National Grid. The Narragansett Electric Company. Docket No. December 27, Submitted by: Submitted to: Rhode Island Public Utilities Commission

Size: px
Start display at page:

Download "National Grid. The Narragansett Electric Company. Docket No. December 27, 2012. Submitted by: Submitted to: Rhode Island Public Utilities Commission"

Transcription

1 National Grid Gas Infrastructure, Safety, and Reliability Plan FY 2014 Proposal December 27, 2012 Docket No. Submitted to: Rhode Island Public Utilities Commission Submitted by:

2 Thomas R. Teehan Senior Counsel December 27, 2012 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI RE: National Grid s Proposed FY 2014 Gas Infrastructure, Safety, and Reliability Plan Docket No. Dear Ms. Massaro: On behalf of National Grid 1, I have enclosed ten (10) copies of the Company s proposed Gas Infrastructure, Safety, and Reliability Plan (the Gas ISR Plan or Plan ) for fiscal year This proposed Gas ISR Plan is designed to enhance the safety and reliability of the Company s Rhode Island natural gas distribution system. The proposed Plan was submitted to the Division of Public Utilities and Carriers ( Division ) for review. The Company received and responded to discovery requests from the Division and has met with the Division s representatives regarding this proposed Plan. The Division has agreed to the overall spending portion of this plan, but will continue to review and discuss particular Plan provisions as the Commission conducts its proceeding in this matter. The Gas ISR Plan is designed to protect and improve the gas delivery system through proactively replacing leak-prone gas mains and services, upgrading the system s pressure regulating systems, responding to emergency leak situations, and addressing conflicts that arise out of public works projects. The Plan is intended to achieve these safety and reliability goals through a cost-effective, coordinated work plan. The level of work that the Plan provides will sustain and enhance the safety and reliability of the Rhode Island gas pipeline infrastructure and directly benefit all Rhode Island gas customers. The Plan includes a description of the categories of work the Company proposes to perform in fiscal year 2014 as well as the proposed targeted spending levels for each work category. This filing includes the pre-filed direct testimony of three witnesses: Mr. Walter F. Fromm, whose testimony introduces the Plan document; Mr. William R. Richer, whose testimony explains the Company s revenue requirement 1 (hereinafter referred to as National Grid or the Company ). 2 The Gas ISR Plan is submitted in compliance with the provisions of R.I.G.L

3 Luly Massaro FY 2014 Gas ISR Plan December 27, 2012 Page 2 of 2 calculation; and Ms. Mariella C. Smith, whose testimony describes the rate design and calculation of the ISR rate factors and provides the customer bill impacts of the proposed ISR factor rates. For the average residential heating customer using 846 therms, the cumulative impact of the FY 2014 Gas ISR Plan will represent an annual increase of $2.09, or 0.2 percent. This ISR Plan presents an opportunity to facilitate and encourage investment in the Company s gas utility infrastructure and enhance its ability to provide safe, reliable, and efficient electric service to customers. Thank you for your attention to this transmittal. If you have any questions, please feel free to contact me at (401) Very truly yours, Enclosures Thomas R. Teehan cc: Steve Scialabba Leo Wold, Esq. James Lanni

4 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PRE-FILED DIRECT TESTIMONY OF WALTER F. FROMM December 27, 2012

5 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM Table of Contents I. Introduction and Qualifications... 1 II. Purpose of Testimony... 2 III. Overview IV. Capital Investment Plan... 6

6 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 1 OF I. INTRODUCTION AND QUALIFICATIONS Q. Please state your name, business address, title and areas of responsibility. A. My name is Walter F. Fromm. My business address is 40 Sylvan Road, Waltham, Massachusetts I am employed by National Grid USA Service Company, Inc. ( National Grid ) as Manager, Network Strategy-Gas. I am the Rhode Island state Jurisdictional Lead for all gas Network Strategy issues, including those related to the capital investment strategy for ( Narragansett or the Company ). In my role, I work closely with the Rhode Island Jurisdictional President and staff on all local issues related to the Company s Rhode Island gas system. My responsibilities also include working with regulators on issues related to the gas system, development of strategies to support Company objectives regarding investment in the gas system, and to provide testimony regarding capital investments in the Company s gas system during state regulatory proceedings Q. Please describe your educational background and professional experience. A. I am a Professional Engineer in Massachusetts (#40443) and New Hampshire (#11271). I received a Bachelor of Science degree in Civil Engineering from the University of Massachusetts at Lowell. My experience includes working for approximately two and a half years as a Design Engineer at the Boston Water and Sewer Commission, performing engineering, design, and environmental permitting associated with the construction of new and replacement water, sewer and drainage facilities. I spent almost five years

7 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 2 OF working as a Project Engineer at Fay, Spofford & Thorndike, Inc., continuing my career in the utility engineering and environmental permitting field. I have been employed at National Grid for approximately 13 years in a variety of roles. I joined National Grid as the Supervisor of Short-Term Planning. I later became a Senior Gas Engineer, then Principal Gas Engineer, Manager of Project Engineering & Design, and Manager of Main & Service Replacement. In March 2012, I assumed my current responsibilities Q. Have you previously testified or appeared before the Rhode Island Public Utilities Commission (the Commission )? A. Yes. I previously testified before the Commission at hearings and technical conferences regarding the Company s Accelerated Replacement Program and regarding the subsequent fiscal year ( FY ) 2012 Gas Infrastructure, Safety, and Reliability ( ISR ) Plan. I also provided pre-filed direct testimony for the Company s FY 2012 Gas ISR reconciliation filing in Docket No In addition, I also testified and represented the Company at hearings and technical conferences for the FY 2013 Gas ISR Plan in Docket No II. PURPOSE OF TESTIMONY Q. What is the purpose of your testimony? A. The purpose of my testimony is to describe the Company s proposed Gas ISR Plan for FY

8 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 3 OF ( ISR Plan or the Plan ) 1. Through my testimony, I provide the Commission with Exhibit 1, the Company s proposed FY 2014 Gas ISR Plan, which details the work to be done under the proposed ISR Plan and the anticipated capital investments associated with that work. Mr. William R. Richer is providing testimony on the calculation of the revenue requirement impact associated with the Company s proposed FY 2014 Gas ISR Plan, and Ms. Mariella C. Smith is providing testimony relative to (1) how the rate design was established for the ISR mechanism; (2) the calculation of the ISR rate factors; and (3) the customer bill impacts of the proposed ISR factor rates III. OVERVIEW Q. How was the ISR Plan prepared? A. The Company s FY 2014 Gas ISR Plan was prepared by the Company and submitted to the Division of Public Utilities and Carriers (the Division ) for review. The Company met with the Division and responded to questions from the Division about each of the components of the Plan, including the inclusion of a gas expansion pilot program. The Division agreed to the spending portion of the Plan and will continue to review particular Plan provisions as the Commission conducts its proceeding in this matter. The proposed ISR Plan will allow the Company to meet state and federal safety and reliability requirements and to maintain its gas distribution system in a safe and reliable condition. 1 Pursuant to Rhode Island statutory provisions, the Company is required to annually file an infrastructure, safety, and reliability spending plan with the Commission for review and approval. (R.I.G.L ) In addition to budgeted spending, the annual ISR Plan is to contain a reconcilable allowance for the anticipated capital investments and other spending for the upcoming fiscal year. The Company s FY 2014 runs from April 1, 2013 through March

9 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 4 OF The FY 2014 ISR Plan should improve the safety and reliability of the Company s gas system for the immediate and long-term benefit of Rhode Island s natural gas customers Q. What is the ISR Plan designed to accomplish? A. The Gas ISR Plan is designed to maintain and upgrade the Company s gas delivery system proactively replacing leak-prone gas mains and services, upgrading the system s pressure regulating systems, responding to emergency leak situations, and addressing conflicts that arise out of public works projects. The Plan attempts to attain these safety and reliability goals through a cost-effective, coordinated work plan. The level of work that the Plan provides will sustain and enhance the safety and reliability of the Rhode Island gas pipeline infrastructure and directly benefit Rhode Island gas customers. The Company now submits this Plan to the Commission for final review and approval Q. Are you sponsoring any exhibits through your testimony? A. Yes. The Company s proposed FY 2014 Gas ISR Plan document is attached as Exhibit 1 to my testimony. It is organized as follows: Section 1 Introduction and Summary Section 2 Gas Capital Investment Plan (including major categories of work) Section 3 Revenue Requirement Calculation 31, 2014, and the proposed ISR Plan would be effective April 1, Pursuant to R.I. G. L (d), the Company and the Division are to work together over the course of 60 days in an attempts to reach an agreement on a proposed plan, which would then be submitted to the Commission for review and approval.

