1 Accelerating Organizational Project Management Maturity at Siemens Joseph A. Sopko, PMP, MSP, OPM3 Consultant Senior Consultant, Siemens Corporate Research, Princeton, NJ Kevin McDevitt, MSP PMO Director, Siemens Industry, Inc., Industry Automation Division, Springhouse, PA Session #ADV03

2 Agenda Introduction OPM Maturity Acceleration Initiative in Siemens US Case Study Siemens Energy and Automation Summary

3 Siemens Organization Executive Board Sectors Cross Sector Businesses Corporate Units Industry I Energy E Healthcare H Siemens IT Solutions and Services Industry Automation Fossil Power Generation Imaging & IT Drive Technologies Renewable Energy Workflow & Solutions Siemens Financial Services Building Technologies Osram Oil & Gas Energy Service Dia agnostics Cross Sector Services Corporate Technology CT Industry Solutions Power Transmission Mobility Power Distribution Regions Regional Clusters

4 Siemens Corporate Technology Idea Mega trends Profit Experts in Project, Program, and Portfolio Management PMO Development Six Sigma Implementations Business Consulting CMMI OPM3 People Competency Innovation Management

5 Global presence Americas 97, % 26% Germany 32% Europe, 23% CIS, Africa (excl. Germany) , , % 17% 28% 36% Asia, Australia, Middle East 79, % 21% As of September 30, 2008 Employees Revenue (billions of euros) Major facilities

6 More than 60% of turnover originates from project business

7 Challenges of the project business The project business for external customers has a significant importance for Siemens Challenges of the project business Project business is relevant for nearly all divisions and regions Numerous projects deteriorate during implementation phase Too many crisis projects reduce EBIT significantly More than 60% of the problems in the projects are caused in the early phases PM capabilities are regarded crucial within Siemens Siemens Initiative

8 Agenda Introduction OPM Maturity Acceleration Initiative in Siemens US Case Study Siemens Energy and Automation Summary

9 A Siemens initiative improves operational excellence in PM

10 Optimizing Quantitatively Managed1 Defined Managed Initial MPM assessment benefits from multiple models SEI Assessment & Capability Maturity Model Integration (CMMI ) + Recommendations of PM@Siemens + Elements of PMI: PMBoK and OPM3 Independent and external view Confidentiality Siemens wide standardized methodology + Siemens extensions: Practical experiences & feedback Comparable results = MPM Assessment Methodology References to best practices

11 MPM Process Model Process Project Management Planning & Controlling Supplier & Subcontractor Management Project Quality Management Project Configuration Management Change and Error Management Project Life Cycle Project Acquisition System Engineering Integration and Test Project Installation Process Management Process Definition and Maintenance Organizational Training Process and Product Measurement Process & Technology Improvement

12 MPM assessment process area alignment with OPM3 alignment with Process Project Management Project Life Cycle Process Management Planning & Controlling (L2/3) Supplier & Subcontractor Management (L2/3) Project Quality Management (L2/3) Project Configuration Management (L2) Change and Error Management (L2/3) Project Acquisition (L2/3) Process Definition and Maintenance (L3) System Engineering (L2/3/4) Organizational Training (L3) Integration and Test (L3) Process and Product Measurement (L4) Project Installation (L2/3) Process & Technology Improvement (L5) * Sub areas that have significant alignment with areas that have significant alignment with OPM3 * Sub areas that have partial alignment with areas that have partial alignment with OPM3

13 MPM assessment process area alignment with CMMI Process Project Management Project Life Cycle Process Management Planning & Controlling (L2/3) Supplier & Subcontractor Management (L2/3) Project Quality Management (L2/3) Project Configuration Management (L2) Change and Error Management (L2/3) Project Acquisition (L2/3) Process Definition and Maintenance (L3) System Engineering (L2/3/4) Organizational Training (L3) Integration and Test (L3) Process and Product Measurement (L4) Project Installation (L2/3) Process & Technology Improvement (L5) * Sub areas that have significant alignment with areas that have significant alignment with CMMI * Sub areas that have partial alignment with areas that have partial alignment with CMMI

14 MPM Evaluation of Process Theory and Practice Questions about Theory Questions about Practice OPM3 Capabilities defined? documented? available? Procedures Guidelines Methods Sample Documents Tools Procedures Guidelines Methods Sample Documents Tools well known? accepted? in use? Maturity level of documented process (Theory) Maturity level Total coverage of Theory and Practice Maturity level of implemented process (Practice)

15 MPM Maturity Scale Level: Characteristics: Benefits: M C I OPM3 S 5 Optimizing 4 Quantitatively Managed 3* Defined 2 Managed Continuous improvement utilizing statistical process control Systematic defect prevention processes Predictions of costs, deadlines, quality as well as project control are backed by statistically evaluated historical data Systematic management of reference solutions Organizational standard d process established Standard process owned by the organization Project specific tailoring rules in place Disciplined project management Process owned by project manager Process varies from project to project Quality 1 Initial Procedures not defined; ad hoc methods are used Success depends on few specialists Costs, quality, and deadlines are hardly predictable Risk According to Capability Maturity Model Integration (CMMI) of the SEI * MPM Level 3.0 is PM@Siemens Goal

16 Siemens CT has conducted more than 150 assessments globally

17 Agenda Introduction OPM Maturity Acceleration Initiative in Siemens US Case Study Siemens Energy and Automation Summary

18 Organizational Project Management (OPM) The application of knowledge, skills, tools, and techniques to organizational activities and project, program, and portfolio activities to achieve the aims of an organization through projects PMI Organizational Project Management Maturity Model (OPM3) Second Edition (2008)

19 Project Delivery vs. Maturity Level: 5 Optimizing 4 Quantitatively Managed Target Due Dates, Costs, s, Quality Benefits: Quality 3 Defined 2 Managed 1 Initial Target Due Dates, Costs, Quality Risk

