How To Prepare A Configuration Change Change Request For The Tfnsw Cmaac

Size: px
Start display at page:

Download "How To Prepare A Configuration Change Change Request For The Tfnsw Cmaac"

Transcription

1 Guide TfNSW Configuration Management and Asset Assurance Committee Submissions Guide Important Warning This document is one of a set of standards developed solely and specifically for use on public transport assets which are vested in or owned, managed, controlled, commissioned or funded by the NSW Government, a NSW Government agency or a Transport Agency (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose. You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval. This document may not be current. Current standards are available for download from the Asset Standards Authority website at State of NSW through Transport for NSW

2 Standard governance Owner: Authoriser: Approver: Manager Asset Configuration Systems, Asset Standards Authority Principal Manager Network and Asset Strategy, Asset Standards Authority Director, Asset Standards Authority on behalf of the ASA Configuration Control Board Document history Version Summary of Changes 1.0 First issue For queries regarding this document, please the ASA at or visit State of NSW through Transport for NSW

3 Preface The Asset Standards Authority (ASA) is an independent unit within Transport for NSW (TfNSW) and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering governance frameworks to support industry delivery in the assurance of design, safety, integrity, construction, and commissioning of transport assets for the whole asset life cycle. In order to achieve this, the ASA effectively discharges obligations as the authority for various technical, process, and planning matters across the asset life cycle. The ASA collaborates with industry using stakeholder engagement activities to assist in achieving its mission. These activities help align the ASA to broader government expectations of making it clearer, simpler, and more attractive to do business within the NSW transport industry, allowing the supply chain to deliver safe, efficient, and competent transport services. The ASA develops, maintains, controls, and publishes a suite of standards and other documentation for transport assets of TfNSW. Further, the ASA ensures that these standards are performance-based to create opportunities for innovation and improve access to a broader competitive supply chain. This document aims to provide guidance in relation to submissions to the TfNSW Configuration Management and Asset Assurance Committee. This document is based on principles from AS ISO Quality Management System Guidelines for Configuration Management. This guide has been developed in consultation with key stakeholders across TfNSW. This document is a first issue. State of NSW through Transport for NSW Page 3 of 25

4 Table of contents 1. Introduction Purpose Scope Application Reference documents Terms and definitions Configuration change requests presented to the TfNSW CMAAC Significance of a configuration change Gate 0 configuration changes Significant configuration change requests at gate Minor or moderate configuration change requests at gate Gate 1 configuration changes Significant configuration change requests at gate Minor or moderate configuration change requests at gate Gate 5 configuration changes Significant configuration change requests at gate Moderate configuration change requests at gate Minor configuration change requests at gate Gate 6 configuration changes Overview submission document Submission templates Presentations to the TfNSW CMAAC TfNSW CMAAC assessment TfNSW CMAAC decision Appendix A Submission steps for configuration change State of NSW through Transport for NSW Page 4 of 25

5 1. Introduction A configuration change within the context of the TfNSW transport network is any change that results in the addition, removal or change to TfNSW transport assets or its interfaces whether it be as a result of a project or maintenance activity. In certain circumstances, configuration change requests are required to be submitted to the TfNSW Configuration and Asset Assurance Committee (TfNSW CMAAC) or a delegated authority of the TfNSW CMAAC. T MU AM PL TfNSW Configuration Management Plan defines requirements for the management of configuration changes on the TfNSW transport network. This document supports T MU AM PL by providing practical guidance for the preparation of configuration change request submissions to the TfNSW CMAAC. 2. Purpose 2.1. Scope The purpose of this document is to provide guidance to configuration change managers for preparing, submitting and presenting configuration management change request submissions or notifications to the TfNSW CMAAC in order to progress through the relevant configuration management gates. This document describes the expectations and approach for preparing, submitting and presenting submissions to the TfNSW CMAAC meeting at the following configuration management gates: gate 0 - initiation gate 1 requirements complete gate 5 asset acceptance gate 6 asset assurance review Guidance for submissions made to delegated authorities, commonly referred to as configuration control boards (CCBs) are not covered by this document. This document should be used in conjunction with T MU AM PL which specifies the arrangements for TfNSW configuration management Application This document is applicable to any party accountable or responsible for preparing configuration change requests submissions or notifications required at configuration management gate 0, gate1, gate 5 and gate 6. Submissions and notifications are presented to the TfNSW CMAAC for acceptance in order to progress through the relevant configuration management gates. State of NSW through Transport for NSW Page 5 of 25

6 These configuration management gates occur respectively in the lead up to the strategic business case and final business case, as described in the TfNSW Investment Gating and Assurance guidelines, followed by asset handover and maintenance activities. 3. Reference documents The following documents are cited in the text. For dated references, only the cited edition applies. For undated references, the latest edition of the referenced document applies. Australian standards AS ISO Quality Management System Guidelines for Configuration Management Transport for NSW standards T MU AM PL TfNSW Configuration Management Plan TS System Safety Standard for New or Altered Assets Other references TfNSW, Investment Gating and Assurance Guidelines, 2013, policy no. CPsd13001, (available on request from standards@transport.nsw.gov.au) 4. Terms and definitions The following terms and definitions apply in this document: ASA Asset Standards Authority CCB configuration control board CMAAC Configuration Management and Asset Assurance Committee configuration change request is a formal request to add or change a TfNSW transport asset that is subject to configuration control configuration change manager is the person who has the primary responsibility for a configuration change ISCA initial safety change assessment SFAIRP so far as is reasonably practicable TfNSW Transport for New South Wales State of NSW through Transport for NSW Page 6 of 25

7 5. Configuration change requests presented to the TfNSW CMAAC Configuration changes affecting current or planned TfNSW assets, including property and airspace, need to be accepted by the TfNSW CMAAC at the gates defined in T MU AM PL. The TfNSW CMAAC will review changes that pose substantial risks to TfNSW assets. Safety, financial, reputational, operational, maintenance factors and a whole-of-life costing approach should be considered when determining risk. Configuration changes that are not significant may be presented to the TfNSW CMAAC for acceptance in the form of a notification. Each configuration change will be considered on a case by case basis. Each set of configuration change should be assessed holistically, taking into consideration all interrelated configuration changes. For example, consideration should be given to the effects of individual commissioning stages, the effect to overall change and how changes will integrate into the network. The TfNSW CMAAC may request configuration change requests submissions or audit configuration changes at any point in time Significance of a configuration change The means of determining the significance of a configuration change is defined within the T MU AM PL and TS System Safety Standard for New or Altered Assets. Configuration change managers are responsible for determining the significance of the configuration change and for presenting to the TfNSW CMAAC at gate 0, gate 1, gate 5 and gate Gate 0 configuration changes A proposed configuration change should be presented to the TfNSW CMAAC, or an appropriately authorised delegate, for acceptance at an early stage of planning as shown in Figure 1. Acceptance by the TfNSW CMAAC or delegate forms part of the strategic business case of a project and needs to occur prior to the strategic business case submission. State of NSW through Transport for NSW Page 7 of 25

