CONNECTING. Energy Infrastructure. Postage Stamp Cost Allocation for MEP projects 345 kv and above
|
|
- Poppy McLaughlin
- 7 years ago
- Views:
Transcription
1 CONNECTING Energy Infrastructure Postage Stamp Cost Allocation for MEP projects 345 kv and above Dave Grover ITC Holdings Corp. September 20,
2 Overview of Presentation Review of Postage Stamp Pricing for Transmission across other regions of the U.S. History of Postage Stamp pricing for transmission facilities in MISO Why a Postage Stamp component is appropriate for MEP Projects at 345 kv and above In-Service, Approved and Planned 345 kv Projects in MISO and their Cost Allocation Case for Postage Stamp Pricing for EHV Networked Transmission Facilities 2
3 Postage Stamp Pricing for New Transmission in the US PJM: 50% postage stamp for 500 kv and 345 kv double circuit SPP: Highway-Byway-100% postage stamp for Highway (300 kv and above); 1/3 postage stamp for Byway ( kv) ISO-NE: Reliability Projects and Market Efficiency Transmission Upgrades 115 kv and above 100% postage stamp; public policy projects 70% postage stamp CAISO: Regional Transmission Facilities >200 kv 100% postage stamp 3
4 History of Postage Stamp Pricing for New 345 kv Facilities in MISO Transmission Owners Agreement filed in 1998 After 6 year transition period (Feb. 1, 2002-January 31, 2008), MISO shall file to implement Midwest ISO system-wide transmission rates (i.e. the same transmission rate shall apply to all customers) (i) if all Owners paying the Midwest ISO for transmission service associated with Bundled Load agree; (ii) if all Owners that are paying the Midwest ISO for transmission service associated with Bundled Load are allowed to recover such payments; or (iii) there are no Owners paying the Midwest ISO for transmission service associated with Bundled Load. Postage stamp would have included all voltages in rates The Transmission Owners and MISO filed in 2007 to retain license plate pricing after the end of the transition period 4
5 History of Postage Stamp Pricing for New 345 kv Facilities in MISO RECB I filing (October 7, 2005) included a 20% postage stamp for 345 kv and above Baseline Reliability Projects Task Force began with a key concept that some portion of Network Upgrade costs should be allocated on a regional or postage stamp basis to capture the system-wide benefits of a Transmission System expansion MISO staff produced various analyses which demonstrated that when loads in a single Control Area are supplied only from Network Resources contained within that Control Area, the total Transmission System usage for such a transaction occurs on average 20% to 30% on systems external to the Control Area Filing included a compromise proposal to include a postage stamp component, provided that the component comprises no greater than 20% of the project costs, and that it is applied to Network Upgrades of 345 kv and higher voltage class 5
6 History of Postage Stamp Pricing for New 345 kv Facilities in MISO RECB II filing (November 1, 2006) included a 20% postage stamp for 345 kv and above Regionally Beneficial Projects (now MEPs) Task Force addressed to what extent should the allocation of costs reflect broad system-wide benefits of grid expansions, via a system-wide rate based on load shares (i.e. on a postage stamp basis ) as opposed to a more targeted allocation to specific transmission customers based on evaluations of long term beneficiaries The region-wide component was set a 20%, consistent with the level of postage stamp applied to Baseline Reliability Projects 345 kv and higher Additional analyses presented showed that when the loads of a single zone were served by all market generators in aggregate, the relative usage of others transmission systems was at least as high as the 20% figure in the RECB I filing 6
7 History of Postage Stamp Pricing for New 345 kv Facilities in MISO RECB III filing-phase I (July 9, 2009) modified cost allocation for generator interconnectionrelated network upgrades, eliminating the majority of the cost sharing for 50% of upgrade costs, but retaining a 10% postage stamp component for projects 345 kv and above 7
8 History of Postage Stamp Pricing for New 345 kv Facilities in MISO RECB III filing-phase II (July 15, 2010) established a 100% postage stamp for Multi- Value Projects (MVPs) Economic studies show that MVP-type projects will provide widespread regional benefits, including; substantial reductions in regional congestion costs; reductions in transmission losses, effecting significant, broadly shared cost savings; reductions in the region s installed capacity requirements, thus measurably reducing capacity costs throughout the region Broad regional cost-sharing for MVPs. avoids the disproportionate impacts that threatened continued access. to prime wind-power development areas MVPs will strengthen and enhance reliability across the integrated transmission system on which all regional load and exports rely 8