10 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 5 OF Section 4 Rate Design Section 5 Bill Impacts As noted above, Mr. Richer will testify about and sponsor the revenue requirement calculation included in Section 3 of the Gas ISR Plan, and Ms. Smith will testify about and sponsor rate design and bill impacts outline in Sections 4 and 5 of the Plan Q. What types of infrastructure, safety, and reliability work does the proposed ISR Plan include? A. The Plan seeks not only to maintain the gas distribution system, but also to proactively upgrade its condition to prevent problems before they arise. A safe and reliable gas delivery system in Rhode Island is essential to the health, safety, and well-being of its citizens and is functional to maintaining a healthy economy and continuing to attract new residents and businesses. The Commission embarked on a course of addressing Rhode Island s aging gas infrastructure in 2008, with the establishment of the Accelerated Replacement Plan (the ARP ). In addition to the type of infrastructure, safety and reliability work performed under the ARP, the ISR Plan includes spending related to safety and reliability for public works, mandated programs, special projects, and reliability programs. Included in the ISR Plan document is a description of the Company s proposed budget for capital investment for FY 2014 and a capital forecast for FY 2014 through FY

11 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 6 OF 7 1 IV. CAPITAL INVESTMENT PLAN Q. What levels of spending are proposed in the ISR Plan? A. For FY 2014, the Company proposes ISR spending totaling $65.3 million. The ISR Plan is broken down into categories of programs designed to maintain the safety and reliability of the Company s gas delivery infrastructure. For each program category in the Plan, the Company proposes the following levels of spending: $36.5 million combined for proactive Main and Service Replacement Programs. $0.5 million for Reactive Main Replacement. $1.8 million for Public Works Programs. $13.5 million for Mandated Programs (capital leak repairs, meter replacements, corrosion and non-leak other) $9.0 million for Gas System Reliability, including work relative to System Automation and Gas Control, Pressure Regulating Facilities (including Heater Program, Vent Pole Installation and Control Line Integrity Work), System Reliability Enhancement, Water Intrusion Program, LNG Facilities, and Valve Installation/Replacement. $4.0 million for Special Projects, including the carryover of new main installation work related to the relocation of I- 195 in order to aid in the economic development of Downtown Providence, the replacement of a boil-off compressor at the Exeter LNG Facility, and the introduction of a pilot program designed to provide commercial and residential customers with incentives for gas expansion pilot program.

12 THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID R.I.P.U.C. DOCKET NO. RE: FY 2014 GAS INFRASTRUCTURE, SAFETY, AND RELIABILITY PLAN WITNESS: WALTER F. FROMM PAGE 7 OF Q. In your opinion, does the Gas ISR Plan fulfill the requirements established in relation to the safety and reliability of the Company s gas distribution system in Rhode Island? A. Yes. The Gas ISR Plan for FY 2014 is designed to establish the capital investment in Rhode Island that is necessary to meet the needs of its customers and maintain the overall safety and reliability of the Company s Rhode Island gas distribution system Q. Does this conclude your testimony? A. Yes, it does.

13 DOCKET NO. National Grid Gas Infrastructure, Safety, and Reliability Plan FY 2014 Proposal December 27, 2012 Submitted to: Rhode Island Public Utilities Commission Submitted by:

14 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Table of Contents Section 1: Introduction and Summary... Section 2: Gas Capital Investment Plan... A. Main Replacement Program and Service Replacement Program B. Reactive Main Replacement C. Public Works D. Mandated Programs E. Reliability F. Special Projects Section 3: Revenue Requirement... Section 4: Rate Design... Section 5: Bill Impacts...

15 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Section 1 Introduction and Summary

16 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Page 1 of 5 Introduction and Summary FY 2014 Proposal National Grid 1, in consultation with the Division of Public Utilities and Carriers ( Division ), has developed the following proposed fiscal year ( FY ) 2014 gas infrastructure, safety, and reliability ( Gas ISR ) plan (the Gas ISR Plan or Plan ) in compliance with R.I.G.L (c)(2) (the Decoupling Act ), which provides for an annual gas infrastructure, safety and reliability spending plan for each fiscal year and an annual rate reconciliation mechanism that includes a reconcilable allowance for the anticipated capital investments and other spending pursuant to the annual pre-approved budget The proposed Gas ISR Plan addresses capital spending on gas infrastructure and other costs relating to maintaining the safety and reliability of the gas distribution system. The proposed Plan that the Company is submitting for its gas distribution operations is the product of a collaborative effort with the Division. The Gas ISR Plan is designed to maintain and upgrade the Company s gas delivery system through proactively replacing leak-prone gas mains and services, accelerating the Company s replacement of leak prone facilities, upgrading the system s pressure regulating systems, responding to emergency leak situations, and addressing conflicts that arise out of public works projects. The Plan attempts to achieve these safety and reliability goals through a cost-effective, coordinated work plan. The level of work the Plan provides will sustain 1 2 (hereinafter referred to as National Grid or the Company ). R.I.G.L , An Act Relating to Public Utilities and Carriers Revenue Decoupling.

17 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Page 2 of 5 and enhance the safety and reliability of the Rhode Island gas pipeline infrastructure and directly benefit Rhode Island gas customers. The Company now submits this plan to the Rhode Island Public Utilities Commission ( Commission ) for final review and approval. 3 This Introduction and Summary presents an overview of the proposed FY 2014 Plan for the statutory categories of costs, the resulting FY 2014 revenue requirement associated with the proposed Gas ISR Plan (in conjunction with the base rate proceeding in Docket No. 4323), an illustrative tariff provision enabling the rate adjustments and mechanism underlying the proposed Gas ISR Plan, an illustrative rate design, and the estimated typical bill impacts resulting from the illustrative rate design. The proposed Gas ISR Plan describes the Company s multi-year plan upon which its FY 2014 Plan is based, and it describes the system safety and reliability activities and addresses capital investment in utility infrastructure for the upcoming fiscal year. The proposed Plan also itemizes the recommended work activities by general category and provides budgets for capital investment. As envisioned in the Revenue Decoupling Statute, after the end of the fiscal year, the Company would true up the Gas ISR Plan s budgeted levels to actual investment and expenditures and reconcile the revenue requirement associated with the actual investment and expenditures to the revenue billed from the rate adjustments implemented at the beginning of each fiscal year. The Company will continue to file quarterly reports with the Division and 3 Pursuant to R.I.G.L (d), the Company and the Division must work together over the course of 60 days in an attempt to reach an agreement on a proposed plan, which would then be submitted to the

18 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Page 3 of 5 Commission concerning the progress of its Gas ISR programs. In addition, when the Company makes its reconciliation and rate adjustment filing described below, it will file an annual report on the prior fiscal year s activities. The Company is cognizant that, in implementing the Gas ISR Plan in any fiscal year, the circumstances encountered during the year may require reasonable deviations from the original Gas ISR Plan. In such cases, the Company would include an explanation of any significant deviations in its quarterly reports. The FY 2014 level of capital investment provided in the Company s proposed Gas ISR Plan to maintain the safety and reliability of its gas delivery infrastructure is $65.3 million. A description of the Company s proposed capital investment plan for FY 2014 is provided in Section 2. The revenue requirement description and calculations are contained in Section 3. Gas Capital Investment Plan The Company s proposed gas capital investment plan contained in Section 2 summarizes capital investments in terms of the following key categories: Main Replacements and Service Replacements, Reactive Main Replacements, Public Works, Mandated Programs, Gas System Reliability, and Special Projects. Section 2 itemizes the proposed activities by sub-categories and provides budgets for capital investment. The Company proposes that capital investments be recovered in a manner consistent with the calculation of the rate base in Docket No and in conjunction with the Company s base rate filing in Docket No The Company has included its capital budget, identified the relevant projects that would be part of the FY 2014 Gas Commission for its review and approval.

19 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Page 4 of 5 ISR Plan, and provided its explanation of why these projects are necessary to provide safe and reliable service to its customers. The Company has also provided a five-year capital plan to provide a longer-term approach to infrastructure, safety, and reliability and to demonstrate how the FY 2014 Plan would be incorporated into that longer-term planning approach. Revenue Requirement Based upon the estimated amounts for the proposed Plan, the Company has provided a calculation of the proposed revenue requirement resulting from the proposed FY 2014 capital investment plan. Section 3 contains a description of the revenue requirement model and an illustrative calculation for FY This calculation would form the basis for the Gas ISR rate adjustment, which would become effective April 1, 2013, upon Commission approval. As provided in Section 3, Schedule A, Sheet 6 of the Company s gas tariff, the Company will reconcile this rate adjustment as part of its annual Distribution Adjustment Charge ( DAC ) filing. The pre-tax rate of return on rate base would be that rate of return approved by the Commission in the Company s last general rate case and, going forward, it would change as the Commission may approve changes to the rate of return in future rate case proceedings. Any change in the rate of return would be applicable on a prospective basis effective on the date on which the change is effective. Rate Design The revenue requirement calculated under the proposed Gas ISR Plan is appropriately allocated to the Company s rate classes. For purposes of rate design, the revenue requirement

20 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 1: Introduction and Summary Page 5 of 5 associated with the capital investment is allocated to rate classes based upon the rate base allocator from the Company's Settlement agreement in Docket No For rate classes, the allocated revenue requirement is divided by the applicable fiscal year forecasted therm deliveries for each rate class, arriving at a per-therm factor unique to each rate class. Other related costs mutually agreed upon between the Division and the Company would be allocated to all rate classes on a consistent per-unit basis. The proposed rate design is contained in Section 4. Bill Impacts The estimated typical bill impacts associated with the rate design contained in Section 4 are provided in Section 5. Since the FY 2014 revenue requirement was based upon FY 2014 capital costs that were incremental to the FY 2014 capital costs included in the Company's base rates per the Settlement Agreement in Docket No. 4323, the Company used the base rates provided in its Settlement Agreement for both the current and proposed bill comparisons. In addition, because these base rates now include ISR capital costs for FY 2012 and FY 2013, the Company zeroed out the current ISR factor in the current analysis. As shown in Section 5, the bill impact of the Gas ISR Plan for the average residential heating customer for the period April 1, 2013 through March 31, 2014 would be $1.82, or 0.2 percent.

