White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M
|
|
- Jemimah Oliver
- 7 years ago
- Views:
Transcription
1 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M Version II December 2010
2 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 2 M CG O U G H S CO L L A B O R AT I V E D E L I V E R Y S Y S T E M McGough has a long-established and well-deserved reputation for establishing collaborative, partnering relationships with our owners and design partners at the inception of the construction process and then sustaining these relationships through completion of the project and beyond. Indeed, the exceptional quality of these relationships drives the volume of our repeat business more than three-quarters of our work. T Y P E S O F D E L I V E R Y S Y S T E M S There are two primary project delivery systems in the construction industry: collaborative delivery and hard-bid, or Design-Bid Build (DBB). The collaborative delivery approach differs significantly from the design-bid-build model. DBB requires completion of project design before the contractor is selected. This is a significant disadvantage, because the contractor is not involved in the preconstruction process. This means that the contractor does not participate in value engineering, budgeting, constructability or design review. DBB also lengthens the project schedule and precludes fast-tracking of projects. In contrast, under the collaborative delivery approach, the contractor is selected early in the planning phase of the project and works intensively with the owner and design team to provide budget estimates, value engineering and scheduling input. The contractor establishes a Guaranteed Maximum Price (GMP) for the project when the design scope is well understood. This GMP includes some level of contingency to cover unanticipated changes in scope or unknown conditions that may exist when the GMP is established. When documentation for each major section of work is complete, the contractor competitively bids the work to the subcontractor community. For some portions of the work, McGough may provide added value by self-performing (see McGough s Self-Perform White Paper for a complete review of the benefits of self-performing work). The collaborative approach can be utilized within several delivery systems, including: Construction Manager (CM); Construction Manager Agent; Construction Manager at Risk (CMAR); Design-Build; Design-Assist or single point of responsibility; and Traditional General Contractor (A111). The above are sometimes collectively referred to as negotiated delivery systems.
3 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 3 TWO PRIMARY FORMS OF DELIVERY SYSTEMS COLLABORATIVE DELIVERY PROCESS CMAR and CM/GC (A111) CM Agent Design-Build Design Assist Single Point of Responsibility HYBRID APPROACHES LOW BID DELIVERY PROCESS Design-Bid-Build Lump Sum Contract Hard Bid Qualifications Based Selection and/or Competitive Fee/Rates Early Involvement of Contractor in Design Process Collaborative Budgeting/Scheduling Process Guaranteed Max. Price (GMP) with Contingency Contractor Holds Trade Contracts unless acting as CM Agent Open Book Approach May Use Pre-Qualified Vendors All Savings to Owner Ultimately Lower Project Cost Design Complete prior to Award Contract Documents Completed in Single Package Award based on Lump Sum Contract (lowest responsible bid) Change Orders Used to Increase Initial Bid throughout project GC and Subcontractors Keep all Savings K E Y B E N E F I T S O F T H E CO L L A B O R AT I V E D E L I V E R Y A P P R O A C H The nature of business today places emphasis on increasing quality, increasing the speed of delivery and on reducing cost. These factors have led most owners to consider new delivery methods when they are faced with construction projects. The method most owners including an increasing number of organizations in the public sector are selecting is the collaborative delivery approach. This delivery approach has become the industry norm for most private corporations and is fast replacing the design-bid-build delivery process used for public projects. It has been recognized by owners and industry experts as the delivery process that yields the most cost-effective, timely, and highest quality results. McGough has utilized a collaborative delivery approach for the vast majority of projects throughout our history. Our owners and industry partners have experienced the benefits that this delivery approach provides, including the following: 1. The collaborative delivery system delivers optimum value for the owner. The greatest opportunity to positively impact project costs occurs at the earliest stages of the project, during the design phase. The collaborative approach, unlike others, provides this benefit. Early involvement of the contractor favorably impacts the accuracy and quality of the project s design, budget, value engineering, and constructability. Conversely, as illustrated below, the cost for making changes