20 Value of Increasing OPM Maturity Lower Non Conformance Costs, Better Quality, Better Bottom Lines Business Scalability Top Line Growth/Bottom Line Improvement Improved/sustained margins Employee/Project Management Effectiveness Ramp up Reliable Project Performance Predictability Less RED projects Improved and Measurable Project Performance Capability (SPI, CPI) Improved Employee Satisfaction, Ra amp up, and Retention Superior Customer Satisfaction => Competitive Edge Predictable delivery, costs and quality Less risk exposure Better Referrals Embed change and achieve benefits through Program Management

21 Where we were Initiative (2000) MPM Assessment Model (2002) OPM improvements managed as projects MPM assessment conduc cted Recommendations used to create improvement projects Re assessments to update measures and next steps Benefits are implied

22 Barriers to progress Resource limitations (financial and human) Lack of PMO structure and business relevance Lack of understanding of OPM maturity concept OPM not formally aligned with or measured against business objectives (e.g.. maturity level focused) Improvement programs were multiple projects without formal program management governance Business excellence programs often overlapped with OPM improvement efforts

23 What we learned Critical success enablers were not universally present Cultural differences cloudedd assessment and implementation execution Gap analyses and desk asses ssments may be better alternatives in early stages Project processes => Process management maturity => Business benefits

24 What we learned Improvement by comprehensive assessment alone may not be the best alternative: OPM Training needed What does good look like? Understanding the role of maturity models Focus on business objectiv ves (benefits) to be achieved Increase focus on businesss change management Assessments must be conducted at the proper organizational level

25 OPM Maturity Key Enablers To achieve maturity beyond Standardized): Executive Support Program Management Best Practices Organizational Project Management Office (PMO) Process Management Infrastructure MPM Level 2 (e.g. OPM3 Support the Business Units in establishing these success factors and accelerating organizational project management maturity.

26 OPM3 Organizational Enablers Organizational Project Management Policy and Vision Strategic Alignment Resource Allocation Management Systems Sponsorship Organizational Structures Competency Management Individual Performance Appraisals Project Management Training Organizational Project Management Communities Organizational Project Management Practices Organizational Project Management Methodology Organizational Project Management Techniques Project Management Metrics Project Success Criteria Benchmarking PMIS and Knowledge Management PMI Organizational Project Management Maturity Model (OPM3 )

27 Why use a program approach? Executive support encouraged by link to business benefits Formal program management organization and best practice methodology Commitment to and manage ement of business change MPM maturity assessment tool identifies gaps Maturity improvement initiatives are business change programs and should employ formal program management to deliver expected benefits.

28 Characteristics of Programs vs. Projects Program Management Achieves benefits Broad scope Broadly defined objectives Specifics not clear at the start Complex threads of work Often 3 5 years long Usually major investments Uses senior staff Project Board members Project Management Creates a capability Tightly focused Clear objectives Clear deliverables Often single threaded Often 3 months 2 years Can be small, cheap, fast Uses less senior staff Project Manager & teams Programs are not just large projects. They deliver enabling capabilities, embed business change, and achieve benefits Source: Core I.S.,

29 Program Management Model Sponsoring Group Senior Responsible Owner Program Manager Business Change Manager Program Office Delivering Capability Dossier of Projects Embedding Change Realizing Benefits Source: Managing Successful Programmes Standard, UK OGC, 2007

30 Why we need PMOs Organizational Project Management maturity is difficult to achieve without organizational level support, ownership, and governance Lead and manage the OPM improvement program PM Center of Excellence lesson ns learned and best practice models (e.g. OPM3, CMMI) Business performance measurement and benefits realization Process management and optimization (e.g. OPM3, CMMI, Lean Six Sigma) => ROI

31 Agenda Introduction OPM Maturity Acceleration Initiative in Siemens US Case Study Siemens Energy and Automation Summary

32 Successfully Defined Program Conducted SEP 07 NOV 08 Sponsored and led by Siemens Corporation US Business change program embed best practices to accelerate OPM maturity goal achievement (above MPM Maturity Level 3) Work with all three Siemens sectors in Industry, Energy, and Healthcare (over 20 Business Units from $10 Million to $4 Billion)

33 Successfully Defined Program An iterative approach Provide gap analyses, coaching, and training regarding organizational maturity Introduce and support formal Program Management best practices Leverage lessons learned from maturity assessment experience => key successs enablers

34 Successfully Defined Program Benefits Centralized funding model Utilization of OPMM subject matter experts increased by 3 4 times revitalized PM community in Siemens US Focus on business benefits for executive engagement removes financial barriers realization was a positive factor Business change approach involved the business as usual parts of the organizations => embed improvements and process ownership by business stakeholders Siemens Industry Automation was the early adopter

35 Siemens Energy & Automation Automation and Motion Division (SEA AMD) Preliminar ry Case Study Data

36 Sectors and Divisions: Industry Industry Divisions Drive Technologies Industry Automation Building Technologies Mobility Lighting (OSRAM) Industry Solutions Sectors Energy Divisions Fossil Power Generation Renewablee Energy Oil & Gas Energy Service Power Transmission Power Distribution Healthcare Divisions Imaging & IT Workflow & Solutions Diagnostics Page 36 July 2009 Copyright Siemens AG All rights reserved. Corporate Communications

37 Program Management Model Sponsoring Group Manages the project portfolio and achievement of benefits Program Manager (PM) Senior Responsible Owner (SRO) Business Change Manager (BCM) Sales, Customer Support, Operations, etc. Program Office Delivering Capability Embedding Change

38 Program Or ganizational Char t PM@IA/DT PMO IA & DT Policy, Requirements, Best Practices PM@AMD Program Sponsoring Group Sponsor: Senior Responsible Owner: Program Manager Successfully Defined Program (SDP) Siemens Corporate Research Process Automation Motion Control Simatic ITS Automotive Projects Sensors & Communication Sales BU Manager BU Manager BU Manager BU Manager BU Manager Business Change Manager (BCM) Business Change Manager (BCM) Business Change Manager (BCM) Business Change Manager (BCM) Business Change Manager (BCM) Business Change Manager (BCM) Technical Working Groups Technical Working Groups Technical Working Groups Technical Working Groups Technical Working Groups Technical Working Groups

