1 Developer services Waste water Building over or near a public sewer Application form and Guidance notes

2

3 Developer Services DS 005 Guidance notes Building over or near to a public sewer Please note that where reference is made to public sewer or Section 105A sewer (pipe serving two or more separate units) this should also be taken to include any public lateral drain (pipe outside the property curtilage only serving one unit). Wessex Water has more than 30,000 kilometres of public sewers which have sometimes been laid within the boundaries of properties. You must obtain our agreement to carry out any building work over or within three metres of a public sewer to ensure no damage is caused to it or restrictions made to the way we use and maintain the sewer. Not having a formal approval from your local water company may jeopardise the future sale of your property. Our preferred option is that if you find your proposals could affect a public sewer you should first consider: avoiding the sewer. Modifications are made to your plans so that the buildings are at least three metres away from the sewer. This is often the easiest and cheapest option diverting the sewer. If your plans cannot be modified we will usually require the sewer to be diverted. Plese refer to our diversion application form for further details which can be found on our website: On 1st October 2011, in accordance with the Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011, Wessex Water became responsible for the ownership and maintenance of thousands of kilometres of formerly private sewers and lateral drains (section 105a sewers). Many of these additional pipe lines run at the rear or side of domestic properties in addition to the existing public sewers shown on our record plans. They will coonly be affected by extension proposals and either not shown on the public sewer record plans or their indicated position will be approximate only. It is important to undertake a full survey of the site and surrounding land to determine the local drainage arrangements and to contact us at an early stage if you suspect that a section 105a sewer may be affected. Local authorities are required to consult us where building over or near to a sewer might occur. We need to know about any building work near or over a public sewer to: prevent the sewer collapsing. The extra weight of a new building above a sewer could cause the sewer to collapse, resulting in structural damage to the new building, interrupted drainage from other properties and sewage flooding. It will need to be repaired quickly, even if this involves taking down the building ensure we have access to carry out maintenance and repairs. We need to have access to the sewer and its manholes in order for us to inspect the sewer, clear blockages or carry out repairs. You can contact us to discuss your proposals through our sewer protection team. We will always try to be flexible and helpful in deciding with you the best way of dealing with an affected sewer. Wessex Water makes a charge for every application. The level of the charge will depend on the size of the sewer to be surveyed and whether a detailed investigation is necessary. In some cases, where important sewers are involved, a formal legal agreement may also be required should it be found acceptable to allow a build over/near. Please be aware that every proposal is considered on its merits, and there will be occasions where an application is refused. We will normally be able to give you a decision within 10 working days of receipt of a complete application and we will also keep the building regulations department of the local authority informed. Under no circumstances will building over be permitted where: the sewer is a pressurised pumping main a manhole would be inside a building strategic sewers are affected or those which may require future upgrading. new dwellings/buildings would be constructed over a sewer. Normally, no building over be permitted where: the sewer has a formal easement preventing overbuilding this is normally shown in the deeds of a modern property the sewer diameter is greater than 300 the sewer depth is in excess of three metres In these cases you must contact Wessex Water for technical advice. If, having considered the alternatives, your only option is to apply for building over or near to a sewer, you should make an application to us on the attached form. In some circumstances, we will allow you to build over but you must have our written agreement to do this before you start. The sewer must be in satisfactory condition. It is recoended that an application is made before seeking planning or building regulations approval and well in advance of works coencing on the site. If building over a sewer, you will need to arrange for a survey, usually by closed circuit television (CCTV), to be carried out before you begin work. This will assess if any repair work is needed. Any repair work required will be at your expense but the application fee will be waived. A copy of the CCTV report should be enclosed with the application form. If Wessex Water is not satisfied with the quality of the CCTV survey you will be requested to provide a suitable alternative. The CCTV report should include: a block plan showing the point of entry into the public sewer and length of sewer surveyed the distance surveyed as a running total on the video/cd/dvd of the sewer sewer details: type (foul/surface water), pipe size, material and pipe depth In some instances we may also require a CCTV survey to be carried out on completion of the works. Please note that a CCTV survey will not normally be required if you are not building over a public sewer although in certain cases it will be necessary. In some circumstances, we have the right to stop your works, and have the buildings that are built over public sewers taken down. Please retain notes for reference