4 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 4 dramatically escalates after project design is complete. COST CONTROL BENEFITS COSTS Potential Savings Cost of Changes $ Programming Design Documentation Contract Documents Construction TIME Although the first cost estimates using the collaborative delivery approach are usually greater than DBB, the final cost of the project is generally lower. This results from several factors including fewer and less expensive change orders during the process. The other factors are: McGough competitively bids the materials and subcontractor components of the work, which generally includes more than 90 percent of construction costs. These are charged at actual cost, without mark-up. The remaining project costs are the contractor fee and the general conditions costs, which are typically competitively bid at the time of contractor selection. Additionally, all general conditions costs are treated as pass-through costs without mark-up. The owner pays only the actual costs incurred. Similarly, change orders, if any, are charged at actual cost with no mark-up; the DBB approach typically marks up change orders 15 percent (or more). The McGough collaborative approach returns 100 percent of any cost savings to the owner. Under the DBB approach, 100 percent of the cost savings are retained by the contractor. Under the McGough collaborative approach, the contractor operates according to an open-book process. The owner has access to actual project cost information at all times. As unused portions of the GMP and/or contingency are identified, adjustments can be made to project scope.
5 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 5 2. The collaborative delivery system provides faster project completion. Several key factors enable the contractor to complete projects faster under the collaborative delivery process. These include: The early involvement of the contractor allows fast-tracking and accelerated scheduling of the project, not possible in design-bid-build projects. Similarly, site work, including footings and foundations, can be completed before design is finalized. The flexibility of this approach permits phased design packages throughout the process. Conversely, with the DBB approach, design documents are generally done in a single bid package, which means that design packages cannot be phased and construction is delayed until design is complete. The flexibility of collaborative delivery also allows McGough to anticipate requirements that are not shown in incomplete documents and to respond to changes as the project design evolves. The diagrams shown at right compare the collaborative delivery timeline to the designbid-build (DBB) timeline. As you can see, under the DBB timeline, design must be complete prior to selection of contractor.this sequential phasing will most often lead to a longer schedule for completion of the overall project. Fast-tracking of projects is not supported under the DBB approach. PROJECT START COLLABORATIVE DELIVERY PROJECT TIMELINE SELECT ARCHITECT SELECT CONTRACTOR DESIGN PRECONSTRUCTION CONSTRUCTION SUBSTANTIAL COMPLETION DESIGN-BID-BUILD PROJECT TIMELINE PROJECT START SELECT ARCHITECT DESIGN SELECT CONTRACTOR CONSTRUCTION SUBSTANTIAL COMPLETION
6 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 6 3. The collaborative delivery system provides maximum owner control and leads to high quality results. Under the collaborative delivery approach, the owner maintains project control for the entire duration of the project. The owner can choose the level of project involvement they desire through each phase. The owner clearly outlines project goals (e.g., budget, schedule, quality, etc.), and is positioned to influence those goals and make informed incremental decisions from the commencement of the project through project completion. As an example, the process allows the owner to have significant involvement in evaluating and making decisions regarding the key building components that influence final project cost. These include site work, structure, building envelope, and mechanical and electrical systems. The key characteristics of the collaborative approach that ensure maximum owner control and flexibility are the following: This system is owner-focused, rather than profit-focused. Owners may choose their degree of involvement during each project phase. Owner involvement integrates the perspectives of the owner and the entire project team, which aligns owner goals with project results. This owner-focused approach allows owners to determine project goals budget, schedule, quality and to make adjustments throughout the entire preconstruction and construction process. The collaborative approach places a significant emphasis on achieving high quality results. Since the primary goal of this delivery approach is to meet or exceed the customer goals and expectations, the team manages the trade-offs between quality and cost to ensure an optimum balance is achieved. It produces early and credible cost information for owners, so that they can estimate final project costs and balance these against