1 Building over or close to a public sewer: Guidance notes

2 Building Over or close to a public sewer guidance notes The granting of planning permissions or building regulation approval does not give consent or permission to build over or close to Northumbrian Water assets. Failure to obtain formal approval from ourselves is illegal and may jeopardise the future sale of your property. Introduction Northumbrian water is strongly opposed to construction of any building over, or close to our sewers. This is to protect the sewer and the building from possible damage to each other and to ensure that access to the sewer is not adversely affected. We recognise that under some circumstances, preventing the construction of a building can restrict the improvement of an existing property. In such circumstances and by prior agreement with a property owner, we will accept single story extensions, domestic garages, conservatories and two story extensions to residential properties to be constructed over or close to a sewer, subject to certain conditions, described below Any pipes in our ownership are in good condition and any necessary repairs can be carried out by us (at our expense) before the building over takes place The pipes are properly protected during construction to avoid future maintenance issues for both our pipes and your property. A formal building over or money in lieu agreement is in place where needed to show that you have followed the necessary procedures to protect our drains and your home (and to protect your interests in any future sales of your property) Location of sewers Northumbrian water has over 16,000 kilometres of pubic sewers which have sometimes been laid within boundaries of properties which are shown on our record drawings. In addition to this we recently became responsible for the ownership and maintenance of thousands of kilometres of previously private sewers and lateral drains (pipes outside the property curtilage only serving one unit) which are not currently recorded on our mapping system. Many of these additional pipe lines run at the rear or side of domestic properties in addition to the public sewers and presence of such assets are likely to affect your proposals. If your property was built after July 2011 then your drains may have remained private. When you are requesting a site survey or submitting an application, please indicate the age of your property to allow us to take this into consideration. It is important that you determine the local drainage arrangements on your land and contact us early if you suspect that our drainage pipes may be affected by your proposals. You can find out whether there is a public sewer on your land by visiting any of our offices or the relevant Local Authority offices to view a copy of the public sewer records Alternatively you can request a copy of a plan showing the approximate location of public sewers by contacting our Property Solutions team on There is a nominal fee for this service, please refer to our charges scheme. Please note: Recently transferred sewers and drains are not currently marked on our records.

3 Build Over options If there is a sewer within 3 metres of your proposed works you should first consider one of the following options; Modify your plans to avoid the sewer, so that the buildings are at least 3 metres away. This is often the cheapest and easiest option. If the plans can not be modified, we would usually require the sewer to be diverted. Please refer to our diversion guidance and application form for further details which can be found on our website: Under no circumstances will building over be allowed where; The sewer is a pressurised pumping main An existing or proposed manhole would be located inside the building. The development is a new detached development or redevelopment. The sewer has a formal easement preventing build over. There is an existing water main. If having considered the alternatives your only option is to apply to build over, or close to a public sewer, you should apply using the build over application form. Build over process To determine whether or not your proposals may be affected by any of our pipes, please check the location of your proposed development and the surrounding garden to see if there are any physical signs of drains or sewers. For instance are there any manhole covers or inspection chambers visible? If you are still unsure as to whether you need to submit an application, we are happy for you to contact us and arrange a site visit by a member of our Clerk of works team. They will try and help determine the location of any sewers or drains and advise you on what to do next. They will also attend the site, if your builder discovers any pipe work or manholes after the works have started. Please contact Northumbrian Water on or to arrange this with us. If an application is required then it is recommended that this is made before you seek planning or Building Regulation approval and well in advance of works commencing on site. Once we have received your application we will carry out the following:- Acknowledge your application in writing and inform you whether your proposal is acceptable. If your application is not acceptable, we will inform you of the reasons why. Arrange appointments and attend site meetings where necessary. Arrange for a Closed Circuit Television Survey (CCTV) survey to be carried out of the affected sewer.

4 Assess your proposals against the criteria contained within Part H4 of the building Regulations This will determine whether there is a requirement for a building over or money in lieu agreement. Determine any requirements to modify our assets and determine who can carry out the works. Provide you with technical information on any protection measures specific to your proposals. Liaise with the Local Building control body to keep them updated on the progress of your application. CCTV survey In order to ensure that any pipes in our ownership are in good condition and any necessary repairs can be carried out by us (at our expense) you are required to have a CCTV survey carried out before the building over or close to a pubic sewer takes place. It is our policy, as recommended in the Building Regulations that we inspect the structural and service condition of the sewers prior to allowing any building to be placed above them. We believe this is essential to ensure that any defects are repaired to protect the long term structural integrity of the proposed building. This also protects you and our other customers served by the sewer from the risk of flooding as a consequence of the sewer failing at a later date directly under the extension. As the CCTV survey is required as a result of your proposed building works you are required to pay for the survey as part of your application fee. The CCTV survey will normally be carried out within 10 working days of us receiving your application and payment. Build over agreement or money in lieu A building over agreement or money in lieu payment will be required where the sewer is either: Greater than 3 metres deep. Greater than 225mm diameter in size. The proposed building is built over more than 6 metres of sewer length. There is no satisfactory diversion route. The purpose of a building over agreement is to set out the terms for allowing the building over, the liabilities upon each party with regard to future damage to the building or sewer and agreeing the rights of access to repair the sewer in the event of a collapse. The terms of this agreement can be viewed as quite onerous by some of our customers so we also offer an alternative arrangement in lieu of the legal agreement. In this case customers can pay a sum in lieu of the agreement which insures them against any future failure of the sewer and in this case all repairs to the sewer and consequential damage to the building would be covered by Northumbrian Water.

