders on desired next steps 2

3 Step through the Processes Transmission Planning and Service Resource Adequacy Modeling and Examples Day Ahead and Real- Time Markets 3

4 What is the difference between BTMG and btmg? BTMG references the Module A Tariff definition Lowercase btmg has similar meaning Behind the Meter Generation (BTMG): Generation resources used to serve wholesale or retail load located behind a CPNode that are not included in the Transmission Provider s Setpoint Instructions and in some cases can also be deliverable to Load located within the Transmission Provider Region using either Network Integration, Point- To-Point Transmission Service or transmission service pursuant to a Grandfathered Agreement. These resources have an obligation to be made available during Emergencies. 4

5 CPNodes not included in Setpoint instructions DRR Type 1 Load Zone 5

6 Transmission Planning

7 Planning Sub-processes Generator Interconnection Transmission Service MTEP Generator Retirement

8 Generator Interconnection for BTMG/btmg Similar to any other Generator, a BTMG/btmg needs to go through MISO GI process (Attachment X) only if connecting to MISO Transmission System* Fast track process (Section 14 of Attachment X) for small generators (< 5MW) If a BTMG/btmg is connecting to a non-miso Transmission Facility (or distribution facilities), interconnection customer needs to work with local utility for any evaluation that may be required *MISO Transmission System include Facilities with functional control transferred to MISO through TOA Appendix H and Non-transferred facilities under agency agreement through TOA Appendix G 8

9 Generator Interconnection Products Customer may elect Energy Resource Interconnection Service (ERIS) or Network Resource Interconnection Service (NRIS) ERIS is required in order to connect to the MISO Transmission System NRIS is required in order for a load to use the resource to provide for its Network Integration Transmission Service (NITS) If a Generation Resource connected to the MISO Transmission System desires to be a Capacity Resource for RA purposes, it must either have NRIS interconnection service or ERIS with firm transmission service If a Generation Resource connected to non-miso Transmission Facility desires to be a Capacity Resource for RA purposes, it must procure External NRIS from MISO by entering MISO Interconnection queue (Attachment X) MISO can work with stakeholders to determine interconnection requirements for a BTMG seeking to be a Network Resource for a remote load in the same or different LRZ. 9

10 Transmission Service for BTMG/btmg Transmission customer can use BTMG/btmg as source to procure Transmission Service (PTP or NITS) Typically, customer selects nearest CPNode as source since MISO OASIS has only CPNodes as eligible internal source for Transmission Service Requests (TSRs) Evaluation of Long-term Transmission Service considers BTMG/btmg to the extent that the resources are included in the planning models Long-term TSRs are evaluated using source specific granularity 10

11 Treatment of BTMG/btmg in MTEP MTEP studies explicitly model: All generators with an interconnection agreement pursuant to Attachment X Legacy Designated Network Resources of MISO member utilities All generators that are sources for long-term Firm Point-To-Point Transmission Service Requests Some BTMG may be netted with load when LSE/TO submits load information in planning models. 11

12 What are the appropriate reporting requirements for BTMG/btmg retirement? Currently, there is no requirement for BTMG to notify MISO of its intention to retire. MISO has considered whether some type of notification should be required, and may seek stakeholder input on this issue in the future (no specific timing for this has been contemplated). 12

13 Resource Adequacy

14

15 15

16 Registering as a BTMG type LMR Submit generator test annually and outage data in PowerGADs application through the Portal Register the BTMG annually in MECT* Assign to load Cpnode w/ same Asset Owner Load Forecast should exclude resource output *MECT is the Module E Capacity Tool 16

17 BTMG type LMR Performance Requirements Must be available and respond per MISO s Emergency Operating Procedures Minimum 12 hour notification time Available 5 times annually during the Summer Runs for at least 4 hours during each implementation Submit status daily in the MISO Communication System (MCS) 17