other project goals, such as quality requirements, programming elements and design parameters. It enables owners to evaluate and determine alternative construction components that influence project quality and cost and ultimately impact long-term operating expenses of the facility (e.g., structure, envelope, mechanical/electrical systems). It permits the owner, rather than the builder or project subcontractors, to control change orders, which reduces ultimate final costs. The collaborative delivery system enhances communication among project participants. A key advantage of this delivery system is the quality of communications it produces. Through all phases of the design and construction, the contractor partners with the owner, design team, and project consultants, Collaborative Delivery System White Paper, Version II, I, December
7 White Paper CO L L A B O R AT I V E D E L I V E R Y S Y S T E M 7 subcontractors, material suppliers and vendors to review project progress and make adjustments as necessary. The advantages this approach offers are: Collaboration is characterized by shared expectations and project goals, resulting in a trust environment that is established early and maintained throughout construction. It improves team communications regarding budget and design, and delivers earlier and better cost management direction to the architect and engineer, which reduces the project s design cost. It eliminates adversarial relationships and reduces the likelihood of litigation among project participants that typify the design-bid-build model. This is probably the single biggest reason that McGough has never been in litigation with an owner, design partner or subcontractor. P R O V E N R E S U LT S Researchers at Penn State University have studied the various delivery systems. Here are their findings: According to a 1999 research study completed by two researchers at Penn State University, there are measurable differences with respect to project cost and schedule when utilizing collaborative delivery approaches versus the DBB approach. The chart below summarizes their findings. COMPARISONS Design-Build vs. CM@Risk vs. Level of Metric Design-Bid-Build Design-Bid-Build Certainty Unit Cost 6.1% Lower 1.6% Lower 99% Construction Speed 12% Faster 5.8% Faster 89% Delivery Speed 33.5% Faster 13.3% Faster 88% This study confirms that the collaborative approaches are typically less expensive and faster than the Design-Bid-Build process.
Project Delivery Methods & Contract Types CSTM 102 Spring 2013
Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction
More informationEvaluating Project Delivery Options
Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager
More informationBuilding Capital Projects in Tough Times John Lynch, State of Washington
Building Capital Projects in Tough Times John Lynch, State of Washington Published as a joint effort of the National Association of State Facilities Administrators (NASFA) and the Associated General Contractors
More informationSchool Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
More informationHow to Write the Construction Management RFQ/RFP
2011-06-07 How to Write the Construction Management RFQ/RFP Setting Up a Project for Success Today's Objectives The Art of RFQ/RFP writing First things first Determining the optimum Project Delivery Method
More informationDesign-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
More informationRecommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector
Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build
More informationAN OWNER'S GUIDE TO PROJECT DELIVERY METHODS
AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS Advancing Professional Construction and Program Management Worldwide ACKNOWLEDGMENTS CMAA gratefully acknowledges the time and efforts of those who served as
More informationThe programming, design
Understanding Project Delivery for the Design and Construction of Public Buildings architecture The programming, design and construction of important public buildings require the coordinated efforts of
More informationProgram Management for School Construction
Program Management for School Construction Presented to: Pasadena Unified School District Board of Education January 13, 2009 Project Delivery Options Design Bid Build Design/Build Construction Management
More informationConstruction Management vs. General Contractor Method of Contracting POINTS OF VALUE OF THE CONSTRUCTION MANAGEMENT METHOD
Construction Management vs. General Contractor Method of Contracting POINTS OF VALUE OF THE CONSTRUCTION MANAGEMENT METHOD In an effort to take advantage of our opportunity to discuss with the Owner the
More informationiowa school construction best practices
iowa school construction best practices WHAT IS A DELIVERY METHOD? A delivery method is a way of assigning authority and responsibility to move a project from an idea to a functioning facility. Master
More informationWhat s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM
What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?