39 Program Mandates Goals Vision Implement appropriate methodologies which achieves Maturity Project Management Level 3 in order to exceed customer expectation and manage AMD projects profitably with transparent results. Increased customer and employee satisfaction, managed profitable growth, and standard processes. Realized benefits from achieving goals: Standard processes and tools for creating project phase artifacts (outputs) Financial accountability through measurable results which keep a project on a positive course Greater value to our customers

40 Identifying and Defining Program Goals Defined Deliverables Standard Processes and Tools: Project Acquisition/Execution Change Management Information Management Measure Business Benefits (KPIs): Improve Customer Satisfaction Improve Project Margin Improve Delivery Reliability Improve Delivery Reliability AMD Project Management Office: Project process support Analytical tools and services

41 Program Flow Identifying the Program Defining the Program Managing the Phases Produce Program Brief Vision Statement Desc. of Benefits Risks Business Case Initial list of projects Assessment of Current State Develop of Program Preparation Plan Resources required Desc. of deliverables Schedule of activities Team members Establish Infrastructure Identify Stakeholders Develop Communication plans Develop Blueprint Develop Benefits Profiles (including dis benefits) Design project dossier Identify Phases Develop Governance Develop Program plan Confirm Business Case Prepare for 1st Phase Direct & Manage work Manage risk and issue Monitor and report out Transition and stable operations Delivering the Capabilities Engage stakeholders Align project with: Benefits realization Program objectives Governance: manage and control delivery Realizing the Benefits Embed benefits to business as usual Manage Pre transitions Transitions Post transitions Measure benefits Monitor and report benefit realizations

42 Identifying and Defining Phases Successfully Defined Program (SDP) Kickoff Meeting Maturity in Project Management (MPM) Gap Analysis Program Acceleration through Coaching and Teamwork (PACT) Workshop Program Management Training for Team Strategic Alignment with organization

43 Compliance Controls Phase 1: Project Sales Manage the Phases Deliver the Capability Global LoA Tool Training, Integration of DT global Work Breakdown Structure Project Calculations standardized on EBIT Develop & Deliver training for LoA, Project Acquisition, & Compliance Transition & Measure the Benefits

44 Phase 2: Organizational Enablers Design project KPIs across BUs Adopt Customer Satisfaction Surveys Process Create Change Management Tool Create Sharepoint Project Portal with TDPs Charter AMD Project Management office Adopt PM Profiles, Training, & Competency Mgmt MPM Theory (Desk) Assessment Manage the Phases Deliver the Capability Transition & Measure the Benefits

45 Phase 3: Project Execution Standardize Process Asset Libraries PM and Engineering processes Process Definition & Maintenance Process Create Process Asset Library Viewer with Tailoring for Project Categories Process Tailoring Definition MPM Comprehensive Assessment Manage the Phases Deliver the Capability Transition & Measure the Benefits

46 Improvement Results Program Benefits Achieved: MPM Level One MPM maturity level improvement achieved MPM Level 2006 MPM Level PM@AMD Program Customer satisfaction improved 5% Project Margins (delivered vs. booked) improved by 6% of Sales Project delivery reliability improved by 3% High commitment within the organization towards a continuous process improvement

47 Agenda Introduction OPM Maturity Acceleration Initiative in Siemens US Case Study Siemens Energy and Automation Summary

48 Summary Formal program management and OPM3 OEs are essential for OPM maturity improvement, relevance, and success: Executive support PMO business relevance Delivering benefits and business change Programs and related organizations (e.g. PMO) that are not business relevant do not survive.

49 Summary Establish the PMO at the correct organizational level with: PMO Charter with periodic review for relevance Program leadership best practices Link PMO goals to business strategy Conduct the OPM improvement program at the right organizational level Multiple maturity models (MPM, OPM3, CMMI, ITIL) are beneficial for system solution businesses

50 Summary OPM maturity improves business perform mance!

51 References Lebsanft, K., Strausser, G., Sopko, J. (2007). OPM3 utilization at Siemens. OPM3 Users Forum, PMI. PMI Global Congress 2007 North America, Atlanta, GA. Sopko, J., & Strausser, G. (2008, November). Case study Program management and the PMO critical success factors in improving organizational PM maturity at Siemens. PMO Symposium, San Antonio, TX. Keuten, T. (2009). OPM3 and CMMI Breaking new ground in organizational maturity, a White Paper prepared for the Project Management Institute. Newtown Square, PA: Project Management Institute. Sopko, J., & Husemeier, S. (2009, May). Improving organizational project management maturity: A Siemens Case Study. PMI Global Congress 2009 EMEA, Amsterdam, The Netherlands. Strausser, G. (2009, October). Business Change Management Using Program Management. PMI Global Congress 2009 North America, Orlando, FL.

52 Contact Information: Thank You! Joseph Sopko, PMP, MSP, OPM3 Consultant Telephone: Kevin McDevitt, MSP Telephone: Session: ADV 03

53 Contact Information Name: Joseph Sopko, PMP, MSP, OPM3 Consultant Phone: (W) (C) Session Number #ADV03

Improving Organizational Project Management Maturity A Siemens Case Study

Improving Organizational Project Management Maturity A Siemens Case Study Improving Organizational Project Management Maturity A Siemens Case Study Glenn Strausser Senior Consultant Siemens Corporate Research Princeton, NJ glenn.strausser@ieee.org Joseph Sopko Senior Consultant

More information

Information About Project Portfolio Management Analysis

Information About Project Portfolio Management Analysis Information About Project Portfolio Analysis Frank Westermann PMO15BR6 Corporate Technology Agenda Introduction Motivation Project Portfolio Approach Analysis of Project Portfolio Summary Strategy Level

More information

PMP Examination Tasks Puzzle game

PMP Examination Tasks Puzzle game PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in

More information

Implementing the CMMI within an Information Technology (IT) Organization. March 2005

Implementing the CMMI within an Information Technology (IT) Organization. March 2005 Implementing the CMMI within an Information Technology (IT) Organization March 2005 AGENDA Organization Overview Information Technology (IT) Diversity SEI CMMI IT Sponsorship Information Technology Process

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES) Developed by the Department of Health Informatics Directorate Informatics Capability Development