8 Figure 1 Asset life cycle The gate 0 configuration change request is submitted when initial business requirements are developed and preliminary assessments of the configuration change have been performed. At this point, a single configuration change option may not have been developed but a number of options should have been identified. Evidence of a safety change impact assessment and initial assurance and governance arrangements of the configuration change are also required at this point. The order of preceding assurance activities that is required for gate 0 submission is as shown in Figure 2. The gate 0 submission provides TfNSW with confidence that adequate assurance activities have been performed, that the proposed configuration change is feasible, and that the project has an adequate plan for progressing the proposal from gate 0 through to gate 1. It is intended that any decisions to date will be demonstrated to have ensured safety so far as is reasonably practicable (SFAIRP). Demonstration that a systems engineering approach has been used to manage the development of the proposed configuration change will assist in providing confidence that appropriate assurance activities have been and will continue to be conducted. Where appropriate, a single consolidated gate 0 submission may be submitted to cover a set of similar or related proposed configuration changes that are being managed as a single program of work. Assessment of the significance should be considered based on the overall program submission. State of NSW through Transport for NSW Page 8 of 25

9 Initial Business Requirements Safety Change Impact Assessment Options identified Initial Assurance and Governance Plan TfNSW CMAAC Gate 0 Submission Figure 2 - Gate 0 submission relative to preceding activities 6.1. Significant configuration change requests at gate 0 Gate 0 configuration changes determined by the configuration change manager as being significant are to be presented to the TfNSW CMAAC at a scheduled meeting unless specific arrangements exist for the configuration change request to be accepted by other means Overview submission document The configuration change manager provides an overview of the proposed configuration change through a written submission and short presentation. The submission is not intended to provide in-depth details of the project but should comprise enough information to provide the TfNSW CMAAC with an adequate understanding of the proposal, particularly from an assurance perspective. The overview should include a summary of the following information: the scope of the configuration change assurance activities conducted to date, including activities relating to: ᴑ ᴑ ᴑ ᴑ stakeholders operational and maintenance considerations, such as a high-level operations and maintenance concept network strategy alignment considerations of whole of life costs where possible the structured approach that will be taken to progress to gate 1, including status of the assurance and governance plan identified initial business requirements and the approach taken to develop the requirements State of NSW through Transport for NSW Page 9 of 25

10 assessments, reports or other evidence that show how the safety risks of the configuration change has been assessed and reduced SFAIRP. identified significant risks or outstanding issues and the approach for controlling managing these. Documented risks and issues may include delivery, stakeholder, operational, maintainability, interfaces and safety at a whole-of-network level any other matter the configuration change manager believes the TfNSW CMAAC should be aware of The overview should demonstrate that a systematic approach has been applied to developing the assurance evidence leading to gate 0 and the planned activities through to gate 1.The information provided in the overview should be adequate so as to enable the TfNSW CMAAC to make an informed decision on the proposed change. Templates for TfNSW CMAAC submissions and presentations are available from the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au Supporting documentation A list of supporting documentation should be provided in the overview submission document. Supporting documentation provides evidence that due process has been followed in preparing the proposed configuration change. With the exception of the assurance and governance plan, copies of which need to be included in the submission, supporting documentation does not need to be included as part of the submission itself. Supporting documentation should however be readily available at the time of submission and be available to the TfNSW CMAAC or ASA if requested. Supporting documentation can include the following: initial assurance and governance plan or equivalent evidence of initial business requirements initial operational and maintenance concept document evidence that stakeholders have been identified, consulted and have had their feedback duly considered evidence that an initial safety change assessment has been carried out assessments, reports or other evidence that show how the safety risks of the configuration change has assessed and reduced so far as is reasonably practicable (SFAIRP) evidence of risk based decision making in optioneering State of NSW through Transport for NSW Page 10 of 25

11 assessments showing that cost, maintenance and other factors relevant to the proposed change have been considered to a level appropriate for the stage of the project and are planned to be completely addressed in due course Process for submission and presentation The configuration change manager or their representative should present proposals for a significant configuration change to the TfNSW CMAAC. Although gate 0 submissions may include involvement from the intended delivery organisation, the presentation to the TfNSW CMAAC should be led by the business unit accountable for the proposed change. Any queries regarding submissions and presentations can be directed to the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au. Refer to Table 1 in Appendix A for information on the submission steps for significant configuration change requests to the TfNSW CMAAC Minor or moderate configuration change requests at gate 0 Gate 0 configuration changes determined by the configuration change manager as being of minor or moderate significance are to be presented to the TfNSW CMAAC via a notification unless specific arrangements exist for the configuration change request to be accepted by a delegated body Notification submission document The configuration change manager provides a notification of the proposed configuration change through a written submission. The notification should comprise information focusing on the proposed change and key issues. The notification is to be presented to the regular meeting of the TfNSW CMAAC for acceptance, unless specific arrangements exist for the configuration change request to be accepted by a delegated body. The notification is similar to significant a gate 0 submission, but it is expected to be less detailed. The notification should include a summary of the following: the scope, including context to related configuration changes assurance activities conducted to date, which should include activities related to: ᴑ ᴑ ᴑ stakeholders operational and maintenance considerations network strategy alignment State of NSW through Transport for NSW Page 11 of 25

12 ᴑ whole-of-life costs where possible the structured approach that will be taken to progress to gate 1, including status of assurance and governance plan identified initial business requirements and the structured approach taken to develop the requirements assessments, reports or other evidence that show how the safety risks of the configuration change has assessed and reduced SFAIRP significant identified risks or outstanding issues, including risk and issues related to delivery, stakeholders, operational, maintainability, interfaces and safety any other matter the configuration change manager believes the TfNSW CMAAC should be aware of Process for providing a notification The configuration change manager should prepare the notification of the proposed minor or moderate configuration change to the TfNSW CMAAC. Any queries regarding the submissions and presentations are to be sent to the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au. Refer to Table 2 in Appendix A for the submission steps for minor or moderate configuration change requests to the TfNSW CMAAC. 7. Gate 1 configuration changes Proposed configuration changes should be presented to the TfNSW CMAAC for acceptance at gate 1. At this point, the project is expected to have an approved set of business requirements and system requirements. Acceptance of the configuration change request at gate 1 is an input to the final business case and therefore will need to be obtained before the final business case submission. The order of activities that precede a gate 1 submission will commence with the approval of the business requirements specification. Demonstration that the operation and maintenance concept and the system requirements have been developed will provide the TfNSW CMMAC with confidence that appropriate assurances are taking place. At this point the project is expected to have an approved assurance and governance arrangements of the configuration change. A gate 1 submission to the TfNSW CMAAC can proceed once these activities have taken place. Refer to Figure 3 for a diagram illustrating this process. State of NSW through Transport for NSW Page 12 of 25