More informationAdvanced Water Treatment Facility Alternative Project Delivery A Better Way
Advanced Water Treatment Facility Alternative Project Delivery A Better Way Service Area = 420 Square Miles 43 Cities Population = 4 Million 720,000 acre feet used per year 40% Groundwater from local water
More informationREQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
More informationDESIGN IS GOOD BUSINESS
COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building
More informationLease-Leaseback 201:Lessons Learned in Dancing School. Our Agenda
Lease-Leaseback 201:Lessons Learned in Dancing School CASH Annual Conference February 26, 2013 Travis Kirk, Merced Union High School District Mark Quattrocchi, Quattrocchi Kwok Architects Glenn Gould,
More informationConstruction Delivery Methods for Texas school districts
Construction Delivery Methods for Texas school districts Pfluger Associates Architects, P.L.L.C. ARCHITECTS / PLANNING CONSULTANTS History Prior to 1995, public school districts were required to utilize
More information1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project
More informationLessons Learned/Best Practices: Case Study- Design-Build at SFO
Lessons Learned/Best Practices: Case Study- Design-Build at SFO Speaker(s): Clay Paslay Moderator Ivar Satero, SFO Steven Rule, Turner Bill Hooper, Jr., Gensler SFO s Delivery Options SELECTION TYPES Price
More informationNUCLEAR SUPPLY CHAIN SYMPOSIUM
NUCLEAR SUPPLY CHAIN SYMPOSIUM Canadian Contracting Models Darryl J. Brown Gowling Lafleur Henderson LLP November 10, 2015 Suite 1600 1 First Canadian Place 100 King Street West Toronto, Ontario Canada
More informationHow To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
More informationAn Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method
An Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method Reprinted with the permission of Construction Management Association of America, Inc. Copyright 2007 All Rights
More informationContractor s Estimation of Cost and Bidding Strategy. Construction Project Management_Kumar Neeraj Jha
1 Contractor s Estimation of Cost and Bidding Strategy Contents 1.1 Contractor s estimation and bidding process 1.2 Bidding models 1.3 Determination of optimum mark-up level 1.4 Bidding and estimation
More informationREQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
More informationRebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153
Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153 October 2011 E. Rod Davisson, Esq., Schottenstein Zox & Dunn Co., LPA 250 West Street Columbus, Ohio 43215 614.462.2700
More informationContracting Practices in Mega Projects
CEM 520 Term Paper Contracting Practices in Mega Projects EPC and EPCM A L I A B D U L L A H A L - S A L E M 2 0 0 3 4 2 5 1 0 Outline Introduction Types of Contracts Contracting Strategies The Difference
More informationOwner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
More informationREPORT TO THE UTAH LEGISLATURE. A Performance Audit of School Building Construction. November 2008. Number 2008-14. Audit Performed By:
REPORT TO THE UTAH LEGISLATURE Number 2008-14 A Performance Audit of School Building Construction November 2008 Audit Performed By: Audit Manager Audit Supervisor Audit Staff Tim Osterstock Wayne Kidd
More informationCM/GC Guidelines FOR PUBLIC OWNERS. A Joint Publication Building Your Quality of Life. AGC Publication Number 2912 NASFA Publication Number F-3007
CM/GC Guidelines FOR PUBLIC OWNERS AGC Publication Number 2912 NASFA Publication Number F-3007 A Joint Publication Building Your Quality of Life Building Your Quality of Life Nothing contained in this
More informationScottsdale Road Improvements, Phase 1
CITY AUDITOR'S OFFICE Scottsdale Road Improvements, Phase 1 October 30, 2015 AUDIT REPORT NO. 1509 CITY COUNCIL Mayor W.J. Jim Lane Suzanne Klapp Virginia Korte Kathy Littlefield Linda Milhaven Guy Phillips
More informationProject Organization. System and Project Management 1.040/1.401J Nathaniel Osgood
Project Organization System and Project Management 1.040/1.401J Nathaniel Osgood Center for Construction and Research Education Department of Civil and Environmental Engineering Massachusetts Institute