21 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Section 2 Gas Capital Investment Plan FY 2014 Gas ISR Plan

22 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 1 of 15 Gas Capital Investment Plan FY 2014 Proposal The Company and the Division have worked diligently to arrive at a Gas ISR Plan that meets the goals of the Decoupling Act to provide a safe and reliable gas distribution system for Rhode Island. Background The Company developed its proposed capital investment plan to meet its obligation to provide safe, reliable, and efficient gas distribution service for customers at reasonable costs. 4 The Gas ISR Plan includes capital investment spending needed to meet state and federal regulatory requirements applicable to the Company s gas system and to maintain its distribution infrastructure in a safe and reliable condition. It includes infrastructure, safety and reliability work for cast-iron and non-cathodically protected steel mains and non-cathodically protected steel inside services, to address the replacement of leak-prone gas main and at-risk services. The plan also contains capital spending related to safety and reliability for public works, mandated programs, gas reliability, and special projects, including a gas system expansion pilot program. As the Decoupling Act recognizes, in order to continue providing safe and reliable gas delivery service to customers, it is critical that the Company remain vigilant with respect to investing in its infrastructure and that it has the appropriate and timely cost recovery to do so. 4 The Company delivers natural gas to approximately 253,000 Rhode Island residential and commercial and industrial customers in 33 cities and towns in Rhode Island. To provide this service, the Company owns and maintains over 3,100 miles of mains and approximately 190,000 services.

23 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 2 of 15 To that end, the Company is outlining the proposed FY 2014 Plan, 5 which identifies the capital spending it expects to place into service during FY Table 1 contains a description of the proposed budget for the capital investment plan for FY Table 2 contains a five-year Capital Forecast for FY 2014 through FY The Company proposes to invest a total of $77.2 million, $65.3 million of ISR investments that would be included in either the rate base included in Docket No or in the FY 2014 Gas ISR recovery mechanism. 6 The FY 2014 Gas ISR Plan is designed to maintain the safety and reliability of the Company s gas delivery infrastructure. Table 3 includes the FY 2013 Capital Budget filed in the FY 2013 ISR Plan, along with the FY 2013 Forecast through Q As set forth on Table 1, of the $65.3 million that the Company proposes for its FY 2014 Gas ISR Plan spending, the Company proposes the following levels of spending for each category of programs: $36.5 million combined for proactive Main and Service Replacement Programs. $0.5 million for Reactive Main Replacement. $1.8 million for Public Works Programs. $13.5 million for Mandated Programs (capital leak repairs, meter replacements, corrosion and non-leak other). $9.0 million for Gas System Reliability, including work relative to System Automation and Gas Control, Pressure Regulating Facilities (including Heater Program, Vent Pole Installation and Control Line Integrity Work), System Reliability Enhancement, 5 6 FY 2014 is defined as the twelve months ending March 31, From the $77.2 million of total investment, the Company would remove $11.9 million of projected growth spending.

24 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 3 of 15 Water Intrusion Program, LNG Facilities, and Valve Installation/Replacement. $4.0 million for Special Projects, including the carryover of new main installation work related to the relocation of I-195 in order to aid in the economic development of Downtown Providence, the replacement of a boil-off compressor at the Exeter LNG Facility, and the introduction of a pilot program designed to provide commercial and residential customers with incentives in providing gas main extensions. The Company is excluding $11.9 million for growth spending from the proposed FY 2014 Gas ISR Plan. As noted above, the Company will continue to file quarterly reports with the Division on the progress of its Gas ISR programs. Description of Large Programs and Projects The proposed FY 2014 Gas ISR Plan is comprised of several programs that account for the total amount of plan spending for FY Those programs are described in detail below. A. Main Replacement Program and Service Replacement Program The value of, and need for, targeted spending on the replacement of leak-prone gas main and services is well-documented and has been accepted by both the Division and the Commission. For FY 2014, the Company forecasts spending $33.4 million on its main replacement program (approximately 50 miles of leak prone pipe) and $3.1 million on the service replacement program (1,100 services) for a total spend of $36.5 million on these two programs.

25 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 4 of 15 B. Reactive Main Replacement The Company proposes to spend $0.5 million in Reactive Main Replacement. This category of work consists of emergency main replacements due to leaks or other unplanned work where main condition dictates immediate replacement. Reactive Main Replacement would account for approximately 1.0 mile of emergency main replacements. C. Public Works The purpose of the Public Works program is to address existing gas infrastructure conflicts, as appropriate, to improve the safety and reliability of the Company s natural gas distribution system in conjunction with public works projects, providing significant incremental benefits to customers and communities. Municipal work affords the Company an opportunity to replace additional leak-prone pipe and reduce paving costs by coordinating the Company s main replacement work with these planned public works construction projects, while also benefitting customers and communities by improving service delivery and minimizing construction impacts and inconvenience. National Grid has an ongoing plan to replace targeted (integrity-based selections) mains on a risk-based approach. Integration of the Company s Integrity programs with the public works process has yielded increased system reliability and system integrity. This integration has also optimized capital spending through coordination with planned public works projects. While the primary purpose of Public Works spending is to address direct conflict with

26 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 5 of 15 existing gas infrastructure, Public Works spending provides the opportunity to coordinate other system improvement work, such as the replacement of leak-prone pipe, system reliability upgrades, the elimination of redundant main, and regulator station upgrades. The Company will manage multiple projects to address the dynamic nature of the public work process through effective liaison activity. Specifically, it must be recognized that, while municipal schedules and plans change due largely to funding, other factors also contribute to the scheduling of these projects (e.g. political, demand maintenance, etc.). Municipal changes in projects can and do create additional work in developing and coordinating the Company s planning and budgeting processes. Using the Company s five-year work planning process, the Company can provide some flexibility in scheduling, coordinating, and engineering projects in concert with municipal public works initiatives. For FY 2014, the proposed plan incorporates $1.8 million in spending under the Public Works category and an additional $1.3 million in reimbursable projects. D. Mandated Programs Spending for Mandated Programs falls into four categories: Corrosion, Meter Replacement, Capital Leak Repairs, and Non-leak Other. The Corrosion Program adds cathodic protection to existing coated steel main installed prior to U.S Department of Transportation ( DOT ) requirements (pre-1971). In 1971, the Code of Federal Regulations, Part 192, required the cathodic protection of all new buried steel gas facilities. Cathodic protection effectively extends the service life of buried steel facilities (as compared to

27 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 6 of 15 unprotected buried steel facilities) and can prolong replacement by twenty years or more. National Grid has standardized the process used to determine the cost-effectiveness of cathodically-protecting steel pipe installed prior to National Grid is targeting adding cathodic protection to ten miles of pre-1971 pipe during FY 2014 for the purpose of extending the life of the pipe. Capital costs for the Meter Replacement Program are required for the procurement of replacement meters. The Capital Leak Repair Program addresses leaking gas services and extends the useful life of cast iron mains through the encapsulation of leaking cast iron joints. Non-leak Other is associated with the capital costs for service relocations, meter protection, service abandonments, and the installation of curb valves. For FY 2014, the proposed plan includes $13.5 million for all categories of mandated work. E. Reliability Reliability spending includes programs to address system automation and control, system pressure regulating facilities (including heaters, vent pole installations and control line integrity), system reliability enhancement, water intrusion projects, LNG facilities, and valve installation and/or replacements. The proposed FY 2014 Gas ISR Plan includes $9.0 million in spending for Reliability. These programs are summarized below. 1. System Automation and Control The primary purpose of this program is to (a) meet the new DOT code requirements under 49 CFR Part 192, Docket ID , issued on December 3, These new code provisions contain the following pipeline

28 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 7 of 15 safety requirements: (a) Control Room Management/Human Factors, (b) modernization of the Company s system data and telemetry recording, and (c) increasing the level of system automation and control. The overall program will increase the safety, reliability, and efficiency of the gas system and, by extension, the level of service the Company provides to its customers. National Grid s ability to provide safe and reliable service is governed to a large extent by the Company s ability to maintain adequate pressure in its gas mains. To accomplish this task, National Grid has 205 pressure regulator stations disbursed throughout its Rhode Island gas service territory. While a limited number of these regulator stations have full system telemetry and control capability, most do not. In addition to monitoring and controlling the regulator stations, National Grid must also monitor system end points to ensure that adequate system pressures are being maintained in remote areas under a variety of operating conditions. Increased monitoring of these system low points is exacerbated by the need and desire to minimize the amount of system reinforcement necessary to support system load, thereby reducing our capital requirement, and to maximize the operational efficiency of the gas distribution system. National Grid is proposing implementation of a system automation and control program that would address approximately 20 percent of its pressure regulating facilities and adding select end-point monitoring. National Grid s

29 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 8 of 15 proposal for FY 2014 would provide AC power to fifty (50) regulator stations, telemetry to forty (40) sites and install remote controls at five (5) locations. 2. Pressure Regulating Facilities The pressure regulating facilities have been designed to reliably control system pressures and maintain continuity of supply during normal and critical gas demand periods. Each station has specific requirements for flows and pressures based on the anticipated needs of the station. A facility includes both pressure regulating piping and equipment as well as control lines, but may also include a heater or a scrubber. A program has been initiated to address condition-based assessments. Accepted engineering guidelines provide for design, planning, and operation of these gas distribution facilities. Applicable state and federal codes are followed to help ensure safe and continuous supply of natural gas to our customers and the communities we serve. National Grid s proposed plan would address condition-based assessments and perform work at the following facilities in FY 2014: Regulator Stations: 1. Elliot Street, N. Providence 2. Gentian, N. Providence 3. Wilson, Johnston 4. Taunton, E. Providence 5. Chestnut, Providence 6. Wood, Bristol 7. Division Street, East Greenwich 8. St. Georges, Middletown

30 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 9 of Tiverton Gate Main Road, Tiverton 10. Allens Avenue, Providence Heater Projects: 1. Route 116 Gate, Lincoln 2. Portsmouth Gate State, Portsmouth Control Line Projects: 1. Ann & Hope Way, Cumberland 2. North Bend Street, Pawtucket 3. North Country Club, Warwick 4. Traver Avenue, Johnston In addition to the work identified above, the Company is proposing to install vent poles at another twenty (20) pressure regulating facilities during FY System Reliability Enhancement Program The System Reliability Enhancement Program identifies projects that support system reliability through standardization and simplification of system operations (e.g., system up-ratings and de-ratings and regulator elimination), integration of systems (e.g. tie-ins) and new supply sources (e.g. take stations). 4. Water Intrusion Program The Water Intrusion Program identifies projects that address recurring customer outages resulting from water intrusion into low-pressure distribution systems through the replacement of existing leak-prone pipe. 5. LNG Facilities