13 Approved Business Requirements Specification Safety Change Impact Assessment Approved System Requirements Specification Assurance and Governance Plan Operations Concept Definition and Maintenance Concept Definition TfNSW CMAAC Gate 1 Submission Figure 3 Gate 1 submission relative to preceding assurance activities 7.1. Significant configuration change requests at gate 1 Gate 1 configuration changes determined by the configuration change manager as being significant are to be presented to the TfNSW CMAAC at a regular meeting Overview submission document The configuration change manager provides an overview of the proposed configuration change through a written submission and short presentation. The submission is not intended to provide in-depth details of the project but should comprise enough information to provide the TfNSW CMAAC with an understanding of the proposal, key issues and the management plan for those key issues. The overview should include a summary of the following: the scope of the configuration change assurance and governance arrangements of the proposed change final business requirement specifications stakeholder identification and engagement the safety SFAIRP argument supporting the preferred option over other options, and evidence that the selected option is most effective in terms of reducing safety risk when balanced against cost and effort the argument demonstrating the preferred option has been developed to be safe SFAIRP, the development of the selected option has considered safety risks and specified requirement that manage those risk SFAIRP the stage of the life cycle at which the independent safety assessor (ISA) will be appointed operational and maintenance assurance activities, and identified impacts relationship to network strategy State of NSW through Transport for NSW Page 13 of 25

14 details of whole of life cost assessment activities and processes (not dollar values) concessions to TfNSW standards that are likely to be required, including impact of the concession to operations, maintenance, safety and costs significant identified risks or outstanding issues, including risks to delivery, stakeholders, operations, maintainability, interfaces and safety any other matter the configuration change manager believes the TfNSW CMAAC should be aware of Supporting documentation The supporting documentation should demonstrate that assurance activities have been undertaken by the project. All the supporting documents are reviewed by ASA subject matter experts and any issues identified are notified to the project. Copies of the following supporting documentation should be provided as separate documents with the submission to the ASA: approved assurance and governance plan or equivalent approved business requirements specification and system required specification initial safety change assessment (ISCA) independent safety assessment report (where ISA is required to be appointed) safety assurance plan The following supporting documentation should be available upon request but does not need to be included in the submission: approved operation concept definition and maintenance concept definition evidence that stakeholders have been consulted and have had their feedback duly considered additional assessments, reports or evidence that show how the safety risks of the configuration change has reduced so far as is reasonably practicable (SFAIRP) evidence of risk based decision making in determining possible options for the configuration change assessments, reports or other evidence that show that maintenance, operational and implementation risks and factors have been considered evidence of whole of life costing activities and outcomes State of NSW through Transport for NSW Page 14 of 25

15 Process for submission and presentation The configuration change manager or their representative should present their submission to the TfNSW CMAAC. Gate 1 submission should have representation from the sponsor but may also include external consultants and personnel from the delivery organisation. Any queries regarding the submissions and presentations can be directed to the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au. Refer to Table 1 in Appendix A for an outline of the submission steps for significant configuration change requests to the TfNSW CMAAC Minor or moderate configuration change requests at gate 1 Gate 1 configuration changes determined by the configuration change manager as being of minor or moderate significance are presented to the TfNSW CMAAC via a notification unless specific arrangements exist for the configuration change request to be accepted by a delegated body Notification submission document The configuration change manager provides a notification of the proposed configuration change through a written submission. The notification should comprise enough information to provide the TfNSW CMAAC with an adequate understanding of the proposed change and key issues. The notification is to be presented to the scheduled sitting of the TfNSW CMAAC for acceptance unless specific arrangements exist for the configuration change request to be accepted by a delegated body. The notification is similar to a significant gate 1 submission but it is expected to be less detailed. The notification should include a summary of the following: the scope of the proposed change assurance and governance arrangements final business requirements specification and system required specifications stakeholder identification and engagement the safety SFAIRP argument supporting the preferred option over other options, and evidence that the selected option is most effective in terms of reducing safety risk when balanced against cost and effort State of NSW through Transport for NSW Page 15 of 25

16 the argument demonstrating the preferred option has been developed to be safe SFAIRP; the development of the selected option has considered safety risks; and, the specified the requirements that manage those risk SFAIRP operational and maintenance assurance activities and identified impacts relationship to network strategy details of whole of life cost assessment activities and process (not dollar values) concessions to TfNSW standards that are likely to be required, including impact of the concession to operations, maintenance, safety and costs significant identified risks or outstanding issues, including to delivery, stakeholders, operations, maintainability, interfaces and safety any other matter the configuration change manager believes the TfNSW CMAAC should be aware of Process for providing a notification The configuration change manager should prepare a notification of the proposed minor or moderate configuration change to the TfNSW CMAAC. Any queries regarding the submissions and presentations can be directed to the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au. Refer to Table 2 in Appendix A for an outline of the submission steps for minor or moderate configuration change requests to the TfNSW CMAAC. 8. Gate 5 configuration changes The TfNSW CMAAC or the CCB with delegated authority needs to accept any configuration change that is be commissioned. This section provides guidance for the preparation of gate 5 submissions to the TfNSW CMAAC Significant configuration change requests at gate 5 Gate 5 configuration changes determined by the configuration change manager as being significant are to be presented to the TfNSW CMAAC at a regular meeting. This gate occurs at the point shortly before the handover of the asset from the project team to maintainer. State of NSW through Transport for NSW Page 16 of 25

17 Overview submission document T MU AM GU The configuration change manager provides an overview of the configuration change through a written submission and short presentation. The overview is not intended to provide in-depth details of the project but should comprise enough information to provide the TfNSW CMAAC with an adequate understanding of the proposed configuration, key issues, and the management plan for those key issues. The overview should include a summary of the following: the scope of the proposed change compliance to the approved assurance and governance plan, or a summary of the assurance and governance arrangements if the project was started prior to the requirement for an assurance and governance plan preceding configuration change requests, particularly any outstanding conditions associated evidence that the approved business and system requirements have been met. Evidence that any variance to the requirements have been managed since initial approval. stakeholder consultation, particularly in relation to operational readiness. Summarise significant issues identified from stakeholders consultation and how it has been managed. the argument that the implemented configuration change is safe SFAIRP and evidence of the independent safety assessment and conclusion residual safety risks and hazards that TfNSW is being asked to accept and the status of these in relation to the future asset operator and maintainer the status of the operational safety argument commissioning and operational readiness planning activities evidence that technical approvals for all the elements of the configuration change has been obtained concessions to TfNSW standards that have been required, including noting the status and resulting impact to safety, whole of life cost, operations and maintainability of the concessions. Configuration changes are expected to be managed so as to be presented at gate 5 with no outstanding concessions. asset information has been delivered and schedules in place for the delivery of the remaining asset information how configuration information has or will be checked for accuracy and completeness before being delivered to the custodian State of NSW through Transport for NSW Page 17 of 25

18 any risks, issues and outstanding matters to be addressed prior to the completion of the project and time frames for their completion Supporting documentation A list of the supporting documentation available should be provided in the overview. Copies of the following supporting documentation should be provided as separate documents, but still part of the submission to TfNSW CMAAC Secretary: safety assurance report evidence, in the form of a safety report, that safety risks of the configuration change have been reduced SFAIRP an operational safety argument and supporting evidence with content as required by TS an independent safety assessment report The following supporting documentation should be available upon request but does not need to be included in the submission: evidence that stakeholders have been identified, consulted and have had their feedback duly considered evidence of acceptance of preceding configuration change requests evidence showing compliance to an assurance and governance plan stakeholder consultation report and register operational readiness arrangements such as an operational readiness plan asset hand over plan evidence that technical approvals for all the elements of the configuration change has been obtained requirements traceability evidence that configuration information has been checked for accuracy and completeness before being delivered evidence of hazard identification, hazard log and analysis report any other document that supports the claims made in the submission document Process for submission and presentation The configuration change manager or their representative should present their submission to the TfNSW CMAAC. State of NSW through Transport for NSW Page 18 of 25

