Interfacing Earned Value and Risk Management

Size: px
Start display at page:

Download "Interfacing Earned Value and Risk Management"

Transcription

1 risk decisions 2 whitepaper Interfacing Earned Value and Risk Management by Val Jonas, CEO, Risk Decisions Group Lauren Bone, Managing Director, Bone Consulting Ltd management solutions

2 Val Jonas and Lauren Bone: Interfacing Earned Value and Risk Management whitepaper Interfacing Earned Value and Risk Management The difference between risks, issues and uncertainties Sound risk management process and robust earned value management application each offer the opportunity to improve project control and provide the project manager with reliable information on which to base proactive management decisions. All too often the disciplines are practised in isolation with focus on the mechanisms rather than the management value. They can compete with each other for resource and project management attention, rather than leveraging the advantages each has to offer. Instead, it should be recognised that they complement each other to deliver more holistic project management. This white paper explains how risk and earned value approaches work together during different phases of a project lifecycle, starting with setting the baseline, then change control as the project progresses, finally looking at how to improve Estimates to Complete. It demonstrates how to combine the two disciplines of Risk Management and Earned Value Management, in order to support better decision making, encourage more communication and increase chances of delivering a successful project. Introduction As separate disciplines, both Earned Value and Risk Management are valuable components of project management and control, needed to manage projects successfully. Even projects that don t undertake these disciplines in a formal way will nonetheless be following the basic elements of both disciplines: understanding what needs to be done, by whom and when, agreeing budgets, understanding and managing what might go wrong, measuring progress, estimating and forecasting outcomes. The disciplines of Earned Value and Risk Management simply apply a rigour to all of these activities. It s advisable to put in place the appropriate foundations for the application of Earned Value as early as possible in the project lifecycle. This includes identifying a product based Work Breakdown Structure (WBS), creating an effective schedule structure, as well as recording early basis of estimates and assumptions against preliminary scope definitions. While it is possible to draft these features at the outset, unfortunately application of Earned Value does not typically commence until the project concept is transformed into a scope of work. On the other hand, Risk Management commonly does commence early in the project lifecycle: during the concept phase it is used to inject realism into the planning process, challenging over-enthusiastic optimism and ensuring the plan is within an agreed level of risk appetite. For example, you may decide to take risks to bring a new product out on time, to beat a competitor to market; however, you must understand what level of risk you are taking and whether the organisation can bear the consequences. Understanding an organisation s capacity to proactively take risk is a very important part of the early decision making process, whereby the project is allowed to go to the detailed design and planning stages. Going forward, the role of Risk Management includes the top down identification of key sources of uncertainty and potential risk events, with associated risk responses. A risk budget is set and used to manage risk and keep the project on target, through to completion. Earned Value Management involves the establishment of a baseline that combines work, budget, schedule and responsibility. This baseline is then used to measure performance, understand variance, extrapolate likely outcomes and support action to manage variance back to the baseline targets. While each discipline is useful on its own, together they add up to more than the sum of the parts. The benefits of bringing the two together include: An improved baseline, which takes risk into account (including incorporation of risk response actions) More robust calculation of risk management budget (Management Reserve) Early identification of risks (threats and opportunities), leading to more proactive management Confidence that agreed risk response actions will be actively managed, because they have been explicitly included within the baseline More robust forecasts (Estimates to Complete) that include a view of risk In addition, for management, these benefits support a better appreciation of the significance of variance with regard to risk appetite and the challenge incorporated into the baseline. It also streamlines the governance of change involving identified risk and risk responses. This white paper goes through the steps required to implement Risk and Earned Value side by side, to take advantage of these benefits, improve project control and increase the chances of project success. Establish the baseline For a project to be successful, it will need to start with a realistic baseline. This requires the scope to be clearly defined, the associated work scheduled and budgets set. This is done in 3 stages: Adding an allowance first for uncertainty, then for known risk and finally for unknown (or emergent) risk. Adjusting the baseline based on uncertainty and risk appetite We start with identifying a time-phased budget for the known scope as planned in the schedule. (This might typically look like Figure 1). However, a risk analyst would want to consider optimistic or pessimistic scenarios when estimating the work, based on future uncertainties. They would do cost and schedule risk analysis, which results in a range of values instead of a fixed completion date and budget (this envelope of uncertainty is shown as a red box in Figure 2). 2 risk decisions 2