31 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 10 of 15 LNG facility upgrades include replacement of aging equipment and infrastructure at the Rhode Island stations excluding the Providence facility. 6. Valve Installation/Replacement Valves are used to sectionalize portions of the gas network when required to support both planned and unplanned field activities. Valve replacement is necessary to ensure the Company s continued ability to effectively isolate portions of the distribution system as inoperable valves are identified. New valve installations are also occasionally needed to provide the capability to reduce the size of an isolation area where existing valves would result in broader shutdown than desired. F. Special Projects Three projects have been identified for FY The first project is the carryover of work associated with the Rhode Island Department of Transportation ( RIDOT ) project to relocate sections of interstate I-195 through the City of Providence. This work is required to safely and reliably serve the new parcels of land, and aid in the economic development of this area. The second project is the replacement of the boil-off compressor located the at Exeter LNG facility. The Company has had difficulty procuring parts to maintain the aging equipment, and believes that a replacement is a more prudent proactive approach to maintaining

32 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 11 of 15 plant reliability and safety. The third project is the Gas Expansion Pilot Program, which is described below. The Gas Expansion Pilot Program would provide for the prudent expansion of the Company s gas infrastructure to remove or reduce financial barriers that may prevent residential and commercial customers from taking advantage of historically low gas commodity prices. The recent abundance of natural gas supply has led to historically low commodity prices and a number of states are recognizing this market shift and are now examining programs that would expand the availability of natural gas as an energy source within their jurisdictions. Currently, in Rhode Island, customers may be required to pay a Contribution In Aid of Construction ( CIAC ) to help cover the costs associated with main extensions required to provide them gas service. This upfront capital cost can present a significant barrier for potential customers. The Gas Expansion Pilot Program seeks to remove or reduce this impediment by supporting projects that have the opportunity to bring gas service to more customers where the costs described above would otherwise have acted as a barrier. At this time, the Company and the Division have agreed that the Gas Expansion Pilot Program would be funded at a level of $3.0 million for the FY 2014 Gas ISR Plan. The Company and the Division are finalizing more specific criteria that would be used under the program to identify and evaluate these potential residential and commercial customers. A detailed description of the pilot program criteria will be submitted in this proceeding to the Commission when it has been finalized.

33 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 12 of 15 Table 1 Capital Investment Plan Growth - Mains - Services - Reinforcement Replacement Program - Main Replacement - Service Replacements FY 2014 ($000s) Description $ 11,942 Installation of new main and services. Spending is generally not included in the Gas ISR Plan. $ 36,462 Includes the replacement of approximately 50 miles of leak prone gas main and approximately 1,100 highpressure, unprotected steel gas services with inside meter sets. Public Works $ 1,821 Includes all municipal public works projects including $1.3 million of reimbursable work. Reactive Main Replacement $ 500 Emergency work resulting in the immediate replacement of main resulting from leaks or other unplanned work Mandated Programs $ 13,522 All emergency service replacements resulting from leaks. All cast iron joint leak repairs. Replacement of approximately 19,000 meters Install corrosion protection on approximately 8.5 miles of main. Non-leak other related work load. Reliability $ 8,987 System Automation Regulator Stations Heater Upgrades Control Lines Installation of vent poles Reactive Water Intrusion projects Special Projects $ 4,000 Carryover of the RIDOT I-195 relocation project originally indentified in the FY 2013 filing Replacement of boiler-off compressor at Exeter LNG facility Main extension pilot program TOTAL $ 77,233

34 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 13 of 15 Table 2 Capital Forecast (000s) Investment Categories FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TOTAL Growth (1) $ 11,942 $ 16,325 $ 15,944 $ 16,485 $ 16,891 $ 77,588 Main Replacement Program (2) $ 33,362 $ 37,107 $ 39,991 $ 43,705 $ 44,579 $ 198,743 Service Replacement Program (3) $ 3,100 $ 3,100 $ - $ - $ - $ 6,200 Sub-total $ 36,462 $ 40,207 $ 39,991 $ 43,705 $ 44,579 $ 204,943 Public Works $ 1,821 $ 1,857 $ 1,857 $ 1,857 $ 1,857 $ 9,249 Reactive Main Replacement $ 500 $ 510 $ 510 $ 510 $ 510 $ 2,540 Mandated Program $ 13,522 $ 14,671 $ 14,824 $ 14,880 $ 14,936 $ 72,833 Reliability $ 8,987 $ 8,690 $ 9,371 $ 9,135 $ 11,231 $ 47,412 Special Projects $ 4,000 $ 387 $ - $ - $ - $ 4,387 TOTAL $ 77,233 $ 82,648 $ 82,497 $ 86,571 $ 90,004 $ 418,953 (1) Growth is generally not included in the Gas ISR Plan (2) Main Replacement mileage increases annually (50, 53, 55, 60, 60) (3) Service Replacement Program is projected to conclude in FY15

35 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 14 of 15 Table 3 Capital Spending by Investment Categories Fiscal Year 2013 Year to Date - Through September 30, 2012 ($000s) Fiscal Year 2013 to Date Fiscal Year 2013 Total Investment Categories Budget Actual Variance Budget Forecast Variance Proactive Main Replacement Program $17,695 $20,454 $2,760 $33,362 $31,680 ($1,682) Service Replacement Program $2,072 $2,960 $888 $3,906 $3,956 $50 Public Works Program $947 $,71 ($876) $1,785 $1,785 $0 Reactive Main Replacement Program $541 $109 ($432) $1,020 $500 ($520) Mandated Program $6,435 $6,000 ($436) $12,133 $11,928 ($205) Reliability Program $4,767 $2,560 ($2,206) $8,987 $6,655 ($2,332) Special Project (I-195) $0 $0 $0 $692 $0 ($692) Total Capital Investments $32,456 $32,154 ($302) $61,885 $56,505 ($5,381) FY 2013 Capital Spending by Category: Proactive Main Replacement Program $2.8M variance to budget year-to-date To date, the Company has installed 38.7 miles of the planned 50 miles and has abandoned 17.8 miles (12 percent ahead of plan). The Company is on target to meet its proposed replacement of 50 miles of leak prone gas main and is currently projecting year-end costs to be less than budget due to lower than forecasted unit costs. Service Replacement Program $0.9M variance to budget year-to-date To date, the Company has completed 918 of the 1,625 service replacements and 22 of the 49 farm taps and is currently projected to be on budget at year-end. Public Works Program ($0.9M) variance to budget year-to-date To-date, public works construction activity is below forecast; however, it is anticipated that construction activity will increase in the upcoming months. The Public Works Program is currently projected to be on budget at year-end. Reactive Main Replacement Program ($0.4M) variance to budget year-to-date To-date, the lower-than-budget spending is due to lower-than-forecasted unplanned emergency-related work. This variance is currently projected to carry through to year-end.

36 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 2: Gas Capital Investment Plan Page 15 of 15 Mandated Program ($0.4M) variance to budget year-to-date To date, the primary driver for the lower-than-budget spending is the shifting of resources to accelerate the service replacement program and to address growth related services. However, it is expected that Mandated Program spending will be on or near budget at fiscal year-end. Reliability Program ($2.2M) variance to budget year-to-date To date, the lower-than-budgeted spending is primarily driven by the delay in the relocation of three regulator stations (Canal Street, Friendship Street, Westerly) due to conflicts with a water main as well as fewer water intrusion projects than forecasted. This variance is currently projected to carry through to year-end. Special Project (I-195) Deferred to FY 2014 To date, there has been no spending on this project. All proposed work for FY 2013 has been deferred to the FY 2014 plan.

37 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 3: Revenue Requirement Section 3 Revenue Requirement FY 2014 Gas ISR Plan

38 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 3: Revenue Requirement Page 1 of 9 Revenue Requirement FY 2014 Proposal The attached proposed revenue requirement calculation reflects the revenue requirement related to the Company s proposed investment in its Gas Infrastructure, Safety, and Reliability ( ISR ) Plan ( ISR Plan ) for the fiscal year ( FY ) ended March 31, Notably, the revenue requirement for the FY 2014 ISR recovery mechanism excludes amounts embedded in base rates in Docket No for FY years 2012, 2013, and 2014 investments. As shown on Page 1, Column (a) of Attachment 1, the Company s FY 2014 Gas ISR Plan revenue requirement totals $664,509 and consists of the revenue requirement on FY 2014 proposed incremental non-growth ISR capital investment, as calculated on Attachment 1, Page 2, plus the FY 2014 revenue requirement on incremental non-growth ISR capital investment of $-0- and $459,728 for FY 2013 and FY 2012 incremental investment, respectively. Incremental nongrowth capital investment for this purpose is intended to represent the net change in net plant for non-growth infrastructure investments during the relevant FY and is defined as capital additions plus cost of removal, less annual depreciation expense not ultimately embedded in the Company s base rates (excluding depreciation expense attributable to general plant). These amounts are shown on Lines 1 through 8. For illustration purposes only, Column (b) of Page 1 of Attachment 1 provides the FY 2015 revenue requirement for the respective vintage year capital investments as calculated on Attachment 1, Pages 2 and 3. Importantly, these amounts will be trued up to actual investment