18 Modeling

19 Model Purpose/goal MISO Modeling Build accurate EMS models that strike a balance between modeling detail and model performance. MISO BA load BA load is calculated in Real time as generation minus tie-lines. MISO Transmission MISO transmission is generally 100kV and above 19

20 BTMG modeling MISO Modeling Explicitly model all generators greater than 5 MW and directly connected to MISO Transmission. (this generation must have telemetry - MW, MVAR, status) Local Balancing Authority load forecast must be calculated with same set of generators present in the MISO model. Practically, should all BTMG be modeled? This would require modeling in much greater detail, the effort of which would exceed the benefit. 20

21 Does btmg need to be registered? If explicitly modeled, the btmg needs to be registered as a DRR Type II or Elemental pricing node of a DRR Type I or Load Zone If not explicitly modeled, the impact of the btmg will be seen through the load zone Registration is required to participate in the Resource Adequacy Construct 21

22 BPM 010 Attachment D Examples 22

23 23

24 24

25 25

26 26

27 27

28 Day-Ahead and Real-time Markets

29

30 BTMG/btmg Use during Max Gen Events MISO utilizes SO-P-EOP MISO Market Capacity Emergency Procedure to manage Max Gen events BTMG/btmg Expectations during a Max Gen Event Alert/Warning LMR/EDRs update offers in MCS DRR-I and DRR-II update offers in Portal Event Step 1 DRR-I and DRR-II committed Event Step 2 LMR/EDRs committed 30

31 Max Gen Emergency Procedure Progression Tier I Offer Floor Event - Step 1: a) Commit AME b) Implement Emergency Max Limits c) Declare NERC Energy Emergency Alert (EEA) 1 - All available non-emergency resources in use Tier II Offer Floor Event Step 2: a) Declare NERC EEA 2 - Load Mgmt procedures in effect b) Implement LMR (BTMG & DR) & Load Management Measures (LMM) Stage 1 c) Commit Emergency Demand Response (EDR) d) Implement Emergency Energy Purchases Event - Step 3: a) Utilize Operating Reserves b) Instruct load reduction of Load Management Measures (LMM) Stage 2 31

32 How do you verify accounting for BTMG/btmg? BPM 26 describes DRR Performance Assessment in section 4.8 EDR Performance Assessment in section 5.5 LMR Performance Assessment in section 6.3 Appendix A: Consumption Baseline Examples in Section 9 Measurement and Verification Procedures are documented in Sections 6-8 of Schedule 30 for EDRs 32

33 Next Steps Questions? Review Action Items Contacts Kim Sperry Justin Stewart 33

Demand Response and Energy Efficiency in the Midwest ISO. A Primer

Demand Response and Energy Efficiency in the Midwest ISO. A Primer Demand Response and Energy Efficiency in the Midwest ISO A Primer John Moore Bruce Campbell Kevin Murray September 28, 2010 1 Agenda Types of Midwest ISO Demand Response (DR). Products DR is eligible to

More information

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out 1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

GIP. 3.2.3 Net Zero Interconnection Service.

GIP. 3.2.3 Net Zero Interconnection Service. GIP and GIA Energy Displacement Agreement shall mean an agreement between an Interconnection Customer with a commercially operating Generating Facility on the Transmission Provider s Transmission System

More information

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant

More information

Applicability and Eligibility

Applicability and Eligibility Application for Resource Adequacy Deliverability Status for a Distributed Generation Resource Interconnected or Seeking Interconnection to the Distribution Facilities of an Investor-Owned Utility Participating

More information

New York State of the Market System - NYISO Success Project

New York State of the Market System - NYISO Success Project Auxiliary Market Products Additional Capacity Zones The NYISO and stakeholders are developing the rationale in 2010 for creating additional capacity zones, identified as a recommendation in the 2009 State

More information

Appendix C-2. Entergy Services, Inc. June 8, 2016

Appendix C-2. Entergy Services, Inc. June 8, 2016 Appendix C-2 Preliminary Due Diligence List (Existing Resources) For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016

More information

Transmission Service Reference Manual. April 29, 2015

Transmission Service Reference Manual. April 29, 2015 Transmission Service Reference Manual April 29, 2015 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 Author Shari Brown Change Description Initial creation of draft

More information

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Appendix A Glossary For 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 Website means the internet website https://spofossil.entergy.com/entrfp/send/2016ellrenewablerfp/index.htm.