More informationSchedule Acceleration Techniques Using a CM
College of Engineering Schedule Acceleration Techniques Using a CM By PI: Dr. Jesús M. de la Garza, Vecellio Professor Graduate Student: Ms. Daniela Escobar Hidrobo Final Report September 1, 2006 Invent
More informationCM at Risk. process of design-bid-build as an established method of project delivery. a 3D/International essay
a 3D/International essay CM at Risk Management at Risk (CM at Risk), similar to established private sector methods of construction contracting, is gaining popularity in the public sector. It is a process
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13
More informationCONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS
CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS Senate Bill 914, ratified by the General Assembly December 6, 2001, made more changes to the public bidding and construction
More informationAGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing
More informationCommissioning Large Public Projects Using Construction Manager at Risk (CM@R)
Commissioning Large Public Projects Using Construction Manager at Risk (CM@R) Greg Cunningham, AIA Enovity, Inc. Synopsis Over the past ten years, an alternative method of project delivery has evolved
More informationConstruction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About
More informationNOTICE TO CM/GC Companies
NOTICE TO CM/GC Companies Facilities and Construction Management Jefferson County School District R-1 (Jeffco) is pre-qualifying Construction Manager/General Contractors for CM/GC services for a new K-6
More informationBest Practices and Trends in Design-Build and Construction Management at-risk from The Municipal Water and Wastewater Design-Build Handbook
Best Practices and Trends in Design-Build and Construction Management at-risk from The Municipal Water and Wastewater Design-Build Handbook Water Design-Build Council March 31, 2011 Kansas City, MO Presentation
More information6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
More informationTLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
More informationPuget Sound Emergency Radio Network: Project Schedule and Cost Risks
Puget Sound Emergency Radio Network: Project Schedule and Cost Risks Thomas Wood Tina Rogers November 10, 2015 Executive Summary Work to replace the aging Puget Sound Emergency Radio Network (PSERN) is
More informationHow to get value for money from service providers on major projects
How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the
More informationASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
More informationConstruction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida
Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida Young H. Kwak, Ph.D. 1 and Randall Bushey, P.E. 2 Abstract The traditional
More informationCOMMUNITY LIBRARY (SUNBURY) RFP for Construction Manager at Risk
Project Name: Addition to Community Library (Sunbury) Project Location: 44 Burrer Drive, Sunbury, Ohio 43074 Owner: Community Library Board of Trustees Address: 44 Burrer Drive, Sunbury, Ohio 43074 Project
More informationInfo for CM at Risk RFP Butterfly Conservatory and Genomics Classroom
Info for Butterfly Conservatory and Genomics Classroom 1. Introduction to the project The (CSC), located in downtown Hartford, is a non-profit organization dedicated to enhancing science education throughout
More informationA Guide to Building Delivery. Ready, Set, Build.
A Guide to Building Delivery Ready, Set, Build. Getting Started So You Want to Build a Building? For many individuals faced with the responsibility of administering the construction of a building, the
More informationAlternative Project Delivery Methods (APDM) Valley Schools Management Group
Alternative Project Delivery Methods (APDM) Valley Schools Management Group Introduction Bill Munch Tim O Brien Ken Carter David Cantelme Skip Brown bmunch@vsit.org (602) 677-1988 tobrien@vsit.org (602)
More informationREQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES Big Rapids Public Schools Building Program 2005 OWNER Big Rapids Public Schools 21034 15-Mile Road Big Rapids, Michigan 49307 PHONE: (231) 796-2627
More informationDesign-Build Options for Public Projects