5 In the above circumstances you therefore have two options: Option 1 - Building over Indemnity Undertaking (Building over agreement) This undertaking provides you and future purchasers of your property reassurance that you have followed all of the correct procedures in order to protect your property and our sewer during your building over process. Such an Undertaking gives Northumbrian Water the option to move all or part of the building, if the sewer requires future repair or replacement, without paying compensation. Option 2 - Payment in lieu of such an Indemnity Undertaking. Such an Undertaking gives Northumbrian Water the option to move all or part of the building, if the sewer requires future repair or replacement, and Northumbrian Water will fully reinstate the building at our cost. Payment in Lieu is based on the floor area used for building regulation purposes. The charges associated with entering into a formal building over or money in lieu agreement is additional to the administration charges and given in the charges scheme section of this guidance and the building over application form. Site survey or inspections We are happy for you to contact us and arrange a site visit by a member of our Clerk of works team before submitting an application. Please contact Northumbrian Water on or to arrange this with us. As part of the application process, it may be necessary for us to carry out further site visits for the following reasons: To advise your builder on any protection measures specific to your proposals i.e. such as where sewers cross beneath any load bearing walls. To determine the requirement of any necessary minor alterations to the existing sewer. To help us provide you with any estimated costs for minor alterations on the existing sewer where we have not give permissions for your builder to carry out the works. To inspect works that have been carried out to protect existing pipe work. The charges for these site visits are included within the application charge, although there is an additional charge for us to inspect and approve minor alterations to our sewers that we have give your builder permission to carry out. We recognise that there may be a need for you to request a site survey to try and determine the location of any pipe work on land which you do not own as part of a conveyancing process. We are willing to carry out such a site survey although there will be an additional charge for this service and we will need to be satisfied that you have the consent of the land owner. Please refer to our charges scheme.

6 Making minor alterations and new connections Under no circumstances will building over be allowed where an existing or proposed manhole would be located inside the proposed building. Where feasible manholes should be removed and piped through or re-located on the line of the sewer outside the limits of the building. Northumbrian Water are prepared to allow your builder to carry out any necessary minor alterations on plastic manholes and pipes up to 225mm in diameter which are less than 1.05 metre deep. This will be subject to an additional administration and inspection charge to ensure the works meet the required standards. For any minor alterations necessary on our assets which are greater than 225mm in diameter or deeper than 1.05 metres, all works should be carried out by one of Northumbrian Water approved contractors, at your own expense. Costs will be given and agreed with you before work commences. If your proposals require a new connection to a public sewer, you will need to make a separate application to us. Please refer to our new connection guidance and application form for further details which can be found on our website: Foundation Design Foundations that are located above or within the vicinity of a sewer must be designed to ensure that no loads are imposed on the sewer, and to allow the sewer to be re-laid in the future, without the excavation undermining the building. Where the sewer is to be built over and is passing through the wall of the building, the foundation must bridge the sewer with a suitably designed reinforced lintel. There must be a minimum of 150mm between the underside of the lintel and the sewer, with some form of compressible material placed between the sewer and the lintel. The foundations on either side of the sewer must be constructed to a minimum level of 150mm below the sewer, and the foundation must be adequately separated from the pipe surround/bedding material. Where extensions or buildings are erected wholly to one side of a public sewer the foundation should be placed at an appropriate depth so no load is transferred to the sewer, where the load transference line is assumed to be forty five degrees from the underside of the foundation. When considering the depth of foundation an allowance should be made for the trench width and for any possible future maintenance requirements, which will depend on the size and depth of the sewer. Where a sewer is small diameter and one metre deep or less it should be possible to place the foundation as close to the sewer as practicable by placing a filler board/compressible filler between the foundation and the sewer. Any foundation placed within one metre of a sewer should be placed at least to invert level. Where sewers are greater than 1.80m deep the above will apply but a structurally designed reinforced concrete raft foundation or a piled foundation may also be suitable alternatives. Should you require any further information or assistance relating to foundation designs please contact us on:

7 Planning Permission and Building Regulations Please be aware that whilst you may have already obtained planning permissions and may have applied for building regulations approval for your proposed works, you still require our formal approval to carry out works within 3 metres of a public sewer The legislation that allows us to control the building over or close to a sewer is the Water Industry Act 1991 which imposes a duty on us to maintain all public sewers. Part H of the Building Regulations 2000 (2002 as amended) sets out the conditions that must be adhered to in order for the Building Control Authority or Approved inspector to allow the construction of a building over or close to public sewer. We work closely with both the local planning and building control authorities to determine our requirements. As part of our building over process, we will liaise with these to keep them updated on the progress of your application. Charges There are charges associated with making an application. These are given in the building over or close to application form and charges scheme. The level of charges will depend on the size of the sewer to be surveyed. There will be additional charges if there is a requirement for a formal building over or money in lieu agreement and/or we have allowed your builder to carry out minor alterations on our existing drainage system. The application charges include: Technical vetting and administration Sewer condition survey (CCTV) and report A site visit if needed. Liaising with the Local Authority in line with Building Regulations A cheque payable to Northumbrian Water Ltd. should be sent with the application to the address given. Filling in your application form The applicant s detail is the address to which you would like us to use for all communications. Please let us know whether the best way to contact you is by post or . In the other details section please confirm details of the existing drainage arrangements if known. This is something that our Clerk of works can help you with during a site survey. If you are aware of any access issues to your property that may affect our contractors ability to carry out the CCTV survey can you please note these on the form Using the information in the minor alterations section please indicate if there is a requirement for alterations giving a brief description of what is required and your preference

8 to who will carry out this work (Please remember that you only have a choice if the excavation work is no greater than 1.05 metres to the bottom of the manhole or pipe work). If there is a requirement for a formal building over agreement, please indicate whether you intend to enter into a building over agreement or you would prefer to make a payment of money in lieu of this agreement. Please indicate the method of payment you have chosen and provide us with your signature. If you prefer to your application form to us then please our New Development team at and we can send you electronic forms for completion. How to contact us Should you require any further information or assistance relating to building over or close to sewers please contact us on: You can write to us by post at: Building Control Team New Development Northumbrian Water Limited Leat House Pattinson Road Washington NE38 8LB Alternatively you can us at:

9 Northumbrian Water s build over or close to public sewer charges scheme Application Charges The current charges for a build over or close to a public sewer application are: Class I Sewer up to and including 150mm diameter II Sewer over 150mm diameter up to and including 375mm diameter III Sewers over 375mm diameter The application charges include: Technical vetting and administration. Sewer condition survey (CCTV) and report. Attendance on site to agree proposals. Liaising with the Local Authority in line with Building Regulations. Agreement Charges (These are in addition to the above) The charge for a building over indemnity undertaking Building over Agreement is The following charges are made in lieu of entering into a Building over Agreement. The charging bands are based on the floor areas used for building regulation purposes: Building Size (m 2 ) Single Storey Two Storey Less than 6 m m m , m , m , m ,592 More than 39 m 2 1,473 2,397 Site Survey To determine the location of sewers as part of conveyancing process is Inspection charges (This is in addition to the application charge) The charge for the administration and inspection of minor alterations made by householders own builders Initial Location Plan Enquiries (This will not include recently transferred drains and sewers) Copy of the sewerage records single plan A , A , A , A All the above charges include VAT where applicable.

10 Frequently asked questions Why do I need your approval if I already have planning permission and I have applied for building regulations approval? We need to approve your proposals if you intend to build over or within 3 metres of a public sewer. This is to protect the sewer and the building from possible damage from each other and to ensure access to the sewer is not adversely affected. The granting of planning permissions or building regulation approval does not replace the requirement for this consent. What happens if work is carried out without your approval? It is illegal to undertake works that may damage or interfere with our assets. If we become aware that you have carried out works prior to our approval we can take legal action. Without our approval you may have problems selling your property in the future. Why do I have to pay? We must recover our costs, to be fair to our existing customers, in dealing with something that an individual customer is proposing. Why do I have to pay for a CCTV survey of your sewer? It is important that we inspect the structural and service condition of the sewer prior to allowing any building to be placed above them. We believe this is essential to ensure that any defects are repaired to protect the long term structural integrity of the proposed. As the CCTV survey is required as a result of your proposed building works, you are required to pay for the survey as part of your application fee. What happens if the CCTV shows that the sewer is damaged? We will carry out any necessary repairs at our expense prior to allowing any building to be placed above or close to the sewer. My builder has found a pipe which was not shown on your public sewer records. How do I find out who is responsible for its protection? In 2011, we became responsible for the ownership and maintenance of thousands of kilometres of formally private sewers and lateral drains in addition to the public sewers which are shown on our record drawings. These are not mapped, so to help everybody understand who is responsible for the pipe, we would carry out a site inspection free of charge. Why can t my builder carry out minor alterations on your assets greater than 225mm diameter or deeper than 1.05 metres? It is our preference that all minor alterations are normally carried out by our own contractors to ensure the highest possible standards of construction and health and safety are applied. However, in instances where the sewers are small diameter and at such a shallow depth that we believe it may be appropriate for your own builder to carry out the work under our supervision we will allow you to do so. Why can t I build over an existing manhole? The building regulations does not allow manholes serving two or more properties to be located within buildings. The regulations state that access points should be in places where they are accessible for use in an emergency; such as when sewers may become blocked or collapsed and are causing flooding. They also require that any access points which are removed to allow

11 building works must be replaced by a suitable alternative which allows a similar level of access for maintenance purposes. Can I carry out piling works near sewers? Where piling works are to be carried out it is important to establish the exact location. We do allow piling works but is recommended that you discuss your proposals with us well in advance of works commencing on site. Will I have to change my foundation design if located above or near to a sewer? Foundations must be designed to ensure that no loads are imposed on the sewer and to allow the sewer to be re-laid in the future, without excavation undermining the building.