3 whitepaper Val Jonas and Lauren Bone: Interfacing Earned Value and Risk Management Figure 1. Typical Earned Value baseline The optimistic and pessimistic scenarios should be examined in order to extract any significant threats or opportunities that should be tracked and managed proactively via a risk register. Now, Earned Value must measure progress against a specific target and not a range. Therefore the envelope of uncertainty is used to decide where to set the baseline, based on your risk appetite. If you are confident that you can deliver against a challenging timescale and budget, then you should set an aggressive baseline closer to the line. In this optimistic case, we may expect variances to arise more often and be of greater magnitude as the control system warns us that the optimistic scenario has not been achieved. On the other hand, if we take a risk averse attitude and approve the pessimistic baseline, we should be very worried if we experience even minor variance, as this would indicate we are not even managing to achieve a worst case' scenario, with very little opportunity to redress the situation. In this case the ability of the system to provide us with an early management warning has been greatly diminished Pessimistic Figure 2. Using optimistic and pessimistic analysis to generate an envelope of uncertainty Typically, the baseline will be set at neither of the pessimistic or optimistic extremes, but instead will be set somewhere in the middle as shown in Figure 3. The reasons for choosing one baseline over another are many and varied, often more to do with politics and behaviour than good project management practice. Wherever the baseline is set, the management interpretation of variance must be based on an understanding of whether we have softened the system. Note: Your project contracting and delivery mechanism may also affect how aggressively you set your baseline. For example, you may decide to set an aggressive deadline and offer a bonus incentive if your contractor achieves the deadline. This baseline against which Earned Value metrics will be assessed (representing agreed work to be executed, with a target schedule and budget) is referred to as the, shown in Figure 3. Figure 3. Risk adjusted baseline (uncertainty) Pessimistic In this first stage, Risk Management has helped make the Earned Value baseline more robust and set an expectation for what level of variances might arise. Allowing for known risk in the baseline We now turn to a different type of work and expenditure the kind that arises from future uncertain scenarios and risk events that are not covered in the scheduled baseline. An amount of budget and time needs to be set aside for known risk, a stated set of events or future scenarios which will affect your ability to deliver the project scope, for which likelihood and impact information has been evaluated. For example, this could be an analysed risk for the requirement of re-work to achieve agreed quality; or it may be that you need to execute a second trial because the original one failed to prove a requirement. Both of these examples would be regarded as in-scope risks; whereas, additional design that results in increased functionality not included in the original scope would not be allowable. A statement of known risk is established and (usually) recorded in a risk register, initially without risk responses. A preliminary risk budget is calculated, based on an overall analysis of the probability and impacts of all known risks. This is shown as the yellow band in Figure 4. Cost-effective risk response actions now need to be identified, and the ones that are approved are then transferred into the Earned Value baseline. Note that transfer of work (risk response action) into the baseline results in an increase in the baseline scope and budget, shown by the red arrow in Figure 4. This is normally accompanied by a risk decisions 2 3

4 Val Jonas and Lauren Bone: Interfacing Earned Value and Risk Management Figure 4. Risk adjusted baseline part 2: adding risk response actions to the baseline reduction in residual risk, shown by the green arrow in Figure 4. By including the agreed risk response actions in the baseline, the Earned Value process will ensure that these actions are managed alongside the original scope. On-going management of these included actions as part of the risk discipline should be used to ensure that any schedule delay does not undermine the effectiveness of the action, for example, because it fails to mitigate the risk in a timely manner. So far, we have only considered budget, but we also need to ensure the extra work is incorporated into the schedule, which may result in extending project timescales. A more realistic view of the baseline is shown in Figure 5, which includes a provision for schedule risk in addition to the provision for the risk budget. Drawdown risk budget: Transfer work and budget in to the PMB Figure 5. with risk provision for both budget and schedule Note: Budget risk provision is often calculated as an expected value of risk (the simplest mechanism for calculating this is by summing the risks impacts weighted by each of their probability values). The provision for schedule cannot be calculated in such a simplistic way, as activities incorporated into the schedule will only impact on overall timescales if they are on the schedule s critical path. One way of recognising that risks are likely to arise and impact the schedule delivery is to set milestone target or promise dates. This technique incorporates an element of schedule reserve immediately after the dates indicated by the, without altering the baseline dates against which performance will be measured. This introduces a 'buffer' between the milestone promise dates (which may be contractual) and the baseline target dates. Schedule Buffers Milestone Promise Dates Figure 6. Schedule reserve inserted as buffers on milestone promise dates Once the budget and schedule provision for known risk is agreed, project governance will need to establish the mechanism by which this budget (both cost and schedule) can be drawn down. As long as a sufficiently robust risk process is in place to approve risk response actions, there is no reason why, subject to appropriate audit, this budget should require any higher level sign off than the project manager. Allowing for unknown (emergent) risk in the baseline While every endeavour should be made to identify known risks when setting the baseline, it will not be possible to foresee everything that may occur. Therefore, you will need to make an allowance for unknown risk, to cover things that emerge during project execution. The amount of provision you set aside must not be pure guesswork; instead, there are various methods you should employ to come to an acceptable and justifiable level of provision. Methods you might consider using include: expert opinion on current maturity of project definition the level of budget and schedule buffer required to satisfy your organisation s risk appetite consideration of previous out-turns for projects of this type The combination of the budget determined for known risk and that for emergent risk is callled the Management Reserve in Earned Value terminology. This is made up of both the yellow and grey areas shown in Figure 7. As new risk emerges, and is identified into the risk register, budget set aside for emergent risk will be drawn down into the provision for known risk. The risk will then be treated as any other known risk, including identifying response actions, with further transfer of budget into the baseline to cover the associated work as appropriate. Whereas it was suggested above that the draw down against provision for known risks can be managed within the project, it is possible that approval of budget for emergent risk may need to be the remit of the 4 risk decisions 2