19 Any queries regarding the submissions and presentations can be directed to the TfNSW CMAAC Secretary via Refer to Table 1 in Appendix A for an outline of the submission steps for significant configuration change requests to the TfNSW CMAAC Moderate configuration change requests at gate 5 Gate 5 configuration changes determined by the configuration change manager as being of moderate significance are to be presented to the TfNSW CMAAC via a notification unless specific arrangements exist for the configuration change request to be accepted by a delegated body Notification submission document The configuration change manager provides a notification of the proposed configuration change through a written submission. The notification is not intended to provide in-depth details of all activities performed in supporting the project but should comprise enough information to provide the TfNSW CMAAC with an adequate understanding of the proposed change and key issues in relation to configuration management and asset assurance. The notification is similar to gate 5 significant submissions but it is expected to be less detailed. The notification should include a summary of the following: the scope of the configuration change compliance to the approved assurance and governance plan, or a summary the assurance and governance arrangements if the project was started prior to the requirement for an assurance and governance plan preceding configuration change requests, particularly any outstanding conditions associated confirmation that business and system requirements have been met stakeholder consultation particularly in relation to operational readiness the argument that the implemented configuration change is safe SFAIRP and evidence of the independent safety assessment and conclusion residual safety risks and hazards that TfNSW is being asked to accept and the status of these in relation to the future asset operator and maintainer the status of the operational safety argument commissioning and operational readiness planning activities State of NSW through Transport for NSW Page 19 of 25

20 evidence that technical approvals for all the elements of the configuration change has been obtained concessions to TfNSW standards that have been required, including noting the status and resulting impact to safety, whole of life cost, operations and maintainability of the concessions. Configuration changes are expected to be managed so as to be presented at gate 5 with no outstanding concessions. asset information has been delivered and schedules in place for the delivery of the remaining asset information configuration information has or will be checked for accuracy and completeness before being delivered to the custodian any risks, issues or outstanding matters to be addressed prior to the completion of the project; and timeframes for their completion Process for providing a notification The configuration change manager should prepare a notification of the proposed moderate configuration change to the TfNSW CMAAC. Any queries regarding the submissions and presentations can be directed to the TfNSW CMAAC Secretary via configuration@transport.nsw.gov.au. Refer to Table 2 of Appendix A for an outline of the submission steps for moderate configuration change to the TfNSW CMAAC Minor configuration change requests at gate 5 Gate 5 configuration changes determined by the configuration change manager as being of minor significance does not require presentation to the TfNSW CMAAC. However, acceptance should be provided from a delegated CCB. If no delegated CCB exists, the minor configuration change should apply the same provisions as moderate configuration changes. Refer to Section 8.2 State of NSW through Transport for NSW Page 20 of 25

21 9. Gate 6 configuration changes T MU AM GU Parties in control of TfNSW transport assets during the operate and maintain stage of an asset life cycle are required to present a gate 6 configuration change request to the TfNSW CMAAC as required. Parties in control of TfNSW transport assets typically have at least one CCB with delegated authority. This is obtained by having their configuration management plan approved by the ASA CCB. The submission is intended to achieve the following objectives: demonstrate that a risk based approach has been applied in developing the asset maintenance plan and annual works plan demonstrate that the asset or system meets its appropriate and intended requirements under stated operating conditions demonstrate that the previous asset maintenance plan and annual works plan have been achieved identify incomplete work and justification of risks and mitigation activities demonstrate that monthly key performances such as punctuality, reliability, reduced incidents, and so on have been achieved provide evidence of appropriate control and assurance of assets in the form of asset condition or audit reports, or reviews of such documents by second or third parties provide justified confidence in the delivery of approved asset maintenance plans and associated annual work plans demonstrate evidence of appropriate configuration control and assurance activities in accordance with approved documentation over the preceding review period demonstrate evidence of appropriate configuration management and assurance activities in planning the continued management, change control and assurance of the assets over the review period Review periods should be defined in the configuration management plan of the organisation in control of the TfNSW transport asset. Where no review period is specified, the organisation should consult with the ASA to determine an appropriate time frame. Typically reviews are expected to occur on an annual basis, and within a period that allows the outcome of the gate 6 submission to influence decisions about planned works in the following period. The configuration change manager for a gate 6 submission should be selected by the organisation submitting the configuration change. The chair of the peak delegated CCB within State of NSW through Transport for NSW Page 21 of 25

22 an organisation in control of assets during operation and maintenance would be a likely candidate to fulfil the role of configuration change manager Overview submission document The configuration change manager provides an overview of the configuration change through a written submission and short presentation. The overview is not intended to provide in-depth details of all activities performed in the course of managing the assets being controlled but should comprise enough information to provide the TfNSW CMAAC with an adequate understanding of the processes and decisions made in the course of managing and planning for the management of the asset as appropriate. The overview should include summaries of the following: the scope of assets and activities performed assurance and governance arrangements identified significant configuration changes that will be presented to the TfNSW CMAAC, gate 0, gate 1 and gate 5 which is not managed under the delegated configuration control authority of the organisation planning arrangements for maintenance activities and planned configuration changes having been selected based on an appropriate processes that consider the network strategy and the long term interests of TfNSW argument to support the case that the assets managed over the preceding review period have been done safely SFAIRP argument to support the case that the planning for the management of the assets over the proceeding period will result in assets that are safe SFAIRP Supporting documentation The supporting documentation available should be listed in the overview and be readily available for TfNSW CMAAC review. Copies of the following supporting documentation should be included as part of the submission to the TfNSW CMAAC Secretary: asset maintenance plan past and planned annual works plan asset assurance reports KPI reports such as the Rail Services Contract (RSC) report evidence of audit report carried out on asset conditions and performance State of NSW through Transport for NSW Page 22 of 25

23 evidence of appropriate configuration change control over the preceding review period evidence of appropriate safety and risk assurance in the course of maintaining and changing assets over the preceding review period 10. Submission templates The ASA manages a set of configuration change request templates for submissions to the TfNSW CMAAC. The latest versions of the templates are available to configuration change managers from the ASA when a project initially engages with the ASA to discuss their submission. Configuration change managers should ensure that the latest template has been used in their submission. 11. Presentations to the TfNSW CMAAC Presentations to the TfNSW CMAAC should consist of a concise slide show lasting less than five minutes. The slide show should focus on the key governance and assurance activities and supporting evidence developed by the project. Presentations should be limited to five slides of content. Information about the project background and scope should be minimised in the presentation slides. Presenters will usually be provided with a copy of the same documented guidance that the ASA provides to TfNSW CMAAC members. Presenters should be prepared to answer questions related to points listed in the guidance. To improve the possibility of an unconditional acceptance by the TfNSW CMAAC, a written response to the matters raised in the ASA guidance should be prepared and provided during the presentation to the TfNSW CMAAC members. Fifteen minutes will usually be allocated to each configuration change request presented to the TfNSW CMAAC. This is to allow time for questions and discussion. 12. TfNSW CMAAC assessment The TfNSW CMAAC will assess each proposal or asset acceptance configuration change request on a case by case basis. The TfNSW CMAAC members will base their decision on the following: compliance to appropriate due processes evidence showing that the configuration change will be adequately controlled evidence showing that expected outcomes will be delivered State of NSW through Transport for NSW Page 23 of 25