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

Policy Guidance Notes and Requirements

Policy Guidance Notes and Requirements Policy Guidance Notes and Requirements Building over/close to Public Sewers Domestic Extensions and Garages 1.0 Introduction Householders and developers planning to build close to or over a public sewer

More information

Building over or near a public sewer

Building over or near a public sewer Developer services Waste water Building over or near a public sewer Application form and Guidance notes www.wessexwater.co.uk/developerservices Developer Services DS 005 Guidance notes Building over or

More information

Application for the diversion of a Severn Trent Water sewerage asset

Application for the diversion of a Severn Trent Water sewerage asset Application for the diversion of a Severn Trent Water sewerage asset Form Office use only: Section 1: Applicant s details If there is more than one applicant, please attach name and contact details on

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

Please read these guidance notes carefully before completing the attached application form.

Please read these guidance notes carefully before completing the attached application form. Sewerage supply connections guidance notes Sections 106 to 109 Water Industry Act 1991 Please read these guidance notes carefully before completing the attached application form. Introduction This guide

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act Note Note. 1.

Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act Note Note. 1. Sewer diversion Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act 1991 NOTE: Please ensure all relevant sections of the application are

More information

Application Pack 7. How to apply for the Adoption of Existing Sewerage

Application Pack 7. How to apply for the Adoption of Existing Sewerage Application Pack 7 How to apply for the Adoption of Existing Sewerage Guidance Notes and Specification The provisions of the Water Industry Act 1991 (WIA91) take precedence over these notes. You may wish

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled

More information

Guide to working on Public Sewers

Guide to working on Public Sewers Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to

More information

Water Leakage & Your Responsibilities

Water Leakage & Your Responsibilities Water Leakage & Your Responsibilities Information & Guidance Contents 1. Introduction 2. Who is responsible for underground pipework? 3. Who is responsible for repairing the supply pipe if there is a leak?

More information

Application for a new connection to a public sewer

Application for a new connection to a public sewer Application for a new connection to a public sewer Application form and guidance notes Please detach and return the application form and retain our guidance notes for reference. Please complete all sections

More information

A guide to having a water meter HOUSEHOLD CUSTOMERS 1INS dwrcymru.com

A guide to having a water meter HOUSEHOLD CUSTOMERS 1INS dwrcymru.com A guide to having a water meter HOUSEHOLD CUSTOMERS 1INS 0013 Welcome Here at Dŵr Cymru Welsh Water, we don t have shareholders, so our focus is on looking after you - our customers and the communities

More information

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...

More information

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE 1 of 13 Affinity Water Limited CODE OF PRACTICE ON LEAKAGE LEAKAGE FROM DOMESTIC CUSTOMERS WATER SUPPLY PIPES Dated: 10 July 2014 1 INTRODUCTION 2 of 13 The Company is committed to a policy of water efficiency

More information

Application for the Alteration of a Gas Supply

Application for the Alteration of a Gas Supply Application for the Alteration of a Gas Supply SSE Enterprise Utilities is a trading name of SSE Utility Solutions Limited which is part of the SSE Group. The Registered Office of SSE Utility Solutions

More information

Measuring Drainage Below Ground in Accordance with ARM4:an Introductory Demonstration

Measuring Drainage Below Ground in Accordance with ARM4:an Introductory Demonstration Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2013-04-24 Measuring Drainage Below Ground in Accordance with ARM4:an Introductory Demonstration

More information

CODE OF PRACTICE FOR LEAKAGE (HOUSEHOLD AND NON-HOUSEHOLD CUSTOMERS)

CODE OF PRACTICE FOR LEAKAGE (HOUSEHOLD AND NON-HOUSEHOLD CUSTOMERS) CODE OF PRACTICE FOR LEAKAGE (HOUSEHOLD AND NON-HOUSEHOLD CUSTOMERS) ABOUT THIS CODE Issue No 7 November 2012 This Code of Practice, which has been approved by Ofwat, the regulatory body for the water

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES

GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES CUSTOMER SERVICES DIVISION GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES September 2000 FOREWORD This document provides guidelines for the structural

More information

YORKSHIRE WATER PROTECTION OF MAINS AND SERVICES

YORKSHIRE WATER PROTECTION OF MAINS AND SERVICES LNX-A4JHSS Received:3 November 05 Completed:5 April 06 YORKSHIRE WATER PROTECTION OF MAINS AND SERVICES. The position of Yorkshire Water Services Ltd (YWS) apparatus shown on the existing mains record