5 whitepaper Val Jonas and Lauren Bone: Interfacing Earned Value and Risk Management project sponsor, at a higher level than the project itself. This is to ensure the right level of monitoring of unforeseen activities, partly to consider whether the project will still meet its overall completion targets, but also to avoid the temptation to use this grey area of budget to add unauthorised scope. This budget, combining the known work, known risks and emergent risks, provides a complete picture of the baseline budget, or Budget at Completion for the project. This may not be the same amount as the total project target cost; for example, if the project is to be delivered by an external contractor, then the final cost may also include a margin for profit. We do not cover any such extra costs in this white paper. Change Management Provision for emergent risks Figure 7. Addition of provision for emergent risks Although setting a realistic baseline is fundamental to the success of any project, keeping the project under control as it progresses is equally important. This is where a sound Earned Value system plays a very significant role, by being a major enabler of project control. Earned Value not only measures actual performance against the baseline of agreed work, but by quantifying variance to that baseline it also provides information to plan corrective action as necessary. At the same time, risk management seeks to manage the inevitable changes that a project will experience. Risk management does this in two ways (a) Using proactive risk response actions to prevent or minimise the impact of risks (b) Using reactive risk response actions to recover as quickly as possible from risks that happen New risk response actions approved for inclusion in the, utilise risk budget drawn down from known risk provision to budget for the additional work. Variances recorded through Earned Value monitoring occur in the main due to error in the estimates of work (value or time), whether this was original work or work added to respond to risks. Budget at completion Improved Estimates to Complete Although variances are a key indicator of progress and a measure of what volume of corrective action is required to get back on track, the periodic generation of an Estimates to Complete (ETC) is the mechanism by which management will get the complete picture of likely project outcome. Forecasts of Estimates to Complete using Earned Value data provide an understanding of the likely cost and schedule out-turn of the project based on performance so far. By including the impact of risk on the Estimate to Complete you will have a much more thorough assessment of the likely outturn of your project. The Estimate to Complete will provide a basis for confidence (or not!) in achieving the desired results. Having this level of robust forecast information from both disciplines enables you to make better decisions to: implement corrective actions to address performance issues; proactively take significant risks or opportunities; authorise pro-active strategies for dealing with significant risks; target budget and management attention on those areas that need it most and so on. Any bottom up Estimate to Complete should consider the same steps adopted in generation of the original baseline: this exercise must include not only a forecast against allocated work, but also forecasts for identified and emergent risk; it should also adopt the same risk appetite to enable effective comparison of the Estimate at Completion to the original budget. Conclusions Sound risk management process and robust earned value management application each offer the opportunity to improve project control and provide the project manager with reliable information on which to base proactive management decisions. All too often the disciplines are practiced in isolation with focus on the mechanisms rather than the management value. They can compete with each other for resource and project management attention, rather than leveraging the advantages each has to offer. Instead, it should be recognised that they complement each other and deliver more holistic project management. Implementing Risk and Earned Value together delivers more effective project control than each discipline being executed separately. Together they provide mechanisms for: improving the soundness of the by considering uncertainty and risk appetite; focussing attention on addressing what risk response actions should be included in the project from the outset; controlling change, particularly the change required for inclusion of effective risk responses; facilitating timely change by introducing the potential to pre-approve potential risk responses to known risks; ensuring all approved work is effectively performance monitored in the same system and providing an effective reporting drum beat for the re-assessment of risk and risk responses in line with performance reporting; and improving confidence in Estimates to Complete. Ultimately this facilitates project management and achieves improved project out-turns in terms of cost, schedule and quality. risk decisions 2 5