More information

BEST PRACTICES IN CHANGE MANAGEMENT

BEST PRACTICES IN CHANGE MANAGEMENT BEST PRACTICES IN CHANGE MANAGEMENT 2016 EDITION Executive Summary Best Practices in Change Management 2016 edition slide 1 THE LARGEST BODY OF KNOWLEDGE ON CHANGE MANAGEMENT Continuing to lead the discipline

More information

Project Governance & Controls

Project Governance & Controls Project Governance & Controls The PMI Perspective, Challenges, Initiatives and Opportunities Sean Whitaker, BA, MSc, MBA, PMP Overview This presentation provides an overview of project management governance

More information

Driving PPM Adoption Through Effective Change Management

Driving PPM Adoption Through Effective Change Management Driving PPM Adoption Through Effective Change Management Presenters: David Boghossian, Founder, PowerSteering Software Jay Hoskins, PowerSteering Business PPM Consultant Welcome! Thank you for joining

More information

Visual Enterprise Architecture

Visual Enterprise Architecture Business Process Management & Enterprise Architecture Services and Solutions October 2012 VEA: Click About to edit Us Master title style Global Presence Service and Solution Delivery in 22 Countries and

More information

Project Management Professional (PMP) Examination Content Outline

Project Management Professional (PMP) Examination Content Outline Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management

More information

ISO 21500: Did we need it? A Consultant's Point of View after a first experience. Session EM13TLD04

ISO 21500: Did we need it? A Consultant's Point of View after a first experience. Session EM13TLD04 ISO 21500: Did we need it? A Consultant's Point of View after a first experience Session EM13TLD04 Maria Cristina Barbero, MBA, PMI-ACP, PMP Nexen SPA PMI is a registered trade and service mark of the

More information

Aligning CMMI & ITIL. Where Am I and Which Way Do I Go? 2006 - cognence, inc.

Aligning CMMI & ITIL. Where Am I and Which Way Do I Go? 2006 - cognence, inc. Aligning CMMI & ITIL Where Am I and Which Way Do I Go? 2006 - cognence, inc. Agenda Where Am I? Current Situation Process Improvement Objectives How Do I Get There? CMMI ITIL Mapping, Commonalities, Differences

More information

Introduction to ITIL for Project Managers

Introduction to ITIL for Project Managers CSC NORTH AMERICAN PUBLIC SECTOR Introduction to ITIL for Project Managers May Chantilly Luncheon Linda Budiman, PMP ITILv2 & ITILv3 Process Architect ITIL Service Manager, CobiT certified 5/13/2008 8:08:45

More information

Project Management Office Best Practices

Project Management Office Best Practices Project Management Office Best Practices Agenda Maturity Models (Industry & PMO) PMO Areas of Expertise (Scale & Scope) Project Management Office Process Model Project Management Framework PMO Implementation

More information

Assessing the Appropriate Level of Project, Program, and PMO Structure

Assessing the Appropriate Level of Project, Program, and PMO Structure PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects

More information

Integrating Project Management and Service Management

Integrating Project Management and Service Management Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming

More information

Project Management Office Charter

Project Management Office Charter Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management

More information

Meet AkzoNobel Leading market positions delivering leading performance

Meet AkzoNobel Leading market positions delivering leading performance Meet AkzoNobel Leading market positions delivering leading performance BI Thema dag VNSG A Business Intelligence journey John Wenmakers AkzoNobel Leon Huijsmans Interdobs December 10, 2013 Agenda A Business

More information

Agile SW Development @ Siemens

Agile SW Development @ Siemens CON ECT INFORMUNITY, 24.3.2014 Agile SW Development @ Siemens Corporate Development Center Unrestricted Siemens Aktiengesellschaft Österreich 2013 All rights reserved. Eva Kišo ová - that s me Faculty

More information

Creating High Performance Project Teams

Creating High Performance Project Teams Creating High Performance Project Teams EDWARD BYERS, PMP, S SGB ONIT MANAGEMENT CONSULTING e d w a r d. b y e r s @ o n i t m c. c o m 2013 AGENDA 1. Describe the value of a systematized approach in building

More information

Complimentary Relationship Between ITIL and PMBOK

Complimentary Relationship Between ITIL and PMBOK CSC NORTH AMERICAN PUBLIC SECTOR Complimentary Relationship Between ITIL and PMBOK August Chantilly Luncheon Linda Budiman, PMP ITIL Business Process Architect ITIL Service Manager, COBIT certified 8/20/2008

More information

Benefits of conducting a Project Management Maturity Assessment with PM Academy:

Benefits of conducting a Project Management Maturity Assessment with PM Academy: PROJECT MANAGEMENT MATURITY ASSESSMENT At PM Academy we believe that assessing the maturity of your project is the first step in improving the infrastructure surrounding project management in your organisation.

More information

Improve Project Team Collaboration Using Microsoft Project Online

Improve Project Team Collaboration Using Microsoft Project Online Improve Project Team Collaboration Using Microsoft Project Online Presented by Steven Vowles, PMP, CISA, MCTS Senior Program Director, Infor Consulting Services Global PMO April 29, 2016 1 Discipline!

More information

Symbios Overview Lean Supply Chain Quality Improvement Customer Satisfaction Productivity Speed Cost

Symbios Overview Lean Supply Chain Quality Improvement Customer Satisfaction Productivity Speed Cost Symbios Overview Lean Supply Chain Quality Improvement Customer Satisfaction Productivity Speed Cost 2 Company formed in the UK by people from Ford Motor Company and AlliedSignal Brief History of Symbios

More information

Frank P.Saladis PMP, PMI Fellow

Frank P.Saladis PMP, PMI Fellow Frank P.Saladis PMP, PMI Fellow Success factors for Project Portfolio Management The Purpose of Portfolio Management Organizational Assessment Planning a Portfolio Management Strategy The Portfolio Management

More information

Agile SW Development @ Siemens

Agile SW Development @ Siemens CON ECT INFORMUNITY, 19.9.2013 Neue Software-Trends Agilität Prozesse & RE Agile SW Development @ Siemens Corporate Development Center Dr. Kurt Hofmann > 25 years Siemens ACT SW developer at PSE Team leader