More information

Drainage. Information for those with problem drains

Drainage. Information for those with problem drains Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers

More information

Septic Tanks Definition & Types

Septic Tanks Definition & Types Septic Tanks Definition & Types Definition of Septic Tanks/Sewage Treatment Plant Definition A septic tank is a key component of the septic system, a small-scale sewage treatment system common in areas

More information

Dealing with leaks. Our code of practice: on leakage

Dealing with leaks. Our code of practice: on leakage Dealing with leaks Our code of practice: on leakage Our code of practice on leakage In this leaflet Here at Northumbrian Water we have a duty to all of our customers and to the environment to promote the

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

ARLINGTON COUNTY CODE. Chapter 18 PLUMBING AND GAS CODES

ARLINGTON COUNTY CODE. Chapter 18 PLUMBING AND GAS CODES Chapter 18 18-1. Title and Scope. 18-2. Definitions. 18-3. Availability of Codes. 18-4. Administration and Enforcement. 18-5. Registration of Contractors and Certification Requirements. 18-6. Permits and

More information

DISTRIBUTION CONNECTION

DISTRIBUTION CONNECTION DISTRIBUTION CONNECTION POLICY Page 1/15 TABLE OF CONTENTS 1 Introduction... 3 2 Acceptance of requests for a connection... 3 2.1 Who can request a connection... 3 2.2 How to request a connection... 4

More information

Leaseholders guide to making improvements to your home

Leaseholders guide to making improvements to your home Leaseholders guide to making improvements to your home This information is to help you decide whether you are eligible under your leasehold agreement to carry out improvements to your home. It also gives

More information

Additional Services Agreement. Part 3: Schedule of our requirements

Additional Services Agreement. Part 3: Schedule of our requirements Additional Services Agreement Part 3: Schedule of our requirements Schedule of our requirements Part A Water Services 1 All water services All connections to our water mains, including those used for construction

More information

Sewer Connection Application

Sewer Connection Application Sewer Connection This application form is to be used for connections to a public sewer for the following: Housing Units Site Accommodation Student Accommodation Guidance section Sewer Connection When completing

More information

Pipelaying powers on private land

Pipelaying powers on private land Pipelaying powers on private land Code of Practice page 1 - Code of Practice Contents Paragraphs Page number Introduction 1-6 3 Section one - Before the work begins Surveying and trial holes 7 4 Consultation

More information

Sewer flooding guidance and technical information.

Sewer flooding guidance and technical information. Sewer flooding guidance and technical information www.nwl.co.uk Sewer flooding is a very serious issue and Northumbrian Water is committed to reducing the risk of it occurring in our region. Whilst we

More information

Essential Water. Customer Charter

Essential Water. Customer Charter Essential Water Customer Charter Who is Essential Water? Essential Water is a division of Essential Energy and provides water supply services to over 20,000 people in Broken Hill, Menindee, Sunset Strip

More information

Sample Property PSL Precedent

Sample Property PSL Precedent Sample Property PSL Precedent WARNING: This document is a sample Property PSL precedent. It contains clauses for inclusion in a transfer of part (e.g. easements, covenants etc.). This document is not the

More information

Document Name: Tier 4 Engineering Guidelines for Subdivision and Development Standards Testing Record No: T4/0458 Commitment Statement: Water

Document Name: Tier 4 Engineering Guidelines for Subdivision and Development Standards Testing Record No: T4/0458 Commitment Statement: Water Document Name: Tier 4 Engineering Guidelines for Subdivision and Development Standards Testing Record No: T4/0458 Commitment Statement: Water Services Version No: 1 Issue Date: 3 September 2015 Page 1

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

CAPITAL WORKS GUIDANCE DOCUMENT

CAPITAL WORKS GUIDANCE DOCUMENT COMMUNITY BUILDINGS TRANSFER PROGRAMME CAPITAL WORKS GUIDANCE DOCUMENT This document has been prepared to assist and advise management groups of community buildings who are involved in Durham County Council

More information

Resourcing the world Leaks on supply pipes

Resourcing the world Leaks on supply pipes Resourcing the world Leaks on supply pipes and how they can affect you Fresh water is a precious and finite resource. It s coming under increasing pressure from growing populations, increased water use

More information

Leakage Code of Practice. Domestic Customers

Leakage Code of Practice. Domestic Customers Leakage Code of Practice Domestic Customers A Leakage Code of Practice Domestic Customers The advice in this Leakage Code of Practice is important and has been approved by the Water Services Regulation

More information

Guide to Conservatory Installation and Sewers

Guide to Conservatory Installation and Sewers ADVICE FOR TRADE AND CONSUMERS REFERENCE NUMBER 35.2 AUGUST 2011 Guide to Conservatory Installation and Sewers www.ggf.org.uk/publications GGF guide to the members of the Conservatory Association with