More information

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations G1 DEFINITIONS In the ISO rules: acceptable operational reason means with respect to a source asset, any one or more of the following: i) a circumstance related to the operation of the generating asset

More information

Energy Imbalance Market

Energy Imbalance Market Energy Imbalance Market Tariff Framework September 10, 2013 CAIS[Type text] [Type text] [Type text] Table of Contents 1. Introduction... 1 2. Guiding Objectives for the Tariff Framework... 2 3. Tariff

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Capacity Procurement Mechanism Replacement Doc ID: GNFDMDEHU6BB-46-53 Page 1 of 18 Disclaimer All information contained in this draft Business s Specification (BRS) as provided

More information

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market Settling the Day-Ahead Market Charge Codes included in this training: 6011, 6800, 6700, 6301. EXTERNAL Customer Services Page 1 of 45 Disclaimer All information contained in this document is provided for

More information

MICHIGAN RENEWABLE ENERGY CERTIFICATION SYSTEM OPERATING PROCEDURES

MICHIGAN RENEWABLE ENERGY CERTIFICATION SYSTEM OPERATING PROCEDURES MICHIGAN RENEWABLE ENERGY CERTIFICATION SYSTEM OPERATING PROCEDURES November, 2012 Table of Contents Glossary... iiiv 1 Introduction... 1 2 MIRECS User Registration... 2 2.1 Participation in MIRECS...

More information

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No.

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 1 2 3 4 Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 2000) comments regarding Transmission and Generation

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION Sheet 1 Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services from the Distribution Company, with the exception of

More information

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE This paper describes the issues associated with using Batch-Load Demand Response i resources to provide Contingency Reserve

More information

Distributed Energy Resource Services and Pricing Caltech Resnick Ins;tute Grid 2020 Seminar

Distributed Energy Resource Services and Pricing Caltech Resnick Ins;tute Grid 2020 Seminar Distributed Energy Resource Services and Pricing Caltech Resnick Ins;tute Grid 2020 Seminar Ali Ipakchi VP, Smart Grid and Green Power February 21, 2013 Trade Secret This document and attachments contain

More information

Overview of Reliability Demand Response Resource

Overview of Reliability Demand Response Resource Overview of Reliability Demand Response Resource Radha Madrigal Customer Service Department May 8, 2014 Agenda Product overview and purpose Define Reliability Demand Response Resource Agreements & registration

More information

Updated November 20, 2015. Director, System Planning

Updated November 20, 2015. Director, System Planning Updated November 20, 2015 Job Descriptions Job Title Reports To Job Description SYSTEM PLANNING & SERVICES VP Compliance Manages the system planning and services staff. The director is responsible for

More information

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff Alcoa Power Generating Inc. Long Sault Division ALCOA POWER GENERATING INC. Long Sault Division Open Access Transmission Tariff The following sheets reflect all revisions submitted to the Federal Energy

More information

TRANSMISSION SERVICES MANUAL

TRANSMISSION SERVICES MANUAL TRANSMISSION SERVICES MANUAL Transmission Services Manual Version: 2.0 Revision Date: January 20, 2005 Committee Approved: January 19, 2005 Effectivity Date: February 1, 2005 Disclaimer The information

More information

References... 4. Appendices... 5. I. INTRODUCTION... 6 A. Background... 6 B. Standards... 6

References... 4. Appendices... 5. I. INTRODUCTION... 6 A. Background... 6 B. Standards... 6 ISO New England Operating Procedure No. 14 - Technical Requirements for Generators, Demand Resources, Asset Related Demands and Alternative Technology Regulation Resources Effective Date: January 29, 2015