6 Val Jonas and Lauren Bone: Interfacing Earned Value and Risk Management Bibliography Association for Project Management 28 Interfacing Risk and Earned Value management, APM publishing, High Wycombe, Bucks, UK; ISBN-1: Jonas, V. and Welch, A (22) The integration of Risk and Earned Value Management, Proceedings of the 1st UK International management Symposium, presented in Bristol, UK, 3 October 22 Jonas, V and Welch, A (23) Risk and EVM: An Integrated Approach to handling Management Reserve, Proceedings of the 2nd UK International Management Symposium, presented in London, UK, 9 October 23 For further information visit: or contact Sandra Cohen at: Risk Decisions Ltd, Whichford House, Parkway Court, Oxford Business Park South, Oxford, O4 2JY Tel: sandra.cohen@riskdecisions.com European HQ For enquiries from the UK and mainland Europe. Risk Decisions Ltd Whichford House Parkway Court Oxford Business Park South Oxford O4 2JY United Kingdom For general enquiries: Tel: +44 () Fax: +44 () enquiries@riskdecisions.com For help desk support: Tel: +44 () Fax: +44 () support@riskdecisions.com management solutions

Portfolio Risk Management: aligning projects with business objectives to deliver value

Portfolio Risk Management: aligning projects with business objectives to deliver value risk decisions 2011 Portfolio Risk Management: aligning projects with business objectives to deliver value by Val Jonas CEO Risk Decisions Group and Susheel Chumber Professional Services Manager, Risk

More information

Five steps to Enterprise Risk Management

Five steps to Enterprise Risk Management risk decisions 2011 Five steps to Enterprise Risk Management by Val Jonas CEO Risk Decisions Group www.riskdecisions.com management solutions Val Jonas: Five steps to Enterprise Risk Management Five steps

More information

1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles

1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles 1. What is PRINCE2? Projects In a Controlled Environment Structured project management method Generic based on proven principles Isolates the management from the specialist 2 1.1. What is a Project? Change

More information

PLANNING FOR YOUR PROJECT

PLANNING FOR YOUR PROJECT PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations

More information

The Advanced Certificate in Performance Audit for International and Public Affairs Management. Workshop Overview

The Advanced Certificate in Performance Audit for International and Public Affairs Management. Workshop Overview The Advanced Certificate in Performance Audit for International and Public Affairs Management Workshop Overview Performance Audit What is it? We will discuss the principles of performance audit. The session

More information

Extending the Risk Process to Manage Opportunities

Extending the Risk Process to Manage Opportunities Extending the Risk Process to Manage Opportunities Dr David Hillson PMP FAPM MIRM Director of Consultancy, Project Management Professional Learning Limited 7 Amersham Hill, High Wycombe, Bucks HP13 6NS,

More information

Space project management

Space project management ECSS-M-ST-80C Space project management Risk management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of ECSS Standards

More information

Good Practice Guide: the internal audit role in information assurance

Good Practice Guide: the internal audit role in information assurance Good Practice Guide: the internal audit role in information assurance Janaury 2010 Good Practice Guide: the internal audit role in information assurance January 2010 Official versions of this document

More information

Risk Management & Business Continuity Manual 2011-2014

Risk Management & Business Continuity Manual 2011-2014 ANNEX C Risk Management & Business Continuity Manual 2011-2014 Produced by the Risk Produced and by the Business Risk and Business Continuity Continuity Team Team February 2011 April 2011 Draft V.10 Page

More information

Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth

Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth January 2014 Purpose of this document The duty to have regard to the desirability of promoting economic growth (the growth duty )

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

Ongoing N/A TBC. Baseline

Ongoing N/A TBC. Baseline Position Title: Executive General Manager, Core Services Systems Operations Classification: SES Band 2 Position Number: 1018 Position Status (ongoing/nonongoing): Ongoing Division: Core Services Systems

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk

ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk ENGINEERING COUNCIL Guidance on Risk for the Engineering Profession www.engc.org.uk/risk This guidance describes the role of professional engineers and technicians in dealing with risk, and their responsibilities

More information

Making a positive difference for energy consumers. Competency Framework Band C

Making a positive difference for energy consumers. Competency Framework Band C Making a positive difference for energy consumers Competency Framework 2 Competency framework Indicators of behaviours Strategic Cluster Setting Direction 1. Seeing the Big Picture Seeing the big picture

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Procurement policy Working with our suppliers to support strategic growth

Procurement policy Working with our suppliers to support strategic growth Procurement policy Working with our suppliers to support strategic growth Mission Statement The Procurement Department is the focal point for commercial relationships with Eversheds supply chains, ensuring

More information

Government Communication Professional Competency Framework

Government Communication Professional Competency Framework Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their

More information

PROJECT RISK ANALYSIS AND MANAGEMENT

PROJECT RISK ANALYSIS AND MANAGEMENT PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest

More information

Information Security: Business Assurance Guidelines

Information Security: Business Assurance Guidelines Information Security: Business Assurance Guidelines The DTI drives our ambition of prosperity for all by working to create the best environment for business success in the UK. We help people and companies

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

UNIVERSITY OF LONDON GUIDE TO RISK MANAGEMENT. Purpose of the guide... 2

UNIVERSITY OF LONDON GUIDE TO RISK MANAGEMENT. Purpose of the guide... 2 UNIVERSITY OF LONDON GUIDE TO RISK MANAGEMENT Purpose of the guide... 2 Risk Management The Basics... 2 What is Risk Management?... 2 Applying Risk Management... 2 The Use of Risk Registers in Risk Management...