24 identification of potential risks and measures to address those risks 13. TfNSW CMAAC decision Upon assessment of a concept or asset acceptance configuration change request, the TfNSW CMAAC may decide to accept the change, accept the change with conditions or defer its decision. Where an acceptance to the change is granted with conditions, the conditions are to be met and maintained for the acceptance to remain valid. Where conditions require specific activities to be performed, configuration change managers are expected to provide evidence to the TfNSW CMAAC that the conditions have been met prior to proceeding to the subsequent configuration management gates. State of NSW through Transport for NSW Page 24 of 25

25 Appendix A Submission steps for configuration change The submission steps for significant, moderate and minor configuration change are outlined in the Table 1 and Table 2. All notifications and submissions should be sent to configuration@transport.nsw.gov.au Table 1 Submission steps for significant configuration change requests Step Description When 1 Notify Manager Asset Configuration Systems, ASA of the development of a proposed configuration change 2 Notify the TfNSW CMAAC Secretary that acceptance of the proposed configuration change will be sought in the near future. This assists the ASA and TfNSW CMAAC to plan meeting arrangements. 3 Request the TfNSW CMAAC Secretary add the proposed configuration change to the next available TfNSW CMAAC meeting. If feedback from the ASA is sought then provide a draft submission. 4 Provide the TfNSW CMAAC Secretary with the final submission and supporting documentation for circulation to TfNSW CMAAC members. This is required for the submission to be included on the agenda. Early in the development of the proposed configuration change Three months prior to presentation at the TfNSW CMAAC Six weeks prior to presentation at the TfNSW CMAAC Two weeks prior to presentation at the TfNSW CMAAC 5 Provide the TfNSW CMAAC Secretary with the presentation Two days prior to presentation at the TfNSW CMAAC Table 2 Submission steps for moderate and minor configuration change requests Step Description When 1 Notify the TfNSW CMAAC Secretary of the development of a proposed configuration change. 2 Notify the TfNSW CMAAC Secretary that acceptance of the proposed configuration change will be sought at a forthcoming TfNSW CMAAC meeting. 4 Provide the TfNSW CMAAC Secretary with a completed notification. This is required for the notification to be included on the agenda Early in the development of the proposed configuration change Six weeks prior to submitting notification to the TfNSW CMAAC Two weeks prior to applicable TfNSW CMAAC meeting State of NSW through Transport for NSW Page 25 of 25

Superseded by T MU AM 04001 PL v2.0

Superseded by T MU AM 04001 PL v2.0 Plan T MU AM 04001 PL TfNSW Configuration Management Plan Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by

More information

Engineering Procedure

Engineering Procedure Engineering Procedure Design Owner: EPD 0014 MANAGING CONFIGURATION CHANGE Manager, Engineering Standards and Configuration Version 2.1 Issued February 2010 Approved Jagath Peiris Authorised Jim Modrouvanos

More information

TfNSW Standard Requirements TSR T Technical Management

TfNSW Standard Requirements TSR T Technical Management Template Applicable to: Transport Projects Quality Management System Status: Division: Approved Transport Projects Version: 5.0 Desksite No.: 3455797_1 Date of issue: 1 July 2014 Effective date: 1 July

More information

AEO Guide to Engineering Management

AEO Guide to Engineering Management Management standard AEO Guide to Engineering Management Issued Date: 4 June 2013 Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network

More information

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart)

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) Audit activity is governed by the HEFCE Code of Audit Practice. 1. Determining audit activity a) Audits will be conducted

More information

Rail Network Configuration Management

Rail Network Configuration Management Division / Business Unit: Function: Document Type: Enterprise Services Engineering Procedure Rail Network Configuration Management Applicability ARTC Network Wide SMS Publication Requirement Internal /

More information

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER As at 31 March 2014 BOARD CHARTER Contents 1. Role of the Board... 4 2. Responsibilities of the Board... 4 2.1 Board responsibilities... 4 2.2 Executive

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

Corporate Governance Report

Corporate Governance Report Corporate Governance Report Chairman s introduction From 1 January 2015 until 31 December 2015, the company applied the 2014 edition of the UK Corporate Governance Code (the Code ). 1. BOARD COMPOSITION

More information

Collaborative development of evaluation capacity and tools for natural resource management

Collaborative development of evaluation capacity and tools for natural resource management Collaborative development of evaluation capacity and tools for natural resource management Helen Watts (Adaptive Environmental Management, formerly NSW Department of Environment and Climate Change) Sandra

More information

Project Management Fact Sheet:

Project Management Fact Sheet: Project Management Fact Sheet: Project Documentation Version: 2.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that

More information

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS Approved 10 July 2015 CONTENTS 1. INTRODUCTION 1 2. OVERVIEW OF THE ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING

More information

Project Management Manual

Project Management Manual Project Management Manual PM01 Introduction to the Project Management Manual Ref: PM01 (V7.01) - Uncontrolled once Printed Issued on 20 th December 2006 Manual Owner: James Couper Head of Project Management

More information

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Manager Organisational Development

More information

Reporting Service Performance Information

Reporting Service Performance Information AASB Exposure Draft ED 270 August 2015 Reporting Service Performance Information Comments to the AASB by 12 February 2016 PLEASE NOTE THIS DATE HAS BEEN EXTENDED TO 29 APRIL 2016 How to comment on this

More information

Risk Management Committee (Committee) Terms of Reference

Risk Management Committee (Committee) Terms of Reference Risk Management Committee (Committee) Terms of Reference 1. Objective of Committee 1.1 The Risk Management Committee ( the Committee ) is a formal sub-committee of the Board of the JSE ( the Board ). 1.2

More information

2015 REVIEW QUALITY ASSURANCE STRATEGIC PLAN

2015 REVIEW QUALITY ASSURANCE STRATEGIC PLAN 2015 REVIEW QUALITY ASSURANCE STRATEGIC PLAN May 2014 CONTENTS INTRODUCTION 1 OBJECTIVES 1 WHAT WE WANT TO ACHIEVE? 1 WHO HAS RESPONSIBILITY? 2 STRATEGIES 2 QA STRATEGIES FOR THE 2015 REVIEW 2 OBJECTIVE

More information

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper august09 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface Corporate governance - which refers broadly to the processes

More information

Quality Assurance. Policy P7

Quality Assurance. Policy P7 Quality Assurance Policy P7 Table of Content Quality assurance... 3 IIA Australia quality assurance and professional standards... 3 Quality assurance and professional qualifications... 4 Quality assurance

More information

Australian Standard. Quality management systems Guidelines for configuration management AS ISO 10007 2003 ISO 10007:2003 AS ISO 10007

Australian Standard. Quality management systems Guidelines for configuration management AS ISO 10007 2003 ISO 10007:2003 AS ISO 10007 AS ISO 10007 2003 ISO 10007:2003 AS ISO 10007 Australian Standard Quality management systems Guidelines for configuration management This Australian Standard was prepared by Committee QR-008, Quality Systems.