9 Is the current 20% Postage Stamp for MEPs 345 kv and above still appropriate? Yes. If there is any change considered, the postage stamp component should probably be a higher percentage of the total Networked facilities 345 kv and above provide regional benefits Reduction of Congestion and Production Costs is just one of many benefits, and the hardest to predict over the long term Examining APC results across model years and across futures shows changes in benefits and beneficiaries identifying beneficiaries is very sensitive to assumptions about many items that are inherently uncertain Over the long term, the usage or function of new networked 345 kv transmission lines that have been justified based on different types of initial drivers (reliability, economics or public policy) may not be very different All networked 345 kv lines are Multi-Value lines 9
10 Transmission 345 kv and above Pre kv Lines Pre kv lines Pre
11 Transmission 345 kv and above Existing, Approved and Planned 345 kv 2010 & after Pre kv Pre
12 Transmission 345 kv and above, by Type Existing, Approved and Planned 345 kv % P.S Baseline Reliability 20% Market Efficiency 20% Multi-Value 100% Zonal 0% Pre % 500 kv Pre % 12
13 The North-South MISO Divide Since MISO South was added to the footprint in December 2013, there has been much discussion about how to allocate costs across the new larger region Is the combined region too large, or the two sub-regions too disconnected for projects to provide region-wide benefits? Entergy Transition Period limits cost sharing for at least 5 years across both North and South MISO has proposed to eliminate postage stamp for MISO- SPP 345 kv Tariff Gap Interregional Projects Allocation of costs in MISO for these 345 kv projects would be 100% based on APC benefits It will be difficult to get consensus on tariff changes to treat the north and south differently Cost allocation is a zero-sum game 13
14 Benefits of a MISO-wide (North and South) Postage Stamp charge Avoids need to change existing tariff provisions Stakeholder consensus on cost allocation changes is often difficult to achieve It is hard to identify today if there would be a cost shift bias (and in which direction) over the long term Better Planning The more that all projects are paid for the same way, the more that the focus becomes the most efficient, least cost solutions to identified needs Unity Region-wide postage stamp best supports the vision of MISO as a single, strong RTO region 14
15 QUESTIONS? 16
New York s Transmission Challenges and Opportunities: An Overview
New York s Transmission Challenges and Opportunities: An Overview By: Dr. Matthew Cordaro 2012 is shaping up to be the year of the grid. Governor Cuomo has proposed an energy highway aimed at finding ways
More informationPJM LMP Market Overview
PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people
More informationINDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional
More informationComments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015
Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers On MISO South Market Congestion Planning Study September 18, 2015 In response to the MISO Staff s September 11, 2015 request
More informationBEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION
BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION Electric Generation Alternatives Analysis for Proposed ) Permit, to Install No. 341-07, for an Advanced Supercritical ) Case No. U-15996 Pulverized Coal Boiler
More informationThe Wind Coalition WIND ENERGY IS HERE TODAY AND IN AMERICA S FUTURE
The Wind Coalition 1 WIND ENERGY IS HERE TODAY AND IN AMERICA S FUTURE We will harness the sun and the winds and the soil to fuel our cars and run our factories. And we will transform our schools and colleges
More informationElectricity from the Power Plant To the Consumer
Electric Transmission Lines Electricity from the Power Plant To the Consumer The Nature of Electricity Electricity must be used as it is generated. Unlike other commodities, there is very little ability
More informationKey Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out
1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate
More informationA Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations
A Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations S. Fink, K. Porter, C. Mudd, and J. Rogers Exeter Associates, Inc. Columbia, Maryland NREL is a national laboratory
More informationTransmission Leadership. Teresa Mogensen Vice President, Transmission
Transmission Leadership Teresa Mogensen Vice President, Transmission 1 Safe Harbor This material contains forward-looking statements that are subject to certain risks, uncertainties ies and assumptions.