More information

SECTIONAL TITLE ACT IN LAYMAN S TERMS

SECTIONAL TITLE ACT IN LAYMAN S TERMS SECTIONAL TITLE ACT IN LAYMAN S TERMS INDEX 1. What is sectional title? 2. Registration 3. Types of schemes 4. Description of ownership 5. What to check 6. Sectional plan 7. Common property 8. Participation

More information

Guidance Notes: HIGHWAYS STATUTORY DUTIES AND VESTED POWERS

Guidance Notes: HIGHWAYS STATUTORY DUTIES AND VESTED POWERS Page 1 of 7 Guidance Notes: HIGHWAYS STATUTORY DUTIES AND VESTED POWERS If you are unsure about anything within these notes then please contact the Derbyshire County Council division on the details at

More information

MANX GAS LTD. Avoiding Danger from Underground Services

MANX GAS LTD. Avoiding Danger from Underground Services MANX GAS LTD Avoiding Danger from Underground Services Information and Advice from Manx Gas Edition Date: November 2011 MGD001 Rev 2 Contents 1 Introduction... 2 2 Consequence of damage to plant can include:-...

More information

Introductory Booklet for Sectional Titles

Introductory Booklet for Sectional Titles Introductory Booklet for Sectional Titles by Graham Paddock INDEX 1. What is sectional title? 2. Registration 3. Types of schemes 4. Description of ownership 5. What to check 6. Sectional plan 7. Common

More information

Homeowner building regulations application form

Homeowner building regulations application form Homeowner building regulations application form The Building Act 1984 The Building Regulations (as amended) For office use only Building Regulations Plan Number: This form is for work in connection with

More information

Your guide to sewer flooding

Your guide to sewer flooding Your guide to sewer flooding We re here to help 2 Severn Trent Water Your guide to sewer flooding This leaflet has been produced to give you further information on: What causes sewer flooding Who is responsible

More information

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Application No: 11/2196N Location: Proposal: Applicant: Expiry Date: K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Extension and New Store Mr Dan Mellor 17-Aug-2011 SUMMARY RECOMMENDATION Approve

More information

Getting connected. What to expect when getting a new gas connection or making a change to your gas supply

Getting connected. What to expect when getting a new gas connection or making a change to your gas supply Getting connected What to expect when getting a new gas connection or making a change to your gas supply How it all works 1 2 3 0 4 9 2 7 5 6 m 3 Our service pipe Emergency control valve Gas meter Gas

More information

Interim Regional As-Built Specifications. 23 October 2013

Interim Regional As-Built Specifications. 23 October 2013 Interim Regional As-Built Specifications 23 October 2013 Document Quality Control This document was developed for Capacity Infrastructure Services Ltd. Report Status v3 23 October 2013 Originator: Capacity

More information

A GUIDE TO YOUR REAL ESTATE PURCHASE

A GUIDE TO YOUR REAL ESTATE PURCHASE Settlements A GUIDE TO YOUR REAL ESTATE PURCHASE The following information is provided to help your purchase proceed with maximum efficiency, and by the due date for settlement. Please read this carefully

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

Type of Sewer Systems. Solomon Seyoum

Type of Sewer Systems. Solomon Seyoum Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of

More information

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Application No: 11/2196N Location: Proposal: Applicant: Expiry Date: K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Extension and New Store Mr Dan Mellor 17-Aug-2011 SUMMARY RECOMMENDATION Approve

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

Drainage Your Responsibilities

Drainage Your Responsibilities 1 County Borough Map 2 Drainage Your Responsibilities What do I do if a road gully blocks? Contact Neath Port Talbot Borough Council s Service First Team by telephone on 01639 686868 (24 hours). Land Drainage

More information

Charges for Water and Sewerage Services to Non- Household Premises 2015/16

Charges for Water and Sewerage Services to Non- Household Premises 2015/16 Charges for Water and Sewerage Services to Non- Household Premises 2015/16 CONTENTS 1 SCOPE OF THIS CHARGES SCHEME... 2 2 CONDITIONS APPLYING TO OTHER WHOLESALE SERVICES... 3 3 CHARGES FOR OTHER WHOLESALE

More information

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION N.B. WORK MUST NOT COMMENCE UNTIL LICENCE IS ISSUED June 2014 Roads Section

More information

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows: THE CORPORATION OF THE CITY OF GUELPH By-law (1993)-14515 A by-law respecting storm water disposal from private property in the City of Guelph, to amend By-law (1987)-12602 and to adopt Municipal Code

More information

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Applicant Details Name: Postal Address: Telephone Home: Work: Signed: Date: Proposed Contractor: Proposed Start Date:

More information

Guide to Selling and Buying your Home

Guide to Selling and Buying your Home Guide to Selling and Buying your Home Selling and buying property can be one of the most stressful periods in anyone s life. So, what can you do to ensure that the process goes as smoothly as possible?

More information

Conveyancing Guide Making your Home yours..