More information

Housing Related Support Contract Management Framework 2009/10

Housing Related Support Contract Management Framework 2009/10 Housing Related Support Contract Management Framework 2009/10 0 If you would like this information in large print, audio tape or in any other format or language please contact the public information officer

More information

Clinical Risk Management: its Application in the Manufacture of Health IT Systems - Implementation Guidance

Clinical Risk Management: its Application in the Manufacture of Health IT Systems - Implementation Guidance Document filename: ISB 0129 Implementation Guidance v2.1 Directorate Solution Design Standards and Assurance Project Clinical Safety Document Reference NPFIT-FNT-TO-TOCLNSA-1300.03 Director Rob Shaw Status

More information

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation Page 1 of 11 Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation This work is copyright. It may be reproduced in whole or in part for study or training purposes

More information

Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux

Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux Version 6.3 Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux France Secretariat email: gfsinfo@theconsumergoodsforum.com

More information

DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS

DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS WELDING FABRICATOR CERTIFICATION SCHEME DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS 6 th Edition July 2012 Issued under the authority of the Governing Board for Certification All correspondence should

More information

Clarius Group Risk Management Policy and Framework

Clarius Group Risk Management Policy and Framework 1. Introduction Clarius Group Risk Management Policy and Framework 1.1 Definition Risk is the chance of something happening that will have an impact on objectives. Risk provides the opportunity (upside)

More information

The Compliance Universe

The Compliance Universe The Compliance Universe Principle 6.1 The board should ensure that the company complies with applicable laws and considers adherence to non-binding rules, codes and standards This practice note is intended

More information

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY

More information

Assessment and Reporting in Society and Culture Stage 6

Assessment and Reporting in Society and Culture Stage 6 Assessment and Reporting in Society and Culture Stage 6 Effective from 2015 HSC Date published June 2014 This document contains the Board of Studies, Teaching and Educational Standards NSW (BOSTES) requirements

More information

The New Zealand Human Services Quality Framework - ISO9002:2008 to 2012

The New Zealand Human Services Quality Framework - ISO9002:2008 to 2012 HUMAN SERVICES QUALITY FRAMEWORK STANDARDS - POLICIES DOCUMENT Q:/1 DATE REVEIWED: REFERENCE: GOVERNANCE AND August 2014 MANAGEMENT POLICY AUTHORISATION: STANDARD REFERENCE: NEXT REVIEW DATE: Management

More information

Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011

Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011 Australian Medical Council Limited Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011 Medical School Accreditation Committee These procedures were approved

More information

3 August 2012 Policy updated to reflect name changes and alignment with current Aurora Energy Group Policy standards.

3 August 2012 Policy updated to reflect name changes and alignment with current Aurora Energy Group Policy standards. Aurora Energy Risk Management Policy Version History REV NO. DATE REVISION DESCRIPTION APPROVAL 0 19/11/98 Risk Management Policy Prepared by: Manager Internal Audit 1 March 2007 Risk Management Policy

More information

Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement.

Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement. Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement June 2011 DISCLAIMER: This document is intended as a general guide only.

More information

JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES. Draft

JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES. Draft APPENDIX 1 JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES Draft CONTENTS 1. INTRODUCTION 2. SCOPE 3. PROGRAMME AND PROJECT MANAGEMENT GOVERNANCE 4. PROGRAMME MANAGEMENT

More information

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218 Copyright in the material is owned by the State of New South Wales. Apart from any use as permitted under the Copyright Act 1968 and/or as explicitly permitted below, all other rights are reserved. You

More information

28.02.2012. Mr Timothy Pilgrim The Privacy Commissioner Office of the Australian Information Commissioner GPO Box 5218 SYDNEY NSW 2001

28.02.2012. Mr Timothy Pilgrim The Privacy Commissioner Office of the Australian Information Commissioner GPO Box 5218 SYDNEY NSW 2001 28.02.2012 Mr Timothy Pilgrim The Privacy Commissioner Office of the Australian Information Commissioner GPO Box 5218 SYDNEY NSW 2001 Dear Mr Pilgrim, The Australian Taxation Office (ATO) appreciates the

More information

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES WHS UNIT WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES Contents 1 Purpose... 1 2 Scope... 1 3 Definitions... 1 4 Responsibilities... 1 4.1 WHS Unit... 1 4.2 Auditor(s)... 1 4.3 Managers of Faculties

More information

Completing the critical reflection log

Completing the critical reflection log The assessed and supported year in employment in adult services Completing the critical reflection log Supporting guidance www.skillsforcare.org.uk/asye Completing the critical reflection log: Supporting

More information

Monitoring Highways England The monitoring framework

Monitoring Highways England The monitoring framework Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested

More information

South East Water Corporation Finance Audit and Risk Management Committee Charter. October 2012

South East Water Corporation Finance Audit and Risk Management Committee Charter. October 2012 South East Water Corporation Finance Audit and Risk Management Committee Charter October 2012 Version: 1.0 Page 1 of 6 DOCUMENT NUMBER BS 2359 1. Purpose The South East Water Corporation Board's Finance

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Accreditation at Highly Accomplished and Lead Teacher. Information for Referees

Accreditation at Highly Accomplished and Lead Teacher. Information for Referees Accreditation at Highly Accomplished and Lead Teacher Information for Referees Contents Introduction... 3 Candidate s evidence for accreditation... 3 Importance of referee statements... 3 Candidate s selection

More information

Engineering Procedure

Engineering Procedure Engineering Procedure Design EPD 0005 REQUIREMENTS ANALYSIS, ALLOCATION AND TRACEABILITY Owner: Manager, Engineering Standards and Configuration Version 2.0 Issued October 2009 Approved Jagath Peiris Authorised

More information

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 D to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 This page has been left blank intentionally Page 2 of 24 Page 3 of 24 This page has been left blank intentionally Page 4 of 24 Strategic

More information

Internal Audit Division

Internal Audit Division Internal Audit Division at the Financial Conduct Authority Information Pack April 2013 Contents of Information Pack A. Introduction B. Internal Audit Terms of Reference C. Organisation D. Skills and Competencies

More information

QUALITY MANAGEMENT PLAN

QUALITY MANAGEMENT PLAN QUALITY MANAGEMENT PLAN Project Name EfW CHP Facility, North Yard, Devonport Project Number: C1005 Location: North Yard, Devonport Dockyard, Plymouth Approved by: Dated: Signed: KIER Project Manager Reviewed