More information

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria A. Purpose: The FRCC Reliability Coordinator (RC) Contingency Analysis (CA) application is essential to maintaining the reliability of the FRCC Bulk Electric System. The application has the capability

More information

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

Resource Monitoring and Deliverability Tool Paper

Resource Monitoring and Deliverability Tool Paper Resource Monitoring and Deliverability Tool Paper NWPP MC Phase 3 Operations Integration Work Group 11/30/2014 Page 1 of 16 Table of Contents Executive Summary... 3 1. Purpose... 5 2. Existent Methods

More information

Demand Response FAQs

Demand Response FAQs 1 Under the current CAISO tariff, assuming it would otherwise meet the requirements under the CAISO tariff and business practice manuals to do so, can the Load associated with a retail meter participate

More information

Introduction to the Integrated Marketplace

Introduction to the Integrated Marketplace The information, practices, processes and procedures outlined and contained in this publication are the intellectual property of Southwest Power Pool, Inc. and are protected by law. This publication or

More information

RIG Acceptance Test (RAT) Procedures

RIG Acceptance Test (RAT) Procedures RIG Acceptance Test (RAT) Procedures RIG Acceptance Test (RAT) Procedure 0 Print Date 2 /20/2007 REVISION HISTORY REVISON NO. DATE DESCRIPTION 1.0 Initial Release 0 Update Logo and Links i RIG Acceptance

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA STANDBY

More information

Texas transformed. Achieving significant savings through a new electricity market management system

Texas transformed. Achieving significant savings through a new electricity market management system Texas transformed Achieving significant savings through a new electricity market management system KHOSROW MOSLEHI The state of Texas has long been the center of energy activities in the United States,

More information

Status of Demand Response in Europe. Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015

Status of Demand Response in Europe. Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015 Status of Demand Response in Europe Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015 The Smart Energy Demand Coalition (SEDC) is an European Industry Association

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles. Stakeholder Call August 23, 2013 9:30 a.m. - 12:00 p.m.

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles. Stakeholder Call August 23, 2013 9:30 a.m. - 12:00 p.m. Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Stakeholder Call August 23, 2013 9:30 a.m. - 12:00 p.m. 1. Introduction Mercy Parker Helget Sr. Stakeholder Engagement

More information

Duke Energy Progress Standards of Conduct Transmission Function Employee Job Titles and Job Descriptions 9/1/13

Duke Energy Progress Standards of Conduct Transmission Function Employee Job Titles and Job Descriptions 9/1/13 Duke Energy Progress Standards of Conduct Transmission Function Employee Job Titles and Job Descriptions 9/1/13 Transmission Operations & Planning Carolinas Power System Operations Director Power System

More information

Appendix D. Minimum Requirements For Developmental Resources. For

Appendix D. Minimum Requirements For Developmental Resources. For z Appendix D Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 MINIMUM REQUIREMENTS

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

Update on Texas Restructuring. NAESB Conference September 24, 2002 Baltimore, MD Chairman, Rebecca Klein

Update on Texas Restructuring. NAESB Conference September 24, 2002 Baltimore, MD Chairman, Rebecca Klein Update on Texas Restructuring NAESB Conference September 24, 2002 Baltimore, MD Chairman, Rebecca Klein OUTLINE State of the National Energy/Electric Industry State of Texas Electricity Industry Status

More information

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 Grid Operations & Planning Summary March 2014 Operations The peak demand of 54,549 MW on March 3 rd was greater than the mid-term

More information

ELECTRIC SCHEDULE E-1 Sheet 1 RESIDENTIAL SERVICES

ELECTRIC SCHEDULE E-1 Sheet 1 RESIDENTIAL SERVICES Revised Cal. P.U.C. Sheet No. 37050-E Cancelling Revised Cal. P.U.C. Sheet No. 36706-E ELECTRIC SCHEDULE E-1 Sheet 1 APPLICABILITY: TERRITORY: RATES: This schedule is applicable to single-phase and polyphase