4 Building over or near minor sewers up to and including 150 (6 ) diameter Wessex Water will consider building over or near minor sewers where diversion is not practical and the extension cannot be redesigned. This includes section 105a sewers, however these may not be shown on our record plans. Any permission will be subject to the following conditions: the public sewers are accurately located on site and plotted on to the deposited plans submitted for building regulations permission. For building notices the same conditions will apply for a sewer up to 1.5m deep the nearest edge of foundations should normally be no closer than one metre from the edge of the sewer for a sewer 1.5m to three metres deep, the distance between the sewer and foundations should be equal to the depth of the sewer where possible where foundations to the building are at any point within one metre of the sewer, they are to be carried down and formed at 150 below the invert level of the sewer. At greater clearance an angle of 45º can be taken from a point one metre clear of the sewer up to the required footing level. If building over a sewer, the sewer line should be surveyed by closed circuit television and a record made of its structural condition before any work is carried out to protect both the householder and Wessex Water s interests. This should be arranged by the applicant who will need to supply the recording and report with the formal application. On request by the householder, Wessex Water can arrange this work on a rechargeable basis, although this will take longer and costs may be higher. Any defects on the sewer must be made good at the householder s expense. This may require complete replacement or repair. Guidance should be requested from Wessex Water to ensure the system is satisfactory before any further work is carried out. Where necessary, the sewer crossing the site must be relaid beneath the building from a new manhole (if provided) to the boundary of the site. It should be laid using approved new pipes (normally clay) with normal flexible joints and a granular bed and surround of not less than 150 in thickness or 10 to 14 nominal single size or 14 to 5 graded granular material. Where new pipes are connected to the existing sewer either an appropriate sleeve joint or a band seal repair connector is to be used. Where the sewer crosses beneath any load bearing walls, the foundations of the walls are to be stopped short of the sewer by not less than 150, and the sewer line is to be bridged by load bearing lintels (Building Control approved) placed above it so that no loads from the structure are transmitted to the sewer pipes. The void around the sewer is to be filled with highly compressible material. Cantilever type slab foundations will be considered details to be supplied for agreement. Where an existing chamber will come within the new building, a new manhole should be constructed to the current standard of Sewers for Adoption published by the Water Research Centre Plc on the line of the sewer outside the limits of the building, to provide a replacement point of access to the sewer. Connections to the existing chamber will need to be diverted and relaid to the new chamber. The existing chamber should be removed. All work should be carried out by a qualified contractor (see attached terms and conditions). All work must be inspected and approved by the building control surveyor and/or Wessex Water prior to back filling. It must be acknowledged that the sewerage undertaker s easement within the site to carry out repair and maintenance to the sewer, is not in any way prejudiced by the approval of Wessex Water to the proposed building work. Sewers over 150 (6 ) up to and including 300 (12 ) diameter Wessex Water will consider building over or in close proximity to these sewers provided that there are less than approximately 25 properties served by the sewer conditions as for minor sewers apply where more than approximately 25 properties are served, Please retain notes for reference the applicant must show that he has considered diverting the sewer, or repositioning or redesigning his proposed development. Only where no other option is viable and using appropriate protection measures will overbuild then be considered.

5 Building close to or over minor public sewers Public highway Existing dwelling Existing dwelling Existing dwelling Public land Existing dwelling A A B B C C < 3m Typical build near Build over with relocation of manhole outside the new extension Typical build over Build near all works within 3m of a lateral drain require approval Key Public sewer Public manhole Diverted private drain Lateral drain (public) Private rodding eye / manhole New public manhole Private drain Abandoned private drain Removed public manhole Section A A Building close to a public sewer Foundations less than 1m from the sewer Where foundations to the buildings are at any point within 1m from the sewer, they are to be carried down at least 150 below the invert of the sewer. Floor level Foundation Ground level 1m or less Public sewer 150 Section B B Load bearing wall construction detail Block or brickwork 150 Mass fill foundation Pre-stressed concrete lintel(s) 50 celotex or polystyrene Granular bedding material Sub soil or bedrock Section C C Building over a public sewer Foundations less than 1m from the sewer Where foundations to the buildings are at any point within 1m from the sewer, they are to be carried down at least 150 below the invert of the sewer. Floor level 150 Public sewer 1m or less Foundation Ground level Foundations more than 1m from the sewer At a greater distance than 1m, an angle of 45 degrees can be taken to determine the required footing level. Floor level Foundation 45 Ground level More than 1m Public sewer Important The information on this page is intended to show examples of typical scenarios and should be used for general guidance puposes only. Significant variations on a site by site basis are to be expected and it is in no way implied that meeting any of the above will guarantee approval. Drawings are not to scale. Foundations more than 1m from the sewer At a greater distance than 1m, an angle of 45 degrees can be taken to determine the required footing level. Floor level Public sewer More than 1m 45 Foundation Ground level