More information

ITIL V3 AND THE SERVICE LIFECYCLE PART I THE MISSING COMPONENT

ITIL V3 AND THE SERVICE LIFECYCLE PART I THE MISSING COMPONENT ITIL V3 AND THE SERVICE LIFECYCLE PART I THE MISSING COMPONENT PLANVIEW INC. BACKGROUND IT departments continually have tremendous demands placed on them to manage new initiatives, projects, incidents,

More information

CMMi and Application Outsourcing

CMMi and Application Outsourcing White Paper CMMi and Application Outsourcing Abstract A lot of applications outsourcing providers in the market today are claiming for being assessed in different maturity levels of CMMi. But it is important

More information

Contrasting CMMI and the PMBOK. CMMI Technology Conference & User Group November 2005

Contrasting CMMI and the PMBOK. CMMI Technology Conference & User Group November 2005 Contrasting CMMI and the PMBOK CMMI Technology Conference & User Group November 2005 Wayne Sherer U.S. Army ARDEC Sandy Thrasher, PMP Anteon Corporation Agenda Purpose & Overview Considerations for Comparison

More information

The Standard for Portfolio Management. Paul E. Shaltry, PMP Deputy PM PPMS (2003-06) BNS02

The Standard for Portfolio Management. Paul E. Shaltry, PMP Deputy PM PPMS (2003-06) BNS02 The Standard for Portfolio Management Paul E. Shaltry, PMP Deputy PM PPMS (2003-06) BNS02 Purpose of this Presentation To provide information about The Standard for Portfolio Management Agenda Background

More information

PROJECT MANAGEMENT SALARY SURVEY 2014

PROJECT MANAGEMENT SALARY SURVEY 2014 ESI INTERNATIONAL ASIA PACIFIC PROJECT MANAGEMENT SALARY SURVEY 2014 An ESI International study SURVEY OBJECTIVES The inaugural Asia Pacific project management salary survey conducted by ESI International

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

ITIL Service Lifecycles and the Project Manager

ITIL Service Lifecycles and the Project Manager 1 ITIL Service Lifecycles and the Project Manager The intersection of IT Service and Project Delivery Presented to: Kansas City Mid-America PMI Chapter Mark Thomas January 17, 2011 1 Agenda 2 Introduction

More information

Selecting a project management methodology

Selecting a project management methodology VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:

More information

MGMT 4135 Project Management. Chapter-16. Project Oversight

MGMT 4135 Project Management. Chapter-16. Project Oversight MGMT 4135 Project Management Chapter-16 Project Oversight Project Oversight: defined as a set of principles and processes to guide and improve the management of projects. Ensures projects meet the needs

More information

Distributed and Outsourced Software Engineering. The CMMI Model. Peter Kolb. Software Engineering

Distributed and Outsourced Software Engineering. The CMMI Model. Peter Kolb. Software Engineering Distributed and Outsourced Software Engineering The CMMI Model Peter Kolb Software Engineering SEI Trademarks and Service Marks SM CMM Integration SCAMPI are service marks of Carnegie Mellon University

More information

Benefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja "Bezpieczny Projekt" WARSZAWA 11 maja 2010 r.

Benefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja Bezpieczny Projekt WARSZAWA 11 maja 2010 r. Programme Plan MIRACLE Benefits Benefits What is going on in here? I have no idea! 1 W A R S Z A W A R Z E S Z Ó W W R O C Ł A W 1 Fitting the pieces together How the APMG Product Set helps you manage

More information

What Every Project Manager should know about ITIL s Service Lifecycle Framework. Daniel Cayouette PMP - daniel@cayouette.

What Every Project Manager should know about ITIL s Service Lifecycle Framework. Daniel Cayouette PMP - daniel@cayouette. What Every Project Manager should know about ITIL s Lifecycle Framework Daniel Cayouette PMP - daniel@cayouette.com Sept 19, 2009 1 Presentation Objectives This presentation will provide a high-level view

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

Establishing Testing Knowledge and Experience Sharing at Siemens

Establishing Testing Knowledge and Experience Sharing at Siemens WWW.QUALTECHCONFERENCES.COM Europe s Premier Software Testing Event World Forum Convention Centre, The Hague, Netherlands The Future of Software Testing Establishing Testing Knowledge and Experience Sharing

More information

Driving Project Management Excellence at the New AT&T

Driving Project Management Excellence at the New AT&T Driving Project Management Excellence at the New AT&T Jennifer Birch, PMP Jim Schneidmuller, PMP AT&T PMCOE November 1, 2007 The AT&T PMCOE is a PMI Registered Education Provider Today s Topics Introduction

More information

Introduction to project management and concepts

Introduction to project management and concepts 37E01500 Project Management and Consulting Practice Introduction to project management and concepts Matti Rossi, Professor Dept. of Information and Service Economy Lecture 1, Mon 26.10.2015 Learning objectives

More information

SITA Service Management Strategy Implementation. Presented by: SITA Service Management Centre

SITA Service Management Strategy Implementation. Presented by: SITA Service Management Centre SITA Service Management Strategy Implementation Presented by: SITA Service Management Centre Contents What is a Service? What is Service Management? SITA Service Management Strategy Methodology Service

More information

Nydia González 1, Franck Marle 1 and Jean-Claude Bocquet 1. Ecole Centrale Paris, FRANCE

Nydia González 1, Franck Marle 1 and Jean-Claude Bocquet 1. Ecole Centrale Paris, FRANCE INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN, ICED 07 28-31 AUGUST 2007, CITE DES SCIENCES ET DE L'INDUSTRIE, PARIS, FRANCE Nydia González 1, Franck Marle 1 and Jean-Claude Bocquet 1 1 Ecole Centrale

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

OPM3 TM. Kevin Chui Vice President, PMI Hong Kong Chapter

OPM3 TM. Kevin Chui Vice President, PMI Hong Kong Chapter OPM3 TM Organizational Project Management Maturity Model Kevin Chui Vice President, PMI Hong Kong Chapter Translate strategy into success... Drive Business Improvement... Gain a Competitive Advantage!