Conveyancing Guide Making your Home yours.. Conveyancing Guide Making your Home yours.. Introduction to Conveyancing Buying your new home can be a long and difficult process and the final step, the legal one, often seems the biggest. Buying a house

More information

Developer charges 2014/2015

Developer charges 2014/2015 Developer charges 2014/2015 Helping you calculate development charges 2 Severn Trent Water Developer Charges 2014/2015 Contents Section 1: Service connection charges 4-5 Section 2: Development enquiry/point

More information

Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation

Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation Contents The Contents of this Section are as follows: page 2.7.1 Introduction 2 2.7.2 Construction Conditions of Contract

More information

CITY PLANNING DEPARTMENT DEVELOPMENT APPLICATIONS AWARENESS GUIDE

CITY PLANNING DEPARTMENT DEVELOPMENT APPLICATIONS AWARENESS GUIDE CITY PLANNING DEPARTMENT DEVELOPMENT APPLICATIONS AWARENESS GUIDE January 2010 1. What is Development? Development is a very broad term that encompasses activities that result in a change of density, construction

More information

APPLICATION FOR A NEW DOMESTIC WATER SUPPLY CONNECTION

APPLICATION FOR A NEW DOMESTIC WATER SUPPLY CONNECTION APPLICATION FOR A NEW DOMESTIC WATER SUPPLY CONNECTION This application is to be used to apply for a new/replacement domestic water service connection(s) under the Water Industry Act 1991, to Northumbrian

More information

Repairing and rebuilding multi-unit residential buildings

Repairing and rebuilding multi-unit residential buildings Introduction The Ministry of Business, Innovation and Employment (MBIE) has released technical guidance on repairing and rebuilding multi-unit residential buildings in Canterbury. The guidance applies

More information

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and

More information

Land Development Manual. Updated December 2013

Land Development Manual. Updated December 2013 Land Development Manual Updated December 2013 Table of contents Contact us 1 Disclaimer 1 Terms and definitions 1 1 About the Land Development Manual 2 1.1 Introduction 2 1.2 Intended audience 2 1.3 Barwon

More information

Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991

Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991 Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991 Taking care of your waste water: It s part of our Blueprint for Yorkshire

More information

SWINDON ASSISTED LIVING HOUSING LOCAL DEVELOPMENT ORDERS. Statement of Reasons

SWINDON ASSISTED LIVING HOUSING LOCAL DEVELOPMENT ORDERS. Statement of Reasons SWINDON ASSISTED LIVING HOUSING LOCAL DEVELOPMENT ORDERS 8 th December 2015 Statement of Reasons Assisted Living Housing LDO 2: Land behind Bembridge Close / Beaufort Green, Park North 1 Context The Local

More information

Wholesale charges scheme

Wholesale charges scheme Wholesale charges scheme 2016-2017 1 Contents Introduction 3 Water supply wholesale charges scheme 2016 4 Introduction This booklet sets out the Wholesale Charges Schemes made by Thames Water Utilities

More information

DEVELOPMENT MANAGEMENT

DEVELOPMENT MANAGEMENT DEVELOPMENT MANAGEMENT Sub Heading Sub Heading 2 march 2012 PRE APPLICATION ADVICE SERVICE FOR PLANNING APPLICATIONS Introduction CONTACT DETAILS Telephone 0191 433 3416 / 0191 433 3426 Fax 0191 477 8422

More information

Before applying for a Road Opening Licence, please read and understand the following information.

Before applying for a Road Opening Licence, please read and understand the following information. Sept 2012 Before applying for a Road Opening Licence, please read and understand the following information. What is a Road Opening Licence? A Road Opening Licence (ROL) is a licence that allows the holder

More information

One Call Away. www.factor8ltd.co.uk

One Call Away. www.factor8ltd.co.uk One Call Away www.factor8ltd.co.uk Who We Are Factor 8 Ltd is a young, dynamic and reliable property management company which brings years of varied knowledge and experience together to produce a dedicated,

More information

Solo for Self Build. A guide to the cover

Solo for Self Build. A guide to the cover Solo for Self Build A guide to the cover Choosing the plot, arranging planning permission and finance, designing and building your dream home and finally moving in. Building your own home is, without doubt,

More information

BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION

BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION Buying or leasing commercial premises is often a large financial and long term commitment. It is always advisable

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993 AS AN OWNER BUILDER building work? What records should I keep? Is insurance required? W I need approval for? What do I need approval for? How do I obtain building work? How do I obtain approval? What records

More information

for the exercise of pipelaying powers on private land

for the exercise of pipelaying powers on private land ode of practice for the exercise of pipelaying powers on private land www.wessexwater.co.uk This booklet is our code of practice, prepared under section 182 of the Water Industry Act 1991 (the Act) and

More information

guide for obtaining new water and waste water services

guide for obtaining new water and waste water services You can write to us at: Customer Connections Scottish Water 419 Balmore Road Glasgow G22 6NU Please quote this reference code when contacting us: SWP&DS/DG2 04/08 Alternative formats of this leaflet can