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

CORPORATE PLAN 2012-13 2013-14 2014-15

CORPORATE PLAN 2012-13 2013-14 2014-15 CORPORATE PLAN 2012-13 2013-14 2014-15 V0.3 170412 1 1. Introduction This Corporate Plan identifies the main strategic challenges facing the Agency over the next three years, and sets out its key performance

More information

10 Reasons Why Project Managers Need Project Portfolio Management (PPM)

10 Reasons Why Project Managers Need Project Portfolio Management (PPM) 10 Reasons Why Project Managers Need Project Portfolio Management (PPM) Introduction Many project managers might think they are doing just fine with spreadsheets or basic project management software and

More information

Performance Management in Medical Affairs Kinapse Consulting, 2011

Performance Management in Medical Affairs Kinapse Consulting, 2011 Kinapse Consulting, 2011 Advise Build Operate www.kinapse.com As Medical Affairs evolves and takes a more prominent role in the development and commercialisation of medicines, it needs a more robust approach

More information

General Dental Council Website Review: Dental Professionals Survey Invitation to Tender

General Dental Council Website Review: Dental Professionals Survey Invitation to Tender General Dental Council Website Review: Dental Professionals Survey Invitation to Tender Summary 1. The General Dental Council (GDC) invites tender proposals for a research project on the usability of the

More information

How to Choose the Right Apparel PLM Solution

How to Choose the Right Apparel PLM Solution How to Choose the Right Apparel PLM Solution 200 Vesey Street Brookfield Place New York, NY 10281-1017 212-408-3809 info@ In modern product development, process efficiency is the key to profitability.

More information

How to Measure a Loyalty Programme s Return on Investment. Managing information and transactions securely

How to Measure a Loyalty Programme s Return on Investment. Managing information and transactions securely How to Measure a Loyalty Programme s Return on Investment Managing information and transactions securely Introduction Successful programmes have longevity because the overall benefits clearly justify the

More information

CHESHIRE FIRE AUTHORITY SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM TERM FINANCIAL PLAN

CHESHIRE FIRE AUTHORITY SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM TERM FINANCIAL PLAN CHESHIRE FIRE AUTHORITY Item 2 ITEM: 2 MEETING OF : FIRE AUTHORITY DATE : 12 FEBRUARY 2014 REPORT OF : CHIEF FIRE OFFICER AUTHOR : HEAD OF FINANCE SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM

More information

Future funding outlook for councils 2019/20

Future funding outlook for councils 2019/20 Future funding outlook for councils 2019/20 Interim 2015 update June 2015 www.local.gov.uk Future funding outlook for councils 2019/20 1 Contents Executive summary 4 Introduction 6 The path of council

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

Chapter 1 Developing a healthy appetite for risk [DTI] 3. Chapter 2 Getting the best bang per buck [DEFRA] 5

Chapter 1 Developing a healthy appetite for risk [DTI] 3. Chapter 2 Getting the best bang per buck [DEFRA] 5 CONTENTS Page Chapter 1 Developing a healthy appetite for risk [DTI] 3 Chapter 2 Getting the best bang per buck [DEFRA] 5 Chapter 3 Getting your house in order [Companies House] 9 Thinking About Risk -

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7. Welcome to the November 2009 INSIGHTS published by acumen7. The purpose of this newsletter is to bring you new perspectives on key subjects to stimulate your own thoughts and ideas. In each edition (which

More information

THE COMBINED CODE PRINCIPLES OF GOOD GOVERNANCE AND CODE OF BEST PRACTICE

THE COMBINED CODE PRINCIPLES OF GOOD GOVERNANCE AND CODE OF BEST PRACTICE THE COMBINED CODE PRINCIPLES OF GOOD GOVERNANCE AND CODE OF BEST PRACTICE Derived by the Committee on Corporate Governance from the Committee s Final Report and from the Cadbury and Greenbury Reports.