6 TERMS AND CONDITIONS 1 The works are to be undertaken under the provisions of section 185 (and section 106 if they incorporate any new connection) of the Water Industry Act All works are to be carried out wholly within land owned by the applicant. 3 The closure and removal of any part of the public sewer network that shall become totally redundant during the course of the works must only have served premises and land owned by the applicant. Any redundant sewer must be sealed, removed, or fully filled with grout. 4 All works will be carried out at the applicants expense. 5 The works shall be carried out in accordance with the appropriate specifications contained in the current WRc publication Sewers for Adoption a design & construction guide for developers. A copy can be purchased from WRC plc by calling / or online at 6. Variations to the works shall only be carried out with the prior written permission of Wessex Water. 7 All work must be carried out in a workmanlike safety conscious manner and completed as soon as practicable after they have coenced. During the construction of the works adequate provision will be taken to ensure that the flow of sewage through the public sewerage system is not adversely impeded by the works. 8 Sufficient notice and opportunity to monitor the works will be given to Wessex Water. 9 Wessex Water reserves the right to take control of the works and/or satisfactorily complete the works with or without notice at the applicants cost on a fully rechargeable basis. Sufficient access to the works will be provided at all times to carry out inspections and complete the works if necessary. 10 The construction of any building or extension shall be carried out with the due exercise of care to protect the public sewer network from damage at all times. Foundations and walls shall be designed and constructed in such a way so as not to place any loading on to the public sewer network. 11 All drainage work must be carried out by a suitably qualified contractor. Unless agreed otherwise, the contractor should be from the list which can be found on our website under Connecting to a public sewer. Alternatively, details can be ed/posted. If you select a contractor not on the list, they should hold the appropriate City and Guilds confined spaces qualification. In addition, medical certification, method statements and risk assessments may be required.

7 Application to build over or near to a public sewer Frequently asked questions I have planning permission and have applied for building regulations approval so why do I need the approval of Wessex Water as well? Wessex Water is responsible for maintenance and repair of public sewers and therefore development proposals close to or over our apparatus will require our formal approval to protect our interests. By law, building control must advise us of any works within 3 metres of a public sewer. What do you consider to be close to a public sewer? Within 3 metres of the outer edge of sewers up to 300 diameter increasing to 6 metres for larger diameter sewers. How do I know where the sewer is and what size it is? The exact details of the sewer should be established by site survey carried out by the applicant or the developer/ architect. I have found a sewer pipe how do I know if it is a private drain or public sewer? If the pipe only serves your property it is a private drain and you do not require our approval to build over or near to it. Building Control will monitor any works related to the protection of the drain. If the pipe is shared by two or more properties, or it is a drain (described above) which has left your property boundary, it is a public sewer and any work within 3 metres of its outer edge will require our approval. When is building over a public sewer not permitted? Where over pumping mains Where over strategic sewers On new development sites Where over manholes What are strategic sewers? Generally sewers 225 diameter and over as these take significant flows (although it can include sewers of smaller diameter in certain circumstances). Why do I have to pay? Wessex Water must recover its costs, to be fair to our existing customers, in dealing with something that a particular customer is proposing. The fee covers our costs in administering the application, evaluating the proposed works, liaison with building control officers, issuing approval and site inspection if necessary. Why do I have to pay more for a larger sewer? The review we need to make regarding a larger sewer is more extensive. We may need to seek operational guidance, carry out additional site visits and look at drainage area studies. The technical and administration costs would therefore be higher. Do conservatories require the approval of Wessex Water? Yes if you are building over or near a public sewer. Does the sewer have a right to be in my property even if there is nothing in the property deeds? If laid by Wessex or previous authorities, compensation will have been paid to the original landowner at the time of laying. Where laid by the property developer, Wessex (or previous authority) will have taken on the sewer with its right of location and access as part of the vesting arrangement. All public sewers are covered by statutory easement. This is normally from the outer edge of the sewer and is a minimum 6m wide although greater if sewer of large diameter. Modern properties (post 1990) will normally have specific easement details in their deeds. What rights does Wessex Water have to prevent me from carrying out my proposed building works? For every public sewer we have a statutory easement. In some cases this easement is supplemented by a written deed of grant, but these are rare. The statutory easement is the right in favour of Wessex to maintain, repair, replace, renew etc. its public sewers under sec 159 of the Water Industry Act If anyone does anything that interferes with our statutory easement we could seek an injunction for the removal of offending buildings and damages. What special protection work is required? Foundation design in accordance with the details given in our guidance notes For sewers over 3m deep it is likely that pile foundations will be required or for deep footings constructed in short sections In certain circumstances (non preferred) we will consider reinforced and thickened concrete slab (raft foundation), which should be designed to minimise ground disturbance as well as transfer and spread loads Load bearing lintels to be used where the sewer line is built over in accordance with guidance details What if an existing manhole is located within the footprint of the proposed development? Inspection chambers should be removed where they fall within a new building and if still required, replaced outside the limits of the building to standards of SFA.