More information

SECTION 4 EXCAVATION, TRENCHING AND BACKFILLING 4.01 SCOPE OF WORK

SECTION 4 EXCAVATION, TRENCHING AND BACKFILLING 4.01 SCOPE OF WORK 4.01 SCOPE OF WORK The work covered by this section shall consist of furnishing all materials, equipment and labor for the excavating, trenching, backfilling, and bore and jack required to install or repair

More information

Portsmouth Water. changing to a WATER METER

Portsmouth Water. changing to a WATER METER Portsmouth Water changing to a WATER METER 2014-2015 CONTENTS SECTION ONE - DOMESTIC CUSTOMERS 2 Can I transfer to a measured supply? 2 Can I revert back to an unmeasured supply? 2 How often will I receive

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

RURAL DRIVEWAY STANDARD

RURAL DRIVEWAY STANDARD RURAL DRIVEWAY STANDARD Scope This standard applies for rural or other land uses where there is no kerb and channel along the frontage of the property. This excludes industrial or commercial uses unless

More information

Householder Design Guide

Householder Design Guide Householder Design Guide Advice on making changes to your property Introduction The aim of this leaflet is to help residents who want to alter or extend their houses. The content contained within this

More information

LEAKING SUPPLY PIPE? YOUR GUIDE TO WATER SUPPLY LEAKS. You were out when we visited today.

LEAKING SUPPLY PIPE? YOUR GUIDE TO WATER SUPPLY LEAKS. You were out when we visited today. LEAKING SUPPLY PIPE? YOUR GUIDE TO WATER SUPPLY LEAKS You were out when we visited today. Check the back of this leaflet to find out why we called and what happens next. NW FSM3-1/15 INTRODUCTION Helping

More information

8. I have assessed that i do need building regulations approval, so what do i do next?

8. I have assessed that i do need building regulations approval, so what do i do next? 1. What are building regulations? 2. Is building regulation approval the same as planning permission? 3. Who administers building regulations? 4. Can I get retrospective consent? 5. When do I need building

More information

CITY OF MEMPHIS CITY ENGINEER S OFFICE PROCEDURES FOR STREET / UTILITY CUT PERMIT

CITY OF MEMPHIS CITY ENGINEER S OFFICE PROCEDURES FOR STREET / UTILITY CUT PERMIT CITY OF MEMPHIS CITY ENGINEER S OFFICE PROCEDURES FOR STREET / UTILITY CUT PERMIT Amended 3/07 APPLICABILITY: These procedures will apply where an individual desires to cut or dig into or open any pit

More information

Do I need planning permission?

Do I need planning permission? Do I need planning permission? Advice for householders on house improvements on house improvements Planning Services www.leeds.gov.uk/planning What does this leaflet cover? Certain minor changes to a house

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES

Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES This leaflet about drains and sewers has been prepared by Breckland Council and gives information and advice to private and commercial property

More information

Renovations Factsheet

Renovations Factsheet RENOVATIONS TO A LOT When proposing to undertake renovations to a lot, the Lot Owners should review this factsheet and we suggest you complete the accompanying application form and checklist. Upon completion,

More information

Plumbing and Drainage Act 2011 No 59

Plumbing and Drainage Act 2011 No 59 New South Wales Plumbing and Drainage Act 2011 No 59 Contents Part 1 Part 2 Preliminary Page 1 Name of Act 2 2 Commencement 2 3 Definitions 2 4 Plumbing and drainage work meaning 3 5 Responsible person

More information

DEVELOPER CHARGES 2015/16. Helpful information on new development connection types and charges.

DEVELOPER CHARGES 2015/16. Helpful information on new development connection types and charges. DEVELOPER CHARGES 2015/16 Helpful information on new development connection types and charges. CONTENTS SECTION 1: Service connection charges 4-5 SECTION 2: Development enquiry/point of connection assessments

More information

S P E C I M E N. Law Society Property Information Form (3rd edition) TA6. Address of the property. Full names of the seller. Seller s solicitor

S P E C I M E N. Law Society Property Information Form (3rd edition) TA6. Address of the property. Full names of the seller. Seller s solicitor Law Society Property Information Form (3rd edition) Address of the property Full names of the seller Seller s solicitor Name of solicitor s fi rm Address Email Reference number About this form Definitions

More information

APPLICATION FOR LANDLORDS CONSENT TO ALTERATIONS AND LICENCE

APPLICATION FOR LANDLORDS CONSENT TO ALTERATIONS AND LICENCE APPLICATION FOR LANDLORDS CONSENT TO ALTERATIONS AND LICENCE This form must be completed and returned to the address below, together with all relevant documentation as referred to. No fee is payable at

More information

SEWER OVERFLOWS. Information on plumbing blockages and wet weather overflows

SEWER OVERFLOWS. Information on plumbing blockages and wet weather overflows SEWER OVERFLOWS Information on plumbing blockages and wet weather overflows This guide has been designed to assist people who have experienced a sewer overflow. Queensland Urban Utilities provides water

More information

DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES

DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES WBCA 403 DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES A guide to assist those intending to install or who are involved in installing conservatories. Includes information about: conservatory and component

More information