FERC Order No. 890 The Next Generation of OATT Transmission Service

Size: px
Start display at page:

Download "FERC Order No. 890 The Next Generation of OATT Transmission Service"

Transcription

1 FERC Order No. 890 The Next Generation of OATT Transmission Service

2 Agenda 9:30 9:45 Welcome Cliff Sikora, Co-Chair of the Troutman Sanders Energy Practice 9:45-10:00 Opening Remarks Daniel Larcamp 10:00 11:00 The New Transmission Planning Paradigm Chris Jones, Troutman Sanders 11:00 11:15 Break 11:15-12:00 Calculating ATC Andrea Chambers, Troutman Sanders 12:00-1:15 Lunch and Presentation David Cook, Vice President and General Counsel, NERC 1:15-2:00 Transmission Pricing Issues Anne Dailey and Rebecca Roback, Troutman Sanders 2:00-2:45 Changes Relating to Non-Rate Terms and Conditions David Rubin, Troutman Sanders 2:45-3:00 Break 3:00-3:30 OASIS Transparency, Performance Metrics and Penalties Amie Colby, Troutman Sanders 3:30-3:45 Summary of Compliance Dates 3:45 4:00 Closing Remarks

3 Transmission Planning Chris Jones

4 Basic Premise for Planning Reform Order No. 888 basic principle Build the system to meet the needs of open access customers. Order No. 888-A encouraged joint planning but did not require that transmission providers coordinate with either their network or PTP customers in transmission planning or otherwise publish the criteria, assumptions, or data underlying their transmission plans. Order No. 890 finds that the existing OATT lacks the specific planning criteria to counter the incentives of a transmission owner to plan its system in a discriminatory manner. The lack of coordination, openness, and transparency results in opportunities for undue discrimination in transmission planning.

5 Basic Planning Requirements of Order 890 Order No. 890 requires a more open, transparent, inclusive planning process than FERC feels is not occurring under the current OATT regime. Order requires all transmission providers to file a new attachment to their OATT containing their transmission planning process. The transmission planning process to be memorialized in the OATT must follow 9 Transmission Planning Principles

6 Planning Principles 1. Coordination The transmission provider must meet with all of its transmission customers and interconnected neighbors to develop a transmission plan. FERC responded to comments and decided not to dictate the form of coordination (e.g. the number and structure of meetings) Suggests formation of a permanent planning committee made up of TP, neighboring transmission providers, affected state authorities, customers, and other stakeholders. FERC more concerned with substance over form in complying with this requirement.

7 Planning Principles 2. Openness Transmission planning meetings must be open to all affected parties. Some commenters expressed concerns that meetings must be open to the public. FERC did not order that requirement. Planning meetings must be open to all affected parties including, but not limited to, all transmission and interconnection customers, state commissions and other stakeholders. Smaller groups OK on specific issues.

8 Planning Principles 3. Transparency The transmission provider is required to disclose to all customers and other stakeholders the basic criteria, assumptions, and data that underlie its planning. This means: The basic criteria and data used for transmission planning must be reduced to writing and posted. Outside parties should be able to replicate the results. FERC expects non-jurisdictionals to comply as well. FERC deems Forms 714 and 715 to be insufficient, primarily because TP s have discretion in what they report. Encourages simultaneous disclosure to alleviate Standards of Conduct concerns but pledges to address those issues in the SoC NOPR.

9 Planning Principles 4 Information Exchange Transmission customers are required to submit information on their projected loads and resources, and the transmission provider must allow market participants the opportunity to review and comment on draft transmission plans. Network customers will need to submit information on their projected loads and resources on a comparable basis (e.g., planning horizon and format) as used by transmission providers in planning for their native load PTP customers will be required to submit any projections they have of a need for service over that planning horizon and at what receipt and delivery points. TPs must develop a format and schedule for these submittals.

10 Planning Principles 5. Comparability The transmission system plan should meet the specific service requests of transmission customers and otherwise treat similarly situated customers comparably. Restatement of existing OATT rule? FERC included this principle to address comments that transmission providers continue to plan their transmission systems such that their own interests are addressed without regard to, or ahead of, the interests of their customers. Does not require all customers to be treated the same only similarly-situated customers.

11 Planning Principles 6. Dispute Resolution FERC adopts the NOPR s proposal to require transmission providers to develop a dispute resolution process. Opens the door to prove up existing dispute resolution process as sufficient, but such a showing is required. Dispute resolution process should be available to address both substantive and procedural planning disputes. Will not cover any issues over which the Commission does not have jurisdiction (e.g. state siting issues).

12 Planning Principles 7. Regional Participation The transmission provider is required to coordinate with interconnected systems to share system plans and ensure that they are simultaneously feasible and identify system enhancements that could relieve significant and recurring transmission congestion. Proper venue? RTOs, NERC sub-regions, something new? FERC encourages projects with regional benefits. FERC declines to dictate the vehicle for regional planning and further does not dictate the appropriate geographic scope. Compliance filings must explain each TP s choice.

13 Planning Principles 8. Economic Planning Studies The transmission provider is required to annually prepare studies identifying significant and recurring congestion and to post such studies on OASIS. FERC disagrees that economic upgrades should be considered only in the context of individual requests for service under the OATT. Planning it s not just reliability any more. FERC clarifies no obligation to build. Does this concept apply easily outside of RTO markets? If it s not reliability-driven, and its not related to requested service, WHO PAYS FOR IT?

14 Planning Principles 9. Cost Allocation for New Projects For a planning process to comply with the Rule, it must address cost allocation for new projects. Rather than imposing a particular allocation method, FERC permits transmission providers and stakeholders to determine their own criteria. FERC provides several cost allocation principles: (1) costs should be fairly assigned among participants, including those who cause them to be incurred and those who otherwise benefit from them; (2) cost allocation proposals should provide adequate incentives to construct new transmission; and (3) the allocation proposal should be generally supported by state authorities and participants across the region.

15 Other Planning Issues Independent Third Party Coordinator State Commission Participation Flexibility in Implementation Recovery of Planning Costs Open Season for Joint Ownership Specific Study Processes Beyond Reliability and Congestion Level of Detail in the OATT

16 Jurisdictional Issues Comments on the NOPR contained several challenges to FERC s jurisdiction over transmission planning and warnings not to extend into realm of traditional state regulation. FERC relies on new Section 217 of the FPA. Congress further directed the Commission to exercise its authority under EPAct 2005 in a manner that facilitates the planning and expansion of transmission facilities to meet the reasonable needs of load-serving entities. Contends this jurisdiction enhances authority it already had over planning.

17 Compliance Requirements Each transmission provider is required to submit in a compliance filing 210 days after publication of the Rule: (1) A proposal for a coordinated and regional planning process that complies with the planning principles and other requirements in the Final Rule. OR (2) a compliance filing describing how its existing planning process is consistent with or superior to the requirements of the Final Rule. Under either of these approaches, the process must be documented as an attachment to the transmission provider s OATT.

18 Compliance Requirements Each transmission provider is also required to construct and post on OASIS a strawman proposal for its compliance with the Rule within 75 days of publication the rule FERC strongly encourages consulting with stakeholders in developing the strawman. Strawman should include designation of planning region FERC plans on scheduling several regional Technical Conferences in the period from 90 to 120 days after the publication of the Rule.

19 Calculating and Posting Available Transfer Capability - ATC Andrea Chambers

20 Basic Premise for ATC Reform Under Order Nos. 888 and 889, FERC did not prescribe a specific methodology for calculating ATC, but encouraged the industry to develop a consistent, industry-wide approach. Order No. 890 finds that this process has been unsuccessful and that inconsistencies are apparent across the industry.