More information

Chapter 7 System Operations and Physical Markets

Chapter 7 System Operations and Physical Markets MDP_RUL_0002_07 Market Rules Chapter 7 System Operations and Physical Markets Public Issue Date: June 3, 2015 Library Record No. MDP_RUL_0002_07 Document Name Market Rules for the Ontario Electricity Market

More information

Demand Response Frequently Asked Questions (Last Updated 02/23/16)

Demand Response Frequently Asked Questions (Last Updated 02/23/16) # Questions Answers 1 Under the current CAISO tariff, assuming it would otherwise meet the requirements under the CAISO tariff and business practice manuals to do so, can the Load associated with a retail

More information

Model Building and Maintenance as a Hosted Service. Farrokh Albuyeh, Ph.D. Open Access Technology International June 2006

Model Building and Maintenance as a Hosted Service. Farrokh Albuyeh, Ph.D. Open Access Technology International June 2006 Model Building and Maintenance as a Hosted Service Farrokh Albuyeh, Ph.D. Open Access Technology International June 2006 Model Building and Maintenance Problem: Many Models Inconsistent Models Internal

More information

Market Solutions to Loop Flow

Market Solutions to Loop Flow Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution

More information

Consolidated Edison Company of New York, Inc.

Consolidated Edison Company of New York, Inc. Glossary of Terms Appendix A For the purpose of this Operating Manual, the following terms have the meanings stated below: Annual Period is the 12 months beginning with the month in which the customer

More information

Southern California Edison Revised Cal. PUC Sheet No. 55628-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No. 55628-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 55628-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53984-E Schedule D Sheet 1 APPLICABILITY Applicable to domestic service

More information

PJM LMP Market Overview

PJM LMP Market Overview PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people

More information

PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement

PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement Asanga Perera Market-to-Market Lead Market Implementation Committee August 12, 2015 Purpose Overview This presentation provides

More information

2012 Proposed Projects. Project Title Project Description. Business Intelligence Products

2012 Proposed Projects. Project Title Project Description. Business Intelligence Products Business Intelligence Products etariff Public Website Module This project will add the etariff Public Website module to www.nyiso.com. This is a small effort with new enhancements for the MPs. It allows

More information

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1 PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public

More information

146 FERC 61,180 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

146 FERC 61,180 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 146 FERC 61,180 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Acting Chairman; Philip D. Moeller, John R. Norris, and Tony Clark. Midcontinent Independent

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

Energy Efficiency Measurement & Verification

Energy Efficiency Measurement & Verification PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 02 Effective Date: 12/17/2015 Prepared by PJM Forward Market Operations PJM 2015 PJM 2008 Revision, Effective Date: i Table of Contents

More information

+ + + + Advancing and maximizing the. Technology. December 2014

+ + + + Advancing and maximizing the. Technology. December 2014 Advancing and maximizing the value of Energy Storage Technology A California Roadmap December 2014 This roadmap is a product of collaboration among three organizations the California Independent System

More information

What is hourly pricing and what does it mean for you? Customer Meetings May 2006

What is hourly pricing and what does it mean for you? Customer Meetings May 2006 What is hourly pricing and what does it mean for you? Customer Meetings May 2006 Catherine McDonough Project Manager 1 (315) 428-5641 Background In 1998, National Grid (NG) extended hourly pricing to our

More information

MISO Schedule 41 Charge to Recover Costs of Entergy Storm Securitization SCHEDULES 33.0.0 SCHEDULE 41

MISO Schedule 41 Charge to Recover Costs of Entergy Storm Securitization SCHEDULES 33.0.0 SCHEDULE 41 SCHEDULE 41 Charges from Entergy Operating Companies Pricing Zones I. GENERAL This Schedule 41 provides for the recovery of the storm securitization charges consistent with settlement agreements approved

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

62-110. Certificate of convenience and necessity.