More information

September 17, 1:00 PM. Dean Sorensen, Founder, IBP Collaborative

September 17, 1:00 PM. Dean Sorensen, Founder, IBP Collaborative BUSINESS FORECASTING AND INNOVATION FORUM 2015 September 17-18, 2015 Boston, MA September 17, 1:00 PM Track A Session: Transforming FP&A via Strategic, Financial & Operational Integration Improve forecast

More information

Central Agency for Information Technology

Central Agency for Information Technology Central Agency for Information Technology Development of a National IT Governance Framework Project Management Agenda 1 What is project management? Why it is important? 2 Leading practices 3 Project management

More information

Managing Successful Programmes

Managing Successful Programmes Managing Successful Programmes Syllabus 2011 (Version 2.0 - July 2012) 1. Introduction The Managing Successful Programmes (MSP) guidance explains the programme management principles, governance themes

More information

Key Leadership Behaviors Necessary to Advance in Project Management

Key Leadership Behaviors Necessary to Advance in Project Management Key Leadership Behaviors Necessary to Advance in Project Management Project / Program Management Research Lynda Carter, Kristin Tull and Donna VanRooy Specific behaviors need to be developed in order to

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

QUALITY CONSULTING SERVICES RAISE

QUALITY CONSULTING SERVICES RAISE QUALITY CONSULTING SERVICES RAISE RAISE with the experts With increasing competition companies are under pressure to cut costs, and many organizations are leveraging technology to address the problem.

More information

Project Management. Willis H. Thomas, PhD, PMP, CPT. Training Project Management Office (TPMO) Willis H. Thomas, PhD, PMP, CPT

Project Management. Willis H. Thomas, PhD, PMP, CPT. Training Project Management Office (TPMO) Willis H. Thomas, PhD, PMP, CPT Re-defining the Training & Development Structure Project Leadership Project Management Topics What we will cover during our discussion 1 2 What is the value of the TPMO? Why would an organization establish

More information

The Oracle Approach To ITSM Introducing The Customer Success Index

The Oracle Approach To ITSM Introducing The Customer Success Index The Oracle Approach To ITSM Introducing The Customer Success Index Barry Goodwin Vice President Global Customer Management Agenda Agenda Introduction To Oracle The Oracle Customer

More information

ORACLE NAIO Excellence combined with Quality A CMMI Case study

ORACLE NAIO Excellence combined with Quality A CMMI Case study CASE STUDY ORACLE NAIO Excellence combined with Quality A CMMI Case study softwaredi xide com www.qaiasia.com THE CLIENT Process and Quality are important for measuring improvement. Improvement means different

More information

Business Analysis Standardization & Maturity

Business Analysis Standardization & Maturity Business Analysis Standardization & Maturity Contact Us: 210.399.4240 info@enfocussolutions.com Copyright 2014 Enfocus Solutions Inc. Enfocus Requirements Suite is a trademark of Enfocus Solutions Inc.

More information

Project Management Institute IMPLEMENTING ORGANIZATIONAL PROJECT MANAGEMENT: A PRACTICE GUIDE

Project Management Institute IMPLEMENTING ORGANIZATIONAL PROJECT MANAGEMENT: A PRACTICE GUIDE Project Management Institute IMPLEMENTING ORGANIZATIONAL PROJECT MANAGEMENT: A PRACTICE GUIDE Library of Congress Cataloging-in-Publication Data Implementing organizational project management: a practice

More information

Between Trapezes: Maintaining Fidelity While Switching Midstream from a CMMI-Driven Waterfall to an Enterprise Lean/Agile Transformation

Between Trapezes: Maintaining Fidelity While Switching Midstream from a CMMI-Driven Waterfall to an Enterprise Lean/Agile Transformation Between Trapezes: Maintaining Fidelity While Switching Midstream from a CMMI-Driven Waterfall to an Enterprise Lean/Agile Transformation SEPG 2013 Chad Haggerty, John Maher, Alok Kumar, Girish Dandekar

More information

Dunja Hahn. Profile. Senior Consultant EDUCATION. 2010 Diploma in business administration (equivalent to Master)

Dunja Hahn. Profile. Senior Consultant EDUCATION. 2010 Diploma in business administration (equivalent to Master) Profile Dunja Hahn Senior Consultant Email: dunja.hahn@arcondis.com EDUCATION PROFESSIONAL TRAINING 2010 Diploma in business administration (equivalent to Master) 2008 Economic interpreter of the English

More information

Optimizing Organizational Measurement and Analysis ROI for Small Diverse Projects. Susanna Schwab July 2007

Optimizing Organizational Measurement and Analysis ROI for Small Diverse Projects. Susanna Schwab July 2007 Optimizing Organizational Measurement and Analysis ROI for Small Diverse Projects Susanna Schwab July 2007 Introduction EITS Measurement Program Objective: Define and deploy an integrated cost effective

More information

Project Manager Skills Benchmark SPONSORED BY

Project Manager Skills Benchmark SPONSORED BY Project Manager Skills Benchmark 2015 SPONSORED BY 2 Project Manager Skills Benchmark 2015 INTRODUCTION PM Solutions Research has been surveying organizations about their project management practices for

More information

Foundations of Project Management. Presented by: Kelly Baumer, MBA, PMP Mindy Rings, MBA, PMP

Foundations of Project Management. Presented by: Kelly Baumer, MBA, PMP Mindy Rings, MBA, PMP Foundations of Project Management Presented by: Kelly Baumer, MBA, PMP Mindy Rings, MBA, PMP August 18, 2014 Project Management Basics In the next slides we will cover: Basic project management terminology

More information

DTE Energy, Major Enterprise Projects Journey to Project Excellence. Victor Allen 18 November 2014 Session #PMO14BR20 1

DTE Energy, Major Enterprise Projects Journey to Project Excellence. Victor Allen 18 November 2014 Session #PMO14BR20 1 DTE Energy, Major Enterprise Projects Journey to Project Excellence Victor Allen 18 November 2014 Session #PMO14BR20 1 Objectives To understand what makes a PMO successful To understand the value of project

More information

October 7, 2011. Presented to. The PMI Washington DC Chapter. Pedro Agosto. Director of Client Services, XA Systems, LLC. pedro.agosto@xasystems.