More informationTemplate for Submission of Comments on Convergence Bidding and Bid Cost Recovery
Template for Submission of Comments on Convergence Bidding and Bid Cost Recovery The CAISO is requesting written comments to presentations and documents discussed at the October 16 th Convergence Bidding
More informationMarket Solutions to Loop Flow
Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution
More informationAAPG 2011 Annual Convention & Exhibition April 10, 2011
Generator Transmission Grid Interconnection Guidelines AAPG 2011 Annual Convention & Exhibition April 10, 2011 Hala Ballouz, B.Sc., M.Sc. TAMU, P.E. President, Electric Power Engineers, Inc. Partner &
More informationGeneration and Transmission Interconnection Process
PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents
More informationWind Power and Electricity Markets
PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: info@uwig.org Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy
More informationTHE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS
THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS Presentation by George Gross University of Illinois at Urbana-Champaign Modernizing the National Electric Power Grid NSF Workshop November 18-19,
More informationThe Benefits of Electric Transmission:
A WIRES Report on The Benefits of Electric Transmission: Identifying and Analyzing the Value of Investments The Brattle Group Judy W. Chang Johannes P. Pfeifenberger J. Michael Hagerty July 2013 www.wiresgroup.com
More informationPortfolio Manager and Green Power Tracking
Building owners and operators can buy green power products as a way of reducing the environmental impacts associated with purchased electricity use in their facilities. The Environmental Protection Agency
More informationCompetition in Transmission Planning and Development:
Competition in Transmission Planning and Development: Current Status and International Experience Presented at EUCI Transmission Policy: A National Summit Washington, DC Prepared by Johannes Pfeifenberger
More informationSeptember 29, 2014. Docket No. ER14- -000 Amendment to CAISO FERC Electric Tariff to Eliminate Annual External Operations Review
California Independent System Operator Corporation September 29, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California
More informationTechnical and Institutional Barriers to the Expansion of Wind and Solar Energy
Technical and Institutional Barriers to the Expansion of Wind and Solar Energy Near term measures to foster development Prepared for Peter Fiekowsky, Citizen s Climate Lobby June 19, 2015 AUTHORS Patrick
More informationGenerator Interconnection and Deliverability Study Methodology Technical Paper
Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:
More informationNew York State of the Market System - NYISO Success Project
Auxiliary Market Products Additional Capacity Zones The NYISO and stakeholders are developing the rationale in 2010 for creating additional capacity zones, identified as a recommendation in the 2009 State
More informationRenewable Energy Transmission Planning Process (RETPP) Second Draft Final Proposal
Renewable Energy Transmission Planning Process (RETPP) Second Draft Final Proposal April 2, 2010 Second Draft Final Proposal Introduction The central objective of the ISO s proposed renewable energy transmission
More informationAddressing Affected System Impacts of Generator Interconnection: Processes and Principles. Stakeholder Call August 23, 2013 9:30 a.m. - 12:00 p.m.
Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Stakeholder Call August 23, 2013 9:30 a.m. - 12:00 p.m. 1. Introduction Mercy Parker Helget Sr. Stakeholder Engagement
More informationDemand Response and Energy Efficiency in the Midwest ISO. A Primer
Demand Response and Energy Efficiency in the Midwest ISO A Primer John Moore Bruce Campbell Kevin Murray September 28, 2010 1 Agenda Types of Midwest ISO Demand Response (DR). Products DR is eligible to
More informationGas Electric System Interface Study. PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO)
Gas Electric System Interface Study PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO) Table of Contents History Participating Planning Authorities (PPAs) / Study Region PPA Stakeholder Groups
More informationSection 4: Integrating Public Policy Drivers
Public Policy Drivers Section : Integrating Public Policy Drivers PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV Section.0: The Role of Public Policy in the RTEP Process Figure.1: Public Policy Drivers
More informationNatural Gas Pipeline Penalty Recovery Issue Paper
Natural Gas Pipeline Penalty Recovery Issue Paper September 16, 2014 Table of Contents I. Introduction and Background... 3 II. Scope of Initiative and Plan for Stakeholder Engagement... 4 III. The Approved
More informationPerformance Metrics. For Independent System Operators And Regional Transmission Organizations
Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April
More information153 FERC 61,221 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DIRECTING REPORTS. (Issued November 20, 2015) TABLE OF CONTENTS
153 FERC 61,221 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Price Formation in
More informationMerchant Interconnectors
Merchant Interconnectors David Newbery EPRG Winter Research Seminar Cambridge 15 December 2006 http://www.electricitypolicy.org.uk Outline Strong pressure from EC to increase interconnection impeded by
More information1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting of initial version
Document History Version Date Revision Class Originator Section Update Details 1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 101. (Docket No. RM04-12-000; Order No. 668)
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 101 (Docket No. RM04-12-000; Order No. 668) Accounting and Financial Reporting for Public Utilities Including RTOs (Issued December
More informationNext Generation Gigabit WiFi 802.11ac
Next Generation Gigabit WiFi 802.11ac WHITE PAPER NEXT GENERATION GIGABIT WIFI - 802.11AC The first WiFi-enabled devices were introduced in 1997. For the first time, we were liberated from a physical Internet
More informationInstructions for use:
TRANSMISSION MONTHLY PROJECT PROGRESS REPORT INSTRUCTIONS FOR COMPLETION TEMPLATE Instructions for use: PURPOSE OF FORM: The Transmission monthly Project Progress Report form is to be used by the Transmission
More informationTRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014. Senior Vice President Trans Grid Development & Portfolio Services
TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014 Senior Vice President Trans Grid Development & Portfolio Services The Senior Vice President Transmission Grid Development & Portfolio
More informationRwanda Natural Capital Accounting
Rwanda Natural Capital Accounting Presented for: Mrs. Fatina Mukarubibi PS Ministry of Natural Resources Date: June 1, 2015 Wealth Accounting and the Valuation of Ecosystem Services www.wavespartnership.org
More informationWinter 2013-14 Energy Market Assessment Report to the Commission
Winter 2013-14 Energy Market Assessment Report to the Commission Docket No. AD06-3-000 October 2013 Disclaimer: The matters presented in this staff report do not necessarily represent the views of the
More informationEXHIBIT PH-1. TEXAS CREZ AND LONG TERM NEEDS, A COMPREHENSIVE TRANSMISSION PROPOSAL BY ELECTRIC TRANSMISSION TEXAS, LLC (ETT) February 27, 2007
TEXAS CREZ AND LONG TERM NEEDS, A COMPREHENSIVE TRANSMISSION PROPOSAL BY ELECTRIC TRANSMISSION TEXAS, LLC (ETT) February 27, 2007 1 ETT CREZ TRANSMISSION PROPOSAL I. EXECUTIVE SUMMARY II. KEY ISSUES ADDRESSED
More information103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. Ontario Energy Trading International
More informationPG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES
Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage
More informationTehachapi Wind Energy Storage Project (TSP)
Tehachapi Wind Energy Storage Project (TSP) Peer Review Presented by Mr. Loïc Gaillac October 20, 2011 San Diego, CA 1 Outline Policy Challenges SCE s Position SCE Smart Grid Vision Project Description
More informationAnalysis and Selection of Analytical Tools to Assess National-Interest Transmission Bottlenecks Final Report
Analysis and Selection of Analytical Tools to Assess National-Interest Transmission Bottlenecks Final Report This work described in this report was coordinated by the Consortium for Electric Reliability
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER12-365-000
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Rock Island Clean Line LLC ) Docket No. ER12-365-000 ROCK ISLAND CLEAN LINE LLC S ANSWER TO COMMENTS OF INTERSTATE POWER AND LIGHT
More informationState Of California's Energy Bill
2750 Monroe Boulevard Valley Forge Corporate Center Audubon, PA 19403 James M. Burlew Counsel Telephone: (610) 666-4345 Fax (610) 666-8211 Email Address: james.burlew@pjm.com December 15, 2015 The Honorable
More informationRobust Adaptive Topology Control
Robust Adaptive Topology Control Mladen Kezunovic, PI Texas A&M University Kory W. Hedman, Co-PI Arizona State University January 14-15, 2015 System Integration Robust Adaptive Topology Control (RATC)
More informationAGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233
SA 2507 INTERSTATE POWER AND LIGHT COMPANY E&P AGREEMENT VERSION 1.0.0 EFFECTIVE 3/1/2013 AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 Agreement for Preliminary Engineering Design - MISO
More informationA market design to support climate policy
A market design to support climate policy Karsten Neuhoff, karsten.neuhoff@cpiberlin.org David Newbery, Christian von Hirschhausen, Benjamin Hobbs, Christoph Weber, Janusz Bialek, Frieder Borggrefe, Julian
More informationMINNESOTA POWER. Company Background: CapX2020 Transmission Plan
TRANSMISSION PROJECTS: AT A GLANCE MINNESOTA POWER MINNESOTA POWER Company Background: Minnesota Power, a division of ALLETE, provides electricity in a 26,000 square mile electric service area located
More informationBOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY
Background BOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY On April 11, 2012, the New York Energy Highway Task Force (Task Force) issued a request for information
More informationUplift in RTO and ISO Markets
i Staff Analysis of Uplift in RTO and ISO Markets August 2014 For further information, please contact: William Sauer Office of Energy Policy and Innovation Federal Energy Regulatory Commission 888 First
More informationGas transport tariffs calculation
Ad Hoc Expert Facility under the INOGATE project Support to Energy Market Integration and Sustainable Energy in the NIS (SEMISE) Gas transport tariffs calculation 1 TABLE OF CONTENTS 1. INTRODUCTION...
More informationEuropean Distribution System Operators for Smart Grids
European Distribution System Operators for Smart Grids Integrating electricity storage in distribution grids May 2016 Introduction Since the start of mass-electrification, the electricity industry has
More informationMemorandum. This memorandum requires Board action. Executive Summary
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: July 8, 2014 Re: Decision on the Delaney-Colorado
More informationERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update
ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update ERCOT Public October 16, 2015 ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update In August 2015, the U.S. Environmental
More informationGrid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations
Grid of the Future Integration of Renewables Energy Storage Smart Grid Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Current Power System Gen. Trans. Dist.Cust.
More informationwww.ecn.nl Alternative regulation and DSO business DG-GRID workshop, The Hague, 15 Nov 2006 Jaap C. Jansen models
Alternative regulation and DSO business models DG-GRID workshop, The Hague, 15 Nov 2006 Jaap C. Jansen www.ecn.nl Presentation outline Introduction to current DSO business model Key features of current
More information2010 STATE OF THE MARKET REPORT
2010 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market August 2011 TABLE OF CONTENTS Executive Summary...