Design-Build Options for Public Projects Mark C. Friedlander Schiff Hardin LLP TETRA TECH MPS Most Municipal Construction Design Bid Build OWNER A/E General Contractor Design Bid Build Reasons Why Municipal
More informationCAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ
INTRODUCTION All Capital Project Budgets have 2 basic components: Construction Fees, Project Management, and Administration This presentation looks at COST DRIVERS that impact these 2 components and COST
More informationOBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
More informationVerification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review
Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a
More informationON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS
ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ACC REAL ESTATE COMMITTEE PRESENTATION SEPTEMBER 17, 2009 SEAN T. BOULGER, ESQ. WILMER CUTLER PICKERING HALE AND DORR LLP I. Introduction
More informationComparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery
Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery By Bob Prieto Design Bid Build (DBB) and Design Build Finance Operate Maintain (DBFOM) project delivery differ
More informationOregon Public Contracting Coalition Guide to CM/GC Contracting
NOTE: REFERENCES TO ORS 279 AND BOLI REGULATIONS CONTAINED HEREIN DO NOT REFLECT ANY CHANGES OCCURING SUBSEQUENT TO THE PUBLICATION DATE. THE USER OF THIS DOCUMENT IS RESPONSIBLE FOR USING REGULATIONS
More informationATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
More informationThe Construction Management Delivery System An Architect s Point of View
Session 1421 The Construction Management Delivery System An Architect s Point of View Daniel Davis, AIA University of Hartford Abstract There are at least three different building project delivery systems
More informationBRG Look Back Study. November 30, 2015
BRG Look Back Study November 30, 2015 1 BRG Look Back Study 2 BRG Look Back Study Fully Independent, No Prior GLX History, No Conflicts Document Review and Analysis Interviews and Site Visit MassDOT/MBTA
More informationOP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for the administration of construction
More informationDesign Build Institute of America (DBIA)
Design Build Institute of America (DBIA) 1 D E S I G N B U I L D L E S S O N S L E A R N E D J O S É D. N U Ñ E Z, L E E D A P V I C E C H A N C E L L O R F A C I L I T I E S P L A N N I N G, M A I N T
More informationMajor Changes to Public Contracting and the CM/GC Delivery Method
Major Changes to Public Contracting and the CM/GC Delivery Method Jeremy Vermilyea Schwabe Williamson & Wyatt Oregon Public Contracting Code & Model Public Contract Rules Section 137-049-0690 The CM/GC
More informationThe Regents of the University of California
The Regents of the University of California Analysis of the Master University of California Controlled Insurance Program for construction projects with values over $25,000,000 Prepared by: Grace M. Crickette,
More informationConsidered: 05/24/2016
EXECUTIVE SUMMARY SANTA CLARA COUNTY CIVIC CENTER PROPOSED MASTER DEVELOPMENT AGREEMENT Revised May 2, 2016 County Team County, Office of Asset and Economic Development, Office of the County Executive
More informationIndependent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
More informationProfessional Practice Commission: March 2013. Alternative Project Delivery Systems
Professional Practice Commission: March 2013 Alternative Project Delivery Systems UIA Accord Building project delivery systems. Definition Building project delivery systems are defined as the contractual
More informationGENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
More informationC.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods
C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods Friday, December 3, 2010 9:00 a.m. to 3:00 p.m. Ontario Airport Radisson 2200 East Holt Boulevard
More informationRevised 4-13-2013 Subject to Change
HARVARD GRADUATE SCHOOL OF DESIGN Course Title: PRO 7415 Project Delivery Department of Architecture Lecture 4 credits Spring 2013 Time: Mondays, 3:00-6:00 pm Room: Gund 124 Instructor: Dr. Richard W.