39 DOCKET NO. FY 2014 Gas Infrastructure, Safety, and Reliability Plan Section 3: Revenue Requirement Page 2 of 9 activity after the conclusion of the FY, with rate adjustments for the revenue requirement differences incorporated in future ISR filings. Impacts of Base Rate Case Docket No on FY 2014 Gas ISR Revenue Requirement In April 2012, the Company filed an application with the Commission seeking a change in base rates for its electric and gas distribution businesses. The application was assigned Docket No The test year used in the Company s request was calendar year The effective date of new rates in that proceeding is February 1, 2013 for a Rate Year ending January 31, On October 19, 2012, the Company entered into a settlement agreement with the Division and the U.S. Department of the Navy with regard to the Company s base rate change request. On November 14, 2012, the Company entered into an amended settlement agreement (the Amended Settlement Agreement ) with the Division and the U.S. Department of the Navy with regard to the Company s base rate request. The Commission approved the Amended Settlement Agreement on December 20, The base rate change request and associated Amended Settlement Agreement have affected various aspects of the FY 2014 Gas ISR Plan as follows: The FY 2014 revenue requirement associated with the Company s capital investment in gas utility infrastructure is based on incremental capital investment in excess of capital investment that has been reflected in rate base in the Company s base rate case. The FY 2014 ISR revenue requirement has been calculated on estimated FY 2014 incremental capital investment, as well as on incremental capital investment for FY 2012 and FY 2013 because some or all of the capital investment for these years will occur beyond the end of the test year ended December 31, The FY 2014 gas infrastructure revenue requirement has been calculated based upon the agreed-to level of embedded depreciation expense and associated composite depreciation rate, effective property tax rate, capital structure, and cost

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

March 21, 2016 VIA HAND DELIVERY & ELECTRONIC MAIL

March 21, 2016 VIA HAND DELIVERY & ELECTRONIC MAIL Jennifer Brooks Hutchinson Senior Counsel March 21, 2016 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI

More information

THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES RIPUC DOCKET NO.

THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES RIPUC DOCKET NO. THE NARRAGANSETT ELECTRIC COMPANY d/b/a NATIONAL GRID INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES RIPUC DOCKET NO. BEFORE THE RHODE ISLAND PUBLIC UTILITIES COMMISSION TESTIMONY AND EXHIBITS

More information

The Narragansett Electric Company d/b/a National Grid, Filing to Amend Terms and Conditions for Distribution Service Docket No.

The Narragansett Electric Company d/b/a National Grid, Filing to Amend Terms and Conditions for Distribution Service Docket No. Jennifer Brooks Hutchinson Senior Counsel September 3, 2010 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick,

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF DELAWARE ) ) ) DIRECT TESTIMONY OF ON BEHALF OF COMMISSION STAFF

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF DELAWARE ) ) ) DIRECT TESTIMONY OF ON BEHALF OF COMMISSION STAFF BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF DELAWARE APPLICATION OF TIDEWATER UTILITIES, INC. FOR A GENERAL RATE INCREASE IN WATER BASE RATES & TARIFF REVISIONS (FILED NOVEMBER 25, 2013) ) ) )

More information

SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM

SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Page 1 of 9 SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Distribution Integrity Management Program ( DIMP ) activities are focused on obtaining and evaluating information

More information

Indiana's Natural Gas Cost Adjustment Act

Indiana's Natural Gas Cost Adjustment Act STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION PETITION OF THE BOARD OF DIRECTORS FOR ) UTILITIES OF THE DEPARTMENT OF PUBLIC ) UTILITIES OF THE CITY OF INDIANAPOLIS, AS ) CAUSE NO. 37399 GCA 3

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888 STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888 IN RE: Narragansett Bay Commission : Application For Authority

More information

INFRASTRUCTURE COST RECOVERY UPDATE

INFRASTRUCTURE COST RECOVERY UPDATE A Periodic Update on Innovative Rate Designs INFRASTRUCTURE COST RECOVERY UPDATE June 2012 In 2007, when AGA published its first report on infrastructure cost recovery methods, 15 natural gas utilities

More information

DEPARTMENT OF PUBLIC UTILITIES

DEPARTMENT OF PUBLIC UTILITIES THE COMMONWEALTH OF MASSACHUSETTS DEPARTMENT OF PUBLIC UTILITIES CHARLES D. BAKER GOVERNOR KARYN E. POLITO LIEUTENANT GOVERNOR MATTHEW A. BEATON SECRETARY OF ENERGY AND ENVIRONMENTAL AFFAIRS ONE SOUTH

More information

RATES AND RULES GOVERNING THE FURNISHING OF NATURAL GAS SERVICE TO RETAIL GAS CUSTOMERS

RATES AND RULES GOVERNING THE FURNISHING OF NATURAL GAS SERVICE TO RETAIL GAS CUSTOMERS Supplement No. 69 Gas PA PUC No. 45 PEOPLES NATURAL GAS COMPANY LLC RATES AND RULES GOVERNING THE FURNISHING OF NATURAL GAS SERVICE TO RETAIL GAS CUSTOMERS RATE MLX REPLACING RATE SET ISSUED: April 29,

More information

Funding the Vision: Investing in Safe, Reliable Service

Funding the Vision: Investing in Safe, Reliable Service Funding the Vision: Investing in Safe, Reliable Service KUB Financial Plan Executive Summary Fiscal Year 2015 Table of Contents Funding The Vision: Investing in Safe, Reliable Service 1 KUB Proposed Fiscal

More information

October 17, 2013 BY HAND DELIVERY & ELECTRONIC MAIL

October 17, 2013 BY HAND DELIVERY & ELECTRONIC MAIL Thomas R. Teehan Senior Counsel October 17, 2013 BY HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI 02888 RE:

More information

Responsible for pipeline engineering and plant operations for DTI and Cove Point.

Responsible for pipeline engineering and plant operations for DTI and Cove Point. GAS TRANSMISSION DTI - Pipeline Vice President, Pipeline Responsible for pipeline operations for DTI and Cove Point. Vice President, Pipeline Engineering & Plant Managing Director, Pipeline Director, Gas

More information

DIRECT TESTIMONY OF LAURA SITRIN CITY OF NEWPORT FINANCE DIRECTOR ON BEHALF OF THE CITY OF NEWPORT, UTILITIES DEPARTMENT, WATER DIVISION

DIRECT TESTIMONY OF LAURA SITRIN CITY OF NEWPORT FINANCE DIRECTOR ON BEHALF OF THE CITY OF NEWPORT, UTILITIES DEPARTMENT, WATER DIVISION DIRECT TESTIMONY OF LAURA SITRIN CITY OF NEWPORT FINANCE DIRECTOR ON BEHALF OF THE CITY OF NEWPORT, UTILITIES DEPARTMENT, WATER DIVISION In re: City of Newport Utilities Department, Water Division Docket

More information

Order 20253 - Cox Comm.: Rate Change Notification Filing

Order 20253 - Cox Comm.: Rate Change Notification Filing Page 1 of 5 Order 20253 - Cox Comm.: Rate Change Notification Filing STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION DIVISION OF PUBLIC UTILITIES AND CARRIERS PROVIDENCE, RHODE ISLAND

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION DIVISION OF PUBLIC UTILITIES AND CARRIERS PROVIDENCE, RHODE ISLAND STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION DIVISION OF PUBLIC UTILITIES AND CARRIERS PROVIDENCE, RHODE ISLAND IN RE: RULES AND REGULATIONS PRESCRIBING STANDARDS FOR GAS

More information

Rhode Island Municipal Police Training Academy. Annual Report 2005 Glenford J. Shibley Acting Director

Rhode Island Municipal Police Training Academy. Annual Report 2005 Glenford J. Shibley Acting Director Rhode Island Municipal Police Training Academy Annual Report 2005 Glenford J. Shibley Acting Director Community College of Rhode Island Flanagan Campus Lincoln, RI Table of Contents I Introduction to Report

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888 STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS 89 JEFFERSON BOULEVARD WARWICK, RHODE ISLAND 02888 IN RE: CoxCom, Inc. d/b/a/cox : Communications - Rate Change

More information

PREPARED DIRECT TESTIMONY OF MICHAEL R. WOODRUFF ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

PREPARED DIRECT TESTIMONY OF MICHAEL R. WOODRUFF ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-0-01 Exhibit No.: Witness: M. Woodruff In The Matter of the Application of San Diego Gas & Electric Company (U 0 G) and Southern California Gas Company (U 0 G) for a Certificate of

More information

Enterprise Funds: A Best Practice

Enterprise Funds: A Best Practice Enterprise Funds: A Best Practice Purpose Introduction This guide will help you understand: The definition of Enterprise Fund. Why enterprise funds are important to your utility. How to implement enterprise

More information

FOR DISCUSSION PURPOSES ONLY NOT FOR PUBLICATION

FOR DISCUSSION PURPOSES ONLY NOT FOR PUBLICATION Massachusetts Grid Working Group Model Option Title: Program Models Author: The Office of the Attorney General Date: May 13, 2013 Customerfacing, gridfacing or both Rationale for, or summary of, model

More information

78th OREGON LEGISLATIVE ASSEMBLY--2016 Regular Session. Enrolled

78th OREGON LEGISLATIVE ASSEMBLY--2016 Regular Session. Enrolled 78th OREGON LEGISLATIVE ASSEMBLY--2016 Regular Session Enrolled Senate Bill 1547 Sponsored by Senator BEYER; Senators BATES, BURDICK, DEMBROW, DEVLIN, GELSER, HASS, MONNES ANDERSON, MONROE, RILEY, ROSENBAUM,