21 CONSISTENCY AND TRANSPARENCY FOR ATC Order 890 does not provide a formula for ATC. Enter NERC INDUSTY STANDARDS PROCESS: Public utilities, working through NERC and NAESB processes must improve the consistency and transparency of ATC calculation methods (including, components, data inputs, modeling assumptions, and data exchange). NERC to modify its ATC-related reliability standards within 270 days. Utilities and NAESB develop business practices within 360 days. NERC/NAESB file a workplan within 90 days.

22 OATT AND OASIS REQUIREMENTS FERC also increases transparency of ATC calculations by requiring each transmission provider s OATT to include its specific ATC calculation methodology, and to post relevant data and models on each transmission provider s OASIS.

23 OATT Attachment C- Minimum Requirements Specify NERC-approved ATC methodology (e.g. contract path, network ATC, or network AFC) Provide Detailed Description of the Algorithm for firm and non-firm ATC for scheduling (same day and real-time), operating (day ahead and preschedule), and planning (beyond operating day). Provide Flow Diagram of ATC calculation

24 OATT Attachment C- Minimum Requirements Define each ATC component (i.e. TTC, ETC, TRM and CBM) and provide detailed explanation of derivation for both operating and planning horizons. Update 60 days after NERC/NAESB process to include any revised/standards regarding ATC. May protect confidential or CEII material, but may not merely refer to NERC/NAESB/WECC business practices. Requires annual CBM studies and narrative of CBM practices.

25 ATC COMPONENTS STANDARDIZATION Total Transfer Capacity /Total Flowgate Capacity ( TTC/TFC ) Set by NERC Reliability Standards- any requests for regional differences to be resolved through NERC processes

26 ATC Components Existing Transmission Commitments ( ETC ) (1) Native Load (including Network) (2) Grandfathered Transmission Agreements (3) Appropriate Point to Point (4) Rollover rights with Long-Term Firm (5) Other uses identified by NERC NOT FOR PLANNING OR CONTINGENCY RESERVES (use TRM or CBM) All Reserved, but Unused Capacity (nonscheduled) to be released as Non-Firm ATC

27 ATC COMPONENTS ETC (cont.) POR/POD - May not model a firm reservation with a single generator source (point of receipt) and multiple load sinks (points of delivery) if the combined reservations exceed the generator s nameplate rating. Utilities to work through NERC to develop requirements in MOD-001 regarding these reservations; work through NAESB for business practices to implement MOD-001.

28 ATC Components Capacity Benefit Margin ( CBM ) Despite concerns that Transmission Provider s have preferential access to interface capacity, Commission decides that Load Serving Entities are allowed to set aside transfer capability to maintain their generation reliability requirement as CBM; But..the Transmission Provider must remove the costs of CBM from Point to Point Rates (limited 205 due within 120 days, no cost of service data required, no change to revenue)

29 ATC Components Capacity Benefit Margin ( CBM ) Implementation Issues How does removing the costs of CBM work? Is there a CBM rate? Is CBM still path-specific? If so, how will it be pulled out of transmission rates?

30 ATC Components CBM (cont.) (1) Utilities/NERC/NAESB- to develop standards regarding (a) how CBM value to be determined; (b) how CBM should be allocated across paths, and (c) how CBM to be used. (2) Utilities/NERC- to specify standard for generation deficiency conditions when LSE allowed to use CBM (3) Transmission set aside as CBM to be zero in non-firm ATC (4) Utilities/NAESB- to develop OASIS mechanism to Audit CBM usage

31 ATC Components Transmission Reliability Margin ( TRM ) Utilities/NERC to modify standards in MOD-008 and MOD-009 using guidance below: TP can set aside TRM for: (i) load forecast and load distribution error, (ii) facility loading variation, (iii) uncertain transmission system topology, (iv) loop flow impact, (v) variations in generator dispatch, (vi) automatic reserve sharing, (vii) NERC identified uncertainties. Unused TRM is not required to be sold non-firm.

32 ATC Components TRM (cont.) Utilities/NERC- to establish MAXIMUM TRM Each Transmission Provider to calculate, and allocate on each path/flowgate the aggregate TRM for all LSEs in the area Upon request by any Transmission Customer or LSE within its Control Area, Transmission Provider must make available all underlying data, including load flow base cases, used to determine TRM (subject to confidentiality if needed).

33 Posting on OASIS ATC/TTC POSTINGS/DATA/STUDIES - FERC continues to require ATC/TTC posting on OASIS including all data used to calculate ATC and TTC for any constrained paths and any system planning studies or specific network impact studies, and a list of studies. CBM-Requires posting of CBM data per path. TRM - Requires posting of TRM data for paths for which ATC, TTC, and CBM are already posted.

34 Posting on OASIS CHANGES IN ATC/TTC -Requires posting of narrative explanation of changes in ATC on constrained paths monthly or annually if TTC changes more than 10% or if ATC remains unchanged at a value of zero for more than 6 month. Can each change in ATC be explained in narrative? What if loop flows from two systems over cause the change? What are the liability implications of these statements?

35 OASIS Metrics - for processing TSRs Posting of Unused Transfer Capacity- Transfer Capacity associated with reservations not scheduled in real time are to be made available as non-firm on OASIS

36 Posting on OASIS Denials of Service - Extends from 3 to 5 years the data retention requirement for denials of service and expands access to this information. Affiliate Requests - Requires posting the number of affiliate & nonaffiliate requests for transmission service that have been made and how many have been rejected. Forecast Data - Post all underlying load forecasts, including load forecasts and actual daily peak load for both system-wide load (including native load) and native load. (Orders NAESB to standardize.) CEII - Requires standard disclosure process for CEII. Network Resource designation requests/terminations must be requested over OASIS posted on OASIS for 90 days and available for audit for 5 years.

37 Models, Assumptions, Input Data Periodic Update of Models-Utilities/NERC must modify reliability standards MOD-10 thru MOD-25 to incorporate period review of models (e.g., load flow base cases with contingency, short circuit data, transient and dynamic stability simulation data) ATC Models Consistent with Planning Models includes load levels, gen. dispatch, maintenance schedules, etc. Consistent Models of Base Generation Dispatch Utilities/NERC to develop standards regarding which generators to mode (Base generation will model DNRs and others that have legal obligation to run, uncommitted resources that can be delivered to the control area, economically dispatched, as needed, for balancing. Models of Transmission Reservations Utilities and NERC to develop reliability standards regarding reflecting approaches for simulating reservations

38 Transmission Pricing Rebecca Roback and Anne Dailey

39 Energy Imbalance Definition: Energy Imbalance Service is provided when the transmission provider makes up for any difference that occurs over a single hour between the scheduled and actual delivery of energy to a load located within its control area.

40 Energy Imbalance In Order No. 888, the Commission included energy imbalance as one of the six ancillary services that must be provided in the OATT. The Commission s rationale an energy deviation band would be appropriate for load variations and a price for exceeding that deviation band would be appropriate for excessive load variations. It also encourages good scheduling practices.

41 Energy Imbalance Application since Order No Commission only required inclusion of imbalance penalties in an OATT for excessive load variations, but has allowed in certain cases the inclusion of generator imbalance provisions in an OATT or individual interconnection agreement.

42 Energy Imbalance Changes in Order No. 890: New Schedule 9, adding standardized charges for generator imbalance Standardized three tiered pricing methodology for both energy imbalance and generator imbalance charges Exemption from certain penalties for intermittent resources

43 Energy Imbalance Order No. 890 criteria for imbalance charges: (1) The charges must be based on incremental cost or some multiple thereof; (2) The charges must provide an incentive for accurate scheduling; (3) The provisions must account for the special circumstances of intermittent generators

44 Energy Imbalance Three-tiered approach to imbalance charges: Tier 1 Imbalances of less than or equal to 1.5% of the scheduled energy (or 2 MW, whichever is larger) are netted monthly and settled at 100% of the incremental or decremental cost Only tier where netting is allowed Tier 2 Imbalances between 1.5% and 7.5% of the scheduled energy (or between 2-10 MW, whichever is larger) are settled at 90% of the decremental cost for overscheduling or 110% of the incremental cost for underscheduling;

45 Energy Imbalance Tier 3 Imbalances greater than 7.5% (or 10MW, whichever is larger) are settled at 75% of the decremental cost for overscheduling or 125% of the incremental cost for underscheduling.