8 Internal manholes have been non preferred for many years under building regulations and our own guidance. Internal manholes can cause a problem if access is needed and the householder is not at home. You should, therefore, look to revise your proposals to avoid the manhole or apply to divert the sewer. Why do I have to have a CCTV survey? This is the quickest and most efficient way of making a structural assessment of the current condition of a pipeline. Why do I have to pay for the CCTV survey? Because you as the customer is requesting to build over or near to our asset. Prior to agreeing to your proposals we have to be satisfied that our asset is in good condition, which Wessex are quite happy with and have no plans or requirements to expend any time or costs on. What if the sewer is already shown to have defects on the CCTV survey? You will need to resolve and fund these works although we will refund the application fee. Why do I have to pay to repair your sewer? Because we have no iediate plans to expend any time or costs on this particular asset which is currently operating satisfactorily and to which we have unrestricted access. Will a record of my buildover/buildnear agreement be kept by Wessex Water for reference in the future? Yes, a record will be kept on our mapping system showing the reference number and date of agreement against a specific property (for all agreements made from 1 April 2003). This information will be used in Solicitors searches should you decide to sell your property. Getting in touch with us For enquiries regarding this application or any other questions relating to your building or development work please contact us on: (8.30am to 4.30pm, Mon Thurs, 8.30am to 4pm, Fri). You can wrtite to us at you can us at or visit our website at Wessex Water, Developer Services, Claverton Down, Bath BA2 7WW sewer.protection@wessexwater.co.uk Wessex Water general contact information (Telephone calls may be recorded to monitor quality standards.) Billing and customer services Emergencies and operational problems (8am to 6pm, Mon Fri) customer.services@wessexwater.co.uk BWBSL, 1 Clevedon Walk, Nailsea, Bristol BS48 1WA. Please include your customer reference number and/or billing address when calling or ing. We may contact you by telephone in response to your to discuss your query. Please provide your phone number when you contact us. Operations centre, Bath (main office) (8.30am to 5pm, Mon Fri) Wessex Water, Claverton Down Bath BA2 7WW info@wessexwater.co.uk (8am to 6pm, Mon Fri, emergency service at other times) operational.enquiries@wessexwater.co.uk Minicom (for those with impaired hearing) Sewage floodline (in a property) Leakstoppers (24 hours) leakstoppers@wessexwater.co.uk

9 Developer Services Buildover ref: DS 005 Application form (please refer to the guidance notes before completing this form) Building over or near to a public sewer A Applicant's details Company/Name Contact name Company Reg. no. Signature Your address Postcode Contact number Fax number address B Agent s details (if different from A) Agent s name (company name where appropriate) Address Postcode Phone number Your fax number address C Site details Site address Postcode Site contact name Site agent's name and number Plan details Applicant s drawings should include a plan and sufficient sections to adequately show the position of the building relative to the sewer. A location plan indicating the position of the building work relative to site boundaries, highways and other identifiable features is also required. Drawings submitted for building regulations are usually sufficient as long as the sewer is clearly and accurately plotted in relation to the proposed works. Applicants should not scale from our sewer records. Site plans should be at 1:50 or 1:100 scale or larger. D Development details Type of development Side extension Rear extension Other Please specify Local authority area Have you applied for building regulations approval? Yes No If yes, please state the local authority/approved inspector reference number Local authority/approved inspector contact name Date of application/notice

10 E Other details Please confirm the type of public sewer to be built over/near: Foul Surface Combined Unknown Please confirm the size of sewer (if known) Depth of any manholes indicated on the site plan: (metres) Do you need to make a new connection to the public sewer? Yes No (If yes, a separate application will be necessary which can be downloaded from our website at or can be sent to you on request). F Fees/charges (please indicate which sewer class your application is for): Class I: 225 (Sewer up to and including 150 (6 ) diameter) Class II: 315 (Sewer over 150 and up to and including 300 (12 ) diameter) Class III: 500 (Sewer over 300 in diameter) Please note that we would not normally permit Class III sewers to be built over. Cheques should be made payable to Wessex Water with the reference number (if known) written on the back. If you wish to pay by credit card please tick here Contact name and tel. no: G Checklist and declaration (please ensure that you have included the following): Drawings Appropriate fees CCTV survey and report (if building over the sewer) Has the sewer(s) been accurately located on site Yes No Has the precise route of the sewer(s) been plotted on the submitted drawings Yes No PLEASE NOTE Failure to include any of the above may be deemed as an incomplete application and result in the application being delayed/returned. By signing this application, you are not automatically granted approval. No works should start until full payment has been received and formal written approval has been granted. I confirm to the best of my knowledge the above information to be complete and correct. Will the applicant be responsible for the fees as shown in section F? Yes No (if no, please provide details below of the person responsible) Name Address Signature of person responsible Date:

Policy Guidance Notes and Requirements

Policy Guidance Notes and Requirements Policy Guidance Notes and Requirements Building over/close to Public Sewers Domestic Extensions and Garages 1.0 Introduction Householders and developers planning to build close to or over a public sewer

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

Sewer Connection Application

Sewer Connection Application Sewer Connection This application form is to be used for connections to a public sewer for the following: Housing Units Site Accommodation Student Accommodation Guidance section Sewer Connection When completing

More information

Drainage. Information for those with problem drains

Drainage. Information for those with problem drains Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991

Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991 Application for a new connection to the public sewer network under the provisions of sections 106 & 102 of the Water Industry Act 1991 Taking care of your waste water: It s part of our Blueprint for Yorkshire