More informationQUANTA ENERGIZED SERVICES
QUANTA ENERGIZED SERVICES Quanta s patented LineMaster robotic arm enables: Increasing utilization of existing transmission assets Safely reconductoring, ctoring rebuilding and replacing/adding lines and
More informationConvergence Bidding Stakeholder Conference Call
Convergence Bidding Stakeholder Conference Call Margaret Miller Senior Market Design & Policy Specialist Convergence Bidding Stakeholder Conference Call August 13, 2009 Agenda 1:00 1:15 - Plan for Stakeholder
More informationAppendix C-2. Entergy Services, Inc. June 8, 2016
Appendix C-2 Preliminary Due Diligence List (Existing Resources) For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016
More informationNew York Independent System Operator (NYISO)
New York Independent System Operator (NYISO) 2010 ISO/RTO Metrics Report 196 Section 5 NYISO Performance Metrics and Other Information The New York Independent System Operator ( NYISO ) is a not-for-profit
More informationData Center Life Cycle Analysis. Christophe Garnier EMEA Technical Work Group Member Schneider Electric
Data Center Life Cycle Analysis Christophe Garnier EMEA Technical Work Group Member Schneider Electric V3 The 3 Pillars of Sustainability Sustainability = meet the needs of the present without compromising
More informationCOMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011
COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and
More informationNV Energy ISO Energy Imbalance Market Economic Assessment
March 25, 2014 NV Energy ISO Energy Imbalance Market Economic Assessment NV Energy ISO Energy Imbalance Market Economic Assessment 2014 Copyright. All Rights Reserved. Energy and Environmental Economics,
More information2012-2016 Strategic Plan
2012-2016 Strategic Plan A Message from John R. Bear, President and CEO J. Michael Evans, Chairman of the Board of Directors MISO prides itself on continually fostering a transparent, effective stakeholder
More information152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM15-24-000]
152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 35 [Docket No. RM15-24-000] Settlement Intervals and Shortage Pricing in Markets Operated by Regional Transmission
More informationPJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations
PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region
More informationGeneration Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
More informationElectric Transmission Planning under FERC Order No. 1000
Electric Transmission Planning under FERC Order No. 1000 The Essentials: The Federal Energy Regulatory Commission (FERC) regulates interstate electricity commerce over long- distance transmission lines.
More informationTransmission Cost Allocation and Cost Recovery in the West
Transmission Cost Allocation and Cost Recovery in the West Presented at: Transmission Executive Forum WEST 2011 Strategies for Meeting the Transmission Needs in the West Presented by: Johannes Pfeifenberger
More informationRetail Electric Rates in Deregulated and Regulated States: A Ten Year Comparison
Retail Electric Rates in Deregulated and Regulated States: A Ten Year Comparison Published March 2008 1875 Connecticut Avenue, NW Washington, D.C. 20009-5715 202/467-2900 www.appanet.org Retail Electric
More informationUnderstanding the Impact of Transportation on Economic Development
A1A06: Committee on Transportation and Economic Development Chairman: Norman Foster, Minnesota Department of Transportation Understanding the Impact of Transportation on Economic Development RANDALL EBERTS,
More informationData Management Issues associated with the August 14, 2003 Blackout Investigation
Material derived from PNNL-SA-40401 Originally presented June 8, 2004 Data Management Issues associated with the August 14, 2003 Blackout Investigation Jeff Dagle, PE Chief Electrical Engineer and Team
More informationGas pricing and network access
OIL & GAS Gas pricing and network access Regional Gas Competence Seminar - Mozambique 22 September - 2015 Bert Kiewiet 1 DNV GL 2015 DNV GL - Bert Kiewiet 22 September, 2015 SAFER, SMARTER, GREENER About
More informationSunrun project policies guidebook
Sunrun project policies guidebook a handy guide about the projects we want (and the ones we don t) CSLB #969975; NJ #13VH07020300 Project Policies Guidebook Sunrun and our partner network put in service
More informationResponsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No.
1 2 3 4 Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 2000) comments regarding Transmission and Generation
More informationStatus of Demand Response in Europe. Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015
Status of Demand Response in Europe Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015 The Smart Energy Demand Coalition (SEDC) is an European Industry Association
More informationClean Power Plan: MISO Analysis ADEQ/APSC Stakeholder Meeting
Clean Power Plan: MISO Analysis ADEQ/APSC Stakeholder Meeting 8/28/2014 The generation fleet in MISO is being affected by timing, fuel prices and multiple phases of environmental regulations. MATS CSAPR
More informationU.S. Department of Energy Benefits of Demand Response and Recommendations
ii The Secretary [of Energy] shall be responsible for not later than 180 days after the date of enactment of the Energy Policy Act of 2005, providing Congress with a report that identifies and quantifies
More informationJob Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards
Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant
More informationConvergence Bidding Tutorial & Panel Discussion
Convergence Bidding Tutorial & Panel Discussion CAISO June 13, 2006 Joe Bowring PJM Market Monitor www.pjm.com Convergence Basics Day-Ahead Market basics Day-Ahead and Real-Time Market interactions Increment
More informationESDER Implementation and TeMix Comments
Stakeholder Comments Template Submitted by Company Date Submitted Edward G. Cazalet TeMix Inc. August 10, 2015 ed@temix.com 408-621-2772 General Comments TeMix respectfully suggests that this CAISO Proposal
More informationChanges in regulated electricity prices from 1 July 2012
Independent Pricing and Regulatory Tribunal FACT SHEET Changes in regulated electricity prices from 1 July 2012 Based on Final Determination, 13 June 2012 The Independent Pricing and Regulatory Tribunal
More informationRich Dewey Vice President, Information Technology & CIO New York Independent System Operator Budget and Priorities Working Group August 25, 2009
Infrastructure Master Plan Strategy Update Rich Dewey Vice President, Information Technology & CIO New York Independent System Operator Budget and Priorities Working Group August 25, 2009 Background The
More informationSHARED SERVICES OR OUTSOURCING?