46 Energy Imbalance Incremental and Decremental Costs are defined in the Schedules as the Transmission Provider s actual average hourly cost of the last 10 MW dispatched to supply the Transmission Provider s native load, based on the replacement cost of fuel, unit heat rates, start-up costs, incremental operation and maintenance costs, and purchased and interchange power costs and taxes, as applicable.

47 Energy Imbalance Intermittent Resources get exemption from third tier charges and will pay second tier charges for all deviations greater than the larger of 1.5% or 2 MW. Exemption because intermittent resources cannot always follow schedules accurately. Intermittent Resource defined as electric generator that is not dispatchable and cannot store its fuel source and therefore cannot respond to changes in system demand or respond to transmission security constraints

48 Energy Imbalance Tiered approach applies to: (1) Schedule 4 Energy Imbalance Service; and (2) Schedule 9 Generator Imbalance Service A transmission customer can be assessed penalties for one or the other, but not both

49 Energy Imbalance To the extent a transmission provider wants to deviate from the Schedule 4 and Schedule 9 provisions, it may file an FPA Section 205 filing to show its provisions are consistent with or superior to the pro forma OATT. The Commission will not abrogate existing generator imbalance agreements between transmission providers and their customers

50 Energy Imbalance Intentional Deviations FERC has not adopted intentional schedule deviations, but believes the three-tiered approach should be sufficient to discourage intentional power dumps or leans on other generation.

51 Energy Imbalance Inadvertent Energy, which is the difference between a control area s net actual interchange and the net scheduled interchange, will be treated differently from imbalances. Currently, under NAESB standards, inadvertent energy is handled adequately through a return-in-kind approach. The Commission notes that if such an approach is no longer sufficient to maintain reliability, FERC may adopt new standard.

52 Energy Imbalance Treatment of revenues received above incremental costs For revenues received above incremental costs, transmission providers must develop and file in a compliance filing mechanisms to credit penalty revenues above incremental costs to all nonoffending transmission customers, including affiliated transmission customers.

53 Transmission Credits for Network Customers Under Order No. 888, new transmission facilities constructed by a network customer were eligible for transmission credits if they were jointly planned with the transmission provider. In Order No. 890, the link between joint planning and credits has been severed. A network customer shall receive credits if its facilities are integrated into the operations of the transmission provider s facilities. Only applies to facilities added after the effective date of the final rule. Costs are not automatically recovered in the transmission provider s cost of service.

54 Capacity Reassignment The Commission determined that the capacity reassignment market has failed to develop into a robust secondary market. In order to facilitate market development, the Commission removed the price cap on capacity reassignment.

55 Capacity Reassignment FERC will monitor the capacity reassignment market to ensure that it is developing properly. This includes: All sales or assignments of capacity are to be posted on OASIS before the reassigned service commences; Assignees of transmission capacity must execute a service agreement before the reassigned service commences; Transmission providers are required to provide quarterly reports summarizing the service agreements; and FERC staff will monitor the reassignment data to identify any problems, including market power.

56 Operational Penalties If a transmission customer uses transmission service in excess of the capacity it has reserved, or uses unreserved transmission service, it will incur transmission use penalties. No class of customer is exempt from such penalties. Applies to transmission provider when taking service under the OATT. Network customers incur penalties if they use network service to support off system sales.

57 Operational Penalties Transmission Providers have discretion in setting penalty rates, as long as the penalty rates are based on the period of unreserved use. Rates must meet the following criteria: The penalty for a single hour of unreserved use is based on the rate for daily firm point-to-point service. More than one penalty assessment for a given duration will lead to an increase in the penalty assessment to the next given duration; i.e., more than one daily penalty will lead to the incurrance of a weekly penalty. The penalty rates must be stated explicitly in the OATT. Transmission Providers are required to distribute all collected unreserved use penalties, and provide an annual report detailing the penalties received and distributed.

58 Other Ancillary Services Reactive Supply and Voltage Control, Regulation and Frequency Response, Energy Imbalance, Spinning Reserves, Supplemental Reserves, and Generator Imbalance may be provided by generating units or non-generating resources.

59 Changes to Non-Rate Terms and Conditions of Service David Rubin

60 RECIPROCITY The Commission retains the reciprocity language in the Order No. 888 pro forma OATT, but updates it to include references to ISOs and RTOs. If an ISO or RTO is the transmission provider, the reciprocity obligation is owed to all members of that ISO or RTO. Retain Order No. 888 s three alternative provisions for satisfying the reciprocity condition, (1) a bilateral agreement, (2) waiver from the public utility, or (3) file a safe harbor tariff with the Commission. The safe harbor tariff, its provisions must be substantially conforming or superior to the revised pro forma OATT in this Final Rule. Will not adopt a generic rule to implement the new FPA section 211A. Existing waivers of the obligation to file an OATT or otherwise offer open access transmission service remain in place.

61 PLANNING REDISPATCH AND CONDITIONAL FIRM SERVICE Under the current OATT - Planning (or economic) Redispatch - Reliability Redispatch

62 Planning Redispatch Provider must expand or upgrade system or, if it is more economical, plan to redispatch its resources to provide requested firm point-to-point service, provided redispatch does not: Degrade or impair the reliability of service to native load customers, network customers and other transmission customers taking firm point-to-point service or Interfere with the transmission provider s ability to meet prior firm contractual commitments to others.

63 Reliability Redispatch Required, when feasible, to relieve system constraints that would otherwise cause curtailment of the network customer or transmission provider loads. To provide reliability redispatch, the transmission provider redispatches all network resources and transmission provider resources on a least-cost basis. The transmission provider and network customers each pay a load ratio share of these redispatch costs.

64 Order No. 890 Changes Modifies the current planning redispatch requirement. Creates a new conditional firm service option.

65 Eligibility Planning redispatch and conditional firm options need only be made available to customers who request firm point-to-point service of more than a year in duration and the requested service is not available.

66 Process As part of the System Impact Study, customers will have the choice of whether to request a study of the planning redispatch option, the conditional firm option or both. Transmission providers may recover the costs of studying these options through the system impact study agreement.

67 Limitations Providers do not have to offer planning redispatch or conditional firm service if doing so: (1) would degrade or impair the reliability of service to native load customers, network customers, and other customers taking firm point-to-point service or (2) interfere with the transmission provider s ability to meet prior firm contractual commitments to others. No excuse due to the need to manage multiple planning redispatch or conditional curtailment obligations.

68 Planning Redispatch Studies The System Impact Study must identify: (1) the system constraints, identified by transmission facility or flowgate, causing the need for the System Impact Study; (2) additional direct assignment facilities or network upgrades required to provide the requested service; and (3) redispatch options, including a non-binding estimate of the incremental costs of redispatch and the relevant congested transmission facilities for which redispatch will be provided. Transmission providers will not be required to estimate the number of hours of redispatch that may be required to accommodate the requested service as proposed in the NOPR.

69 Conditional Firm Studies Study must specify: (1) the number of conditional curtailment hours and (2) the specific system conditions during which conditional curtailment may occur. FERC does not propose a standardized method of modeling the conditional curtailment hours and will allow transmission providers to add a risk factor to their calculation of annual curtailment hours to account for forecasting risks. FERC requires annual caps on the number of hours and encourages the provider to offer monthly or seasonal caps.

70 Service Agreement Specify the relevant congested transmission facilities and whether the transmission provider will provide planning redispatch, a mix of planning redispatch and conditional firm, or conditional firm in order to provide the point-to-point transmission service. For conditional firm option, customers must choose either (1) specific system condition(s) during which conditional curtailment may occur or (2) annual number of conditional curtailment hours during which conditional curtailment may occur. Service agreements are considered to be non-conforming agreements and must be filed.