More information

Application for a water connection to a commercial or mixed use development

Application for a water connection to a commercial or mixed use development Application for a water connection to a commercial or mixed use development Providing clean, safe water: It s part of our Blueprint for Yorkshire Your application form for a water connection to a commercial

More information

East Riding of Yorkshire Council

East Riding of Yorkshire Council East Riding of Yorkshire Council Lead Local Flood Authority Interim Standing Advice Revision A - April 2015 1. Introduction From April 2015 the Lead Local Flood Authority (LLFA) became a statutory consultee

More information

Water Leakage & Your Responsibilities

Water Leakage & Your Responsibilities Water Leakage & Your Responsibilities Information & Guidance Contents 1. Introduction 2. Who is responsible for underground pipework? 3. Who is responsible for repairing the supply pipe if there is a leak?

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled

More information

Your guide to sewer flooding

Your guide to sewer flooding Your guide to sewer flooding We re here to help 2 Severn Trent Water Your guide to sewer flooding This leaflet has been produced to give you further information on: What causes sewer flooding Who is responsible

More information

code of practice for household customers

code of practice for household customers leakage code of practice for household customers Our household leakage policy This policy applies to any customer whose service pipe supplies water to premises which are occupied wholly as a household

More information

Guide to working on Public Sewers

Guide to working on Public Sewers Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to

More information

A Property Owner s Guide

A Property Owner s Guide The Operation and Maintenance of Domestic and Commercial Sewers A Property Owner s Guide KILDARE LOCAL AUTHORITIES WATER SERVICES DEPARTMENT TABLE OF CONTENTS Introduction 1. Why should I care? 2. What

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

Leakage Code of Practice. Domestic Customers

Leakage Code of Practice. Domestic Customers Leakage Code of Practice Domestic Customers A Leakage Code of Practice Domestic Customers The advice in this Leakage Code of Practice is important and has been approved by the Water Services Regulation

More information

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE 1 of 13 Affinity Water Limited CODE OF PRACTICE ON LEAKAGE LEAKAGE FROM DOMESTIC CUSTOMERS WATER SUPPLY PIPES Dated: 10 July 2014 1 INTRODUCTION 2 of 13 The Company is committed to a policy of water efficiency

More information

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...

More information

www.dorsetforyou.com/pollution

www.dorsetforyou.com/pollution www.dorsetforyou.com/pollution Waste water is normally removed from your home via a system of underground pipes consisting of both drains and sewers. There is usually a separate system for rainwater and

More information

guide for obtaining new water and waste water services

guide for obtaining new water and waste water services You can write to us at: Customer Connections Scottish Water 419 Balmore Road Glasgow G22 6NU Please quote this reference code when contacting us: SWP&DS/DG2 04/08 Alternative formats of this leaflet can

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES

Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES Sewers and Drains A GUIDE TO MAINTENANCE RESPONSIBILITIES This leaflet about drains and sewers has been prepared by Breckland Council and gives information and advice to private and commercial property

More information

DATED 2013 THE COUNCIL OF THE CITY OF WAKEFIELD. and WAKEFIELD WASTE PFI LIMITED. and YORKSHIRE WATER SERVICES LIMITED DEED OF GRANT OF EASEMENT

DATED 2013 THE COUNCIL OF THE CITY OF WAKEFIELD. and WAKEFIELD WASTE PFI LIMITED. and YORKSHIRE WATER SERVICES LIMITED DEED OF GRANT OF EASEMENT DATED 2013 THE COUNCIL OF THE CITY OF WAKEFIELD and WAKEFIELD WASTE PFI LIMITED and YORKSHIRE WATER SERVICES LIMITED DEED OF GRANT OF EASEMENT Relating to sewers in land at the former South Kirkby Colliery

More information

Foul Drainage, systems and responsibility. Environmental Protection

Foul Drainage, systems and responsibility. Environmental Protection Foul Drainage, systems and responsibility Environmental Protection The Building Act 1984 The Building Act 1984 can be used to deal with unsatisfactory provision for drainage and appliances which are harmful

More information

Essential Water. Customer Charter

Essential Water. Customer Charter Essential Water Customer Charter Who is Essential Water? Essential Water is a division of Essential Energy and provides water supply services to over 20,000 people in Broken Hill, Menindee, Sunset Strip

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

guidance notes Form C

guidance notes Form C guidance notes Form C These guidance notes are designed to help you complete Form C Application for new water infrastructure and plot(s) connection for industrial/commercial development(s) Important: Form

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

DISTRIBUTION CONNECTION

DISTRIBUTION CONNECTION DISTRIBUTION CONNECTION POLICY Page 1/15 TABLE OF CONTENTS 1 Introduction... 3 2 Acceptance of requests for a connection... 3 2.1 Who can request a connection... 3 2.2 How to request a connection... 4