62-110. Certificate of convenience and necessity. Article 6. The Utility Franchise. 62-110. Certificate of convenience and necessity. (a) Except as provided for bus companies in Article 12 of this Chapter, no public utility shall hereafter begin the construction

More information

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

Energy Management System (EMS) Model Updates and Quality Assurance (QA) PJM Manual 3A: Energy Management System (EMS) Model Updates and Quality Assurance (QA) Revision: 10 Effective Date: June 25, 2015 Prepared by: Operation Support Division PJM 2015 PJM 2007 Revision 0, Effective

More information

Natural Gas Pipeline Penalty Recovery Issue Paper

Natural Gas Pipeline Penalty Recovery Issue Paper Natural Gas Pipeline Penalty Recovery Issue Paper September 16, 2014 Table of Contents I. Introduction and Background... 3 II. Scope of Initiative and Plan for Stakeholder Engagement... 4 III. The Approved

More information

The RES Handbook. A Guide to Conducting Business with Ameren in the Competitive Electric Marketplace in Illinois

The RES Handbook. A Guide to Conducting Business with Ameren in the Competitive Electric Marketplace in Illinois The RES Handbook A Guide to Conducting Business with Ameren in the Competitive Electric Marketplace in Illinois Table of Contents Preface Page 3 Chapter 1: The Competitive Marketplace Page 4 Chapter 2:

More information

Weather-readiness assessment model for Utilities. Shy Muralidharan Global Product Manager Energy Solutions Schneider Electric

Weather-readiness assessment model for Utilities. Shy Muralidharan Global Product Manager Energy Solutions Schneider Electric Weather-readiness assessment model for Utilities Shy Muralidharan Global Product Manager Energy Solutions Schneider Electric 1 Agenda > Impact of weather on Utilities businesses > Why should you be weather

More information

2015/2016 Planning Resource Auction Results. April 14, 2015

2015/2016 Planning Resource Auction Results. April 14, 2015 2015/2016 Planning Resource Auction Results April 14, 2015 Executive Summary MISO successfully completed its third annual Planning Resource Auction The MISO region has adequate resources to meet its Planning

More information

Chapter 9 Settlements and Billing

Chapter 9 Settlements and Billing MDP_RUL_0002_09 Market Rules Chapter 9 Settlements and Billing Public Issue Date: December 2, 2015 Library Record No. MDP_RUL_0002_09 Document Name Market Rules for the Ontario Electricity Market Issue

More information

Special Union for the International Deposit of Industrial Designs (Hague Union)

Special Union for the International Deposit of Industrial Designs (Hague Union) E H/A/35/1 ORIGINAL: ENGLISH DATE: JULY 7, 2015 Special Union for the International Deposit of Industrial Designs (Hague Union) Assembly Thirty-Fifth (20 th Ordinary) Session Geneva, October 5 to 14, 2015

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Version.16 October 19, 211 Revision History Date Version Description Author 6/8/211.8 Created the external business

More information

Two Settlement - Virtual Bidding and Transactions

Two Settlement - Virtual Bidding and Transactions Two Settlement - Virtual Bidding and Transactions (Fall 2009) PJM 2009 2009 PJM 1 Agenda Two-Settlement Overview Two-Settlement Features & System Two-Settlement Business Rules Two-Settlement Data Requirements

More information

Administrative Services for the PJM Interconnection Operating Agreement

Administrative Services for the PJM Interconnection Operating Agreement PJM Manual 33: Administrative Services for the PJM Interconnection Operating Agreement Revision: 12 Effective Date: March 31, 2016 Prepared by Member Relations PJM 2016 PAGE iii lviii PJM 2008 Revision

More information

Deliverability Testing

Deliverability Testing Deliverability Testing Henry Chao Vice President System & Resource Planning New York Independent System Operator New York State Reliability Council Executive Committee Meeting September 12, 2008 Definition

More information

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Integration of Renewables Energy Storage Smart Grid Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Current Power System Gen. Trans. Dist.Cust.