71 Modifications to Service Agreement If the service is for more than two years, but the customer does not commit to a facilities study or the payment of network upgrade costs, the transmission provider has a periodic right to reassess the service every two years. The transmission provider may not implement reassessments during intervening periods nor may it reassess the conditions in order to amend the service agreement in an intervening year should it forego any biennial reassessment. If the customer commits to paying the costs associated with upgrades, the conditions or hours identified by the transmission provider shall remain in effect until such time as the upgrades have been completed.

72 Redispatch, Conditional Firm and RTOs and ISOs FERC does not require RTOs and ISOs with real-time energy markets to adopt the provisions for conditional firm point-to-point service. RTOs and ISOs need not amend their tariffs if the Commission has previously found that these tariffs were just and reasonable without the inclusion of pro forma section 13.5 planning redispatch provisions. However, RTOs and ISOs that already provide planning redispatch pursuant to section 13.5 of the pro forma OATT must modify the relevant provisions of their tariffs consistent with the directives in the Final Rule, including the obligation to post monthly redispatch costs for each transmission facility over which planning and reliability redispatch are provided.

73 Redispatch from Third Party Resources Transmission providers must identify: (1) generation resources located within the control area, including its own resources, that can relieve the congested transmission facility at issue, and (2) the impact of each identified resource on the congested facilities, e.g., the generator shift factor. In addition to identifying generation resources within the control area, the provider must identify resources outside the control area that may be able to relieve congested transmission facilities. No obligation to solicit third party resources in order to provide planning redispatch. No requirement to use network customer resources or other third party resources in the provision of planning redispatch. Must work with customers to facilitate the use of third party generation, where available. This entails review of redispatch plans.

74 OASIS REQUIREMENTS FOR REDISPATCH Post monthly average cost of redispatch for each internal congested transmission facility or interface over which it provides redispatch service using planning redispatch or reliability redispatch under the pro forma OATT. Also post a high and low redispatch cost for the month for these same constraints. Calculate the monthly average cost in $/MWh for each congested transmission facility by dividing monthly total redispatch costs (at the facility) by the total MWhs that would otherwise be curtailed (at the facility) in the month absent the redispatch. Must post regardless of whether customer is required to pay these exact costs. Post at the end of each month - no later than when invoices are sent. Direct transmission providers to work in conjunction with NAESB to develop this new OASIS functionality and any necessary business practice standards.

75 OASIS Requirements for Redispatch FERC directs transmission providers to modify their OASIS sites to allow for posting of third party offers. Work with NAESB to develop this functionality and need not implement this new OASIS functionality and any related business practices until NAESB develops appropriate standards.

76 Pricing of Planning Redispatch No longer cap redispatch costs over the term of the service at the costs of expansion. Customers will have the option of paying (1) the higher of (a) actual incremental costs of redispatch or (b) the applicable embedded cost transmission rate on file with the Commission or (2) a fixed rate for redispatch to be negotiated by the transmission provider and customer and subject to a cap representing the total fixed and variable costs of the resources expected to provide the service. If the customer selects the higher of incremental cost or the embedded-cost rate, the transmission provider shall calculate the costs of redispatch monthly and charge the higher of redispatch or the embedded cost rate each month. For purposes of calculating planning redispatch charges, incremental costs shall include fuel or purchase power costs caused by ramping up generator(s) at the point of delivery and ramping down generator(s) at the point of receipt. Additionally, where applicable, transmission providers may specify in customer service agreements other incremental costs for inclusion in the monthly actual incremental costs, including opportunity costs.

77 Curtailment Priority for Conditional Firm Service Conditional firm service, when the conditions are in operation, will share the same priority as secondary network service. (Since the customer is paying the long-term firm point-to-point rate, it receives the highest non-firm curtailment priority during the conditional curtailment hours). Short-term firm service reserved prior to the reservation of conditional firm service should maintain priority over conditional firm service in the periods when conditional firm service is conditional. During non-conditional periods, conditional firm service is subject to pro rata curtailment consistent with curtailment of other long-term firm service.

78 Hourly Firm Service Proposed in the NOPR Not included in the Final Rule Can be included in a 205 Filing as equal or superior to

79 ROLLOVER RIGHTS Section 2.2 of the current pro forma OATT allows existing customers with contracts of one year or more, the right to continue to take transmission service from the transmission provider when the customer s contract expires. A transmission customer must give notice of whether it will exercise its right of first refusal 60 days before the expiration of its service agreement. The transmission provider may restrict a right of first refusal based on projections of load growth or pre-existing contracts that commence in the future if the transmission provider knows at the time of the execution of the original service agreement that ATC used to serve a customer will be available for only a particular time period.

80 Changes to Rollover Rights Under Order No. 890 Adopts a five-year minimum contract term to be eligible for a rollover right. At the end of its initial five-year contract term, a transmission customer must, within the one-year notice period agree to another five-year contract term or match any longer-term competing request as to term and rate. No change to rollover restrictions based on reasonable forecasts of native load growth or preexisting contracts that commence in the future to be included in the initial transmission service agreement. Rollover reform is to be effective at the time of acceptance by the Commission of a transmission provider s coordinated and regional planning process.

81 PROCESSING OF REQUESTS FOR SERVICE - CLUSTERING FERC does not require transmission providers to study transmission requests in a cluster, unless the customers involved request the cluster and the transmission provider can reasonably accommodate the request. FERC does require each transmission provider to include tariff language in its compliance filing that describes how it will process a request to cluster and how it will structure the transmission customers obligations when they have joined a cluster.

82 PROCESSING OF SERVICE REQUESTS MULTIPLE SYSTEMS FERC requires transmission providers working through NAESB to develop business practice standards related to coordination of requests across multiple transmission systems and to allow a transmission customer to rebid a counteroffer of partial service so the transmission customer is allowed to take the same quantity of service across all linked transmission service requests.

83 RESERVATION PRIORITY Gives priority to pre-confirmed non-firm point-to-point transmission service requests and short-term firm point-to-point transmission service requests. A pre-confirmed request for transmission service will not pre-empt an equal duration request that has already been confirmed. Longer duration requests for transmission service will continue to have priority over shorter duration requests for transmission service, with pre-confirmation serving as a tie-breaker for requests of equal duration. Prohibit transmission customers from withdrawing pre-confirmed non-firm and short-term firm point-to-point transmission service requests prior to when the transmission customer is offered service or a system impact study. Price will be a tie-breaker when the transmission provider is willing to discount transmission service.

84 Window for Submission FERC allows but not mandate that transmission providers can propose a window within which all transmission service requests the transmission provider receives will be deemed to have been submitted simultaneously. Such a policy is particularly appropriate in circumstances when a tariff or business practice calls for requests to be submitted no earlier than a specific deadline. Requests submitted within the window should not be publicly available until the window has closed. Require transmission providers to propose a method for allocating transmission capacity if sufficient capacity is not available to meet all requests submitted within the specified time period.

85 DESIGNATION OF NETWORK RESOURCES QUALIFICATION AS A NETWORK RESOURCE Supply provided under the new Conditional Firm Transmission Service can qualify as a network resource.

86 LD Contracts FERC finds that a make whole LD provision, such as that found in the EEI Firm LD Product and in the WSPP Schedule C agreement, can qualify for network designation. Any contract which contains an unacceptable LD provision, but otherwise qualifies for designation as a network resource and has been properly designated as a network resource prior to the effective date of this Final Rule, will be grandfathered only until the earlier of: (1) the expiration of the current term of the power purchase agreement or (2) an indefinite termination of the power purchase agreement as a designated network resource pursuant to section 30.3 of the pro forma OATT. FERC notes that the WSPP Schedule C agreement allows interruptions to meet [the] Seller s obligations to its customers and thus, appears to allow interruptions for reasons other than reliability. This needs to be revised.