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name Wellington New K-8 EM/MS Response Deadline
More informationLos Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director
Los Angeles Community College District PROGRAM MANAGEMENT SERVICES Terri Mestas Program Director CMAA Southern California Chapter February 13, 2015 1 LACCD Overview Established in 1969 Governed by seven-member
More informationCovance Construction Management Staffing Plan Chandler, Arizona
INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according
More informationREQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified
More informationAN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT. Enabling Project Success Under Any Delivery Method
AN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT Enabling Project Success Under Any Delivery Method Acknowledgments CMAA gratefully acknowledges the time and efforts of those who served as contributing
More informationPRINCIPAL ARRANGED INSURANCE PROGRAM
PRINCIPAL ARRANGED INSURANCE PROGRAM Kieran Lynch LL.B, M.Proj.Mgt Abstract This article provides an update on the works and construction liability cover provided by Main Road s principal arranged insurance
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: School District Board + OFCC Project Name Groveport Madison High School Response Deadline 10/17/2014 4:00pm local time Project
More informationPROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
More informationDocumented Evidence of Property Management Value, Part 3
Cover Article Value Based Asset Management Documented Evidence of Property Management Value, Part 3 By Robert J. McFarland, CPPM, CF, Hoosiers Chapter Part 3 of this series by Bob McFarland covers database
More informationAGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
More informationThe Total Cost of Ownership (TCO) of migrating to SUSE Linux Enterprise Server for System z
The Total Cost of Ownership (TCO) of migrating to SUSE Linux Enterprise Server for System z This White Paper explores the financial benefits and cost savings of moving workloads from distributed to mainframe
More informationUsing Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
More informationBLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE
CONSTRUCTION PRACTICE BLUEPRINT October 2014 www.willis.com PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS Owners of construction projects face many risk management challenges
More informationChecklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
More informationRequest for Qualifications
Request for Qualifications to provide Construction Management Services (CM@ Risk) to Carrollton Independent School System 106 Trojan Drive Carrollton, Georgia 30117 For Replacement Facilities for: Carrollton
More informationFINDING AND UTILIZING QUALITY CONSTRUCTION LEADS. Kenneth Borah, Sr. Editor, CDCNews
FINDING AND UTILIZING QUALITY CONSTRUCTION LEADS Kenneth Borah, Sr. Editor, CDCNews FINDING AND UTILIZING QUALITY CONSTRUCTION LEADS Several years ago, the Associated Builders & Contractors surveyed their
More informationAIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
More informationReduce Capital Cost Overruns with Repeatable Engineering Designs
WHITE PAPER Reduce Capital Cost Overruns with Repeatable Engineering Designs by Ron Beck, Industry Marketing Director, Aspen Technology, Inc. The use of standardized and modular designs to reduce engineering
More informationConstruction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
More informationVIEWPOINT ARTICLE. Facility Management Outsourcing: Negotiating the Business Model. AgileOAK.com
Facility Management Outsourcing: Negotiating the Business Model 1 TABLE OF CONTENTS Executive Summary... 3 Discussion... 4 The Business Model... 4 Pricing Structure... 4 Allowable Pass-Through Expenses...
More informationSMACNA Participant Workbook Cash Flow. October 2013
SMACNA Participant Workbook Cash Flow October 2013 MANAGING THE LIFEBLOOD OF CONTRACTING CASH FLOW MAXIM CONSUTING GROUP OVERVIEW AGENDA Do you have a cash flow problem? Best Practices that improve cash
More informationEanes Independent School District
EANES INDEPENDENT SCHOOL DISTRICT 601 Camp Craft Road Austin, Texas 78746 Request for Qualifications Construction Manager at Risk Services Eanes Independent School District Construct a District Operations
More informationPricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
More informationOffice of the Inspector General
Office of the Inspector General Commonwealth of Massachusetts Gregory W. Sullivan Inspector General Experience of Massachusetts Public Agencies with Construction Management at Risk Under M.G.L. c. 149A
More informationINTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
More information5. Whether the timely completion of the project is critical to the university s ability to repay debt service or to meet grant obligations.
OP-B-11-C2 CONSTRUCTION MANAGER SELECTION PROCESS SPECIFIC AUTHORITY Sections 1001.74(28), 1013.46, F. S. OBJECTIVE To provide guidelines for the selection of construction managers. OVERVIEW This procedure
More informationREPORT TO UTAH STATE LEGISLATURE. A Performance Audit of Construction Management by Political Subdivisions
REPORT TO UTAH STATE LEGISLATURE Report No. 98-06 A Performance Audit of Construction Management by Political Subdivisions October 1998 Audit Performed by: Audit Manager Audit Supervisor Audit Staff Richard
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location
More information