More information

WHITE PAPER: SALES & MARKETING. Seven levers of sales and marketing performance that drive sales growth and deliver sustainable competitive advantage

WHITE PAPER: SALES & MARKETING. Seven levers of sales and marketing performance that drive sales growth and deliver sustainable competitive advantage WHITE PAPER: SALES & MARKETING Seven levers of sales and marketing performance that drive sales growth and deliver sustainable competitive advantage Sales & Marketing 2 Seven levers of sales and marketing

More information

Queensland Treasury. Queensland Government. Program Evaluation Guidelines

Queensland Treasury. Queensland Government. Program Evaluation Guidelines Queensland Treasury Queensland Government Program Evaluation Guidelines November 2014 Document details Security Classification Date of Review of Security Classification Authority Author PUBLIC November

More information

Technical Journal. Paper 142

Technical Journal. Paper 142 Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

We released this document in response to a Freedom of Information request. Over time it may become out of date. Department for Work and Pensions

We released this document in response to a Freedom of Information request. Over time it may become out of date. Department for Work and Pensions We released this document in response to a Freedom of Information request. Over time it may become out of date. Department for Work and Pensions 1. Change Control Principles Schedule 24: Change Control

More information

Buying and Setting up a Business with a Post Office A Guide

Buying and Setting up a Business with a Post Office A Guide Buying and Setting up a Business with a Post Office A Guide NOTE: The information in this document is not intended as an exhaustive list of all the information you require in order to set up a business

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

PRINCE2:2009 Glossary of Terms (English)

PRINCE2:2009 Glossary of Terms (English) accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain

More information

ABERDEEN CITY COUNCIL JOB DESCRIPTION

ABERDEEN CITY COUNCIL JOB DESCRIPTION ABERDEEN CITY COUNCIL JOB DESCRIPTION All employees are required to carry out their duties and responsibilities in accordance with the Council s Safety Policy and all other Council policies and legislation

More information

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future Asset Management Strategy (2013-2017) A New Approach for a sustainable future Contents Introduction... 2 The Asset Management Vision, Policy Statement & Strategic Themes... 5 Part B The Asset Management

More information

Position Description

Position Description Position Description Job title Group Section Responsible to Responsibility for staff Project Coordinator Natural Resource Operations Rotorua Lakes Protection & Restoration Programme Rotorua Lakes Business

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Appendix 3: Project Management Substation Guidelines (General Process Flow Template)

Appendix 3: Project Management Substation Guidelines (General Process Flow Template) 365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It

More information

Risk Management Primer

Risk Management Primer Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders

More information

Head of Lease Terms - Ten Steps to a Successful negotiation

Head of Lease Terms - Ten Steps to a Successful negotiation Imperial College ThinkSpace Leasing Terminology Head of lease terms The principal terms upon which the lease will be drafted are detailed within a single document, entitles the Heads of Lease Terms. These

More information

Risk appetite How hungry are you?

Risk appetite How hungry are you? Risk appetite How hungry are you? 8 by Richard Barfield Richard Barfield Director, Valuation & Strategy, UK Tel: 44 20 7804 6658 Email: richard.barfield@uk.pwc.com 9 Regulatory pressures, such as Basel

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services PERFORMANCE MANAGEMENT GOING AGILE Nicolle Strauss Director, People Services 1 OVERVIEW In the increasing shift to a mobile and global workforce the need for performance management and more broadly talent

More information

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan Of interest to students of Paper P5 Integrated Management. Increasingly, there seems to be a greater recognition of the

More information

Project organisation and establishing a programme management office

Project organisation and establishing a programme management office PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Risk Management Policy Record Number D14/79827 Responsible Manager Manager Strategy and Governance Last reviewed 10 March 2015 Adoption reference Council Resolution number 90.5 Previous

More information

TAXREP 01/16 (ICAEW REP 02/16)

TAXREP 01/16 (ICAEW REP 02/16) TAXREP 01/16 (ICAEW REP 02/16) January 2016 ICAEW research survey: HMRC Customer Service Standards 2015 Results of the ICAEW 2015 research survey among ICAEW smaller agents about HMRC service standards.

More information

Public reporting in a Solvency II environment

Public reporting in a Solvency II environment Public in a Survey report August 014 kpmg.co.uk 0 PUBLIC REPORTING IN A SOLVENCY ENVIRONMENT Contents Page 1 4 5 Introduction Executive Summary Public Disclosures 4 Changes to Financial Framework 11 KPMG

More information

13. Performance Management

13. Performance Management 13. Performance Management Summary Delivering schemes on time and on budget Management of Capital Programme Management of Risk Gateway Reviews Resource requirements Project Management and skills development

More information

Adopting Agile Testing

Adopting Agile Testing Adopting Agile Testing A Borland Agile Testing White Paper August 2012 Executive Summary More and more companies are adopting Agile methods as a flexible way to introduce new software products. An important

More information

STAG Technical Database Section 13

STAG Technical Database Section 13 Risk and Uncertainty May 2014 Transport Scotland Once printed or downloaded this document is considered to be uncontrolled. For the current version refer to the Scot-TAG section of the Transport Scotland