More information

Subject: WW Resp II 15/04430/FUL & 15/04715/FUL The Royal High School

Subject: WW Resp II 15/04430/FUL & 15/04715/FUL The Royal High School Sammy Grimsby From: Mike Fox Sent: 10 February 2016 10:04 To: Cc: Kelly Brown; Sasha Berezina Subject: RE: WW Resp II 15/04430/FUL & 15/04715/FUL The Royal High School Thanks

More information

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993 AS AN OWNER BUILDER building work? What records should I keep? Is insurance required? W I need approval for? What do I need approval for? How do I obtain building work? How do I obtain approval? What records

More information

for sewerage customers on a water meter

for sewerage customers on a water meter 022BWN0091 Welcome to Wessex Water for sewerage customers on a water meter Contents Welcome Welcome 3 About Wessex Water 4 Your sewerage service 5 Advice for avoiding blockages 7 Your bill 8 Our service

More information

APPLICATION FOR INDIVIDUAL WATER & WASTEWATER FACILTIES

APPLICATION FOR INDIVIDUAL WATER & WASTEWATER FACILTIES INDIAN HEALTH SERVICE APPLICATION FOR INDIVIDUAL WATER & WASTEWATER FACILTIES Please retain top information section for your records and return the application section to your tribal IHS liaison. Homeowner

More information

Application for the Alteration of a Gas Supply

Application for the Alteration of a Gas Supply Application for the Alteration of a Gas Supply SSE Enterprise Utilities is a trading name of SSE Utility Solutions Limited which is part of the SSE Group. The Registered Office of SSE Utility Solutions

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

ORDINANCE NO. 2013 -

ORDINANCE NO. 2013 - ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION

More information

For more information. This leaflet is available on request in other formats such as large print and languages other than English.

For more information. This leaflet is available on request in other formats such as large print and languages other than English. For more information This Code of practice is approved by Ofwat and forms part of a suite of code of practice leaflets available to customers. This leaflet is available on request in other formats such

More information

Prepare a drainage system layout and specification notes for a low- rise building.

Prepare a drainage system layout and specification notes for a low- rise building. STUDENT MATERIALS Prepare a drainage system layout and specification notes for a low- Outcome 1 - rise building. In this outcome you will study the technology of below and above ground drainage systems.

More information

Replacing lead and common supply pipes

Replacing lead and common supply pipes Replacing lead and common supply pipes How do I know if I have lead pipes? If your home was built before 1970, there s a chance that your water supply pipe is made from lead. This is the pipe that brings

More information

Our sewerage services - how we deal with your used water. www.nwl.co.uk

Our sewerage services - how we deal with your used water. www.nwl.co.uk Our sewerage services - how we deal with your used water www.nwl.co.uk Our sewerage services A sewer is a pipe which carries and removes either rain water or foul water from more than one property. This

More information

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Applicant Details Name: Postal Address: Telephone Home: Work: Signed: Date: Proposed Contractor: Proposed Start Date:

More information

GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES

GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES CUSTOMER SERVICES DIVISION GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES September 2000 FOREWORD This document provides guidelines for the structural

More information

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and

More information

The Pipelines Regulations, 2000

The Pipelines Regulations, 2000 PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21. NOTE: This consolidation is not

More information

Shire of Coolgardie. Waste Water Services. Customer Service Charter for. Waste Water Services. Revision One Updated June 2014. Shire of Coolgardie

Shire of Coolgardie. Waste Water Services. Customer Service Charter for. Waste Water Services. Revision One Updated June 2014. Shire of Coolgardie Shire of Coolgardie Waste Water Services Customer Service Charter for Waste Water Services Shire of Coolgardie Irish Mulgar Drive, Kambalda Bayley Street, Coolgardie Revision One Updated June 2014 Postal

More information

MOBILE HOME LAW. Revised November 2001

MOBILE HOME LAW. Revised November 2001 MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

www.defra.gov.uk Annex B

www.defra.gov.uk Annex B www.defra.gov.uk Annex B National Build Standards Design and Construction of new gravity foul sewers and lateral drains Water Industry Act 1991 Section 106B Flood and Water Management Act 2010 Section

More information

PEEL WATER NETWORKS LIMITED STANDARDS OF SERVICE SCHEME

PEEL WATER NETWORKS LIMITED STANDARDS OF SERVICE SCHEME PEEL WATER NETWORKS LIMITED STANDARDS OF SERVICE SCHEME Peel Water Networks Limited, Peel Dome, The Trafford Centre, Manchester. M17 8PL Registered No: 6680258 Table of Contents Table of Contents...2 1.