87 Documentation of Network Resources Transmission providers continue to be responsible for verifying that third-party transmission arrangements for external network generation are firm. Transmission providers are not responsible for verifying that the generating units and power purchase agreements network customers designate as network resources satisfy the requirements in sections 30.1 and 30.7 of the pro forma OATT. FERC adopts the requirement for both the transmission provider s merchant function and network customers to include a statement with each application for network service or to designate a new network resource that attests: (1) the customer owns or has committed to purchase the designated resource and (2) the network resource comports with the requirements for designated network resources. The network customer should include this attestation in the customer s comment section of the request when it confirms the request on OASIS.

88 Undesignation of Network Resources Network customers and the transmission provider s merchant function may only enter into a third-party power sale from a designated network resource if the purchase agreement allows the seller to interrupt power sales in order to serve network load. Alternatively, they may submit a request to undesignate a resource. FERC clarifies that requests to undesignate network resources that are submitted concurrently with a request to redesignate those network resources at a specific point in time shall be considered temporary terminations. Direct transmission providers working through NAESB, to modify OASIS allow network customers to provide all required information for such terminations. Prior to implementation of this functionality, requests for temporary or indefinite terminations of network resources may be submitted by telefax or providing the information by telephone over the transmission provider s time recorded telephone line.

89 PROVISIONS NOT MODIFIED BY ORDER 890 Stranded Cost Recovery Behind the Meter Generation Force Majeure Indemnification and Liability

90 OASIS Transparency, Performance Metrics and Penalties Amie Colby

91 OASIS Transparency POST IT!

92 OASIS Performance Metrics Parameters Post performance metrics for each calendar quarter within 15 days of the end of the quarter Begin tracking upon the effective date of the Final Rule Keep the performance metrics on OASIS site for three years Calculate performance metrics separately for affiliates and non-affiliates

93 OASIS Performance Metrics Quarterly Postings Processing time from initial service request to offer of a system impact study agreement System impact study processing time Service requests withdrawn from system impact study queue Process time from completed system impact study to offer of facilities study Facilities study processing time Service requests withdrawn from the facilities study queue

94 OASIS Performance Metrics Notification Filings Must notify Commission if process more than 20% of non-affiliates studies outside of the 60 day due diligence deadline for two consecutive quarters Once the notification filing occurs, the transmission provider must post (1) the average of the employee hours expended per completed system impact study; (2) the average of the employee hours expended per completed facilities study; (3) the number of employees dedicated to processing studies

95 OASIS Performance Metrics Non-Compliance If the transmission provider cannot meet the prescribed 60-day due diligence deadlines, FERC will subject the transmission provider to penalties if it continues to be out of compliance for each of the two quarters following the notification filing A transmission provider will be out of compliance if it completes 10 percent or more of non-affiliates studies outside the 60-day period

96 OASIS Performance Metrics Penalties The penalty for failure to comply with the performance metrics is $500 a day The penalty will be assessed on a quarterly basis, starting with the quarter following the notification filing and continuing until the transmision provider completes at least 90 percent of all studies within 60 days after the study agreement has been executed

97 Enforcement Strong Audit Program Compliance officer No safe harbors Attorney-client privilege Market-Based Rates FERC will revoke an entity s market-based rate authority in response to an OATT violation only upon a finding of specific factual nexus between the violation and the entity s market-based rate authority It is FERC s burden to show the factual nexus

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff Alcoa Power Generating Inc. Long Sault Division ALCOA POWER GENERATING INC. Long Sault Division Open Access Transmission Tariff The following sheets reflect all revisions submitted to the Federal Energy

More information

Transmission Service Reference Manual. April 29, 2015

Transmission Service Reference Manual. April 29, 2015 Transmission Service Reference Manual April 29, 2015 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 Author Shari Brown Change Description Initial creation of draft

More information

SCHEDULE 1. Scheduling, System Control and Dispatch Service

SCHEDULE 1. Scheduling, System Control and Dispatch Service Seventh Revised Volume No. 5 (MT) Original Sheet No. 71 SCHEDULE 1 Scheduling, System Control and Dispatch Service This service is required to schedule the movement of power through, out of, within, or

More information

TENNESSEE VALLEY AUTHORITY. TRANSMISSION SERVICE GUIDELINES 2013 Edition

TENNESSEE VALLEY AUTHORITY. TRANSMISSION SERVICE GUIDELINES 2013 Edition TENNESSEE VALLEY AUTHORITY TRANSMISSION SERVICE GUIDELINES EFFECTIVE DECEMBER 1, 2013 Original Sheet No. 2 TABLE OF CONTENTS FOREWORD... 9 I. COMMON SERVICE PROVISIONS... 9 1 Definitions... 9 1.1 Affiliate...

More information

New Brunswick Electricity Business Rules

New Brunswick Electricity Business Rules New Brunswick Electricity Business Rules Table of Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 Administration and Participation Transmission Planning and Connections Reliable Operations Billing and

More information

Rules on Southern Companies Energy Auction Participation

Rules on Southern Companies Energy Auction Participation Southern Company Services, Inc. First Revised Sheet No. 20B Superseding Original Sheet No. 20B Rules on Southern Companies Energy Auction Participation 1.0 Participation; Definitions 1.1 Southern Companies

More information

ISO-NE Transmission Markets and Services Tariff Cross Sound Cable Business Practices. Version 10.0 April 17, 2013

ISO-NE Transmission Markets and Services Tariff Cross Sound Cable Business Practices. Version 10.0 April 17, 2013 ISO-NE Transmission Markets and Services Tariff Cross Sound Cable Business Practices Version 10.0 April 17, 2013 ISO-NE Transmission, Markets and Services Tariff Cross Sound Cable Business Practices Version

More information

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations G1 DEFINITIONS In the ISO rules: acceptable operational reason means with respect to a source asset, any one or more of the following: i) a circumstance related to the operation of the generating asset

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

Energy Imbalance Market

Energy Imbalance Market Energy Imbalance Market Tariff Framework September 10, 2013 CAIS[Type text] [Type text] [Type text] Table of Contents 1. Introduction... 1 2. Guiding Objectives for the Tariff Framework... 2 3. Tariff

More information

153 FERC 61,306 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON REHEARING AND CLARIFICATION. (Issued December 17, 2015)

153 FERC 61,306 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON REHEARING AND CLARIFICATION. (Issued December 17, 2015) 153 FERC 61,306 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Nevada Power Company

More information

ATTACHMENT G. Network Operating Agreement

ATTACHMENT G. Network Operating Agreement ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service

More information

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Specific amendments to the Capacity Allocation and Congestion Management Network Code Annex: Specific amendments to the Capacity Allocation and Congestion Management Network Code I. Amendments with respect to entry into force and application The Network Code defines deadlines for several

More information

THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS

THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS Presentation by George Gross University of Illinois at Urbana-Champaign Modernizing the National Electric Power Grid NSF Workshop November 18-19,

More information

Natural Gas Pipeline Penalty Recovery Issue Paper

Natural Gas Pipeline Penalty Recovery Issue Paper Natural Gas Pipeline Penalty Recovery Issue Paper September 16, 2014 Table of Contents I. Introduction and Background... 3 II. Scope of Initiative and Plan for Stakeholder Engagement... 4 III. The Approved

More information

July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009

July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009 July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009 1) Will questions related to the July 2009 Baseload RFP be addressed at the LPSC

More information

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time

More information

APPENDIX A: SYSTEM OF ASSURANCE OF NET METERING ELIGIBILITY

APPENDIX A: SYSTEM OF ASSURANCE OF NET METERING ELIGIBILITY APPENDIX A: SYSTEM OF ASSURANCE OF NET METERING ELIGIBILITY Sections 1. Purpose... 1 2. Scope... 1 3. Definitions... 1 4. Obtaining a Cap Allocation... 3 5. Duties of the Administrator and Fees... 5 6.