More information

BLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL

BLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL 130 Wisbech Road Outwell Wisbech Cambridgeshire PE14 8PF Tel: (01945) 772578 Fax: (01945) 773135 Copyright 2003. This Manual and the information contained herein are the property Bloom & Wake (Electrical

More information

Compliance Management Framework. Managing Compliance at the University

Compliance Management Framework. Managing Compliance at the University Compliance Management Framework Managing Compliance at the University Risk and Compliance Office Effective from 07-10-2014 Contents 1 Compliance Management Framework... 2 1.1 Purpose of the Compliance

More information

South East Water Corporation Finance Assurance and Risk Management Committee Charter

South East Water Corporation Finance Assurance and Risk Management Committee Charter South East Water Corporation Finance Assurance and Risk Management Committee Charter Created: October 2012 Document number: BS 2359 Last reviewed: May 2015 1. Purpose The South East Water Corporation Board's

More information

NSW Data & Information Custodianship Policy. June 2013 v1.0

NSW Data & Information Custodianship Policy. June 2013 v1.0 NSW Data & Information Custodianship Policy June 2013 v1.0 CONTENTS 1. PURPOSE... 4 2. INTRODUCTION... 4 2.1 Information Management Framework... 4 2.2 Data and information custodianship... 4 2.3 Terms...

More information

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Department of Planning, Transport and Infrastructure 136 North

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

Disability ACT. Policy Management Framework

Disability ACT. Policy Management Framework Disability ACT Policy Management Framework OCT 2012 Disability ACT Policy Management Framework Version October 2012 Page 1 of 19 1. Context... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 Background... 3 1.4

More information

Australian Standard. Information technology Service management. Part 2: Guidance on the application of service management systems

Australian Standard. Information technology Service management. Part 2: Guidance on the application of service management systems ISO/IEC 20000-2:2012 AS ISO/IEC 20000.2 2013 Australian Standard Information technology Service Part 2: Guidance on the application of service systems This Australian Standard was prepared by Committee

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

Tasmania Prison Service Department of Justice. Performance Management Policy and Framework

Tasmania Prison Service Department of Justice. Performance Management Policy and Framework Tasmania Prison Service Department of Justice Performance Management Policy and Framework January 2014 1 Authorised by: Position of authorising person: Brian Edwards Director, Tasmania Prison Service Date

More information

Relationship Manager (Banking) Assessment Plan

Relationship Manager (Banking) Assessment Plan Relationship Manager (Banking) Assessment Plan ST0184/AP03 1. Introduction and Overview The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It

More information

Risk management systems of responsible entities: Further proposals

Risk management systems of responsible entities: Further proposals CONSULTATION PAPER 263 Risk management systems of responsible entities: Further proposals July 2016 About this paper This paper sets out our proposals to provide guidance to responsible entities on our

More information

Information and Communications Technology (ICT) Steering Committee - Information Sheet

Information and Communications Technology (ICT) Steering Committee - Information Sheet Information and Communications Technology (ICT) Steering Committee - Information Sheet Version 2.2 Thursday, June 30, 2011 Document Ownership Information Document Owner M Livesley Document Preparation

More information

Dodo Power & Gas Complaint Management Policy

Dodo Power & Gas Complaint Management Policy DODO POWER & GAS PTY LTD Dodo Power & Gas Complaint Management Policy Jurisdiction: All 2013 Policy Reference ref DPG 100-004 Version: 1.2 Author: Status Andrew Mair Draft Publication Date 7/06/2013 Location:

More information

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010 Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0

More information

SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY

SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY 1. POLICY STATEMENT Having regard to AS/NZS ISO 31000 Risk Management, it shall be the Policy of SRW to manage risk to protect public safety, quality

More information

Quality Assurance Checklist

Quality Assurance Checklist Internal Audit Foundations Standards 1000, 1010, 1100, 1110, 1111, 1120, 1130, 1300, 1310, 1320, 1321, 1322, 2000, 2040 There is an Internal Audit Charter in place Internal Audit Charter is in place The

More information

Tool Enhancement Assessment Framework

Tool Enhancement Assessment Framework Tool Enhancement Assessment Framework VERSION 1.0 January 2014 Published by Office of Environment and Heritage 59 Goulburn Street PO Box A290 Sydney South NSW 1232 Ph: (02) 9995 5000 (switchboard) Ph:

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

Information Management Responsibilities and Accountability GUIDANCE September 2013 Version 1

Information Management Responsibilities and Accountability GUIDANCE September 2013 Version 1 Information Management Responsibilities and Accountability GUIDANCE September 2013 Version 1 Document Control Document history Date Version No. Description Author September 2013 1.0 Final Department of

More information

CODE GOVERNANCE COMMITTEE CHARTER. 1 Functions and responsibilities of the Code Governance Committee

CODE GOVERNANCE COMMITTEE CHARTER. 1 Functions and responsibilities of the Code Governance Committee CODE GOVERNANCE COMMITTEE CHARTER 1 Functions and responsibilities of the Code Governance Committee 1.1 Consistent with the Code and the Constitution, the Code Governance Committee shall be responsible

More information

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive

More information

Spillemyndigheden s change management programme. Version 1.3.0 of 1 July 2012

Spillemyndigheden s change management programme. Version 1.3.0 of 1 July 2012 Version 1.3.0 of 1 July 2012 Contents 1 Introduction... 3 1.1 Authority... 3 1.2 Objective... 3 1.3 Target audience... 3 1.4 Version... 3 1.5 Enquiries... 3 2. Framework for managing system changes...

More information

Quality Management: Co-ordinated activities to direct and control an organisation with regards to quality ISO9000

Quality Management: Co-ordinated activities to direct and control an organisation with regards to quality ISO9000 Plan the Development of Your Quality System Half a day spent thinking and planning how you will approach your ISO 9001 accreditation and certification will leave you with a project scope that makes sense,

More information

Automated Funding Proposal

Automated Funding Proposal Disability Services Individual Support Package Automated Funding Proposal Business Practice Guide For application in: Client Relationship Information System and Client Relationship Information System for

More information

Preparation of a Rail Safety Management System Guideline

Preparation of a Rail Safety Management System Guideline Preparation of a Rail Safety Management System Guideline Page 1 of 99 Version History Version No. Approved by Date approved Review date 1 By 20 January 2014 Guideline for Preparation of a Safety Management

More information

Drinking Water Quality Management Plan Review and Audit Guideline

Drinking Water Quality Management Plan Review and Audit Guideline Drinking Water Quality Management Plan Review and Audit Guideline This publication has been compiled by Queensland Water Supply Regulator, Department of Energy and Water Supply. State of Queensland, 2013.