October 7, 2011. Presented to. The PMI Washington DC Chapter. Pedro Agosto. Director of Client Services, XA Systems, LLC. pedro.agosto@xasystems. October 7, 2011 Presented to The PMI Washington DC Chapter By Pedro Agosto Director of Client Services, XA Systems, LLC pedro.agosto@xasystems.com Introduction Re-evaluating IT Services Today s Challenges

More information

Case Study of CMMI implementation at Bank of Montreal (BMO) Financial Group

Case Study of CMMI implementation at Bank of Montreal (BMO) Financial Group Case Study of CMMI implementation at Bank of Montreal (BMO) Financial Group Background Started in 1817, Bank of Montreal - BMO Financial Group (NYSE, TSX: BMO) is a highly diversified financial services

More information

Before getting started, we need to make sure we. Business Intelligence Project Management 101: Managing BI Projects Within the PMI Process Group

Before getting started, we need to make sure we. Business Intelligence Project Management 101: Managing BI Projects Within the PMI Process Group PMI Virtual Library 2010 Carole Wittemann Business Intelligence Project Management 101: Managing BI Projects Within the PMI Process Group By Carole Wittemann, PMP Abstract Too many times, business intelligence

More information

Contents. 2. Why use a Project Management methodology?

Contents. 2. Why use a Project Management methodology? Case Study Ericsson Services Ireland The APM Group Limited 7-8 Queen Square High Wycombe Buckinghamshire HP11 2BP Tel: + 44 (0) 1494 452450 Fax + 44 (0) 1494 459559 http://www.apmgroup.co.uk/ Q:\Users\Marie

More information

The Power of Metrics in Enterprise-wide Project Management

The Power of Metrics in Enterprise-wide Project Management The Power of Metrics in Enterprise-wide Project Management Presented By: DENNIS L. BOLLES, PMP PMI Great Lakes Chapter September 10, 2012 0 Speaker Introduction Dennis Bolles has more than 40 years experience

More information

ISO20000: What it is and how it relates to ITIL v3

ISO20000: What it is and how it relates to ITIL v3 ISO20000: What it is and how it relates to ITIL v3 John DiMaria; Certified Six Sigma BB, HISP BSI Product Manager; ICT (ISMS,ITSM,BCM) Objectives and Agenda To raise awareness, to inform and to enthuse

More information

San Francisco Chapter. Cassius Downs Network Edge LLC

San Francisco Chapter. Cassius Downs Network Edge LLC Cassius Downs Network Edge LLC ITIL History ITIL Books V3 Objectives Business Benefits of V3 V3 Changes Training & Certification V2 or V3? Summary 2 The 12 Rules 1. EXERCISE Rule #1: Exercise boosts brain

More information

Best of Everything ITIL, CMMI & Lean Six Sigma

Best of Everything ITIL, CMMI & Lean Six Sigma Best of Everything ITIL, CMMI & Lean Six Sigma SEPG 2008, Tampa FL March 2008 What will be covered? Key Issues / Problem Statement Understanding individual frameworks / methodologies Comparison of approaches

More information

Project Management and ITIL Transitions

Project Management and ITIL Transitions Project Management and ITIL Transitions April 30 th 2012 Linda Budiman Director CSC 1 Agenda Thought Leadership: Linda Budiman What is ITIL & Project Management: Applied to Transitions Challenges & Successes:

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Life Cycle Models, CMMI, Lean, Six Sigma Why use them?

Life Cycle Models, CMMI, Lean, Six Sigma Why use them? Life Cycle Models, CMMI, Lean, Six Sigma Why use them? John Walz IEEE Computer Society, VP for Standards QuEST Forum Best Practices Conference Track 3 What, Where, How & Why Monday, 24-Sep-07, 4:30 5:30

More information

An Implementation Roadmap

An Implementation Roadmap An Implementation Roadmap The 2nd Abu Dhabi IT s Forum P J Corum, CSQA, CSTE, ITSM Managing Director Quality Assurance Institute Middle East and Africa Dubai, UAE Quality Assurance Institute Middle East

More information

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services PERFORMANCE MANAGEMENT GOING AGILE Nicolle Strauss Director, People Services 1 OVERVIEW In the increasing shift to a mobile and global workforce the need for performance management and more broadly talent

More information

Analytics Strategy Information Architecture Data Management Analytics Value and Governance Realization

Analytics Strategy Information Architecture Data Management Analytics Value and Governance Realization 1/22 As a part of Qlik Consulting, works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics journey. Qlik Advisory 2/22

More information

NEW YORK STATE-WIDE PAYROLL CONFERENCE. Presented to:

NEW YORK STATE-WIDE PAYROLL CONFERENCE. Presented to: NEW YORK STATE-WIDE PAYROLL CONFERENCE Presented to: Felicia Cheek, Practice Leader Global Time to Pay Advisory 15 September 2014 Statement of Confidentiality and Usage Restrictions This document contains

More information

Wilhelmenia Ravenell IT Manager Eli Lilly and Company

Wilhelmenia Ravenell IT Manager Eli Lilly and Company Wilhelmenia Ravenell IT Manager Eli Lilly and Company Agenda Introductions The Service Management Framework Keys of a successful Service management transformation Why transform? ROI and the customer experience

More information

Enterprise Data Governance

Enterprise Data Governance DATA GOVERNANCE Enterprise Data Governance Strategies and Approaches for Implementing a Multi-Domain Data Governance Model Mark Allen Sr. Consultant, Enterprise Data Governance WellPoint, Inc. 1 Introduction:

More information

Strategic solutions to drive results in matrix organizations

Strategic solutions to drive results in matrix organizations Strategic solutions to drive results in matrix organizations Copyright 2004-2006, e-strategia Consulting Group, Inc. Alpharetta, GA, USA or subsidiaries. All International Copyright Convention and Treaty