More information

Resource Monitoring and Deliverability Tool Paper

Resource Monitoring and Deliverability Tool Paper Resource Monitoring and Deliverability Tool Paper NWPP MC Phase 3 Operations Integration Work Group 11/30/2014 Page 1 of 16 Table of Contents Executive Summary... 3 1. Purpose... 5 2. Existent Methods

More information

151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

Chapter 7 System Operations and Physical Markets

Chapter 7 System Operations and Physical Markets MDP_RUL_0002_07 Market Rules Chapter 7 System Operations and Physical Markets Public Issue Date: June 3, 2015 Library Record No. MDP_RUL_0002_07 Document Name Market Rules for the Ontario Electricity Market

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

No substantive change proposed; minor wording changes proposed to reflect new definitions. 358.1 Applicability.

No substantive change proposed; minor wording changes proposed to reflect new definitions. 358.1 Applicability. Docket No.RM07-1-000-1 - Appendix B: Comparison of Current and Proposed Regulatory Text 358.1 Applicability. (a) This part applies to any interstate natural gas pipeline that transports gas for others

More information

PROVO CITY UTILITIES NET METERING LICENSE AGREEMENT

PROVO CITY UTILITIES NET METERING LICENSE AGREEMENT PROVO CITY UTILITIES NET METERING LICENSE AGREEMENT Customer-Owned Electric Generating Systems of 25kW or Less This NET METERING LICENSE AGREEMENT ( Agreement ) is between ( Customer ) and Provo City -

More information

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out 1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate

More information

MONROE GAS STORAGE COMPANY, LLC

MONROE GAS STORAGE COMPANY, LLC FERC GAS TARIFF FIRST REVISED VOLUME NO. 1 (Superseding Original Volume No. 1) of MONROE GAS STORAGE COMPANY, LLC Filed with the FEDERAL ENERGY REGULATORY COMMISSION Communications Concerning this Tariff

More information

BILLING CODE 6717-01-P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission. [Docket No. IC16-2-000]

BILLING CODE 6717-01-P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission. [Docket No. IC16-2-000] This document is scheduled to be published in the Federal Register on 11/04/2015 and available online at http://federalregister.gov/a/2015-28086, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF ENERGY

More information

TRANSMISSION SERVICES MANUAL

TRANSMISSION SERVICES MANUAL TRANSMISSION SERVICES MANUAL Transmission Services Manual Version: 2.0 Revision Date: January 20, 2005 Committee Approved: January 19, 2005 Effectivity Date: February 1, 2005 Disclaimer The information

More information

North American Electric Reliability Corporation. Compliance Monitoring and Enforcement Program. December 19, 2008

North American Electric Reliability Corporation. Compliance Monitoring and Enforcement Program. December 19, 2008 116-390 Village Boulevard Princeton, New Jersey 08540-5721 North American Electric Reliability Corporation Compliance Monitoring and Enforcement Program December 19, 2008 APPENDIX 4C TO THE RULES OF PROCEDURE

More information

Energy Efficiency Measurement & Verification

Energy Efficiency Measurement & Verification PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 02 Effective Date: 12/17/2015 Prepared by PJM Forward Market Operations PJM 2015 PJM 2008 Revision, Effective Date: i Table of Contents

More information

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE JULY 2001 Table of Provisions Clause Page 1. Authority...2 2. Application...2 3. Objectives...2 4. Ring-Fencing Minimum Obligations...2 5. Compliance with

More information

State of Illinois Vendor Payment Program. Program Terms December 13, 2012

State of Illinois Vendor Payment Program. Program Terms December 13, 2012 State of Illinois Vendor Payment Program Program Terms December 13, 2012 Background: As a result of the current cash flow deficit, the State of Illinois (the State ) has been forced to delay payment to

More information

DISPATCH AGREEMENT RECITALS

DISPATCH AGREEMENT RECITALS DISPATCH AGREEMENT This DISPATCH AGREEMENT (the Agreement ) is made and entered into as of May 2, 2002, by and between the Department of Water Resources, an agency of the State of California, with respect

More information

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. WORKING CAPITAL POLICY AND PROCEDURE

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. WORKING CAPITAL POLICY AND PROCEDURE Note: This Policy is an interim policy which clarifies the provisions for working capital funding in the current NYISO tariffs, as delineated below. This Policy is subject to change, subsequent to FERC

More information

Performance Metrics. For Independent System Operators And Regional Transmission Organizations

Performance Metrics. For Independent System Operators And Regional Transmission Organizations Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April

More information

Operations Reliability Coordination Agreement

Operations Reliability Coordination Agreement Operations Reliability Coordination Agreement This Agreement regarding Operations Reliability Coordination ( Agreement ) is made and entered into as of the 19th day of June, 2013, by and between Midcontinent

More information

October 30, 2015. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission Room 1A-East 888 First Street, N.E. Washington, D.C.

October 30, 2015. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission Room 1A-East 888 First Street, N.E. Washington, D.C. William M. Dudley Lead - Assistant General Counsel October 30, 2015 1800 Larimer St., Street, 11th Floor Denver, CO 80202 Phone: 303.294.2842 Fax: 303.204.2852 Email: bill.dudley@xcelenergy.com. Ms. Kimberly

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA

ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA DC Electric Supplier--P.S.C. of D.C. No. 1 ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA Date of Issue: May 2, 2014 Date Effective: June 1, 2014 DC Electric Supplier--P.S.C. of D.C.

More information

ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA

ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA DC Electric Supplier--P.S.C. of D.C. No. 1 ELECTRICITY SUPPLIER COORDINATION TARIFF IN THE DISTRICT OF COLUMBIA Date of Issue: December 30, 2015 Date Effective: December 25, 2015 DC Electric Supplier--P.S.C.

More information

Transmission Pricing. Donald Hertzmark July 2008

Transmission Pricing. Donald Hertzmark July 2008 Transmission Pricing Donald Hertzmark July 2008 Topics 1. Key Issues in Transmission Pricing 2. Experiences in Other Systems 3. Pricing Alternatives 4. Electricity Market Structure and Transmission Services

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Corporation ) Docket No. ER10-500-000 MOTION OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS

CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS Page 1 of 16 CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS PROPOSED TERMS AND CONDITIONS January 2015 Page 2 of 16 TABLE OF CONTENTS 1. Definitions... 3 2. Curtailable Load Options... 6 3. Nomination

More information

Updated November 20, 2015. Director, System Planning

Updated November 20, 2015. Director, System Planning Updated November 20, 2015 Job Descriptions Job Title Reports To Job Description SYSTEM PLANNING & SERVICES VP Compliance Manages the system planning and services staff. The director is responsible for

More information

(UNOFFICIAL TRANSLATION)

(UNOFFICIAL TRANSLATION) (UNOFFICIAL TRANSLATION) Readers should be aware that only the original Thai text has legal force and that this English translation is strictly for reference. The SEC, Thailand cannot undertake any responsibility

More information

AGCS Gas Clearing and Settlement AG

AGCS Gas Clearing and Settlement AG Annex to the General Terms and Conditions of the Balance Group Coordinator (GTC BGC) Balancing energy management in the Eastern distribution area V 5.0 Annex Balancing energy management Version 5.0 Page

More information

Piedmont Natural Gas Company, Inc. Tennessee Index of Tariff & Service Regulations

Piedmont Natural Gas Company, Inc. Tennessee Index of Tariff & Service Regulations Tennessee Index of Tariff & Service Regulations Rate Schedule 301 Rate Schedule 302 Rate Schedule 303 Rate Schedule 304 Rate Schedule 306 Rate Schedule 307 Rate Schedule 309 Rate Schedule 310 Rate Schedule

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Administrative Services for the PJM Interconnection Operating Agreement