More information

THE NARRAGANSETT ELECTRIC COMPANY Summary of Retail Delivery Rates

THE NARRAGANSETT ELECTRIC COMPANY Summary of Retail Delivery Rates THE NARRAGANSETT ELECTRIC COMPANY Summary of Retail Delivery Rates R.I.P.U.C. Tariff No. 2095 Sheet 1 of 3 Energy Renewable Operating & O&M CapEx CapEx RDM Pension Billing Net Long- Energy LIHEAP Base

More information

DIRECT SUPPLEMENTAL TESTIMONY OF DONALD E. KITNER IN FLORIDA PUBLIC UTILITIES COMPANY DOCKET NO 080366-GU

DIRECT SUPPLEMENTAL TESTIMONY OF DONALD E. KITNER IN FLORIDA PUBLIC UTILITIES COMPANY DOCKET NO 080366-GU DIRECT SUPPLEMENTAL TESTIMONY OF DONALD E. KITNER IN FLORIDA PUBLIC UTILITIES COMPANY DOCKET NO 00-GU IN RE: PETITION OF FLORIDA PUBLIC UTILITIES COMPANY FOR A NATURAL GAS RATE INCREASE 2 A. Please state

More information

East Kentucky Power Cooperative, Inc. Demand Side Management and Renewable Energy Collaborative Charter. Introduction

East Kentucky Power Cooperative, Inc. Demand Side Management and Renewable Energy Collaborative Charter. Introduction East Kentucky Power Cooperative, Inc. Demand Side Management and Renewable Energy Collaborative Charter Introduction The Demand Side Management and Renewable Energy Collaborative ( Collaborative ) of East

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION Sheet 1 Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services from the Distribution Company, with the exception of

More information

Rhode Island Election Calendar 2016

Rhode Island Election Calendar 2016 Rhode Island Election Calendar 2016 A guide for elections officials elections@sos.ri.gov 401.222.2340 www.sos.ri.gov @RISecState This guide was produced by the Rhode Island Department of State Nellie M.

More information

STATE OF NEW HAMPSHIRE BEFORE THE DT 08-013. Com cast Phone of New Hampshire, LLC Request for Authority to Provide Local Telecommunications

STATE OF NEW HAMPSHIRE BEFORE THE DT 08-013. Com cast Phone of New Hampshire, LLC Request for Authority to Provide Local Telecommunications STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION DT 08-013 Com cast Phone of New Hampshire, LLC Request for Authority to Provide Local Telecommunications Services Objection by New Hampshire

More information

CIN: A-01-98-04000. Ms. Elizabeth Huidekoper Vice President for Finance Harvard University Massachusetts Hall Cambridge. Massachusetts 02 138

CIN: A-01-98-04000. Ms. Elizabeth Huidekoper Vice President for Finance Harvard University Massachusetts Hall Cambridge. Massachusetts 02 138 DEPARTMENT OF HEALTH HUMAN SERVICES OFFICE OF INSPECTOR GENERAL Office of Audit Services Region I John F. Kennedy Federal Building Boston. MA 02203 (6 17) CIN: A-01-98-04000 Ms. Elizabeth Huidekoper Vice

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E s : D IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT AND OPERATE

More information

National Grid. Gas Long-Range Resource and Requirements Plan For the Forecast Period 2013/14 to 2022/23. The Narragansett Electric Company. Docket No.

National Grid. Gas Long-Range Resource and Requirements Plan For the Forecast Period 2013/14 to 2022/23. The Narragansett Electric Company. Docket No. National Grid The Narragansett Electric Company Gas Long-Range Resource and Requirements Plan For the Forecast Period 2013/14 to 2022/23 March 10, 2014 Docket No. Submitted to: Rhode Island Public Utilities

More information

Rhode Island Renewable Energy Standard (RES) Annual RES Compliance Report For Compliance Year 2012

Rhode Island Renewable Energy Standard (RES) Annual RES Compliance Report For Compliance Year 2012 Rhode Island Renewable Energy Standard (RES) Annual RES Compliance Report For Compliance Year 2012 (Revised 3/25/14) February 2014 Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick,

More information

APPLYING FOR PUBLIC AND SUBSIDIZED HOUSING IN RHODE ISLAND

APPLYING FOR PUBLIC AND SUBSIDIZED HOUSING IN RHODE ISLAND APPLYING FOR PUBLIC AND SUBSIDIZED HOUSING IN RHODE ISLAND This handbook has been prepared for you by RHODE ISLAND LEGAL SERVICES, INC. For more information, please call the office nearest you. PROVIDENCE:

More information

PG&E Corporation Second Quarter Earnings Call August 7, 2012

PG&E Corporation Second Quarter Earnings Call August 7, 2012 1 PG&E Corporation Second Quarter Earnings Call August 7, 2012 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on August

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Constellation Energy Commodities ) Docket No. IN12-7-000 Group, Inc.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Constellation Energy Commodities ) Docket No. IN12-7-000 Group, Inc. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Constellation Energy Commodities ) Docket No. IN12-7-000 Group, Inc. ) ) NEW ENGLAND PARTIES JOINT REQUEST FOR DISBURSEMENT On

More information

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR RESIDENTIAL CUSTOMERS

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR RESIDENTIAL CUSTOMERS Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for a solar electricity generating facility ( Residential Small-Scale Solar Project or Project

More information

THE COMMONWEALTH OF MASSACHUSETTS OFFICE OF THE ATTORNEY GENERAL ONE ASHBURTON PLACE BOSTON, MASSACHUSETTS 02108

THE COMMONWEALTH OF MASSACHUSETTS OFFICE OF THE ATTORNEY GENERAL ONE ASHBURTON PLACE BOSTON, MASSACHUSETTS 02108 THE COMMONWEALTH OF MASSACHUSETTS OFFICE OF THE ATTORNEY GENERAL ONE ASHBURTON PLACE BOSTON, MASSACHUSETTS 02108 MARTHA COAKLEY ATTORNEY GENERAL (617) 727-2200 (617) 727-4765 TTY www.mass.gov/ago June

More information

APPENDIX J GAS DISTRIBUTION

APPENDIX J GAS DISTRIBUTION APPENDIX J GAS DISTRIBUTION Ji Jii APPENDIX J GAS DISTRIBUTION NEIL G. THOMPSON, PH.D. 1 SUMMARY The natural gas distribution system includes 2,785,000 km (1,730,000 mi) of relatively small-diameter, low-pressure

More information

NW Natural & Pipeline Safety

NW Natural & Pipeline Safety NW Natural & Pipeline Safety We Grew Up Here NW Natural is an Oregon-based utility company founded in 1859. The company purchases natural gas for its core market in western Oregon and southwestern Washington,

More information

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX] EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy

More information

RHODE ISLAND PUBLIC UTILITIES COMMISSION DOCKET NO. 4243 CITY OF NEWPORT WATER DIVISION PREFILED TESTIMONY OF CHRISTOPHER P.N.

RHODE ISLAND PUBLIC UTILITIES COMMISSION DOCKET NO. 4243 CITY OF NEWPORT WATER DIVISION PREFILED TESTIMONY OF CHRISTOPHER P.N. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 RHODE ISLAND PUBLIC UTILITIES COMMISSION DOCKET NO. 4243 CITY OF NEWPORT WATER DIVISION PREFILED TESTIMONY OF CHRISTOPHER P.N. WOODCOCK 21 22 23 24 25

More information

Regulation of Natural Gas Pipelines. June 23, 2008

Regulation of Natural Gas Pipelines. June 23, 2008 Regulation of Natural Gas Pipelines June 23, 2008 Federal and State Regulations Federal: 49 United States Code 60101. et. seq. Title 49 Code of Federal Regulations The Office of Pipeline Safety (OPS),

More information

STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS. SECTION DESCRIPTION Page

STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS. SECTION DESCRIPTION Page STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS SECTION DESCRIPTION Page 1 Executive Summary / Brief History 2 2 Services Provided / Administration

More information

Background on NAWC New Jersey Chapter

Background on NAWC New Jersey Chapter The National Association of Water Companies New Jersey Chapter (NAWC-NJ) strongly supports the implementation of a Distribution System Improvement Charge (DSIC) in New Jersey. We applaud the Board of Public

More information

A&R MARINE CORP. D/B/A PRUDENCE & BAY ISLANDS TRANSPORT GENERAL RATE FILING RIPUC DOCKET NO. 4586 BEFORE THE RHODE ISLAND PUBLIC UTILITIES COMMISSION

A&R MARINE CORP. D/B/A PRUDENCE & BAY ISLANDS TRANSPORT GENERAL RATE FILING RIPUC DOCKET NO. 4586 BEFORE THE RHODE ISLAND PUBLIC UTILITIES COMMISSION A&R MARINE CORP. D/B/A PRUDENCE & BAY ISLANDS TRANSPORT GENERAL RATE FILING RIPUC DOCKET NO. BEFORE THE RHODE ISLAND PUBLIC UTILITIES COMMISSION TESTIMONY AND EXHIBITS OF DAVID J. EFFRON ON BEHALF OF THE

More information

The Narragansett Electric Company. d/b/a National Grid INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES. Testimony and Schedules of:

The Narragansett Electric Company. d/b/a National Grid INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES. Testimony and Schedules of: The Narragansett Electric Company d/b/a National Grid INVESTIGATION AS TO THE PROPRIETY OF PROPOSED TARIFF CHANGES Testimony and Schedules of: Timothy F. Horan Robert B. Hevert Maureen P. Heaphy Book of

More information

How To Understand And Understand The Capital Expenditures Of Fortisbc

How To Understand And Understand The Capital Expenditures Of Fortisbc Preliminary 00 Revenue Requirements Tab Capital Expenditures Preliminary 00 Revenue Requirements Capital Expenditures - Tab Table of Contents.0 OVERVIEW.... 00 FORECAST..... GENERATION..... TRANSMISSION