SHARED SERVICES OR OUTSOURCING? Assessing Scope, Process Maturity and Organizational Design Kevin Lewis, ISG Director; CPA, CGMA www.isg-one.com INTRODUCTION As organizations grow in size and complexity,
More informationWorkshop B. 11:15 a.m. to 12:30 p.m.
Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30
More informationBENCHMARK YOUR TEST FUNCTION AGAINST A WORLD-CLASS TESTING ORGANIZATION
BENCHMARK YOUR TEST FUNCTION AGAINST A WORLD-CLASS TESTING ORGANIZATION PRACTICE OBJECTIVE This practice will enable you to conduct an assessment of your testing organization, using eight criteria that
More informationHow could suppliers and customers dramatically reduce future electricity bill? Professor Furong Li Chair in Electrical Power Systems
How could suppliers and customers dramatically reduce future electricity bill? Professor Furong Li Chair in Electrical Power Systems Measures to Reduce Bills 3000kWh/yr @ 17pence/kWh x = 500/yr Reducing
More informationThe Importance of Marginal Loss Pricing in an RTO Environment
The Importance of Marginal Loss Pricing in an RTO Environment Leslie Liu, Tabors Caramanis & Associates Assef Zobian, Cambridge Energy Solutions 50 Church Street Cambridge, MA 02138 Abstract This paper
More informationThe Unfinished Business of the Baby Boom Generation: Healthcare for the 21 st Century
Clinical Neuroscience Practice 2009 Annual Conference The Unfinished Business of the Baby Boom Generation: Healthcare for the 21 st Century John Kitzhaber, M.D. The Greatest Generation Won Second World
More informationChallenges And Opportunities For The NEM s Retail Electricity Market
Challenges and opportunities for the NEM s retail electricity arrangements Iain MacGill Associate Professor, School of Electrical Engineering and Telecommunications Joint Director (Engineering), CEEM Energy
More informationHow To Understand The Benefits Of The French Power Market Plan
Why Did the US (Mostly) Go With LMP? Benefits of Flow Based Allocation Benjamin F. Hobbs EPRG, University of Cambridge, UK DoGEE, Johns Hopkins University, USA Market Surveillance Committee, California
More informationBrochure Introducing HVDC
Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in
More informationJune 2016 Commission Meeting Summaries
June 2016 Commission Meeting Summaries These are summaries of orders voted by the Federal Energy Regulatory Commission at its June 16, 2016 public meeting. The summaries are produced by FERC s Office of
More informationRetail Electric Rates
Retail Electric Rates in Deregulated and Regulated States: Update Published April 2016 2451 Crystal Dr. Arlington, VA 22202 202.467.2900 www.publicpower.org Retail Electric Rates in Deregulated and Regulated
More informationPUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-
Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability
More informationBEPS ACTIONS 8-10. Revised Guidance on Profit Splits
BEPS ACTIONS 8-10 Revised Guidance on Profit Splits DISCUSSION DRAFT ON THE REVISED GUIDANCE ON PROFIT SPLITS 4 July 2016 Public comments are invited on this discussion draft which deals with the clarification
More information