More information

Project Management Change Management Procedure

Project Management Change Management Procedure Change Management Procedure Procedure # Description: Overview Outlines the steps for a Project Manager to manage change in an organization Objective To ensure that organizational change is managed in a

More information

An Introduction to Organizational Maturity Assessment: Measuring Organizational Capabilities

An Introduction to Organizational Maturity Assessment: Measuring Organizational Capabilities International Public Management Association Assessment Council An Introduction to Organizational Maturity Assessment: Measuring Organizational Capabilities Selena Rezvani, M.S.W. Objectives Define and

More information

Enterprise Architecture Process, Structure and Organization

Enterprise Architecture Process, Structure and Organization Organizational development Enterprise Process, Structure and Organization t-eam* - a framework derived from project experience Dipl.-Inform. Klaus D. Niemann Managing Director...act! consulting GmbH Glockengießerwall

More information

Capital Markets Day 2012 DHL Supply Chain. Bruce A. Edwards London, 24 May 2012

Capital Markets Day 2012 DHL Supply Chain. Bruce A. Edwards London, 24 May 2012 Capital Markets Day 2012 DHL Supply Chain Bruce A. Edwards London, 24 May 2012 What we said in the past... Capital Markets Day 2009 Capital Markets Day 2010 Continued to improve our financial metrics to

More information

Operational Excellence using Lean Six Sigma Amit Dasgupta

Operational Excellence using Lean Six Sigma Amit Dasgupta Operational Excellence using Lean Six Sigma Amit Dasgupta Amit Dasgupta 1 Contents Introduction to Operational Excellence Deployment Practice Our Services Amit Dasgupta 2 Operational Excellence using Lean

More information

Process Improvement. From the Software Engineering Institute:

Process Improvement. From the Software Engineering Institute: Process Improvement From the Software Engineering Institute: The Software Capability Maturity Model (SW-CMM, CMMI) (Especially CMMI V1.1 Tutorial) The Personal Software Process (PSP) (Also see The Team

More information

Measurement Strategies in the CMMI

Measurement Strategies in the CMMI Measurement Strategies in the CMMI International Software Measurement & Analysis Conference 9-14 September 2007 Rick Hefner, Ph.D. Director, Process Management Northrop Grumman Corporation One Space Park,

More information

A European manufacturer

A European manufacturer A European manufacturer Saving nearly USD19 million through improved workplace management Overview The need Balance the pressure for growth against aggressive cost reduction targets. The solution The organization

More information

METRICS TO HELP IMPROVE YOUR WORKFORCE PRODUCTIVITY

METRICS TO HELP IMPROVE YOUR WORKFORCE PRODUCTIVITY METRICS TO HELP IMPROVE YOUR WORKFORCE PRODUCTIVITY KEY RESULTS FROM MERCER 2013-2014 WORKFORCE METRICS DATABASE Tom Jacob, Mercer Ephraim Spehrer-Patrick, Mercer Milan Taylor, Mercer TODAY S PRESENTERS

More information

Developing and Implementing a Balanced Scorecard: A Practical Approach

Developing and Implementing a Balanced Scorecard: A Practical Approach RL Consulting Developing and Implementing a Balanced Scorecard: A Practical Approach White Paper Prepared by: Rick Leopoldi March 31, 2004 Copyright 2004. All rights reserved. Duplication of this document

More information

Rapidly Defining a Lean CMMI Maturity Level 3 Process

Rapidly Defining a Lean CMMI Maturity Level 3 Process Rapidly Defining a Lean CMMI Maturity Level 3 Process Zia Tufail, zia@hp.com, 301.233.4228 Julie Kellum, Julie.Kellum@hp.com, 404.731. 52.63 Tim Olson-QIC, Tim.Olson@qic-inc.com, 760.804.1405 2004 Hewlett-Packard

More information

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Project Portfolio Management: Metrics that Work James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Agenda PPM Interest What is Project Portfolio Management? Challenges Myths Benefits

More information

Maximize the synergies between ITIL and DevOps

Maximize the synergies between ITIL and DevOps BEST PRACTICES WHITE PAPER Maximize the synergies between ITIL and DevOps By Anthony Orr, Director of Service Management, Office of the CTO, BMC Software TABLE OF CONTENTS EXECUTIVE SUMMARY...............................................

More information

Chapter 1: An Introduction to Project, Program, and Portfolio Management

Chapter 1: An Introduction to Project, Program, and Portfolio Management CIS 586 IS Project and Change Management Chapter 1 Jongwook Woo, PhD jwoo5@calstatela.edu California State University, LA Computer Information Systems Department Chapter 1: An Introduction to Project,

More information

Process-Based Business Transformation. Todd Lohr, Practice Director

Process-Based Business Transformation. Todd Lohr, Practice Director Process-Based Business Transformation Todd Lohr, Practice Director Process-Based Business Transformation Business Process Management Process-Based Business Transformation Service Oriented Architecture

More information

CDC UNIFIED PROCESS PRACTICES GUIDE

CDC UNIFIED PROCESS PRACTICES GUIDE Document Purpose The purpose of this document is to provide guidance on the practice of Quality Management and to describe the practice overview, requirements, best practices, activities, and key terms

More information

Sales Enablement at Solvay Specialty Polymers. Vlerick Sales Conference June 3 2015

Sales Enablement at Solvay Specialty Polymers. Vlerick Sales Conference June 3 2015 Sales Enablement at Solvay Specialty Polymers Vlerick Sales Conference June 3 2015 COMPANY OVERVIEW Who are we? A major global player in Chemicals with compelling strengths Created by Ernest Solvay in

More information

ROI Building The Business Case For Professional Services Automation

ROI Building The Business Case For Professional Services Automation ROI Building The Business Case For Professional Services Automation Robert D. Anderson, CPA Director Specialized Services Hitachi Consulting Kimberly McDonald Baker Vice-President, Sales and Marketing

More information

Enterprise Service Management (ESM)

Enterprise Service Management (ESM) Enterprise Service Management (ESM) A Reference Model for Adopting and Adapting IT Best Practices Across and Enterprise itsm003 v.3.0 Agenda and Objectives What are ESM Best Practices? What is the ESM