More information

Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT

Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT FERC Conference on Increasing Real-Time and Day-Ahead Market Efficiency through Improved

More information

Wind Power and Electricity Markets

Wind Power and Electricity Markets PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: info@uwig.org Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy

More information

Overview and Comparison of Demand Response Programs in North American Electricity Markets

Overview and Comparison of Demand Response Programs in North American Electricity Markets , pp.22-29 http://dx.doi.org/10.14257/astl.205.97.04 Overview and Comparison of Demand Response Programs in North American Electricity Markets Pedro Faria 1, Zita Vale 1 1 GECAD Knowledge Engineering and

More information

2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc.

2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc. 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc. Entergy Arkansas, Inc. May 26, 2016 TABLE OF CONTENTS 1. GENERAL INFORMATION... 1 1.1. Introduction...

More information

INFORMATION FOR ALTERNATIVE ELECTRIC SUPPLIERS

INFORMATION FOR ALTERNATIVE ELECTRIC SUPPLIERS On June 5, 2000, new legislation entitled the Customer Choice and Electricity Reliability Act, 2000 PA 141 (Act 141) and 2000 PA 142, became effective. Section 10a (2) of the act provides that the Michigan

More information

Selling Renewable Energy in Michigan. Julie Baldwin Michigan Public Service Commission Michigan Wind Conference 2009 March 3, 2009

Selling Renewable Energy in Michigan. Julie Baldwin Michigan Public Service Commission Michigan Wind Conference 2009 March 3, 2009 Selling Renewable Energy in Michigan Julie Baldwin Michigan Public Service Commission Michigan Wind Conference 2009 March 3, 2009 Michigan Public Service Commission Three Governor-appointed Commissioners

More information

New Brunswick Electricity Business Rules

New Brunswick Electricity Business Rules New Brunswick Electricity Business Rules Table of Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 Administration and Participation Transmission Planning and Connections Reliable Operations Billing and

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 of New York, Inc. (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION

More information

Link 2 Vehicle Maintenance System

Link 2 Vehicle Maintenance System Link 2 Vehicle Maintenance System Link 2 Data Module - Monitors Critical Vehicle Information - Records CAN J1939 data bus for engine, transmission and ABS along with aerial, PTO and generator information

More information

State Of California's Energy Bill

State Of California's Energy Bill 2750 Monroe Boulevard Valley Forge Corporate Center Audubon, PA 19403 James M. Burlew Counsel Telephone: (610) 666-4345 Fax (610) 666-8211 Email Address: james.burlew@pjm.com December 15, 2015 The Honorable

More information

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016 Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042 Market Subcommittee (MSC) May 3, 2016 Purpose Purpose and Key Takeaways Review proposed FERC Energy Offer Cap rules, and potential

More information

Emergency Demand Response Program Manual

Emergency Demand Response Program Manual MANUAL 7 Emergency Demand Response Program Manual June 2016 Version: 7.2 Effective Date: 06/03/2016 Committee Acceptance: 05/18/2016 BIC This document was prepared by: NYISO Demand Response Operations

More information

* Revised March 2013 *

* Revised March 2013 * * Revised March 2013 * 2 Table of Contents Welcome Letter...3 Resource List...4 Business Center/Account Management...5 Overview...5 Customer Enrollment...21 Overview...21 Customer Eligibility......21 Retailer

More information

ATTACHMENT G. Network Operating Agreement

ATTACHMENT G. Network Operating Agreement ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service

More information

2016 Santee Cooper Solar Home & Solar Share Home Program Manual

2016 Santee Cooper Solar Home & Solar Share Home Program Manual 2016-17 2016 Santee Cooper Solar Home & Solar Share Home Program Manual Version 03232016 This Program Manual is intended to serve as a reference for Santee Cooper s residential Customers that are interested

More information

SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications. Contents

SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications. Contents SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications Contents 1. Objective... 2 2. Background... 2 3. Responsibilities... 3 4. Controls... 4 5. Instructions... 5 5.1 Document Operations

More information

MEMORANDUM OF UNDERSTANDING THE INDEPENDENT ELECTRICITY SYSTEM OPERATOR THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