More information

COBIT 5 Introduction. 28 February 2012

COBIT 5 Introduction. 28 February 2012 COBIT 5 Introduction 28 February 2012 COBIT 5 Executive Summary 2012 ISACA. All rights reserved. 2 Information! Information is a key resource for all enterprises. Information is created, used, retained,

More information

The European and UK Space Agencies

The European and UK Space Agencies The European and UK Space Agencies A response to the House of Commons Science and Technology Select Committee April 2013 Introduction The Royal Academy of Engineering is pleased to submit evidence to the

More information

Risk management and prevention How professionals render their projects financially weatherproof

Risk management and prevention How professionals render their projects financially weatherproof Six step to deal with potentially costly - project risks Risk management and prevention How professionals render their projects financially weatherproof Many project managers do not think of risks while

More information

Monitoring capital projects and addressing signs of trouble

Monitoring capital projects and addressing signs of trouble /01 / Leadership Series 6 PROJECT ADVISORY Monitoring capital projects and addressing signs of trouble Leadership Series 6 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards

More information

2009 NASCIO Recognition Award Nomination State of Georgia

2009 NASCIO Recognition Award Nomination State of Georgia 2009 NASCIO Recognition Award Nomination State of Georgia Nomination Category: IT Project and Portfolio Management Title of Nomination: IT Project Governance: Delivering on the Promise Nomination Submitted

More information

Job description Customer Care Team Leader (Engagement)

Job description Customer Care Team Leader (Engagement) Job description Customer Care Team Leader (Engagement) Main purpose of job The Customer Care Team Leader will manage the day to day running of the internal Customer Care engagement team, ensuring it provides

More information

LexisOne. LexisOne. Powered by Microsoft Dynamics AX 2012. EnterpriseSolutions

LexisOne. LexisOne. Powered by Microsoft Dynamics AX 2012. EnterpriseSolutions LexisOne Powered by Microsoft Dynamics AX 2012 LexisOne LexisOne powered by Microsoft Dynamics AX 2012 from LexisNexis goes beyond traditional practice management software currently available to legal

More information

www.ronrosenhead.co.uk Joining Instructions for 3 day project management event

www.ronrosenhead.co.uk Joining Instructions for 3 day project management event Joining Instructions for 3 day project management event To: All Participants We are looking forward to working with you to develop your project management skills and to discuss their application to current

More information

Solvency II benchmarking survey

Solvency II benchmarking survey INSURaNce Solvency II benchmarking survey Life Insurers November 2011 kpmg.co.uk/solvencyii 2 SoLveNcy II benchmarking SURvey - LIfe INSUReRS SoLveNcy II benchmarking SURvey - LIfe INSUReRS 3 Contents

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

COGENT CONSULTING, INC.

COGENT CONSULTING, INC. COGENT CONSULTING, INC. point of view Taking the Guesswork out of Resource Allocation How to align marketing investments with growth opportunities and potential Doing More with Less The Patent Cliff. The

More information

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer

More information

Management Information & KPIs: How and why to use information effectively in the Financial Services sector. Research White Paper

Management Information & KPIs: How and why to use information effectively in the Financial Services sector. Research White Paper Management Information & KPIs: How and why to use information effectively in the Financial Services sector Research White Paper Index 1 3 4 5 6 7 8 9 10 Introduction The commercial importance of Management

More information

Annual defined benefit funding statement 2015

Annual defined benefit funding statement 2015 Annual defined benefit funding statement 2015 May 2015 Introduction 1. This statement is relevant to trustees and employers of all defined benefit (DB) pension schemes but is primarily aimed at those undertaking

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111

More information

Activate Learning Further Education Corporation

Activate Learning Further Education Corporation Activate Learning Further Education Corporation MINUTES of a meeting of the Audit Committee held on 10 June 2014 at 5.30 pm in room A106 at Oxford City College Campus. Present: In attendance: C Jones (Chairman);

More information

SETTING UP YOUR OWN LEGAL BUSINESS

SETTING UP YOUR OWN LEGAL BUSINESS SETTING UP YOUR OWN LEGAL BUSINESS CONTENTS Why do I want my own business? 2 Your business idea 3 Areas of competence and qualifications 4 Reserved legal activities 5 Practice rights 6 What can I call

More information

WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101

WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101 WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101 Prepared by: Phillip Bailey, Service Management Consultant Steve Ingall, Head of Service Management Consultancy 60 Lombard Street London EC3V 9EA

More information

Making the Most of Property

Making the Most of Property the High performance portfolio: Making the Most of Property Management Agreements SUMMARY Property management agreements create the framework for who does what, when, where, and for how much in the relationship

More information

Intelligent Field Service. The complete solution for field-based organisations

Intelligent Field Service. The complete solution for field-based organisations Intelligent Field Service The complete solution for field-based organisations Kirona Intelligent Field Service 01 Introducing Kirona Kirona helps organisations to deliver exceptional field-based services