Administrative Services for the PJM Interconnection Operating Agreement PJM Manual 33: Administrative Services for the PJM Interconnection Operating Agreement Revision: 12 Effective Date: March 31, 2016 Prepared by Member Relations PJM 2016 PAGE iii lviii PJM 2008 Revision

More information

GENERAL INFORMATION. 8. LIMITATIONS OF SERVICE CLASSIFICATIONS (Continued)

GENERAL INFORMATION. 8. LIMITATIONS OF SERVICE CLASSIFICATIONS (Continued) P.S.C. NO. 3 ELECTRICITY LEAF: 114 8. LIMITATIONS OF SERVICE CLASSIFICATIONS (Continued) 8.3 STANDBY AND BUY-BACK SERVICES (Continued) A customer who operates a Qualifying Facility or a Qualifying Small

More information

RATE SCHEDULE FTP Firm Transportation Service Production Area

RATE SCHEDULE FTP Firm Transportation Service Production Area RATE SCHEDULE FTP Firm Transportation Service Production Area 1. AVAILABILITY 1.1 Service under this rate schedule is available on Transcontinental Gas Pipe Line Company LLC s (hereinafter referred to

More information

138 FERC 61,135 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING CONTINUATION OF STANDARDS OF CONDUCT WAIVER

138 FERC 61,135 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING CONTINUATION OF STANDARDS OF CONDUCT WAIVER 138 FERC 61,135 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Cross-Sound Cable

More information

Section 4: Scheduling Philosophy & Tools

Section 4: Scheduling Philosophy & Tools Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy

More information

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1 PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electric Creditworthiness Standards ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electric Creditworthiness Standards ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Creditworthiness Standards ) Docket No. AD04-8-000 Comments of the California Independent System Operator Corporation I.

More information

Methodology for Merit Order Dispatch. Version 1.0

Methodology for Merit Order Dispatch. Version 1.0 Methodology for Merit Order Dispatch Version 1.0 25 th April 2011 TABLE OF CONTENTS 1. OBJECTIVES... 1 2. ROADMAP FOR IMPLEMENTATION... 1 3. DEFINITIONS... 3 4. OPERATIONS PLANNING... 3 4.1. General Considerations...

More information

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016 Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042 Market Subcommittee (MSC) May 3, 2016 Purpose Purpose and Key Takeaways Review proposed FERC Energy Offer Cap rules, and potential

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Independent Market Monitor for PJM v. PJM Interconnection, L.L.C. ) ) ) ) ) ) Docket No. EL14- -000 COMPLAINT AND MOTION TO CONSOLIDATE

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

Title 1, Chapter 57 of the Texas Administrative Code

Title 1, Chapter 57 of the Texas Administrative Code Title 1, Chapter 57 of the Texas Administrative Code 57.1.Definitions. The following words and terms, when used in this chapter, shall have the following meanings, unless the context clearly indicates

More information

Rules on Southern Companies Energy Auction Participation. 1.2.1 Available Capacity: See Section 1.3 of Appendix DA-1 and Section 1.3 of Appendix HA-1.

Rules on Southern Companies Energy Auction Participation. 1.2.1 Available Capacity: See Section 1.3 of Appendix DA-1 and Section 1.3 of Appendix HA-1. Rules on Southern Companies Energy Auction Participation 1.0 Participation; Definitions 1.1 Southern Companies shall participate in the Energy Auction in accordance with these Rules on Southern Companies

More information

PERFORMANCE METRICS IN REGIONS OUTSIDE ISOs AND RTOs

PERFORMANCE METRICS IN REGIONS OUTSIDE ISOs AND RTOs PERFORMANCE METRICS IN REGIONS OUTSIDE ISOs AND RTOs Commission Staff Report Federal Energy Regulatory Commission October 15, 2012 This report does not necessarily reflect the views of the Commission,

More information

149 FERC 61,247 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

149 FERC 61,247 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 149 FERC 61,247 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, and Norman C. Bay. Public Service Company

More information

MERCHANT SERVICES, LEASING AND OPERATING AGREEMENT. ( Blackboard ). In this Agreement, the words; BbOne Card means a stored-value account

MERCHANT SERVICES, LEASING AND OPERATING AGREEMENT. ( Blackboard ). In this Agreement, the words; BbOne Card means a stored-value account MERCHANT SERVICES, LEASING AND OPERATING AGREEMENT This Agreement is between the Business set forth on the first page ( Business ) and Blackboard Inc., having offices at 650 Massachusetts Ave, N.W., 6th

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Pacific Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system to

More information

ONTARIO ENERGY BOARD STORAGE AND TRANSPORTATION ACCESS RULE

ONTARIO ENERGY BOARD STORAGE AND TRANSPORTATION ACCESS RULE ONTARIO ENERGY BOARD STORAGE AND TRANSPORTATION ACCESS RULE December 9, 2009 TABLE OF CONTENTS 1. GENERAL AND ADMINISTRATIVE PROVISIONS... - 3-1.1 Purpose of this Rule... - 3-1.2 Definitions... - 3-1.3

More information

Automated Clearing House

Automated Clearing House Automated Clearing House THE SERVICE Customer wishes to initiate credit and/or debit Entries as an Originator through Bank to Accounts maintained at Bank and in other depository financial institutions

More information

Appendix C-2. Entergy Services, Inc. June 8, 2016

Appendix C-2. Entergy Services, Inc. June 8, 2016 Appendix C-2 Preliminary Due Diligence List (Existing Resources) For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016

More information

EL PASO ELECTRIC COMPANY WRITTEN PROCEDURES IMPLEMENTING THE FEDERAL ENERGY REGULATORY COMMISSION S STANDARDS OF CONDUCT IN ORDER NO.

EL PASO ELECTRIC COMPANY WRITTEN PROCEDURES IMPLEMENTING THE FEDERAL ENERGY REGULATORY COMMISSION S STANDARDS OF CONDUCT IN ORDER NO. EL PASO ELECTRIC COMPANY WRITTEN PROCEDURES IMPLEMENTING THE FEDERAL ENERGY REGULATORY COMMISSION S STANDARDS OF CONDUCT IN ORDER NO. 717 POSTED PURSUANT TO 18 C.F.R. 358.7(d) NOVEMBER 26, 2008 (Last Update

More information

Agreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection)

Agreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection) Agreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection) This Agreement for Net Metering and Interconnection Services ( Agreement ) is made and entered into this day of

More information

INTRODUCING BROKER COMMODITY FUTURES CUSTOMER AGREEMENT WITH E*TRADE SECURITIES LLC

INTRODUCING BROKER COMMODITY FUTURES CUSTOMER AGREEMENT WITH E*TRADE SECURITIES LLC INTRODUCING BROKER COMMODITY FUTURES CUSTOMER AGREEMENT WITH E*TRADE SECURITIES LLC Re: Supplement to Commodity Futures Customer Agreement dated between MF Global, Inc ( MF Global ) and the customer named

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE Effective: April 2015 Billing Cycle Supersedes: November 2012 Billing

More information

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009 An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for

More information

SUBCHAPTER X. Preferred Provider Plans 28 TAC 3.3701-3.3713. 1. INTRODUCTION. The Texas Department of Insurance (Department) proposes

SUBCHAPTER X. Preferred Provider Plans 28 TAC 3.3701-3.3713. 1. INTRODUCTION. The Texas Department of Insurance (Department) proposes Part I. Texas Department of Insurance Page 1 of 267 SUBCHAPTER X. Preferred Provider Plans 28 TAC 3.3701-3.3713 1. INTRODUCTION. The Texas Department of Insurance (Department) proposes amendments to 3.3701

More information

YANKEE GAS SERVICES COMPANY, DBA EVERSOURCE ENERGY. TRANSPORTATION RECEIPT SERVICE Page 1 of 11

YANKEE GAS SERVICES COMPANY, DBA EVERSOURCE ENERGY. TRANSPORTATION RECEIPT SERVICE Page 1 of 11 Page 1 of 11 AVAILABILITY: Available to any Customer acting as its own supplier or approved Operator of gas supply (Operator) delivering gas supplies to a customer or Pool(s) of customers using Rates 03,