MEMORANDUM OF UNDERSTANDING THE INDEPENDENT ELECTRICITY SYSTEM OPERATOR THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION MEMORANDUM OF UNDERSTANDING BETWEEN THE INDEPENDENT ELECTRICITY SYSTEM OPERATOR AND THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION AND THE NORTHEAST POWER COORDINATING COUNCIL, CROSS-BORDER REGIONAL

More information

2014 EIA Energy Conference. Edward Randolph Director, Energy Division California Public Utilities Commission

2014 EIA Energy Conference. Edward Randolph Director, Energy Division California Public Utilities Commission 2014 EIA Energy Conference Edward Randolph Director, Energy Division California Public Utilities Commission July 14, 2014 Clean Electricity Policy Initiatives In California (Partial) Wholesale Renewables

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Reliability Technical Conference Docket No. AD16-15-000 Prepared Statement of Mark Rothleder on behalf of the California Independent System

More information

The Market Guide. An introductory guide to how the Electric Reliability Council of Texas (ERCOT) facilitates the competitive power market

The Market Guide. An introductory guide to how the Electric Reliability Council of Texas (ERCOT) facilitates the competitive power market The Market Guide An introductory guide to how the Electric Reliability Council of Texas (ERCOT) facilitates the competitive power market This version is based on operations of the ERCOT market on January

More information

Convergence Bidding Stakeholder Conference Call

Convergence Bidding Stakeholder Conference Call Convergence Bidding Stakeholder Conference Call Margaret Miller Senior Market Design & Policy Specialist Convergence Bidding Stakeholder Conference Call August 13, 2009 Agenda 1:00 1:15 - Plan for Stakeholder

More information

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England Business Models for Transactive Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England About ISO New England (ISO) Not-for-profit

More information

Draft for comment - OpenADR 2.0 Demand Response Program Guide

Draft for comment - OpenADR 2.0 Demand Response Program Guide Draft for comment - OpenADR 2.0 Demand Response Program Guide Revision Number: 0.75 Document Status: Working Text Document Number: 20140701 The information within this document is the property of the OpenADR

More information

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public Overview of the IESO-Administered Markets IESO Training Updated: January, 2014 Public Overview of the IESO-Administered Markets AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the

More information

ANCILLARY SERVICES. A Paper for PPC. Establishment Organisation and Pilot Operation of the HTSO. 21 September 2000

ANCILLARY SERVICES. A Paper for PPC. Establishment Organisation and Pilot Operation of the HTSO. 21 September 2000 ANCILLARY SERVICES A Paper for PPC Establishment Organisation and Pilot Operation of the HTSO 21 September 2000 TABLE OF CONTENTS 1. INTRODUCTION 1 2. SYSTEM TRADING ARRANGEMENTS 2 3. OPTIONS FOR PROCUREMENT

More information

ELECTRIC SCHEDULE E-1 Sheet 1 RESIDENTIAL SERVICES

ELECTRIC SCHEDULE E-1 Sheet 1 RESIDENTIAL SERVICES Revised Cal. P.U.C. Sheet No. 35144-E Cancelling Revised Cal. P.U.C. Sheet No. 34679-E ELECTRIC SCHEDULE E-1 Sheet 1 APPLICABILITY: TERRITORY: RATES: This schedule is applicable to single-phase and polyphase

More information

Grid Operations and Planning

Grid Operations and Planning Grid Operations and Planning Report Kent Saathoff ERCOT Board of Directors April 20, 2010 Kent Content Summary March 2010 Operations Peak Demand: Actual vs. Forecast On-line Resources: Total at Peak and

More information

PNMsoft Sequence Ticketing Solution (PSTS)

PNMsoft Sequence Ticketing Solution (PSTS) PNMsoft Sequence Ticketing Solution (PSTS) PNMsoft Sequence Ticketing Solution (PSTS) is a software solution built on an industry leading Business Process Management platform. It enables organizations

More information