More information

A quick guide to our floodcare scheme

A quick guide to our floodcare scheme A quick guide to our floodcare scheme What to do in case of sewer flooding We re here to help We appreciate that dealing with the results of sewage flooding is always unpleasant and we know how upsetting

More information

How To Apply For Land Division In Australia

How To Apply For Land Division In Australia Development Act 1993 GUIDE FOR APPLICANTS Land Division Guide GUIDE FOR APPLICANTS Land Division Guide Planning SA Primary Industries and Resources SA 136 North Terrace Adelaide GPO Box 1815 South Australia

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS Village of Airmont BUILDING AND ZONING DEPARTMENT 251 CHERRY LANE, AIRMONT, NEW YORK Mailing Address: P.O. BOX 578, TALLMAN, NEW YORK 10982 Telephone: 845-369-8813 Fax: 845-357-8307 Website: www.airmont.org

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

SECTION 3 SANITARY SEWER DESIGN

SECTION 3 SANITARY SEWER DESIGN SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary

More information

Emergency Services in Dorset County

Emergency Services in Dorset County Organisations 24 Hour Response Appendix 3 Dorset County Council CBC/EDDC Dorset Waste Partnership Environment Agency Highway maintenance and flooding Assistance with sandbags Social Services Our out of

More information

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Application No: 11/2196N Location: Proposal: Applicant: Expiry Date: K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Extension and New Store Mr Dan Mellor 17-Aug-2011 SUMMARY RECOMMENDATION Approve

More information

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public

More information

Knock Down Rebuild. Building Process Building process - knock down rebuild 1

Knock Down Rebuild. Building Process Building process - knock down rebuild 1 Knock Down Rebuild Building Process Building process - knock down rebuild 1 Building Process Your action Our action REMINDER Pre site Step 1 New Home Selection Congratulations. This marks the start of

More information

Single House New Connections A Quick Reference Guide

Single House New Connections A Quick Reference Guide Single House New Connections A Quick Reference Guide To assist with all aspects of water and waste water connection to the public network Including conversions from private water supplies 1. Why might

More information

WIN. Factoring Services News. Factoring Services News. Common repairs what happens! page 6. worth of vouchers

WIN. Factoring Services News. Factoring Services News. Common repairs what happens! page 6. worth of vouchers Factoring news for homeowners in mixed tenure blocks in East Renfrewshire www.eastrenfrewshire.gov.uk/housing Winter 2015 Factoring Services News Complete our customer satisfaction survey inside this edition

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

TOWNSVILLE WATER Customer Service Standards

TOWNSVILLE WATER Customer Service Standards TOWNSVILLE WATER Customer Service Standards CONTENTS Townsville Water who are we? 3 What is the Customer Service Standard? 3 >> Does the Customer Service Standard apply to me? 3 >> What will Townsville

More information

Relocating your household water meter 2015/2016

Relocating your household water meter 2015/2016 Relocating your household water meter 2015/2016 Moving your water meter is no ordinary piece of DIY. It s a precise job that has to follow certain rules to keep everything flowing smoothly. This leaflet

More information

Your Guide to Household Water Metering

Your Guide to Household Water Metering Your Guide to Household Water Metering Introduction It s generally considered that it s fairer to pay for the amount of water you actually use, rather than by a fixed amount. After all, you pay for electricity

More information

Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References

Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References Introduction General This Technical Booklet has been prepared by the Department of the Environment for Northern Ireland and provides for certain methods and standards of building which, if followed, will

More information

A Guide to the Design Build Process

A Guide to the Design Build Process A Guide to the Design Build Process Essential reading for anyone considering or undertaking building work We are an affiliation of Chartered Architects and Chartered Building Surveyors who together provide

More information

ARLINGTON COUNTY CODE. Chapter 18 PLUMBING AND GAS CODES

ARLINGTON COUNTY CODE. Chapter 18 PLUMBING AND GAS CODES Chapter 18 18-1. Title and Scope. 18-2. Definitions. 18-3. Availability of Codes. 18-4. Administration and Enforcement. 18-5. Registration of Contractors and Certification Requirements. 18-6. Permits and

More information

Does Part of My Basement Floor Have to Be Removed to Install. Where Does the Water from the Sump Pump Go?...Page 5

Does Part of My Basement Floor Have to Be Removed to Install. Where Does the Water from the Sump Pump Go?...Page 5 PROTECTIVE PLUMBING - WHAT IS IT? TABLE OF CONTENTS Protective Plumbing What is it?...page 1 What is Foundation Drainage?...Page 2 What is a Sump Pumping System?...Page 4 Does Part of My Basement Floor

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

ab YOUR GUIDE TO THE LEGAL PROCESS FOR SELLING A PROPERTY

ab YOUR GUIDE TO THE LEGAL PROCESS FOR SELLING A PROPERTY YOUR GUIDE TO THE LEGAL PROCESS FOR SELLING A PROPERTY Selling a house or flat is almost certainly one of the most important transactions you'll ever make. Obviously you want to get it right, and it's

More information

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk ALL YOUR NEEDS Tel: 01384 482228 www.midlanddrainage.co.uk Welcome to Midland Drainage Services Midland Drainage Services is a family owned and operated Drainage Company, based in the West Midlands and