More information

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids

More information

HSHS BUSINESS ASSOCIATE AGREEMENT BACKGROUND AND RECITALS

HSHS BUSINESS ASSOCIATE AGREEMENT BACKGROUND AND RECITALS HSHS BUSINESS ASSOCIATE AGREEMENT This HIPAA Business Associate Agreement, ( Agreement ) is entered into on the date(s) set forth below by and between Hospital Sisters Health System on its own behalf and

More information

The Commonwealth of Massachusetts

The Commonwealth of Massachusetts SENATE, NO. 2476 [Senate, June 17, 2010 - New draft of Senate, No. 462 and House, No. 979 reported from the committee on Financial Services.] The Commonwealth of Massachusetts IN THE YEAR OF TWO THOUSAND

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS RENEWABLE ENERGY CERTIFICATES SOURCED FROM RENEWABLE RESOURCES CERTIFIED BY THE CALIFORNIA ENERGY COMMISSION February 18, 2015 1.0 Introduction of Pittsburg Power Company dba Island

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 101. (Docket No. RM04-12-000; Order No. 668)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 101. (Docket No. RM04-12-000; Order No. 668) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 101 (Docket No. RM04-12-000; Order No. 668) Accounting and Financial Reporting for Public Utilities Including RTOs (Issued December

More information

114CSR14 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 14 UNFAIR TRADE PRACTICES

114CSR14 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 14 UNFAIR TRADE PRACTICES 114CSR14 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 14 UNFAIR TRADE PRACTICES Section. 114-14-1. General. 114-14-2. Definitions. 114-14-3. File and Record Documentation. 114-14-4. Representation

More information

PROCEDURES FOR IMPLEMENTATION of FERC STANDARDS OF CONDUCT for OHIO VALLEY ELECTRIC CORPORATION AND INDIANA KENTUCKY ELECTRIC CORPORATION

PROCEDURES FOR IMPLEMENTATION of FERC STANDARDS OF CONDUCT for OHIO VALLEY ELECTRIC CORPORATION AND INDIANA KENTUCKY ELECTRIC CORPORATION PROCEDURES FOR IMPLEMENTATION of FERC STANDARDS OF CONDUCT for OHIO VALLEY ELECTRIC CORPORATION AND INDIANA KENTUCKY ELECTRIC CORPORATION In accordance with Rule 358.7(d) of the Federal Energy Regulatory

More information

Ancillary Services and Flexible Generation

Ancillary Services and Flexible Generation Ancillary Services and Flexible Generation Contents Ancillary Services Overview Types of Ancillary Services Market Impact Benefits of Medium Speed Solution Contact Information What are Ancillary Services?

More information

CITY OF LEMOORE REQUEST FOR PROPOSALS FOR CREDIT CARD PROCESSING SERVICE. City of Lemoore Finance Department 119 Fox St Lemoore, CA 93245

CITY OF LEMOORE REQUEST FOR PROPOSALS FOR CREDIT CARD PROCESSING SERVICE. City of Lemoore Finance Department 119 Fox St Lemoore, CA 93245 CITY OF LEMOORE REQUEST FOR PROPOSALS FOR CREDIT CARD PROCESSING SERVICE City of Lemoore Finance Department 119 Fox St Lemoore, CA 93245 Notice is hereby given that the City of Lemoore is soliciting proposals

More information

PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA. LCB File No. R107-00. October 10, 2000

PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA. LCB File No. R107-00. October 10, 2000 PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA LCB File No. R107-00 October 10, 2000 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted.

More information

Overview of Reliability Demand Response Resource

Overview of Reliability Demand Response Resource Overview of Reliability Demand Response Resource Radha Madrigal Customer Service Department May 8, 2014 Agenda Product overview and purpose Define Reliability Demand Response Resource Agreements & registration

More information

Accounting and Billing Manual

Accounting and Billing Manual MANUAL 14 Accounting and Billing Manual December 2014 Version: 3.3 Effective Date: 12/29/2014 Committee Acceptance: BIC 12/10/2014 This document was prepared by: NYISO Customer Settlements New York Independent

More information

PROJECT NO. 24462 PROPOSAL FOR PUBLICATION OF NEW 25.88 AS APPROVED AT THE SEPTEMBER 25, 2002 OPEN MEETING

PROJECT NO. 24462 PROPOSAL FOR PUBLICATION OF NEW 25.88 AS APPROVED AT THE SEPTEMBER 25, 2002 OPEN MEETING PROJECT NO. 24462 PERFORMANCE MEASURES FOR THE RETAIL ELECTRIC MAKRET PUBLIC UTILITY COMMISSION OF TEXAS PROPOSAL FOR PUBLICATION OF NEW 25.88 AS APPROVED AT THE SEPTEMBER 25, 2002 OPEN MEETING The Public

More information

OPERATIONAL ORDER. of eustream, a.s. as a transmission system operator

OPERATIONAL ORDER. of eustream, a.s. as a transmission system operator OPERATIONAL ORDER of eustream, a.s. as a transmission system operator laying down commercial conditions for access to the transmission network and gas transmission and for connection to the transmission

More information

SINGLE MARKET-BASED RATE TARIFF

SINGLE MARKET-BASED RATE TARIFF Fairless Energy, LLC,Single Market-Based Rate Tariff Filing Category: Compliance Filing Date: 05/01/2013 FERC Docket: ER13-01398-000 FERC Action: Accept FERC Order: Delegated Letter Order Order Date: 07/01/2013

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff. Appendix V

California Independent System Operator Corporation Fifth Replacement Electronic Tariff. Appendix V Appendix V Standard Large Generator Interconnection Agreement STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) [INTERCONNECTION CUSTOMER] [PARTICIPATING TO] CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

BILLING & COLLECTIONS SERVICES STATEMENT OF GENERALLY AVAILABLE TERMS AND CONDITIONS

BILLING & COLLECTIONS SERVICES STATEMENT OF GENERALLY AVAILABLE TERMS AND CONDITIONS BILLING & COLLECTIONS SERVICES STATEMENT OF GENERALLY AVAILABLE TERMS AND CONDITIONS Description of Service This Statement of Generally Available Terms and Conditions ( Statement ) provides details under

More information

Aliso Canyon Gas-Electric Coordination. Issue Paper

Aliso Canyon Gas-Electric Coordination. Issue Paper Aliso Canyon Gas-Electric Coordination March 17, 2016 Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3. Background... 5 3.1. Aliso Canyon Impact... 5 3.2. FERC Order

More information

THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers

THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers Sheet 1 THE NARRAGANSETT ELECTRIC COMPANY Terms and Conditions for Nonregulated Power Producers The delivery of electricity shall be in accordance with the provisions of law, regulation and these Terms

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON 10 STORAGE CORPORATION STATEMENT OF OPERATING CONDITIONS

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON 10 STORAGE CORPORATION STATEMENT OF OPERATING CONDITIONS UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON 10 STORAGE CORPORATION STATEMENT OF OPERATING CONDITIONS AS OF OCTOBER 4, 2013 TABLE OF CONTENTS Storage Services Firm Storage Service

More information

97 FERC 61,026 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

97 FERC 61,026 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 97 FERC 61,026 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, Linda Breathitt, and Nora Mead Brownell. Northeast Utilities

More information

GIP. 3.2.3 Net Zero Interconnection Service.

GIP. 3.2.3 Net Zero Interconnection Service. GIP and GIA Energy Displacement Agreement shall mean an agreement between an Interconnection Customer with a commercially operating Generating Facility on the Transmission Provider s Transmission System

More information

131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued May 20, 2010)

131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued May 20, 2010) 131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. California Independent

More information