More information

The Swedish Natural Gas Act and Ordinances

The Swedish Natural Gas Act and Ordinances The Swedish Natural Gas Act and Ordinances The Swedish Natural Gas Act and Ordinances CONTENTS Chapter 1 Introductory Provisions... 4 Chapter 2 Concession... 5 Chapter 3 Obligations of the Natural Gas

More information

June 14, 2007. Update of Public Utilities Commission Reimbursement Fee for Fiscal Year 2007-08 - Gas

June 14, 2007. Update of Public Utilities Commission Reimbursement Fee for Fiscal Year 2007-08 - Gas Akbar Jazayeri Vice President, Revenue and Tariffs June 14, 2007 ADVICE 141-G (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Update of Public Utilities Commission

More information

COMMONWEALTH OF MASSACHUSETTS DEPARTMENT OF PUBLIC UTILITIES

COMMONWEALTH OF MASSACHUSETTS DEPARTMENT OF PUBLIC UTILITIES COMMONWEALTH OF MASSACHUSETTS DEPARTMENT OF PUBLIC UTILITIES Massachusetts Electric Company/ Nantucket Electric Company d/b/a National Grid D.P.U, 10- PETITION FOR INVESTIGATION OF MASSACHUSETTS ELECTRIC

More information

How To Plan A University Budget

How To Plan A University Budget Annual Budget Plan Guidelines & Instructions 9/1/2010 Table of Contents INTRODUCTION...3 INTRODUCTION:...4 THE GOALS OF THE BUDGET PROCESS:...4 PRINCIPLES OF EFFECTIVE BUDGETING:...4 GUIDELINES FOR RESOURCE

More information

Contact: Ken Bond Deborah Hellinger Oracle Investor Relations Oracle Corporate Communications 1.650.607.0349 1.212.508.7935

Contact: Ken Bond Deborah Hellinger Oracle Investor Relations Oracle Corporate Communications 1.650.607.0349 1.212.508.7935 For Immediate Release Contact: Ken Bond Deborah Hellinger Oracle Investor Relations Oracle Corporate Communications 1.650.607.0349 1.212.508.7935 ken.bond@oracle.com deborah.hellinger@oracle.com CLOUD

More information

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER IV

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER IV Application No.: A.0-0-0 Exhibit No.: SCG Date: March, 00 Witness: Christopher R. Olmsted SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER IV INFORMATION SYSTEMS, APPLICATION DEVELOPMENT

More information

The Small Business Renewable Energy Task Force

The Small Business Renewable Energy Task Force The Small Business Renewable Energy Task Force FINDINGS and RECOMMENDATIONS Respectfully submitted to the Rhode Island House of Representatives May 2011 THE SMALL BUSINESS RENEWABLE ENERGY TASK FORCE:

More information

PDC I DATE: September 28, 2015

PDC I DATE: September 28, 2015 PDC I PORTLAND DEVELOPMENT COMMISSION www.pdc.us J. Scott Andrews Commission Chair DATE: Aneshka Dickson John C. Mohlis Steven Straus Charles A. Wilhoite Charlie Hales Mayor Patrick Quinton Executive Director

More information

THE NARRAGANSETT ELECTRIC COMPANY OPTIONAL LARGE DEMAND BACK-UP SERVICE RATE (B-62) RETAIL DELIVERY SERVICE

THE NARRAGANSETT ELECTRIC COMPANY OPTIONAL LARGE DEMAND BACK-UP SERVICE RATE (B-62) RETAIL DELIVERY SERVICE Sheet 1 AVAILABILITY This service shall apply to Customers in the class identified below: (i) (ii) who receive all or any portion of their electric supply from non-emergency generation unit(s) with a nameplate

More information

b. Peak Hourly Flow decreased at Lawton Valley in FY 2010 because customer demand was such that the plant was not required to operate at a higher

b. Peak Hourly Flow decreased at Lawton Valley in FY 2010 because customer demand was such that the plant was not required to operate at a higher Navy 2-1: Referring to HJS Schedule D-3 Update, specifically the electronic spreadsheet COSS model tab Production, please provide the following information: a. Please provide a narrative explaining how

More information

THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers

THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers Sheet 1 THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers The delivery of electricity shall be in accordance with the provisions of law, regulation and these Terms

More information

Community Choice Aggregation Demonstration Program

Community Choice Aggregation Demonstration Program Community Choice Aggregation Demonstration Program Frequently Asked Questions (Last revised July 7,2015) Q 1. What is Community Choice Aggregation (CCA)? c/o Village of Ossining 16 Croton Avenue Ossining,

More information

NORTHWESTERN ENERGY REPORTS THIRD QUARTER 2015 FINANCIAL RESULTS

NORTHWESTERN ENERGY REPORTS THIRD QUARTER 2015 FINANCIAL RESULTS NorthWestern Corporation d/b/a NorthWestern Energy 3010 W. 69 th Street Sioux Falls, SD 57108 www.northwesternenergy.com NYSE: NWE FOR IMMEDIATE RELEASE NORTHWESTERN ENERGY REPORTS THIRD QUARTER 2015 FINANCIAL

More information

TAX CREDIT AND INCENTIVE REPORT FISCAL YEAR 2014

TAX CREDIT AND INCENTIVE REPORT FISCAL YEAR 2014 TAX CREDIT AND INCENTIVE REPORT FISCAL YEAR 2014 Rhode Island General Laws (RIGL) require the Division of Taxation to annually report a recipient s name, address and amount of tax incentives received during

More information

Redemption of Shares Class A Sales Charge Waivers beginning on page 37 of the Fund s Statement of Additional Information.

Redemption of Shares Class A Sales Charge Waivers beginning on page 37 of the Fund s Statement of Additional Information. USA Mutuals Barrier Fund Trading Symbols: Institutional Class Shares VICVX Investor Class Shares VICEX Class A Shares VICAX Class C Shares VICCX Summary Prospectus July 29, 2015 Before you invest, you

More information

REBUTTAL TESTIMONY OF JASON P. NIELSEN

REBUTTAL TESTIMONY OF JASON P. NIELSEN REBUTTAL TESTIMONY OF JASON P. NIELSEN BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION IN THE MATTER OF INTERSTATE POWER AND LIGHT COMPANY S PETITION

More information

Before the Maryland Public Service Commission. Case No. 9326. Prepared Surrebuttal Testimony of. Stephen J. Woerner. on Behalf of

Before the Maryland Public Service Commission. Case No. 9326. Prepared Surrebuttal Testimony of. Stephen J. Woerner. on Behalf of Before the Maryland Public Service Commission Case No. Prepared Surrebuttal Testimony of Stephen J. Woerner on Behalf of Baltimore Gas and Electric Company October, 01 LIST OF ISSUES AND MAJOR CONCLUSIONS

More information

MISSISSIPPI LEGISLATURE REGULAR SESSION 2016

MISSISSIPPI LEGISLATURE REGULAR SESSION 2016 MISSISSIPPI LEGISLATURE REGULAR SESSION 2016 By: Representative Baker To: Judiciary A HOUSE BILL NO. 738 1 AN ACT TO AMEND SECTIONS 7-5-1 AND 7-5-8, MISSISSIPPI CODE OF 2 1972, TO REQUIRE APPROVAL OF THE

More information

Department of Management and Budget

Department of Management and Budget Director Debt Deputy Director and Budget FOCUS Business Support Group Budget Development & Production Revenue & Tax Analysis Customer & Information Technology Core Financial Processing Capital Projects/CIP

More information

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 1 Purpose of Strategic Plan This document serves as the road map for the Public Works Department. It identifies where we are going and how we are going

More information

File & Suspend Rate Cases. Water & Wastewater Reference Manual 1

File & Suspend Rate Cases. Water & Wastewater Reference Manual 1 File & Suspend Rate Cases 1 Basics of a File & Suspend Rate Case A file and suspend rate case is a process required to be used by Class A and Class B water and wastewater utilities. Under this process,

More information

GAS & ELECTRIC UTILITY APPLICATION SUPPLEMENT

GAS & ELECTRIC UTILITY APPLICATION SUPPLEMENT Chubb Group of Insurance Companies 15 Mountain View Road, Warren, New Jersey 07059 GAS & ELECTRIC UTILITY APPLICATION SUPPLEMENT GENERAL INFORMATION Applicant Name: A. Applicant is: Investor Owned Utility

More information

AGENCY: National Telecommunications and Information Administration, U.S. Department of

AGENCY: National Telecommunications and Information Administration, U.S. Department of This document is scheduled to be published in the Federal Register on 12/15/2015 and available online at http://federalregister.gov/a/2015-31516, and on FDsys.gov Billing Code: 3510-60-P DEPARTMENT OF

More information

STATE OF VERMONT PUBLIC SERVICE BOARD

STATE OF VERMONT PUBLIC SERVICE BOARD STATE OF VERMONT PUBLIC SERVICE BOARD Petition of GMPSolar -Richmond, LLC for a Certificate ) of Public Good, pursuant to 0 V.S.A., authorizing ) the installation and operation of a.0 MW solar electric

More information

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT P.O. BOX 134 PINE, ARIZONA 85544-0134 REQUEST FOR PROPOSALS

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT P.O. BOX 134 PINE, ARIZONA 85544-0134 REQUEST FOR PROPOSALS PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT P.O. BOX 134 PINE, ARIZONA 85544-0134 REQUEST FOR PROPOSALS Point to Point Leak Detection Survey RFP # 2014-02 PROPOSAL OPENING DATE July 26, 2013 3:00 PM REQUEST

More information

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)

More information

References (Statutes/Resos/Policies): Title 32 C.R.S.,, Land Development Regulation, Zoning Resolution; CC92-47; CC97-544;CC03-388, CC05-398

References (Statutes/Resos/Policies): Title 32 C.R.S.,, Land Development Regulation, Zoning Resolution; CC92-47; CC97-544;CC03-388, CC05-398 Title: Regulatory Policy Special Districts Policy Custodian Planning and Zoning Division Policy No. Part 7, Planning and Land Use Chapter 2, Regulations Section 5 Effective Date December 5, 2006 Adoption/Revision

More information

CITY OF CHESAPEAKE ORGANIZATION

CITY OF CHESAPEAKE ORGANIZATION CITY OF CHESAPEAKE ORGANIZATION The City of Chesapeake derives its governing authority from a Charter granted by the General Assembly of the Commonwealth of Virginia. The City is organized under a Council-Manager

More information

Budgeting and Planning Process

Budgeting and Planning Process Budgeting and Planning Process Summary The budget is an important annual planning document for the university and reflects choices, priorities and tactics set forth as the result of intensive planning.