More information

Application for a predevelopment enquiry

Application for a predevelopment enquiry Application for a predevelopment enquiry Guidance notes thameswater.co.uk Guidance notes - Pre development enquiry Pre development enquiries are designed to aid developers and their consultants in understanding

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION

BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION BUYING OR LEASING A COMMERCIAL PROPERTY THE LEGAL PROCESS INITIAL INSTRUCTIONS TO COMPLETION Buying or leasing commercial premises is often a large financial and long term commitment. It is always advisable

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Household customer. Wastewater flooding guidelines. www.thameswateruk.co.uk

Household customer. Wastewater flooding guidelines. www.thameswateruk.co.uk Household customer Wastewater flooding guidelines www.thameswateruk.co.uk We are very sorry that you have recently suffered wastewater flooding to your property. This leaflet has been designed to answer

More information

Business Charter. Our promise and guarantees to you

Business Charter. Our promise and guarantees to you Business Charter Our promise and guarantees to you About our Business Charter We re committed to providing the highest quality services and by law we must meet certain standards. This leaflet explains

More information

SECTION IX SLIP LINING PIPELINES

SECTION IX SLIP LINING PIPELINES AN SECTION IX SLIP LINING PIPELINES February, 2008 TABLE OF CONTENTS SECTION IX - SLIP LINING PIPELINES 9.01.00 GENERAL...2 9.01.01 SCOPE... 2 9.02.00 MATERIAL...2 9.03.00 CONSTRUCTION...2 9.03.01 REQUIREMENTS...

More information

CHAPTER 32 PLUMBING CODE

CHAPTER 32 PLUMBING CODE CHAPTER 32 PLUMBING CODE 32.01 DEFINITION Plumbing for the purpose of this chapter is hereby defined as follows: (a) As is stated in Section 145.01 (1), (a), (c), (d), and (e) of the Wisconsin Statutes.

More information

Conveyancing Guide. We welcome you as a client of Tyndallwoods and thank you for your instructions. Conveyancing has two basic stages

Conveyancing Guide. We welcome you as a client of Tyndallwoods and thank you for your instructions. Conveyancing has two basic stages Conveyancing Guide We welcome you as a client of Tyndallwoods and thank you for your instructions. This guide is part of the Tyndallwoods commitment to quality of service. We are well aware that moving

More information

New Home Construction Packet

New Home Construction Packet New Home Construction Packet Congratulations! You are building a new home in Meyerland. This packet of information was assembled to assist you with the process. It contains all the forms that you will

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

Finding and fixing leaks Our Code of Practice for leakage from domestic water supplies

Finding and fixing leaks Our Code of Practice for leakage from domestic water supplies Finding and fixing leaks Our Code of Practice for leakage from domestic water supplies water Finding and fixing your leaks Sutton and East Surrey Water has one of the lowest levels of water leakage in

More information

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Application No: 11/2196N Location: Proposal: Applicant: Expiry Date: K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Extension and New Store Mr Dan Mellor 17-Aug-2011 SUMMARY RECOMMENDATION Approve

More information

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS -

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS - ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS - INSTRUCTIONS TO DESIGNERS CONTENTS 1. INTRODUCTION 3 2. ROLE OF THE WATER SERVICING COORDINATOR 3 3. ROLE OF THE DESIGNER 3 4.

More information

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01. Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

PERMISSION A GUIDE FOR EXTENDING A DETACHED OR SEMI-DETACHED HOUSE

PERMISSION A GUIDE FOR EXTENDING A DETACHED OR SEMI-DETACHED HOUSE PLANNING PERMISSION A GUIDE FOR EXTENDING A DETACHED OR SEMI-DETACHED HOUSE Introduction Foreword by Councilor Dave Smith - Chair of the Planning & Highways Committee. Planning Permissions B Owners of

More information

OVER-HEAD SEWER ASSISTANCE GRANT

OVER-HEAD SEWER ASSISTANCE GRANT OVER-HEAD SEWER ASSISTANCE GRANT The Village of North Aurora has a vested interest in the proper operation of the North Aurora sanitary system. Understanding that some residential users of the sanitary

More information

Development enquiry request

Development enquiry request Development enquiry request Water supply and/or drainage capacity assessment for a proposed development NOTE: Please ensure all relevant sections of the application are completed and refer to the attached

More information

EXPLANATORY NOTES & CONDITIONS

EXPLANATORY NOTES & CONDITIONS ON FARM SCHEME OF GRANT AID FOR THE DEVELOPMENT OF THE ORGANIC SECTOR EXPLANATORY NOTES & CONDITIONS It is important to read the Explanatory Notes and Conditions before making application under this Scheme

More information

Repair and Renew Grant. Croydon RRG Scheme

Repair and Renew Grant. Croydon RRG Scheme Repair and Renew Grant Croydon RRG Scheme Development & Environment April 2014 Croydon Repair and Renew Grant Scheme Support for independent businessess and property owners affected by flooding December

More information