More information

From ICAAP/ORSA to ERM: Board and Senior Management Oversight. Leon Bloom, Partner, Deloitte & Touche LLP lebloom@deloitte.ca

From ICAAP/ORSA to ERM: Board and Senior Management Oversight. Leon Bloom, Partner, Deloitte & Touche LLP lebloom@deloitte.ca From ICAAP/ORSA to ERM: Board and Senior Management Oversight Leon Bloom, Partner, Deloitte & Touche LLP lebloom@deloitte.ca Agenda Basel II ICAAP Solvency II ORSA ERM From ICAAP/ORSA to ERM: Governance

More information

The English Nature and Joint Committee of Staff

The English Nature and Joint Committee of Staff This paper was provided to the Joint Committee for decision/discussion or information. Please refer to the minutes of the meeting for Committee s position on the paper. To view other Joint Committee papers

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

1. What types of organisation do you fund? 2. Do you give grants for individual children and young people?

1. What types of organisation do you fund? 2. Do you give grants for individual children and young people? Frequently Asked Questions (FAQs) Who can apply for a grant? 1. What types of organisation do you fund? 2. Do you give grants for individual children and young people? 3. Some of the young people our organisation

More information

IT Professional Standards. Information Security Discipline. Sub-discipline 605 Information Security Testing and Information Assurance Methodologies

IT Professional Standards. Information Security Discipline. Sub-discipline 605 Information Security Testing and Information Assurance Methodologies IT Professional Standards Information Security Discipline Sub-discipline 605 Information Security Testing and Information Assurance Methodologies December 2012 Draft Version 0.6 DOCUMENT REVIEW Document

More information

RISK APPETITE STATEMENT

RISK APPETITE STATEMENT RISK APPETITE STATEMENT make or break? PREPARED BY NADINE BOGHDADI, RISK CONSULTANT WILLIS RISK SERVICES MARCH 2015 When an organisation embarks on defining its risk appetite, the process, debate and discussion

More information

Strategic Program Management

Strategic Program Management Governance Assessment Organizational Change Management Strategic Program Management Continuous Improvement Framework Processes Strategy Strategic Program Management Bob Prieto Published by Construction

More information

THAMESIDE financial planning

THAMESIDE financial planning THAMESIDE financial planning OUR INVESTMENT APPROACH UNDERSTANDING INVESTMENT RISK An overview Thameside Financial Planning recognises the importance of working with you to understand, achieve and maintain

More information

ScottishPower Competency Based Recruitment Competency Guidelines External Candidate. pp077682 ScottishPower [Pick the date]

ScottishPower Competency Based Recruitment Competency Guidelines External Candidate. pp077682 ScottishPower [Pick the date] ScottishPower Competency Based Recruitment Competency Guidelines External Candidate pp077682 ScottishPower [Pick the date] Aims and Objectives This document will give you an overview of the selection process

More information

Capacity Management Improvement - From Assessment to Benefits

Capacity Management Improvement - From Assessment to Benefits Capacity Improvement - From Assessment to Benefits Neil McMenemy, Principal Consultant, Capacitas Agenda Reasons for engagement Structure of the improvement program Progress to date Capability of team

More information

By email to: ISAPeertoPeerConsultation@hmtreasury.gsi.gov.uk. ISA qualifying investments: Consultation on including peer-to-peer loans

By email to: ISAPeertoPeerConsultation@hmtreasury.gsi.gov.uk. ISA qualifying investments: Consultation on including peer-to-peer loans ISA Peer to Peer Consultation Pensions and Savings Team HM Treasury 1 Horse Guards Road London SW1A 2HQ By email to: ISAPeertoPeerConsultation@hmtreasury.gsi.gov.uk 12 December 2014 Dear Sirs, ISA qualifying

More information

Report of visit Level of follow-up: Estyn monitoring

Report of visit Level of follow-up: Estyn monitoring Report of visit Level of follow-up: Estyn monitoring Bridgend Adult Community Learning Partnership Bridgend County Borough Council Civic Offices Angel Street Bridgend CF31 4WB Date of visit: by Estyn,

More information

OF CPAB INSPECTION FINDINGS

OF CPAB INSPECTION FINDINGS PROTOCOL FOR AUDIT FIRM COMMUNICATION OF CPAB INSPECTION FINDINGS WITH AUDIT COMMITTEES CONSULTATION PAPER NOVEMBER 2013 The Canadian Public Accountability Board ( CPAB ) is requesting comments on the

More information

Develop and implement marketing plans for your area of responsibility

Develop and implement marketing plans for your area of responsibility Overview What this Unit is about This Unit is about developing and implementing marketing plans for your area of. This Unit describes the classic model of marketing planning, implementation and control,

More information