More information

August 27, 2007 Advice Letter 2146-E. Advice Letter 2146-E is effective August 31, 2007. Thank you for your time.

August 27, 2007 Advice Letter 2146-E. Advice Letter 2146-E is effective August 31, 2007. Thank you for your time. STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE Tel. No. (415) 703-2626 SAN FRANCISCO, CA 94102-3298 August 27, 2007 Advice Letter 2146-E Akbar Jazayeri

More information

Cost Allocation Method

Cost Allocation Method Cost Allocation Method Ergon Energy Corporation Limited Document Summary Version: 4.0 Status: AER Approved Version History and Date of Issue Version Date Issued Summary of Changes 1.0 March 2009 Initial

More information

SUPREME COURT OF COLORADO

SUPREME COURT OF COLORADO SUPREME COURT OF COLORADO OFFICE OF THE CHIEF JUSTICE Chief Justice Directive 12-03 DIRECTIVE CONCERNING COURT COMPENSATION OF EXPERT WITNESSES AND PROFESSIONALS CONDUCTING MENTAL HEALTH EVALUATIONS, SANITY

More information

Ameren Illinois Company Ill. C. C. No. 1 d/b/a Ameren Illinois Original Sheet No. 47 Electric Service Schedule Ill. C. C. No. 1

Ameren Illinois Company Ill. C. C. No. 1 d/b/a Ameren Illinois Original Sheet No. 47 Electric Service Schedule Ill. C. C. No. 1 d/b/a Ameren Illinois Original Sheet No. 47 PURPOSE OF RIDER The Hazardous Materials Adjustment Clause (HMAC) shall operate to recover allowable HMAC Costs (as defined herein) of the Company. APPLICABLE

More information

WATER UTILITY REFERENCE MANUAL

WATER UTILITY REFERENCE MANUAL Utility Plant and Accumulated Depreciation Capitalization Policy Costs are capitalized in the utility plant accounts, rather than being expensed in the current year, if: the service life is more than one

More information

State of Rhode Island and Providence Plantations. Budget. Fiscal Year 2017. Technical Appendix. Gina M. Raimondo, Governor

State of Rhode Island and Providence Plantations. Budget. Fiscal Year 2017. Technical Appendix. Gina M. Raimondo, Governor State of Rhode Island and Providence Plantations Budget Fiscal Year 2017 Technical Appendix Gina M. Raimondo, Governor Internal Service Fund Accounts Internal Service Fund accounts are established to

More information

J. KENNEDY ASSOCIATES, INC.

J. KENNEDY ASSOCIATES, INC. J. KENNEDY AND ASSOCIATES, INC. PROPOSAL TO THE LOUISIANA PUBLIC SERVICE COMMISSION IN RESPONSE TO RFP 14-22 DIXIE ELECTRIC MEMBERSHIP CORPORATION IN RE: 2014-2017 FORMULA RATE PLAN ANNUAL REPORT FILING

More information

2015 -- H 6268 S T A T E O F R H O D E I S L A N D

2015 -- H 6268 S T A T E O F R H O D E I S L A N D LC00 01 -- H S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO ALCOHOLIC BEVERAGES -- RETAIL LICENSES -- TOWN OF MIDDLETOWN Introduced By: Representatives

More information

The Office of Pipeline Safety does not object to the granting of these waivers if the following conditions are included:

The Office of Pipeline Safety does not object to the granting of these waivers if the following conditions are included: Mr. Charles C. Constantine Executive Secretary Maryland Public Service Commission 301 West Preston Street Baltimore, Maryland 21201 Dear Mr. Constantine: This will acknowledge receipt of Case No. 6533

More information

FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY )

FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY ) BEFORE THE r r r ARKANSAS PUBLIC SERVICE COMMI&@ FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY ) DOCKET NO. 08 -

More information

CASE STUDY. City of Grand Rapids Stormwater Asset Management Program. City of Grand Rapids. By the Numbers

CASE STUDY. City of Grand Rapids Stormwater Asset Management Program. City of Grand Rapids. By the Numbers United States Environmental Protection Agency CASE STUDY City of Grand Rapids Stormwater Asset Management Program Overview With increasing pressure to meet water quality targets, address population growth,

More information

Asset Management: A Best Practice

Asset Management: A Best Practice Asset Management: A Best Practice Purpose Introduction This guide will help you understand: The definition of Asset Management. Why asset management is important to your utility. The best practices in

More information

Public schools remain at the center of Rhode Island life, The Top Schools: Patterns

Public schools remain at the center of Rhode Island life, The Top Schools: Patterns Public schools remain at the center of Rhode Island life, from the capital city of Providence to the smallest towns on the shores of Narragansett Bay. And for families living, working, and paying taxes

More information

ORIGIN.AL,, STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION ORDER OF THE COMMISSION

ORIGIN.AL,, STATE OF INDIANA INDIANA UTILITY REGULATORY COMMISSION ORDER OF THE COMMISSION ORIGIN.AL,, STATE OF INDIANA ~ INDIANA UTILITY REGULATORY COMMISSION IN THE MATTER OF THE VERIFIED PETITION ) OF INDIANA MICHIGAN POWER COMPANY ) FOR APPROVAL OF AN ADJUSTMENT TO ITS ) RATES THROUGH ITS

More information

NWN OPUC Advice No. 15-11 / UG (UM 1635 / UG 221)

NWN OPUC Advice No. 15-11 / UG (UM 1635 / UG 221) ONITA R. KING Rates & Regulatory Affairs Tel: 503.721.2452 Fax: 503.721.2516 Email: ork@nwnatural.com July 31, 2015 NWN OPUC Advice No. 15-11 / UG (UM 1635 / UG 221) VIA ELECTRONIC FILING Public Utility

More information

Office of Capital Facilities

Office of Capital Facilities LOB #57: LAND ACQUISITION Office of Capital Facilities Purpose Land Acquisition s purpose is to acquire the land rights necessary to enable construction of all County capital improvement projects. This

More information

On June 28, 2011, the Municipal Services Committee recommended that the City Council adopt the recommendations stated in the subject agenda report.

On June 28, 2011, the Municipal Services Committee recommended that the City Council adopt the recommendations stated in the subject agenda report. Agenda Report July 11, 2 0 11 TO: Honorable Mayor and City Council THROUGH: Municipal Services Committee (June 28, 2011) FROM: SUBJECT: Water and Power Department AUTHORIZE THE CITY MANAGER TO ENTER INTO

More information

CITY OF ARCADIA, FLORIDA ANNUAL FINANCIAL REPORT. For the Fiscal Year Ended September 30, 2015

CITY OF ARCADIA, FLORIDA ANNUAL FINANCIAL REPORT. For the Fiscal Year Ended September 30, 2015 ANNUAL FINANCIAL REPORT For the Fiscal Year Ended September 30, 2015 ANNUAL FINANCIAL REPORT FOR THE FISCAL YEAR ENDED SEPTEMBER 30, 2015 TABLE OF CONTENTS Page INDEPENDENT AUDITOR'S REPORT... 1 MANAGEMENT'S

More information

BEFORE THE GUAM PUBLIC UTILITIES COMMISSION ) ) ) ) ) ) BACKGROUND

BEFORE THE GUAM PUBLIC UTILITIES COMMISSION ) ) ) ) ) ) BACKGROUND BEFORE THE GUAM PUBLIC UTILITIES COMMISSION In the Matter of: PTI PACIFICA INC. USAC CERTIFICATION PUC LEGAL COUNSEL REPORT BACKGROUND On August 7, 2012, ( PTI petitioned the Guam Public Utilities Commission

More information

May 26, 2015. Governor Charlie Baker Massachusetts State House Office of the Governor Room 280 Boston, MA 02133

May 26, 2015. Governor Charlie Baker Massachusetts State House Office of the Governor Room 280 Boston, MA 02133 May 26, 2015 Governor Charlie Baker Massachusetts State House Office of the Governor Room 280 Boston, MA 02133 Re: Transitioning to a Renewable Future Dear Governor Baker: The energy sector is in a period

More information

360 CMR: MASSACHUSETTS WATER RESOURCES AUTHORITY 360 CMR 12.00: LEAK DETECTION REGULATIONS

360 CMR: MASSACHUSETTS WATER RESOURCES AUTHORITY 360 CMR 12.00: LEAK DETECTION REGULATIONS 360 CMR 12.00: LEAK DETECTION REGULATIONS Section 12.01: Preamble 12.02: Effective Date 12.03: Definitions 12.04: Applicability of Leak Detection and Repair Program 12.05: Minimum Frequency 12.06: Methods

More information

SUMMARY OF CAPITAL EXPENDITURES

SUMMARY OF CAPITAL EXPENDITURES Filed: 0--9 EB-0-0 Exhibit D Tab Schedule Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL EXPENDITURES 8 The requested capital expenditures result from the rigorous business planning and work

More information