More information

ISO 9001: 2008 Boosting quality to differentiate yourself from the competition. xxxx November 2008

ISO 9001: 2008 Boosting quality to differentiate yourself from the competition. xxxx November 2008 ISO 9001: 2008 Boosting quality to differentiate yourself from the competition xxxx November 2008 ISO 9001 - Periodic Review ISO 9001:2008 Periodic Review ISO 9001, like all standards is subject to periodic

More information

Board Charter. May 2014

Board Charter. May 2014 May 2014 Document History and Version Control Document History Document Title: Board Charter Document Type: Charter Owner: Board [Company Secretary] Description of content: Corporate Governance practices

More information

QUALITY MANAGEMENT POLICY & PROCEDURES

QUALITY MANAGEMENT POLICY & PROCEDURES QUALITY MANAGEMENT POLICY & PROCEDURES Policy Statement Cotleigh Engineering Co. Limited specialises in the recruitment of engineering & technical personnel in the oil & energy, rail, civil engineering,

More information

Network Rail Limited (the Company ) Terms of Reference. for. The Nomination and Corporate Governance Committee of the Board

Network Rail Limited (the Company ) Terms of Reference. for. The Nomination and Corporate Governance Committee of the Board Network Rail Limited (the Company ) Terms of Reference for The Nomination and Corporate Governance Committee of the Board Membership 1 The Nomination and Corporate Governance Committee (NCGCom) shall comprise

More information

ACADEMIC POLICY FRAMEWORK

ACADEMIC POLICY FRAMEWORK ACADEMIC POLICY FRAMEWORK Principles, Procedures and Guidance for the Development & Review of Academic Policies [V.1] Page 2 of 11 TABLE OF CONTENTS 1. FRAMEWORK OVERVIEW... 3 2. PRINCIPLES... 4 3. PROCESS...

More information

GUIDANCE NOTE DECISION-MAKING PROCESS

GUIDANCE NOTE DECISION-MAKING PROCESS GUIDANCE NOTE DECISION-MAKING PROCESS This document is intended as a general guide to the way in which the Jersey Financial Services Commission (the Commission ), normally approaches the exercise of its

More information

QUALITY MANAGEMENT SYSTEM DEVELOPMENT AND REVIEW PROCEDURE

QUALITY MANAGEMENT SYSTEM DEVELOPMENT AND REVIEW PROCEDURE Controlled Document Refer to NMIT website or intranet for latest version QUALITY MANAGEMENT SYSTEM DEVELOPMENT AND REVIEW PROCEDURE Section Approval Date 24.07.2013 Approved by Chief Executive Next Review

More information

Internal Audit (policy & procedure)

Internal Audit (policy & procedure) Internal Audit (policy & procedure) Objective (purpose) The purpose of this document is to ensure the Crime and Corruption Commission s (CCC) internal audit function operates efficiently and effectively

More information

Risk Management Policy

Risk Management Policy Principles Through a process of Risk Management, the University seeks to reduce the frequency and impact of Adverse Events that may affect the achievement of its objectives. In particular, Risk Management

More information

Communications Policy

Communications Policy [insert organisation name/logo] Communications Policy Document Status: Draft or Final Date Issued: [date] Lead Author: [name and position] Approved by: [insert organisation name] Board of Directors on

More information

ISO 9001:2008 Quality Management System Requirements (Third Revision)

ISO 9001:2008 Quality Management System Requirements (Third Revision) ISO 9001:2008 Quality Management System Requirements (Third Revision) Contents Page 1 Scope 1 1.1 General. 1 1.2 Application.. 1 2 Normative references.. 1 3 Terms and definitions. 1 4 Quality management

More information

REGULATIONS REGARDING THE HUMAN RESOURCES AND REMUNERATION COMMITTEE OF THE BOARD OF DIRECTORS OF PJSC SIBUR HOLDING (Revision No.

REGULATIONS REGARDING THE HUMAN RESOURCES AND REMUNERATION COMMITTEE OF THE BOARD OF DIRECTORS OF PJSC SIBUR HOLDING (Revision No. Approved by the Board of Directors of PJSC SIBUR Holding Minutes No. 180 of March 23, 2015 REGULATIONS REGARDING THE HUMAN RESOURCES AND REMUNERATION COMMITTEE OF THE BOARD OF DIRECTORS OF PJSC SIBUR HOLDING

More information

National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP)

National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP) National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP) Operating Manual Please check the CRN Website for the latest version. Version: 6.0 Status: Consultation in

More information

1.1 The Chair welcomed the Board members and officials to the meeting. 1.3 The Board accepted the Minute of 30 September as a true record.

1.1 The Chair welcomed the Board members and officials to the meeting. 1.3 The Board accepted the Minute of 30 September as a true record. Meeting of the Revenue Scotland Board MINUTE 09:00, 4 November 2015, Conference Room 3, VQ, Edinburgh Present: Dr Keith Nicholson [Chair] Lynn Bradley Jane Ryder OBE Ian Tait John Whiting OBE Attended:

More information

SOMERSET PARTNERSHIP NHS FOUNDATION TRUST RECORDS MANAGEMENT STRATEGY. Report to the Trust Board 22 September 2015. Information Governance Manager

SOMERSET PARTNERSHIP NHS FOUNDATION TRUST RECORDS MANAGEMENT STRATEGY. Report to the Trust Board 22 September 2015. Information Governance Manager SOMERSET PARTNERSHIP NHS FOUNDATION TRUST RECORDS MANAGEMENT STRATEGY Report to the Trust Board 22 September 2015 Sponsoring Director: Author: Purpose of the report: Key Issues and Recommendations: Director

More information

INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT.

INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT. INTERNAL AUDIT REPORT ON THE FINANCIAL MANAGEMENT CONTROL FRAMEWORK FOR INITIATIVES RELATED TO CANADA S ECONOMIC ACTION PLAN (EAP) REPORT July 2010 PREPARED BY THE INTERNAL AUDIT BRANCH (IAB) Project No:

More information

DNV GL Assessment Checklist ISO 9001:2015

DNV GL Assessment Checklist ISO 9001:2015 DNV GL Assessment Checklist ISO 9001:2015 Rev 0 - December 2015 4 Context of the Organization No. Question Proc. Ref. Comments 4.1 Understanding the Organization and its context 1 Has the organization

More information

VCE Systems Engineering: Administrative advice for School-based Assessment in 2015

VCE Systems Engineering: Administrative advice for School-based Assessment in 2015 VCE Systems Engineering: Administrative advice for School-based Assessment in 2015 Units 3 and 4 School-assessed Task The School-assessed Task contributes 50 per cent to the study score and is commenced

More information

Internal Audit Manual

Internal Audit Manual Internal Audit Manual Version 1.0 AUDIT AND EVALUATION SECTOR AUDIT AND ASSURANCE SERVICES BRANCH INDIAN AND NORTHERN AFFAIRS CANADA April 25, 2008 #933907 Acknowledgements The Institute of Internal Auditors

More information

ITIL Service Management Practices:

ITIL Service Management Practices: ITIL Service Management Practices: ITIL Master Qualification in IT Service Management Frequently Asked Questions (FAQs) May 2012 Page 1 Requirements Coverage 1 Do I have to cover every item listed in the

More information

Registration standard: Endorsement as a nurse practitioner

Registration standard: Endorsement as a nurse practitioner Registration standard: Endorsement as a nurse practitioner Consultation report February 2016 Nursing and Midwifery Board of Australia G.P.O. Box 9958 Melbourne VIC 3001 www.nursingmidwiferyboard.gov.au

More information

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information